NDrc

Embed Size (px)

Citation preview

  • 7/29/2019 NDrc

    1/9

    REQUIREMENTS AND RECOMMENDATIONSFOR NONDISRUPTIVE ROAD CROSSINGS

    2002 Edition / Version 1.0

  • 7/29/2019 NDrc

    2/9

    SECTION 1:

    REQUIREMENTS FOR NONDISRUPTIVE ROAD CROSSINGS

    1.1 SUBMITTALS REQUIRED FOR PERMIT TO CONDUCT NDRC 6

    1.2 MONITORING SYSTEM 6

    1.3 UNACCEPTABLE GROUND SURFACE MOVEMENT 7

    1.4 REPAIR AND REINSTATEMENT 7

    1.5 PROTECTION OF ADJACENT AREAS AND WORKS 7

    SECTION 2:

    RECOMMENDATIONS FOR NONDISRUPTIVE ROAD CROSSINGS

    2.1 PURPOSE AND SCOPE 10

    2.2 PRELIMINARY NDRC PLANNING 10

    2.3 GEOTECHNICAL INVESTIGATION 10

    2.3.1 RPOSE 10

    2.3.1.1 ROUTE SELECTION 10

    2.3.1.2 NDRC METHOD SELECTION AND OPTIMIZATION 11

    2.3.1.3 DETERMINATION OF DESIGN PARAMETERS 11

    2.3.2 SCOPE OF THE GEOTECHNICAL INVESTIGATION 11

    2.4 DESIGN 11

    2.4.1 ENGINEERING ANALYSIS 11

    2.4.1.1 GENERAL ANALYSIS OF THE NDRC DRIVE 11

    2.4.1.2 GROUND SURFACE MOVEMENT 12

    2.4.1.3 SHORING FOR ENTRY AND EXIT PITS 13

    2.4.1.4 DEWATERING 13

    2.4.1.5 GROUND IMPROVEMENT 13

    2.4.1.6 ALTERNATIVES TO NDRC TECHNIQUES 14

    2.4.2 GENERAL RECOMMENDATIONS FOR DESIGN OF NDRCS 14

    2.4.2.1 DEPTH 14

    2.4.2.2 LOCATION OF ENTRY AND EXIT PITS 14

    2.5 CONSTRUCTION SUPERVISION AND MONITORING 14

    CONTENTS

  • 7/29/2019 NDrc

    3/9

    REQUIREMENTS FORNONDISRUPTIVE

    ROAD CROSSINGS

    5

  • 7/29/2019 NDrc

    4/9

    Requirements and Recommendations for Nondistruptive Road Crossings2002 Edition / Municipality of Abu Dhabi City

    7

    2 Upon completion o NDRC construction.

    3 At a subsequent time ater completion o NDRC construction as directed by the De-

    partment.

    Benchmarks or measurement o elevation shall be located a minimum o 50 meters outside

    o the monitoring area.

    All survey work shall be done using equipment capable o an accuracy o 0.1 millimeter.

    1.3 UNACCEPTABLE GROUND SURFACE MOVEMENT

    Unacceptable ground surace movement (settlement or heave) s hall be dened

    as movement greater than 6.0 millimeters vertically anywhere in a rectangular areacovering the entire width o the roadway along the drive and to boundaries extending

    outwards rom the centerline o the NDRC drive. The distance o these boundaries rom

    the centerline o the drive shall be as ollows:

    ForanNDRCwithadiameter1.0meterorless,theboundariesshallbelocatedone

    meter on each side o the drive centerline.

    ForanNDRCwithadiametergreaterthan1.0meter,theboundariesshallbelocated

    at a distance equal to the drive diameter on each side o the drive centerline.

    Any ground surace movement exceeding the above limits that are detected during or

    ater NDRC construction shall be immediately reported to the Department and proposed

    remedial measures and/or intended actions shall be stated.

    Measurements or ground surace movement shall be taken relative to the nished level o

    the roadway at the time o measurement.

    Ground surace movement limits in the specied area shall remain in eect or 10 years rom

    dateofcompletionoftheNDRC,incompliancewithArticle16oftheGeneralConditionsof

    Contract in the Field o Contracts o Civil Works.

    1.4 REPAIR AND REINSTATEMENT

    I ground movement as measured on the roadway surace exceeds the Departments stated

    limits(Section1.3,above)orifdamageisapparentinadjacentareas,thecontractorshall

    repair and

    reinstatetheroadwayand/oradjacentareastotheiroriginalline,level,andcondition.The

    expense or the repair and reinstatement shall be borne by the party responsible or the

    project.RepairandreinstatementshallbedoneinaccordancewiththeRoadDepartments

    StandardSpecicationsforRoadandBridgeConstructionandissubjecttothe

    Departments approval.

