naval architect Project Report

Embed Size (px)

Citation preview

  • 7/30/2019 naval architect Project Report

    1/62

  • 7/30/2019 naval architect Project Report

    2/62

    2

    INDEX

    1. Introduction 41.1 Ship design 4

    1.1.1 Concept design 5

    1.1.2 Preliminary design 5

    2.Aim of the project 5

    3.Glossary of terms 6

    4.Owners requirement 7

    5.Parent ship data and analysis 96.Algorithm 10

    7.Estimation of main dimensions & coefficients 12

    7.1 Main dimensions 12

    7.2 Form coefficients 13

    7.2.1 Block coefficient 13

    7.2.2 Midship coefficient 14

    7.2.3 Prismatic coefficient 14

    7.2.4 Coefficient of water plane area 15

    7.3Calculations 16

    8. Sectional area curve 18

    9. Lines plan 19

    9.1 Body plan 19

    9.2 Half-breadth plan 20

    9.3 Profile plan 21

    10. Bonjean curves 22

    10.1 Bonjean calculation 22

    11. Hydrostatic curves 23

    11.1 Hydrostatic calculations 23

  • 7/30/2019 naval architect Project Report

    3/62

    3

    11.1.1 Longitudinal Center of Buoyancy 24

    11.1.2 Vertical Center of Buoyancy 29

    11.1.3 Longitudinal Center of Floatation 32

    11.1.4 Tonnes Per Centimeter immersion 3811.1.5 Moment to Change Trim by 1 cm 38

    11.1.6 Metacentric height in transeverse and

    longitudinal section 38

    12. General Arrangement 50

    12.1 Introduction 50

    12.2 Frame spacing & bulkhead disposition 50

    12.3 Sketches 5112.4Superstructure 52

    12.5 Accommodation 53

    12.6 Painting and Cathodic protection 54

    12.7 Pipe work colouring 56

    12.8 Life savings and fire fighting equipment 56

    12.9 Navigation lights 56

    13 Detailed Capacity Calculations and Drawings 58

    13.1Introduction 58

    13.2 loading Calculation 59

    14 Conclusion 62

  • 7/30/2019 naval architect Project Report

    4/62

    4

    1.Intoduction

    A tugboat (tug) is a boat that maneuvers vessels by pushing or towing them. Tugsmove vessels that either should not move themselves, such as ships in a crowded

    harbor or a narrow canal or those that cannot move by themselves, such as barges,

    disabled ships, log rafts, or oil platforms. Tugboats are powerful for their size and

    strongly built, and some are ocean-going. Some tugboats serve as

    icebreakers orsalvage boats. Early tugboats had steam engines, but today most

    have diesel engines. Many tugboats have firefighting monitors, allowing them to

    assist in firefighting, especially in harbors

    1.1 Ship Design

    Ship design is a complex process. The principle fact in this process is the

    creativity involved in designing a good functional unit, the ship which meets the

    various regulatory body requirements and the design practices and meet the owners

    requirement.

    Basic design involves the determination of major characteristics affecting

    cost & performance.

    (1)Main dimensions: L,B,T,D

    (2)Hull form: Lines design

    (3)Power: Resistance & propulsion

    (4)Preliminary General Arrangement

    (5)Major structure.

    The proper selection of the above should satisfy the following mission

    requirements

    (1)Good sea keeping performance.

    (2)Maneuverability

    (3)The desired speed.

    (4)Endurance

    (5)Cargo capacity

    (6)Dead weight.

    http://en.wikipedia.org/wiki/Icebreakerhttp://en.wikipedia.org/wiki/Salvage_tughttp://en.wikipedia.org/wiki/Steam_enginehttp://en.wikipedia.org/wiki/Diesel_enginehttp://en.wikipedia.org/wiki/Deluge_gunhttp://en.wikipedia.org/wiki/Deluge_gunhttp://en.wikipedia.org/wiki/Diesel_enginehttp://en.wikipedia.org/wiki/Steam_enginehttp://en.wikipedia.org/wiki/Salvage_tughttp://en.wikipedia.org/wiki/Icebreaker
  • 7/30/2019 naval architect Project Report

    5/62

    5

    The project involves the basic design of double skin PSV vessel with specifications

    and encompasses:

    (a)Concept design

    (b)Preliminary design

    1.1.1 Concept design

    This translates the mission requirements into Naval Architecture & Engg.

    characteristics. It includes the technological feasibility studies to determine the

    fundamental elements of the proposed vessel such as Length (L), Breadth (B),

    Draught (T), Coefficients (CB, Cw, CM, Cp), Power or alternative sets of

    characteristics which meet the required speed, dead weight. It includes preliminary

    light ship weight estimates. The selected concept design forms the basis of

    obtaining approximate cost.

    1.1.2Preliminary design

    It defines the major ship characteristics affecting cost & performance.

    Certain controlling factors like Length, Beam, Horsepower & DWT are not

    expected to change upon completion of this phase. Its completion provides a

    precise definition of the vessel that would meet the mission requirements.

    2.Aim of the project

    The main aim of this project is to design a Harbor, Ocean Towing Tug &also is to make a hydrostatic curve for a harbor tug with a bollard pull of 20tons.,

  • 7/30/2019 naval architect Project Report

    6/62

    6

    3.Glossary of terms

    LOA : Length Overall

    B : Breadth

    D : Depth

    T : Draft

    LWL : Load Water Line

    LBP : Length between Perpendicular

    DWT : Dead weight of ship

    LWT : Light Weight of ship

    CB : Block coefficient

    CM : Midship Coefficient

    CP : Prismatic Coefficient

    AM : Area of Midship

    AWL : Area of water line

    (CW) : Coefficient of fineness of the water- plane area

    (LCB) : Longitudinal centre of buoyancy

    (VCB) : Vertical centre of buoyancy

    (LCF) : Longitudinal centre of floatation

    (TPCi) : Tones per centimeter immersion

    (MCTi) : Moment to change trim by one centimeter

    (BMT &BML): Metacentric height in transverse & longitudinalsections

  • 7/30/2019 naval architect Project Report

    7/62

    7

    4.Owners requirement

    The main aim of this project is to design a: Harbor, Ocean Towing Tug with

    20 tons bollard pull . It has the following specifications.

    TYPE : Harbor, Ocean Towing Tug

    Service speed : 11knots

    Classification : R.I.NA. Registro Italiano Navale

    LOA : 21 metres

    LBP : 19metres

    Moulded Breadth : 8 metres

    Moulded Depth : 3.8metres

    Summer Load Draft : 2.8 metresGross Tonnage :

  • 7/30/2019 naval architect Project Report

    8/62

    8

    Accomodation

    Single cabin :0Double Cabin :4Crew messroom :1

    Total accommodation : 8

    Navigation & Communication

    Depth recorderGPS Navigator

    Radars x 2N 1 Radar X Band GEM SC 1210 NRadio systems Sailor system 4000 HT 4520

    Autopilot SteeringTelephone System Mobile

    VHF DSC SAILOR RT 4822 DSCAIS - Navtex FURUNO NX 500

  • 7/30/2019 naval architect Project Report

    9/62

    9

    5. Parent ship data and analysis

    The relevant data of 15-40 bollard pull were analysed & ratios are

    calculated. They are expressed in the tabular form below.

    NAME DIMENSIONS Assumed

    Velocity

    Bollard

    Pull

    (Metric

    Tonnes)

    LOA Depth Deep Draft Gross Registered

    Tonnage

    Ft In LBP Meter Ft Meter Ft Meter Ft Meter Tonnes InternalVolume

    Knots m/s

    1 SIGNETRANGER

    82 19.995 25.0 26 7.925 11 3.3528 9 2.7432 98 277.4 15 7.7166 36

    2 JIM COLLE 78 19.02 23.8 27 8.23 11 3.3528 8 2.5654 145 410.5 9 4.63 29.1

    3 SIGNET

    COURAGEOUS

    90 21.946 27.4 28 8.534 15 4.572 12 3.6576 152 430.3 12 6.1733 44

    4 SIGNET

    CHALLENGER

    104 25.359 31.7 36 10.97 16 4.8768 13 4.1148 379 1073 15 7.7166 46.5

    5 SIGNET

    VOLUNTEER

    70 17.069 21.3 26 7.925 11 3.3528 9 2.7432 146 413.3 13 6.6877 13.5

    6 NATALIECOLLE

    81 6 19.873 24.8 32 9.754 16 4.8768 13 3.9624 215 608.7 11.5 5.9161 42.5

    7 DANIEL

    COLLE

    81 6 19.873 24.8 32 9.754 16 4.8768 13 3.9624 215 608.7 11.5 5.9161 42.5

    L/B B/D L/D B/T

    2.523077 2.363636 5.963636 2.888889

    2.311111 2.454545 5.672727 3.207921

    2.571429 1.866667 4.8 2.333333

    2.311111 2.25 5.2 2.666667

    2.153846 2.363636 5.090909 2.888889

    2.0375 2 4.075 2.461538

    2.0375 2 4.075 2.461538

  • 7/30/2019 naval architect Project Report

    10/62

    10

    Analysis of ratios

    Range Average

    L/B 2.032.57 2.27

    B/T 2.33-3.2 2.70

    L/D 4.075-5.96 4.98

    B/D 1.8-2.45 2.18

    6.Alogorithm

    As mentioned in the aim we started research about the different types of

    ship. It may lead us to find out most of the ship details and we aware about the

    different types of bulk carrier.

