Upload
ashish-chaudhari
View
222
Download
0
Embed Size (px)
Citation preview
8/4/2019 Nar_IWMP_1
1/180
District Watershed Development Unit | Narmada
NANI KORVAI
IWMP-1DETAILED PROJECT REPORT
8/4/2019 Nar_IWMP_1
2/180
District Watershed Development unit Narmada Page 2
1.1 Project Background ....................................................................................................................................................................................................................................................... 11
Table no.1: Basic project information ....................................................................................................................................................................................................................... 12
1.2 Need of Watershed Development Programme ................................................................................................................................................................................................... 14
Table no. 2.1 Criteria and weightage for selection of watershed .................................................................................................................................................................... 15
Table no.3: Watershed information ........................................................................................................................................................................................................................... 16
1.3 Other developmental projects/schemes running in the Project area ........................................................................................................................................................ 17
Table no.4: Developmental programmes running in the project area: ........................................................................................................................................................ 17
Table no. 5: Previous Watershed programmes in the project area ............................................................................................................................................................... 17
2.1. Project Implementing Agency ............................................................................................................................................................................................................. 21
2.2 About District Watershed Development Unit (DWDU), Narmada ..........................................................................................Error! Bookmark not defined.
2.2.1 The organization and its objectives: ........................................................................................................................................................ Error! Bookmark not defined.
2.2.2 Programmes/projects of DWDU, Narmada: ......................................................................................................................................... Error! Bookmark not defined.
2.3 SWOT Analysis of the DWDU: ...............................................................................................................................................................Error! Bookmark not defined.
Table no. 6: PIA: ..................................................................................................................................................................................................... Error! Bookmark not defined.
Table no. 7: Staff at PIA level: ............................................................................................................................................................................ Error! Bookmark not defined.
3.1.1 Land use pattern: ........................................................................................................................................................................................................................................................ 26
Table no. 8: Land use pattern: ...................................................................................................................................................................................................................................... 26
3.1.2 Soil and topography: .................................................................................................................................................................................................................................................. 27
8/4/2019 Nar_IWMP_1
3/180
District Watershed Development unit Narmada Page 3
Table no. 9: Soil type and topography: ...................................................................................................................................................................................................................... 27
Table no. 10: Flood and drought condition: ............................................................................................................................................................................................................ 29
Table no. 11: Soil Erosion ............................................................................................................................................................................................................................................... 30
Table no. 11.2: Soil Salinity/Alkalinity (Salinity ingress) .................................................................................................................................................................................. 30
Table no.12: Climatic conditions ................................................................................................................................................................................................................................. 30
Table no. 13: Physiography and relief ....................................................................................................................................................................................................................... 31
3.1.3 Land and Agriculture: ................................................................................................................................................................................................................................................ 31
Table no. 14: Land ownership details ........................................................................................................................................................................................................................ 31
Table no. 15: Agriculture ................................................................................................................................................................................................................................................ 32
Table no. 16: Irrigation .................................................................................................................................................................................................................................................... 33
Table no. 17: Crop details: .............................................................................................................................................................................................................................................. 34
3.1.4 Livestock: ................................................................................................................................................................................................................................................................... 37
Table no. 18: Livestock .................................................................................................................................................................................................................................................... 37
Table no. 19: Drinking water ........................................................................................................................................................................................................................................ 38
Table no. 20: Details of Common Property Resources ........................................................................................................................................................................................ 39
3.2. Socio-Economic Profile ................................................................................................................................................................................................................................................ 40
3.2.1 Demographic Status: ............................................................................................................................................................................................................................................. 40
Table no. 21: Demographic information ................................................................................................................................................................................................................... 40
Table no. 22: Literacy rate ............................................................................................................................................................................................................................................. 41
8/4/2019 Nar_IWMP_1
4/180
District Watershed Development unit Narmada Page 4
Migration Pattern: ............................................................................................................................................................................................................................................................. 42
Table no. 24: Poverty ....................................................................................................................................................................................................................................................... 43
Infrastructure facilities: .................................................................................................................................................................................................................................................. 43
Table no. 25: Village infrastructure ............................................................................................................................................................................................................................ 44
Table no. 26: Facilities / HH assets ............................................................................................................................................................................................................................. 45
3.3. Livelihood pattern: ........................................................................................................................................................................................................................................................ 46
Table no. 27: Per capita Income ................................................................................................................................................................................................................................... 46
Dependence on Common Property Resource ............................................................................................................................................................................................................. 47
Table no.28: Dependence on Forest/CPR ................................................................................................................................................................................................................ 47
Table no. 29: Livelihood pattern (Occupational distribution) ......................................................................................................................................................................... 48
3.4. Comparative data of the crop productivity of the area: project area vs. District vs. State vs. Country vs. World: ............ ............ ............ ............ ............ ...... 50
Watershed Activities ....................................................................................................................................................................................................................................... 58
4.1. Scientific Planning: ........................................................................................................................................................................................................................................................ 58
Table no. 30: Details of Scientific Planning and Inputs in IWMP projects ................................................................................................................................................... 62
4.2. Institution building ....................................................................................................................................................................................................................................................... 64
Table no. 31.1: Watershed Committee details of sabuti ..................................................................................................................................................................................... 64
Table no. 31.2: Watershed Committee details of kundi Amba ......................................................................................................................................................................... 65
Table no. 31.3: Watershed Committee details of Barsan ................................................................................................................................................................................... 66
Table no. 31.4: Watershed Committee details of Khokhraumar ..................................................................................................................................................................... 67
8/4/2019 Nar_IWMP_1
5/180
District Watershed Development unit Narmada Page 5
Table no. 31.5: Watershed Committee details of Bharada ................................................................................................................................................................................ 68
Table no. 31.6: Watershed Committee details of Relva ...................................................................................................................................................................................... 69
Table no. 31.7: Watershed Committee details of Moskut ........... ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ .......... 70
Table no. 31.8: Watershed Committee details of Vadapada ............................................................................................................................................................................. 71
Table no. 31.9: Watershed Committee details of Nanikorvai ........................................................................................................................................................................... 72
Table no. 31.10: Watershed Committee details of Anjanvai ............................................................................................................................................................................. 73
Table no. 32: SHG details ................................................................................................................................................................................................................................................ 74
Table no. 32: SHG details ................................................................................................................................................................................................................................................ 75
Figure 4.Focused Group Discussion with villagers ................................................................................................................................................................................................... 76
User Group: .............................................................................................................................................................................................................................................................................. 77
Table no. 33: UG detail ..................................................................................................................................................................................................................................................... 77
4.3. Physical activities to be undertaken under IWMP 1 (Nani Korvai) ........................................................................................................................................................... 78
4.3.1 Entry Point activity (EPA) ................................................................................................................................................................................................................................... 78
Table no.34: Entry point activities (EPA) (All financial figures in lakh Rs.) ............................................................................................................................................... 78
Table no.34.1: Convergence under Entry point activities (EPA) (All financial figures in lakh Rs.) ........... ............ ............ ............ ............ ............ ............ ............ .... 80
4.3.2. Watershed Development Works: .................................................................................................................................................................................................................... 85
Table no.36: Activities related to Surface water resources in the project areas (all financial figures in lakh Rs.) ......... ............ ............ ............ ............ ............ 88
Table no. 36.1: ..................................................................................................................................................................................................................................................................... 91
Table no. 38: Activities related to livelihoods by Self Help Groups (SHGs) and user group (UGs)in the project areas ................ ............ ............ ............ ........ 94