    1.5 PROTECTION OF ADJACENT AREAS AND WORKS

    Uponcompletionofconstruction,curbs,sidewalks,orothersurfaceareasadjacenttothe

    roadway shall not show any visible sign o disturbance or stress.

    Any immediate or delayed damage occurring to Department property that is an indirect

    result o utilities damage inficted as a result o the NDRC installation shall be the

    responsibility o the contractor. Damage caused to other services or utilities shall be dealt

    with separately with the concerned agency.

    REQUIREMENTS FOR NONDISRUPTIVEROAD CROSSINGS

    The ollowing subsections describe the Abu Dhabi Municipality Road Departments

    requirements or construction o nondisruptive road crossings (NDRC).

    Theserequirementsdonotcovertherequire-mentsofotheragencieswithjurisdictionfor

    worksadjacenttooralreadyexistingbeneaththeroadway.Contractorsareresponsiblefor

    procuringanyotherrequiredpermitsorapprovalsfromagencieswithjurisdictionoversuch

    surace or subsurace works.

    1.1 SUBMITTALS REQUIRED FOR PERMIT TO CONDUCT NDRC

    PermissionoftheRoadDepartment(hereinafter,theDepartment)isrequiredforany

    NDRCworkcarriedoutbelowpropertyunderthejurisdictionoftheDepartment.The

    ollowing items shall be submitted to the Department when applying or a permit: JusticationforconductinganNDRCasop-posedtoanopencutorusingexisting

    ducts.

    AbriefdescriptionoftheNDRCmethodandequipmenttobeused.

    ThenameofthecontractorandNDRCsub-contractorconductingtheworks.

    LettersofapprovaloftheNDRCdesign,methodstatement,andsubcontractorsfrom

    the consultant and the concerned agency (client) commissioning the NDRC work.

    AbriefstatementonthesoilconditionsinthelocationoftheNDRC.

    AgeneralplanthatclearlyshowstherouteandlocationoftheproposedNDRC.

    Clearplan,prole,andsectiondrawingsoftheproposeddriveshowingthedetails

    (suchasinternalandexternaldiameter,wallthickness,couplingsystem,etc.)of

    thecasing(orsleeve),pipeline(carrierpipe),andintendedutilityinstallationand

    their respective depths below the road surace. The drawings shall also show the

    microtunnel(bore)andoverbreakdetails,aswellastheconstructiondetailsofentry

    and exit pits and their planned location in relation to the road.

    Sketchandscheduleofgroundsurfacemovementmonitoringsystemandbaseline

    readingsformonitoringpointscollectedduringinitialsurvey(seenextsection),as

    well as predicted ground movement (settlement and/or heave) based on scientic

    calculations.

    BankguaranteeandassociatedDepartmentalforms.

    1.2 MONITORING SYSTEM

    Forpurposesofmonitoringforgroundsurfacemovementontheroadway,thecontractor

    shall install fush-head pins (35.0 millimeters to 50.0 millimeters in length) in the road

    pavement. These pins shall be the monitoring points. The pins shall be installed in a grid

    pattern with approximately 2.0-meter centers.

    The grid o monitoring points shall cover the entire width o the roadway along the drive and

    shall extend outwards in each direction rom the centerline o the drive to a distance o the

    drive centerline depth below the road surace.

    The contractor shall conduct surveys o all monitoring points and provide the Department

    with drawings and precise survey inormation on each point three times:

    1 Prior to commencement o NDRC construction (see Section 2.5 or Departmental

    recommendation on the establishment o monitoring point baseline inormation).

  • 7/29/2019 NDrc

    5/9

    RECOMMENDATIONSFOR NONDISRUPTIVE

    ROAD CROSSINGS

    9

  • 7/29/2019 NDrc

    6/9

    Requirements and Recommendations for Nondistruptive Road Crossings2002 Edition / Municipality of Abu Dhabi City

    11

    2.3.1.2 NDRC METHOD SELECTION AND OPTIMIZATION

    The soil investigation analysis should be used as the basis or the selection o the optimum

    NDRCmethodandrelevanttunnelingmachinery(pipejacking,microtunneling,jetdrilling,

    directionaldrilling,augerboring,etc.),aswellasfordeningtheoptimumoperational

    variables(RPM,axialfeedrate,torque,ushandlubricantrate

    andspecications,facepressure,etc.)forthechosentechnique.

