84
NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES IN DISASTER PRONE AREAS IN GHANA COMPILED BY JOHN TETTEY CONSULTANT JULY, 2011 1

NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES IN DISASTER PRONE AREAS IN GHANA

COMPILED BY

JOHN TETTEY

CONSULTANT

JULY, 2011

1

Page 2: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

TABLE OF CONTENTS

PREFACE

A. INTRODUCTION B. SITE

3.0 SITE INVESTIGATION AND PREPARATION

3.1 Site selection

3.2 Ground Investigation

3.3 Site preparation

C. SUBSTRUCTURE

4.0 FOUNDATIONS

4.1 General

4.2 Classification of foundations

5.0 EXCAVATION AND EARTHWORKS

5.1 Setting-out of foundation

5.2 Excavation

5.3 Backfill

2

Page 3: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

5.4 Hardcore filling

D MATERIALS

6.0 Formwork 6.1 Materials 6.2 Beam formwork 6.3 Wall and column formwork 6.4 Stricking time for insitu works 6.5 Boardmarked formwork 6.6 Plywoodmarked formwork 6.7 Sawn formwork 6.8 Inserts 6.9 Precast concrete formwork

7.0 Cement 7.1 Specifications 7.2 Types 7.3 Storage 7.4 Clay pozzolana

8.0 Aggregates 8.1 Coarse aggregate 8.2 Fine aggregate 8.3 Alkali aggregate 8.4 Storage aggregate

9.0 Water 9.1 Water/cement ratio

3

Page 4: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

10.0 Concrete

10.1 Classification of concrete mixes

10.2 Designed mix

10.3 Prescribed mix

10.4 Durability

10.5 Basic Tools for concrete works

10.6 Concrete trial mixes

10.7 Transportation of concrete

10.8 Placing concrete

11.0 Steel for reinforced concrete

11.1 Recommended types

11.2 Sizes of Reinforcements

11.3 Placing Reinforcements

11.3 Bending Reinforcements 11.4 Placing Reinforcements 11.5 Cover of concrete

4

Page 5: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

12.0 Masonry (Sandcrete Blocks , Bricks ,landcrete or stabilized earth)

12.1 Scope

12.2 Required reinforcements

12.3 Masonry units

12.4 Testing of Blocks 12.5 Blocklaying 12.6 Burnt Clay Bricks

13.0 Mortar

13.1 Lime

13.2 Mortar Mixes

13.3 Mortar Joints

14.0 Waterproofing and dampproofing

14.1 Waterproofing of walls

14.2 Dampproofing of walls

E. SUPERSTRUCTURE

5

Page 6: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

15.0 MASONRY JOINTS AND SUPPORTS

15.1 Solid Masonry Joints

15.2 Hollow Masonry Joints

15.3 Contraction and expansion joints

15.4 Masonry Support

15.5 Wall Thickness and Height

15.6 Masonry Veneer

15.7 Columns

15.8 Lintel

16.0 STAIRCASES 16.1 Private Stairways 16.2 Common Stairways 16.3 Landings 16.4 Insitu Concrete Steps 16.5 Single Steps supported from a Central Loadbearing Column 17.0 ROOFING 17.1 Roof Protection 17.2 Roofing Nails 17.3 Roofing Staples 17.4 Roof Slope 17.5 Flashing at Intersections

6

Page 7: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

17.6 Types of Roofing 17.7 Trussed Rafters 17.8 Roof Ridges 17.9 Corrugated Sheets 17.10 Flat Pan Tile Roofing 17.11 Protection of roof against windstorm 18.0 CARPENTRY AND JOINERY 18.1 Timber 18.2 Nails and Screws 18.3 Ceiling 18.4 Doors 18.5 Windows F. FINISHES 19.0 WALL AND FLOOR FINISHES 19.1 Wall Tiles 19.2 Flooring 20.0 IRONMONGERY 20.1 Screws 20.2 Locks 20.3 Hinges 20.4 Welding 21.0 PLUMBING INSTALLATION 21.1 Portable Water 21.2 Piping Facilities 21.3 Sewerage and Waste Disposal 21.4 Soil Pipes 22.0 ELECTRICAL INSTALLATION 22.1 Distribution 22.2 Fuses 22.3 Circuit Breaks

7

Page 8: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

22.4 Earthing 22.5 Cables 22.6 Lighting Outlets 22.7 Emergency lighting 22.8 Lighting arrester 22.9 Fire safety 23.0 PAINTING 23.1 Primers 23.2 Mixing 23.3 Preparation for Commencement of Work 23.4 Protection of wet painted surfaces G. EXTERNAL WORKS 24.0 DRAINAGE 24.1 Scope 24.2 Installation 24.3 Drainage disposal 24.4 Surface drainage 25.0 RETAINING WALLS AND REVETMENTS 25.1 Types 25.2 Temporal structures 25.3 Permanent structures 25.4 Revertments 25.5 Gravity walls 25.6 Flexible walls 26.0 FENCES AND HEDGES 26.1 Common fencing materials 26.2 Concrete Fence 26.3 Steel Fence 26.4 Hedges

8

Page 9: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

1.0 PREFACE The National Disaster Management Organization, (NADMO) was established by Act

517 of 1996 to manage disasters and similar emergencies in Ghana. The Act inter alia,

makes NADMO responsible for the implementation of Government policy on Disaster

Prevention, Disaster Risk Reduction and Climate Change Management as well as the

implementation of National, Regional and District Disaster Management Plans.

It is known worldwide, that most natural and man-made disasters are exacerbated or

mitigated by the nature of houses and structures in affected communities and NADMO,

as far back as 1998 recognized the need for hazard resistant buildings, especially

earthquake and flood resistant structures in earthquake and flood prone areas in the

country. NADMO also recognizes the need for building regulations and codes that

adequately incorporate standards for the design and construction of buildings in disaster

prone areas.

In Ghana currently, there is serious indiscipline in the building industry resulting from: :

Inadequate or non-enforcement of existing building regulations and by laws Lack of building inspectors

Decline in the use of the services of professionals in the building industry and

most dwelling houses are built with little or no professional architectural or

engineering advice. Rate of development out-pacing the rate of plan preparation Building plots are sold and bought without reference to planning schemes.

Many buildings are sited in hazardous areas such as flood plains and on expansive soils.

This has made most buildings vulnerable to disasters especially earthquakes, fires and

floods. Accessibility to these buildings is poor and in emergencies, response agencies

are not able to operate efficiently resulting in the loss of lives and property.

NADMO, in collaboration with various stake holders has initiated action to ensure that

the National Building Regulations are revised and updated and National Building Codes

and standards adapted to regulate the building industry. A draft Building Code prepared by the Building and Road Research Institute (BRRI)

since 1990 is to be adopted as a national document and the revision of the National

Building Regulations is progressing.

In the mean time NADMO has found it appropriate to manage the situation by coming out with a National Building Guide (NBG) to equip artisans and developers with basic

9

Page 10: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

knowledge for the construction of lightly loaded structures in hazard prone areas of Ghana as part of its disaster risk reduction strategies. This guide is not meant to replace the National Building Regulations or Building Codes

when they are available. It is also not a substitute for the services of trained

professionals like Architects and Engineers. It is always safer to have trained

professionals design and construct buildings. NADMO recommends that the services of

building professionals are used as much as possible. However it has been observed that a very large number of people do not use the

services of professionals but build with the help of artisans only. The NBG is meant to

provide guidance for developers when professional help is not readily available.

NADMO wishes to express its gratitude to the United Nations Development Programme

(UNDP) and the various stake holders for their assistance in the preparation of this

building guide.

10

Page 11: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

INTRODUCTION

In recent times, there has been a trend towards increasing occurrence of natural and manmade disasters that may be associated with other environmental issues, such as:

Global climate change. Inappropriate location of structures near natural hazard zones. Increased population and population density. Growth in natural hazard zones. Urban growth. Inadequate or non-enforcement of building codes and regulations.

The consequences have increased human suffering, loss of life, and economic losses.

In response, the National Disaster Management Organisation (NADMO) was

established by an Act of Parliament (Act 517) dated September 1996 to manage

disasters and similar emergencies in Ghana.

NADMO recognises that building safer houses that could better withstand the

devastating effects of disasters contributes to disaster prevention and with the

assistance of the UNDP prepared this National Building Guide for the use of artisans

and developers in the construction of lightly loaded structures

The aim of this guide is to equip artisans and developers with basic knowledge for the construction of lightly loaded structures in hazard prone areas of Ghana.

The building guide applies to buildings of two storey’s or less in build building area not exceeding

220m2and which are intended to be used for residential business, mercantile and medium and low hazard industrial occupancy.

The National Building Guide gives guidance on: i. Site investigation ii. Selection of Building Materials iii. Construction of the Substructure and Superstructure iv. Finishes and External Works.

DISASTERS AND HAZARDS

Disasters that may occur in Ghana have been classified into six groups. i. Pest and Insect Infestation ii. Disease Epidemics iii. Fires iv. Hydro –Metrological

11

Page 12: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

v. Geological vi. Man-Made

Specific Hazards that need attention in building design and construction are listed in Table 1. Table 1: Hazard Types and Specific area of Occurrence in Ghana

DISASTER GROUP HAZARD TYPE SPECIFIC AREAS OF

OCCURENCE IN GHANA

Pest and Insect Termites Nationwide

Infestation

Disease Epidemics Cerebro-Spinal Meningitis Upper West; Upper East; (CSM) Northern; Volta and Brong Ahafo

Regions. Fires Bush, Domestic and Nationwide

Industrial Fires

Hydro –Metrological Rainfall-Runoff Nationwide

Hydro –Metrological River Flooding River Basins (Figure 4: Floods

Hazard Map)

Hydro –Metrological Lagoon Flooding Coastal Zones

Hydro –Metrological Tidal Flooding Coastal Zones

Hydro –Metrological Man-Made Flooding Nationwide (Hazard Mapping

(blocking of river courses; Needed) dam burst etc)

Hydro –Metrological Rain/Wind Storms Nationwide

Earthquakes Southern Ghana (Figure 1: Seismic Hazard Map)

Geological Tsunami Coastal Zones

Geological Expansive Soils Nationwide (Hazard Mapping

Needed) Geological Soil Erosion Nationwide (Hazard Mapping

Needed) Geological Coastal erosion Coastal Zones (Figure 2: Coastal

Erosion Hazard Map)

Geological Land Slide Hilly Areas of Ghana (Figure 3: Landslide Map) Geological Radon Gas Emissions Nationwide (Hazard Mapping

Needed) Man-Made Collapse of Buildings Nationwide

SITE INVESTIGATION AND PREPARATION Before a site is used for a building project, it must be investigated. Site investigation here refers to processes to:

i. Determine whether the site is earmarked or zoned for the proposed project

by the local planning authority. ii. Obtain data required for the design of the foundation of buildings.

12

Page 13: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

iii. Determine whether the site is suitable for building or the project. iv. Identify rock outcrop, landfills, vegetation, water bodies, existing underground

services etc. v. Identify the types of Hazards that exist in the area.

Avoidance is the least expensive and most logical strategy to reduce vulnerability to floods, coastal erosion, earthquakes and landslides when selecting a building site. The simplest approach to avoidance involves urban and land-use planning. Community

decision-makers should enact public policies and take actions that avoid building in

hazardous areas.

In preparing the site the top soil and vegetative matter shall be removed. Where there are termites, an ant anti-termite treatment should be applied.

SPECIAL RECOMMENDATIONS Ordinary portland cement, sand, gravel, crushed rock, reinforcement steel bars, wood,

metal roofing sheets and concrete roofing tiles are the predominant building materials

used in Ghana today.

Use of pozzolana cement, burnt brick, landcrete or stabilized earth and other local building materials that meet GSB specification should be encouraged.

Correct selection and mixing of materials are important in the construction of hazard

resistant buildings. Concrete mixes and water/cement ratio for all concrete mixes, shall

be as prescribed and the right sizes of steel must be used at all times. The use of

white core plywood should be discouraged and red core plywood used.

In Areas where a naked fire is predominant, it is not recommended to use timber for

internal and external walls. In earthquake prone areas, special attention must be

given to foundation and superstructure design and construction. Roofs need to be

wind/rain storm resistant and concrete foundations are better in flood prone areas

All electrical materials used must be approved by Ghana Standard Board or other

competent authority and electrical installations must be carried out by qualified

professionals. All buildings must have fire detection, fire alarm and fire fighting devices and be protected with a well grounded lightning arrester. All portable L.P.G bottles shall be located outside the building when in use.