8/4/2019 Nar_IWMP_1
6/180
District Watershed Development unit Narmada Page 6
Table no. 38.1: Activities related to livelihoods by Self Help Groups (SHGs) and user group (UGs) in the project areas ............ ............ ............ ............ ........ 96
Table no. 38.1: Activities related to livelihoods for landless (Animal unit) ............................................................................................................................................... 99
Table no. 39: Other activities of watershed works phase Proposed target .......................................................................................................................................... 100
Table no.40: Details of engineering structures in watershed works*........................................................................................................................................................ 100
Table No. 40.1: Technical Specification of stone bund ..................................................................................................................................................................................... 101
Table No. 40.2: Technical Details of Continuous Contour Trenches (CCT) in Gopaliya village (Survey no.21) ........... ............ ............ ............ ............ ............ . 101
Table No 40.3 Quantity Calculation: CCT .............................................................................................................................................................................................................. 102
Table no 40.5: Quantity Calculation of Border Contour trench .................................................................................................................................................................... 103
Table no 40.6: Technical details of percolation tank on Survey no. (Compartment no) 406 (Village Relva) .................. ............ ............ ............ ............ ......... 103
Table no 40.7: Quantity details of percolation tank on Survey no. (Compartment no) 406 (Village Relva) .................... ............ ............ ............ ............ ......... 104
Table no 40.8: Technical details of Check dam on compartment no: 405 near gamtal (village Anjanvai).................................................................................. 104
Table no 40.9: Quantity Calculation of Check dam on compartment no: 405 near gamtal (village Anjanvai) ............... ............ ............ ............ ............ ........... 105
Table no 40.10: Technical details of Check dam No. 2 on Compartment no.408 (Village:Sorapada)............................................................................................ 105
Table no 40.11: Quantity Calculation of Check dam No. 2 on Compartment no.408 (Village: Sorapada) ............ ............ ............ ............ ............ ............ ........... 106
Table no 40.12: Technical details of Village pond Compartment no: 414 (Village Ghankhetar) .................................................................................................... 106
Table no 40.13: Quantity Calculation of Village pond Compartment no: 414 (Village Ghankhetar) ............ ............ ............ ............ ............ ............ ............ ......... 107
Table no 40.14: Technical details of Earth Bund No. 5 on Survey no. 299 ............................................................................................................................................... 107
Table no 40.15: Quantity Calculation of Earth Bund No.5 Survey no. 299 ............................................................................................................................................... 108
Stone banding:...................................................................................................................................................................................................................................................................... 108
8/4/2019 Nar_IWMP_1
7/180
District Watershed Development unit Narmada Page 7
Table No. 40.16: Technical Details of Stone banding on survey no.67 (Village:Kokaraumar) ......................................................................................................... 108
Table No. 40.17: Quantity Excavation for Stone banding on survey no.67 (Village:Kokaraumar) ................................................................................................ 108
Table No. 40.18: Technical Details of Check wall on Survey no.55 (Village:Vadpada) ....................................................................................................................... 109
Table No. 40.19, Quantity Excavation for Check wall on Survey no.55 (Village:Vadpada) ............................................................................................................... 109
Table no.41: Details of activities connected with vegetative cover in watershed works ................................................................................................................... 110
Table No. 41.1: Technical Details of Afforestation Activities ........................................................................................................................................................................ 110
Table No. 41.2: Cost Estimation for afforestation activity .............................................................................................................................................................................. 111
Table no.42: Details of allied / other activities ................................................................................................................................................................................................... 111
Production System-1: Cement pole making (Primary model for cement pole making) ..................................................................................................................... 112
Table no: 34.1, Cost of Cement pole making ........................................................................................................................................................................................................ 113
Table No. 34.1.2 Total cost for 500 cement pole ................................................................................................................................................................................................ 113
Table No. 34.1.3, Revenue and return Details. .................................................................................................................................................................................................... 114
Table No. 35.3, Revenue and return Details. ........................................................................................................................................................................................................ 117
Production system: 3 Vegetable (Bottle guard) Production .............................................................................................................................................................................. 118
Figure:8 Bottle guard production ................................................................................................................................................................................................................................. 118
Table no: 36.1, Cost of cultivation for bottle guard production ................................................................................................................................................................... 120
Table No. 36.2. Initial investment for fodder bank ............................................................................................................................................................................................ 120
Table No. 36.3, Revenue and return Details. ........................................................................................................................................................................................................ 121
Production System - 4: Vermicompost unit for Nani Korvai ............................................................................................................................................................................. 121
8/4/2019 Nar_IWMP_1
8/180
District Watershed Development unit Narmada Page 8
Table: 37.1: Model for A Vermi-compost Unit ..................................................................................................................................................................................................... 124
Table No.37.2: Returns from vermicomposting ................................................................................................................................................................................................. 125
Table no.43: Details of activities in the CPRs in the project areas ............................................................................................................................................................... 126
4.4. Capacity Building: ....................................................................................................................................................................................................................................................... 126
Table no. 44: Capacity Building Institution: ......................................................................................................................................................................................................... 127
Table no. 45: Capacity Building plan:...................................................................................................................................................................................................................... 127
Table no.46: Information, education and Communication Activities: ....................................................................................................................................................... 128
Budgeting .......................................................................................................................................................................................................................................................... 130
Table no. 47: Budget at a glance ............................................................................................................................................................................................................................... 130
Table no. 48: Village component wise budget available under IWMP ....................................................................................................................................................... 131
Table no. 49: Village wise gap in funds requirement ....................................................................................................................................................................................... 132
Table no.50: Details of Convergence of IWMP with other Schemes ........................................................................................................................................................... 133
Table no.50.1: Details of Convergence of IWMP (Livelihood and production system) with other Schemes ................ ............ ............ ............ ............ ............ . 136
6.1 Expected Outcomes..................................................................................................................................................................................................................................................... 142
6.1.1 Employment .......................................................................................................................................................................................................................................................... 142
Table no. 52: Employment in Project area ............................................................................................................................................................................................................ 142
6.1.2Migration .................................................................................................................................................................................................................................................................. 143
Table no. 53: Details of seasonal migration from Project area ..................................................................................................................................................................... 144
Table no. 54: Details of average ground water table depth in the project areas (in meters) ........................................................................................................... 145
8/4/2019 Nar_IWMP_1
9/180
District Watershed Development unit Narmada Page 9
6.1.4 Drinking water ...................................................................................................................................................................................................................................................... 145
Table no. 55: Status of Drinking water ................................................................................................................................................................................................................... 145
6.1.5 Crops ......................................................................................................................................................................................................................................................................... 147
Table no. 56: Details of crop area and yield in the project area ................................................................................................................................................................... 147
6.1.6 Horticulture ........................................................................................................................................................................................................................................................... 148
Table no. 57: Area under horticulture .................................................................................................................................................................................................................... 148
1.7 Vegetative cover ...................................................................................................................................................................................................................................................... 149
Table no. 58: Forest/vegetative cover ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ............ ....... 149
6.1.8 Livestock ................................................................................................................................................................................................................................................................. 150
Table no. 59: Details of livestock in the project areas (for fluids please mention in litres, for solids please mention in kgs. and income in Rs.) ..... . 150
Table no. 60: Backward-Forward linkages ........................................................................................................................................................................................................... 151
Logical Framework Analysis .......................................................................................................................................................................................................................................... 152
7 Quality and Sustainability Issues .......................................................................................................................................................................................................... 157
7.1 Plans for Monitoring and Evaluation ................................................................................................................................................................................................................... 157
7.2 Plans for Project management: .............................................................................................................................................................................................................................. 158
7.3 Watershed Development Fund: ............................................................................................................................................................................................................................. 158
7.4 User Charges:................................................................................................................................................................................................................................................................. 158
8.Maps.............................................................................................................................................................................................................................................................180
8/4/2019 Nar_IWMP_1
10/180
District Watershed Development unit Narmada Page 10
CHAPTER -1
PROJECT BACKGROUND
8/4/2019 Nar_IWMP_1
11/180
District Watershed Development unit Narmada Page 11
1.1 Project Background
Nani Korvai (IWMP-1) project is located in Dadiyapada Taluka, Narmada District of Gujarat state. The project is a cluster of ten micro-
watersheds with 5D1A6d1f, 5D1A6d1a, 5D1A6c3b, 5D1A6d1d, 5D1A6d1b,D1A6b3b being their respective codes. The total project area of the
watershed is about 4730.9 Ha, of which 4730.9 Ha has been undertaken to be treated under Integrated Watershed Management Programme (IWMP)
starting year 2009-10.
The nearest town is Dediyapada which is about 12 Km from Nani Korvai project and is well connected by pucca road. The watershed includes
fifteen village of Nani Korvai,Gankhatr,Sabuti,Kanjai,Relva,Barsan,Moskut,Vadpada,Barada,Gopaliya,Khupar barsan,Kundhai Amba,Sorapada,Khokra
Umar. Vasava,Tadvi,Padvi And STcommunities are the primary inhabitants of the village. The livelihood of these people is primarily based on rainfed
agriculture, animal husbandry, wage labour, goat and poultry rearing. Mostly houses made by soil and bamboo.
