Upload
roycewiles
View
214
Download
0
Embed Size (px)
Citation preview
8/10/2019 National Solidarity Program Operational Manual (March 2004)
1/43
NATIONAL SOLIDARITY PROGRAM
OPERATIONAL MANUAL
TABLE OF CONTENTS
PREFACE 5
I. INTRODUCTION 6A. Background 6B. Goal and Objectives of the NSP 6C. Core Elements and Approach 6D. Scope and Targeting 7E. Conditions for Eligibility and Project Menu 9
II. ORGANIZATIONAL STRUCTURE 13A. Community 13B. Community Development Council and Project Management Committees 13
C. Facilitating Partner 18D. Ministry of Rural Rehabilitation and Development 19E. NSP Steering Committee 20
III. CYCLE OF ACTIVITIES 21A. Preparation 21B. Appraisal 22C. Sub-Project Implementation 24D. Monitoring by the Community 25E. Physical and Financial Progress Monitoring 25F. Sub-Project Completion 26
IV. FINANCING AND FUND-FLOW SYSTEM 26A. Overall Fund-Flow Arrangements 26B. Fund Transfer Mechanism 28C. Tripartite Agreement 29D. Disbursement to Communities 30E. Fund Management at the Community level 32F. Financial Reporting by Facilitating Partners 33
V. COMMUNITY PROCUREMENT 33A. Procurement of Goods and Materials 34B. Procurement of Works 34
C. Procurement of Services 35D. Storage 35E. Transport 36F. Administrative Costs 36G. Savings 36H. Transparency 36
VI. COMPLAINTS PROCESSING AND RESOLUTION 38
VII. MONITORING AND EVALUATION 39
NSP-II OperationalManual-21March04 Page 1 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
2/43
Acronyms and abbreviations
CDC Community Development Council
DAB Da Afghanistan Bank
FP Facilitating Partners
IDA International Development Association
IDP Internally Displaced Persons
MoF Ministry of Finance
MRRD Ministry of Rural Rehabilitation and Development
NGO Non-governmental Organization
NSP National Solidarity Program
OC Oversight Consultant
RRD Provincial office of MRRD
UXO Unexploded ordnance
Annex 1
Disbursement Prequalification Forms:
Disbursement Form 1 Community Profile (Baseline Data) FormDisbursement Form 2 Election Monitoring & CertificationDisbursement Form 3 Community Development Council Registration Application
Disbursement Form 4 Signatory Authorization (for block grant withdrawals)Disbursement Form 4a Bank Account Application FormDisbursement Form 4b Bank Account Withdrawal Authorization (for block grant
withdrawals)Disbursement Form 5 Certificate of Registration of Community Development CouncilDisbursement Form 6 Community Development PlanDisbursement Form 7 Sub-Project Proposal FormDisbursement Form 7a Mine Risk Clearance (English)Disbursement Form 7b Sub Project Summary Sheet (English)Disbursement Form 7c Project Eligibility Appraisal (English)Disbursement Form 8 Tripartite Agreement
Disbursement Form 9 Block Grant Fund Request
Annex 2
NSP Accounting Forms
1 Accounting InstructionsAcc Form 1 Cash Receipt VoucherAcc Form 2 Vendors InvoiceAcc Form 3 CDC Cash BookAcc Form 4 DAB ChequeAcc Form 5 CDC Bank BookAcc Form 6 CDC Cash Advance Book
NSP-II OperationalManual-21March04 Page 2 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
3/43
Acc Form 7 CDC Petty Cash Count FormAcc Form 8 CDC Stock book
Annex 3
NSP Procurement Forms
1 NSP Procurement InstructionsProc Form 1-0 Page SeparatorProc Form 1-0 Shopping Guidelines Instruction SheetProc Form 1-1a Invitation to QuoteProc Form 1-1b Technical SpecificationsProc Form 1-2 CDC Quotations Evaluation FormProc Form 1-3-1a Purchase OrderProc Form 1-3-1b Technical SpecificationsProc Form 1-3-2 Consultant Contract
Proc Form 1-4 Goods Received FormProc Form 2-0 Page SeparatorProc Form 2-0 Tendering Guidelines Instruction SheetProc Form 2-1-0 Invitation to BidProc Form 2-1-1 Instruction for BiddersProc Form 2-1-2 Bid Data SheetProc Form 2-1-3 Technical Specifications FormProc Form 2-1-4-0 Tender FormProc Form 2-1-4-1 Price ScheduleProc Form 2-1-4-2 Delivery ScheduleProc Form 2-2 CDC Quotations Evaluation FormProc Form 2-3-5-1 Order & Contract for Supply of GoodsProc Form 2-3-5-2 Contract for Civil WorksProc Form 2-3-5-3 Order & Contract for Consulting ServicesProc Form 2-4 Goods Received FormProc Form 3-0 Page SeparatorProc Form 3-0 Procurement Rule Waiver GuidelinesProc Form 3-1 Approval to Use Competitive Shopping MethodProc Form 4-0 Page SeparatorProc Form 4-01 Impartiality Confidentiality Declaration
Annex 4
NSP Reporting Forms
Reporting Form 1 - Project Completion FormReporting Form 2 - Certificate of Completion of a Sub-projectReporting Form 3 Sample Audit of Facilitating Partner by NSPInstructions for Quarterly Progress ReportsReporting Form 4 - Community Quarterly ReportReporting Form 4a - Community Progress ReportReporting Form 5 - Spot Check Reporting Form
Reporting Form 6 - Format for Monthly Status ReportReporting Form 7 - Facilitating Partner Quarterly Report
NSP-II OperationalManual-21March04 Page 3 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
4/43
8/10/2019 National Solidarity Program Operational Manual (March 2004)
5/43
PREFACE
The National Solidarity Program (NSP) is executed by the Ministry of Rural Rehabilitation
and Development (MRRD) with funding from the International Development Association
(IDA). The NSP operational manual provides information on key aspects of the NSP
including the project mandate, objectives, institutional arrangements, sub-project processes,
transfer of funds and financial management, and monitoring and evaluation procedures
among others. The main audiences for the NSP operational manual are the national,
provincial and district level government officials, Facilitating Partners, the Oversight
Consultant, and other consultants. The NSP operational manual is intended to ensure
consistency, transparency and accountability in the application of project management
procedures at all levels. The NSP operational manual is considered to be part of the
Development Grant Agreement with IDA and is therefore a legally binding document. The
NSP operational manual will be reviewed and revised biannually based on lessons learned
from the field.
NSP-II OperationalManual-21March04 Page 5 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
6/43
INTRODUCTION
A. Background
The National Solidarity Program (NSP) was created by the Government of Afghanistan to
develop the ability of Afghan communities to identify, plan, manage, and monitor their own
development projects. NSP promotes a new development paradigm whereby communities
are empowered to make decisions and control resources during all stages of the project cycle.
In accordance with government policy, the program is expected to lay the foundations for a
long-term strengthening of local governance, to make it more inclusive (e.g. for women,
Internally Displaced Persons, returnees, ethnic minorities), and to provide assistance for
reconstruction and development of communities.
The NSP has an implementation framework that includes a methodology for providing direct
financing to communities through transparent eligibility procedures for selection of sub-
projects. This methodology focuses on the development and strengthening of inclusive
community institutions through participatory planning and resource management as a basis
for community development.
B. Goal and Objectives of the NSP
The goal of the NSP is to reduce poverty through empowering communities with regard to
improved governance, and social, human, and economic capital. The objectives of the
program are to: (1) lay the foundations for a strengthening of community level governance,and to (2) support community-managed sub-projects comprising reconstruction and
development that improve the access of rural communities to social and productive
infrastructure and services. The outcomes that the NSP aims to achieve are (i) the
establishment of a framework for village level consultative decision making and
representative local leadership as a basis for interaction within and between communities on
the one hand, and with the administration and aid agencies on the other, and (ii) local level
reconstruction, development, and capacity building which will lead to a decrease in poverty
levels.