The guide when used properly will make Ghana’

13

Page 14: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIGURE 1: SEISMIC HAZARD MAP OF GHANA

14

Page 15: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIGURE 2: COASTAL EROSION HAZARD MAP OF GHANA

15

Page 16: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIGURE 3: LANDSLIDE HAZARD MAP OF GHANA

16

Page 17: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIGURE 4: FLOODS HAZARD MAP OF GHANA

17

Page 18: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

B. SITE

3.0 SITE INVESTIGATION AND PREPARATION

Site investigation is the process by which geological, geotechnical and other relevant

information which might affect the construction or the performance of a civil engineering

or building project is acquired .Site investigation should be undertaken in order to obtain

data required for an Intelligent design of the foundation of buildings. The following activities are to be carriedout to prepare the site for construction:

3.1 Site selection: i) Zoning : determine whether the site is earmarked or zoned

for the proposed project. In an on unplanned area or community, seek an expert advice to determine:

ii) Suitability: Determine whether whether the site is suitable for building. iii) Surface characteristics: For the identification of surface characteristics, e.g. rock

outcrop, landfills etc. i iv.) Vegetation: identification vegetation types and species of existing trees. v) Water bodies: Identify surface water flowing on or around the site . vi) Existing underground services: Determine the location of water supply and drainage

pipes, electrical telephone and other cables. vii) Existing structures: Determine closeness of adjacent structures to site and closeness of

their foundations to the proposed building.

3.2 Ground Investigation: In the event that the site is in doubt, ground investigation is carriedout.This must be done by an expert:

a) To determine subsoil characteristics. b) To determine the load bearing capacity of the soil at various depths. c) To determine the order of settlement which is likely to occur with the established safe

load bearing pressure on the soil at various depths or with the applied pressure where

this is lower. d) To decide on the suitable construction method e) To determine the groundwater level its seasonal fluctuation . f) To identify on any harmful chemicals present in the soil or in the groundwater.

18

Page 19: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

3.2.1 Some Methods of Soil Investigations: The two methods of soil investigations are Trial pits and by Boring

3.2.2 Boring Method: This system of establishing the bearing capacity of soil is useful in areas

where it is difficult to coduct proper laboratory tests. This employs mechanical means of

of excavation of depths not exceeding 3m.

3.2.3 Trial Pit Method: Involves the excavation of shallow pits covering small planned areas, about 1mx1m

3.2.4 Types of ground: Rocks, Gravels, Laterite, Sands, soil, clays, fill.

Rocks: They are normally excellent foundation materials with high load bearing properties and negligible settlement under load.

Gravel: Are deposited loosely and can easily be removed by shovel: 50mm diameter stakes can be driven without trouble.

Literite: Has good load bearing properties. Sands: They are compact and require a pick for excavation.

Silt: Are soft soils, early moulded with fingers, or formwork.

Clays: Can be soft or stiff, hard, brittle and cohesive.

Fill: Can be composed of miscellaneous materials e.g. Mineral waste, rubble, organic waste etc. Hard pan: Well cemented gravel silty sand.

Bearing capacity: Bearing capacity of a soil is the ability of the soil to carry a load.

3.3 Site Preparation

19

Page 20: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

3.3.1 Site Clearing: The top soil and vegetable matter in all unexcavated areas for the proposed building shall be removed.

3,3.2 Antitermite treatment: Where there are termites an antitermite treatment should be

applied as follows:

(i) All termite rests on the site shall be opened up, the Queen extracted and destroyed.

(ii) The rests shall be broken open at the top and a approved chemical applied.

(iii) 3 days after treatment, the rest and the surroundings shall be totally excavated

300mm in each direction clear of the fungus gardens and filled with approved materials.

(iv) All termite runways should be traced and treated until all termite life is

exterminated.

20

Page 21: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

C. SUBSTRUCTURE

4.0 FOUNDATIONS

The foundation of a structure is defined as that part of the structure with direct contact

with direct contact with the ground and which transmits the load of the structure to the

ground.

4.1 General

A satisfactory foundation must meet three (3) technical requirements:

i) It must be placed at an adequate depth to prevent heave undermining by scour or damage from construction nearby.

ii) It must be safe against breaking into the ground. iii) It must not settle enough to disfigure or damage the structure.

4.2 Classification of Foundations

Foundations can be classified as deep foundations (caissons and piles) or shallow

foundation (strip, pad, raft/mat). For the purposes of this building guide it is

recommended to use shallow foundations. 4.2.1 Strip foundation :Strip foundation consists of continuous strip of mass concrete or other

material like stones or bricks which rests on the soil at depth and width depending on the

bearing capacity and type of soil. This is a common foundation used for load bearing wall

structures on good and average bearing soils. Strips may also be designed to span on cantilever

or soft sports in the ground.

Strip foundatios are used:

21

Page 22: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

i) Under walls, pilasters, columns, piers and chimneys that bear on soil or rock.

ii) If the foundations of a building are constructed as strip foundations of plain concrete

situated centrally under the walls, the strip foundation shall rest on undisturbed soil or rock. There shall not be a wide variation in the type of subsoil within the loaded area and no weaker type of soil below. The soil on which the foundations rest within such a depth as may impair the stability of the structure.

4.2.2 Footing Width: The width of the strip foundations shall be determined by the site conditions, the type of soil and the size of building as shown on table 4A.

4.2.3 Footing Thickness: The thickness of strip foundations shall not be less than its projection

from the base of the wall or footing and shall in no case be less than 150mm.

4.2.4 Footings laid at more than one level: Where the strip foundations are laid at more than

one level at each change of level the higher foundations shall extend over and unite with the lower foundations for a distance not less than the thickness of the foundations and in no case less than 300mm.

4.2.5 Pier, Buttress or Chimney forming part of a Wall: Where there is a pier buttress or

chimney forming part of a wall, the foundations shall project beyond the pier, buttress or chimney on all sides to at least the same extent as they project beyond the wall.

4.2.6 Pad Foundation: Pad foundation is usually square , rectangular near or circular. Pad

foundation normally support columns and piers.

4.2.7 Raft/Mat Foundation: Raft foundation consist of a continuous reinforced concrete slab

under the whole building taking up all the downward loads and distributing them over a

large enough area to avoid overstressing the soil beyond its bearing capacity. It is

recommended to be used at places where the soil have weak load bearing properties .

Raft foundations are appropriate if the sum of the individual footing base areas

exceeds about one-half of the total foundation area, if the subsurface strata contains

cavities or compressible lenses difficult to define, if resistance to hydrostatic uplift is

required.

4.2.8 Piled Foundation: Piled foundations are used in areas where settlement is greater than

acceptable or unpredictable, but where load bearing soil is formal under the poorer soil

at a depth where the use of pile would be economical.

Where pile type foundations are used, piles shall be designed to support the applied loads from the superstructure in conformance with good engineering practice.

Where piles are used as foundation system in a building of a storey in building height, the piles shall be installed to support the principal framing members and shall be spaced

22

Page 23: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

not more than 3.66mm apart along the framing, unless the piles and their footings are

designed for larger spacings. The height of such piles shall not exceed 3 times their least

bare dimension at the base of the pile. Where sandcrete block piles are used, and when

the width or the building is 4.27m or less they shall be laid with their longest dimension

at right angles to the longest dimension of the building.

TABLE 4A

TYPES OF SOILS

Condition Type of Field Test Minimum width in millimetres

Subsoil Applicable Single storey Two storey

I

Rock Not Requires at In each case equal to the width

inferior to least a

sandstone pneumatic or

or other

limestone mechanically

operated pick

for excavation

II

Gravel Compact Requires pick 250 - 400 500 - 650

Sand Compact for excavation,

wooden peg

50mm square

in cross-

section hard to

drive beyond

150mm

III Cannot be

Clay Stiff moulded with 250 - 400 500 - 650

Sandy Clay Stiff fingers and

requires a pick

or pneumatic

or

mechanically

operated

spade for its

removal

IV Can be

23

Page 24: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Clay Firm moulded by 250 - 450 600 - 850

Sandy Clay Firm substantial

pressure with

fingers and can

be excavated

with graft and

spade

V Can be

Sand Loose excavated with

Silty Sand Loose spade.

Clayey Sand Loose Wooden peg

50mm square 400 - 600 To be caculated

in cross-

section can be

easily driven

VII

Silt Soft Fairly early 450 - 650 To be calculated

Clay Soft moulded in the

Sandy Clay Soft fingers and

Silty Clay Soft readily

excavated

VII

Silt Very soft Natural sample 600 - 850 To be calculate

Clay Very soft in rainy season

Sandy Clay Very soft exudes

Silty Clay Very soft between

fingers when

squeezed in

frost

24

Page 25: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 5: STRIP AND PAD FOUNDATIONS

A. LIGHLY –LOADED SHALLOW STRIP FOUNDATION EXCAVATED BY HAUG OF THE SITATING A FAIRLY WIDE TRENCH, ESPECIALLY IN LOOSE SOILS DEPTY OF SHOULD BE MINIMUM 150MM, OUT NOT LESS THAN

B. LIGHTLY –LOADED DEEP AND NARROW STRIP FOUNDATION

IN CLAY, MECHANICALLY EXCAVATED, DEPTY OF STRIP ACCORDING TO AND END BEARING.

STRIP FOUNDATIONS C. STRIP FOUNDATION WITH ADDITIONAL 75mm THICK SLIDING

IN LOOSE SOIL.REINFORCED CONCRETE STRIP SHUTTERED STRENGTH A CONCRETE T-BEAM IS SUGGESTED.

POSSIBLE GROUND BEAM

PAD CAN BE SHAPED AS SHOWN BY DOTTED LINE BUT IT IS RARELY ECONOMIC DO SO FOR SMALL BUILDINGS

SECTION

THIS AREA IS SUBJECT TO UPWARD REACTION FROM S WHEN CONDERING BENDING MOMENT.

THIS AREA IS SUBJECT TO UPWARD REACTION FROM S WHEN CONSIDERING SHEAR.

PLAN 25

Page 26: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 6: PAD, RAFT, AND PILED FOUNDATIONS

RAFT FOUNDATIONS SOLID REINFORCED CONCRETE OR CELLULAR

CONSTRUCTION, LANDSCAPE TO PLAN, FOR SMALL

BUILDINGS 225MM THICKNESS OF RAFT FOR LARGER

BUILDING 225 TO 375MM.

AS APROX OF 1.0 TO 1.50m WITH SLIGHT FALL IS DESIRABLE

BOTTOM STEEL REINFORCEMENT RESISTS SWELLING CLAY,

6.75mm THICK COARSE SAND OR GRAVEL BUILDING IS LAID

WHEN OTHER RAFT

1. TYPICAL GROUP OF PILES UNDER A REINFORCED CONCRETE PILE CAP THERE MAY BE SEVERAL ROWS OF

P ILES EACH WAY 2. RAKING PILES TO RESIST LARGE HORIZONTAL LOADS.

UNDER-REAMED PILE FOUNDATIONS HAVE BEEN USED SUCCESSFULLY IN INDIA FOR OVER 20 YEARS IN SOILS SUSCEPT TO EXPANSION AND SHRINKAGE. LENGTH OF UNDER REAMED PILES RANGES FROM TO 8M DIAMETER OF THE MANUALLY BORED SHAFT IS FROM 200 TO 500MM DIAMETER OF UNDER-REAMED BULB IS NORMALLY 2 TIMES THE SHAFT DIAMETER

26

Page 27: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

5.0 EXCAVATION AND EARTHWORKS

5.1 Setting-out of Foundation: The approximate area for the building is excavated to a

depth of 150mm. Rough profile are set around the perimeter of the working area of the

building. Accurate setting out is required. Setting out must be especially accurate for

building with a precast concrete panel system (refer to diagram for details).

5.2 Excavation: Excavation will be classified “rock excavation” o accordance with the following definitions:

(i) Rock is defined as material of such hardness and texture that cannot be loosened

or broken by hand drifting picks, mechanical excavations including rooters, or

power-driven hand tools, but requires drilling and blasting, wedging, barring and

sledging where blasting is not permitted or unsuitable for the proper execution

of the work, and also all boulders or debris piece of rock (as defined above) more

than or a cubic metre in volume in open excavation or more than 0.4m3 volume when excavating in narrow trenches.

(ii) Excavation of all other materials, whether hard or soft, to which the definition of rock as aforesaid does not excavation”apply.shall

(iii) All excavations shall be carried out to the lines and limits shown on the excavation plan and other drawings.

(iv) The bottoms of excavations shall be leveled and trimmed to full width and shall be well watered and rammed before placing of concrete.

(v) The sides and ends of all trenches and excavations wherever necessary are to be

protected with strong, close timbering and shall prevent any fall or run of earth

or sand from any portion of the ground of the trench or excavation.

5.2.1 Bottom of excavation: The bottom of every excavation shall be free of all organic

materials. 5.2.2 Water Removed: Excavations shall be kept free of standing water 5.2.3 Disposal of excavated materials

(i) Any suitable materials removed during excavation may be used for backfill.

Materials removed from trenches shall be placed alongside the trench at a

27

Page 28: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

sufficient distance to prevent it from felling to the trench, or its weight causing the trench sides to cave in.

(ii) Rock and waste materials not suitable or not required for backfill shall be spread or removed from site.

5.3 BACKFILL

5.3.1 Placing:Backfill shall be placed to avoid damaging drainage tile or the water proofing of walls.

5.3.2 Grading: Backfill shall be graded to prevent drainage towards the foundation after

settling.

5.3.3 Boulders: backfill within 600mm of the foundation shall be free of deleterious debris

and boulders larger than 250mm diameter.

5.4 HARDCORE FILLING

5.4.1 Material: The hardcore material shall be selected granular laterite stone concrete free from rubbish and dust and broken to pass 75mm ring with sufficient smaller materials to fill interstices.