8/4/2019 Nar_IWMP_1
12/180
District Watershed Development unit Narmada Page 12
Table no.1: Basic project information
Sl
No.
Name of
the
project
Villages Gram
Panchayats
Taluka District Area of
the
project
Area
proposed
to be
treated
Total
project
cost(Rs.
in lakh)
PIA
Name Census code
1
NaniKorvai
Nani korvai01532800 Kundiamba Dediyapada Narmada
4730.9
50.70 ha 608400
ForestDepartmentr,Narmada
2Gankhater
01527500 Khokhraumar Dediyapada Narmada 549.60 ha 6595200
3Sabuti
01536100 Sabuti Dediyapada Narmada 376.00 ha 4512000
4Kanjai
01534800 Sabuti Dediyapada Narmada 312.85 ha 3754200
8/4/2019 Nar_IWMP_1
13/180
District Watershed Development unit Narmada Page 13
5Ralva
01535900 Sabuti Dediyapada Narmada 158.80 1905600
6Barsan
01536800 Bharada Dediyapada Narmada 61.10 733200
7Moskut
01536200 Vadapada Dediyapada Narmada 284.60 3415200
8Vadpada
01536500 Vadapada Dediyapada Narmada 247.40 2968800
9Barada
01534600 Bharada Dediyapada Narmada 394.30 4731600
10Gopaliya
01536600 Gopaliya Dediyapada Narmada 155.70 1868400
11
Khupar
barsan 01537100 Gopaliya Dediyapada Narmada 142.60 1711200
12kundi amba
01532600kundi amba
Dediyapada Narmada 603.80 7245600
13Sorapada
01529100 Khakhar Pada Dediyapada Narmada 430.60 5167200
14Kokaraumar
01525900Kokaraumar
Dediyapada Narmada 398.05 4776600
15Anjavi
01533000kundi amba
Dediyapada Narmada 564.80 6777600
8/4/2019 Nar_IWMP_1
14/180
District Watershed Development unit Narmada Page 14
1.2 Need of Watershed Development Programme
Watershed Development Programme is prioritised on the basis of thirteen parameters namely Poverty Index, Percentage of SC/ST, Actual
wages, Percentage of small and marginal farmers, Ground water status, Moisture Index, Area under rainfed agriculture, Drinking water situation in the
area, Percentage of the degraded land, Productivity potential of the land, Continuity of another watershed that has already developed/treated, Cluster
approach for plain or for hilly terrain. Based on these thirteen parameters a composite ranking was given to Nani Korvai Watershed project as given in
table no. 2.
The total number of families under BPL is 1633 (69%), which is less than 80 per cent of the total households of the village. Hence a score of 7.5
is allotted. The percentage of schedule castes in the village is about 99.5 per cent to the total population; hence a score of 10 was allotted. More than
60 per cent of the farmers are small and marginal by nature and the actual wages earned by the labour is less than the minimum wages hence a
composite rank of 5, 3 and 5 are allotted respectively.
The soil type is black cotton and production of the land can be significantly enriched with the availability of timely irrigation. Cluster approach
was followed taking into consideration four micro-watersheds covering a total area of 4730.9 Ha. All the parameters taken together give a cumulative
score of 113 to the watershed (reference Table 2.1 below).
Table no. 2: Weightage of the project
Projectname
Projecttype
Weightage
IWMP 1 otheri ii iii iv v vi vii viii ix x xi xii Xiii
7.5 10 5 10 3 10 15 7.5 10 10 15 15 NA
8/4/2019 Nar_IWMP_1
15/180
District Watershed Development unit Narmada Page 15
Table no. 2.1 Criteria and weightage for selection of watershed
S.No.
CriteriaMaximum
scoreRanges & scores
i Poverty index (% of poor topopulation)
10 Above 80 % (10) 80 to 50 % (7.5) 50 to 20 % (5) Below 20% (2.5)
ii % of SC/ ST population 10 More than 40 % (10) 20 to 40 % (5) Less than 20 % (3)
iii Actual wages 5 Actual wages aresignificantly lower thanminimum wages (5)
Actual wages are equalto or higher thanminimum wages (0)
iv % of small and marginalfarmers
10 More than 80 % (10) 50 to 80 % (5) Less than 50 % (3)
v Ground water status 5 Over exploited (5) Critical (3) Sub critical (2) Safe (0)
vi Moisture index/DPAP/ DDP Block
15 -66.7 & below (15)DDP Block
-33.3 to -66.6 (10)DPAP Block
0 to -33.2 (0)Non DPAP/ DDP Block
vii Area under rain-fedagriculture
15 More than 90 % (15) 80 to 90 % (10) 70 to 80% (5) Above 70% (Reject)
viii Drinking water 10 No source (10) Problematic village(7.5) Partially covered (5) Fullycovered(0)
ix Degraded land 15 High above 20 % (15) Medium 10 to 20 %(10)
Low- less than 10 % ofTGA (5)
x Productivity potential ofthe land
15 Lands with lowproduction & whereproductivity can besignificantly enhancedwith reasonable efforts(15)
Lands with moderateproduction & whereproductivity can beenhanced withreasonable efforts (10)
Lands with highproduction & whereproductivity can bemarginally enhancedwith reasonableefforts (5)
xi Contiguity to anotherwatershed that has alreadybeen developed/ treated
10 Contiguous to previouslytreated watershed &contiguity within themicrowatersheds in theproject (10)
Contiguity within themicrowatersheds in theproject but noncontiguous topreviously treatedwatershed (5)
Neither contiguous topreviously treatedwatershed norcontiguity within themicrowatersheds inthe project (0)
8/4/2019 Nar_IWMP_1
16/180
District Watershed Development unit Narmada Page 16
xii Cluster approach in theplains (more than onecontiguous micro-watersheds in the project)
15 Above 6 micro-watershedsin cluster (15)
4 to 6 microwatershedsin cluster (10)
2 to 4microwatersheds incluster (5)
xiii Cluster approach in thehills (more than onecontiguous micro-watersheds in the project)
15 Above 5 micro-watershedsin cluster (15)
3 to 5 microwatershedsin cluster (10)
2 to 3microwatersheds incluster (5)
Total 150 150 90 41 2.5
Table no.3: Watershed information
Name of the project No. of watersheds to be treated Watershed code Watershed regime/type/order
IWMP 1 Nani Korvai 106A1B7a2b, 6A1B7a2a,6A1B7a2c, 6A1B7a1a
Mini Watershed
8/4/2019 Nar_IWMP_1
17/180
District Watershed Development unit Narmada Page 17
1.3 Other developmental projects/schemes running in the Project area
This Nani Korvai project has been on top priority of a number of developmental projects. These programmes are Mahatma Gandhi National Rural
Employment Guarantee Scheme (MGNREGS),Total Sanitation Campaign (TSC), Swarnajayanti Gram Swarojgar Yojana (SGSY), Indira Awas Yojana
(IAY) and Sardar Awas Yojana (SAY).
Table no.4: Developmental programmes running in the project area:
Sno
Name of theprogramme/scheme
Sponsoringagency
Objectives of theprogramme/scheme
Year of commencementVillagescovered
Estimatednumber of
beneficiaries
1 MGNREGS
Rural
DevelopmentDept.
Employment 2009 111255
Household
2 IAYRural
DevelopmentDept.
Housing 2004-05 13 223
3 TSC Central Govt. Toylet 2006-07 12 1186
Table no. 5: Previous Watershed programmes in the project area
In project area IWMP is the first watershed programme.