    We started researching on different apparent ships from those ship details we

    find out a desirable detail for our ship. From those values we get the following

    details.

    Fig: Basic concept of ship

  • 7/30/2019 naval architect Project Report

    11/62

    11

    Length overall (LOA)

    Length of a ship measured horizontally from foremost part of stem to

    foremost part of bow.

    Length between perpendiculars (LBP)

    It is often abbreviated as LPP, LBP orLength BPP is a term describing the

    length of a ship. LBP refers to the length of a vessel along the waterline from the

    forward perpendicular to the aft perpendicular.

    Beam or Breadth (B)

    It is the maximum width along the midship.

    Depth (D)

    It is the maximum depth of a ship.

    Draft (T)

    It is the depth of a ship measured from keel to waterline.

    Loads water line (LWL)

    It is an imaginary line drawn along the surface of water measured from

    intersection of contour to forward perpendicular and the aft perpendicular.

    Dimension ratios

    Dimensions of the underwater body are sometimes referred to in ratio form.

    These are noted below, with approximate ranges for each:

    Ratio of length to breadth = L/B Approx. range 2 to 8.

    Ratio of length to draft = L/T Approx. range 6 to 30.Ratio of breadth to draft = B/T Approx. range 1.8 to 5.

  • 7/30/2019 naval architect Project Report

    12/62

    12

    Under water volume or displacement

    An object that sinks displaces an amount of fluid equal to the object's

    volume. Thus buoyancy is expressed through Archimedes' principle, which states

    that the weight of the object is reduced by its volume multiplied by the density of

    the fluid. If the weight of the object is less than this displaced quantity, the object

    floats; if more, it sinks. It is the same for a ship

    To find the underwater volume we have to analyze the formula

    Density = mass /volume

    Volume = mass/density

    Mass = considering the ships total weightDensity of sea water (approx. = 1.025 T/m3)

    7.Estimation of main dimensions & coefficients

    7.1 Main dimensions

    The main dimensions have a decisive effect on many of the ship characteristics. It

    affects

    Stability

    Hold capacity

    Hydro dynamic qualities such as resistance, maneuvering, sea keeping

    Economic efficiency

    Determining the main dimensions, proportions and form coefficient is one of

    the most important phases of overall design.

    Platform supply vessel are essentially moderate speed ship carrying dry

    cargo. Demand for the dry bulks in offshore field has increased tremendously.

    Hence the need for economic optimality in design, capacity etc is necessitated.

    Symbols list

  • 7/30/2019 naval architect Project Report

    13/62

    13

    DWT Dead weight

    Displacement

    LBP Length between perpendiculars

    V Velocity

    g Acceleration due to gravity

    B Moulded breadth of the ship

    D Moulded depth of the ship

    T Draft of the ship

    CB Block coefficient of the ship

    Fn Froude number

    7.2 Form coefficients

    7.2.1Block coefficient (CB)

    Block coefficient (CB) is the volume (V) divided by the LWL x B x T. If you

    draw a box around the submerged part of the ship, it is the ratio of the box volume

    occupied by the ship. It gives a sense of how much of the block defined by the

    LWL, beam (B) & draft (T) is filled by the hull. Full forms such as oil tankers willhave a high CB where fine shapes such as sailboats will have a low CB.

  • 7/30/2019 naval architect Project Report

    14/62

    14

    Fig: Block coefficient

    7.2.2Midship Coefficient (CM)

    Midship coefficient (CM orCX) is the cross-sectional area (Ax) of the slice

    at Midship (or at the largest section for CX) divided by beam x draft. It displays the

    ratio of the largest underwater section of the hull to a rectangle of the same overall

    width and depth as the underwater section of the hull. This defines the fullness of

    the underbody. A low CM indicates a cut-away mid-section and a high CM

    indicates a boxy section shape. Sailboats have a cut-away mid-section with low CX

    whereas cargo vessels have a boxy section with high CX to help increase the CB.

    7.2.3Prismatic Coefficient (CP)

    Prismatic coefficient (Cp) is the volume (V) divided by LBP x Ax. It displays

    the ratio of the immersed volume of the hull to a volume of a prism with equallength to the ship and cross-sectional area equal to the largest underwater section

    of the hull (midship section). This is used to evaluate the distribution of the volume

    of the underbody. A low or fine Cp indicates a full mid-section and fine ends, a

    high or full Cp indicates a boat with fuller ends. Planing hulls and other high-speed

    hulls tend towards a higher Cp. Efficient displacement hulls travelling at a low

    Froude number will tend to have a low Cp.

  • 7/30/2019 naval architect Project Report

    15/62

    15

    Fig: Prismatic coefficient

    7.2.4Coefficient of fineness of the water- plane area (CW)

    Water plane coefficient (CW) is the waterplane area divided by LPP x B. The

    waterplane coefficient expresses the fullness of the waterplane, or the ratio of the

    waterplane area to a rectangle of the same length and width. A low C W figure

    indicates fine ends and a high CW figure indicates fuller ends. High CW improves

    stability as well as handling behavior in rough conditions.

    Fig: Water plane coefficient

  • 7/30/2019 naval architect Project Report

    16/62

    16

    7.3 Calculations

    LOA = 21mtr

    LBP = 19mtr

    Breadth = 8 mtr

    Depth upto deck = 3.8 mtr

    Draft (Design) = 2.8mtr

    LWT = 145 T

    CB is in th range of 0.5 - 0.8 in case of harbor tug.

    After correction CB value = 0.60

    CB =

    Under water volume = CB x L x B x T

    = 0.60 x 19 x 8 x 2.8

    = 255.36 m3

    FN=

  • 7/30/2019 naval architect Project Report

    17/62

    17

    (1 KNOT = 0.5144 m/s)

    Assuming CW value = 0.84

    CW =

    Water Plane Area = 0.84 x 19 x 8

    = 127.68m2

    Assuming Cm=0.91

    Cm =

    Midship Area = 0.91 x 2.8 x 8

    = 20.3844m3

    CP=

    =

    Displacement = Dead weight + Light weight ship

    Displacement = Under Water Volume x Density

    =255.36 * 1.025 = 261.744T

    Dead weight = Displacement - Light weight of the ship

    = 261.744145

    = 116.744T

  • 7/30/2019 naval architect Project Report

    18/62

    18

    8.Sectional area curveA fundamental drawing in the design of a ship particularly relative to resistance

    is the sectional area curve, for a ship with some parallel middle body. The sectional

    area curve represents the longitudinal distribution of cross sectional area below the

    DWL.

    The ordinates of a sectional area curve are plotted in distance-squared units.

    Inasmuch as the horizontal scale, or abscissa, represents longitudinal distances

    along the ship, it is clear that the area under the curve represents the volume of

    water displaced by the vessel up to the DWL, or volume of displacement.

    Alternatively, the ordinate and abscissa of the curve may be made non-dimensional

    by dividing by the midship area and length of ship, respectively. In either case, the

    shape of the sectional area curve determines the relative "fullness" of the ship. The

    sectional area curve and the half breadth are drawn keeping the underwater volume

    and the form coefficients kept in mind.

    Fig: Sectional area curve

  • 7/30/2019 naval architect Project Report

    19/62

    19

    9.Lines planThe lines plan are drafted for each ship according to the unique feature of

    the ship involved. Makin the lines plan is the first stage of the design spiral and is

    one of the most important part of the entire design process since these line plansare provided to the operator and are constantly referred as part of the operation of

    the ship.

    The body plan is generate from the sectional area curve and the half breadth.

    The lines are fared to avoid any kinks in the lines and also to make sure that the

    lines are in perfect curves. The final underwater area and volume are calculate and

    corrected to the previously corrected values.

    9.1 Body Plan

    Fig: Body plan

    Planes parallel to the front and back of the imaginary box are called stations.There are three important stations. The intersection of the stem of the ship at the

    design water line is called Forward Perpendicular (FP). The intersection of the

    stern at design water line(immersed transom) or the rudder stock is called the Aft

    Perpendicular (AP). The station midway between the perpendiculars is called the

    midship stations.

  • 7/30/2019 naval architect Project Report

    20/62

    20

    Each station plane will intersect the ship's hull and form a curved line at the

    points of intersection. These lines are called sectional lines and are all projected

    onto a single plane called the Body Plan.

    The body plan takes advantage of the ship's symmetry. Hence only half thesection is show; the sections forward of amidships are drawn on the right side, and

    the sections aft of the amidships are drawn on the left side. The amidships section

    is generally shown on both sides of the body plan. The vertical line in the center

    separating the left and right half of the ship is called the centerline.

    9.2 Half-Breadth Plan

    Fig: Half Breadth plan

    The bottom of the box is a reference plane called the base plane. The base

    plane is usually level with the keel. A series of planes parallel and above the base

    plan are imagined at regular intervals, usually at every meter. Each plane will

    intersect the ship's hull and form a line at the points of intersection. These lines are

    called waterlines and are all projected onto a single plane called the Half-Breadth

    Plan.

