8
National Highways leading to Chardham (A)Yamnotri 1. NH -123 (Herbertpur to Barkot Bend) km. 0.00 to 111.35 = 111.350 km. (PWD) 2. NH-94 (Dharasu to Phoolchatti) km. 122.00 to 217.00 = 95.00 km. (PWD) (B) Badrinath 1. NH -58 (Rishikesh to Rudraprayag) km. 228.00 to 368.00 = 140.00 km. (PWD) 2. NH-58 (Rudraprayag to Mana) km. 368.00 to 532.00 = 264.00 km. (BRO) (C) Kedarnath 1. NH -109(Rudraprayag to Gaurikund) km. 0.00 to 76.00 = 76.00 km. (PWD) (D) Gangotri 1. NH -94 (Rishikesh to Dharasu) km. 0.00 to 141.40 = 141.40 km. (BRO) 2. NH-108 (Dharasu to Gangotri) km. 0.00 to 124.00 = 124.00 km. (BRO)

National Highways Leading to Chardham

Embed Size (px)

DESCRIPTION

National Highways

Citation preview

  • National Highways leading to ChardhamYamnotri

    NH -123 (Herbertpur to Barkot Bend) km. 0.00 to 111.35 = 111.350 km. (PWD)2. NH-94 (Dharasu to Phoolchatti) km. 122.00 to 217.00 = 95.00 km. (PWD)

    (B) Badrinath

    NH -58 (Rishikesh to Rudraprayag) km. 228.00 to 368.00 = 140.00 km. (PWD)2. NH-58 (Rudraprayag to Mana) km. 368.00 to 532.00 = 264.00 km. (BRO)

    (C) Kedarnath

    NH -109(Rudraprayag to Gaurikund) km. 0.00 to 76.00 = 76.00 km. (PWD)

    (D) Gangotri

    NH -94 (Rishikesh to Dharasu) km. 0.00 to 141.40 = 141.40 km. (BRO)2. NH-108 (Dharasu to Gangotri) km. 0.00 to 124.00 = 124.00 km. (BRO)

  • National Highways leading to ChardhamNH- 123 (Yamnotri)

    Km. 0.00 60.00 - Surface SatisfactoryKm. 60.00 65.00 - 2-Lane widening in progress Single lane resurfacing will be completed upto 20.04.2015

    Km. 65.00 84.00- Surface satisfactoryKm. 84.00 97.00- Patch repair in progress will be completed upto 20.04.15

    Km. 97.00 101.00 - Surface satisfactoryKm. 101.00 107.00- 2-lane widening in progress Single lane resurfacing will be completed upto 20.04.2015

    Km. 107.00 111.35 - Surface satisfactory

  • National Highways leading to Chardham(B) NH- 94 (Yamnotri)

    Km. 122.00 176.00 - Surface Satisfactory. Patch work in progress.

    Km. 176.00 182.00 - Surface damaged. Resurfacing in single lane will be completed upto 20.04.15

    Km. 182.00 211.00- Patch repair and resurfacing in progress will be completed upto 20.04.2015

    Km. 84.00 97.00- Patch repair in progress will be completed upto 20.04.15

    Km. 211.00 217.00 - For resurfacing WBM work in progress. Resurfacing will be completed upto 20.04.2015

  • National Highways leading to ChardhamBadrinath

    (A) NH-58 (Rishikesh to Rudraprayag)

    Km. 228.00 250.00 - Resurfacing in progress. 8.00 km. completed. - Will be completed upto 15.04.2015

    Km. 250.00 268.00 - Patch work completed. Surface satisfactory. Strengthening work sanctioned by Ministry will be completed upto 30.05.2015

    Km. 268.00 300.00- Resurfacing in progress. 14 km. completed, will be completed upto 15.04.2015

    Km. 300.00 317.00- Two laning formation cutting in progress by BRO. Single lane surfacing work will be completed by PWD upto 20.04.2015

    Km. 317.00 364.00 - Surface satisfactory. Patch work completed.

    Km. 364.00 368.00- Resurfacing by BRO will be completed upto 15.04.2015

  • National Highways leading to ChardhamKedarnath

    NH-109 (km. 0.00 to 76.00 (Rudraprayag - Gaurikund)

    - Surface satisfactory. Total 8 points measuring 1.700 km. total length required resurfacing. WBM work complete. Black topping will be completed upto 15.04.2015.

    -Tender for Rs. 47.65 Cr. Prptection work will be received on 16.04.2015

  • National Highways leading to ChardhamBadrinath (BRO)

    NH-58 (Rudraprayag - Mana)

    - Riding surface in following land slide stretches requiring improvement.1. Nand Prayag2. Maithana3. Birahi4. Pagal Nala5. Patal Ganga6. Helong7. Baldora8. Lambagar

  • National Highways leading to ChardhamGangotri (BRO)

    NH-94 (Rishikesh to Dharasu) - Surface satisfactory

    NH-108 (Dharasu to Gangotri)

    - PWD Uttarkashi started work for resurfacing in following reaches. 1. Nalupani, Dunda, Sigoti, Banderkot, Matli and and Badethi chungi to Gangori in 13.20 km. length 2. Bhukki, Gangnani, & Sukki top in 8.100 km. length - BRO is working in its sanctioned stretches