S.No
Projectname
Yearstarted
Name ofvillages
No. Ofmicro
Watershedcodes
Areaunder
Funding
Nodalagency
PIA Total costExpenditure incurred
% financialcompletion
% physicalcompletion
8/4/2019 Nar_IWMP_1
18/180
District Watershed Development unit Narmada Page 18
watershed treatment source up to startof IWMP
1 - -
Nanikorvai - - - - - - - - - -
2 - -
Gankhater - - - - - - - - - -
3 - -Sabuti
- - - - - - - - - -
4 - -Kanjai
- - - - - - - - - -
5 - -Ralva
- - - - - - - - - -
6 - -Barsan
- - - - - - - - - -
7 - -Moskut
- - - - - - - - - -
8 - -Vadpad
a - - - - - - - - - -
9 - -Barada
- - - - - - - - - -
10 - -
Gopaliya - - - - - - - - - -
11 - -
Khuparbarsan - - - - - - - - - -
12 - -
kundiamba - - - - - - - - - -
13 - -
Sorapada - - - - - - - - - -
8/4/2019 Nar_IWMP_1
19/180
District Watershed Development unit Narmada Page 19
14 - -
Kokaraumar - - - - - - - - - -
15 - -Anjavi
- - - - - - - - - -
8/4/2019 Nar_IWMP_1
20/180
8/4/2019 Nar_IWMP_1
21/180
District Watershed Development unit Narmada Page 21
2.1. Project Implementing Agency
The Project Implementing Agencies (PIA) is selected by an appropriate mechanism by Gujarat State Watershed Management Agency (GSWMA), the
State Level Nodal Agency (SLNA) for Integrated Watershed Management Programme (IWMP) in Gujarat. The PIAs are responsible for implementation
of watershed project. These PIAs may include relevant line departments, autonomous organizations under State/ Central Governments,
Government Institutes/ Research bodies, Intermediate Panchayats, Voluntary Organizations (VOs).The PIA for Nani Korvai watershed Project is
Line Department Rajpipla (Narmada).
2.2 About Project Implementing Agency, Rajpipla (Narmada)
2.2.1 The organization and its objectives:
PIA of the Nani Korvai project is Rajpipla East Forestry Division. The Deputy Conservator of Forest (DCF) is the head of division. PIA has dedicatedand experienced staff comprising one Range Forest Officer (Nodal officer) and a watershed development team of civil engineer, agriculture
expert and community mobiliser, Data Entry Operator, surveyor, and accountant. The objective of the PIA is supervising, planning, implementing,documenting and promoting watershed development projects and related developmental activities at project level as per guidelines. This alsosubmits the documents at the district level. The DWDU, Narmada is not working as a PIA for any IWMP projects.
2.2 SWOT Analysis of the PIA:
Strength:
(1) Dedicated and experienced staff and a multidisciplinary team
(2) Independent District Level Nodal Agency.
(3) Strong linkages with national and state level institutions, agricultural universities, South Gujarat University and NGOs for capacity building and
technical guidance
(4) Scientific planning in watershed projects with the help of BISAG, Gandhinagar,
(5) District level monitoring, coordination & Co-operation Committee
Weakness:
8/4/2019 Nar_IWMP_1
22/180
District Watershed Development unit Narmada Page 22
(1) Lack of permanent staff.
(2) Total project area is Tribal
Opportunities:
(1) A number of different other development schemes of the government are running; so, there can be horizontal integration and convergence of
programmes
(2) Better financial provision under IWMP(3) Usage of new ICT tools like GIS, GPS
Threats:
(1) Rainfall being very scarce and unreliable in the project area, the activities planned to be taken up may yield limited impact
(2) Irregularities in fund flow can derail the smooth functioning
(3) Lack of contribution and cooperation from local people
(4) Low literacy rate in the project are
Table no. 6: PIA:
Sl. No. Names of project Details of PIA
1IWMP-1
Nani-Korvai Project
(i) Type of organization PIA (Project Implementing Agency)
(ii) Name of organization East forest division Rajpipla
(iii) Designation & Address DFO East division Vadiya palace(iv) Telephone 224647(v) Fax 220896(vi) E-mail [email protected]
Table no. 7: Staff at PIA level:
S.no
Name Age Sex Designation Qualification Experience Job assignedMonthly
remuneration(Rs)
mailto:[email protected]:[email protected]:[email protected]8/4/2019 Nar_IWMP_1
23/180
District Watershed Development unit Narmada Page 23
1. Dr.Shashi Kumar 31 M DFO PhD (Horticulture) 2 Monitoring 50000.00
2. Vasava.S 50 M RFO Bsc (Agriculture) 25 Project officer 43000.00
3.Jaydeep 25 M WDT(Agriculture) BRS(Agri) 4 Years Agriculture
Development8000.00
4.Gamit Apeksha 24 F WDT(Community
Mob.)BA 3 Years Community
Mobilization8000.00
5.Komal 25 F WDT (Data Entry
Operator)PGDCA 2 Years Data Entry 5000.00
6. Rajvadi Paresh 32 M WDT.Eng Diploma Civil 4 Years Technical 800007. Piyush Suthar 29 M Messenger MA (English) 4Years 30008. Nilesh 30 M Surveyor ITI(Surveyor) 10Years Survey 6000
CHAPTER 3
BASIC INFORMATION OF THE PROJECT AREA
8/4/2019 Nar_IWMP_1
24/180
District Watershed Development unit Narmada Page 24
8/4/2019 Nar_IWMP_1
25/180
District Watershed Development unit Narmada Page 25
Figure: 1 Base line survey
3.1. Geography and Geo-hydrology
8/4/2019 Nar_IWMP_1
26/180
District Watershed Development unit Narmada Page 26
3.1.1 Land use pattern:
The net geographical area of Nani Korvai watershed is about 4730.9 ha out of which 55% is forest area. About 31.8% of land is under
agriculture which is rain-fed and irrigated; mainly Rabi and kharibcrops are taken. About 15.64% of the total land is classified under wasteland of
which 44 percent is cultivable and rest is uncultivable. The watershed consists of bamboo which is a main livelihood source in project area.
Table no. 8: Land use pattern:
S. No.Names ofvillages
Geographical Areaof the village (ha)
Forest Area(ha)
Land underagricultural use
(ha)
Rain-fedarea (ha)
Permanentpastures (ha)
Wasteland
Cultivable(ha)
Non-cultivable(ha)
1Nani korvai
50.70 404.6 0.00 0.00 15 - -
2Gankhater
549.60 447.0 133.30 133.30 0 33.3 -
3Sabuti
376.00 - 304.00 304.00 0 35.5 36.4
4 Kanjai 312.85 285.85 - - 0 - -
5Ralva
158.80 - 129.40 129.40 0 3.1 26.4
6 Barsan 61.10 - - 40.70 0 - 20.4
7Moskut
284.60 84.4 84.40 166.80 0 28.0 5.4
8Vadpada
247.40 32.2 32.20 174.20 0 6.4 34.7
9Bharada(Ralva) 394.30 - 330.40 38.10 0 - 154.3
10Gopaliya
155.70 8.1 8.10 103.60 0 44.1 -
11Khuparbarsan 142.60 - 0.00 84.96 0 57.7 -
8/4/2019 Nar_IWMP_1
27/180
District Watershed Development unit Narmada Page 27
12kundi amba
603.80 - 0.00 416.90 0 49.5 137.4
13Sorapada
430.60 253.1 - 0 8.1 5.1
14 Kokaraumar 398.05 269.5 - 0 62.9 -
15Anjanvai
564.80 462.9 462.90 60.30 0
3.1.2 Soil and topography:
Nani Korvai watershed project (NWP) falls under South Gujarat Agro Climatic Zone. The soil is mainly deep black and clay. The soil is brown to black
in surface colour. The depth of soil is moderate to deep about 25 to 75 cm.The annual rainfall is 1000 mm. The predominant texture of soil is loamy
and clay. The soil fertility is average with low contain of nitrogen, phosphorus and potash. The topography of the area is moderate ranging from 0-
15% slope.