5.4.2 Beds: Hardcore beds and filling are to be deposited in layers not more than 150mm in

thickness. Each layer shall be thoroughly consolidated by ramping and rolling with heavy roller.

28

Page 29: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 7: SETTING-OUT AND EXCAVATION SHOWING ARRANGEMENTS OF PROFILE BOARDS AND PEGS

PROFILE BOARDS AND PEGS FOR CORNERS OF THE BUILDING AND AT POSITION OF

PROFILE BOARDS AND PEGS FOR CORNERS OF THE BUILDING AND AT POSITION OF INTERNAL LOAD

A DATUM IS ESTABLISHED ON THE SITE WITH THE HELP OF A WOODEN STAKE, STEEL ON CONCRETE POST SET FIRM IN A CONCRETE BASE,

WITH THE TOP AS THE

CLOSER DATUM. ALL

LEVELS ON THE SITE

AND BUILDING RELATE

29

Page 30: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

.

D. MATERIALS 6.0 Formwork

6.1 Materials: Formwork shall be I)in every respect be adapted to the structure and to the

refused surface finish of the concrete. i) Made of sound and seasoned timber, wrought and thickness, where required and of sufficient thickness, or of steel or laminated wood, suitably supported. ii) Fixed in perfect alignment and securely braced so as to be able to withstand deflection displacement or movement of any kind. iii) Wedges and clamps shall be used wherever practicable instead of nails in the construction of the shelters. Iv) Portions of shelters at the level of each lift shall be removable to ensure the thorough cleaning out of any rubbish.

6.2 Beam Formwork:i) The bottom of all beam formwork shall have a chamber of form

1/350 of the span according to the size of the beam. ii)Beam formwork shall be so constructed such that the only portion immediately removable shall be those directly above the supporting struts. iii) All formwork shall be thoroughly and efficiently cleaned out before placing steel reinforcement and/or concrete therein. Iv) “Wash-outs” shall provided in suitable locations in the bottom of all beam formwork for this purpose. v)The inside of the formwork shall be treated with a coat of mould oil to prevent adhesion between the concrete and the formwork.

6.3 Wall and column formwork: i)Wall and column formwork shall be executed in 1500mm

lifts as concreting proceeds in order to control effectively, the deposition of concrete and to avoid segregation. ii) Where it is necessary to use spacers or ties through walk for supporting the formwork above, the spacers or ties shall be of approved pattern and have a built-in portion where are not less than 50mm from either face of the wall. iii)The holes left in the concrete shall be neatly pointed with an approved expanding grout as soon as the form work is applied. Iv) Concrete shall not be placed against vertical or inched earth faces in lieu of formwork without the approval of the Engineer.

6.4. Striking times for cast in-situ works: The time for removal of forms as set out in the Table 6.4A below shall not apply to slabs and beams spanning more than 10 metres.

30

Page 31: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Table 6.4A

FORMS ORDINARY PORTLAND CEMENT DAY (24-HOURS)

Wall Columns (unloaded) Beam side 2

Slabs –props left under 4

Beam soffits –props left under 7

Slabs –removal of props 10

Beam –removal of props 16

6.5 Board Marked Formwork: Where board marked formwork is specified it shall be made

from 255mm wide rough sawn timber boards. The edge joints of the boards shall be covered with a 12mm x 22mm twice splayed wrought hardwood fillet to form a groove in the concrete. The resulting concrete shall clearly show grain and individual board marks, shall be free from honey-combing and excessive air holes, and shall be of uniform colour.

6.6 Wrought Formwork or Plywood Lined Formwork: Where wrought or plywood lined

formwork is specified for the concrete the formwork shall be made from plywood or such other approved material as will ensure that the finished surface of the concrete shall be perfectly true, smooth and even. Small imperfections-good” mayby rubbing with a carborundum store dipped in cement paste.

6.7 Sawn Formwork: Where a concrete surface is covered in the furnished works, the formwork shall be made from rough sawn timber boards not necessarily of uniform width. Where concrete surfaces are required to be rendered in the finished works, the concrete surface shall be scored or hacked to provide a key for the render.

6.8 Inserts: Incorporate and concrete members all electrical conduits, pipes, fixing blocks,

closes, matrices, as specified. All fixing shock, chases, holes etc. shall be accurately set out and cast into the concrete.

6.9 Precast Concretework (moulds generally)

6.9.1 Construction: The moulds shall be constructed so that the time dimensions shown on the drawing are maintained and shall withstand all loading without movement of any kind under the weight of the wet concrete and all temporary loading. Before any concrete is placed, all moulds must be checked for position and alignment.

31

Page 32: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

6.9.2 Timber Moulds: Timber moulds shall be constructed with well seasoned timber. All moulds shall be constructed so as to prevent leakage of liquid cement, remain time to shape at all times during use and give to specified finish to the unit.

6.9.3 Coating: Moulds shall be coated with approved non-standing mould oil before each unit

is cast. Care must be taken that the oil does not touch the reinforcement or accumulate at the bottom of the moulds. Before placing the concrete, all moulds must be cleaned of all concrete or mortar adhering to the surface and all rubbish, sawdust, chippings, nails and other deleterious materials must be removed.

6.10 Demoulding Unit

(i) No unit shall be demoulded before 48 hours have elapsed after coasting is

finished.

(ii) Freshly demoulded units shall be handled with the greatest of care so as to

avoid cracking and damage to the surface and arises.

(iii) All moulds shall be removed without any shock or vibration which might damage

the concrete or have any other detrimental effect on the unit. 6.11 Handling Lifting and Transporting

(i) All units shall be handled, lifted and transported in a manner which does not

cause damage or cracking. When units are lifted by crane the weight shall be taken up gradually without snatch. When units are being covered they shall not be dropped but shall be let down gently into position without impact.

(ii) No units are to be lifted until the design strength or the concrete has been

verified from cube test results.

(iii) Where the position for lifting holes or slings are shown on the drawing, they shall

not be departed from without prior permission. 6.12 Storage of Units on Site

(i) All precast units shall be stored on site in a manner and in the positions which

will prevent damage or cracking of any kind and permit erection with a minimum of preliminary handling and transporting.

(ii) All bolt holes, necessary and other cavities shall be temporarily plugged to

prevent the entry of rain or other water unless such water can freely drawn away.

32

Page 33: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

7.0 CEMENT

7.1 Specification: Cement used for cement mortar and concrete works shall be ordinary and

rapid hardening Portland cement and shall comply with GS914: 2011 (3rd Edition) Building and Construction Materials –Specification for Portland Limestone and Portland Dilomitic Limestone Cement.

7.2 Types: Some types of cement are:

i. Ordinary Portland Cement

ii. Rapid hardening Portland Cement

iii. Suphate Resisting Portland Cement

iv. White or Coloured Portland Cement

v. Pozollana cement 7.3 Storage

i. Cement shall be obtained directly from the manufacturers in sealed bags bearing

the mark of the manufacturer and shall be stored in these bags on the site in a suitable building affording adequate protection against the weather and against the ingress of moisture from any source. Rebased cement, cement in plain bags or cement in bags will not be permitted on site.

ii. The floor of the cement storage building shall be of timber at least 300mm from

the ground, the grace between the floor and the ground being kept open in order to provide adequate ventilation. The use of loose cement from the bags occasioned by any reason will not be permitted.

iii. Storage shall be arranged so that cement is used in the order in which it was

delivered so that the Engineer can rapidly identify any particular consignment for sampling and testing.

7.4 Clay Pozzolana

i. The mixing ratio of clay pozzolana and Portland cement in construction is as

shown on Table7.4 below.

33

Page 34: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Table7.4

PRODUCT POZZOLANA AND PORTLAND

CEMENT MIXED RATIOS

Mortar 1:2

Blocks 1:2

Concrete 1:3

Plastering 1:2

Drains & Culverts 1:3

7.4.1 Directions of use of clay pozzolana

i. Mix pozzolana with Portland cement in recommended ratio in dry state. ii. Add blended cement to the sand or stones (where necessary). iii. Mix all the materials very well to form a uniform mix. iv. Gradually, add water to the materials . Ample use of water is recommended. v. Use it for your work to get a fine finish.

8.0 AGGREGATES

Aggregates can be fine or coarse and shall consist of sand, gravel, crushed rock, expanded clay. Aggregates shall be clean well-graded and free of injurious amounts of organic and other deleterious materials. Care should be taken in the selection of coarse aggregates to ensure uniformity of sizes.

The grading of fine aggregates shall be as illustrated in the Table 8.0A below:

Table 8.0A

Percentage by weight passing BSSieve

Grade Zone

1 2 3 4

5mm 90 –100 90 –100 90 –100 95 –100

No. 7 60 –100 75 - 100 85 –100 95 –100

No. 14 30 –70 55 - 90 75 –100 90 - 100

No. 25 15 –34 35 - 59 60 –79 80 –100

No. 52 5 –20 8 - 30 12 –40 15 –50

No. 100 0 - 10 0 - 10 0 - 10 0 -10

8.1 Coarse Aggregates: The coarse aggregates shall be granite, gravel or other hard stone. The nominal size of the aggregates shall be as stipulated below:

34

Page 35: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

8.2 Fine Aggregate:

Table 8.0B

Percentage by weight passing BS Sieve

BS Sieve Size

Normal size of graded Aggregate

40mm to 5mm 20mm to 5mm

80mm 100 -

40mm 95 –100 100

20mm 30 –70 95 –100

10mm 10 –35 25 –35

5mm 0 - 5 0 - 10

8.3 Alkali Aggregates Reactivity: Aggregates must not contain any matter, which is likely to undergo disruptive expansive reactions with alkali in the concrete mix or which is likely to negatively affect the long term durability of the concrete.

8.4 Storage of Aggregates

i. The fine and coarse aggregates shall be stored in properly constructed open bins

with hard clean drained floors or in such a manner that they shall not become contaminated with any deleterious extraneous matter.

ii. All sand and aggregates shall be stored on close fitting timber, steel or concrete

stage of approved design with drainage slopes or in bins of substantial construction in such a manner as to prevent segregation of sizes and to avoid the inclusion of dirt and other foreign materials in the concrete.

9.0 WATER

Water shall be clean and free of injurious amounts of oil, organic matter, sendiment or any other deleterious material. Water that is fit for drinking is to be used for concreting and should be stored in tanks, barrels near the mixed or mixing pad on site.

9.1 Water/Cement Ratio: The maximum water/cement ratio for all the concrete mixes,

unless otherwise specified shall be 0.45 except for concrete classes 22.5/38 and 10/38 which shall be 0.50 and 0.6 respectively. They shall be determined by the trial mixes and shall not exceed the values given above. Efficient means shall be provided for the moisture content and absorption values of the sand and coarse aggregate at all times.

35

Page 36: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

10.0 CONCRETE

10.1 Classification of Concrete mixes: Concrete mixes shall be classified as designed mixes or

prescribed mixes.

10.2 Designed Mix: For a designed mix, the contractor or manufacturer shall be responsible

for selecting the mix proportions to achieve the required strength and workability but the Engineer shall be responsible for specifying the minimum cement content and other properties required to ensure durability.

10.3 Prescribed Mix: For a prescribed mix, the Engineer shall specify the mix proportions and

the contractor or manufacturer shall undertake to provide a properly mixed concrete containing the constituent in the specified proportions.

10.4 Durability: The minimum cement content kg/m3 required in Portland Cement concrete to ensure durability and nominal cover to reinforcement shall be a listed in Table 10.0A and Table 10.0B respectively.

TABLE 10.0A –MINIMUM CEMENT CONTENT (KG/M3) REQURED IN PORTLAND CEMENT CONCRETE TO ENSURE DURABILITY

Reinforced Concrete

Exposure Nominal maximum size of agg-mm

40 20 14 10

Mild – for example, completely protected against

weather or aggressive conditions, except for a brief

period of exposure to normal weather conditions during

construction 220 250 270 290

Moderate –for example, sheltered from severe rain.

Buried concreted and concrete continuously under water 260 290 320 340

Severe –for example, exposed to sea, water, driving rain,

alternate wetting and drying and subject to heavy

condensation or corrosive fumes 320 360 390 410

Column 1 2 3 4

36

Page 37: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

TABLE 10.0B –NOMINAL COVER TO REINFORCEMENT

Nominal Cover –mm

Condition of exposure Concrete grade

20 25 30 40 50 and over

Mild – for example, completely protected against

weather, or aggressive conditions, except for brief

period of exposure to normal weather conditions

during construction. 25 20 15 15 15

Moderate –for example, sheltered from severe rain.

Buried concrete and concrete continuously under water N/A 40 30 25 20

Severe –for example, exposed to driving rain, alternate

wetting and drying, subject to heavy condensation or

corrosion

Very severe –exposed to sea water and with abrasion

Column 1 2 3 4 5

10.5 Basic Tools for concrete works: Guage Boxes, Spirit level, Builders severe, Wooden Float, Steel Brush, Wheel Barrow, Crowbar, Vibrator Pickaxe, Steel Moulds for test cubes, Mattock, Hollow Frustum Core, Rule, Pincers, Trowel, Builders Line, Measuring Tape, Straight Edge, Hacksaw, Bott Cutter, Headpans, Wawa Boards, Shovel, Spade, Concrete Mixer, Tamping Rod, , Pliers, Bender.