  • 7/30/2019 naval architect Project Report

    21/62

    21

    Each waterline shows the true shape of the hull from the top view for some

    elevation above the base plane. The water lines referred to here has nothing to do

    with where the ship actually floats. There waterlines are the intersection of the

    ship's hull with some imaginary plane above the base plane. Since ships are

    symmetric about their centerline they only need be drawn for the starboard or port

    side, thus the name Half-Breadth Plan.

    9.3Profile Plan

    Fig: Profile plan

    A plane that runs from bow to stern directly through the center of the ship

    and parallel to the sides of the imaginary box is called the centerline plane. A

    series of planes parallel to one side of the centerline plane are imagined at regular

    intervals from the centerline. Each plane will intersect the ship's hull and form acurved line at the points of intersection. These lines are called buttock or butt lines

    and are projected onto a single plane called the Sheer Plan.

  • 7/30/2019 naval architect Project Report

    22/62

    22

    Each buttock line shows the true shape of the hull from the side view for

    some distance from the centerline of the ship. The centerline plane shows a special

    butt line called the profile of the ship.

    10.Bonjean Curves

    The curves of cross sectional area for all body plan stations are collectively

    called Bonjean Curves. One of the principal uses of Bonjean Curves is determining

    volume of displacement of the ship at any level or trimmed waterline.

    10.1 Bonjean calculations

    Fig: Bonjean curve

    In the Bonjean calculation the sectional area and moment of each station up

    to each waterline is calculated. This enables the calculation of Displacement, LCB

    and VCB for any waterline for even keel and also trimmed condition.

    The uses of Bonjeans are:

    1) Hydrostatic calculations.

    2) For flooding calculations.

    3) Launching calculations.

    4) Longitudinal strength calculations.

  • 7/30/2019 naval architect Project Report

    23/62

    23

    11.Hydrostatic Curves

    It is customary in the design of a ship to calculate and plot as curves a

    number of hydrostatic properties of the vessel's form at a series of drafts. Such

    curves are useful in loading and stability studies during the design phase. Largescale plots of these curves for a newly built ship are then made for the assistance of

    the vessel's operating personnel. Such curves are known as the vessel's curves

    of form, or synonymously, hydrostatic curves.

    11.1 Hydrostatic calculations

    It is mandatory in the design of a ship to calculate and plot as curves a

    number of hydrostatic properties of the vessels form at a series of drafts. Th rough

    out its life a ship changes its weight, trim & freeboard. Its condition at any state of

    circumstances can be found from hydrostatic curves. Hydrostatic particulars

    corresponding to different waterlines are calculated.

    List of formulae used.

    1)Awp = 2/3 x h x f(A)

    2) Mx = 2 x h2/3 x f(M)

    3) LCF, x = h x f(M)

    f(A)

    4) IL = (2h3/3) x f(IL)

    5) IT = (2 x h/9) x f(IT)

    6) TPC = (Awp x 1.025)

    100

    7) BMT = IT/

    8) BML = IL/

    9) MCT = x GML

  • 7/30/2019 naval architect Project Report

    24/62

    24

    100 x LWL

    10) KM = BM + KB

    11) CB =

    LBP x B x T

    12) CM = A/(B x T)

    13) CW = AWP / (L x B)

    14) CP = CB/CM

    11.1.1 Longitudinal Centre of Buoyancy (LCB)

    Longitudinal centre of buoyancy (LCB) is the longitudinal distance from a

    point of reference (often midships) to the centre of the displaced volume of water

    when the hull is not moving. Note that the longitudinal centre of gravity or centre

    of the weight of the vessel must align with the LCB when the hull is in

    equilibrium.

  • 7/30/2019 naval architect Project Report

    25/62

    25

    Calculation table

    WATERLINE 0.5 WATERLINE 1

    STATION HALF AREA AREA SM f(V) LEVER f(M) STATION HALF AREA AREA SM f(V) LEVER f(M)

    00 0

    10

    00

    00 0

    10

    00

    10 0

    40

    10

    10 0

    40

    10

    20 0

    20

    20

    20 0

    20

    20

    30 0

    40

    30

    30 0

    40

    30

    40 0

    20

    40

    40 0

    20

    40

    5

    0 0

    4

    0

    5

    0

    5

    0.829 1.66

    4

    3.3

    5

    16.57

    61 1.92

    22

    611.5

    62.575 5.15

    25.2

    630.9

    71 2.76

    46

    738.6

    73.144 6.29

    413

    788.02

    81 2.76

    23

    822.1

    83.144 6.29

    26.3

    850.3

    91 2.76

    46

    949.7

    93.144 6.29

    413

    9113.2

    101 2.76

    23

    1027.6

    103.144 6.29

    26.3

    1062.87

    11

    1 2.76

    4

    6

    11

    60.7

    11

    3.144 6.29

    4

    13

    11

    138.3

    121 2.76

    23

    1233.1

    123.144 6.29

    26.3

    1275.45

    131 1.87

    44

    1348.6

    132.435 4.87

    49.7

    13126.6

    140 0.96

    21

    1413.4

    141.649 3.3

    23.3

    1446.18

    150 0.68

    41

    1520.4

    151.253 2.51

    45

    1575.18

    160 0.44

    20

    167.02

    160.888 1.78

    21.8

    1628.42

    170 0.18

    40

    176.05

    170.638 1.28

    42.6

    1743.4

    180 0

    10

    180

    180.013 0.03

    10

    180.234

    34 339 87 895.7

    LCB 10.08 LCB 10.2

    VOLUME 11.09 VOLUME 28.9

  • 7/30/2019 naval architect Project Report

    26/62

    26

    WATERLINE 1.5 WATERLINE 2

    STATI

    ON

    HALF

    AREA AREA SM

    f(V

    )

    LEVE

    R

    f(M

    )

    STATI

    ON

    HALF

    ARE

    A AREA SM

    f(V

    )

    LEVE

    R f(M)

    0 0 0 1 0 0 0 0 0 0 1 0 0 0

    1 0 0 4 0 1 0 1 0 0 4 0 1 0

    20 0

    20

    20

    20.38 0.759

    20.7

    62

    1.51

    88

    30 0

    40

    30

    30.99

    2 1.9844

    3.9

    73

    11.9

    04

    40 0.94

    20.

    94

    3.7

    74

    1.94 3.882

    3.8

    84

    15.5

    2

    52 4.77

    49.

    55

    47.

    75

    4.14 8.284

    16.

    65

    82.8

    6 4 8.76 2 8.8 6 52.5 6 6.27 12.54 2 12.5 6 75.24

    75 10.1

    420

    7141

    77.01 14.02

    428

    7196.

    28

    85 10.1

    210

    880.

    68

    7.01 14.022

    148

    112.

    16

    95 10.1

    420

    9181

    97.01 14.02

    428

    9252.

    36

    105 10.1

    210

    10101

    107.01 14.02

    214

    10140.

    2

    115 10.1

    420

    11222

    117.01 14.02

    428

    11308.

    44

    12 5 10.1 2 10 12 121 12 7.01 14.02 2 14 12

    168.

    24

    134 8.22

    416

    13214

    135.89 11.78

    423.

    613

    306.

    28

    143 6.26

    26.

    314

    87.

    614

    4.77 9.542

    9.5

    414

    133.

    56

    153 5.06

    410

    15152

    154.03 8.06

    416.

    115

    241.

    8

    162 3.88

    23.

    916

    62.

    116

    3.26 6.522

    6.5

    216

    104.

    32

    172 3.06

    46.

    117

    10417

    2.65 5.34

    10.

    617

    180.

    2

    180 0.78

    10.

    418

    7.0

    618

    1.01 2.021

    1.0

    118

    18.1

    815

    3

    157

    7

    23

    1 2349

    LCB 10.3 LCB

    10.

    2

    VOLU

    ME

    50.5

    5

    VOLU

    ME

    76.

    3

  • 7/30/2019 naval architect Project Report

    27/62

    27

    WATERLINE 2.5 WATERLINE 2.8

    STATI

    ON

    HALF

    AREA AREA SM

    f(V

    )

    LEV

    ER

    f(M

    )

    STATI

    ON

    HALF

    AREA AREA SM

    f(V

    )

    LEV

    ER f(M)

    00.704 1.4082

    10.

    70

    00

    1.449 2.8981

    1.

    40

    0

    11.142 2.2836

    44.

    61

    4.5

    71

    2 44

    81

    8

    21.75 3.5

    23.

    52

    72

    2.7 5.42

    5.

    42

    10.8

    32.538 5.076

    410

    330.

    53

    3.56 7.124

    143

    42.7

    2

    43.667 7.334

    27.

    34

    29.

    34

    4.771 9.5422

    9.

    54

    38.1

    7

    56.01 12.02

    424

    5120

    57.16 14.32

    429

    5143.

    2

    6

    8.22 16.44

    2

    16

    698.

    6

    6

    9.42 18.84

    2

    19

    6

    1137

    9 184

    367

    2527

    10.2 20.44

    417

    285.

    6

    89 18

    218

    8144

    810.2 20.4

    220

    8163.

    2

    99 18

    436

    9324

    910.2 20.4

    441

    9367.

