Upload
dstv2005
View
217
Download
0
Embed Size (px)
Citation preview
7/29/2019 NDrc
1/9
REQUIREMENTS AND RECOMMENDATIONSFOR NONDISRUPTIVE ROAD CROSSINGS
2002 Edition / Version 1.0
7/29/2019 NDrc
2/9
SECTION 1:
REQUIREMENTS FOR NONDISRUPTIVE ROAD CROSSINGS
1.1 SUBMITTALS REQUIRED FOR PERMIT TO CONDUCT NDRC 6
1.2 MONITORING SYSTEM 6
1.3 UNACCEPTABLE GROUND SURFACE MOVEMENT 7
1.4 REPAIR AND REINSTATEMENT 7
1.5 PROTECTION OF ADJACENT AREAS AND WORKS 7
SECTION 2:
RECOMMENDATIONS FOR NONDISRUPTIVE ROAD CROSSINGS
2.1 PURPOSE AND SCOPE 10
2.2 PRELIMINARY NDRC PLANNING 10
2.3 GEOTECHNICAL INVESTIGATION 10
2.3.1 RPOSE 10
2.3.1.1 ROUTE SELECTION 10
2.3.1.2 NDRC METHOD SELECTION AND OPTIMIZATION 11
2.3.1.3 DETERMINATION OF DESIGN PARAMETERS 11
2.3.2 SCOPE OF THE GEOTECHNICAL INVESTIGATION 11
2.4 DESIGN 11
2.4.1 ENGINEERING ANALYSIS 11
2.4.1.1 GENERAL ANALYSIS OF THE NDRC DRIVE 11
2.4.1.2 GROUND SURFACE MOVEMENT 12
2.4.1.3 SHORING FOR ENTRY AND EXIT PITS 13
2.4.1.4 DEWATERING 13
2.4.1.5 GROUND IMPROVEMENT 13
2.4.1.6 ALTERNATIVES TO NDRC TECHNIQUES 14
2.4.2 GENERAL RECOMMENDATIONS FOR DESIGN OF NDRCS 14
2.4.2.1 DEPTH 14
2.4.2.2 LOCATION OF ENTRY AND EXIT PITS 14
2.5 CONSTRUCTION SUPERVISION AND MONITORING 14
CONTENTS
7/29/2019 NDrc
3/9
REQUIREMENTS FORNONDISRUPTIVE
ROAD CROSSINGS
5
7/29/2019 NDrc
4/9
Requirements and Recommendations for Nondistruptive Road Crossings2002 Edition / Municipality of Abu Dhabi City
7
2 Upon completion o NDRC construction.
3 At a subsequent time ater completion o NDRC construction as directed by the De-
partment.
Benchmarks or measurement o elevation shall be located a minimum o 50 meters outside
o the monitoring area.
All survey work shall be done using equipment capable o an accuracy o 0.1 millimeter.
1.3 UNACCEPTABLE GROUND SURFACE MOVEMENT
Unacceptable ground surace movement (settlement or heave) s hall be dened
as movement greater than 6.0 millimeters vertically anywhere in a rectangular areacovering the entire width o the roadway along the drive and to boundaries extending
outwards rom the centerline o the NDRC drive. The distance o these boundaries rom
the centerline o the drive shall be as ollows:
ForanNDRCwithadiameter1.0meterorless,theboundariesshallbelocatedone
meter on each side o the drive centerline.
ForanNDRCwithadiametergreaterthan1.0meter,theboundariesshallbelocated
at a distance equal to the drive diameter on each side o the drive centerline.
Any ground surace movement exceeding the above limits that are detected during or
ater NDRC construction shall be immediately reported to the Department and proposed
remedial measures and/or intended actions shall be stated.
Measurements or ground surace movement shall be taken relative to the nished level o
the roadway at the time o measurement.
Ground surace movement limits in the specied area shall remain in eect or 10 years rom
dateofcompletionoftheNDRC,incompliancewithArticle16oftheGeneralConditionsof
Contract in the Field o Contracts o Civil Works.
1.4 REPAIR AND REINSTATEMENT
I ground movement as measured on the roadway surace exceeds the Departments stated
limits(Section1.3,above)orifdamageisapparentinadjacentareas,thecontractorshall
repair and
reinstatetheroadwayand/oradjacentareastotheiroriginalline,level,andcondition.The
expense or the repair and reinstatement shall be borne by the party responsible or the
project.RepairandreinstatementshallbedoneinaccordancewiththeRoadDepartments
StandardSpecicationsforRoadandBridgeConstructionandissubjecttothe
Departments approval.