The NSP grants to villages are intended to act as catalysts in this process and at the same time
provide much needed support for local reconstruction and development activities.
C. Core Elements and Approach
The design of NSP consists of four core elements:
Facilitationat the community level to assist communities establish inclusivecommunity institutions through elections, reach consensus on priorities andcorresponding sub-project activities, develop eligible sub-proposals that comply with
NSP appraisal criteria, and implement approved project sub-proposals;
NSP-II OperationalManual-21March04 Page 6 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
7/43
8/10/2019 National Solidarity Program Operational Manual (March 2004)
8/43
and optimal use of field staff.1 Funds will be allocated for projects that have been appraised
by the NSP as meeting the eligibility criteria of the NSP (See Section E below), and for
which financing agreements have been signed between the NSP and the community
organization and the FPs (Disbursement Form 8).
Communities will be defined on the basis of existing available information from government
records (e.g. the list of registered villages from the 1970s, or the list of villages prepared for
the nomination of the members of the 2002Loya Jirga). However, since the reliability of the
available official data on villages was inconsistent when the records were established, and
since it is by now outdated due to population increase and/or displacements, the identification
of communities for the purpose of the NSP would have to reflect the ground realities existing
today. Where Facilitating Partners find that the realities on the ground deviate significantly
from the existing official village lists, local authorities (e.g. woluswal, MRRD provincial
office) should be consulted where possible to arrive at a more operationally practical
definition of communities that corresponds to existing local settlement patterns. The
proposed plan for defining communities for the purpose of NSP would then have to be
approved by NSP, Kabul. The establishment of a Community Development Council would
not affect the village's legal standing with the Ministry of the Interior.
The definition of a community for the purposes of block grant allocation will be based on the
following principles:
A community is a village of more than 25 families;
One Community Development Council will be established for each community.Development Councils can not be established for sub-sets of an existing village (e.g. avillage can not be split into its constituent political or ethnic/qaumsub-divisions);
One block grant (budget) will be allocated to each community at a rate of US$200 perfamily with an upper limit of US$60,000 per community. This allocation requires thatthe community develops one or more eligible sub-project proposals within the budgetframe.
The community is willing to contribute at least 10 % of the value of the block grant todevelopment activities financed out of the block grant.
A family is defined as a nuclear family consisting of a man, his wife (or wives) and
unmarried children, or a widow(er) and her/his unmarried children. The number of families
in the targeted village communities will be assessed by the Facilitating Partner, and this
enumeration can be verified through such means as a community meeting, consultations with
the local mullah(s), and existing village lists for voluntary contributions towards ashar,
mosque repair etc. Once village selection is confirmed (the community will have to confirm
its interest to participate during a mass meeting) and the number of families is agreed, the
1 i.e. villages chosen for annual implementation coverage should to the extent possible be more or lessadjacent to facilitate optimal utilization of facilitation staff and transport resources.
NSP-II OperationalManual-21March04 Page 8 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
9/43
block grant amount would be adjusted to reflect the more accurate population size, and
communicated to the community.
As stated above, the minimum size of a community potentially eligible for a block grant
allocation would be 25 families. Smaller settlements should be encouraged to join with other
ones to pool their block grant allocations for larger scale joint activities (e.g. a clinic, a
school, or a multi-village pipe water supply system). Where this is not possible, isolated
settlements below 25 families can be exceptionally included.
The block grant of a community can be carried forward to the next year if it has not been
fully committed or disbursed for specific projects during Year 1. It can only be carried
forward from one year to the next. After that, the un-committed amounts would be cancelled.
An option to facilitate re-integration of IDPs and returning refugees is to communicate to
specific communities with a considerable IDP/refugee population, that the block grantallocation can be increased upon the return of IDPs/refugees and their participation in project
planning. This incentive could encourage communities with a high proportion of IDPs or
refugees to initiate consultation with them about their return during the project preparation
phase to obtain access to an increased block grant allocation. Where a return of
IDPs/refugees is planned, and IDPs/refugee families or family members return to their
communities during the project preparation phase, a reassessment of the population size
should be undertaken prior to final project development and costing to enable an adjustment
of the block grant allocation. Where such planning is undertaken, the Facilitating Partner
should assist the community in assessing whether the additional resources provided through
the enhanced block grant and the proposed project activities would enable a sustainable re-
integration of the returnees.
While no specific conditions have been established for targeting women during the first year
of the project, it is expected that all Facilitating Partners will attempt to engage female
facilitation staff, and develop arrangements in consultation with the community for the
involvement of women during the sub-project cycle mechanisms for consultation with
womens groups, getting their input when prioritizing needs, electing officials, etc., should be
described in the Facilitating Partner work plan.
E. Conditions for Eligibility and Project Menu
The Community Development Council will be registered (Disbursement Form 5) with
MRRD after it has been verified that the election was conducted in compliance with the
election rules (see Chapter II.B and Disbursement Form 2). Then the community will be
eligible for the block Grant.
(i) To make use of the block grant allocation, the community must develop aCommunity Development Plan and an eligible sub-project proposal (or proposals)
NSP-II OperationalManual-21March04 Page 9 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
10/43
that fulfils the following criteria: is proposed by a representative CommunityDevelopment Council(which has been elected through a community-wide
process),
(ii) is endorsed through a community-wide process,
(iii) provides equitable access to benefits,(iv) is technically and financially sound,
(v) includes an operation and maintenance plan,
(vi) has at least 10% community contributions towards capital costs ,
(vii) includes a commitment to and plans for ensuring transparency of the use of blockgrant funds.
The community contribution towards capital costs can comprise cash, labour, or in kind
contributions such as construction materials and/or transport.2 The requisite community
contributions in estimated monetary equivalent for each project milestone must be clearlyspecified (e.g. the amount of labor or materials to be provided at specific stages during
implementation). The Facilitating Partner will monitor, assess and report quarterly to the
NSP as to whether this condition is being adequately met.
Toprepare a Sub-project proposal the community should take note that NSP will accept an
open menu of sub-projects within four types of investments, subject to a short negative list.
The four types of investments are3:
Community infrastructure (the investments will comply with defined technical
standards, and will only comprise public goods);
Human capital development activities (e.g., time-bound literacy classes, hygieneeducation etc., that are not planned to incur recurrent costs from the state);
Self-help savings and credit schemes for women and disabled that would draw on bestpractice lessons from other projects and be based on a predefined methodologydeveloped by NSP (this practice can only comprise 10% of the total value of a blockgrant with an upper limit of US$5,000 equivalent).
Productive asset transfers for vulnerable women and disabled that would draw on bestpractice lessons from other projects and will be based on a predefined methodology
developed by NSP (i.e. sewing machines, looms etc. supported by training asrequired) (the value of the assets can only comprise 10% of the total value of a blockgrant with an upper limit of US$3,000 equivalent).
Public infrastructure projects would include, but not necessarily be restricted to: irrigation
works; roads including culverts and small bridges; erosion protection; structures promoting
2 The time spent by members of the Development Council will not be counted towards the communitycontribution, and can not be compensated out of the block grant. If the community decides that members of theDevelopment Council should be compensated for their time, this should be from a community contribution over
and above the 10% contributed towards the capital costs of projects.3 Investments in income generating assets if later included in the menu would draw on best practicelessons from other projects.
NSP-II OperationalManual-21March04 Page 10 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
11/43
watershed management; water supply facilities; public baths (hamam); and school buildings.
When school buildings are proposed by the community, endorsement would be required from
Ministry of Education that these are included in the development plans of the ministry, and
that funding of operational costs would be provided (fully or with committed contributions
from other agencies). Where clinics are proposed for block grants, endorsement is required
by the Ministry of Health that they are included in its development plans and that it will cover
the associated operational costs.