10.6 Concrete Trial Mixes: The components of concrete (cement, sand, stone and water) are often mixed in various proportions depending on the purpose for which it is intended to be used. This is done so as to achieve the minimum grade or strength for a particular concrete work. The classification of mixes, cement contents and required strength are shown below:

Table 10.0C

Minimum weight of cement for

Mix Proportion Grade Designation N/mm2 cubic metre of concrete placed

1:1:2 31.0 360 kgs/m3

1:1 –½:3 25.5 310 kgs/m3

1:2:4 21.0 280 kgs/m3

1:3:6 12.0 210 kgs/m3

The concrete for structural works shall be designated mixes which comply with the minimum requirement specified. The preliminary or trial mixes should generally give strength 25% higher than the specified “wo not less than half a cubic meter of concrete and shall be mixed in a mechanical mixer.

37

Page 38: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

The quantities of all the ingredients of each trial mix including water shall be carefully determined by weight according to the approved mix design.

10.7 Transportation of Concrete: The concrete shall be discharged from the mixers and transported to the works by means that shall prevent contamination (by dust, rain, or other causes) segregation or loss of ingredients. The means of transportation shall ensure that the concrete is of the required workability at the point of placing.

10.8 Placing Concrete: Concrete shall be used not later than thirty after it leaves the drum of

the mixer. The concrete shall be conveyed in such a way that no segregation of the constituent materials takes place. No concrete shall on any account be used after it has developed the initial set and any batch or parts of a batch which has commenced to set before being used shall be rejected. The concrete should be well worked into all corners of the formwork and between and around the reinforcing bars, to ensure compact and smooth-faced concrete.

The greatest care should be taken to prevent any displacement or bending of the reinforcing bars, ties, links and strings before commencing concreting. Care should be taken to insert or adjust members in their correct positions before concreting commences.

10.8.1 Foundation Casting: Foundations shall be cast insitu continuosouly without break making sure that the top is level. Concrete placed in timbered excavations shall be well rammed.

10.8.2 Concrete on rock surface: On rock surface a 25mm layer of 1:3 mortar shall be spread immediately prior to placing concrete and shall be well worked into the surface with the aid of brushes. All openings should be filled with concrete.

10.8.3 Blinding: Reinforced concrete shall not be placed directly on earth surfaces. Blinding shall be cast with a layer of concrete mix 1:4:8 of minimum thickness of 50mm.

10.9 Vibration of Concrete: Mechanical vibrators shall be employed where applicable for consolidating concrete. The vibrators shall operate at a frequency of not less than 5,000 cycles per minute. Freshly placed concrete shall not be vibrated in a manner likely to cause damage to concrete previously placed. All concrete to be vibrated must have a dry consistency and shall be deposited into the formwork approximately in its final position.

10.10 Curing Concrete: All surfaces of concrete shall be protected from rain, not dry and

windy weather and be kept continuously moist for several days (at least 28days) after placing. The concrete shall be covered immediately after being deposited with Hessian sacking adequately weighed down and kept through wet or with a layer of sand of other suitable material watered at frequent intervals or in some equally effective manner approved by the Engineer.

38

Page 39: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

10.11 Breaks during Construction: i Breaks in concrete casting should be avoided as much as possible.

ii. However, where it becomes necessary eg. Shortbreak for meals, then on stoppage of work. mixing machines, mixing platforms, chutes and wheel barrows used for carrying concrete shall be emptied and cleaned properly with water.

iii. Upon commencement or recommencement of work, the first batch of concrete

passed through any mixer shall contain half the normal quantity of coarse aggregate.

10..12 Joints between fresh and hardened concrete:

i. In order to obtain an efficient joint between fresh and hardened concrete the face of the latter shall be prepared by removing the surface of the hardened concrete while it is green to expose the aggregate and leave a sound, roughened surface which may be effected by spraying with water or air assisted with light brushing as necessary. If surface preparation is not carried out while the concrete is green, the surface shall be thoroughly ha cked with a power operated tool to expose the aggregate. Care shall be taken to avoid damage to the aggregate.

ii. Prior to placing fresh concrete against hardened concrete, the surface of the

hardened concrete shall be slightly moist. Vertical surfaces shall be treated with a thin layer of cement grout well worked into the surface of the hardened concrete. On horizontal joints the workability of the first batches of concrete placed in contact with the joint shall be slightly increased.

11.0 STEEL FOR REINFORCED CONCRETE 11.1 Recommended types

Stronger steel is not preferable to mild steel in earthquake prone regions. Mild steel is far preferable to higher strength steel in areas of structural members where yielding of the steel is likely(such as in potential plastic hinge zones) from earthquake loads. Mild steel is more ductile.

11.2 Sizes of reinforcements: Care should be taken in the purchase of reinforcements. A professional should be used to purchase the specified reinforcements. The normal sizes are : 6,10,12,16,20mm.

11.3 Bending Reinforcement:

39

Page 40: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

i. All reinforcement shall be carefully set to the correct dimensions in a manner, which will not damage the material. In particular no reinforcement shall be heated before bending.

ii. Bends cranks on reinforcements bars shall be carefully formed in accordance

with the bending dimensions and scheduling of bars.

iii. Reinforcement shall be stored by type, size and length in covered racks either

above ground level or on cleaned surface areas.

iv. Reinforcements shall not be joined by welding, unless indicated on the drawing.

v. Reinforcement shall be fixed in the position indicated on the drawings. The

maximum deviation of the actual position of the reinforcement from the indicated position shall be in accordance with Table 11A. All intersections of the bars shall be securely tied with malleable iron wire of suitable gauge.

Table11A - Recommended Deviations

DIMENSION MAXIMUM DEVIATION

Lateral Dimension between Bars = 12mm

Longitudinal Position of Bars = 25mm

Concrete Cover Position of Bars = 30mm

11.4 Placing Reinforcement

i. The number, size, form and position of all the bars, ties, links, strings and other

members of the reinforcement shall be in accordance with the working drawings. Nothing shall be allowed to interfere with the specified position of the reinforcement. It should be fixed by means of amended iron wire of suitable gauge to prevent displacement before and during the process of concreting. Horizontal bars in beam shall be laid parallel to each other and the stirrups shall be kept to the bars they embrace.

ii. The reinforcement may be kept in position in the framework required by means

of concrete spacers and the like. Spacers may be made of correct mortar blocks of thickness corresponding to the necessary cover. Such blocks shall not exceed 40mm length or breadth and shall be composed of one part of cement to two parts of fine aggregate.

40

Page 41: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

11.5 Cover of Concrete: Unless otherwise indicated on the drawing, the reinforcement bars shall be so placed in formwork so as to give a minimum cover of 25mm of concrete.

12.0 MASONRY ( SANCRETE BLOCKS, BRICKS, LANDCRETE OR STABILIZED EARTH) 12.1 Scope: This section applies to unreinforced masonry and masonry veneer .

12.2 Required reinforcements: Loadbearing elements of masonry buildings shall be

reinforced with at least the minimum amount of reinforcement. Masonry walls shall be reinforced horizontally and vertically with steel having a total cross-sectional area of not less than 0.002 times the cross-sectional area of the wall, so

that not less than 1/3 of the required area is installed either horizontally or vertically and the remaining in the other direction.

12.3 Masonry Units

12.3.1 Materials specifications for masonry units: Masonry units shall comply with the following GS .3921 : icks1974andblocks“ClayBS. br2028 : 1978 “Pr blocks”:GS297-1 :2010 2nd Edition “Part1 Precast Sancrete

“ 12.3.2 Used Masonry: Used bricks shall be free of old mortar, soot or other surface coating and

shall conform to article 11.4.1. 12.3.3 Stone: Stone shall be sound and durable. 12.3.4 Compressive strength: Except as provided in Article 11.4.1 the compressive strength of

masonry units in a wall of a house of one or two storey or of a building which is divided

into flats, shall have a compressive strength of not less than 2.75 N/mm2 for blocks and

5.5 N/mm2 for bricks.

12.3.5 The Compressive strength of bricks and blocks for non-loadbearing partitions shall be

not less than 1.4 N/mm2 provided the bricks and blocks are satisfactory in other respects.

12.3.6 Manufacture of Sandcrete blocks: The following is a guide for the manufacture of good

quality blocks: i. The blocks shall be composed of at least one part of cement to six parts of sand by

volume, unless otherwise specified or directed on site. ii. Mixed thoroughly until it is of an even colour and consistency throughout. iii Water shall then be added gently from watering can or through a hose, the quantity of

water being just sufficient to sense adhesiveness. iv. After wetting, the mixture should be turned over thoroughly and well rammed into

moulds and smoothed off with a steel faced tool. v. After removal from the machine on pallets, the blocks shall be matured in the shade in

separate rows one block high with a space between each block for at least 24 hours.

41

Page 42: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

vi. They shall then be removed from the pallets but shall not be stacked up or removed from the shade for at least a further 7 days. Pack them not more than 5 blocks high in the shade for a minimum of 14 days and keep them well watered at all times before use.

12.4 Testing of blocks: An experienced technician or mason can determine the quality of a good block by observation and scratching the edge of the block. Part breaks only with great difficulty and it is impossible to powder it with fingers. Cracks on the surface of a block is an indication of bad quality block and possible presence of clay in the sand used for moulding the blocks. A block could be weighed and immersed into water for 24

hours. A good block should not absorb water more than 1/6th of its weight. Also a block

that turns green easily after immersing it into clean water for about a week is an indication of low content of cement.

12.5 Block laying

i. All blocks shall be thoroughly wetted before being laid or built on

ii. Laying shall be properly bonded together and leveled through every second

course. All corners, cross wall junctions and reveal shall be properly bonded. Special care shall be taken that all vertical joints are filled with mortar.

iii. Block laying shall be carried out in a uniform manner. No one position shall be

raised more than 0.90 metres above another at any time. 12.6 Burnt clay bricks

i. Scope: Fired Clay bricks each of clay or shale shall conform to BS3921, Part2. ii. Common bricks: Shall have a thickness of 65mm, and manufactured by approved

brick and tile factory. iii. Ordinary burnt hollow bricks: Shall be 100 and 150mm thick. IV. Facing bricks: Shall be 65mm thick as selected by consultant.

12.7 Stabilized Earth Bricks

i. Stabilized laterite bricks shall be composed of sand stabilized with 5-10% cement by volume and shall conform to BS1924.

ii. Soil for stabilized laterite bricks shall conform to BS 882. iii. The size of laterite bricks shall be 290x127x90mm. iv. Curing of cement stabilized earth bricks shall be under humid conditions.

42

Page 43: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

13.0 MORTAR 13.1 Lime: Lime used in mortar shall be hydrated.

13.2 Mortar Mixes: Mortar Mixes shall conform to Table 13A. Mortar containing Portland

cement shall not be used later than two and half hours after mixing.

Table 13A

Permissible Use of Mortar Cement Lime Sand

All Locations 1 1 5 to 6

1 2 8 to 9

1 - 5 to 6

1 2 4

1 - 3

13.3 Mortar Joints

13.3.1 Thickness: The maximum average thickness shall be 13mm. Maximum thickness of an individual joint shall be 20mm.

14.0 WATER PROOFING AND DAMPPROOFING

14.1 Waterproofing of Walls: Where hydrostatic pressure occurs, floors on ground and

exterior surfaces of walls below ground level shall be waterproofed.

14.2 Dampproofing of Walls: Where hydrostatic pressure does not occur and the exterior

finished ground level is at a higher elevation than the ground level inside the foundation walls exterior surfaces of foundation walls below ground level shall be dampproofed.

14.2.1 Any part of a building next to the ground shall have a floor which is so constructed as to prevent the passage of moisture from the ground to the upper surface of the floor.

14.2.2 Any floor which is next to the ground shall be so constructed as to prevent any part of

the floor being adversely affected by moisture or water vapour from the ground.

14.2.3 No hardcore laid under floor which is next to the ground shall contain water-soluble

sulphates or other deleterious matter in such quantities as to be liable to cause damage to any part of the floor.

43

Page 44: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

E. SUPERSTRUCTURE

15.0 MASONRY JOINTS AND SUPPORT 15.1 Solid masonry joint: Solid masonry units shall be laid with full head and bed joints.

15.2 Hollow masonry joints: Hollow masonry units shall be laid with mortar applied to head

and bed joints of both inner and outer face shells. 15.3 Contraction and Expansion Joints

15.3.1 Expansion Joint Materials: Expansion joint materials shall be approved bitumen impregnated fibre board, like “Flexcel”.

15.3.2 Expansion Joint Sealer: Expansion joint sealer shall be approved cold, or knife applied sealant or

“Plastic joint” likeor“Plastic”“Sealastiand approved not applied sealed sealant. All sealers should be applied strictly in accordance with the manufacturer’s instructions.

15.4 Masonry Support: All masonry shall be supported on masonry, concrete or steel.

15.5 Wall thickness and height: Every wall shall be at least as thick as the wall it supports.

15.5.1 Thickness of solid external walls: Masonry external walls other than cavity walls in 1 storey building and top storeys of 2 storey buildings shall be not less than 125mm thick provided the walls are not more than 2.74m high at the eaves and 4.57m high at the peaks of gable ends, the external walls of the bottom storey of 2 storey buildings shall not be less than 150mm.