Table no. 9: Soil type and topography:
S. No.Name of the Agro-climatic zone
covers project areaArea in ha
Names of thevillages
Major soil typesTopography
a)Type b) Area in ha
1
Southern Hills
50.70Nani korvai
Black Cotton soil 50.70Flat to moderate
slope
2 549.60Gankhater
Black Cotton soil
549.60
3 376.00Sabuti
Black Cotton soil
376.00
8/4/2019 Nar_IWMP_1
28/180
District Watershed Development unit Narmada Page 28
4 312.85Kanjai
Black Cotton soil
312.85
5 158.80Ralva
Black Cotton soil
158.80
6 61.10Barsan
Black Cotton soil
61.10
7 284.60Moskut
Black Cotton soil
284.60
8 247.40Vadpada
Black Cotton soil
247.40
9 394.36Bharada (Ralva)
Black Cotton soil
394.36
10 155.70Gopaliya
Black Cotton soil
155.70
11 142.60Khupar barsan
Black Cotton soil
142.60
12 603.80kundi amba
Black Cotton soil
603.80
13 430.60Sorapada
Black Cotton soil
430.60
14 398.05 KokaraumarBlack Cotton soil
398.05
15 564.80Anjanvai
Black Cotton soil
564.80
8/4/2019 Nar_IWMP_1
29/180
District Watershed Development unit Narmada Page 29
Table no. 10: Flood and drought condition:
S.No Village Flood (Incidence) Drought (Incidence)
1Nani korvai
Nil Once in 5 Years
2Gankhater
NilOnce in 5 Years
3Sabuti
NilOnce in 5 Years
4Kanjai
NilOnce in 5 Years
5Ralva
NilOnce in 5 Years
6Barsan
NilOnce in 5 Years
7Moskut
NilOnce in 5 Years
8Vadpada
NilOnce in 5 Years
9Bharada (Ralva)
NilOnce in 5 Years
10Gopaliya
NilOnce in 5 Years
11Khupar barsan
NilOnce in 5 Years
12kundi amba
NilOnce in 5 Years
13Sorapada
NilOnce in 5 Years
14 Kokaraumar Nil Once in 5 Years
15Anjanvai
NilOnce in 5 Years
8/4/2019 Nar_IWMP_1
30/180
District Watershed Development unit Narmada Page 30
Table no. 11: Soil Erosion
Cause Type of erosion Area affected (ha)Run off
(mm/ year)Average soil loss (Tonnes/
ha/ year)
Water erosiona Sheet 2134 350 -b Rill 948 460 30%
c Gully 500 320 22%
Sub-Total 3582Wind erosion 1950 NA 22%
Total
Table no. 11.2: Soil Salinity/Alkalinity (Salinity ingress)
Name of the project Survey Number Soil pHType of Salinity
(Inherent/Ingress)Nani Korvai 7.8 Inherent
Table no.12: Climatic conditions
Sl. No. Year Rainfall (in mm)Temperature (C) Highest intensity of Rainfall (mm
in a day)Max. Min.
1 2004 1130.25 42 27 2002 2005 1178.00 42.5 27 190
3 2006 1604.00 43 28 2104 2007 1389.50 44 27.5 200
5 2008 1146.25 43 28 1806 2009 822.25 44 27 210
The average rainfall of this area is about 1100 mm (from past five year data) with a highest intensity of 200 mm within span of a day. This
uneven distribution is leading to runoff of soil every year.
8/4/2019 Nar_IWMP_1
31/180
District Watershed Development unit Narmada Page 31
Table no. 13: Physiography and relief
Project name Elevation(MSL) Slope range (%) Major streamsNani Korvai(IWMP1) 171.42 meters 0-20 % Karjan,Narmada
3.1.3 Land and Agriculture:
The average land holding is about 0.4 ha ranging from 0.171 to 0.629 ha. Lack of irrigation source forces the majority of the farmers to migrate
to ensure their livelihood. This affects directly the demographic profile of the village. The major crops cultivated by the farmers are Rice (paddy),
Groundnut, Cotton, Pigonpea and Wheat. Farmers take crops according to mansoon. The land conservation measures such as Check dams and farm
bunds in the area will help them to increase cropping intensity of project area.
Table no. 14: Land ownership details
S No VillageTotal owned land (in ha)
Gen OBC SC ST1
Nani korvai0 0 0
2Gankhater
0 0 0 82.4
3Sabuti
0 0 0 168.408
4Kanjai
0 0 0 46.8
5Ralva
0 0 0 93
6Barsan
0 0 0 42.2
7Moskut
0 0 0 122.72
8Vadpada
0 0 0 132.4
8/4/2019 Nar_IWMP_1
32/180
District Watershed Development unit Narmada Page 32
9Bharada (Ralva)
0 0 0 182.4
10Gopaliya
0 0 0 160.12
11Khupar barsan
0 0 0 79.8
12kundi amba
0 0 0 205.6
13Sorapada
0 0 0 181.4
14Kokaraumar
0 0 0 45.8
15Anjanvai
58.3
Table no. 15: Agriculture
S.No Village Net sown area(ha)
Nani korvaiOne time Two times Three times
Gankhater76.4 56.2 35.5
Sabuti192 65.2 56.2
Kanjai51.2 45.6 29.5
Ralva60.6 52.2 43.6
Barsan 31.4 28.2 21.5
Moskut87.52 43.76 21.88
Vadpada110 57.2 45.6
8/4/2019 Nar_IWMP_1
33/180
District Watershed Development unit Narmada Page 33
Bharada (Ralva)144.16 126.5 116.2
Gopaliya53.1 48 32
Khupar barsan72 59 39
kundi amba150.4 145.2 130.5
Sorapada59.2 35.2
Kokaraumar20.4 16.2
Anjanvai51.45 46 28
Table no. 16: Irrigation
SNo
VillageSource 1 : Canal Source 2 : Check dam / Pond Source 3 : Well
Availabilitymonths
Net areaGrossarea
Availabilitymonths
Net areaGrossarea
Availabilitymonths
Net areaGrossarea
1Nani korvai
0 0 0 0 0 0 6 Months 20 hec 40 hec
2Gankhater
0 0 0 0 0 0 7 Months 120 hec 120 ha
3Sabuti
0 0 0 0 0 0 6 Months 40 hec 50 hec
4 Kanjai 0 0 0 0 0 0 6 Months 60 ha 60 hec
5Ralva
0 0 0 0 0 0 5 Months 45 ha 60 hec
6Barsan
0 0 0 0 0 0 6 Months 24 hec 40 hec
8/4/2019 Nar_IWMP_1
34/180
District Watershed Development unit Narmada Page 34
7Moskut
0 0 0 0 0 0 7 Months 80 ha 80 hec
8Vadpada
0 0 0 0 0 0 6 Months 95 ha 120 hec
9Bharada (Ralva)
0 0 0 0 0 0 6 Months 40 ha 60 hec
10Gopaliya
0 0 0 0 0 0 7 Months 20 ha 20 hec
11Khupar barsan
0 0 0 0 0 0 5 Months 64 ha 70 hec
12kundi amba
0 0 0 0 0 0 6 Months 65 ha 70 hec
13Sorapada
0 0 0 0 0 0 6 Months 20 ha 25 hec
14Kokaraumar
0 0 0 0 0 0 6 Months 65 ha 65 hec
15Anjavi
0 0 0 0 0 0 6 Months 88 ha 90 hec
Table no. 17: Crop details:
S.No Village Kharif (Monsoon)Cotton Rice
Area(ha)
Production (000kg)Productivity
(kg/ha)Area(ha)
Production (000kg) Productivity (kg/ha)
1Nani korvai
2Gankhater
41.2 156 210 35.5 129 199
3Sabuti
307 153.34 686 253 145.2 525
4Kanjai
48 166 225 55 175 256
5 Ralva 52 179 245 42 155 206
8/4/2019 Nar_IWMP_1
35/180
District Watershed Development unit Narmada Page 35
6Barsan
26 123 145 28 131 142
7Moskut
42.5 159 205 36.2 121 205
8Vadpada
79.6 156 265 47.2 165 199
9Bharada (Ralva)
75.6 146 256 54.96 171 215
10Gopaliya
51 158 259 49 159 243
11Khupar barsan
65 185 249 56 175 232
12kundi amba
425 223.15 746 335 190.5 623
13Sorapada
56 146 235 46 155 194
14Kokaraumar
25 126 135 18 105 129
15Anjanvai
23.58 132 159 39 145 215
Sl no Village Rabi (Winter)Paddy
Juvar
Area (ha)Production
(000kg)Productivity
(kg/ha)Area (ha) Production (kg)
Productivity(kg/ha)
1Nani korvai
46.3 135 202 35 125 216
2Gankhater
32.2 126 156 28.5 126 145
8/4/2019 Nar_IWMP_1
36/180
District Watershed Development unit Narmada Page 36
3Sabuti
103 46 305 41.3 270 105
4Kanjai
42 156 215 48 145 208
5Ralva
56 189 256 46 159 216
6Barsan
24 121 139 32 145 216
7Moskut
21.88 115 126 15.5 94.5 115
8Vadpada
34 135 146 29 125 148
9Bharada (Ralva)
43 145 203 41 265 115
10Gopaliya
42 155 239 39 145 215
11Khupar barsan
52 181 246 41 146 203
12 kundi amba 125 75 226 89.5 216 123
13Sorapada
49 159 245 35 132 205
14Kokaraumar
23 126 235 20 121 223
15Anjanvai
26 131 245 46 158 230
8/4/2019 Nar_IWMP_1
37/180
District Watershed Development unit Narmada Page 37
3.1.4 Livestock:
The Nani Korvai project area has 738 cows, 574 buffaloes, 1512 bullocks, 343 goats and 0 sheep. Majority ofVasava,Tadvicommunity depends on
Buffalo and cow rearing for their livelihood. Cows and buffaloes are of local breed. Lack of rain and surface water has reduced the fodder and pasture
availability for their animals..