The project will notfund:
equipment or materials that are included in the annual implementation plans by otheragencies (e.g. by other government or NGO projects that are operating in the area);
political campaign materials or donations in any form;
weapons including (but not limited to), mines, guns and ammunition; chainsaws;
pesticides, herbicides and other chemicals;4
investments detrimental to the environment;
land (purchase or lease), under any conditions;
construction, rehabilitation, or maintenance of any government office buildings;
payments of salaries to government servants or the salaries of the staff of governmentsubsidized organizations;
any activity on land that is considered dangerous due to security hazards or thepresence of unexploded mines or bombs, UXOs,
any activity on land that has disputed ownership or tenure rights .
any activity that will support drug crop production or processing of such crops.
The table on the next page defines the eligibility for block grant funding of different types of
subprojects that are not clearly public goods infrastructure. This list may not be exhaustive
and future sub-project proposals that fall in the grey area between public and private goods
will be reviewed by the NSP/MRRD/OC on a case by case basis.
As part of promoting technical soundness, each activity must take into account environmental
and social impacts as defined in the governments Environmental and Social Safeguards
Framework. Since most of the works are expected to be small community-based projects,
environmental risks are generally considered to be minimal. To ensure compliance with the
safeguards framework, all proposals must include completed simple environmental and social
4
Exceptions may be considered based on an assessment by the NSP (with specialized consultantassistance, if required, and after no objection from IDA) in special situations such as eradication of infestationsof locusts or sen pest.
NSP-II OperationalManual-21March04 Page 11 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
12/43
checklists developed by NSP, which describe impacts and mitigations measures, if any (see
Disbursement Form 7c).
Involuntary land acquisition and forced (involuntary) resettlement caused by acquisition of
land or houses are not allowed under any condition. If any minor areas of land would be
needed for a project (e.g. realignment of an irrigation canal, or land for a school), such land
can only be obtained through either private voluntary donations, compensation paid by the
community (i.e. transaction between willing buyer-willing seller), or from available
government land. Private voluntary donations and community purchases would be
documented as required by the Environment & Social Safeguards Framework agreed between
the government and IDA, and for government land, documentation would be needed that the
land is free of encroachments, squatters or other encumbrances, and has been transferred to
the project by the authorities. Any activity that in any way involves voluntary resettlement
requires an early special approval from the NSP. The negative list will be reviewed and if
necessary revised by NSP every year.
Sub-Project Proposal
Generally
Eligible for
Block Grant
funding
Eligible under the
Women/Disabled
category
Eligible under
the Asset
Transfer
category
Comment
Diesel Water Pump (irrigation) No No No On negative list
Micro Hydropower Yes - - Equity & O&M plan
Generator for electricity Yes - - Realistic O&M plan
Public Bath (Hamam) Yes - - Realistic O&M plan
Bakery No Yes Yes Business plan & O&M
Mill (diesel) Yes - - O&M plan
Mill (water) Yes - - O&M plan
Carpet/gelim weaving No Yes Yes Equity & Business plan
Tailoring No Yes Yes Equity & Business plan
Farm animals (goats, cow, etc) No Yes Yes Equity & Business plan
Farm inputs (fertilizer, seed) No Yes Yes Equity & Business plan
Grocery store No No Yes Business plan
Tractor No No No
Thresher No No No
Truck, Bus No No No
Religious buildings No No No
Cash donation for disabled No No No
Land leveling for agriculture No No No
Vocational training Yes Yes - Equity in access to benefit
Literacy training Yes Yes - Equity in access to benefit
Other training (computer, tractoretc)
Yes Yes Yes Equity in access to benefit
Once it is determined through an appraisal of the project proposal (Disbursement Form 7 andSection III.B) by NSP that the eligibility criteria listed above have been complied with, the
NSP-II OperationalManual-21March04 Page 12 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
13/43
funds will be paid directly from the NSP to a community, according to defined payment
schedule based on the Tripartite Agreement (see Chapter IV.C and Disbursement Form 8).
The result of the appraisal of the community project proposal will be confirmed on the first
page of Disbursement Form 7.
I. ORGANIZATIONAL STRUCTURE
A. Community
For the purposes of the NSP, a community is defined as a village consisting of at least 25
families that is able to identify a need and come together to access NSP funds. Communities
will be identified on the basis of existing local settlement and social patterns. However, this
would not prevent different distinct villages from joining together to develop assets (e.g. a
school, or a pipe water system) that serves more than one village. In such a situation, people
from all areas that make direct use of the asset should be included as part of the community
for the purposes of the planning, implementation, and maintenance of the joint asset. The
block grant for such joint projects will be equal to the aggregate amount for the collaborating
communities or a portion thereof as required and agreed by the communities.
While a community will be assisted by NSP financially, a key characteristic of this approach
is that it promotes a high level of community participation and ownership during all phases of
the project cycle. As such, functions of the community will include:
Identifying and prioritising needs; Electing the Community Development Council and relevant Project Management
Committees;
Preparation of a community development plan and sub-project proposals;
Providing community contributions;
Participating in field appraisal, project launch ceremony, and all other communitymeetings related to the project;
Management of project implementation by the community through its CommunityDevelopment Council or Project Management Committee(s);
Providing oversight of project implementation with regard to quality and use of funds;
Maintaining the asset after completion with community cost contributions.
B. Community Development Council and Project Management Committees
The Community Development Council (CDC) will be a community-based decision making
body which is elected by the community through elections based on a secret ballot. As the
representative body of the community with regard to the NSP, the Development Council will
be responsible for overseeing the preparation of the Community Development Plan (defining
community needs and priorities, and the project or sub-projects to address some or all of
NSP-II OperationalManual-21March04 Page 13 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
14/43
these priorities), and the preparation and implementation of individual sub-projects. The
Development Council should at least comprise a Chairperson, Treasurer and Secretary. The
Development Council should obtain the endorsement through community meetings
regarding:
decisions on rehabilitation or development priorities, and the final selection of projectproposals developed on the basis of agreed priorities,
the size and composition of community contributions, and the use of project funds,
transparency arrangements,
arrangements for maintenance of completed projects.
The Community Development Council will sign an overall Tripartite Agreement
(Disbursement Form 8) with NSP and the Facilitating Partner on behalf of the community.
Depending on the number of sub-projects to be managed, smaller Community Project
Management Committees may be established to prepare and manage individual sub-projects,
but they will report to the Community Development Council and the community-wide
meetings. On the other hand, if a community chooses to implement only one or two sub-
projects, the Development Council may manage implementation of those projects. These
representative Development Councils must be registered with NSP as a condition for
receiving assistance and overseeing the management of communally owned property
(Disbursement Form 5). A Community Project Management Committee (which can be
identical with the Development Council and should comprise at least a Chairperson,
Secretary, Treasurer, and Storekeeper) nominated by a community wide assembly will be
able to withdraw funds and procure goods and services for implementation of the project after
being registered with the NSP (Disbursement Form 4).
Specifically, the Community Development Council will be responsible for:
Overseeing preparation of the community development plan;
Convening community wide meetings;
Overseeing planning and preparation of individual sub-projects through the
community project management committees; Mobilizing community contributions;
Ensuring community participation during all phases;
Presenting the sub-project plans at appraisal;
Managing and supervising sub-project implementation;
Overseeing (or directly handling) procurement and financial management at thecommunity level;
Reporting to the community and to NSP on project progress and use of funds.
NSP-II OperationalManual-21March04 Page 14 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
15/43
The Community Development Council will be established through an election which will be
conducted according to the following rules:
Everybody in the community who is entitled to vote in government elections isentitled to be registered as a voter;
Each person has one vote ;
The voting will be conducted through a secret ballot;
Both men and women are eligible to be members of the Community DevelopmentCouncil;
Predefined candidate lists and electioneering are prohibited; and
At least 40% of eligible voters to have voted for an election to be valid.
Development councils elected under an election that does not comply with these rules will
not be eligible for funding under the NSP.
Regarding the first point above, registering as a voter is an entitlement, not an obligation.
However, in declaring whether the election for the Council is valid, an estimate of all eligible
voters, not all registered voters should be used. Whether the community wishes to extend
voting entitlements to people who are not eligible to vote in government elections is a matter
for the community to decide.
