Nathan Hale High School Modernization
Budget: $87 million
Schedule: summer 2007 to summer 2011
Delivery Method: multi-prime (design/bid/build and GC/CM)
Size: 15,000 SF (new) and 205,000 SF (renovation)
Scope: Demolish the 1973 library addition and portables, new addition for
library and arts classrooms, and renovate a 1963 high school campus
including seismic and life safety, ADA, exterior envelope, roofing, interior
finishes, furnishings, mechanical and electrical systems, site improvements.
Program Manager Prime Architect Prime Contractors
Revised Plan:
• Accelerate start of design and construction by two years
• Renovate in phases while school is occupied
• Complete the project one year early
Phasing Plan
Floor Plans
Courtesy of Mahlum
Under construction: Placing new grade beams for Project 1 art classrooms
3D BIM modeling was used in Project 2 for MEP coordination
Before/after of a typical
hallway
Renovated classroom
New studio and teaching spaces for KNHC / C89.5 in Project 1
Photo by Benjamin Benschneider
Completed project in fall 2011
Renovated south (student) entry
View of renovated Court 03
Photo by Benjamin Benschneider
View of new library addition (Phase 1) from 110th Street
Photo by Benjamin Benschneider
Nathan Hale High School
Performance:
Schedule: Budget: Change Orders: Sustainability: Innovation:
Community Outreach: Awards:
Core PM Team:
Senior Project Manager:
Construction Managers:
Project Engineer:
Modernization
11 months early (building) under budget * (0.1%) 13.7% ** WSSP Phased/occupied, BIM, GC/CM, portables/TI, sustainability, site conditions Over 225 documented outreach events AIA and ASHRAE (nominated) CMAA (nominated/pending) CEFPI Regional (nominated/pending)
Ian Kell (Heery) Tracy Silla and Jill Kurfirst (DKA) Earl Edwards (SSD)