Table no. 18: Livestock
Sl
no Village Buffalo(Lit/annum) Cow(Lit/annum)
Total Milk
(Buffalo+Cow) Goat Sheep Bullock Hen OthersNo milk No Milk (Lit/annum) No Milk Camel
1Nani korvai
45 500 34 20 0 50 10
2Gankhater
18 50 63 60 110 31 0 139 64
3Sabuti
71 488 77 320 808 25 0 171 102
4Kanjai
20 147 34 185 332 7 73 29
5 Ralva 57 281 26 249 530 32 0 75 56
6Barsan
4 12 18 26 38 10 0 20 15
7Moskut
17 45 30 56 101 35 0 126 25
8Vadpada
31 155 45 195 350 31 0 153 27
9Bharada(Ralva) 46 225 68 530 755 1 0 120 46
10Gopaliya
61 412 50 323 735 12 0 137 30
11Khuparbarsan 34 157 29 155 312 12 0 82 36
12 kundi amba 70 272 104 260 532 21 0 133 90
8/4/2019 Nar_IWMP_1
38/180
8/4/2019 Nar_IWMP_1
39/180
District Watershed Development unit Narmada Page 39
12kundi amba
12 Well,Handpump 12 Good
13Sorapada
10 Well,Handpump 12 Good
14Kokaraumar
11 Well,Handpump 12 Good
15
Anjanvai
11 Well,Handpump 12 Good
Table no. 20: Details of Common Property Resources
S.No.
Names ofproject
CPRParticulars
Total Area (ha)Area owned/ In possession of
Area available for treatment (ha)
Pvt. personsGovt.
(Specifydept.)
PRIAny other
(Pl. Specify)Pvt.
persons
Govt.(Specify
dept.)PRI
Any other(Pl. Specify)
NaniKorvai
Wasteland/ degraded land 3540 1540
Pastures 95Orchards 0Village WoodlotForest 2100Village Ponds/ Tanks 12Community Buildings 24Weekly MarketsPermanent marketsTemples/ Places of worship 16Others (Pl. specify)
8/4/2019 Nar_IWMP_1
40/180
District Watershed Development unit Narmada Page 40
3.2. Socio-Economic Profile
3.2.1 Demographic Status:
Nani Korvai watershed project has a total of 2337 households with a population of 10111 ( as per base-line survey) out of which 5080 are male
and 5031 female. Nani Korvai project has more than 98% ST population. The sex ratio is 988 female to 1000 male. There are 1633 BPL families. The
average family size is 6. The literacy rate is very low i.e.55 per cent; male literacy rate is 68 per cent (of total male population) and female literacy rate
is as low as 40 per cent (of total female population). Ten people are graduate in project area. The major castes in the project area are vasava and talvi
(ST). Majority of population is involved in agriculture and animal husbandry.
Table no. 21: Demographic information
S no Village Population Population SC STTotal Male Female Total Male Female % Total Male Female
1Nani korvai 662
343 319 0 0 0 0 662 343 319
2 Gankhater 629 318 311 4 2 2 98.6 617 317 311
3Sabuti
888 449 439 98.9 878 449 437
4Kanjai
245 119 126 100 245 119 126
5Ralva
928 487 441 98.2 911 487 439
6Barsan
107 46 61 100 107 46 61
7Moskut
497 235 262 98.2 488 235 260
8Vadpada
767 406 361 3 1 2 97.5 748 406 358
9Bharada(Ralva) 626 283 250 100 626 283 250
8/4/2019 Nar_IWMP_1
41/180
District Watershed Development unit Narmada Page 41
10Gopaliya
817 407 410 1 1 0 99.3 811 406 410
11Khupar barsan
658 306 352 99.7 656 305 352
12kundi amba
1496 780 716 98.1 1468 780 714
13Sorapada
630 314 316 100 630 314 316
14 Kokaraumar 1467 763 704 98 1437 763 702
15Anjanvai
356 167 189 98.6 351 167 187
Table no. 22: Literacy rate
Sl no VillageLiteracy
Total % Male % Female %
1
Nani korvai
390 59 235 60.25 155 39.24
2Gankhater
324 62.3 210 81.3 114 43.5
3Sabuti
424 58.8 269 73.5 155 43.7
4Kanjai
89 47.3 82 57.1 37 38.1
5Relva
637 79.2 357 87.1 280 71.1
6Barsan
38 42.7 21 55.3 17 33.3
7Moskut
228 55.7 145 76.3 83 37.9
8Vadpada
332 54.7 229 69.2 103 37.3
9 Bharada (Ralva) 310 68.7 191 80.9 119 55.3
8/4/2019 Nar_IWMP_1
42/180
District Watershed Development unit Narmada Page 42
10Gopaliya
217 33.2 153 47.4 64 19.4
11Khupar barsan
272 51.5 164 67.5 108 37.9
12kundi amba
760 59.5 475 72.1 285 46.1
13
Sorapada
318 62.2 188 70.4 130 53.3
14Kokaraumar
651 52.5 427 65.8 224 38.0
15Anjanvai
125 43.1 83 63.4 42 26.4
Migration Pattern:
People migrate during summer season to different parts of the state like Surat, Baroda, and Ahamdabad as daily wagers, agricultural labours and
construction workers.Table no. 23: Migration details
Sl no VillageTotal
population
Migration Migration by monthsMain reasonfor migration
Incomeduring
migration /month
Total Male FemaleUp to 3months
3-6 monthsMore than 6
months
1Nani korvai
661 27 17 10 7 6 13Rs
3000/month
2Gankhater
665 11 6 5 1 5 5Rs
3000/month
3Sabuti
1007 82 45 37 16 45 25Rs
3000/month
4Kanjai
295 29 16 13 11 9 9Rs
2000/month
5Ralva
589 22 14 8 10 4 8Rs
3000/month
8/4/2019 Nar_IWMP_1
43/180
District Watershed Development unit Narmada Page 43
6Barsan
199 14 10 4 7 7 0Rs
4000/month
7Moskut
629 14 9 5 2 6 6Rs
4500/month
8Vadpada
872 10 7 3 4 3 3Rs
5500/month
9Bharada (Ralva)
1115 43 27 16 15 19 9Rs
5000/month
10 Gopaliya 961 15 9 6 10 3 2 Rs5000/month
11Khupar barsan
744 32 18 14 15 6 11Rs
5700/month
12kundi amba
1097 45 25 20 20 15 10Rs
6000/month
13Sorapada
863 70 40 30 25 35 10Rs
3500/month
14Kokaraumar
0 0 0 0 0 0 0
15 Anjanvai 481 35 25 10 16 12 7 Rs3000/month
Table no. 24: Poverty
S noProjectName
Total BPLHousehold
BPL% of BPL HH Total Land less HH % of land less HH
0-16 16-20 Total1 Nani Korvai 1633 300 1333 1633 69 520 21
Infrastructure facilities:
Nani Korvai watershed is well connected with Dediyapada Taluka with pucca roads. The mostly villages have electricity connectivity. Nearly 82 per
cent of households in the village have their personal electric meters. All villages have a primary school with all facilities like computers. For middle
8/4/2019 Nar_IWMP_1
44/180
District Watershed Development unit Narmada Page 44
and higher secondary education, the students have to go to Dediyapada Taluka which is about 10 kilometres away. This also contributes to lower
education level of the people.