In the case of the secret ballot, it is essential to remove, or at least minimise, the opportunity
for undue influence to be exerted when people are voting. The exact mechanism to ensure
this will need to be determined on a case-by-case basis, but the underlying principle is that
each individual should cast his or her vote in private.5
Prohibition of candidature and electioneering is critical to reduce the likelihood of elite
capture and intimidation, recognising that it will not remove it. To avoid the problem of
selecting unwilling candidates, community members will prior to the election have an
opportunity to declare, that they are not prepared to accept the position if elected. All
members of the community are candidates until they take the positive step to declare
themselves ineligible.
The combination of high levels of illiteracy and the prohibition of predefined candidate lists
and electioneering will present a range of challenges to the Facilitating Partners. However,
both aspects are so central to the program that innovative and creative solutions will need to
be developed. Since the elections will take place in small clusters of households many of
5 This could involve separate ballot boxes for men and women, decisions on whether the ballot paperwill have a list of all interested eligible cluster members, or whether the name of the candidate for which a voteis cast is written on the ballot paper. If either of these solutions is agreed, assistance would have to be providedto illiterate voters by the Facilitating Partner, and a process to verify votes cast on a sample basis would also
need to be agreed. Another issue that may require different local solutions is whether the names of women canbe listed on ballot papers, and where this is not possible, how the number of eligible women voters isestablished, and how votes are cast for female candidates.
NSP-II OperationalManual-21March04 Page 15 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
16/43
whom know each other, such solutions are possible. An obvious solution is for the
Facilitating Partner to assist the illiterate members of the community. An alternative is to
prepare ballot papers in the forms of maps of the village, with people marking the address of
the person that they wish to vote for and a symbol for the person within that address (e.g.
distinct symbol for oldest male, oldest female, etc).
To have functioning Development Councils, the number of representatives should be between
5 and 15 persons depending on the size of the community. The Development Councils
should select a Chairperson, Secretary and Treasurer. For the Development Council to have
the authority to make decisions over resources it must also have a quorum of the community
involved in the election. For the first round of NSP, a quorum is defined as 40% of all
eligible voters. It is government policy to increase this percentage over the life of the
program
Where local norms regardingPurdahdo not allow women to participate directly in
community wide meetings or in the Development Council, the Facilitating Partner must
promote the establishment of a separate forum where women can define their priorities. The
Facilitating Partner should also ensure that the priorities defined by women are discussed
with the men, and that those defined by the men are discussed with the women, so that the
Community Development Plan takes account of both.
To ensure inclusiveness in terms of different socio-economic, factional, and ethnic/tribal
(qaum) sub-divisions within the community, the election process should be based on division
of the community into groups of families (clusters), which will each elect one representative
for the Development Council. Since neighbours are usually also relatives, the division into
clusters will also reducepurdah restrictions on women and thereby facilitate their active
involvement in discussions of the qualities required for representatives and in the election
itself. The size of such clusters will vary depending on the size of the community, but should
not exceed about 20 families. The clusters would in turn serve as the framework for
community wide consultations on proposals from the Development Council, through a
process where the elected councillors consult with and seek feed-back from their electorate
before decisions on priorities, sub-projects, and community contributions are finalized.
Since communities will only have one Development Council, local solutions should be
agreed for large communities (>300 families) with assistance from the Facilitating Partner.
One such solution could be a two-tier voting process, where candidates elected by clusters of
20 families elect a smaller Development Council (see diagram on following page)
NSP-II OperationalManual-21March04 Page 16 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
17/43
NSP-II OperationalManual-21March04 Page 17 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
18/43
C. Facilitating Partner
The primary role of the Facilitating Partner is to provide support and guidance to the
community in meeting the requirements of NSP as described in this manual.
The Facilitating Partner will report to the NSP. An agreement will be signed with thecommunity on the community development plan regarding the exact inputs to be provided
and services to be performed by the Facilitating Partner (Disbursement Form 8).
In each province one or more Facilitating Partners will deploy community facilitators and
technical specialists for three districts at a time to cover a target of up to 216 communities per
year.6 Depending on capacity, individual Facilitating Partners will undertake these activities
in one or more districts, or in one or more provinces.
The roles of the Facilitating Partners are to:
Facilitate elections of inclusive CDCs;
Facilitate consultative community project planning comprising CommunityDevelopment Plans and sub-project proposals;
Provide technical assistance to develop sub-project proposals through either:
o facilitating community access to technical assistance available in the market orfrom other agencies; or,
o technical assistance provided by the Facilitating Partner,7
Provide technical assistance to communities during implementation;
Provide training to communities (e.g. book-keeping, procurement, contracting);
Conduct monitoring and reporting.
The expected outputs of the Facilitating Partners are:
Eligible project proposals (measured by the number of projects appraised andapproved by the NSP);
Implementation of funded projects (measured by the number of projects completed inaccordance with design standards and in a sustainable manner);
Depending on the number of districts and number of communities defined in the Facilitating
Partners contract, performance will be assessed against the following annual target outputs
for year 1. Achieving or exceeding the targets as defined in the table below will be a key
determinant for extension/expansion of the contracts of the Facilitating Partners.
6 Where feasible, the Facilitating Partner is expected to recruit and deploy female field staff to enableinvolvement of women in the targeted communities in the prioritisation, decision-making, and implementationof projects.7
While the preferred approach under NSP is for communities to avail themselves of technical assistancefor project design through the market, it is recognized that this may not be feasible in many rural areas, and thatin such situations, technical assistance will have to be provided by the Facilitating Partner.
NSP-II OperationalManual-21March04 Page 18 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
19/43
District 1 # ofcommunities
# offamilies
Appraised andapproved project
proposals
Completedprojects
(% of fundedprojects
completed)
% ofsub-projectsfunctioning 3months aftercompletion
1
st
cycle 80% 80% 80%2ndcycle 80% 80%
3rd
cycle 80% 0%
Total 80% 53% 80%
The table above assumes that the Facilitating Partners staff is deployed so that facilitation of
project preparation and implementation in a district is undertaken in three successive batches,
each with a four month period for community planning, project preparation and appraisal,
followed by an implementation period depending on the type of project that is undertaken.
The table reflects that some of the target communities in the 3rdbatch would still be in the
process of project preparation and appraisal by the end of year 1, and that implementation, if
started, would not be completed. Likewise, for some of the target communities in the 2nd
batch, ongoing implementation would not be completed by the end of year 1. Since not all
Facilitating Partners may choose to deploy their field staff for coverage of their annual target
as outlined above, an aggregate target is provided for expected outputs in a district in year 1.
The NSP will hold Facilitating Partners accountable for performance against outputs, but the
NSP will provide flexibility to its partners in the choice of specific facilitation methods and
work planning. The Facilitating Partners may use facilitation methods that they deem
appropriate while respecting the eligibility criteria to achieve the outputs against which the
eligibility of community project proposals will be appraised (see Section I.E above), and may
also plan the deployment of their staff and sequencing of activities in ways they consider
optimal for achieving their overall output targets.
D. Ministry of Rural Rehabilitation and Development
MRRD will be responsible for overall management and supervision of the National Solidarity
Program (NSP). Within the ministry, the NSP will be managed by an Oversight Consultant
working with MRRD counterparts in the Community Led Development Department to
strengthen capacity for community development and program management. The Oversight
Consultant will support the Community-Led Development Department regarding:
Management of the NSP block grants for community projects (including effectingfund transfers, tranche payments, financial management, and accounting);
Supervision of the performance of Facilitating Partners (including contractmanagement, contracting of Facilitating Partners beyond those recruited by MRRD
prior to the Oversight Consultant being recruited in order to secure services ofFacilitating Partners to cover all 32 provinces at the scale required);
Appraisal of community project proposals;
NSP-II OperationalManual-21March04 Page 19 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
20/43
Planning and conducting training for the field staff of Facilitating Partners (eitherdirectly or through sub-contracting);
Undertaking technical and financial monitoring, and producing consolidated progressreports, and
Managing an information and communication campaign.