1.5 PROTECTION OF ADJACENT AREAS AND WORKS
Uponcompletionofconstruction,curbs,sidewalks,orothersurfaceareasadjacenttothe
roadway shall not show any visible sign o disturbance or stress.
Any immediate or delayed damage occurring to Department property that is an indirect
result o utilities damage inficted as a result o the NDRC installation shall be the
responsibility o the contractor. Damage caused to other services or utilities shall be dealt
with separately with the concerned agency.
REQUIREMENTS FOR NONDISRUPTIVEROAD CROSSINGS
The ollowing subsections describe the Abu Dhabi Municipality Road Departments
requirements or construction o nondisruptive road crossings (NDRC).
Theserequirementsdonotcovertherequire-mentsofotheragencieswithjurisdictionfor
worksadjacenttooralreadyexistingbeneaththeroadway.Contractorsareresponsiblefor
procuringanyotherrequiredpermitsorapprovalsfromagencieswithjurisdictionoversuch
surace or subsurace works.
1.1 SUBMITTALS REQUIRED FOR PERMIT TO CONDUCT NDRC
PermissionoftheRoadDepartment(hereinafter,theDepartment)isrequiredforany
NDRCworkcarriedoutbelowpropertyunderthejurisdictionoftheDepartment.The
ollowing items shall be submitted to the Department when applying or a permit: JusticationforconductinganNDRCasop-posedtoanopencutorusingexisting
ducts.
AbriefdescriptionoftheNDRCmethodandequipmenttobeused.
ThenameofthecontractorandNDRCsub-contractorconductingtheworks.
LettersofapprovaloftheNDRCdesign,methodstatement,andsubcontractorsfrom
the consultant and the concerned agency (client) commissioning the NDRC work.
AbriefstatementonthesoilconditionsinthelocationoftheNDRC.
AgeneralplanthatclearlyshowstherouteandlocationoftheproposedNDRC.
Clearplan,prole,andsectiondrawingsoftheproposeddriveshowingthedetails
(suchasinternalandexternaldiameter,wallthickness,couplingsystem,etc.)of
thecasing(orsleeve),pipeline(carrierpipe),andintendedutilityinstallationand
their respective depths below the road surace. The drawings shall also show the
microtunnel(bore)andoverbreakdetails,aswellastheconstructiondetailsofentry
and exit pits and their planned location in relation to the road.
Sketchandscheduleofgroundsurfacemovementmonitoringsystemandbaseline
readingsformonitoringpointscollectedduringinitialsurvey(seenextsection),as
well as predicted ground movement (settlement and/or heave) based on scientic
calculations.
BankguaranteeandassociatedDepartmentalforms.
1.2 MONITORING SYSTEM
Forpurposesofmonitoringforgroundsurfacemovementontheroadway,thecontractor
shall install fush-head pins (35.0 millimeters to 50.0 millimeters in length) in the road
pavement. These pins shall be the monitoring points. The pins shall be installed in a grid
pattern with approximately 2.0-meter centers.
The grid o monitoring points shall cover the entire width o the roadway along the drive and
shall extend outwards in each direction rom the centerline o the drive to a distance o the
drive centerline depth below the road surace.
The contractor shall conduct surveys o all monitoring points and provide the Department
with drawings and precise survey inormation on each point three times:
1 Prior to commencement o NDRC construction (see Section 2.5 or Departmental
recommendation on the establishment o monitoring point baseline inormation).
7/29/2019 NDrc
5/9
RECOMMENDATIONSFOR NONDISRUPTIVE
ROAD CROSSINGS
9
7/29/2019 NDrc
6/9
Requirements and Recommendations for Nondistruptive Road Crossings2002 Edition / Municipality of Abu Dhabi City
11
2.3.1.2 NDRC METHOD SELECTION AND OPTIMIZATION
The soil investigation analysis should be used as the basis or the selection o the optimum
NDRCmethodandrelevanttunnelingmachinery(pipejacking,microtunneling,jetdrilling,
directionaldrilling,augerboring,etc.),aswellasfordeningtheoptimumoperational
variables(RPM,axialfeedrate,torque,ushandlubricantrate
andspecications,facepressure,etc.)forthechosentechnique.
