111
Nebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E Assistant Materials and Research Engineer Nebraska Department of Roads February 22, 2012 Thursday, April 19, 2012

Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

Nebraska ProjectsAddressing the Top Ten RAP Issues

Robert C. Rea, P.EAssistant Materials and Research Engineer

Nebraska Department of RoadsFebruary 22, 2012

Thursday, April 19, 2012

Page 2: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

Thursday, April 19, 2012

Page 3: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

Thursday, April 19, 2012

Page 4: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer

Thursday, April 19, 2012

Page 5: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 6: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’

Thursday, April 19, 2012

Page 7: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it

Thursday, April 19, 2012

Page 8: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used

Thursday, April 19, 2012

Page 9: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum

Thursday, April 19, 2012

Page 10: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP

Thursday, April 19, 2012

Page 11: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP

Thursday, April 19, 2012

Page 12: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 13: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 14: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 15: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

• True• Must manage equally as any different aggregate• Its affects to the mix properties are critical as it is 40 – 50 %

Thursday, April 19, 2012

Page 16: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

• True• Must manage equally as any different aggregate• Its affects to the mix properties are critical as it is 40 – 50 %• Stockpile and manage different RAP in different piles

Thursday, April 19, 2012

Page 17: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

• True• Must manage equally as any different aggregate• Its affects to the mix properties are critical as it is 40 – 50 %• Stockpile and manage different RAP in different piles• Gradations and Binder contents need to be tested

Thursday, April 19, 2012

Page 18: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

• True• Must manage equally as any different aggregate• Its affects to the mix properties are critical as it is 40 – 50 %• Stockpile and manage different RAP in different piles• Gradations and Binder contents need to be tested• Plant and Loader personnel are key to the Management of

the materials

Thursday, April 19, 2012

Page 19: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 20: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 21: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 22: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 23: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 24: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 25: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 26: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 27: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 28: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

10. Too much hassle, one more thing to manage and design for

Thursday, April 19, 2012

Page 29: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 30: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 31: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

Thursday, April 19, 2012

Page 32: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

9. Restrictive Voids and VMA and other properties that limit RAP

Thursday, April 19, 2012

Page 33: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

9. Restrictive Voids and VMA and other properties that limit RAP

• Target 3% Air Voids at 7-65-100 Gyrations• VMA is an issue when using ignition oven Gsb

Thursday, April 19, 2012

Page 34: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

9. Restrictive Voids and VMA and other properties that limit RAP

Thursday, April 19, 2012

Page 35: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

9. Restrictive Voids and VMA and other properties that limit RAP

Thursday, April 19, 2012

Page 36: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

9. Restrictive Voids and VMA and other properties that limit RAP

Thursday, April 19, 2012

Page 37: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

9. Restrictive Voids and VMA and other properties that limit RAP

Virgin  

RAP   Ignition  Oven  

Burn  off  asphalt

RAP  Agg.

Virgin  Agg.  

Thursday, April 19, 2012

Page 38: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 39: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 40: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

Thursday, April 19, 2012

Page 41: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

8. Limits RAP #200 amounts and rejects the RAP

Thursday, April 19, 2012

Page 42: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

8. Limits RAP #200 amounts and rejects the RAP

• Some Agencies wanted to do this

Thursday, April 19, 2012

Page 43: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

8. Limits RAP #200 amounts and rejects the RAP

• Some Agencies wanted to do this• Test the final Product and make the QC/QA do the work• Many plants meter the dust and even drop some if needed

Thursday, April 19, 2012

Page 44: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

8. Limits RAP #200 amounts and rejects the RAP

Thursday, April 19, 2012

Page 45: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

8. Limits RAP #200 amounts and rejects the RAP

Thursday, April 19, 2012

Page 46: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

8. Limits RAP #200 amounts and rejects the RAP

Thursday, April 19, 2012

Page 47: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

8. Limits RAP #200 amounts and rejects the RAP

Thursday, April 19, 2012

Page 48: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 49: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 50: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

Thursday, April 19, 2012

Page 51: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

7. Restrictive in the specification, i.e. dust/asphalt maximum

Thursday, April 19, 2012

Page 52: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

7. Restrictive in the specification, i.e. dust/asphalt maximum

• Use Newest Dust/Binder Recommendations of 0.6 to 1.6, used to be 0.6 to 1.2

• Another increase with the use of 1% Lime

Thursday, April 19, 2012

Page 53: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

7. Restrictive in the specification, i.e. dust/asphalt

Thursday, April 19, 2012

Page 54: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

7. Restrictive in the specification, i.e. dust/asphalt

d/a 0.6 to 1.6, increased to 0.7 to 1.7 with 1% Lime

Thursday, April 19, 2012

Page 55: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 56: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 57: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