E. NSP Steering Committee
A Steering Committee acts in an advisory capacity to MRRD on overall program policy
formulation and direction, and oversees program implementation. At present, the Steering
Committee is composed of representatives from MRRD and Ministry of Finance (MoF). An
External Review Committee consisting of donors, UN agencies, the Independent Commission
for Human Rights, MoF and MRRD meets on a regular basis to review and endorse all policy
and contractual issues.
Discussions are underway to broaden the membership of the Steering Committee by merging
the two bodies. An inter-ministerial committee has been established for policy advice and
coordination. The committee is chaired by MRRD and comprises the ministries of Finance,
Agriculture, Public Health, Education, Irrigation, Labor & Social Affairs, Womens Affairs,
Public Works, Reconstruction, Foreign Affairs, and Refugees.
NSP-II OperationalManual-21March04 Page 20 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
21/43
ORGANIZATIONAL CHART
MRRD NSPCommunity-Led Development
Department and NSP OversightConsultant
NSP Steering
Committee
National Level
MRRD NSPCommunity-Led DevelopmentDepartment and NSP Oversight
Consultant
ProvincialLevel
District andCommunityLevel
FacilitatingPartner
FacilitatingPartner
FacilitatingPartner
Communities
II. CYCLE OF ACTIVITIES
This section covers the activities to be undertaken during preparation, appraisal,
implementation and completion of the sub-project cycle. The goal is to facilitate an inclusive
participatory process within the community which results in an equitable community
development plan including a series of sub-projects that are eligible for funding under the
NSP and/or eligible for funding from other existing programs. The long-term goal is the
creation of community institutions that are to strengthen the communitys ability to mobilize,
consult, plan, finance, implement and evaluate their own development.
A. Preparation
During this phase of the cycle, Facilitating Partners will help:
mobilize the community including facilitating the establishment through elections of aCommunity Development Council and related project implementation committees asagreed with the community;
facilitate a participatory planning process that includes women and the weakersections of the community;
strengthen community capacity to identify and prioritise needs;
NSP-II OperationalManual-21March04 Page 21 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
22/43
assist the community to prepare a Community Profile with baseline data(Disbursement Form 1);
facilitate the preparation of a Community Development Plan (Disbursement Form 6)and proposals for specific project(s) with budget(s);
provide technical assistance to develop sub-project proposals (Disbursement Form 7)for appraisal through either:
o facilitating community access to technical assistance available in the market orfrom other agencies; or,
o technical assistance provided by the Facilitating Partner,
sign off on the Community Development Plan and sub-project proposal(s) withrespect to technical quality, financial feasibility and inclusive communityinvolvement in planning and decision making before they are submitted to NSP.
The community will:
elect an inclusive Community Development Council and establish ProjectManagement Committees as needed for sub-projects;
develop a Community Development Plan (including priority sub-project proposalswith budgets and community cost contributions and O&M arrangements as well as
projects which can be financed and implemented by the community itself);
obtain inputs and endorsement from the community (if necessary through separatemeetings with men and women) regarding the Community Development Plan;
mobilize the required technical expertise to help develop designs within given
technical standards;
8
agree on rules for dissemination of budget and expenditure information;
submit the community development plan and proposal(s) to NSP.
The training manual provides more in-depth guidance on the processes which can be
followed during each phase, however, the Facilitating Partner will have flexibility in the
choice of the facilitation methodology for undertaking the activities listed above.
B. Appraisal
The community (with the assistance of the Facilitating Partner) will complete and submit aCommunity Development Plan and standard sub-project proposal(s) (including technical
designs and cost schedules) to the provincial representative of the NSP. (See Disbursement
Form 6 and 7 for standard format for the community development plan and sub-project
application form). The Community Development Plan constitutes a medium term investment
plan for a particular community, which would provide the basis for additional future
development activities whether funded by NSP or other sources, and also represent for the
8 This may involve getting the required technical assistance from the market (payment can be made
directly as part of the community contribution, or retroactively if and when a project is appraised and foundeligible for funding), or getting this assistance from the Facilitating Partner, where it is unavailable in themarket.
NSP-II OperationalManual-21March04 Page 22 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
23/43
first time ever a bottom-up input to higher level planning at the district, provincial, and
national level.
Appraisal of the community proposal and budget are conducted by the NSP. The Facilitating
Partner will help communities prepare and implement sub-project proposals and be
positioned as allies of the community, while the NSP staff will formally appraise proposals
and make funding decisions.
The NSP will be responsible for appraisal of all community project proposals to determine
whether they meet the eligibility criteria. This will be done using a standard appraisal tool
(Disbursement Form 7c) by the NSP technical staff from the provincial office (and involving
relevant government agencies, e.g. for education). The appraisal will be done using a
transparent procedure. Eligibility criteria, indicators and means of verification are listed in
the table below. The criteria will be made known to the community in order to limit the
discretionary power of the NSP. A proposal is evaluated based on these criteria and assessed
during a field visit to the community. During this appraisal visit the appropriate levels of
installments will be discussed and agreed upon. In the absence of special agreements the
installments will be 50: 40: 10 %.
The community is then informed by the NSP regarding the result of the appraisal, which may
be a) approval of funding for the proposed plan, b) rejection for non-compliance with NSP
rules (e.g. project is on the negative list), c) requiring the community to revise its proposal
with regard to either the election of the Community Development Council, the planning
process, the budget, or the technical standards.
The provincial NSP office will undertake field verification on a sample basis of whether
elections of Community Development Councils conform with the basic principles defined in
this manual. In addition, the national level NSP office will undertake periodic field
supervision audits on a sample basis of the appraisal process to ensure that eligibility criteria
are complied with.
Upon completion of appraisal and approval by NSP of a community sub-project proposal, a
Tripartite Agreement will be signed between the Community Development Council, NSP,and the Facilitating Partner regarding the financing of the sub-project, disbursement schedule
and benchmarks triggering installments and the general obligations of each of the parties to
the agreement (see Section IV, C)
NSP-II OperationalManual-21March04 Page 23 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
24/43
Sub-Project Eligibility and Appraisal Criteria
CorePrinciples Eligibility Criteria Indicator Means of Verification
Does ProposalMeet Eligibility
Criteria?
1.
Representativecommunityinstitution
Establishment of a
community widedecision makingprocess and election ofa representative CDC
CDC elected with representation
from different geographical andoccupational sections
40% of eligible votersparticipated in the election
CDC Registration Form;
CDC registration certificate; Form 2;
Proposal submitted by CDC
(YES) (NO)
2.BeneficiaryParticipation
CommunityDevelopment Planendorsed through acommunity-wideprocess
Community-wide meetings held;
60% of families participated indecision meeting.
Decisions/priorities of womentaken into account
Random interviews withcommunities;
Interviews with womens groupmembers;
Minutes of decision makingcommunity meetings
3.Equity
Sub-project providesbeneficiaries equitableaccess to benefits
Persons from differentgeographical and occupationalsections of the community canaccess benefits
Confirmation of sub-project mapof beneficiaries through randominterviews with communitys
Check proposal on beneficiariesand equity
4.TechnicalSoundness
Sub-project istechnically sound
Sub-project complies withappraisal criteria for technicalquality standards, and the projectnegative list.
Check proposal for technical quality(problem statement, goals &objectives, engineering designs ,implementation arrangements, risksand constraints)
5.FinancialSoundness
Sub-project is financiallysound
Sub-project complies withappraisal criteria for financialsoundness and is correspondingto the technical layout.
Check proposal for financial quality(project budget, procurement plan,disbursement schedule)
6.Compatibilitywith social andenvironmentalsafeguards
Sub-project is sociallyand environmentalsound
Sub-project complies withappraisal criteria, environmentaland social safeguards issues, andthe project negative list.
Check proposal for environmentaland social quality
7.