2.3.1.3 DETERMINATION OF DESIGN PARAMETERS
Theinvestigationshouldresultinproperlyobtained,reliablesoilparameters,whichare
necessaryforadequatedesignofthedrives,shoring,anddewateringdetails.Analysisand
design(calculationsforjackingforces,stressanalysisonthepipeline,groundsurfacesettle-
mentandheaveanalysis,etc.)shouldbebasedonsuchparameters.
2.3.2 SCOPE OF THE GEOTECHNICAL INVESTIGATION
The inormation collected in the geotechnical investigation may include:
Typicalsoilprolesandgroundwaterlevels.
Indexandphaseparameters,suchas:
- Soil classication.
- Phaseparameters,suchasunitweight(),relativedensity(Dr),moisturecontent
(),saturation(S),voidratio(e),porosity(n),andanyotherparametersthatmaybe
useul.
- Shearstrengthparameters,suchascohesion(c),frictionangle(),andunconned
compressive strength (qu).
- Elasticconstantssuchastheelasticmodulus(E),PoissonRatio(),andsub-grade
reaction coecient (K).
- Soilcompressibilityandcollapsecoefcients,suchasvolumecompressibility
(mv,av,M)constantsparameters;compressionindices(dc,dr,etc.),andpre-
compression pressures (pp).
- Permeability (k) and erodability parameters.
- Any other relevant parameters.
2.4 DESIGN
Duringthisstage,adetailedengineeringanalysisshouldbecarriedoutapplyingtheresults
o the geotechnical investigation to the design o t he systems proposed in the preliminary
planning stage.
2.4.1 ENGINEERING ANALYSIS
Engineering analysis includes general geotech-nical analyses o the various aspects and
components o the proposed NDRC system as well as a check on the eects o the drive on
theexistingroadwayandadjacentareas.Thisincludes,butisnotlimitedto,thefollowing:
2.4.1.1 GENERAL ANALYSIS OF THE NDRC DRIVE
An NDRC system should be developed using available actual soil data and surrounding
RECOMMENDATIONS FOR NONDISRUPTIVEROAD CROSSINGS
2.1 PURPOSE AND SCOPE
Thissectionprovidesgeneralrecommendationsforplanning,design,andexecutionof
NDRCworksbelowpropertyunderthejurisdictionoftheDepartment.
NDRCworksconductedbelowAbuDhabiroad-waysunderthejurisdictionofthe
Departmentbyandatthebehestofotherentitiesaresubjecttotheperformance
requirementsoftheDepartment.Itistheresponsibilityofthecontractor,consultant,client
(concernedagency),andanyotherpartiesinvolvedintheconstructionofanNDRCunder
anAbuDhabiroadwaytoensurethatroadpavement,pertinentservices,andadjacent
areas such as sidewalks are not damaged and that any eects are within the acceptable
tolerances stated in the Departments NDRC requirements (Section 1 o this document).
Thesearerecommendationsofgoodpracticesfortheplanning,design,andexecutionof
successul NDRC works. Parties conducting an NDRC are expected to have a sucient
level o knowledge and expertise to carry out the construction successully.
2.2 PRELIMINARY NDRC PLANNING
Basedoninitialsitereconnaissanceandavailablesoilaswellasutilityinformation,adesk
study should be conducted to plan the method and route most appropriate or the purpose
in the given soil conditions. The desk study should accommodate the existing constraints
andallsurroundingconditions.Atthisstage,preliminaryanalysisisusefulincheckingthe
suitability o the proposed NDRC method.
The presence o surace and underground works in the area o the proposed NDRC should
be thoroughly investigated at this stage. Structural and pavement elements must be
considered,aswellasutilities.Conrmationofthepresenceor
absence o underground utilities is best achieved by excavate to locate. As-built drawings
alone may not be sucient or this purpose.
IfutilitiesarelocatedintheimmediatevicinityoftheNDRCwork,contractorsshould
coordinate with the concerned department or agency. Approval by the utility provider may
berequired,andtheprovidermaydemandspecicmeasuresbetakentoprotectitsassets.
2.3 GEOTECHNICAL INVESTIGATION
IfinsufcientgeotechnicalinformationisavailablefortheareawhereanNDRCisproposed,
then a thorough geotechnical investi-gation should be conducted.
2.3.1 PURPOSE
Anumberofobjectivescanbeachievedbyageotechnicalinvestigation:
2.3.1.1 ROUTE SELECTION
Theinvestigationshouldprovidesufcientgroundsfordeningthelineandleveloftheroute,
astheoptimumZ/Dratio(Z=depthtocrownofdrive,D=diameterofdrive)dependsonthe
typeofsoilstrataencounteredandtheNDRCmethodused.TheZ/Dratio,localground
conditions,andtheNDRCmethodhaveadirectrelationshiptothemagnitudeofsurface
deormation (settlement or heave) and breadth o the area aected.