    2.3.1.3 DETERMINATION OF DESIGN PARAMETERS

    Theinvestigationshouldresultinproperlyobtained,reliablesoilparameters,whichare

    necessaryforadequatedesignofthedrives,shoring,anddewateringdetails.Analysisand

    design(calculationsforjackingforces,stressanalysisonthepipeline,groundsurfacesettle-

    mentandheaveanalysis,etc.)shouldbebasedonsuchparameters.

    2.3.2 SCOPE OF THE GEOTECHNICAL INVESTIGATION

    The inormation collected in the geotechnical investigation may include:

    Typicalsoilprolesandgroundwaterlevels.

    Indexandphaseparameters,suchas:

    - Soil classication.

    - Phaseparameters,suchasunitweight(),relativedensity(Dr),moisturecontent

    (),saturation(S),voidratio(e),porosity(n),andanyotherparametersthatmaybe

    useul.

    - Shearstrengthparameters,suchascohesion(c),frictionangle(),andunconned

    compressive strength (qu).

    - Elasticconstantssuchastheelasticmodulus(E),PoissonRatio(),andsub-grade

    reaction coecient (K).

    - Soilcompressibilityandcollapsecoefcients,suchasvolumecompressibility

    (mv,av,M)constantsparameters;compressionindices(dc,dr,etc.),andpre-

    compression pressures (pp).

    - Permeability (k) and erodability parameters.

    - Any other relevant parameters.

    2.4 DESIGN

    Duringthisstage,adetailedengineeringanalysisshouldbecarriedoutapplyingtheresults

    o the geotechnical investigation to the design o t he systems proposed in the preliminary

    planning stage.

    2.4.1 ENGINEERING ANALYSIS

    Engineering analysis includes general geotech-nical analyses o the various aspects and

    components o the proposed NDRC system as well as a check on the eects o the drive on

    theexistingroadwayandadjacentareas.Thisincludes,butisnotlimitedto,thefollowing:

    2.4.1.1 GENERAL ANALYSIS OF THE NDRC DRIVE

    An NDRC system should be developed using available actual soil data and surrounding

    RECOMMENDATIONS FOR NONDISRUPTIVEROAD CROSSINGS

    2.1 PURPOSE AND SCOPE

    Thissectionprovidesgeneralrecommendationsforplanning,design,andexecutionof

    NDRCworksbelowpropertyunderthejurisdictionoftheDepartment.

    NDRCworksconductedbelowAbuDhabiroad-waysunderthejurisdictionofthe

    Departmentbyandatthebehestofotherentitiesaresubjecttotheperformance

    requirementsoftheDepartment.Itistheresponsibilityofthecontractor,consultant,client

    (concernedagency),andanyotherpartiesinvolvedintheconstructionofanNDRCunder

    anAbuDhabiroadwaytoensurethatroadpavement,pertinentservices,andadjacent

    areas such as sidewalks are not damaged and that any eects are within the acceptable

    tolerances stated in the Departments NDRC requirements (Section 1 o this document).

    Thesearerecommendationsofgoodpracticesfortheplanning,design,andexecutionof

    successul NDRC works. Parties conducting an NDRC are expected to have a sucient

    level o knowledge and expertise to carry out the construction successully.

    2.2 PRELIMINARY NDRC PLANNING

    Basedoninitialsitereconnaissanceandavailablesoilaswellasutilityinformation,adesk

    study should be conducted to plan the method and route most appropriate or the purpose

    in the given soil conditions. The desk study should accommodate the existing constraints

    andallsurroundingconditions.Atthisstage,preliminaryanalysisisusefulincheckingthe

    suitability o the proposed NDRC method.

    The presence o surace and underground works in the area o the proposed NDRC should

    be thoroughly investigated at this stage. Structural and pavement elements must be

    considered,aswellasutilities.Conrmationofthepresenceor

    absence o underground utilities is best achieved by excavate to locate. As-built drawings

    alone may not be sucient or this purpose.

    IfutilitiesarelocatedintheimmediatevicinityoftheNDRCwork,contractorsshould

    coordinate with the concerned department or agency. Approval by the utility provider may

    berequired,andtheprovidermaydemandspecicmeasuresbetakentoprotectitsassets.

    2.3 GEOTECHNICAL INVESTIGATION

    IfinsufcientgeotechnicalinformationisavailablefortheareawhereanNDRCisproposed,

    then a thorough geotechnical investi-gation should be conducted.

    2.3.1 PURPOSE

    Anumberofobjectivescanbeachievedbyageotechnicalinvestigation:

    2.3.1.1 ROUTE SELECTION

    Theinvestigationshouldprovidesufcientgroundsfordeningthelineandleveloftheroute,

    astheoptimumZ/Dratio(Z=depthtocrownofdrive,D=diameterofdrive)dependsonthe

    typeofsoilstrataencounteredandtheNDRCmethodused.TheZ/Dratio,localground

    conditions,andtheNDRCmethodhaveadirectrelationshiptothemagnitudeofsurface

    deormation (settlement or heave) and breadth o the area aected.