    2

    10 9 18 2 18 10 180 10 10.2 20.4 2 20 10 204

    119 18

    436

    11396

    1110.2 20.4

    441

    11448.

    8

    129 18

    218

    12216

    1210.2 20.4

    220

    12244.

    8

    13 7.75 15.5 4 31 13 403 13 8.89 17.78 4 36 13 462.3

    146.533 13.066

    213

    14183

    147.64 15.28

    215

    14213.

    9

    155.68 11.36

    423

    15341

    156.74 13.48

    427

    15404.

    4

    164.75 9.5

    29.

    516

    15216

    5.7 11.42

    1116

    182.

    4

    173.885 7.7706

    416

    17264

    174.65 9.3

    419

    17316.

    2

    181.728 3.456

    11.

    718

    31.

    118

    2.17 4.341

    2.

    218

    39.0

    6

    32

    2

    317

    6

    38

    0

    368

    8

    LCB

    9.85

    5 LCB

    9.7

    1

    VOLU

    ME

    106.

    4

    VOLU

    ME

    12

    5

  • 7/30/2019 naval architect Project Report

    28/62

    28

    WATERLINE 3 WATERLINE 3.5

    STATI

    ON

    HALF

    AREA AREA SM

    f(V

    )

    LEV

    ER

    f(M

    )

    STATI

    ON

    HALF

    AREA AREA SM

    f(V

    )

    LEV

    ER f(M)

    01.984 3.968

    12

    00

    03.39 6.78

    13.

    40

    0

    12.6 5.2

    410

    1 10.4

    14.23 8.46

    417

    1 16.92

    23.36 6.72

    26.

    72

    13.

    42

    5.12 10.242

    102

    20.4

    8

    34.27 8.54

    417

    351.

    23

    6.1 12.24

    243

    73.2

    45.52 11.04

    211

    444.

    24

    7.46 14.922

    154

    59.6

    8

    5 7.94 15.88 4 32 5 159 5 9.9 19.8 4 40 5 198

    610.22 20.44

    220

    6123

    612.22 24.44

    224

    6146.

    6

    7 11 22 4 44 7 308 7 13 26 4 52 7 364

    8 11 22 2 22 8 176 8 13 26 2 26 8 208

    9 11 22 4 44 9 396 9 13 26 4 52 9 468

    10 11 22 2 22 10 220 10 13 26 2 26 10 260

    11 11 22 4 44 11 484 11 13 26 4 52 11 572

    12 11 22 2 22 12 264 12 13 26 2 26 12 312

    139.66 19.32

    439

    13502

    1311.64 23.28

    447

    13605.

    3

    148.39 16.78

    217

    14235

    1410.34 20.68

    221

    14289.

    5

    157.47 14.94

    430

    15448

    159.36 18.72

    437

    15561.

    6

    166.37 12.74

    213

    16204

    168.09 16.18

    216

    16 258.9

    175.18 10.36

    421

    17352

    176.51 13.02

    426

    17442.

    7

    182.47 4.94

    12.

    518

    44.

    518

    3.23 6.461

    3.

    218

    58.1

    4

    41

    9

    403

    5

    51

    8

    491

    5

    LCB

    9.63

    7 LCB

    9.4

    9

    VOLU

    ME

    138.

    2

    VOLU

    ME

    17

    1

  • 7/30/2019 naval architect Project Report

    29/62

    29

    WATERLINE 3.8

    STATION

    HALF

    AREA AREA SM f(V) LEVER f(M)

    0 4.26 8.52 1 4.3 0 0

    1 5.27 10.54 4 21 1 21.1

    2 6.22 12.44 2 12 2 24.9

    3 7.23 14.46 4 29 3 86.8

    4 8.63 17.26 2 17 4 69

    5 11.09 22.18 4 44 5 222

    6 13.42 26.84 2 27 6 161

    7 14.2 28.4 4 57 7 398

    8 14.2 28.4 2 28 8 227

    9 14.2 28.4 4 57 9 511

    10 14.2 28.4 2 28 10 284

    11 14.2 28.4 4 57 11 62512 14.2 28.4 2 28 12 341

    13 12.83 25.66 4 51 13 667

    14 11.53 23.06 2 23 14 323

    15 10.53 21.06 4 42 15 632

    16 9.17 18.34 2 18 16 293

    17 7.31 14.62 4 29 17 497

    18 3.69 7.38 1 3.7 18 66.4

    579 5449

    LCB 9.419

    VOLUME 190.9

    11.1.2.Vertical centre of buoyancy (VCB)

    Is the geometric centre of the ships under water area at a particular draughtfrom the vertical section from keel and its position will change with draught. The

    position of the VCB determines where is the buoyancy of that particular draft

    remains in the hull.

  • 7/30/2019 naval architect Project Report

    30/62

    30

    Calculation table

    WATERLINE 1 WATERLINE .5WATER

    LINE

    AR

    EA SM

    f(v

    )

    LEV

    ER

    F(

    M)

    WATER

    LINE

    AR

    EA

    S

    M f(v)

    LEV

    ER

    F(M

    )

    WL.5

    58.

    8 5

    29

    4 0.5 147 wl0 0 5 0 0 0

    WL1

    79.

    86 8

    63

    9 1

    638

    .9 WL.5

    58.

    8 8

    470

    .4 0.5

    235.

    2

    WL1.5

    91.

    15 -1

    -

    91

    .2 1.5

    -

    137 WL1

    79.

    86 -1

    -

    79.

    9 1

    -

    79.8

    684

    2

    649

    .2

    390

    .5

    155.

    34

    VC

    B

    0.7

    71

    VC

    B

    0.3

    98

    WATERLINE 2 WATERLINE 1.5

    WATER

    LINE

    AR

    EA

    S

    M

    f(v

    )

    LEV

    ER

    F(

    M)

    WATER

    LINE

    AR

    EA

    S

    M f(v)

    LEV

    ER F(M)

    WL.5

    58.

    8 1

    58

    .8 0.5

    29.

    4 WL.5

    58.

    8 1

    58.

    8 0.5 29.4

    WL1

    79.

    86 3

    24

    0 1

    239

    .6 WL1

    79.

    86 4

    319

    .4 1

    319.

    44

    WL1.5

    91.

    15 3

    27

    3 1.5

    410

    .2 WL1.5

    91.

    15 1

    91.

    15 1.5

    136.

    725

    WL2107

    .2 110

    7 2214

    .4469

    .4485.565

    67

    9

    893

    .5

    VC

    B

    1.

    32

    VC

    B

    1.0

    34

  • 7/30/2019 naval architect Project Report

    31/62

    31

    WATERLINE 2.8 WATERLINE 2.5

    WATERLI

    NE

    ARE

    A

    S

    M f(v)

    LEV

    ER

    F(M

    )

    WATERLI

    NE

    ARE

    A

    S

    M f(v)

    LEV

    ER F(M)

    WL.5

    58.

    8 1

    58.

    8 0.5

    29.

    4 WL.5 58.8 1

    58.

    8 0.5 29.4

    WL1

    79.

    86 4 319 1

    319

    .4 WL1

    79.8

    6 4

    319

    .4 1

    319.4

    4

    WL1.5

    91.

    15 2 182 1.5

    273

    .5 WL1.5

    91.1

    5 2

    182

    .3 1.5

    273.4

    5

    WL2

    107

    .2 3 322 2

    643

    .1 WL2

    107.

    19 4

    428

    .8 2

    857.5

    2

    WL2.5

    122

    .2 3 367 2.5

    916

    .3 WL2.5

    122.

    17 1

    122

    .2 2.5

    305.4

    25

    WL2.8

    125

    .9 1 126 2.8

    352

    .6

    111

    1

    1785.

    24

    1375

    2534

    VC

    B

    1.8

    4

    VC

    B

    1.6

    06

    WATERLINE 3.5 WATERLINE 3

    WATERLI

    NE

    ARE

    A SM f(v)

    LEVE

    R

    F(M

    )

    WATERLI

    NE AREA SM f(v)

    LEVE

    R F(M)

    WL.5 58.8 1

    58.

    8 0.5 29.4 WL.5 58.8 1 58.8 0.5 29.4

    WL1

    79.8

    6 4 319 1

    319.

    4 WL1 79.86 4

    319.

    4 1

    319.4

    4

    WL1.5

    91.1

    5 2 182 1.5

    273.

    5 WL1.5 91.15 2

    182.

    3 1.5

    273.4

    5

    WL2

    107.

    2 4 429 2

    857.

    5 WL2

    107.1

    9 4

    428.

    8 2

    857.5

    2

    WL2.5

    122.

    2 2 244 2.5

    610.

    9 WL2.5

    122.1

    7 2

    244.

    3 2.5

    610.8

    5

    WL2.8

    125.

    9 3 378 2.8

    105

    8 WL2.8

    125.9

    4 4

    503.

    8 2.8

    1410.

    53

    WL3.

    128.

    1 3 384 3

    115

    3 WL3.

    128.1

    1 1

    128.

    1 3

    384.3

    3

    WL3.5

    132.

    4 1 132 3.5

    463.

    5

    186

    6

    3885.

