2
Project Area Map & Temporary Detour Route For more information, contact: Sarah Soula, NDOT Public Involvement // [email protected] // 402-479-4871 P.O. Box 94759, Lincoln, NE 68509-4759 Gary Thayer, District Engineer // [email protected] // 308-535-8031 1321 N Jeffers, PO Box 1108, North Platte, 69103-1108 Safety improvements include updating guardrail The existing asphalt is at or beyond its anticipated service life. NEBRASKA DEPARTMENT OF TRANSPORTATION TRYON-MULLEN STP-97-3(102); C.N. 60823 Public Comment Period March 1 - March 31, 2018 The proposed project would widen and resurface 12.67 miles of Nebraska Highway 97 (N-97) between Tryon and Mullen in Hooker County. The project would start near the McPherson-Hooker county line, at mile marker (MM) 44.23, and extend north to MM 56.90, 9.88 miles south of the Mullen corporate limits. Tryon Mullen Seneca Dismal River Thedford Stapleton 83 83 Middle Loup River South Loup River Project Area Temporary Full Closure Temporary Detour Route MAP LEGEND 0 10 miles Hooker County McPherson County Thomas County Logan County 97 2 2 97 92 92

NEBRASKA DEPARTMENT OF TRANSPORTATION TRYON …Project Area Map & Temporary Detour Route For more information, contact: Sarah Soula, NDOT Public Involvement // [email protected]

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NEBRASKA DEPARTMENT OF TRANSPORTATION TRYON …Project Area Map & Temporary Detour Route For more information, contact: Sarah Soula, NDOT Public Involvement // sarah.soula@nebraska.gov

Project Area Map & Temporary Detour Route

For more information, contact:Sarah Soula, NDOT Public Involvement // [email protected] // 402-479-4871P.O. Box 94759, Lincoln, NE 68509-4759Gary Thayer, District Engineer // [email protected] // 308-535-80311321 N Jeffers, PO Box 1108, North Platte, 69103-1108

Safety improvements include updating guardrail

The existing asphalt is at or beyond its anticipated service life.

NEBRASKA DEPARTMENT OF TRANSPORTATION

TRYON-MULLENSTP-97-3(102); C.N. 60823

Public Comment PeriodMarch 1 - March 31, 2018

The proposed project would widen and resurface 12.67 miles of Nebraska Highway 97 (N-97) between Tryon and Mullen in Hooker County.

The project would start near the McPherson-Hooker county line, at mile marker (MM) 44.23, and extend north to MM 56.90, 9.88 miles south of the Mullen corporate limits.

0 5 102.5 Miles

Tryon

MullenSeneca

Dismal River

Thedford

Stapleton

83

83

Middle Loup River

South Loup River

Project Area

Temporary Full Closure

Temporary Detour Route

MAP LEGEND0 10 miles

Hooker County

McPherson County

Thomas County

Logan County

97

2

2

97

92

92

Page 2: NEBRASKA DEPARTMENT OF TRANSPORTATION TRYON …Project Area Map & Temporary Detour Route For more information, contact: Sarah Soula, NDOT Public Involvement // sarah.soula@nebraska.gov

TRYON-MULLEN // STP-97-3(102); C.N. 60823

Information regarding the proposed project will be made available on the NDOT website at http://dot.nebraska.gov/projects/future-projects/ by clicking on the “Tryon - Mullen” link.

The construction of a retaining wall allows for the widening of the roadway without impacting the river.

Purpose and NeedThe purpose of the proposed project is to preserve the transportation asset of N-97, improve the reliability of the transportation system, and perpetuate the mobility of the traveling public. The need for this proposed project is based on the condition of the existing roadway and recent inspections showing that rehabilitation would be required.

Scope of WorkProposed improvements on N-97 would include a minimum 24-foot-wide surfaced top, 6-foot-wide earthen shoulders, curb and flume construction, removing and replacing guardrail, and surfacing underneath guardrail. To facilitate the roadway widening without impacting the Dismal River, a 400-foot-long retaining wall would be constructed on the east side of the highway between MM 53.38 and MM 53.46.

14’ 14’ 5’ 4’5’4’

10’ 10’

NORTHBOUNDSOUTHBOUND

NORTHBOUNDSOUTHBOUND

AREA TOBE FILLED

RETA

ININ

G W

ALL

Proposed Section at the Retaining Wall

Existing Section

Dismal River

Dismal River

FILL AREA ELIMINATED DUE TO

RETAINING WALL

Right-of-WayThis project would require the acquisition of additional property rights which could include new right-of-way (ROW), permanent easements (PE), and/or temporary easements (TE) throughout the project area. Access to adjacent properties would be maintained during construction but may be limited at times due to phasing requirements.

Potential ImpactsMinor wetlands impacts are anticipated; no mitigation is anticipated.

Estimated CostThe cost of the proposed project is approximately $8.5 million and would derive from federal and state funding sources.

Traffic Volumes

N-97 from MM 44.23 - 56.90

Year 2019 2029

Vehicles Per Day (ADT) 335 345

% Heavy Trucks 9% 9%

Construction ScheduleConstruction is tentatively scheduled to begin in March 2020 and completed in May 2021.

Accommodation of TrafficA majority of the project would be constructed under traffic with lane closures controlled by appropriate traffic control devices and practices. Full closure would be needed from MM 53.38 to MM 53.46 for approximately three weeks to facilitate sheet pile driving operations for a retaining wall. The temporary detour route would utilize N-2, US-83, and N-92.