    The soil investigation should target specic routing considerations such as to avoid driving

    throughweak/strongsoilboundaries,weatheringinterfaces,andgroundwatersurfaces.

  • 7/29/2019 NDrc

    7/9

    Requirements and Recommendations for Nondistruptive Road Crossings2002 Edition / Municipality of Abu Dhabi City

    13

    methods may be needed to suciently analyze potential ground movement.

    Sincetolerancesagainstgroundsurfacemove-mentsaresmall,theDepartment

    recommendsthatveryconservativeassumptionsandmethodsbeusedandthattotal,not

    fractional,movementsbedetermined.

    Modesofanalysisshouldincludeallrelevantprinciples,whichinclude,butarenotlimitedto:

    Elastic,elastoplastic,andviscoplasticdeformationalbehavior.

    Immediate,short-term,andlong-termmovements.

    Consolidation,collapse,andswell.

    Volumetriccompressionandexpansion.

    Volumeloss,soilpiping,internalerosion,andhydrocompaction.

    Fractionalandtotalgroundmovements.

    2.4.1.3 SHORING FOR ENTRY AND EXIT PITS

    Proper shoring analysis and design should be conducted to meet the allowable shear

    forces,bendingmoments,deections,andminimumpenetration(socketing)requirements

    ofthewallsystem.Likewise,properanalysisanddesignoftheproposedsupportsystems

    (anchors,bracing,strutting,waling,etc.)shouldbecarriedoutinaccordancewith

    internationally acceptable practice.

    Wheredesignagainstfullorpartialexternalhydraulicpressuresisassumed,watertight

    shor-ing construction should be specied to satisy this condition. This construction should

    preclude soil erosion (soil piping behind shoring) and ground settlement around the pits.

    Hydraulic pressures behind shoring should never be allowed to exceed values considered in

    the design calculations.

    Analyticalorempiricalapproachesmaybeused,providedthevalidityandapplicabilityofthe

    selectedapproachesarejustied.

    2.4.1.4 DEWATERING

    Dewateringsystems,includinganappropriatelteraroundriserpipes,shouldbecarefully

    considered and designed properly. The lter design should ensure against the possibility o

    any internal soil erosion that might cause ground settlement and collapse along t he drive or

    around shoring boundaries. Filters can be either conventional soil lters or geotextile lters.

    The Department preers and recommends the use o geotextile lters.

    2.4.1.5 GROUND IMPROVEMENT

    In cases where conventional NDRC methods seem to be unavorable or a particular

    appli-cationorgivengroundconditions,orincaseswhereextremesensitivity(interms

    oftolerance)oftheadjacentexistingworksdonotfavoranyoftheavailablemethods

    alone,groundimprovement,suchassoilgrouting,maybenecessary.Thegoalofground

    improvement is to enhance local conditions along the proposed route. Cementitious or

    chemicalgroutsystemsappliedbefore,during,orafterconstructionarepossible

    alternatives,dependingonexistinggroundconditions.

    RECOMMENDATIONS FOR NONDISRUPTIVEROAD CROSSINGS

    constraints.Thesystemshouldincluderecom-mendedroute(lineandlevel),boringsize,

    NDRCmethod,pipelinedetails,equipment,andoperationalvariables,allofwhich,in

    combina-tion,willachievetherequiredtolerances.Theproposedsystemshouldthenbe

    analyzed or:

    Jacking/pullingforces.

    Lubricantcharacteristics.

    Facestabil ity.

    Thrustreactionelements.

    Structuraldesignofpipeandjoints.

    Groundsurfacemovement(settlementandheave).

    2.4.1.2 GROUND SURFACE MOVEMENT

    As ground surace movement is the chie risk and problem aced in attempting a successul

    NDRC,itspreventionisdiscussedinmoredetailinthefollowingsubsections.

    a. Ground Surface Movements Caused by NDRC Method and Pipeline

    The combination o NDRC drive methods and pipeline details are key to preventing

    excessivesurfacemovement,whichmayberelatedto:

    Diameteranddepthofdrive.

    Boringmethodandpractice.

    Stiffnessofpipeandjointsystemandstruc-turalintegrity.

    Jointalignment.

    Maximumjacking/pullingforces.

    Lubricationandushdetails.

    Pipe/soilinteraction.

    Overbreakanditsmanagement.

    Facesupportdetails.