6. Required binder bumps/reductions when higher amounts are used

• Used to Require this• Costs about $ 50 more per liquid ton• Again puts a restriction when perfectly good mix can use

more RAP

Thursday, April 19, 2012

Page 58: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

6. Required binder bumps/reductions when higher amounts are used

• Used to Require this• Costs about $ 50 more per liquid ton• Again puts a restriction when perfectly good mix can use

more RAP• This is always covered when using PG XX-34 Grades

across the board

Thursday, April 19, 2012

Page 59: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 60: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 61: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

5. RAP not made available or charges too much for it

• YES, RAP IS WORTH A LOT !• Some wanted way too much, and priced out its use

Thursday, April 19, 2012

Page 62: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

5. RAP not made available or charges too much for it

• YES, RAP IS WORTH A LOT !• Some wanted way too much, and priced out its use• Don’t forget, hauling, stockpiling, handling etc.

Thursday, April 19, 2012

Page 63: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

5. RAP not made available or charges too much for it

• YES, RAP IS WORTH A LOT !• Some wanted way too much, and priced out its use• Don’t forget, hauling, stockpiling, handling etc.• It’s full potential is realized when made available ;

Thursday, April 19, 2012

Page 64: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

5. RAP not made available or charges too much for it

• YES, RAP IS WORTH A LOT !• Some wanted way too much, and priced out its use• Don’t forget, hauling, stockpiling, handling etc.• It’s full potential is realized when made available ;• From the project

Thursday, April 19, 2012

Page 65: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

5. RAP not made available or charges too much for it

• YES, RAP IS WORTH A LOT !• Some wanted way too much, and priced out its use• Don’t forget, hauling, stockpiling, handling etc.• It’s full potential is realized when made available ;• From the project• Stockpiles stated in the Special Provisions• The unit prices are typically 20 to 25% lower

Thursday, April 19, 2012

Page 66: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 67: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 68: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

4. Design not optimizing mill and fill strategies or ‘Road Mining’

• Generate it from the project whenever possible• Milling provides not only the valuable RAP ;• It is on site, minimal haul

Thursday, April 19, 2012

Page 69: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

4. Design not optimizing mill and fill strategies or ‘Road Mining’

• Generate it from the project whenever possible• Milling provides not only the valuable RAP ;• It is on site, minimal haul• It can be tested and properties evaluated prior too

Thursday, April 19, 2012

Page 70: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

4. Design not optimizing mill and fill strategies or ‘Road Mining’

• Generate it from the project whenever possible• Milling provides not only the valuable RAP ;• It is on site, minimal haul• It can be tested and properties evaluated prior too• Provides better texture for overlay to bond

Thursday, April 19, 2012

Page 71: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

4. Design not optimizing mill and fill strategies or ‘Road Mining’

• Generate it from the project whenever possible• Milling provides not only the valuable RAP ;• It is on site, minimal haul• It can be tested and properties evaluated prior too• Provides better texture for overlay to bond• Removes surface irregularities• Can correct the profile

Thursday, April 19, 2012

Page 72: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

4. Design not optimizing mill and fill strategies or ‘Road Mining’

• Removes unwanted hot pour from surface• Provides fresh pulverized millings• Generally makes millings more uniform

Thursday, April 19, 2012

Page 73: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

4. Design not optimizing mill and fill strategies or ‘Road Mining’

• Removes unwanted hot pour from surface• Provides fresh pulverized millings• Generally makes millings more uniform• Reduces grade raise, for any guardrail, curb and gutter,

matching into structures, elevation issues etc.

Thursday, April 19, 2012

Page 74: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

4. Design not optimizing mill and fill strategies or ‘Road Mining’

Thursday, April 19, 2012

Page 75: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

4. Design not optimizing mill and fill strategies or ‘Road Mining’

Thursday, April 19, 2012

Page 76: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

                                   ROAD MINING !

Existing  Original  Base  Pavement

Existing  Asphalt

Subgrade

Thursday, April 19, 2012

Page 77: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

                                   ROAD MINING !

Existing  Original  Base  Pavement

Subgrade

Thursday, April 19, 2012

Page 78: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

                                   ROAD MINING !

Existing  Original  Base  Pavement

Subgrade

Thursday, April 19, 2012

Page 79: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

                                   ROAD MINING !