15.5.2 Thickness of non-loadbearing partitions: Interior non-loadbearing partitions shall be

not less than 100mm thick.

15.6 Masonry Veneer: Masonry veneer resting on a bearing support shall be of solid units not less than 76mm thick for wall heights up to 10.8m. Such veneer over wood frame walls shall have not less than a 25mm air space behind the veneer. Masonry veneer less than 97mm thick shall have unraked joints.

44

Page 45: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

15.7 COLUMNS

15.7.1 Scope: This section applies to columns used to support roofs and beams carrying loads from not more than 2 woodframe floors where the length of joists carried by such

beams does not exceed 4.88m and the live load on any floor does not exceed 2.5KN/m2.

15.7.2 Column Support: Columns shall be centrally located on a footing conforming to section

4.0.

15.7.3 Fastening Columns: shall be securely fastened to the supported member to prevent

lateral movement. 15.7.4 Steel Columns

a) Size: Except as permitted in Article 15.7.4b, steel pipe columns shall have a minimum outside diameter of 73m and a minimum wall thickness of 4.76mm.

b) Exception: Columns of sizes other than as specified in Article 15.7.4a may be used where the loadbearing capacities are shown to be adequate.(put a figure)

c) Bearing Plates: Except on permitted in Article 15.7.4d steel columns shall be fitted with

not less than 100mm by 6mm thick steel plates at each end, and where the column supports a wooden beam, the top plate shall extend across the full width of the beam.

d) Exception: The top plate required in Article 15.7.4c may be omitted where a column

supports a steel beam and provision is made for the attachment of the column to the beam by welding or other approved method.

e) Rust Prevention: Steel columns shall be treated on the outside surface with at least one coat of rust-inhibitive paint as appropriate

15.7.5 Wood Columns

a) Size: The width or diameter of a wood column shall be not less than the width of the supported member. Except as provided in article 15.7.5b, columns shall be not less than 200mm for round columns and 150mm by 150mm for rectangular columns, unless calculations are provided to show that lesser sizes are adequate.

b) Wood Columns for garages and carports: Sizes may be 100mm by 100mm.

c) Construction: Wood columns shall be either solid, glued-laminated or built-up. Built-up

columns shall consist of not less than 50mm thick full-length members bolted together with not less than 10mm diameter bolts spaced not more than 460mm, or nailed together with not less than 75mm nails not more than 300mm.

15.7.6 Solid Concrete Columns

45

Page 46: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

a) Material: Concrete shall conform to section D.

b) Size: Concrete columns shall not be less than 200mm by 200mm for rectangular

columns and 225mm diameter for circular columns.

15.8 LINTEL Masonry over openings shall be supported by steel, reinforced concrete or masonry lintels or arches designed to support improved load.

16.0 STAIRCASES

16.1 Private Stairways:

Means an internal or external stairway of steps with straight nosings on plan which forms part of a building and is either within a dwelling or intended for use solely in connection with one dwelling.

16.1.1 Any private stairway shall be so constructed that the sum of the going of a parallel step plus twice its rise is not less than 550mm and not more than 700mm.

16.1.2 The rise of a step shall be not more than 220mm and the going of a step not less than

220mm.

16.1.3 The pitch of the step shall not be more than 420.

16.2 Common Stairways: Means an internal or external stairway of steps with straight nosings on plan which

forms part of a building and is intended for common use in connection with two or more dwellings.

16.2.1 Any common stairway shall be so constructed that the sum of the going of a parallel step plus twice its rise is not less than 550mm and not more than 700mm.

16.2.2 The rise of a step shall be not more than 190mm and the going of step not less than

230mm. 16.2.3 The pitch of the common stairway shall not be more than 380. 16.2.4 A common stairway shall have not more than 16 rises in any flight.

16.3 Landings: Landings shall be at least as wide and as long as the width of stairs in which they occur, except that length of landing for exterior stairs serving not more than one dwelling unit need not exceed 610mm and the length of landing for all other stairs in a straight run need not exceed 1.12m.

46

Page 47: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

16.4 Insitu concrete steps: Insitu concrete steps should have profiles, if they have no protruding terrazzo or other covers, non-strip trips of hard rubber, carborundum metal, etc should be cast into the tread.

16.5 Single steps supported from a central load-bearing column: The precast terrazzo steps

are reinforced with 8 and 10mm diameter reinforcing roads. The erection sequence is to fix the spiral treads and to cast the reinforced concrete centre core first, second to fix the steel uprights, two to each step, third to weld the flat ms bar for the railing to the upright and last to cover the bar with the PVC profile.

17.0 ROOFING

17.1 Roof Protection: Roof shall be protected with roof covering, including flashing, installed

to shed rain effectively. Roofing materials shall conform to the following CP. 143: 1973, Code of practice for sheet roof and well coverings.

Part 15: Aluminium

Part 10: Galvanised corrugated steel

BS 402: 1974, specifications for clay plain roofing tiles and fittings.

17.2 Roofing Nails: Nails used for roofing shall be corrosion –resistant roofing or shingles

nails. Nails shall have sufficient length to penetrate through or 12mm into roof sheathing. Nails used with wood shingles or shakes shall have a head diameter of not less than 5mm and a shake thickness of not less than 2mm.

17.3 Roofing Staples: Staples used to apply wood shingles shall be corrosion –resistant and

shall be driven with crown parallel to the eaves. Staples used with wood shingles shall be not less than 28mm long; 2mm diameter or thickness, with not less than 10mm crown.

17.4 Roof Slope

17.4.1 Roof Slopes: The roof slopes on which roof covering may be applied shall conform to Table 17.4A.

47

Page 48: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

TABLE 17.4A ROOFING TYPES AND SLOPE LIMITS OF ROOFS

TYPE OF ROOFING MINIMUM SLOPE MAXIMUM SLOPE

Built-up Roofing

Asphalt base (graveled) 0 in 25 20 in 100

Asphalt base (without gravel) 1 in 25 50 in 100

Coal-tar base (graveled) 0 in 25 1 in 25

Wood shingles

Handsplit shakes

Sheet metal roofing

Corrugated metal roofing

Clay tile

Glass fibre reinforced

Polyester roofing panels

17.5 Flashing at Intersections

17.5.1 Sheet metal flashing shall consist of not less than 1.73mm thick sheet load, 0.33mm galvanized steel, 0.36mm thick copper, 0.46mm thick zinc or 0.48mm thick aluminium.

17.5.2 Valley Flashing: Where sloping surfaces or shingled roofs intersect to form a valley, the

valley shall be flashed.

17.5.3 Open Valley Flashing: Open valleys shall be flashed with not less than 1 layer of sheet

metal not less than 600mm wide.

17.5.4 Closed Valley Flashing: Closed valley flashing shall consist of sheet metal not less than

600mm wide. Nails shall not penetrate the flashing within 75mm of the top of the valley or 125mm of the bottom of the valley measured from the centre line of the valley.

17.5.5 Intersection Flashing: The intersection of shingle roofs and masonry walls or chimneys

shall be protected with flashing. Counter flashing embedded not less than 25mm in the masonry shall extend not less than 150mm down the masonry and lap the lower flashing not less than 100mm. Flashing along the slopes of a roof shall be stepped so that there is not less than 75mm head lap in both the lower flashing and counter flashing. Where the roof slopes upwards from the masonry, the flashing shall extend up the roof slope to a point equal in height to the flashing on the masonry, but not less

than 11/2 times the shingle exposure.

17.6 Types of roofing –Framed Timber roof systems

i. Couple roof

48

Page 49: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

ii. Couple roof with cellar tie iii. The mansard roof iv. The purlin system v. The rafter system vi. The Trussed Rafter –Purlin System

17.6.1 Couple roof with collar tie: It relieves the walls of thrust.

17.6.2 The mansard roof: utilizes roof space and reduces pitch. Developed with nearly flat top

in late renaissance and barque period.

17.6.3 The Purlin System: Simple purlin roofs use sawn timber purlins spanning between walls.

They are uneconomic for spans exceeding 4.8m systems of built-up purlin girders with light rafters are more commonly used.

17.6.4 The Rafter System: Unsupported rafter systems are suitable only short spans

(limitations in lengths of sawn timber) up to 6.3m, incorporating a tie.

17.6.5 The Trussed Rafter - Purlin System: This is a popular conventional roof system for

medium sized and large buildings. The light trusses are fixed to the walls at 1.8 to 2.4m centres. Purlin spacing is dictated by the roofing material, and the purlin size by the spacing adopted.

17.7 Trussed Rafters

TABLE 17A MEMBER SIZES OF SIMPLE NAILED TRUSSES

Maximum Span Bottom Chord mm Top Chord mm Web Members mm

4.90 75 x 50 75 x 50 75 x 25

6.75 75 x 50 100 x 50 75 x 25 & 75 x 50

8.50 100 x 45 100 x 45 100 x 25 & 100 x 50

17.7.1 Types of Trussed Rafters

i. Nailed King –Post truss ii. Nailed “W” Truss

49

Page 50: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

17.7.2 Nailed King-post truss with plywood gussets: Suitable for spans up to 7.50m extending top chord individually supported (for covered verandahs).

17.7.3 Nailed “W” truss : Usingwithunclenchedplywood45mmnails, spacedgussetsat every 600mm centres. Suitable for spans up to 8.70m.

17.8 Roof Ridges

17.8.1 Types

i. Half round Ridge ii. Two-piece Ridge iii. Ventilating type of ridge capping in two-piece form

17.8.2) Half round Ridge: The roof pitch for this ridge type should be 20o.

17.8.3) Two-piece Ridge: This is a close fitting type of asbestos cement ridge capping.

17.8.4) Ventilating type of ridge capping in two-piece form: Difference flashing pieces (cable angles and pitch covers) from flat or corrugated asbestos cement and eaves fillers are available.

17.9. Corrugated Sheets

17.9.1 Types consultant should look at other types.not i. 14 Corrugations ii. 8 Corrugations

17.9.2 14 Corrugations: Sheet lengths from 1.22 to 2.44m, width: 975mm, purlin

spacing: 1150mm, side lap: 2 corrugations.

17.9.3 8 Corrugations: Sheet lengths from 1.22 to 3.05m, width: 1000mm, purlin spacing:

1150mm. Side lap 1 corrugation 200mm overlap for 1 and 2 types of sheet, laps to be sealed with martic extrusion.

17.9.4 Minimum guage for roofing sheets: Shall be 0.45mm.

17.10 Flat pan tile roofing

i. Construction: Cable roof with 150 x 50mm merge brackets, 500mm long, fixed with M.S Framing anchors to merge rafter, with build-up fascia and 150x50mm gable board for support of roof battens. 150x50mm rafters are fixed at 900mm centres to 150x75mm wall plate with MS Anchor bolt, cast into reinforced concrete ring beam. 75x50mm timber battens at 300mm centres, 75x50mm joists suspended from rafters with 50x3mm MS Hangers supporting 10mm thick particle boards. 50x15mm cover strip

50

Page 51: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

ground edges. Bituminous paint issued under wall plate. 50x20mm vent battens covering wire netting and 150x50 special fillet piece for eavestile are fixed.

ii. In case where unit tiles are used boarding is strictly recommended with 10mm with felt to be laid as quoted in 17.10i.

17.13 Protection of roof against windstorm To protect the roof against the effect of windstorm the “bottom chord”of the roof trusses should be tied to the wall before fixing the roofing sheets. Also all the eaves of the roof should be ceiled.

51

Page 52: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG.8

Page 53: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 9 TRUSSED RAFTERS

NOTE: The corner assembly, stud assembly at junction of interior partition with external wall (Page 151, fig. 3, 4, 5 and 6) and dimensions of nailed “W” trusses (Page 154) have been adapted from “timber frame–guidein platformconstruction frame “ (council of forest industries of British Colum “Erection of trusses” has been adapted from “notes on of building light timber trusses” (commonwealth experi building station, Dept. of Works and Housing, Crafts wood, N>S>W., Australia).

MAX. SPA BOTTOM TOP CHORD WEB MEMBERS m CHORD mm mm

mm

4.00m 75 x 40 75 x 40 75 x 25 6.75 m 75 x 45 100 x 45 75 x 25 & 75 x 40

8.50 m 100 x 45 100 x 45 100x75 &100x45 FIXED INTO PLACE

Table 15: EXAMPLE OF MEMBER SIZES OF SIMPLE HAILED TRUSSES

NAILED KING –POST TRUSS

ERECTION OF TRUSSES

THREE WORKERS ARE NEEDED. THE

TRUSSES ARE FIRST PLACED ON THE WALL PLATE HANGING UPSIDE DOWN AND TRUSS IS THEN ROTATED UPWARDS INTO THE POSITION AND

WITH PLYWOOD GUSSETS, SUITABLE FOR SPANS UP TO 7.50 M EXTENDING TOP CHORD INDIVIDUALLY SUPPORTED (FOR COVERED VERANDAHS)

NAILED “W” TRUSS WITH PLYWOOD GUSSETS, USING UNCLENCHED 45MM NAILS, SPACED AT EVERY 600MM CENTRES SUITABLE FOR SPANS UP TO 8.70 M.