    Groundwatercontroldetails.

    b. Ground Surface Movement Due to Unfavorable Ground Conditions

    Regardlessofdrivemethodordetails,sur-roundingsoilmaybesusceptibleto

    excessive movements when disturbed by the drive (bore). The ollowing conditions can

    infuence ground movements:

    Residualorswellstressesleadingtoradial-elasticortime-dependentmovements.

    Weaksoilsorshearfailureoftheface.

    Loosecompressiblesoilsaroundorabovethedriveleadingtodensicationandhence

    ground movement upon disturbance.

    Internalerosionofloose,noncohesivesoilduetouncontrolledgroundwater

    movements.

    c. Movement Analysis Methods

    Usingoneoracombinationofnumericalmod-elingmethods,theoreticalandempirical

  • 7/29/2019 NDrc

    8/9

    Requirements and Recommendations for Nondistruptive Road Crossings2002 Edition / Municipality of Abu Dhabi City

    15

    operational variables against the completed driving distance in a properly recorded time

    frame.Thisrecordcanbeusedasatoolandreferenceforinspectionandcontrol,andisa

    permanent record or troubleshooting and interpretation o a drives behavior.

    ThroughoutNDRCconstruction,existingworks(roads,nearbystructures,andutilities)

    should be requently monitored under the supervision o qualied sta to detect any ground

    surace movement.

    BeforeConstruction

    The Department recommends that several surveys be conducted o the monitoring

    points prior to commencement o NDRC construction to establish a baseline level or

    each point.

    DuringConstruction

    The Department recommends that moni-toring points are surveyed or ground surace

    movementtwiceeachworkshift,andmorefrequentlyifanymovementisdetected.

    AfterCompletionofConstruction

    The Department recommends that moni-toring points be surveyed or ground surace

    movementonceperdayforaminimumofoneweek,followedbyprogressively

    decreasing requency or several months.

    The Departments requirements or a monitoring system during NDRC work are

    included in Section 1 o this document.

    RECOMMENDATIONS FOR NONDISRUPTIVEROAD CROSSINGS

    2.4.1.6 ALTERNATIVES TO NDRC TECHNIQUES

    Some situations and congurations are not conducive to or prevent the construction o

    NDRCs.Forexample,itmaynotbefeasibletoconstructalarge-diameterNDRCwhere

    structures or other impediments would require entry and exit pits to be located very near

    pavement boundaries.

    Where engineering analysis and design suggest that tolerances can not be practically

    metwithconventionalNDRCtechniquesandwheregroundimprovementisnotfeasible,

    alternatives to NDRC systems should be considered. The goal o these systems is to allow

    placement o the required pipelines while minimizing trac disruption. Alternative systems

    available include:

    Placingreinforcedconcreteslabs(preferablyprecast)belowthepavementlayerson

    pregrouted soil abutments and excavating under the slabs. Trac disruption in this

    case would be o limited duration and stabilization by anchoring and bolting would be

    possible during excavation.

    Open-trenchpipe-layingorprecastductinstallationfollowedbyquickbackllingusing

    low-strength concrete or an approved fuidized quick-setting cementitious backll

    material. Disruption to trac would be very minimal as the duration o the backlling

    activity would be short.

    Severalothersystemsasdescribedinengineeringandconstructionmethodslitera-

    ture.

    2.4.2 GENERAL RECOMMENDATIONS FOR DESIGN OF NDRCS

    2.4.2.1 DEPTH

    ForNDRCswithadiameterof1.0meterorless,theDepartmentrecommendsaminimum

    depthof3.0meters,measuredfromtheroadsurfacetothecrownofthedrive.ForNDRCs

    withadiameterofgreaterthan1.0meter,theDepartmentrecommendsaminimumdepth

    o three times the NDRCs diameter.

    Inotherwords,whereD=diameterofdriveandZ=depthtocrownofdrive,the

    recommended criteria are:

    IfD1.0meter,Z3.0meters. IfD>1.0meter,Z3D.

    2.4.2.2 LOCATION OF ENTRY AND EXIT PITS

    The Department recommends that entry and exit pits or construction o NDRCs be located

    a minimum o 5.0 meters rom the edges o the paved roadway.

    2.5 CONSTRUCTION SUPERVISION AND MONITORING

    Qualied supervisory sta should be present in the eld during the execution o NDRC works

    to ensure that the approved design and method are being ollowed.

    Onceconstructionhasbegun,automatedormanualrecordingofalloperationalvariables,

    progress,drivebehavior,etc.,shouldbecarriedouttoensurecompliancewiththeintended

    set o operational variables. The record produced should orm a continuous log o all

  • 7/29/2019 NDrc

    9/9