CommunityCommitment
Sub-project has
community contributiontowards capital costs
Minimum of 10% of capital costs
committed (cash, kind or labor)
Check proposal
Random interviews with communities
8.Sustainability
Proposed project hascommunityarrangements foroperation &maintenance (O & M)
O & M plan with budget committedand training plan prepared
Check proposalRandom interviews with communities
9.Transparency
Accept principles oftransparency regardingbudgeting andexpenditures
Budget (and later accounts)posted in public places andthrough meetings (e.g. in themosque and womens meetings)
Check proposalRandom interviews with villagers(both men and women)
10. Mine Risk Mine Risk Safety hasbeen assessed
Questionnaire on Mine RiskSafety/Clearance has been filledout
Check proposalForm 7a
C. Sub-Project Implementation
The primary responsibility for sub-project implementation will rest with the community (the
Community Development Council, Project Management Committee, and the greater
community). Clear divisions of responsibility between the Development Council members
and Project Management Committee members will increase accountability. Three or more
persons at the community level should be identified as responsible for most implementation
activities such as procurement, bookkeeping, supervision, storage and accounting. This willnot only promote transparency and continuity at the community level but it will also ensure
NSP-II OperationalManual-21March04 Page 24 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
25/43
that more than one person in the community has the necessary skills/training to perform the
task.
Depending on the type of sub-project, the community may either be capable of undertaking
implementation itself, or may require external assistance regarding specialized technical
skills or services (e.g. masons for school construction, or lining and hand pump installation
for dug wells for drinking water). The procurement of such services will follow established
procedures (see Annex 3 Procurement Forms).
If a community is using its block grant for more than one sub-project, parallel
implementation is an option, if sufficient capacity is present, since this will speed up overall
implementation, and enable completion of projects within the constraints defined by local
climate and altitude.
The Facilitating Partner will support the community during this process with regard to:
technical assistance on an as needed basis (e.g. procedures for procurement of goodsor contractors);
implementation (e.g. advice on implementation organization, and supervision ofworks and construction quality)
training on matters such as book-keeping, contracting, maintenance tasks etc.
D. Monitoring by the Community
The community wide assembly will agree on the methods and schedule of reporting to the
community (on financial and physical progress) by the Community Development Council
and the relevant Project Management Committees. The methods for information
dissemination should ensure that women are informed about project activities. The
community will also agree on key indicators to monitor joint decision making, project
progress, and transparency. Monitoring against these indicators will be reported in the
Community Progress Reporting Form used by the Facilitating Partners (Reporting Form 4a).
In the community, all records and accounts must be available for inspection by the members
of the community, the Facilitating Partner, and NSP. The arrangements to ensure
transparency shall include regular community wide information meetings, display of all
relevant information on implementation progress and expenditures on notice boards
accessible to the public, and/or announcements of project-related information atJumma
prayers.
E. Physical and Financial Progress Monitoring
The Facilitating Partner will be responsible for physical and financial progress monitoring on
a monthly basis (Reporting Form 6) with summary progress reports and on a quarterly basis
with more comprehensive status reporting (Reporting Forms 7 and 7a). These reports
NSP-II OperationalManual-21March04 Page 25 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
26/43
constitute an input to the overall quarterly progress reporting by NSP (Reporting Form 8).
The Facilitating Partner will report to NSP on process, achievement of implementation
benchmarks, and quality of works as defined in the Tripartite Agreement. Achievement of
implementation benchmarks will be tied to the release of funding to the community.
The NSP staff will perform sample audits of the support for the community carried out by the
Facilitating Partner regarding elections of Community Development Councils, preparation of
sub-project proposals that comply with NSP eligibility criteria, recommendations for release
of block grant instalments based on achievement of agreed milestones, and the adequacy and
realism of progress reporting (Reporting Form 5).
F. Sub-project Completion
A completion report will be prepared by the community and the Facilitating Partner
(Reporting Form 1). The completed project will be inspected by the NSP, and a Certificate of
Completion (Reporting Form 2) will be issued to the community provided the sub-project is
technically sound and that all funds received from NSP have been reconciled. NSP may
approve that any savings that are remaining may be allocated to be used by the community to
increase the scope of the community development plan during the current or following year.
III. FINANCING AND FUND-FLOW SYSTEM
A. Overall Fund-Flow Arrangements
The overall flow of funds to communities will be managed by the NSP based on the process
outlined below, which summarizes the previous chapters in this manual:
1. The Facilitating Partner provides a Community Profile (Disbursement Form 1) including
a preliminary assessment of the block grant entitlement of the community to the
provincial office of NSP/RRD/OC.
2. Elections for the Community Development Council are held, and the Facilitating Partnercertifies that the elections were held in accordance with NSP rules (Disbursement Form
2). The provincial NSP office (Oversight Consultant and MRRD staff) undertakes
sample verification checks.
3. After completion of Community Development Council elections and certification of
these, representatives of the council go to the provincial NSP office to undertake two
tasks:
a. Submit an application to the provincial NSP/RRD/OC office (Disbursement Form 3)
for registration of the Community Development Council (Disbursement Form 5).
NSP-II OperationalManual-21March04 Page 26 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
27/43
b. Submit a form authorizing four community representatives to withdraw block grantfunds on behalf of the Community Development Council (Disbursement Form 4).Where functioning bank branches exist in the provincial center, an application toopen a bank account is submitted (Disbursement Form 4a) together with anauthorization from the Community Development Council for nominated persons to
make withdrawals from the account (Disbursement Form 4b).
4. With support from the Facilitating Partner, the Community Development Council in
consultation with the community at large agrees on a Community Development Plan,
which constitutes a medium term development and investment plan for the community in
question (Disbursement Form 6). The Community Development Plan is submitted to the
provincial NSP/RRD/OC office. Each community development plan will include a list of
priority investment needs (i.e. one or more sub-projects) within the budget envelope
defined by the block grant, the contribution that the community is mobilizing, and funds
that can be accessed from other programs.
5. If required, NSP at the provincial and central level coordinates with relevant line
ministries, so that it is ensured that sub-project proposals for schools or clinics fit with
the sector plans of the concerned ministry, and that operating costs are budgeted by the
ministry in question. NSP assists the community to obtain verification regarding these
issues from the concerned line ministries, and communicates this information in writing
to the community in question.
6. With support from the Facilitating Partner, the Community Development Council in
consultation with the community at large develops one or more sub-project proposals
within the available funding envelope (block grant allocation, community contribution,
funding from other sources). The sub-project proposal(s) is submitted to the provincial
NSP office (Disbursement Form 7).
7. Each sub-project proposal will be appraised individually, but implementation and
funding of sub-projects can take place simultaneously, if the community has the capacity
to manage this. While an overall Tripartite Agreement (Disbursement Form 8) for the
community development plan (or the elements of this plan for which funding is
available) will be signed between the community, NSP, and the Facilitating Partner,
copies of the first page of Disbursement Form 7 (Sub-project approval request) will be
attached to the Tripartite Agreement. This will cover the specific plans and budgets for
each approved sub-project.
8. After the Tripartite Agreement has been signed the CDC requests the release of the first
installment by the NSP/RRD/OC. (Disbursement Form 9)
9. Funds for approved sub-project proposals will be channeled directly from the NSP to the
community based on an agreed installment system of financing. The nominated
community representatives will be accompanied by the Facilitating Partner to the
NSP-II OperationalManual-21March04 Page 27 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
28/43
provincial NSP office for (at least) the first block grant disbursement. The NSP office
will keep a copy of the community letter of authorization and the photos of the
nominated representatives for future verification. A minimum of three signatories are
required for withdrawal of funds.
10.The first block grant installment (maximum 50% of the block grant funding for a
particular sub-project) will be released. The installment will be released from the NSP at
central level to the community (CDC) using either the banking system, where this is
functioning, or a government registeredHawala. Where theHawalasystem operates at
the community level, the fund transfer may take place there to reduce security risks and
expedite disbursements to communities.