GUSSET PLATES AND SPACING OF NAILS (9.5mm thick plates)

53

Page 54: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 10

Page 55: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

18.0 CARPENTRY AND JOINERY

18.1 Timber

18.1.1 Timber types: The recommended timber for construction are sound mahogany, opepe or other approved selected timber expressly stated by a timber expert, free from all defects.

18.1.2 Protection against termites: Timber for carpentry and joinery work shall be made thoroughly

termite-proof with approved preservatives listed in subsection 18.1.3. 18.1.3 Approved Preservatives

Tar Oils: Coaltar Creosote, Dursban, Bartoline or approved eual.

Organic solvent: Chlorinated Naphtateness, pentachlorophenol, organic datives of pentachlorophenol. Water-borne type preservatives:

These salts of such elements as copper, chromium, argenic, zinc, mercury, sodium and potassium which are dissolved in water to give a toxic solution free from deposit. The following are available: Copper/chrome, Copper/Chrome/Arsenate, sodium Pentachlorophenate, Mercuric oxide, Magnesium Floursilicate, Copper Sulphate, sodium fluoride. Dursban,bartoline or equally approved

18.1.4 Storage: Timber shall be ordered sawn and prepared as soon as practicable after the issue of

the order to commence and carefully stacked under cover so that the air will freely circulate around it.

18.1.5 Large Scantlings: Large scantling shall be sawn immediately the work commences to allow for

any shrinkage that may take place.

18.1.6 Specified scantling or unwrought work: Specified scantling or unwrought work shall in all

cases be finished sized. For wrought work the thickness specified are finished sizes after planning.

18.1.7 Ends of timbers built into walls: Ends of timbers built into walls shall have 25mm air space left

between the timber and the walling.

18.2 Nails and Screws: Oval or round brads or nails shall be used for fixing all face work and heads shall be properly punched in and neatly puttied. The size of nail to be used shall depend on the nature of work to be executed.

55

Page 56: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

18.3 CEILING

18.3.1 Construction: Suspended ceiling can be built as, jointless, in modular panels, in strips.

18.3.2 Jointless Ceilings: These are quite heavy when plastered metal lathing is used. Stretched

plastic ceiling membranes are also used or self stretchingfibre glass, reinforced P.V.C. sheeting, clipped to extruding wall fixing battens for single spans, of 4 to 15m.

18.3.3 Ceiling boards and Panels: A large variety of different insulative boards, minerals or wood

fibre panels, with their own suspension systems are used.The use of white core plywood as ceiling board should be discouraged,the use of red core plywood should be used.

18.3.4 Strip Ceiling: These are from hardwood, metal or plastic strips with their own fixing systems.

Hardwood strips are normally fixed tongued and grooved to ceiling joist. 18.3.5 Use of plywood: The use of white core plywood for ceiling is not encouraged as they become

infested with insects in no time. Red core plywood is recommended. 18.4 DOORS

18.4.1 Classification: Framed, unframed and flush doors should be well treated

18.4.2 Framed Doors: There are doors with stiles which are framed to the top middle and bottom

rails and comprise the following: Framed ledge, braced and boarded doors, framed and panel door, framed and glazed door, framed and louverdoor, sliding door.

18.4.3 Unframed Doors: These are traditional and inexpensive doors made from vertical tongued

and groove boards which are held in place by horizontal sections called ledges and strengthened by diagonal braces.

18.4.4 Flush Doors: They are semi-solid cored flush doors constructed with 100mm stiles, 100mm

top and intermediate, 150mm bottom rail and 25mm vertical stiffeners at 50mm centres and covered on both sides with 6mm plywood glued and pressed and securely fixed to wood framing. All flush doors required to be veneered on one or both sides. It should be faced with 5mm selected Hyedua veneered plywood (Grade 1 type WBP).

18.4.5 Fixing of Doors: All doors and other framed works shall be put together immediately upon the

general work being commenced, but shall not be glued and wedged up until the joinery work is prepared in readiness for immediate fixing. All joinery immediately after delivery to the site shall be stored under cover and protected from weather. Hidden faces of joinery timber shall be printed before fixing.

18.4.5 Doorway Sizes

Timber should be well treated

a) Doorway Openings: Doorway openings within dwelling units shall be designed to accommodate not less than the door sizes in Table 16.2A for swing-type doors. Where folding doors are to be provided, the same openings apply.

56

Page 57: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Table 18.2A DOOR SIZES

MINIMUM SIZE OF DOORS

At entrance to Width Height mm mm

Dwelling unit (required

entrance) vestibule or

entrance hall 810 1.980

Stairs to a floor level that

contains a finished space

All doors in at least one line of

passage from the exterior to

the basement 810 1.980

Utility

Walk-in closet 660 1.980

Bathroom, water-closet,

shower room 160 1.980

Rooms not mentioned above,

exterior balconies 160 1.980

Column 2 3

b) Doors to public water-closet rooms: They shall not be less than 810mm in width and 1980mm in height.

18.4.6 Exterior Doors

a) Thickness: Exterior doors shall be at least 44mm thick, except that doors for secondary entrances serving single dwelling units or balconies may be 35mm thick if of solid wood, solid core or stile and rail construction. Storm or combination doors shall be at least 35mm thick for wood doors and 25mm for metal doors.

b) Unprotected Exterior Doors: Where an exterior door opening is not completely protected

from driving rain, it shall be provided with a sill that slopes to the exterior and the sill caulked with suitable caulking to prevent entry of water.

c) Steel frames for exterior doors: It shall be painted with a rust inhibitive paint or otherwise

treated before erection to prevent corrosion.

18.4.7 Interior Doors

a) Interior wood doors in dwelling units other than closet doors or cupboard doors: They shall be at least 35mm thick.

57

Page 58: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

b) Interior wood doors to rooms or spaces used for storage, laundry, drying, vestibules, recreation or water closets in apartments, buildings but not within dwelling units: They shall be at least 44mm thick.

18.4.8 Glass Doors

i) Thickness: Glass thickness and the size of glass for doors shall conform to Table 18.4A.

Table 18.4A Thickness and size of Glass for Doors

Minimum Glass Weights or Thickness Maximum Perimeter m

510gm 2.03

680gm 3.05

907gm 4.06

4.8mm 4.57

5.6mm Not limited

18.4.9 Garage Doors

a) Size: Garage doors shall be not less than 2.44m wide for one car and 4.27m wide for 2 car widths. The height of the door opening with the door in the open position shall be not less than 1.93m. For parking garages, garage doors shall be not less than 3.05m wide for one-way traffic and 4.88m for two-way traffic.

b) Wood doors: It shall be at least 44mm thick in side hinged or one piece overhead and not less

than 35mm thick if sectional overhead.

c) Steel and Aluminium doors: It shall be made with suitably braced frames clad with not less

than 0.6mm galvanized steel prepared for paint.

18.4.10 Overhead Doors: Overhead doors shall have suitable springs or counter-balances and weather stops.

58

Page 59: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 11

Page 60: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 12 TYPES OF DOOR OPENINGS

SIDE-HUNG, OUTWARD OR INWARD OPENING The direction of opening is also described as clockwise or anti-clockwise.

COMBINATION OF OUT-WARD AND INWARD OPENING DOOR:

This is used where and inward opening mosquito screen is required.

SIDE-HUNG SWING DOOR, SINGLE LEAF, DOUBLE SWING: The door can also be a double leaf door. It is used in Hospitals, canteens, Restaurants, etc.

SLIDING DOORS: Many variations are possible which are determined by the choice of track. The doors are normally top hung with bottom guide, with double or triple track, or sliding in a cavity wall. A sliding door can be arranged to have folding leaves. Internal folding partitions are sliding-folding doors PEDESTRIAN OR PASS DOORS TYPES OF DOORS

TWO LEAF DOUBLE SLIDING –FOLDING DOOR DOOR LEAVES FOLDING 90º

TWO LEAF DOUBLE SLIDING-FOLDING DOOR Door leaves folding 180º .

THREE LEAF SLIDING-FOLDING DOOR: Door leaves folding 180º

CENTRE HUNG SLIDING-FOLDING DOOR WITH HALF LEAF: Door leaves folding 90º

INDUSTRIAL DOORS: Industrial doors are straight sliding doors or sliding-folding doors, Top hung with bottom guide on top hung with botton roller. SPECIAL DOORS: FLEXIBLE DOORS: These are specified for positions where the user has his hands otherwise occupied (pushing a trolley, driving a service vehicle in a warehouse etc.) AUTOMATIC DOORS: These are doors with imitating, sensing and timing devices, actuating a motor gear which physically moves

60 the door (for sliding doors, folding doors, swing doors, up and down doors and gate)

Page 61: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 13 FRAMED AND PANNELED DOORS

DOORS DOOR 4: FRAMED AND PANNELED DOOR Interior decorative door, the wood panels are raised and fixed tongued and grooved into stiles and rails. The door is fixed with two pairs of brass butt hinges to 125 x 50 rebated door frame. DOOR 5 : FRAMED AND PANELLED DOOR

Interior door panels are from plywood to mm thick, fixed into stiles and nails. The door is fixed with two pairs of brass butt hinges to 125 x 50 door frame. Door furniture for both doors: Lever handle and mortice lock. FRAMED AND PANELLED DOORS

61

Page 62: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

18.5 WINDOWS

18.5.1 Natural Lighting and Ventilation: This section applies to installation of windows and to the requirements for natural lighting and ventilation to be provided by windows in all buildings.

18.5.2 Window types for the tropics

i. Casement windows ii. Pivot windows iii. Sliding windows iv. Louvre windows v. Awning and projected windows vi. Security or Guard windows

a) Casement Windows: Casement windows can be used as inward opening mosquito screen together with outward opening jalousied shutter, which when closed and bolted from the inside, saves burglar-proofing, they can be made entirely from well seasoned timber without glass. Top-hung open out casements, boarded or shuttered, can be used together with an inward opening mosquito screen. Casements are fixed with casement stays. These windows achieve total window opening. They can, if so required be arranged with fixed picture windows (plain glazed). Case must be taken for easy cleaning.

b) Pivot Windows: All pivot windows should have safety catches to prevent uncontrolled

movements. Horizontal pivots can be fixed to reverse for cleaning. Pivot windows achieve about 90% of window opening. They are normally metal framed and suitable only for buildings which require no mosquito and burglar proofing.

c) Sliding Windows: Sliding windows achieve up to 50% of the total window opening. Horizontal

sliding windows must be drained through the sliding channel at the bottom of the window, if no suitable protection is provided outside against rainwater sliding down the face of the window. Sliding windows are normally metal framed windows from steel and aluminium with many different designs available. They can be produced with mosquito screens which can be clipped onto the frame from the inside and removed for cleaning. Burglar proofing has to be provided separately.

d) Louvre Windows: These are in principle a series of horizontal pivots. Louvres can be made

from timber, metalco”or Louvresglass e.whichg.-Louvre“Ecarriesarefromfixed aluminium carries are usually fixed on a timber soft frame in which mosquito and burglar proofing can be incorporated. Window achieves 90% of total opening.

62

Page 63: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

e) Awning and projected Windows: These are typical metal framed windows with different members of ventilators which open together by normal or mechanical control. Frames can take clipped-on mosquito screens. Window frames should be fixed on timber sub frames.

f) Security or guard Windows: These windows are normally used in prisons. They are bottom

hung, inwards opening metal framed windows with vertical bars as part of the frame.

Table 18.5A MINIMUM GLASS FOR ROOMS OF RESIDENTIAL OCCUPANCY

Location Unobstructed Glass Area

Laundry, basement recreation room,

unfurnished basement or cellar 4 per cent of area served

Water-closet room 0.37m2

Kitchen:

Kitchen Space

Kitchen Alcove 13 per cent of area served

Living rooms, Dining rooms, Bedrooms and

other furnished rooms not mentioned 13 per cent of area served

63

Page 64: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 14: WINDOWS

1. CASEMENT WINDOWS: A. slide –hung open in B. side –hung open out c. Top - hung open out

Casement windows can be used as inward opening mosquito screen together with an outward opening jalousied shutter, which, when closed and bolted from the inside, saves burglar –proofing. They can be made entirely from well- seasoned timber without glass –Top-Hung open out casement Boarded or shuttered, can be used together with an inward opening mosquito screen

Casements are fixed with casement stays. These windows achieve total window opening. They can, if so required, be arranged with fixed picture windows (Plain glazed). Care must be taken for easy cleaning.

2. PIVOTS:

d. Vertical Pivot, e. Off-Centre vertical Pivot f. Horizontal Pivot.

j. Sliding windows are normally metal framed windows from steel and aluminium with many different designs available. They can be produced with mosquito screens which

can be clipped on to the frame from the inside and

removed for cleaning burglar proving has to be

provided separately

4. LOUVRE WINDOWS: These are, in principle, a series of horizontal pivots. Louvers can be made from timber, metal and glass, e.g. “Naco” louverd in NACO-Louvre carriers from aluminium, carriers are usually fixed on a timber subframe in which mosquito and burglar proofing can be incorporated, window achieves 90% of total opening.

All Pivot windows should have safety catches to prevent uncontrolled movements. Horizontal Pivots can be fixed to reverse for cleaning. Pivot windows achieve about 90% of window opening. They are normally metal framed and suitable only for buildings which require no mosquito and burglar proofing.