The soil investigation should target specic routing considerations such as to avoid driving
throughweak/strongsoilboundaries,weatheringinterfaces,andgroundwatersurfaces.
7/29/2019 NDrc
7/9
Requirements and Recommendations for Nondistruptive Road Crossings2002 Edition / Municipality of Abu Dhabi City
13
methods may be needed to suciently analyze potential ground movement.
Sincetolerancesagainstgroundsurfacemove-mentsaresmall,theDepartment
recommendsthatveryconservativeassumptionsandmethodsbeusedandthattotal,not
fractional,movementsbedetermined.
Modesofanalysisshouldincludeallrelevantprinciples,whichinclude,butarenotlimitedto:
Elastic,elastoplastic,andviscoplasticdeformationalbehavior.
Immediate,short-term,andlong-termmovements.
Consolidation,collapse,andswell.
Volumetriccompressionandexpansion.
Volumeloss,soilpiping,internalerosion,andhydrocompaction.
Fractionalandtotalgroundmovements.
2.4.1.3 SHORING FOR ENTRY AND EXIT PITS
Proper shoring analysis and design should be conducted to meet the allowable shear
forces,bendingmoments,deections,andminimumpenetration(socketing)requirements
ofthewallsystem.Likewise,properanalysisanddesignoftheproposedsupportsystems
(anchors,bracing,strutting,waling,etc.)shouldbecarriedoutinaccordancewith
internationally acceptable practice.
Wheredesignagainstfullorpartialexternalhydraulicpressuresisassumed,watertight
shor-ing construction should be specied to satisy this condition. This construction should
preclude soil erosion (soil piping behind shoring) and ground settlement around the pits.
Hydraulic pressures behind shoring should never be allowed to exceed values considered in
the design calculations.
Analyticalorempiricalapproachesmaybeused,providedthevalidityandapplicabilityofthe
selectedapproachesarejustied.
2.4.1.4 DEWATERING
Dewateringsystems,includinganappropriatelteraroundriserpipes,shouldbecarefully
considered and designed properly. The lter design should ensure against the possibility o
any internal soil erosion that might cause ground settlement and collapse along t he drive or
around shoring boundaries. Filters can be either conventional soil lters or geotextile lters.
The Department preers and recommends the use o geotextile lters.
2.4.1.5 GROUND IMPROVEMENT
In cases where conventional NDRC methods seem to be unavorable or a particular
appli-cationorgivengroundconditions,orincaseswhereextremesensitivity(interms
oftolerance)oftheadjacentexistingworksdonotfavoranyoftheavailablemethods
alone,groundimprovement,suchassoilgrouting,maybenecessary.Thegoalofground
improvement is to enhance local conditions along the proposed route. Cementitious or
chemicalgroutsystemsappliedbefore,during,orafterconstructionarepossible
alternatives,dependingonexistinggroundconditions.
RECOMMENDATIONS FOR NONDISRUPTIVEROAD CROSSINGS
constraints.Thesystemshouldincluderecom-mendedroute(lineandlevel),boringsize,
NDRCmethod,pipelinedetails,equipment,andoperationalvariables,allofwhich,in
combina-tion,willachievetherequiredtolerances.Theproposedsystemshouldthenbe
analyzed or:
Jacking/pullingforces.
Lubricantcharacteristics.
Facestabil ity.
Thrustreactionelements.
Structuraldesignofpipeandjoints.
Groundsurfacemovement(settlementandheave).
2.4.1.2 GROUND SURFACE MOVEMENT
As ground surace movement is the chie risk and problem aced in attempting a successul
NDRC,itspreventionisdiscussedinmoredetailinthefollowingsubsections.
a. Ground Surface Movements Caused by NDRC Method and Pipeline
The combination o NDRC drive methods and pipeline details are key to preventing
excessivesurfacemovement,whichmayberelatedto:
Diameteranddepthofdrive.
Boringmethodandpractice.
Stiffnessofpipeandjointsystemandstruc-turalintegrity.
Jointalignment.
Maximumjacking/pullingforces.
Lubricationandushdetails.
Pipe/soilinteraction.
Overbreakanditsmanagement.
Facesupportdetails.
