Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Project Area Map & Temporary Detour Route
For more information, contact:Sarah Soula, NDOT Public Involvement // [email protected] // 402-479-4871P.O. Box 94759, Lincoln, NE 68509-4759Gary Thayer, District Engineer // [email protected] // 308-535-80311321 N Jeffers, PO Box 1108, North Platte, 69103-1108
Safety improvements include updating guardrail
The existing asphalt is at or beyond its anticipated service life.
NEBRASKA DEPARTMENT OF TRANSPORTATION
TRYON-MULLENSTP-97-3(102); C.N. 60823
Public Comment PeriodMarch 1 - March 31, 2018
The proposed project would widen and resurface 12.67 miles of Nebraska Highway 97 (N-97) between Tryon and Mullen in Hooker County.
The project would start near the McPherson-Hooker county line, at mile marker (MM) 44.23, and extend north to MM 56.90, 9.88 miles south of the Mullen corporate limits.
0 5 102.5 Miles
Tryon
MullenSeneca
Dismal River
Thedford
Stapleton
83
83
Middle Loup River
South Loup River
Project Area
Temporary Full Closure
Temporary Detour Route
MAP LEGEND0 10 miles
Hooker County
McPherson County
Thomas County
Logan County
97
2
2
97
92
92
TRYON-MULLEN // STP-97-3(102); C.N. 60823
Information regarding the proposed project will be made available on the NDOT website at http://dot.nebraska.gov/projects/future-projects/ by clicking on the “Tryon - Mullen” link.
The construction of a retaining wall allows for the widening of the roadway without impacting the river.
Purpose and NeedThe purpose of the proposed project is to preserve the transportation asset of N-97, improve the reliability of the transportation system, and perpetuate the mobility of the traveling public. The need for this proposed project is based on the condition of the existing roadway and recent inspections showing that rehabilitation would be required.
Scope of WorkProposed improvements on N-97 would include a minimum 24-foot-wide surfaced top, 6-foot-wide earthen shoulders, curb and flume construction, removing and replacing guardrail, and surfacing underneath guardrail. To facilitate the roadway widening without impacting the Dismal River, a 400-foot-long retaining wall would be constructed on the east side of the highway between MM 53.38 and MM 53.46.
14’ 14’ 5’ 4’5’4’
10’ 10’
NORTHBOUNDSOUTHBOUND
NORTHBOUNDSOUTHBOUND
AREA TOBE FILLED
RETA
ININ
G W
ALL
Proposed Section at the Retaining Wall
Existing Section
Dismal River
Dismal River
FILL AREA ELIMINATED DUE TO
RETAINING WALL
Right-of-WayThis project would require the acquisition of additional property rights which could include new right-of-way (ROW), permanent easements (PE), and/or temporary easements (TE) throughout the project area. Access to adjacent properties would be maintained during construction but may be limited at times due to phasing requirements.
Potential ImpactsMinor wetlands impacts are anticipated; no mitigation is anticipated.
Estimated CostThe cost of the proposed project is approximately $8.5 million and would derive from federal and state funding sources.
Traffic Volumes
N-97 from MM 44.23 - 56.90
Year 2019 2029
Vehicles Per Day (ADT) 335 345
% Heavy Trucks 9% 9%
Construction ScheduleConstruction is tentatively scheduled to begin in March 2020 and completed in May 2021.
Accommodation of TrafficA majority of the project would be constructed under traffic with lane closures controlled by appropriate traffic control devices and practices. Full closure would be needed from MM 53.38 to MM 53.46 for approximately three weeks to facilitate sheet pile driving operations for a retaining wall. The temporary detour route would utilize N-2, US-83, and N-92.