11.The second block grant installment will be released when the CDC certifies through the
FP that:
the agreed milestone as described in the sub-project proposal has been achieved;
the required community cost contribution has been provided;
the community at large has been regularly updated by the CommunityDevelopment Council about project progress and expenditures (e.g. meetings,notice board);
community procurement has been undertaken in compliance with NSP rules;
The installment has been requested of the NSP/RRD/OC through DisbursementForm 9.
12.The provincial NSP office (Oversight Consultant and RRD staff) undertakes sample
verification checks of achievement of milestones and implementation quality.
13.Upon completion of the sub-project, the same five requirements as outlined as condition
for the second installment will have to be fulfilled, and a sub-project completion report
(Reporting Form 1) including a simple financial statement will have to be submitted
before the third installment is released. Then the completion of the Sub-project will be
certified from the NSP/RRD/OC to the community (Reporting Form 2)
14.The provincial NSP office (Oversight Consultant and RRD staff) undertakes sampleverification checks of achievement of milestones and implementation quality.
B. Fund Transfer Mechanism
The Tripartite Agreement defines the schedule of disbursement installments on the basis of
an agreed plan of physical progress of a particular sub-project. Funds will be transferred
using a fixed price or lump-sum method of financing based on several installment (at least
three) per sub-project. The size of individual payments under each tranche (amounts) must
be determined based not only on the technical requirements of the sub-project, but also on
NSP-II OperationalManual-21March04 Page 28 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
29/43
security concerns at the community level. However, the first installment can not exceed 50%
of the sub-project costs.
Where local banks function at the provincial level, communities can maintain a checking
account and make withdrawals and payments as required. Where a banking system is not
functioning, and funds are transferred throughHawalaagents, the community can arrange
with the NSP that specific payments are made directly at the NSP provincial office to
suppliers and contractors in the presence of the community representatives. This would limit
the amount of cash that communities will have to transport, store, and handle. Likewise,
whereHawalaagents do not agree to operate under this arrangement, the transfer of block
grant funds may take place in the community provided theHawalasystem operates at this
level. This would also serve to avoid that provincial NSP/RRD/OC offices would have to
keep cash, would reduce security risks associated with transport of cash by community
representatives, and would expedite disbursements to communities, Where practiced, the
transaction would have to be witnessed and certified by the Facilitating Partner.
Unless there are exceptional circumstances, payment for implementation will be made in
three installments/tranches agreed between MRRD and the CDC on the basis of the funding
requirements of the sub-project in question (the first installment should not exceed 50% of
total sub-project costs). The first installment will be paid following signing of the Tripartite
Agreement, the second installment after achievement of agreed implementation outputs
(milestones), and the third installment by or after sub-project completion supported by a
financial statement. Examples of financial reporting forms at the community, provincial and
national levels, accompanied by explanatory text, are set out in Annex 2: NSP Accounting
Forms.
If a community is using its block grant for more than one sub-project, an assessment will be
made by NSP whether the projects can be funded and implemented in parallel or sequentially
(i.e. the first sub-project must be completed before funding for the next sub-project is
released). The criterion for parallel funding and implementation is that one of the sub-
projects must be identified by women and address their defined needs. In all other cases
where block grants are used for more than one sub-project, these will be financed
sequentially.
C. Tripartite Agreement
The Tripartite Agreement represents the contract between the NSP and the community and is
a complete statement of the obligations and responsibilities of the parties to the contract. (See
Disbursement Form 8). It includes the estimated amount that NSP has agreed to contribute
and the community contribution, and provides a detailed description of the key activities to
be undertaken by the different parties, as well as a time line of when activities are to becompleted. The financing agreement is signed by the community representatives and a
NSP-II OperationalManual-21March04 Page 29 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
30/43
representative of the NSP and the Facilitating Partner. Before the financing agreement is
signed, it must be explained to and understood by the community members. The Tripartite
Agreement forms the contract and the basis of payments to the community.
The agreement including Disbursement Form 7 which is part of the Tripartite Agreement
covers the following:
Scope of activities to be covered/time frame (Disbursement Form 7);
Amount of funding to be provided by NSP and terms and conditions forpayments (for lump-sum payments a set amount will be paid to the communityin tranches based on outputs);
Roles and responsibilities of all parties (the community, the Facilitating Partner,and NSP);
Estimated amount and timeline for community contributions;
NSPs (or representatives of MRRDs) right to inspect the site, work, materials,relevant records, accounts, and documents;
Simple procurement and disbursement plan; (Disbursement Form 7)
Operation and maintenance plan;
Clear specification of who owns the infrastructure after completion;
NSPs right to suspend or terminate the use of funds allocated to the sub-projectin case of negligence and/or mismanagement;
NSPs right to review whether possible environmental impacts have beenassessed and, where necessary, to assess the adequacy of mitigation measures
proposed;
Reporting requirements (financial/physical);
Attachments including technical designs and cost schedules.
D. Disbursement to Communities
The first instalment of funding will be paid to the community as soon as the Tripartite
Agreement based on the approved project work plan and budget is signed and funds are
requested (Disbursement Form 9). Subsequent instalments will be released when thecommunity and the Facilitating Partner confirms that the physical progress milestones have
been reached and community financial reports are in order (Disbursement Form 9).
The national level NSP office will undertake periodic field supervision audits on a sample
basis of the release of tranches to ensure that recommendations regarding new releases are
based on the required outputs and are made on a timely basis (Reporting Form 3).
The Da Afghanistan Bank is in the process of opening branches in all provinces in
Afghanistan and its branches will be used by NSP for Block Grants transfers to the extent
possible. Communities, represented by the CDC, are required to use the banking facilities for
NSP-II OperationalManual-21March04 Page 30 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
31/43
the Block Grant disbursements. The registration certificate issued by NSP/RRD/OC
(Disbursement Form 5) is accepted by the Bank for the opening of a bank account. NSO/OC
will transfer requested funds to the bank account of the CDC and enabling the CDC to use the
banking facilities.
Where banking facilities are not available NSP will use theHawalasystem.
To be acceptable, a money-exchange dealer orHawalathat is selected to transfer funds into
and around Afghanistan must be financially sound and meet the following criteria: The
Hawalaused to transfer funds to the provincial level must be:
Registered with the Central Bank (Da Afghanistan Bank);
Recognized by the Exchange Dealers Association;
Maintain a physical presence at the Sari Shahzada in Kabul;
Authorized to deal in foreign currencies;
Able to issue promptly a detailed monthly statement of funds transfer transactionsrelated to NSP;
Work with other reputable organizations in Kabul (references), having established asatisfactory domestic and international correspondent funds transfer network; and
Charge reasonable fees for its services.
For eachHawalatransaction, good practice requires the following procedural guidelines to
be observed:
Obtain a written document confirming the amount to be transferred, currency,expected payment date, funds transfer destination and transaction fee;
Establish transaction monetary limits based on capacity of theHawala, securitysituation at origin and destination of funds, and community capacity to maintain cashholdings on their premises;
Pay theHawalaafter payment and acknowledgement of funds receipt verbally and inwriting (fax or e-mail) by the intended recipient;
Conduct all financial transactions, apart from predetermined small transactions in asecure location, preferably on the FPs or community development councils
premises; and
Restrict transfer of funds to a specific community to only oneHawalafor purposes ofbetter control and audit trail, although aHawalamay be permitted to service morethan one community.
Funds will be transferred from the NSP national office through aHawalafor distribution to
the nominated community representatives at the NSP provincial level office. The fund
transfer to the nominated community representatives will take place in the presence of the
NSP provincial staff. To minimize the security risk of community members transporting,
storing and managing large amount of cash, arrangements can be made, if the community sowishes, where installments are disbursed in smaller amounts related to specific expenditures.
NSP-II OperationalManual-21March04 Page 31 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
32/43
Moreover, some payments such as those for suppliers or contractors can be made at the NSP
office in the presence of the nominated community representatives authorized to handle
procurement and funds.