Groundwatercontroldetails.
b. Ground Surface Movement Due to Unfavorable Ground Conditions
Regardlessofdrivemethodordetails,sur-roundingsoilmaybesusceptibleto
excessive movements when disturbed by the drive (bore). The ollowing conditions can
infuence ground movements:
Residualorswellstressesleadingtoradial-elasticortime-dependentmovements.
Weaksoilsorshearfailureoftheface.
Loosecompressiblesoilsaroundorabovethedriveleadingtodensicationandhence
ground movement upon disturbance.
Internalerosionofloose,noncohesivesoilduetouncontrolledgroundwater
movements.
c. Movement Analysis Methods
Usingoneoracombinationofnumericalmod-elingmethods,theoreticalandempirical
7/29/2019 NDrc
8/9
Requirements and Recommendations for Nondistruptive Road Crossings2002 Edition / Municipality of Abu Dhabi City
15
operational variables against the completed driving distance in a properly recorded time
frame.Thisrecordcanbeusedasatoolandreferenceforinspectionandcontrol,andisa
permanent record or troubleshooting and interpretation o a drives behavior.
ThroughoutNDRCconstruction,existingworks(roads,nearbystructures,andutilities)
should be requently monitored under the supervision o qualied sta to detect any ground
surace movement.
BeforeConstruction
The Department recommends that several surveys be conducted o the monitoring
points prior to commencement o NDRC construction to establish a baseline level or
each point.
DuringConstruction
The Department recommends that moni-toring points are surveyed or ground surace
movementtwiceeachworkshift,andmorefrequentlyifanymovementisdetected.
AfterCompletionofConstruction
The Department recommends that moni-toring points be surveyed or ground surace
movementonceperdayforaminimumofoneweek,followedbyprogressively
decreasing requency or several months.
The Departments requirements or a monitoring system during NDRC work are
included in Section 1 o this document.
RECOMMENDATIONS FOR NONDISRUPTIVEROAD CROSSINGS
2.4.1.6 ALTERNATIVES TO NDRC TECHNIQUES
Some situations and congurations are not conducive to or prevent the construction o
NDRCs.Forexample,itmaynotbefeasibletoconstructalarge-diameterNDRCwhere
structures or other impediments would require entry and exit pits to be located very near
pavement boundaries.
Where engineering analysis and design suggest that tolerances can not be practically
metwithconventionalNDRCtechniquesandwheregroundimprovementisnotfeasible,
alternatives to NDRC systems should be considered. The goal o these systems is to allow
placement o the required pipelines while minimizing trac disruption. Alternative systems
available include:
Placingreinforcedconcreteslabs(preferablyprecast)belowthepavementlayerson
pregrouted soil abutments and excavating under the slabs. Trac disruption in this
case would be o limited duration and stabilization by anchoring and bolting would be
possible during excavation.
Open-trenchpipe-layingorprecastductinstallationfollowedbyquickbackllingusing
low-strength concrete or an approved fuidized quick-setting cementitious backll
material. Disruption to trac would be very minimal as the duration o the backlling
activity would be short.
Severalothersystemsasdescribedinengineeringandconstructionmethodslitera-
ture.
2.4.2 GENERAL RECOMMENDATIONS FOR DESIGN OF NDRCS
2.4.2.1 DEPTH
ForNDRCswithadiameterof1.0meterorless,theDepartmentrecommendsaminimum
depthof3.0meters,measuredfromtheroadsurfacetothecrownofthedrive.ForNDRCs
withadiameterofgreaterthan1.0meter,theDepartmentrecommendsaminimumdepth
o three times the NDRCs diameter.
Inotherwords,whereD=diameterofdriveandZ=depthtocrownofdrive,the
recommended criteria are:
IfD1.0meter,Z3.0meters. IfD>1.0meter,Z3D.
2.4.2.2 LOCATION OF ENTRY AND EXIT PITS
The Department recommends that entry and exit pits or construction o NDRCs be located
a minimum o 5.0 meters rom the edges o the paved roadway.
2.5 CONSTRUCTION SUPERVISION AND MONITORING
Qualied supervisory sta should be present in the eld during the execution o NDRC works
to ensure that the approved design and method are being ollowed.
Onceconstructionhasbegun,automatedormanualrecordingofalloperationalvariables,
progress,drivebehavior,etc.,shouldbecarriedouttoensurecompliancewiththeintended
set o operational variables. The record produced should orm a continuous log o all
7/29/2019 NDrc
9/9