Table no. 25: Village infrastructure
Sno
Village Puccaroadto the
village(Y/N)
Schools Colleges(Number)
Post Office(Distance)
Banks(Number)
Distancefromnearest
marketyard(km)
Milkcollectioncentre
(Number)
Milkcooperative(Number)
Othercooperatives/ CBIs
(Number)
Any otherinstitution
LP UP HS
1Nani korvai
Y Y N N N N N13
N N N Aaganvadi
2Gankhater Y Y N
YN
5N N N Aaganvadi
3Sabuti Y Y N
YN
25N N N Aaganvadi
4Kanjai Y Y N
NN
25N N N Aaganvadi
5 Ralva Y Y N N N 23 N N N Aaganvadi
6Barsan Y Y N
NN
24N N N Aaganvadi
7Moskut Y Y N
YN
30N N N Aaganvadi
8Vadpada Y Y N
NN
30N N N Aaganvadi
9Bharada(Ralva)
Y Y NN
N22
N N N Aaganvadi
10Gopaliya Y Y N
NN
28N N N Aaganvadi
11Khuparbarsan
Y Y NN
N27
N N N Aaganvadi
8/4/2019 Nar_IWMP_1
45/180
District Watershed Development unit Narmada Page 45
12kundi amba Y Y N
NN
12N N N Aaganvadi
13Sorapada Y Y N
NN
6N N N Aaganvadi
14Kokaraumar Y Y N
YN
3N N N Aaganvadi
15Anjanvai
NY N
NN
17N N N Aaganvadi
Table no. 26: Facilities / HH assets
Slno
VillageHHs withelectricity
HHs withsafety
latrines
HHs with phones HHs with vehicleHHs with
TV set
HHs withcooking
gas
HHs withDrinking
water
HHswith
fridgeLand line Mobile 2-wheeler 4-wheeler
1Nani korvai
7240
2 8 N N
2Gankhater
100 60 3 5 1 0 3N
Y 1
3Sabuti
200 100 2 35 9 3 19N
Y 4
4Kanjai
44 50 1 5 2 0 0N
Y 0
5Ralva
98 17 2 8 6 0 7N
Y 1
6Barsan
29 20 3 15 1 0 5N
Y 1
7Moskut
106 100 6 5 3 0 5N
Y 1
8Vadpada
136 50 5 10N
Y
9Bharada
196 72 2 15 7 0 11N
Y 1
8/4/2019 Nar_IWMP_1
46/180
District Watershed Development unit Narmada Page 46
10Gopaliya
192 72 3 10 0 00 4N
Y 0
11Khupar barsan
137 81 4 10 8 2 6N
Y 0
12kundi amba
282 152 5 10 8 0 8N
Y 3
13Sorapada
132 52 2 20N
Y
14 Kokaraumar 186 56 3 30 N N
15Anjanvai
82 59 2 10 6 00 3N
Y 2
3.3. Livelihood pattern:
The villagers earn their livelihood from animal husbandry and agriculture and during lean seasons they migrate for daily wage labourers in
Rajpipla, Baroda, and Baruch and as agriculture labour in other parts of the state. Another major occupation of the people is Basket making and leaf
plates making using the raw material which they collect from the community land or forest.
Table no. 27: Per capita Income
S No Village Agriculture (in Rs.) Animal husbandry(in Rs.)
Casual labour(In Rs.)
Others (in Rs.) Total (in Rs.)
1 Nani korvai 6530 3218 4250 1008 15006
2 Gankhater 8310 5438 6478 578 20804
3 Sabuti 9140 6320 7130 1290 23880
4Kanjai
6350 5010 6548 234 18142
8/4/2019 Nar_IWMP_1
47/180
District Watershed Development unit Narmada Page 47
5 Ralva 7240 5040 6389 689 19358
6 Barsan 6210 4589 5487 346 16632
7 Moskut 8442 6130 7349 210 22131
8 Vadpada 7242 6230 6578 567 20617
9 Bharada (Ralva) 8234 6231 7140 469 22074
10 Gopaliya 7467 4937 5690 245 18339
11 Khupar barsan 6367 4265 5432 857 16921
12 kundi amba 9110 7130 8200 468 24908
13 Sorapada 7470 5134 6138 348 19090
14 Kokaraumar 7898 6468 6800 678 21884
15 Anjanvai 6478 5118 5548 345 17489
Dependence on Common Property Resource
Nani Korvai watershed has more forest area. So people use bamboo for basket making and most of villagers collect gum from forest area. Project area
has sufficient grazing land and community land.
Table no.28: Dependence on Forest/CPR
Sl no VillageBidi making Mahua making
Total income (Rs)% sells Income (Rs) % sells Income
1 Nani korvai 95 30000 90 10000 40000
8/4/2019 Nar_IWMP_1
48/180
District Watershed Development unit Narmada Page 48
2Gankhater
98 15000 95 5000 20000
3Sabuti
97 40000 93 20000 60000
4Kanjai
98 30000 97 10000 40000
5
Ralva
96 2000 94 8000 10000
6Barsan
99 25000 98 5000 30000
7Moskut
98 3000 96 2000 5000
8Vadpada
97 4000 93 2000 6000
9Bharada(Ralva) 99 3000 92 3000 6000
10 Gopaliya 98 6000 97 3000 9000
11Khupar barsan
97 5500 98 3500 9000
12kundi amba
94 45000 97 20000 65000
13Sorapada
98 40000 94 15000 55000
14Kokaraumar
96 30000 97 15000 45000
15Anjanvai
98 30000 98 10000 40000
Table no. 29: Livelihood pattern (Occupational distribution)
Sl Village Total Agriculture Animal Agriculture + Casual Services Handicraft
8/4/2019 Nar_IWMP_1
49/180
District Watershed Development unit Narmada Page 49
no workforce husbandry(AH)
AH labour
1Nani korvai
300 150 80 50 20 2 0
2Gankhater
150 80 30 70 20 1
3Sabuti
600 300 120 100 80 5 0
4 Kanjai 100 60 20 10 10 0 0
5Ralva
400 200 100 50 50 1 0
6Barsan
50 20 15 40 30 0 0
7Moskut
210 120 50 60 30 1 0
8Vadpada
350 250 100 80 40 2 0
9 Bharada (Ralva) 300 150 100 50 100 1 1
10Gopaliya
400 250 120 50 80 2 2
11Khupar barsan
350 300 100 60 70 2 3
12kundi amba
700 500 200 150 200 4 4
13Sorapada
300 250 100 150 120 0 0
14Kokaraumar
740 400 200 300 150 2 0
15Anjanvai
200 150 100 120 100 0 1
8/4/2019 Nar_IWMP_1
50/180
District Watershed Development unit Narmada Page 50
3.4. Comparative data of the crop productivity of the area: project area vs. District vs. State vs. Country vs. World:
The term productivity in general means the total output per unit of factor input. For example land productivity means output per hectare of
land. Productivity is an average and is calculated by dividing the total output of a particular crop by the total cultivated area under thatcrop.
Data are made available by the Baseline survey (for Nani Korvai village), Handbook of Agriculture, ICAR publication 2006(For Gujarat and
India), and Dept. of Agriculture (for Narmada). The results indicate that Nani Korvai project has low productivity compared to world, India, Gujarat
and Narmada. The productivity is low not only because that the land is unproductive or the farmers lack the skills to manage their crop but also due
lack to of source of irrigation and scarcity of rain.
Farmers mainly grow cotton, wheat, Rice, Rice. So farmers grow crop according to the rainfall. In case of low rainfall they go for sorghum,
castor, and pearl millet.
The world productivity of cotton is 526 kg/ha. In India productivity of 764 kg/ha. Gujarat productivity of about 633 kg/ha. Narmada district has very
good productivity700 kg /ha. The Nani Korvai project area has only 500 kg/ha productivity. It is low compare to district, State, India and world.
8/4/2019 Nar_IWMP_1
51/180
8/4/2019 Nar_IWMP_1
52/180
District Watershed Development unit Narmada Page 52
The world and India productivity of Wheat are 2717 kg,2700 kg per hectare respectively.Gujarat is a major Wheat producing state in India
with the productivity of 2423kg/ha.Wheat productivity of Narmada is 2067 kg/ha and Nani Korvai village has very poor productivity with 620 Kg/ha.