E. Fund Management at the Community Level
The community project management committee will be responsible for procurement of all
goods and services during the course of sub-project implementation. Communities will
determine the best method of payment for suppliers and contractors. Communities will be
trained in simplified procurement and disbursement procedures by the Facilitating Partner
based on guidelines developed by NSP. A Project Management Committee must call regular
community meetings to present its financial and physical progress reports to the community,
and communicate this information by other means as well (e.g. an information board, or
announcements in the mosque).
The community must keep accurate financial accounts and report monthly to the Facilitating
Partner. The financial report provides details of funds received by the community from NSP,
expenditures incurred by category and the balance of funds. All supporting documents must
be kept at the community level, and be available to the Facilitating Partner, NSP, and other
parties (e.g. other NSP donors or external review and evaluation consultants). Cash funds
should be kept in a secure location with restricted access by a person nominated as
responsible by the Community Development Council.
During implementation, the community project management committee will undertake the
following activities:
Maintain a sub-project cash book to account for all expenditures by type.
Maintain receipts, labor registers and other documentation such that all expenses havecorresponding documentary evidence.
Maintain a cash box and a petty cash book for cash expenditures.
Submit periodic reports to the community on the current financial and physical statusof the sub-project through community meetings, notice boards or other agreed means.
Maintain a stock register to record materials kept by the community (for more thanone or two days) before use.
Maintain a community contribution register to record any contribution (cash, labor,materials, etc.) from the community in the course of sub-project implementation.
Open and work with a checking account, check book, and bank statements, if andwhere the branch banking system is functioning.
The project management committee should have a written record of all expenditures to back
up the cash book and petty cash book. These may be in the form of receipts, labor registers,
cash receipts, or others.
NSP-II OperationalManual-21March04 Page 32 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
33/43
F. Financial Reporting by Facilitating Partners
For presentation purposes, the roles, responsibilities, expected outputs and performance
against outputs are discussed in Chapter II, Section C. The key financial reporting
formats/forms submitted by the Facilitating Partners to the NSP are contained in Reporting
Forms 7 and 7a.
Both Facilitating Partners and the Oversight Consultant (i) shall keep accurate and systematic
accounts and records in respect of their use of funds provided under their contract, (ii) shall
maintain records pertaining to the approved sub-project documents and contracts, and to
approval of subsequent installments to the communities based on assessment of satisfactory
output delivery, (iii) shall permit MRRD or its designated representative periodically, and up
to one year from the expiration or termination of their contracts, to inspect these and make
copies thereof as well as to have them audited by auditors appointed by MRRD; and (iv) shall
permit the IDA to inspect the accounts and records relating to the performance of the
facilitating partners, and to have them audited by auditors appointed by the IDA, if so
required by IDA.
IV. COMMUNITY PROCUREMENT
Because funds for implementation of the community sub-projects are disbursed directly to the
community, the project management committee is primarily responsible for procuring
materials, transport, and labor. Communities may set up rotational procurement scheduleswithin the project management committee to ensure that no cliques form and that the
committee adheres to procurement procedures. Communities should also be encouraged to
pay contractors and suppliers in the provincial centers as soon as they receive the funds.
Communities may also useHawalasto pay contractors and suppliers. This would minimize
security issues arising from communities carrying large amounts of money.
A simple procurement plan for the overall sub-project should be developed by the
community. The plan must take into account who will purchase goods, what will be
purchased, and how. The plan should be shared with community representatives who willoversee purchases made by the project management committee as well as the community at
large.
To assist communities with procurement as well as to monitor the economy of goods
procured at the local level, the NSP will develop and maintain a unit cost database. The
database will include costs of most types of items purchased at the community level. The
database will be developed over time (using prices proposed in community budgets as well as
independent research) and updated regularly. .
NSP-II OperationalManual-21March04 Page 33 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
34/43
A. Procurement of Goods/Materials
All materials required for the sub-project are detailed in the bill of quantities attached to the
community proposal. During sub-project implementation, the community financial records
must clearly indicate the exact materials purchased. The following methods should be used
by communities for purchasing materials:
Single Direct Source / Direct purchase (costs which are within a standard price list and/or
less than US$100 equivalent): Procurement can be made directly by calling for a quotation
from only one supplier if the purchase value is less than US $ 100, and the accepted price is
below the price mentioned in the standard price list effective at the time of purchase.
Competitive Shopping / Local shopping(when the amount to be paid is higher than the
amount included in the standard price list and for amounts equivalent or higher than US$100
and below US$5,000 equivalent): At least three quotations will be obtained from suppliersand the best buy is selected. Factors such as quality, availability, local taxes, and
transportation costs must be taken into account. All quotations received as a response must
be maintained in the community files. This method will also be used for purchasing materials
that communities cannot find within the standard price list. Whether prices are reasonable
will be ascertained by comparing prices with the standard price list effective at the time of
purchase.
Local Competitive Bidding: Goods or materials estimated to cost $5,000 equivalent or
more must be procured through competitive bidding, advertised locally or nationally. Simplebidding documents shall be prepared incorporating the technical description/specifications
and quantity of the goods, as well as desired delivery time and place. A bid validity period of
30 days from the date of submission of bids shall be required in the bidding documents. The
invitation for bids shall be advertised through local methods [e.g., fliers, community
meetings, duringJummaprayers, local newspapers or radio, advertisements hung in public
places etc.]. A responsive bid would be the one that would offer goods/materials in
compliance with the technical descriptions/specifications, with required quantity and within
the desired delivery period. The bid price of only the responsive bids would be compared
and the bidder offering the best value shall be awarded the contract. The contract must be
awarded within thirty (30) days from the receipt of the bids. All bids and their comparison
report must be maintained in the community files. (Proc Form 1-2)
B. Procurement of Works
Labor: the community contribution will in most cases comprise voluntary labor.
However, where the unskilled labor requirement for a particular project exceeds the amount
of labor that the community is able or willing to contribute free of cost, arrangements are
required so that the project pays for some of the required labor at or below the market rate
NSP-II OperationalManual-21March04 Page 34 of 43 Rev. Date: 20. March 2004
8/10/2019 National Solidarity Program Operational Manual (March 2004)
35/43
(around US$-- per day). The needs for skilled labor such as foremen, carpenters, bricklayers,
painters, electricians, and plumbers will be estimated before the start of sub-project
implementation and included in the sub-project financing agreement. The NSP will provide
standard pay rates for labor and these scales should not be exceeded. Communities may
decide whether to hire skilled labor for their sub-project directly or to hire a contractor who in
turn will hire the skilled labor. Regardless of who is hiring the skilled labor, preference must
be given first to residents of the sub-project community.
Contractors: In some sub-projects, the community will hire construction foremen and
skilled laborers themselves. If part or all of a sub-project is beyond the capacity of the
community to manage, a contractor may be hired to manage the work. For a works contract
below US$5,000, the contractor may be selected upon inviting quotations from at least three
local contractors.
Contracts equivalent to US$5,000 or more will be procured through competitive bidding,
advertised locally (tendering). A simple bidding document (Proc Forms 2-0) shall be
prepared incorporating the description of the works, simple technical specifications/drawings,
Bill of Quantity, desired delivery time, and the minimum experience of the contractor. The
participation of the community should be clearly defined and not be part of the contract. A
bid validity period of 30 days from the date of submission of bids shall be required in the
bidding documents. The invitation for bids shall be advertised through local methods [e.g.,
fliers, community meetings, duringJummaprayers, local newspapers or radio,
advertisements hung in public places etc.].
A responsive bid would be the one that would offer to complete the works as per the
descriptions/specifications, within the desired delivery period and having the required
minimum experience as contractor. Prior to awarding the contract, interviews may be
conducted by the project management committee together with community representatives
and, if necessary, a representative of the Facilitating Partner. Contract would be awarded to
the contractor, offering a responsive bid with the best value, and who has been found
technically qualified upon the interview by the project management committee. The contract
must be awarded wi