Existing  Original  Base  Pavement

Subgrade

Every inch of millings of existing pavement, 24 foot wide, contains

$30,000 to $40,000 of Oil and Aggregate

Thursday, April 19, 2012

Page 80: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 81: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 82: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

• Need RAP feed system/collar• Grizzly and screening deck• Baghouse and plant need to be checked and see its

capabilities

Thursday, April 19, 2012

Page 83: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

• Need RAP feed system/collar• Grizzly and screening deck• Baghouse and plant need to be checked and see its

capabilities• Something new to some, unknowns

Thursday, April 19, 2012

Page 84: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

• Need RAP feed system/collar• Grizzly and screening deck• Baghouse and plant need to be checked and see its

capabilities• Something new to some, unknowns • Something different• All of our plants typically run between 40 & 50%

Thursday, April 19, 2012

Page 85: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 86: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 87: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 88: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 89: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 90: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 91: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 92: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

3. Plant says ‘Can’t Run it’

Thursday, April 19, 2012

Page 93: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 94: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 95: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

2. Stigma of lesser quality, need to Engineer

• Low temperature binder grades, such as XX-34• Soft base to rejuvenate the aged and oxidized binders• Use Polymer modified as much as you can, polymer loading

Thursday, April 19, 2012

Page 96: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

2. Stigma of lesser quality, need to Engineer

• Low temperature binder grades, such as XX-34• Soft base to rejuvenate the aged and oxidized binders• Use Polymer modified as much as you can, polymer loading• Much better compaction, not beating the heck out of the mat

and not fracturing aggregate• More dense

Thursday, April 19, 2012

Page 97: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

2. Stigma of lesser quality, need to Engineer

• No interconnected voids• Better Joint Density and Compaction• More resistant to water damage and aging due to such a

dense matrix

Thursday, April 19, 2012

Page 98: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

2. Stigma of lesser quality, need to Engineer

• No interconnected voids• Better Joint Density and Compaction• More resistant to water damage and aging due to such a

dense matrix• Compaction at laydown is much better, even with the

polymer modified• SPR is the industries favorite mix to lay

Thursday, April 19, 2012

Page 99: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

VirginRAP

Polymer

2.25%

VirginRAP

Polymer

2.25%1.25%

VirginRAP

Polymer

2.25%1.25%2.25%1.25%2.25%1.25%2.25%  2.50%

Thursday, April 19, 2012

Page 100: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

90%

10%Conventional        (PG  64-­‐28)

VirginRAP

Polymer

2.25%

VirginRAP

Polymer

2.25%1.25%

VirginRAP

Polymer

2.25%1.25%2.25%1.25%2.25%1.25%2.25%  2.50%

Thursday, April 19, 2012

Page 101: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

90%

10%Conventional        (PG  64-­‐28)

VirginRAP

Polymer

2.25%

50%

50%

High  Recycle  Conventional                (PG  64-­‐28)

VirginRAP

Polymer

2.25%1.25%

VirginRAP

Polymer

2.25%1.25%2.25%1.25%2.25%1.25%2.25%  2.50%

Thursday, April 19, 2012

Page 102: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

90%

10%Conventional        (PG  64-­‐28)

VirginRAP

Polymer

2.25%

50%

50%

High  Recycle  Conventional                (PG  64-­‐28)

VirginRAP

Polymer

2.25%1.25%

50%

High  Recycle  Polymer  Loading                (PG  64-­‐34)

VirginRAP

Polymer

2.25%1.25%2.25%1.25%2.25%1.25%2.25%  2.50%

Thursday, April 19, 2012

Page 103: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 104: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

TOP TEN REASONS RAP IS NOT OPTIMIZED

1. Owner/Specifier limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, need to Engineer 3. Plant says ‘Can’t Run it’4. Design not optimizing mill and fill strategies or ‘Road Mining’5. RAP not made available or charges too much for it6. Required binder bumps/reductions when higher amounts are used7. Restrictive in the specification, i.e. dust/asphalt maximum8. Limits RAP #200 amounts and rejects the RAP9. Restrictive Voids and VMA and other properties that limit RAP10. Too much hassle, one more thing to Manage and Design for

Thursday, April 19, 2012

Page 105: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

1. Owner/Specifyer limits use of RAP or says ‘I want the new stuff, not the used stuff ’

Thursday, April 19, 2012

Page 106: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

1. Owner/Specifyer limits use of RAP or says ‘I want the new stuff, not the used stuff ’

Whether  it  is  made  from…….

Thursday, April 19, 2012

Page 107: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

1. Owner/Specifyer limits use of RAP or says ‘I want the new stuff, not the used stuff ’

                     New  Aluminum

Whether  it  is  made  from…….

Thursday, April 19, 2012

Page 108: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

1. Owner/Specifyer limits use of RAP or says ‘I want the new stuff, not the used stuff ’

                     New  Aluminum          Recycled  Aluminum

Whether  it  is  made  from…….

Thursday, April 19, 2012

Page 109: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

1. Owner/Specifyer limits use of RAP or says ‘I want the new stuff, not the used stuff ’

                     New  Aluminum          Recycled  Aluminum

You  can’t  taste  the  difference

Whether  it  is  made  from…….

Thursday, April 19, 2012

Page 110: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

Thursday, April 19, 2012

Page 111: Nebraska Projects - RMACESNebraska Projects Addressing the Top Ten RAP Issues Robert C. Rea, P.E ... that limit RAP • Target 3% Air Voids at 7-65-100 Gyrations • VMA is an issue

Thank You!

Thursday, April 19, 2012