    52

    212

    8

    476

    5

    VC

    B

    2.2

    4

    VC

    B

    2.08

    3

  • 7/30/2019 naval architect Project Report

    32/62

    32

    WATERLINE 3.8

    WATERLINE AREA SM f(v) LEVER F(M)

    WL.5 58.8 1 58.8 0.5 29.4WL1 79.86 4 319 1 319.4

    WL1.5 91.15 2 182 1.5 273.5

    WL2 107.2 4 429 2 857.5

    WL2.5 122.2 2 244 2.5 610.9

    WL2.8 125.9 4 504 2.8 1411

    WL3. 128.1 2 256 3 768.7

    WL3.5 132.4 4 530 3.5 1854

    WL3.8 133.6 1 134 3.8 507.6

    2657 6631

    VCB 2.5

    11.1.3Longitudinal centre of floatation (LCF)

    Longitudinal centre of flotation (LCF) is the geometric centre of the ships

    water-plane area at a particular draught and its position will change with draught.

    The position of the LCF determines how the change of trim will be apportioned

    between the forward and aft draughts.

  • 7/30/2019 naval architect Project Report

    33/62

    33

    Calculation table

    WATERPLANE 0.5 WATERPLANE 1

    STAT

    ION

    halfBREA

    DTH

    fullbrea

    dth

    SMf(A

    )

    LEV

    ER

    f(

    M)

    STAT

    ION

    halfBREA

    DTH

    fullbrea

    dth

    SMf(A

    )

    LEV

    ER

    f(

    M)

    0 0 0 1 0 0 0 0 0 0 1 0 0 0

    1 0 0 4 0 1 0 1 0 0 4 0 1 0

    2 0 0 2 0 2 0 2 0 0 2 0 2 0

    3 0 0 4 0 3 0 3 0 0 4 0 3 0

    4 0 0 2 0 4 0 4 0 0 2 0 4 0

    50 0

    40

    50

    52.8 5.6

    422.

    45

    112

    62.91 5.82

    211.64

    669.

    86

    3.46 6.922

    13.84

    683

    7 3.3 6.6 4 26.4 7 185 7 3.65 7.3 4 29.2 7 204

    83.3 6.6

    213.

    28

    106

    83.65 7.3

    214.

    68

    117

    93.3 6.6

    426.

    49

    238

    93.65 7.3

    429.

    29

    263

    103.3 6.6

    213.

    210

    132

    103.65 7.3

    214.

    610

    146

    113.3 6.6

    426.

    411

    290

    113.65 7.3

    429.

    211

    321

    123.3 6.6

    213.

    212

    158

    123.65 7.3

    214.

    612

    175

    132.69 5.38

    4 21.52

    13 280

    133.22 6.44

    4 25.76

    13 335

    141.8 3.6

    27.2

    14101

    142.73 5.46

    210.92

    14153

    151.3 2.6

    410.

    415

    156

    152.27 4.54

    418.16

    15272

    160.9 1.8

    23.6

    1657.

    616

    1.75 3.52

    716

    112

    170.63 1.26

    45.0

    417

    85.7

    171.5 3

    412

    17204

    180 0

    10

    180

    180.27 0.54

    10.5

    418

    9.72

    178.2

    1858

    242

    2507

    LCF10.43 LCF

    10.36

    AREA

    58.81

    AREA

    79.9

  • 7/30/2019 naval architect Project Report

    34/62

    34

    WATERPLANE 1.5 WATERPLANE 2

    STATI

    ON

    half

    BREADT

    H

    full

    bread

    th

    SMf(A

    )

    LEV

    ER

    f(M

    )

    STATI

    ON

    half

    BREADT

    H

    full

    bread

    th

    SMf(A

    )

    LEV

    ERf(M)

    0 0 0 1 0 0 0 0 0 0 1 0 0 0

    1 0 0 4 0 1 0 1 0 0 4 0 1 0

    20 0

    20

    20

    22.37 4.74

    29.4

    82

    18.9

    6

    30 0

    40

    30

    32.79 5.58

    422.

    33

    66.9

    6

    42.49 4.98

    29.9

    64

    39.

    844

    3.25 6.52

    134

    52

    53.35 6.7

    426.

    85

    1345

    3.64 7.284

    29.

    15

    145.

    6

    63.71 7.42

    214.

    86

    89.

    046

    3.75 7.52

    156

    90

    7

    3.71 7.42

    429.

    7

    7207

    .8

    7

    3.75 7.5

    4

    30

    7

    210

    83.71 7.42

    214.

    88

    118

    .78

    3.75 7.52

    158

    120

    93.71 7.42

    429.

    79

    267

    .19

    3.75 7.54

    309

    270

    103.71 7.42

    214.

    810

    148

    .410

    3.75 7.52

    1510

    150

    113.71 7.42

    429.

    711

    326

    .511

    3.75 7.54

    3011

    330

    123.71 7.42

    214.

    812

    178

    .112

    3.75 7.52

    1512

    180

    133.47 6.94

    427.

    813

    360

    .913

    3.64 7.284

    29.

    113

    378.

    56

    143.14 6.28

    212.

    614

    175

    .814

    3.41 6.822

    13.

    614

    190.

    96

    152.81 5.62

    422.

    515

    337

    .215

    3.15 6.34

    25.

    215

    378

    162.42 4.84

    29.6

    816

    154

    .916

    2.82 5.642

    11.

    316

    180.

    48

    172.05 4.1

    416.

    417

    278

    .817

    2.37 4.744

    1917

    322.

    32

    181.09 2.18

    12.1

    818

    39.

    2418

    1.36 2.721

    2.7

    218

    48.9

    6

    27

    6

    285

    6

    32

    5

    3132

    .8

    LCF

    10.

    3 LCF

    9.6

    44

    ARE

    A

    91.

    2 AREA

    107

    .2

  • 7/30/2019 naval architect Project Report

    35/62

    35

    WATERPLANE 2.5 WATERPLANE 2.8

    STATI

    ON

    half

    BREA

    DTH

    full

    bread

    th

    S

    M

    f(

    A)

    LEV

    ER

    f(M

    )

    STATI

    ON

    half

    BREA

    DTH

    full

    bread

    th

    SMf(

    A)

    LEV

    ERf(M)

    02.33 4.66

    14.

    660

    00

    2.33 4.661

    4.

    660

    0

    12.72 5.44

    421

    .81

    21.

    761

    2.98 5.964

    23

    .81

    23.8

    4

    23.03 6.06

    212

    .12

    24.

    242

    3.26 6.522

    132

    26.0

    8

    33.32 6.64

    426

    .63

    79.

    683

    3.5 74

    283

    84

    43.6 7.2

    214

    .44

    57.

    64

    3.74 7.482

    154

    59.8

    4

    53.81 7.62

    430

    .55

    152

    .45

    3.87 7.744

    315

    154.

    8

    63.81 7.62

    2 15.2

    6 91.44

    63.87 7.74

    2 15.5

    6 92.88

    73.81 7.62

    430

    .57

    213

    .47

    3.87 7.744

    317

    216.

    72

    83.81 7.62

    215

    .28

    121

    .98

    3.87 7.742

    15

    .58

    123.

    84

    93.81 7.62

    430

    .59

    274

    .39

    3.87 7.744

    319

    278.

    64

    103.81 7.62

    215

    .210

    152

    .410

    3.87 7.742

    15

    .510

    154.

    8

    113.81 7.62

    430

    .511

    335

    .311

    3.87 7.744

    3111

    340.

    56

    12

    3.81 7.62

    215

    .2

    12182

    .9

    12

    3.87 7.74

    215

    .5

    12185.

    7613

    3.77 7.544

    30

    .213

    392

    .113

    3.85 7.74

    30

    .813

    400.

    4

    143.63 7.26

    214

    .514

    203

    .314

    3.75 7.52

    1514

    210

    153.44 6.88

    427

    .515

    412

    .815

    3.6 7.24

    28

    .815

    432

    163.1 6.2

    212

    .416

    198

    .416

    3.25 6.52

    1316

    208

    172.54 5.08

    420

    .317

    345

    .417

    2.6 5.24

    20

    .817

    353.

    6

    181.46 2.92

    12.

    9218

    52.

    5618

    1.5 31

    318

    54

    370

    3312

    382

    3399.8

    LCF

    8.

    95 LCF

    8.9

    08

    ARE

    A

    12

    2

    ARE

    A

    125

    .9

  • 7/30/2019 naval architect Project Report

    36/62

    36

    WATERPLANE 3 WATERPLANE 3.5

    STATI

    ON

    half

    BREADTH

    full

    breadt

    h

    SMf(A

    )

    LEVE

    Rf(M)

    STATI

    ON

    half

    BREADTH

    full

    breadt

    h

    SMf(A

    )

    LEVE

    Rf(M)

    02.72 5.44

    15.4

    40

    00

    2.88 5.761

    5.7

    60

    0

    13.1 6.2

    4 24.8

    124.8

    13.38 6.76

    427

    1 27.04

    23.39 6.78

    213.

    62

    27.1

    22

    3.62 7.242

    14.

    52

    28.9

    6

    33.58 7.16

    428.

    63

    85.9

    23

    3.72 7.444

    29.

    83

    89.2

    8

    43.81 7.62

    215.