3. SLIDING WINDOWS:

5. AWNING AND PROJECTED

WINDOWS: These are typical metal framed windows with different number of ventilators which open together by manual or mechanical control. Frames can take clipped-on mosquito screen window frames should be fixed on timber sub frames.

g. Vertical Sliding (Developed in the 18th 6. SECURITY OR

GUARD WINDOWS

century in Europe as “Double

h. Horizontal sliding –Two moving sashes

i. Horizontal sliding-One moving sash, one fixed sash.

j. Horizontal sliding –Two moving sashes, one fixed

sash

k. Horizontal sliding –Three moving sashes

h. Sliding windows achieve up to 50% of the total

window opening. Horizontal sliding windows must

be drained through the sliding channel at the bottom

of the window, if no suitable protection is These windows are normally used in

provided outside against rainwater running down the face

prisons. They are bottom hung, inwards

of the window.

opening metal framed windows with

64

vertical bars as part of the frame

WINDOW TYPES SUITABLE FOR TROPICAL

Page 65: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

F. FINISHES

19.0 WALL AND FLOOR FINISHES 19.1 Wall Tiles

19.1.1 Wall Tile base and adhesive: Ceramic tile shall be set in a mortar base or applied with adhesive. Plastic tile shall be applied with an adhesive.

19.1.2 Mortar for Ceramic Tile: When ceramic tile is applied to a mortar base the cementitions

method shall consist of 1 part Portland cement to not more than ¼ part lime by volume. This shall be mixed in the ratio between 1:3 and 1:5 ( not less than 3 or more to 5 parts of sand per part of cementitions material by volume). Ceramic tile applied to a mortar base shall be thoroughly sealed and pressed into place forcing the mortar into the joints while the tile is wet. 12mm screeded backing to concrete or block wall shall be provided to receive wall tiles.

19.1.3 Adhesive for Ceramic Tile: Adhesives for placing ceramic or plastic tile shall be applied to the

finish coat of plaster that has been smoothened to an even surface or to masonry provided the masonry has an even surface.

19.2 FLOORING

19.2.1 Floor Finishing Materials: Finished flooring in bathrooms, kitchens, public entrance halls, laundry and general storage areas shall consist of resident flooring, concrete terrazzo, ceramic or other types of flooring providing similar degrees of water resistance.

19.2.2 Floor Tiles: Floor tiles shall be laid and jointed in cement and sand in the ratio 1:3 floating

backing. 30mm screeded bed shall be on concrete floor to receive floor tiles.

19.2.3 Suspended reinforced concrete floor: A suspended reinforced concrete floor can be cast

monolithically in situ or it can be formed of a series of pre-cast units in the ratio 1:2:4.

19.2.4 Upper Floors: An upper floor spans between supporting structures, reinforced concrete

frames (columns and beams) or load bearing walls in the ratio 1:2:4.

19.2.5 Wood Sleepers: Wood Sleepers supporting finished flooring over a concrete base on ground

shall be not less than 25mm by 40mm and shall be treated with a soaking coat of approved wood preservative.

19.2.6 Wood Strip Flooring

a) Dimensions: The thickness of wood strip flooring shall conform to Table 19.2.5A.

65

Page 66: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Table 19.2.5A WOOD STRIP FLOORINGS

Type of Flooring Maximum Joist Minimum Actual Structures of Flooring, mm

Spacing mm with sub-floor no sub-floor

Interior or 400 20 20

Exterior 600 20 32

Use

b) Underlay: Wood strip flooring shall not be laid parallel to lumber sub-flooring unless a

separate underlay is provided.

c) Laying of Wood Strip Flooring: If wood strip flooring is applied without sub-floor, it shall be laid at right angles to the joists so that the end joists are staggered and occur over supports or are end matched, it shall be laid so that no two adjoining strips break joints in the same space between supports and each strip bears on no fewer than two supports.

66

Page 67: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

20.0 IRONMONGERY

20.1 Screws: All ironmongery shall be fixed with screws of the same material or shall be of an

approved type for the particular fittings. 20.2 Locks: All locks and fittings are to be tested and well oiled before fixing.

20.3 Hinges:

20.3.1 Brass butt hinges with steel or brass pin are recommended. For panel doors 3 number 100mm brass hinges per door are recommended.

20.3.2 Parliament Hinge: A parliament hinge shall be used where a variation of a fixed pin hinge for

thick frames are required to open 180o 20.3.3 Storm proof butt hinge, cranked 8mm: May be used for casement windows 65mm (100mm

for doors)

20.3.4 Casement Stay: For securing an open casement window into position with stay bar and fixed

pin (fixed to frame). Normally plant or channel sections of brass or Aluminium extrusions, from 200 to 300mm.

20.3.5 Fanlight Stay: For retaining top hung vent in the open position. 20.3.6 Friction Stay: For casement windows, top and bottom, hung vents.

20.3.7 Stay pins: Depending on the joinery application different stay pins may be specified. 20.3.8 Cross tongue fastener: With hook and mortice plate.

20.3.9 Wedge type fastener: With hook plate and fastener.

20.4 Welding: All units shall be prefabricated in the shop wherever possible and only a minimum of site welding employed.

21.0 PLUMBING INSTALLATION

21.1 Potable Water: Buildings are supplied with potable water from an approved public or

community system through tributary pipelines, boreholes or handdug wells. 21.2 Washrooms: Every building must be equipped with toilet facilities.

67

Page 68: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

21.3 Piping Facilities: Where a piped water supply is available, piping for cold water shall be connected to every kitchen sink, bathtub, shower and laundry area. Piping for cold water shall be run to every water closet and hose bib.

21.4 Sewerage and Waste disposal: Building sewers shall discharge into a public sewage system

where such system is available. Where a public sewage system is not available, the building sewer shall discharge into a private sewage disposal system such as a septic tank and disposal field provided the design and installation is approved. A septic tank must be accessible for dislodging.

21.5 Soil Pipes: Soil pipes are normally 100 to 150mm in diameter, waste pipes from 32mm to

50mm in diameter for domestic appliances and 16mm for non-domestic appliances e.g. in hotels and canteens. Main sewer drain pipes vary in size.

68

Page 69: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

22.0 ELECTRICAL INSTALLATION All electrical materials used must be approved by Ghana Standard Board or other

competent authority. Electrical installation must be carried out by qualified persons.

22.1 Distribution: Electricity supply to a building could be connected either overhead or underground from a local transformer sub-station where the supply voltage from the town grid has been reduced to three phase, four wire 415/240 volt, 50 cycles per second supply. The supply is distributed by 3 time cable with a neutral wire which is earthed at the substation. The voltage between any phase wire and neutral is 240 alternating voltage. A three phase supply to a building achieves a more balanced load on the phases by serving different areas of the building with different phases.

22.2 Fuses: Use approved fuses with correct ratings only.

22.3 Circuit Breaker: These are automatic switches which turn themselves on when too much

current passes. They are easier to be turned on again than to replace or rewire a broken fuse although the later is cheaper and more useful for the self help person if fuse wire is available.

22.4 Earthing:

Buildings must be properly earthed with approved earthing material. It is recommended that where the earthing material is buried the area should not be concreted.

22.5 Cables

22.5.1 Types: Cables available are single core, twin core, twin core with earth, three core with earth.

Single Core: These have one conductor only which is enclosed in sheath of insulating material.

Twin Core: These have two conductors separately insulated and enclosed in an outer sheath of the same insulating material.

Twin Core with earth: These are two conductors and an earth wire, each separately insulated and enclosed in an outer sheath.

Three Core with earth: There are three conductors and an earth wire each separately insulated and enclosed in an outer sheath of the same insulating material.

An expert advice should be sought on the proper usage of these cables.

22.6 Lighting Outlets

22.6.1 Exterior Lighting: An exterior lighting outlet with fixture controlled by a wall switch located with the building shall be provided at every entrance of the buildings of residential occupancy.

69

Page 70: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

22.6.2 Lighting Outlets: Lighting outlets with fixture controller by a wall switch shall be provided in kitchens bedrooms, livingrooms, utilityroom, dining room, bathroom, water closet room, vestibules and hallways is dwelling units.

22.7 Emergency lighting

General

22.7.1 This section of the guide is concerned with that part of the emergency lighting necessary to enable persons to move within and escape from a building if the normal lighting fails at the time of an emergency (i.e. fire, earthquake)

22.7.2 Generally, emergency lighting by electricity should be provided in all residential, business, mercantile and medium and low hazard in industrial occupancy.

22.7.3 Emergency lighting fitted with batteries and chargers conforming to BS 5266 should be heated along all escape routes (corridors), stair landings where natural light is not sufficient and locations of possible danger / panic during a power outage

22.8 Lightning arrester All buildings must be protected with a well grounded lightning arrester.

22.9 Fire safety

Appropriate fire detection and fire fighting devices must be installed in all buildings.

22.9.1 Fire detection and alarm devices.

Table 22.9A gives basic fire detection and alarm devices recommended for various areas in the building.

Table .22.9A Fire detection and alarm devices.

Device Recommended Area

Smoke detector (battery Bedrooms, living areas

operated)

Heat detector (battery Kitchen and laundry

operated) areas

Gas detector Kitchen

22.9.2 Fire Extinguishers

Every building should have at least one 6kg dry powder and 2/3kg Co2 fire extinguishers. These fire extinguishers shall be located within travel distance not exceeding 18m and shall be mounted on a wall not more than 1.2m high.

At least one fire blanket shall be placed in the kitchen.

22.9.3 L.P.G Installation

70

Page 71: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

All portable L.P.G bottles shall be located outside the building when in use.

22.9.4 Fire Instructions and drills Fire instruction shall be given by a competent person at such intervals as will ensure that all occupants are instructed at least twice every 12 Months.

Instructions and drills for occupants shall cover the following matters: i. The action to be taken upon discovery a fire. ii. The action to be taken upon hearing the fire alarm. iii. How to call Ghana National Fire Service. iv. How to use fire fighting equipment. v. Knowledge of the escape routes in the building.

22.9.5 Escape Routes

i. Escape routes should be arranged and located in such a manner to allow people to

move within the building and also evacuate the premises quickly and safely.

ii. Doors, exits and routes shall have standard safety signs visible day and night to direct

occupants in any emergency situation.

22.9.6 Direction of Opening of Doors

Doors should be hung in such a way that it will not obstruct any escape routes. (see fig.)

1.2m

Room 1

Room 2

Doors opening into escape route are not acceptable.

1.2m

Room 1 Room 2

71

Page 72: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Correct way of fixing doors along escape route.

Final exit doors should be opened easily from the inside by occupants escaping from the building Doors fixed along escape routes should be fitted with vision panel where appropriate.

22.9.7 EXIT AND DIRECTIONAL SIGNS

1. Any exit which is not a normal route of travel from a building should be indicated by notice bearing

the words “Emergency Exit in should be displaced immediately above the exit opening, where

possible. Where this is

not possible, a position should be chosen where the notice is least likely to be obstructed and most likely to be seen.

2. At suitable points along an escape route where an exit cannot be seen or where a person escaping

might be in doubt as to the location of an exit, a notice should be provided bearing, in letteringEXIT”

ofandnecessaryappropriatthe directional arrow. Such notices should be fixed in conspicuous

positions, where possible 2 metres and 2.5metres above floor level. Exit and directional notices should be internally or otherwise illuminated so as to be clearly legible.

RECOMMENDED LETTERING SIZE FOR EXIT SIGNS

Viewing distance Letter Height

< 20m 50mm

20m to 30m 75mm

30m to 40m 100mm

>40m 125mm

72

Page 73: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

23.0 PAINTING

All paints shall be the best quality obtainable and of approved manufacturer, guaranteed anti-fungus and suitable for use in tropical countries. Where possible fire resisting paint should be used on finished surfaces.

23.1 Primers: Primers shall be as recommended by the manufacturer for each type of paint, having regard to such type of paint and the surface to be coated. NOTE: All carpentry and joinery hardwood should be primed before fixing.

23.2 Mixing: Different types or brands of paint shall not be mixed together. Paint shall be thoroughly stirred up in their original containers. Kettle shall be clean and the paint kept clean and stirred during use. Any skins that may form shall be entirely removed before paint is used.

23.3 Preparation for commencement of work: Before any preparatory work is commenced all ironmongery and similar removable articles shall be removed and only replaced after the final decorative coat is dry and hard.( surface preparation means sand papering scrapping and application of putty).

23.4.1 Fittings such as switches and similar articles which cannot conveniently be removed shall be effectively covered during painting operation.

23.4.2 Floors shall be protected from droppings.

23.4.3 Painting process: Apply

i. Primer ii. Under coat iii. Finish coat

23.4 Protection of wet painted surfaces: Adequate care must be taken to protect surface while wet by the use of screens and “wet paint” si

73

Page 74: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

G. EXTERNAL WORKS

24.0 DRAINAGE 24.1 Scope: This chapter applies to subsurface drainage and to surface drainage. 24.2 Installation

24.2.1 Drain Tile: Draw tile or pipe shall be laid on undisturbed or on well comparted soil.

24.2.2 Granular Cover: The top and sides of drain pipe shall be covered with not less than 150mm of

crushed stone or other clean granular material.