8/4/2019 Nar_IWMP_1
53/180
District Watershed Development unit Narmada Page 53
The world and India productivity of Groundnut are 1554 kg,1150 kg per hectare respectively.Gujarat is a major Groundnut producing state in
India with the productivity of 1367kg/ha.Groundnut productivity of Narmada is 1343 kg/ha and Nani Korvai project has very poor productivity with
700 Kg/ha.
8/4/2019 Nar_IWMP_1
54/180
District Watershed Development unit Narmada Page 54
The Nani Korvai project areahas low productivity because of the following reasons:
i) Full dependence on monsoon:Nani Korvai Project is dependent on monsoon. Water is essential input in agriculture. Due to the absence of proper irrigation facility,80% of
the total cultivated area depends on the uncertain monsoon. Therefore, the suceess or failure of the monsoon determines the success or failure
of agriculture production.The rainfall is unreliable due to two factors: untimely and inadequate.
ii) Low use of fertilizer per unit cropped area:
d ff f l d l k f f f l k d ff f f l
8/4/2019 Nar_IWMP_1
55/180
District Watershed Development unit Narmada Page 55
Farmers do not use sufficient fertilizer due to lack of water, scarcity of fertilizer in market and insufficient money for fertilizer. Many a times
they dont get fertilizer at the right time.
iii) Traditional farming methods:This also leads to low productivity. There is a lot of ignorance about the use of new farming methods and technologies such as multiple
cropping. They dont use FYM and other input in a proper way; that is why they dont get 100% output. So these factors contribute to low
productivity.
iv) Lack of adequate farm machinery:Even today a large number of farmers in Nani Korvai use wooden ploughs and bullocks. They dont have adequate machinery like seed drill. So,
old machineries take more time in tillage practices.
v) Lack of finances for farmers:In Nani Korvai most of the farmers are marginal and small. They do not have enough money to buy good quality seeds, machinery and other
inputs.
vi) Lack of good quality seeds and fertilizers:Good quality seed, fertilizer and pesticide are important factor in agriculture productivity. The use of good quality leads to higher land
productivity. In Nani Korvai, however, there are two limitations in the use of fertilizer. First these fertilizers are most useful in irrigated
condition. But in Nani Korvai 100 per cent of land depend on rainfall. In Nani Korvai mostly farmers use nitrogenous fertilizers especially urea.
This has resulted in disproportionate use of fertilizer depleting the quality of land.
vii) Lack of other facilities such as storage and marketing:
5 10% f i l d d f h i d i f d k f l S h ll l l d
8/4/2019 Nar_IWMP_1
56/180
District Watershed Development unit Narmada Page 56
5-10% of agriculture product damage after harvesting due to scarcity of proper storage and proper market for sale. So he sells to local traders
at the low prices. Farmers mainly face proper means of transportation and roads. And second problem is farmers dont have pro per storage
facilities.
8/4/2019 Nar_IWMP_1
57/180
District Watershed Development unit Narmada Page 57
CHAPTER 4
WATERSHED ACTIVITIES
W h d A i i i
8/4/2019 Nar_IWMP_1
58/180
District Watershed Development unit Narmada Page 58
Watershed Activities
Watershed management as a strategy has been adopted by Government of India especially in the rain-fed regions of semi-arid tropics. These
regions are characterized by low and undependable rain, low soil fertility, poor infrastructure development, low literacy and high incidence of
migration. Several studies have identified that there is a dire need of a systematic and scientific approach to deal with watershed development. The
common guidelines generate a fresh and flexible framework for the next generation watershed development.
4.1. Scientific Planning:
i) Cluster ApproachThis envisages a broader vision of Geo-hydrological unit which involves treating a cluster of micro-watershed. The Nani Korvai Project
consists of ten- watersheds namely5D1A6d1f, 5D1A6d1a, 5D1A6c3b, 5D1A6d1d, 5D1A6d1b, D1A6b3b as their respective codes. Further Nani
Korvai watershed project is in continuation with other watershed projects namely Kakarpada, chikda, Nanasukaamba, Khopi Projects this gives
an element of continuation of the programme.
ii) Base line SurveyTo access the impact of any watershed development programme a detailed baseline survey has to be conducted. This acts a benchmark
for any intervention during and post implementation of any development programme. A detailed baseline survey was undertaken which
involved household census survey, Bio-physical survey and Village level data collection from Talati cum mantri. Household census survey
includes a detailed questionnaire which was been filled by visiting each and every household in the village. This gave in the details of the
demographic profile of the village, the literacy percentage, SC/ST population, number of BPL household, cattle population, net consumption
rate in the village, average milk production of the cattle and various schemes running and their benefits
Bio-physical survey was undertaken to identify various natural resources available in the village. It included the soil typology, well in the
area, crop taken in the field, Cropping pattern, fertilizer used and various sources of irrigation in the field.
iii) Participatory Rural Appraisal (PRA)
8/4/2019 Nar_IWMP_1
59/180
District Watershed Development unit Narmada Page 59
iii) Participatory Rural Appraisal (PRA)
The past experience of watershed has given tremendous input to focus on creating accountability of the stakeholders towards the
programme. This has created an emphasis to include all the stakeholder communities and their local and indigenous Technological Knowledge
(ITK) while planning for any activity. Participatory approach provides a new path for planning, implementing, monitoring and post- withdrawal
activities with a complete accountability of the stakeholders. Various PRA techniques like resource mapping, social mapping, and season
calendars were used to understand the physical and social orientation of the village in general and watershed in specific. These tools put the
villagers in ease than the complicated questionnaires. Various tools like Matrix ranking, Venn Diagram were used to identify various local
vegetations (apt for afforestation) , Fodders crops , various institution and their significance in the life of the farmers
8/4/2019 Nar_IWMP_1
60/180
District Watershed Development unit Narmada Page 60
Figure: 2 Resource mapping
8/4/2019 Nar_IWMP_1
61/180
District Watershed Development unit Narmada Page 61
Figure: 3 Village meeting
iv)
Use of GIS and Remote sensing for planningUse of various high science tools has been promoted at various stages of watershed development.
a) Prioritization
Geographical Information System (GIS) has been used for prioritization process Various layer maps were created like Geo-morphological
8/4/2019 Nar_IWMP_1
62/180
District Watershed Development unit Narmada Page 62
Geographical Information System (GIS) has been used for prioritization process. Various layer maps were created like Geo-morphological,
Soil, BPL Population, SC/ST population, Ground water Status, Drinking water situation Slope percent. These were all given proper weightage
according to the DoLR specification. This helped in prioritization of various watershed areas.
b) PlanningAn action plan matrix was formulated by State Level Nodal Agency (SLNA) taking into account various features like the slope percent, soil
Depth, Soil Texture, Soil erosion in the area for wasteland, forest land and agricultural land. Global positioning System (GPS) was used to
identify each and every water conservation structures available in the project area. This was used to create a map. Contour Map of vertical
interval of 1 meter at a scale of 1:8000 was used for identifying various locations for soil and water conservation structures.
c) Hydrological modellingHydrology modelling technique was used for locating drainage, stream length, flow direction, sink, Flow accumulation. This model overlaid
over cadastral map to calculate the catchment area of each structures like the check dam etc. This has helped to remove the human error which
generally occurs while calculating the catchment area of a check dam.
Table no. 30: Details of Scientific Planning and Inputs in IWMP projects
S. No. Scientific criteria/ inputs usedWhether scientific criteria was
used(A)PlanningCluster approach YesWhether technical back-stopping for the project has been arranged? If yes, mention the name of theInstitute
Baseline survey Yes
Hydro-geological survey Yes
8/4/2019 Nar_IWMP_1
63/180
District Watershed Development unit Narmada Page 63
Hydro-geological survey Yes
Contour mapping YesParticipatory Net Planning (PNP) YesRemote sensing data-especially soil/ crop/ run-off cover
Ridge to Valley treatmentOnline IT connectivity between
(1)Project and DRDA cell/ZP Yes
(2)DRDA and SLNA Yes
(3)SLNA and DoLR Yes
Availability of GIS layers
1. Cadastral map Yes2. Village boundaries Yes3. Drainage Yes4. Soil (Soil nutrient status) Yes5. Land use Yes6. Ground water status Yes7. Watershed boundaries Yes
8.
Activity YesCrop simulation models# NoIntegrated coupled analyzer/ near infrared visible spectroscopy/ medium spectroscopy for highspeed soil nutrient analysis
No
Normalized difference vegetation index (NDVI)# NoWeather Station
(B) Inputs No1. Bio-pesticides No2. Organic manures Yes3. Vermicompost Yes4. Bio-fertilizer Yes
5.
Water saving devices Yes6. Mechanized tools/ implements Yes7. Bio-fencing Yes8. Nutrient budgeting No9. Automatic water level recorders & sediment samplers No
Any other (please specify)
8/4/2019 Nar_IWMP_1
64/180
District Watershed Development unit Narmada Page 64
Any other (please specify)