    24

    60.9

    64

    3.89 7.782

    15.

    64

    62.2

    4

    53.9 7.8

    431.

    25

    1565

    3.94 7.884

    31.

    55

    157.

    6

    63.9 7.8

    215.

    66

    93.66

    4 82

    166

    96

    73.9 7.8

    431.

    27

    218.

    47

    4 84

    327

    224

    83.9 7.8

    215.

    68

    124.

    88

    4 82

    168

    128

    93.9 7.8

    431.

    29

    280.

    89

    4 84

    329

    288

    103.9 7.8

    215.

    610

    15610

    4 82

    1610

    160

    113.9 7.8

    431.

    211

    343.

    211

    4 84

    3211

    352

    123.9 7.8

    215.

    612

    187.

    212

    4 82

    1612

    192

    133.89 7.78

    431.

    113

    404.

    613

    3.97 7.944

    31.

    813

    412.

    88

    143.82 7.64

    215.

    314

    213.

    914

    3.94 7.882

    15.

    814

    220.

    64

    153.69 7.38

    429.

    515

    442.

    815

    3.87 7.744

    3115

    464.

    4

    163.34 6.68

    213.

    416

    213.

    816

    3.55 7.12

    14.

    216

    227.

    2

    172.63 5.26

    421

    17357.

    717

    2.68 5.364

    21.

    417

    364.

    48

    181.51 3.02

    13.0

    218

    54.3

    618

    1.53 3.061

    3.0

    618

    55.0

    8

    38

    8

    344

    6

    40

    1

    3549

    .8

    LCF

    8.8

    8 LCF

    8.84

    6

    AREA

    12

    8 AREA 132.4

  • 7/30/2019 naval architect Project Report

    37/62

    37

    WATERPLANE 3.8

    STATIONhalf

    BREADTH

    full

    breadthSM f(A) LEVER f(M)

    0 2.91 5.82 1 5.82 0 0

    1 3.52 7.04 4 28.16 1 28.162 3.72 7.44 2 14.88 2 29.76

    3 3.8 7.6 4 30.4 3 91.2

    4 3.91 7.82 2 15.64 4 62.56

    5 3.96 7.92 4 31.68 5 158.4

    6 4 8 2 16 6 96

    7 4 8 4 32 7 224

    8 4 8 2 16 8 128

    9 4 8 4 32 9 288

    10 4 8 2 16 10 160

    11 4 8 4 32 11 352

    12 4 8 2 16 12 192

    13 3.98 7.96 4 31.84 13 413.9

    14 3.96 7.92 2 15.84 14 221.8

    15 3.93 7.86 4 31.44 15 471.6

    16 3.64 7.28 2 14.56 16 233

    17 2.68 5.36 4 21.44 17 364.5

    18 1.54 3.08 1 3.08 18 55.44404.78 3570

    LCF 8.8202

    AREA 133.58

  • 7/30/2019 naval architect Project Report

    38/62

    38

    11.1.4.Tones per centimeter immersion (TPCi)

    It is the amount of load in tones required to change of draft in 1 cm. Sincecompared to ships size 1cm is approximately equal to the water plane at particular

    draft.TPCi = ( area of waterplane x 1cm) x density of sea water.

    11.1.5.Moment to change trim by one centimeter (MCTi)

    The MCT 1 cm is the moment required to change the trim of the vessel by 1

    cm and may be calculated by using the formula:

    MCT 1 cm = W x GML/100L

    Where, W = The vessels displacement in tonnes

    GML = The longitudinal metacentric height in metersL = Vessels length (LBP) in meters.

    11.1.6.Metacentric height in transverse & longitudinal sections (BMT &BML)

    The metacentric height (GM) is a measurement of the initial static stability

    of a floating body. It is calculated as the distance between the centre of gravity of a

    ship and its metacentre. A larger metacentric height implies greater initial stability

    against overturning.

  • 7/30/2019 naval architect Project Report

    39/62

    39

    The metacentre is considered to be fixed for small angles of heel; however,

    at larger angles of heel the metacentre can no longer be considered fixed and other

    means must be found to calculate the ship's stability. The metacentre can be

    calculated using the formulae:

    KM = KB + BM

    BM = I/V

    KB orVCB- The centre of buoyancy (height above the keel)

    I - The Second moment of area of the waterplane in m4

    V - The volume of displacement in m3.

    KM - The distance from the keel to the metacentre.

    23

    All of these calculation helps to draw the hydrostatic curves

  • 7/30/2019 naval architect Project Report

    40/62

    40

    Fig: Hydrostatic curve

  • 7/30/2019 naval architect Project Report

    41/62

    41

    Hydrostatic parameters for different water level is shown in tabular form.

    WATERPLANE 0.5

    STATIONhalf

    BREADTH

    full

    breadthSM f(A) LEVER f(M)

    0 0 0 1 0 0 0

    1 0 0 4 0 1 0

    2 0 0 2 0 2 0

    3 0 0 4 0 3 0

    4 0 0 2 0 4 05 0 0 4 0 5 0

    6 2.91 5.82 2 11.64 6 69.84

    7 3.3 6.6 4 26.4 7 184.8

    8 3.3 6.6 2 13.2 8 105.6

    9 3.3 6.6 4 26.4 9 237.6

    10 3.3 6.6 2 13.2 10 132

    11 3.3 6.6 4 26.4 11 290.4

    12 3.3 6.6 2 13.2 12 158.4

    13 2.69 5.38 4 21.52 13 279.76

    14 1.8 3.6 2 7.2 14 100.8

    15 1.3 2.6 4 10.4 15 156

    16 0.9 1.8 2 3.6 16 57.6

    17 0.63 1.26 4 5.04 17 85.68

    18 0 0 1 0 18 0

    178.2 1858.5LCF 10.429

    AREA 58.806

  • 7/30/2019 naval architect Project Report

    42/62

    42

    WATERPLANE 1

    STATIONhalf

    BREADTH

    full

    breadthSM f(A) LEVER f(M)

    0 0 0 1 0 0 0

    1 0 0 4 0 1 0

    2 0 0 2 0 2 0

    3 0 0 4 0 3 0

    4 0 0 2 0 4 0

    5 2.8 5.6 4 22.4 5 112

    6 3.46 6.92 2 13.84 6 83.04

    7 3.65 7.3 4 29.2 7 204.4

    8 3.65 7.3 2 14.6 8 116.8

    9 3.65 7.3 4 29.2 9 262.8

    10 3.65 7.3 2 14.6 10 146

    11 3.65 7.3 4 29.2 11 321.2

    12 3.65 7.3 2 14.6 12 175.2

    13 3.22 6.44 4 25.76 13 334.88

    14 2.73 5.46 2 10.92 14 152.88

    15 2.27 4.54 4 18.16 15 272.4

    16 1.75 3.5 2 7 16 112

    17 1.5 3 4 12 17 204

    180.27 0.54

    10.54

    189.72

    242 2507.3

    LCF 10.36

    AREA 79.87

  • 7/30/2019 naval architect Project Report

    43/62

    43

    WATERPLANE 1.5

    STATIONhalf

    BREADTH

    full

    breadthSM f(A) LEVER f(M)

    0 0 0 1 0 0 0

    1 0 0 4 0 1 0

    2 0 0 2 0 2 0

    3 0 0 4 0 3 0

    4 2.49 4.98 2 9.96 4 39.84

    5 3.35 6.7 4 26.8 5 134

    6 3.71 7.42 2 14.84 6 89.04

    7 3.71 7.42 4 29.68 7 207.76

    8 3.71 7.42 2 14.84 8 118.72

    9 3.71 7.42 4 29.68 9 267.12

    10 3.71 7.42 2 14.84 10 148.4

    11 3.71 7.42 4 29.68 11 326.48

    12 3.71 7.42 2 14.84 12 178.0813 3.47 6.94 4 27.76 13 360.88

    14 3.14 6.28 2 12.56 14 175.84

    15 2.81 5.62 4 22.48 15 337.2

    16 2.42 4.84 2 9.68 16 154.88

    17 2.05 4.1 4 16.4 17 278.8

    18 1.09 2.18 1 2.18 18 39.24

    276.22 2856.28

    LCF 10.3406

    AREA 91.1526

  • 7/30/2019 naval architect Project Report

    44/62

    44

    WATERPLANE 2

    STATIONhalf

    BREADTH

    full

    breadthSM f(A) LEVER f(M)

    0 0 0 1 0 0 0

    1 0 0 4 0 1 0

    2 2.37 4.74 2 9.48 2 18.96

    3 2.79 5.58 4 22.32 3 66.96

    4 3.25 6.5 2 13 4 52

    5 3.64 7.28 4 29.12 5 145.6

    6 3.75 7.5 2 15 6 90

    7 3.75 7.5 4 30 7 210

    8 3.75 7.5 2 15 8 120

    9 3.75 7.5 4 30 9 270

    10 3.75 7.5 2 15 10 150

    11 3.75 7.5 4 30 11 330

    12 3.75 7.5 2 15 12 180

    13 3.64 7.28 4 29.12 13 378.56

    14 3.41 6.82 2 13.64 14 190.96

    15 3.15 6.3 4 25.2 15 378

    16 2.82 5.64 2 11.28 16 180.48

    172.37 4.74

    418.96

    17322.32

    18 1.36 2.72 1 2.72 18 48.96

    324.8 3132.8

    LCF 9.6441

    AREA 107.2

  • 7/30/2019 naval architect Project Report

    45/62

    45

    WATERPLANE 2.5

    STATIONhalf

    BREADTH

    full

    breadthSM f(A) LEVER f(M)

