NCC Infrastructure NCC Wind Power Finland

NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

NCC Wind PowerFinland

Page 2: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

Content1. NCC services2. Contract model3. References in Finland4. Contacts

NCC Infrastructure

Page 3: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

We provide wide range of services for wind parks• Assistance in permitting sites• Site surveys• Design• Civil engineering• Electrical engineering

NCC´s Wind Power Services

Page 4: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• Access roads, platforms and assembly areas ‒ Geotechnical investigations ‒ Design and construction

• Foundations‒ Geotechnical investigations and design ‒ Design and construction of foundations‒ Assembly of anchor cages, cable ducts etc.

• Electrical and data network‒ Design, acquisition and construction of substation, main

transformer, cables and accessories‒ Investigation, testing and energization of electrical system

• Assisting in building permitting processes

NCC’s scope as wind farm contractor

Page 5: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

ReferencesWind Power Projects in Finland

NCC Infrastructure

Page 6: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 6 wind turbines, Vestas• Customer Empower Oy• Construction time 6–11/2011• NCC’s scope‒ Construction of access roads and assembly areas ‒ Road design

Tuuliwatti, Simo Wind Farm

Page 7: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 9 turbines, Nordex N117• Construction time 11/2012–6/2013• NCC’s scope‒ Foundation ground works design and construction ‒ Foundation design and construction‒ Substation, electrical and data network design and construction‒ Main contractor liability during the Nordex works

Taaleritehdas, Honkajoki Wind Farm

Page 8: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 8 turbines, Nordex N117• Construction time 07/2013-07/2014• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Substation, electrical and data network design and construction‒ Main contractor liability during the Nordex works

Taaleritehdas, Nyby Wind Farm

Page 9: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 19 turbines, Nordex N117• Construction time 2/2014–5/2015• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Electrical and data network design and construction‒ Main contractor liability during the Nordex works

Taaleritehdas,Myllykangas Wind Farm

Page 10: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 9 turbines, Nordex N131• Construction time 1–10/2015• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Substation, electrical and data network design and construction‒ Main contractor liability during the Nordex works

Taaleritehdas, Kooninkallio Wind Farm

Page 11: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 6 turbines, Vestas V126• Construction time 1–9/2015• NCC’s scope‒ Access roads, platforms and assembly areas

• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Substation, electrical and data network design and construction

Taaleritehdas, Kytölä Wind Farm

Page 12: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 2 turbines Nordex N131 and 1 N117• Construction time 3–10/2015• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Electrical and data network design and construction‒ Main contractor liability during the Nordex works

Taaleritehdas, Myllykangas II Wind Farm

Page 13: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 13 turbines, Nordex N131• Construction time 12/2015–9/2016• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Substation, electrical and data network design and construction

Taaleritehdas, KiPe Wind Farm (Step 1)

Page 14: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 20 turbines, Nordex N131• Construction time 1/2016–8/2017• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Electrical and data network design and construction

Taaleritehdas, KiPe Wind Farm(Steps 2A and 2B)

Page 15: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 9 turbines, Nordex N131• Construction time 12/2015–9/2016• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Substation, electrical and data network design and construction

Taaleritehdas, Kantti Wind Farm

Page 16: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• 9 turbines, Nordex N131• Construction time 12/2015–9/2016• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Substation, electrical and data network design and construction

Taaleritehdas, Limakko Wind Farm

Page 17: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

NCC Infrastructure

• Joint project with NCC Infrastructure in Sweden• 179 turbines, GE Turbine• Construction time 2017–2019• NCC’s scope‒ Access roads, platforms and assembly areas

• Geotechnical investigations• Design and construction

‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.

‒ Electrical and data network design and construction

Markbygden Wind Farm Piteå, Sweden

Page 18: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design

Mikko NiinimaaGeneral Construction ManagerProject Manager, Wind Power ConstructionTel. +358 50 3100 454, [email protected]

NCC Infrastructure

Contact

Tuomas MäkiläBusiness Manager, Electrical Power Engineering Project Manager, Wind Power ConstructionTel. +358 43 8501 424, [email protected]