2
CASE STUDY NCR – HOSTED SOLUTIONS GROUP Challenge With the acquisition of Radiant Systems, NCR Commercial Real Estate was quick to assess the needs of their newly expanded work force. NCR turned to CBRE to assist in identifying suitable office space that could accommodate a growing business group within the former Radiant Systems that was badly needed. They would need to identify a location, design, and fit out the space to serve the growing teams needs in less than 11 weeks to avoid potential lease hold over as well as provide breathing room for the expanding business unit. Solutions CBRE quickly identified a working team that consisted of NCR business unit leaders, CRE leaders, IT managers as well as the CBRE GCS team assigned to the NCR account. CBRE immediately set up site tours to identify a suitable location for the requirements of the Business Group. Through conducting multiple tours and analysis of project cost data and leasing stipulations CBRE was able to provide a timely recommendation for NCR leaders to evaluate and select a location. Once the selection was made CBRE project management would take the lead and implement a fast track approach to ensure that the space would be ready by the July 30 th deadline which was critical to avoid unnecessary leasing costs. Results CBRE’s recommendation included the selection of a space that could easily be transformed to meet the end users requirements. Through utilizing CBRE standard RFQ’s and competitive bid solutions, CBRE was able to select a team that best met the needs of NCR in a timely and cost efficient approach. The project design and build out revolved around a fast track approach and ultimately lead to the space being completed in time to relocate the new NCR employee’s to a space that would allow them to continue its business without interruption or unwarranted costs. CLIENT TESTIMONIAL Many thanks from myself and from the Midtown team. The space is a fantastic enhancement to our creativity and vision for the Hosted Solutions Group of NCR. Your team’s efforts are very much appreciated. The ball is in our court now to build our business, our customer’s profitability, and the careers of fantastic NCR engineers.” Mike Finley Chief Technology Officer CBRE CONTACT JESSE KELLEY Project Manager T: 404.812.5177 [email protected] QUICK FACTS Location: 817 West Peachtree Street N.W., Atlanta, Ga 30308 Project type (Scope): Office Space, Lab Space Project Size: 6,727 SF Project Value: $166,195.00 Duration (04/09/12–6/30/12) Scope Items: New Work Stations, New Breakroom and Lounge Furniture, Signage, Lab Environment, Audio Visual, Kitchen Appliances, Paint and Carpet and Voice and Data Infrastructure

NCR - Hosted Solutions - Case Study

Embed Size (px)

Citation preview

Page 1: NCR - Hosted Solutions - Case Study

CASE STUDY

NCR – HOSTED SOLUTIONS GROUP

Challenge With the acquisition of Radiant Systems, NCR Commercial Real Estate was quick to assess the needs of their newly expanded work force. NCR turned to CBRE to assist in identifying suitable office space that could accommodate a growing business group within the former Radiant Systems that was badly needed. They would need to identify a location, design, and fit out the space to serve the growing teams needs in less than 11 weeks to avoid potential lease hold over as well as provide breathing room for the expanding business unit.

Solutions CBRE quickly identified a working team that consisted of NCR business unit leaders, CRE leaders, IT managers as well as the CBRE GCS team assigned to the NCR account. CBRE immediately set up site tours to identify a suitable location for the requirements of the Business Group. Through conducting multiple tours and analysis of project cost data and leasing stipulations CBRE was able to provide a timely recommendation for NCR leaders to evaluate and select a location. Once the selection was made CBRE project management would take the lead and implement a fast track approach to ensure that the space would be ready by the July 30th deadline which was critical to avoid unnecessary leasing costs.

Results CBRE’s recommendation included the selection of a space that could easily be transformed to meet the end users requirements. Through utilizing CBRE standard RFQ’s and competitive bid solutions, CBRE was able to select a team that best met the needs of NCR in a timely and cost efficient approach. The project design and build out revolved around a fast track approach and ultimately lead to the space being completed in time to relocate the new NCR employee’s to a space that would allow them to continue its business without interruption or unwarranted costs.

CLIENT TESTIMONIAL

“Many thanks from myself and from the Midtown team.  The space is a fantastic 

enhancement to our creativity and vision for the Hosted Solutions Group of 

NCR.  Your team’s efforts are very much appreciated.  The ball is in our court 

now to build our business, our customer’s profitability, and the careers of 

fantastic NCR engineers.” 

Mike Finley Chief Technology Officer

CBRE CONTACT JESSE KELLEY Project Manager T: 404.812.5177 [email protected]

QUICK FACTS

Location: 817 West Peachtree Street N.W., Atlanta, Ga 30308

Project type (Scope): Office Space, Lab Space

Project Size: 6,727 SF

Project Value: $166,195.00

Duration (04/09/12–6/30/12)

Scope Items: New Work Stations, New Breakroom and Lounge Furniture, Signage, Lab Environment, Audio Visual, Kitchen Appliances, Paint and Carpet and Voice and Data Infrastructure