    0 2.33 4.66 1 4.66 0 0

    1 2.72 5.44 4 21.76 1 21.76

    2 3.03 6.06 2 12.12 2 24.24

    3 3.32 6.64 4 26.56 3 79.68

    4 3.6 7.2 2 14.4 4 57.6

    5 3.81 7.62 4 30.48 5 152.4

    6 3.81 7.62 2 15.24 6 91.44

    7 3.81 7.62 4 30.48 7 213.36

    8 3.81 7.62 2 15.24 8 121.92

    9 3.81 7.62 4 30.48 9 274.32

    10 3.81 7.62 2 15.24 10 152.4

    11 3.81 7.62 4 30.48 11 335.28

    12 3.81 7.62 2 15.24 12 182.8813 3.77 7.54 4 30.16 13 392.08

    14 3.63 7.26 2 14.52 14 203.28

    15 3.44 6.88 4 27.52 15 412.8

    16 3.1 6.2 2 12.4 16 198.4

    17 2.54 5.08 4 20.32 17 345.44

    18 1.46 2.92 1 2.92 18 52.56

    370.22 3311.84

    LCF 8.9456

    AREA 122.1726

  • 7/30/2019 naval architect Project Report

    46/62

    46

    WATERPLANE 2.8

    STATION

    half

    BREADTH

    full

    breadth SM f(A) LEVER f(M)

    0 2.33 4.66 1 4.66 0 0

    1 2.98 5.96 4 23.84 1 23.84

    2 3.26 6.52 2 13.04 2 26.08

    3 3.5 7 4 28 3 84

    4 3.74 7.48 2 14.96 4 59.84

    5 3.87 7.74 4 30.96 5 154.8

    6 3.87 7.74 2 15.48 6 92.88

    7 3.87 7.74 4 30.96 7 216.72

    8 3.87 7.74 2 15.48 8 123.84

    9 3.87 7.74 4 30.96 9 278.64

    10 3.87 7.74 2 15.48 10 154.8

    11 3.87 7.74 4 30.96 11 340.56

    12 3.87 7.74 2 15.48 12 185.76

    13 3.85 7.7 4 30.8 13 400.4

    14 3.75 7.5 2 15 14 210

    15 3.6 7.2 4 28.8 15 432

    16 3.25 6.5 2 13 16 208

    17 2.6 5.2 4 20.8 17 353.6

    18 1.5 3 1 3 18 54

    381.66 3399.76

    LCF 8.907824

    AREA 125.9478

  • 7/30/2019 naval architect Project Report

    47/62

    47

    WATERPLANE 3

    STATION

    half

    BREADTH

    full

    breadth SM f(A) LEVER f(M)

    0 2.72 5.44 1 5.44 0 0

    1 3.1 6.2 4 24.8 1 24.8

    2 3.39 6.78 2 13.56 2 27.12

    3 3.58 7.16 4 28.64 3 85.92

    4 3.81 7.62 2 15.24 4 60.96

    5 3.9 7.8 4 31.2 5 156

    6 3.9 7.8 2 15.6 6 93.67 3.9 7.8 4 31.2 7 218.4

    8 3.9 7.8 2 15.6 8 124.8

    9 3.9 7.8 4 31.2 9 280.8

    10 3.9 7.8 2 15.6 10 156

    11 3.9 7.8 4 31.2 11 343.2

    12 3.9 7.8 2 15.6 12 187.2

    13 3.89 7.78 4 31.12 13 404.56

    14 3.82 7.64 2 15.28 14 213.9215 3.69 7.38 4 29.52 15 442.8

    16 3.34 6.68 2 13.36 16 213.76

    17 2.63 5.26 4 21.04 17 357.68

    18 1.51 3.02 1 3.02 18 54.36

    388.22 3445.88

    LCF 8.876101

    AREA 128.1126

  • 7/30/2019 naval architect Project Report

    48/62

    48

    WATERPLANE 3.5

    STATIONhalf

    BREADTH

    full

    breadthSM f(A) LEVER f(M)

    0 2.88 5.76 1 5.76 0 01 3.38 6.76 4 27.04 1 27.04

    2 3.62 7.24 2 14.48 2 28.96

    3 3.72 7.44 4 29.76 3 89.28

    4 3.89 7.78 2 15.56 4 62.24

    5 3.94 7.88 4 31.52 5 157.6

    6 4 8 2 16 6 96

    74 8

    432

    72248 4 8 2 16 8 128

    9 4 8 4 32 9 288

    10 4 8 2 16 10 160

    11 4 8 4 32 11 352

    12 4 8 2 16 12 192

    13 3.97 7.94 4 31.76 13 412.88

    14 3.94 7.88 2 15.76 14 220.64

    15 3.87 7.74 4 30.96 15 464.4

    16 3.55 7.1 2 14.2 16 227.2

    17 2.68 5.36 4 21.44 17 364.48

    18 1.53 3.06 1 3.06 18 55.08

    401.3 3549.8

    LCF 8.846

    AREA 132.43

  • 7/30/2019 naval architect Project Report

    49/62

    49

    WATERPLANE 3.8

    STATIONhalf

    BREADTH

    full

    breadthSM f(A) LEVER f(M)

    0 2.91 5.82 1 5.82 0 01 3.52 7.04 4 28.16 1 28.16

    2 3.72 7.44 2 14.88 2 29.76

    3 3.8 7.6 4 30.4 3 91.2

    4 3.91 7.82 2 15.64 4 62.56

    5 3.96 7.92 4 31.68 5 158.4

    6 4 8 2 16 6 96

    7 4 8 4 32 7 224

    8 4 8 2 16 8 1289 4 8 4 32 9 288

    10 4 8 2 16 10 160

    11 4 8 4 32 11 352

    12 4 8 2 16 12 192

    13 3.98 7.96 4 31.84 13 413.92

    14 3.96 7.92 2 15.84 14 221.76

    15 3.93 7.86 4 31.44 15 471.6

    16 3.64 7.28 2 14.56 16 232.96

    17 2.68 5.36 4 21.44 17 364.48

    18 1.54 3.08 1 3.08 18 55.44

    404.78 3570.24

    LCF 8.820199

    AREA 133.5774

  • 7/30/2019 naval architect Project Report

    50/62

  • 7/30/2019 naval architect Project Report

    51/62

    51

    12.3 Sketches

    A typical general arrangement of the vessel is given below. The drawings are not

    the scale.

  • 7/30/2019 naval architect Project Report

    52/62

  • 7/30/2019 naval architect Project Report

    53/62

    53

    Accommodation Ladder

    Two accommodation ladders, one on each side, are provided on the upper deck as

    ahown in the G.A plan. They are of the vertical self-stowing type.

    Material Al alloy

    Width Approx. 800 mm

    Windows

    The sizes of windows fitted are:

    Square windows : Approx. 400 x 600 mm in accommodation roomsApprox. 600 x 700 mm in public rooms

    Material : Aluminium alloy.

    12.5 Accommodation

    The requirements should includes

    1. Crew accommodation fwd.

    2. All bulkheads should be of steel. If in contact with weather they have to be

    gas tight and watertight. Means for closing the opening to be provided.

    3. Bulkheads connecting crew space with store, cargo spaced tanks etc should

    be watertight, gas tight.

    4. Bulkheads connecting two galleys, sanitary space, laundry etc should be

    gastight and watertight up to a certain height.

    5. Floors to be properly covered.

    6. Protection:

    a) Protection of crew against injury.

    b) Protection of crew against weather.

    c) Insulation from heat and cold.

  • 7/30/2019 naval architect Project Report

    54/62

    54

    d) Protection from moisture.

    e) Protection from effluent originating in various compartments.

    f) Protection from noise.

    7.No direct opening between accommodation and stores.

    8. Side scuttles can be opened in sleeping rooms, mess rooms, smoking rooms

    and recreation rooms.

    9. Separate sleeping rooms for officers, chief engineers etc.

    10.Mess room should be able to accommodate all officers at the same time.

    11.Recreation room should accommodate 1/3rd

    of the officers.

    12.Recreation are on the open deck.

    officers : 2member

    crew : 6member

    Total : 8 member

    GALLEY

    1. 1 single bowl stainless steel sink with

    2. 1 stainless steel 2 doors refrigerator

    3. 1 air ventilator diameter 8

    4. 3 spare power point.

    5. loose galley equipment such as pot, pan cutlery, for 8 crews.

    12.6 PAINTING AND CATHODIC PROTECTION

    PAINTING GENERALAll steel plate are to be shot blasted Sa 2.5 and primed with one coat epoxy primer

    before fabrication (about 20 microns dry film thickness) or Care must be taken toensure the surfaces are free of all kinds of contamination.

  • 7/30/2019 naval architect Project Report

    55/62

    55

    PAINTING SCHEMES

    Following specifications based on Hempel Coating System are for guidance. Other

    specifications of equal standard would be acceptable.