24.3 Drainage Disposal

24.3.1 Drain Pipe: Drainpipe shall drain to a sewer, drain ditch or dug well.

24.3.2 Dry Wells(soakaway): Dry wells shall not be less than 4.57m from the building foundations

and located so that drainage is away from the building. Dry wells may be used only when located in areas where the natural groundwater level is below the bottom of the dry well.

24.4 Surface Drainage

24.4.1 Surface Drainage: The building shall be located or the building site graded so that water will not accumulate at or near the building.

24.4.2 Location of surface drainage: Surface drainage shall be directed away from the water supply

well or septic tank disposal bed.

24.4.3 Interference with surface drainage: Where runoff water from a drive way is likely to

accumulate or enter a garage, a catch basin shall be installed to provide adequate drainage.

24.4.4 Downspouts: Where downspouts are provided and are not connected to a sewer, provisions

shall be made to prevent soil erosion.

24.4.5 Rain Harvesting: Storage tanks for harvested rain water should be located at a

higher position than septic tanks.

25.0 RETAINING WALLS AND REVETMENTS

The construction of retaining walls and revetments are key to the prevention of soil erosion and landslides.

74

Page 75: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

25.1 Types: Temporal and Permanent Structures.

25.2 Temporal Structures: These are retaining structures which are upholding the sides of an

excavation in loose ground. 25.3 Permanent Structures: Retaining walls and basement walls.

25.4 Revertments: These are surfacing of soil banks or cutting with stones, bricks or concrete to

retain and stabilize the soil and to prevent erosion for landscaping and reservoir walls.

25.5 Gravity walls: These are walls which depend for stability on their own mass and dead weight.

They are up to 2m in height.

25.6 Flexible walls: these are walls designed in such a way that they act as a cantilever beam or

arch between fixed supports.

75

Page 76: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

FIG. 15: RETAINING WALLS AND REVETMENTS A

GRAVITY WALLS: THESE ARE WALLS WHICH DEPEND F STABILITY ON THEIR OWN MASS AND DEAD WEIGHT. THEY ARE UP TO 2M IN HEIGHT.

1. GRAVITY RETAINING WALL BUILT WITH STONES WITH GRANULAR BACK FILL AND 150MM DIAMETER WEEP HOLES AT 4M CENTRES. FACE OF WAL BATTERED 45º FOR DRY SET WALL OR 20º FOR WALLS SET IN MORTAL. 2. PROPORTIONS OF A GRAVITY WALL

3. GRAVITY RETAINING WALL IN CED CONCRETE. 4. GRAVITY RETAINING WALL BUILT WITH BRICKS, SUITABLE FOR LOW HEIGH TO 1.5M AND NO GRE PRESSURE. IF THE WALL IS TO BE TOGETHER, IT SHOULD BE BATTERED AT MAX 12 OR BUILT CURVED FROM BASE

.

5.

B. FLEXIBLE WALLS: THESE WALLS ARE DESIGNED IN SUCH A WAY THAT THEY ACT AS A CANTILEVER, BEAM OR ARCH BETWEEN FIXED SUPPORTS

CANTILEVER WALLS: THESE ARE USUALLY BUILT IN REINFORCED CONCRETE WITH DIFFERENT CANTILEVERS AS SHOWN DOTTED. THEY ARE USED FOR HEIGHTS UP TO 7.5 M CANTILEVERS, BEAM ARCH BETWEEN FIXED SUPPORTS

6. PROPOSITIONS OF CANTILEVER WALL.

THESE ARE NORMALLY USED FOR RETAINING WALLS OF GREATER DEPTH AND HEIGHT WITH VERTICAL OUT

TRESSES AND ADDITIONAL STIFFENING IN FORM OF HORIZONTAL RIBS.

. C. REVETMENTS:

BUTTRESS (INCOMPRESSION) COUNTERFORT (INTENSION) THESE ARE SURFACING OF SOFT BAGS O

CUTTINGS WITH STONES BRICKS OR CONCRETE TO RETAIN AND STERILIZED T SOUL

AND TO PREVENT EROSION76 FOR LANDSCAPING RESERVATION

Page 77: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

26.0 FENCES AND HEDGES

26.1. Common Fencing materials: Galvanised or PVC coated chainlink and barbedwire fixed to concrete posts, timber fence, Hedges, concrete fence and steel fence.

26.2 Concrete Fence: Concrete can form a complete fence wall in form of prefabricated decorated blocks or is normally used for fence posts in conjunction with other materials.

26.3 Steel Fence: Galvanised steel bars or hollow tubes are used in areas where unclimbable

fencing is required. These rigid steel barriers can incorporate panels of different materials, PVC coated wire mesh or barbed wire.

26.4 Hedges: For shelter and covers, hedges, which bend with the wind are more successful

than rigid screens or solid fences.

77

Page 78: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

GLOSSARY

A.

Aggregate: Sand, gravel etc for mixing with cement to make concrete.

Alkali: Any of various soluble chemical bases, especially a hydroxide or carbonate of an alkali metal that combine with acids to form salts.

Arrester: To bring something to a stop.

B.

Bit: A replaceable drilling, boring, etc devise, part of a compound tool.

Bearing Capacity: ability of the oil to carry a load.

Beam: Any of the principal horizontal supporting members of a building.

Basement: The part of a building that is wholly or partly below ground level.

Backfill: Soil dug out of a hole or trench and later used to refill it.

C.

Columns: A pillar that usually consists of a square, rectangular of square shaft, a capital, and a base.

Chimney: A vertical structure incorporated into a building and enclosing a flue or flies for carrying of smoke. Especially the part of such a structure extending above a roof.

Concrete: Hard strong building material made by, mixing a cementing material e.g. Portland cement, and a mineral aggregate, e.g. sand and gravel, with sufficient water to cause the cement to set and bind the entire mass.

Cement: A powder containing lime and clay that is used as a binding agent in mortar and concrete.

Carborundum: Any of various abrasive materials (blend of carbon and carundum)

Conduit: A pipe, tube, or tile for protecting electric wires or cables.

Chase: A groove cut in a surface for a pipe, wire etc.

Corrugated: Folded into alternating parallel ridges and grooves.

Circuit: A complete path of an electric current.

Code: A systematic body of laws, especially one established by statutes. 78

Page 79: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Carpentry: The art or trade of a carpenter. The art of shaping and assembling structural woodwork.

Cables: An assembly of electrical wires insulated from each other and surrounded by a sheath.

Cure: Process of hardening of a material e.g. concrete etc.

Chutes: An inclined plane, channel, or passage down which things may pass.

Compression: The action of compressing or being compressed to press or squeeze something together.

D.

Deleterious: Harmful and detrimental

Drain: To carry away the surface water.

Dampproof: To make a (a wall or building impervious to damp by means of a damp course).

E.

Excavation: To form a cavity or hole in something by hollowing or digging.

Earthing: To connect (an electrical device) to earth.

Epidemics: An outbreak of a disease affecting many individuals within a population.

Extraneous: Not forming an essential or vital part, irrelevant.

Earthworks: An enforcement, field fortification, etc made of earth.

F.

Foundation: An underlying natural or prepared base or support especially the masonry substructure on which building rests.

Formwork: A wooden structure that holds concrete in place and in shape while it hardens.

Fuse: An electrical safety device that includes a wire or strip of fusible metal that melts and interrupts the circuit when the current exceeds a particular value.

Fiberglass: Glass in fibrous form used in making various products, e.g. textiles and insulation materials.

Flashing: Sheet metal used in waterproofing a roof or the angle between a vertical surface and a roof.

79

Page 80: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

G.

Graft: splice, attach, join, fix, embed, implant, insert.

Geology: Science that deals with the original structure, composition, and history of the earth, especially as recorded in rocks.

Geotechnical: Foundation underpinning, soil modification, liquefaction.

Gussets: A plate or bracket for strengthening a joint in a timber or a metal framework.

H.

Heave: In geology, a horizontal displacement, e crust.

Hydration: To cause ( a substance) to take up or combine with water or its constituent elements.

Hydrostatic: Relating to or denoting liquids at rest, or the pressure exerted by them.

Hardcore: Compacted rubble or clinker used especially as foundation or roads, paving, or floors.

I.

Ironmongery: Hardware for joinery.

Infestation: To spread or swarm in or over (something) in a troublesome or undesirable manner.

Insitu: In the natural, original, or permanent position.

Insert: To introduce something into the body of something.

J.

Joinery: The craft or trade of a joiner. Woodwork.

Joists: Any parallel small timbers or metal beams that support a floor or ceiling.

L.

Landslide: Rapid movement of rock, earth etc down a slope, or the moving mass of rock, earth, etc itself.

Lighting: The flashing of light produced by a discharge of atmospheric electricity between two clonds or between a clond and the earth.

80

Page 81: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Lintel: A horizontal architectural member spanning and usually carrying the load above an opening.

Laterite: A usual red clay formed from rock decay and consisting especially of iron oxides and aluminium hydroxides.

Lime: A caustic solid consisting of calcium oxide and some magnesium oxide, obtained by heating calcium carbonate e.g. in the form of shells or limestone to a high temperature, and used in building and in agriculture.

M.

Matrix: A mould in which something is cast or from which a surface in relief e.g. a piece of type, is made by pouring or pressing.

Meteorology: The science of the atmosphere and its phenomena, especially weather and weather forecasting.

Mould: A cavity, dish, or form in which a substance e.g. a jelly or a metal casting is shaped. A frame around which an object is instructed.

Mortar: Mixture of cement, lime, gypsum plaster, etc with sand and water, that hardened and is used to join bricks, stones etc or for plastering.

Masonry: Something build of stone or brick.

P.

Profile: A vertical section of a soil form ground surface to the underlying material.

Pozzolana: Ash used in making hydraulic cement.

Plumbing: The system of pipes, tanks, and fixtures installed or required in supplying the water, sanitation, and heating in a house or building. Preservative: Something that preserves or has the power to preserve specifically a substance used to protect a vulnerable material against decay, discoloration, or shortage.

Purlin: Horizontal beam in a roof bracing the rafters.

Pulley: A wheel with a grooved rim that is used with a rope or chain to change the direction and point of application of a pulling force.

Precast: Of concrete or things made of concrete: cast in the form required before being placed in its final position.

81

Page 82: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Primer: Material used in priming a surface, especially a type of paint used as first coat on plaster, wood etc.

Panels: A separate or distinct part of a surface, e.g. a thing usually rectangular board set in a frame e.g. in a door.

Preumatic: Tyre that is filled with air under pressure.

R.

Raft: A foundation slab for a building usually made of reinforced concrete.

Ridge: The line along which two upward sloping surfaces meet specifically the top of a roof at the intersection of two slopping sides.

Revetment: A facing of stone, concrete etc built to protect a wall or retain an embankment.

Reveal: The side of an opening in a wall for a door or window, especially the part that has between the frame and the outer surface of wall.

Rafter: Any of the parallel beams that form the framework of a roof.

Reinforcement: Material used to increase strength of materials especially concrete.

S.

Struts: To provide, support, or stiffer (something) with strut. A structural piece/designed to support or strengthen a framework by resisting pressure with directive of its length.

Spacers: To place (two or more things) at intervals or arrange (than) with space between.

Slab: To divide or form (something) into slabs.

Sewerage: A system of sewers. The removal and disposal of surface water by sewers.

Scantling: Small piece of timber e.g. an upright piece in the framework of a house.

Sediment:The matter which subsides to the bottom, from water or any other liquid settlings; lees; dregs.

Shale: A timely stratified or laminated rock formed by the consolidation of clay, mud, or silt.

Shingle: To cover (a roof etc) with shingles.

Sheathing: A covering of boards or water proof material on a timber roof or the metal places on a ship’s hull.

82

Page 83: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Staple: A small piece of wire with ends bent at right angles which can be driven through thin sheets of materials.

Seismicity: Shock, earthquake, from shaking.

Substructure: Any structure that forms the foundation or framework on which something is constructed.

Sandcrete: Block made of sand and cement.

Staircase: A structure or part of a building containing a stairway. A flight of stars with the supporting framework, caring, and baldness.

Stairway: One or more flight of stairs, usually with intermediate landings.

T.

Tie: A structural element e.g. a rod or angle iron, holding two pieces together.

Tsunami: A huge sea wave that is produced byunderwater earth movement or volcanic eruption causing svere devastation if it reaches land.

Tributary: Sand of a stream or river: feeding a larger stream or river.

Terrazzo: A mosaic flooring made by embedding and polishing small pieces of marble or granite in mortar.

Trusses: An arrangement of beams rafters girders etc forming a rigid framework e.g. in a roof or bridge.

V.

Voltage: An electric potential difference, electromotive force measurement in volts.

Vibrator: A vibrating electrical apparatus used in message.

Veneer: Thin layer of wood, plastic etc of superior appearance quality, hardness used especially to give a decrative finish to cheaper material.

Vestibule: A lobby or chamber between the outer door and the interior of a building.

W.

Windstorm: Storm with high winds but little or no rain, snow, etc.

Wrought: Said of metals beaten into shape by tools.

83

Page 84: NATIONAL BUILDING GUIDE FOR LIGHTLY LOADED STRUCTURES …

Waterproof: Impervious to water, especially covered or treated with a material to prevent passage of water.

84