    Keel to Waterline Dry Film Thickness

    1 coat Epoxy 15039 30mic 1 coats Epoxy 45889 50mic

    2 coats Antifouling 80900 125mic

    Waterline to Deck

    1 coat Epoxy 15309 30mic

    2 coats Epoxy 15139 150mic

    Main Deck

    1 coat Epoxy 15309 30mic

    2 coats Epoxy 45889 100mic

    F.W. Tanks

    1 coat Epoxy 15039 30mic 2 coats Epoxy 15409 120mic

    Bilge, Void Spaces, Chain Locker & SWB Tanks

    1 coat Epoxy 15309 30mic 2 coats Epoxy 15139 60mic

    F.O. Tank

    1 coat Red Oxide 25mic

    Exterior/ Interior of Superstructure, crew Accommodation, Engine Room & Stores& Steering Gear.

    1 coat 15309 30mic

    1 coat Enamel White 52140 60mic

  • 7/30/2019 naval architect Project Report

    56/62

    56

    CATHODIC PROTECTION

    Zinc anodes are to be bolted the immersed loaded hull rudders and inside of the seachest, total of 8kg x 20pcs zinc anode or equal

    12.7 PIPEWORK COLOURING

    All exposed piping system are to be identified with color bands in accordance with

    the following schemes:1) Bilge & ballast : black

    2) Fire main : bright red

    3) F.W. System Cold : blue

    4) Fuel Oil : brown5) Lub Oil : yellow

    6) Hydraulic Oil : purple7) Sea Suctions : green

    8) Seawater cooling : light green

    12.8 LIFE SAVING AND FIRE FIGHTING EQUIPMENT

    LIFE SAVING EQUIPMENTTo be accordance with Requirement of Singapore Marine Department for as per

    safety plan Tug Boat with a total complement of eight men.Life Raft = 2 x 8men inflatable life raft

    Life Buoys = Eight (8) life buoy

    Life Jacket = Fourteen (8) life jackets complete with light and whistle

    FIRE FIGHTING EQUIPMENTFire Main = Three (3) x 1 fire hydrant with coupling and nozzles

    Fire Man Outfit = One (1) complete set .

    Fire Extinguisher = 8 x 9kgs dry chemical and 1 x 40 Ltr. Wheeled Form Or

    as per Safety plan

    Portable emergency Diesel Pump = One(1) unit 1

    ELECTRICALElectrical fittings use to be of good quality wiring system are comply withclassification societys requirements.

  • 7/30/2019 naval architect Project Report

    57/62

    57

    AC SupplyFrom 2 x 28 kw diesel driven generator set. 415/ 4/ 50 running in single.

    DC SupplyFrom batteries, 2x 150 N and 2X150 N as per classification requirement.

    12.9 Navigation lights

    Navigation lights provided as per SOLAS requirements

    1) Masthead light one on forward mast and one on navigational mast.

    2) Side lights Red light on port side and green light on starboard.

    Fitted on the sides of navigation bridge.3) Anchor lights All round white light at forward mast.

    4) Stern light White light at extreme aft.

    5) Towing light Yellow light at forward mast.

    The tug shall be fitted with the following equipment which must be maintained in

    good working order: -

    1. Compass2. Facility to take compass bearings

    3. RADAR with plotting facility

    4. Echo sounder

    5. Rudder Angle, RPM, variable pitch and bow thrust indicators (if fitted)

    6. Marine VHF radiotelephone installation

    7. Electronic Position Fixing Receiver

    8. Mobile telephone

  • 7/30/2019 naval architect Project Report

    58/62

    58

    13 Detailed Capacity Calculations and Drawings

    13.1 Introduction

    The cargo hold capacity is estimated for checking to carry out capacity of

    the vessel. Aside from their relationship to ship operating revenue, capacity

    calculations include locating center of gravity of all spaces containing significant

    dead weight items. The weights and center of gravities of these items are

    indispensable to stability and trim studies.

    Table shows tank capacity & centre of gravity.

    TANK NAME LOCATION (between stations) VOLUME LCG VCG

    BWT(PORT)1 0-2 3.25 0.984 2.47

    BWT(STARBOARD)2 0-2 3.25 0.984 2.47

    FOT(PORT)1 2--5 9.59 3.44 2.3

    FOT(STARBD)2 2--5 9.59 3.44 2.3

    DT(PORT)1 5--6 0.99 5.41 2.34

    LUBE OIL TANK 5--6 0.99 5.41 2.34

    FOT(PORT)3 12--16 16.4 13.78 0.74

    FOT(STARBD)4 12--16 16.4 13.78 0.74

    FWT(PORT,WINGS)1 16--17 6.33 16.2 1.476

    FWT(STARBD,WINGS)2 16--17 6.33 16.2 1.476

    FPT(PORT)1 17--19 4.44 17.45 1.32

    FPT(STARBD)2 17--19 4.44 17.45 1.32

    SWT(PORT) 7--9 4.12 7.87 0.35

    BWT(PORT)3 5--7 5.45 5.9 1.28

    BWT(STARBOARD)4 5--7 5.45 5.9 1.28

    BWT(PORT)5 6--7 1.27 6.39 0.39

    BWT(STARBOARD)6 6--7 1.27 6.39 0.39

    BWT(PORT)7 4--5 2.06 4.42 1.57

    BWT(STARBOARD)8 4--5 2.06 4.42 1.57

    HYROLIC OIL TANK 5--6 0.37 5.71 0.48

    BWT(STARBOARD)9 7--9 4.12 7.87 0.35

  • 7/30/2019 naval architect Project Report

    59/62

    59

    The capacities of tanks/compartments are determined using computer softwares

    like Autocad/MS excel. Table indicates the moulded capacities of respective

    tanks/compartments along with their location and centre of gravity.

    13.2 Loading conditions

    Procedure

    The LCG of the lightship mass is known. The mass and center of gravity of

    cargo, stores and ballast water are to be determined. Therefore, displacement at any

    loading condition is the sum of the corresponding weight components. Since the

    displacement at each condition is known.

    The range of loading conditions which a ship might experience varies with

    its type and the service in which it is engaged.

    1) Fully loaded departure condition with 90% component

    Loaded departure

    Sr No component weight(T)

    Light weight 145

    Total fresh water (90%) 9.234

    Total ballast water (90%) 34.218

    Total Fuel oil tank (90%) 38.9376

    Total sewage 0Human weight 1.02

    Food(10days) 1.5

    LUBE OIL TANK (90%) 0.784971

    Dirty oil tank 0

    TOTAL WEIGHT 230.6946

  • 7/30/2019 naval architect Project Report

    60/62

    60

    2) Arrival condition with 10% component

    Loaded arrival

    Sr No component weight(T)

    1 Light weight 145

    2 Total fresh water (10%) 1.026

    3 Total ballast water (90%) 34.218

    4 Total Fuel oil tank (10%) 4.3264

    5 Total sewage (90%) 3.888

    6 Human weight 1.02

    7 Food(10days) 0

    8 LUBE OIL TANK (10%) 0.087219

    9 Dirty oil tank (50%) 0.41184

    TOTAL WEIGHT 189.9775

    3) Ballast departure condition with 90% component

    Ballast departuresr No component weight(T)

    1 Light weight 145

    2 Total fresh water (90%) 9.234

    3 Total ballast water (90%) 34.218

    4 Total Fuel oil tank (90%) 38.9376

    5 Total sewage 0

    6 Human weight 1.02

    7 Food(10days) 1.5

    8 LUBE OIL TANK (90%) 0.7849

    9 Dirty oil tank 0

    TOTAL WEIGHT 230.6945

  • 7/30/2019 naval architect Project Report

    61/62

    61

    4) Ballast arrival condition with 10% component

    Ballast arrival

    sr No component weight(T)

    1 Light weight 145

    2 Total fresh water (10%) 1.026

    3 Total ballast water (90%) 34.218

    4 Total Fuel oil tank (10%) 4.3264

    5 Total sewage ( 90%) 3.888

    6 Human weight 1.02

    7 Food(10days) 0

    8 LUBE OIL TANK (10%) 0.087

    9 Dirty oil tank (50%) 0.41184

    TOTAL WEIGHT 189.9775

    5) Ballast arrival condition with 10% component

    Light ship

    Sr No component weight(T)

    1 Light weight 145

    2 Total fresh water 0

    3 Total ballast water 0

    4 Total Fuel oil tank 0

    5 Total sewage 06 human weight 0

    7 food(10days) 0

    8 Lube oil tank 0

    9 Dirty oil tank 0

    TOTAL WEIGHT 145

  • 7/30/2019 naval architect Project Report

    62/62

    14. Conclusion

    One of the principal uses of Bonjean Curves is determining volume of

    displacement of the tug at any level or trimmed waterline.

    Hydrostatic curves are useful in loading and stability studies during the

    design phase.

    While we making the hydrostatic curve of Harbor, Ocean Towing Tug , we

    also study the tug structure, stability, shape, uses of bonjean curve, etc.

    Loading condition of Harbor tug provides a ship's stability, and hence may

    vary considerably during the course of a voyage, or from one voyage to the

    next.