14
Name of TPS-Khaperkheda TPS List of PO proceesed in SETs from Aril 2015 to October 2015 Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if any No. of Qualifying Bidders Supply 1 PROCUREMENT OF CHEMICAL BONDED CASTABLE REFRACTORY FOR UNIT NO 2 AOH AT KHAPERKHEDA TPS 4500058168 KAILASH TRADERS 1997257.50 No 5 Supply 2 SUPPLY OF AIR PORT ASSEMBLY FOR XRP 883 COAL MILL OF UNIT NO 3 &4, KHAPERKHEDA TPS 4500057858 AIA ENGINEERING LTD 1530000.00 No 3 Supply 3 SUPPLY OF THERMOCOUPLES & RTDS ALONG WITH THERMOWELL FOR 210 MW KHAPERKHEDA TPS 4500057881 ELECTROPNEUMATIC ENGINEERS 300615.00 No 3 Supply 4 SUPPLY OF MATERIAL REQUIRED FOR WORK OF INSTALLATION, COMMISSIONING AND TESTING OF BUNKER COAL 3D LEVEL MEASUREMENT SYSTEM AT BUNKERS OF UNIT 5 AT CHP-II, 500MW KHAPERKHEDA T.P.S. 4500057904 BULK MATERIAL HANDLING TECHNOLOGIES 3905402.93 manufacture & supply 2 Supply 5 PROCUREMENT OF 75KW VFD ALONG WITH PANEL FOR F.O. PUMP MOTOR AT OIL HANDLING PLANT, 500MW KPKD. 4500058399 PUNJAB MACHINE TOOLS 536384.10 no 5 Supply 6 PROCUREMENT OF M. S. GRILLS FOR COAL BUNKERS FOR CHP-II, 500 MW UNIT, KHAPERKHEDA TPS. 4500058306 R.S.INDUSTRIES 332808.00 manufacture & supply 6 Supply 7 SUPPLY OF SPARES FOR LIQUID RING VACUUM PUMPS OF NASH CL-2001 MAKE PUMPS INSTALLED IN AHP-II,500 MW KHAPERKHEDA TPS. 4500058446 VS SALES CORPORATION 1212199.80 No 2 Supply 8 PROCUREMENT OF IMPACT IDLERS FOR 1800 MM BELT CONVEYOR & FLAT RETURN ROLLERS FOR 1200 M CON. SYSTEM FOR CHP-II, 500 MW UNIT, KHAPERKHEDA 4500058817 UMASAN ENTERPRISES 403032.00 manufacture & supply 5 Supply 9 SUPPLY OF DOME PLATE & TUBE SHEET WITH PURGE AIR SYSTEM FOR BUFFER HOPPER OF VACUUM BASED ESP ASH EVACUATION SYSTEM AHP,500 MW KHAPERKHEDA TPS. 4500059070 KLEENAIR SYSTEMS PRIVATE LIMITED 955385.55 No 2 Supply 10 SUPPLY OF A4 SIZE XEROX PAPERS ON AS AND WHEN REQUIRED BASIS. 4500059125 GLOBE TRADING COMPANY 612360.00 manufacture or supply 2 Supply 11 SUPPLY & WORK FOR COLD AIR VELOCITY TEST CAVT AT APH OUTLET TO ESP INLET DUCT, INSTALLATION OF DIVERTER PLATES AND FABRIC EXPANSION JOINT IN UNIT NO 4 AOHKHAPERKHEDA TPS 4500059347 FAVOURITE FABRICATORS PVT.LTD. 4382119.20 No 2 Supply 12 PROCUREMENT OF CHEMICAL BONDED CASTABLE REFRACTORY FOR UNIT NO 4 AOH AT KHAPERKHEDA TPS 4500059428 CASTWEL INDUSTRIES 976395.00 No 4 Supply 13 SUPPLY OF MS FASTENERS. 4500059605 ORION INDUSTRIES 616770.00 manufacture or supply 4 Page 1 of 14

Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

  • Upload
    dodan

  • View
    237

  • Download
    14

Embed Size (px)

Citation preview

Page 1: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

Supply 1

PROCUREMENT OF CHEMICAL BONDED

CASTABLE REFRACTORY FOR UNIT NO 2 AOH AT

KHAPERKHEDA TPS

4500058168 KAILASH TRADERS 1997257.50 No 5

Supply 2SUPPLY OF AIR PORT ASSEMBLY FOR XRP 883

COAL MILL OF UNIT NO 3 &4, KHAPERKHEDA TPS4500057858 AIA ENGINEERING LTD 1530000.00 No 3

Supply 3

SUPPLY OF THERMOCOUPLES & RTDS ALONG

WITH THERMOWELL FOR 210 MW KHAPERKHEDA

TPS

4500057881ELECTROPNEUMATIC

ENGINEERS300615.00 No 3

Supply 4

SUPPLY OF MATERIAL REQUIRED FOR WORK OF

INSTALLATION, COMMISSIONING AND TESTING OF

BUNKER COAL 3D LEVEL MEASUREMENT SYSTEM

AT BUNKERS OF UNIT 5 AT CHP-II, 500MW

KHAPERKHEDA T.P.S.

4500057904

BULK MATERIAL

HANDLING

TECHNOLOGIES

3905402.93manufacture &

supply2

Supply 5

PROCUREMENT OF 75KW VFD ALONG WITH

PANEL FOR F.O. PUMP MOTOR AT OIL HANDLING

PLANT, 500MW KPKD.

4500058399PUNJAB MACHINE

TOOLS536384.10 no 5

Supply 6

PROCUREMENT OF M. S. GRILLS FOR COAL

BUNKERS FOR CHP-II, 500 MW UNIT,

KHAPERKHEDA TPS.

4500058306 R.S.INDUSTRIES 332808.00manufacture &

supply6

Supply 7

SUPPLY OF SPARES FOR LIQUID RING VACUUM

PUMPS OF NASH CL-2001 MAKE PUMPS

INSTALLED IN AHP-II,500 MW KHAPERKHEDA TPS.

4500058446VS SALES

CORPORATION1212199.80 No 2

Supply 8

PROCUREMENT OF IMPACT IDLERS FOR 1800 MM

BELT CONVEYOR & FLAT RETURN ROLLERS FOR

1200 M CON. SYSTEM FOR CHP-II, 500 MW UNIT,

KHAPERKHEDA

4500058817UMASAN

ENTERPRISES403032.00

manufacture &

supply5

Supply 9

SUPPLY OF DOME PLATE & TUBE SHEET WITH

PURGE AIR SYSTEM FOR BUFFER HOPPER OF

VACUUM BASED ESP ASH EVACUATION SYSTEM

AHP,500 MW KHAPERKHEDA TPS.

4500059070KLEENAIR SYSTEMS

PRIVATE LIMITED955385.55 No 2

Supply 10SUPPLY OF A4 SIZE XEROX PAPERS ON AS AND

WHEN REQUIRED BASIS.4500059125

GLOBE TRADING

COMPANY612360.00

manufacture or

supply2

Supply 11

SUPPLY & WORK FOR COLD AIR VELOCITY TEST

CAVT AT APH OUTLET TO ESP INLET DUCT,

INSTALLATION OF DIVERTER PLATES AND FABRIC

EXPANSION JOINT IN UNIT NO 4

AOHKHAPERKHEDA TPS

4500059347

FAVOURITE

FABRICATORS

PVT.LTD.

4382119.20 No 2

Supply 12

PROCUREMENT OF CHEMICAL BONDED

CASTABLE REFRACTORY FOR UNIT NO 4 AOH AT

KHAPERKHEDA TPS

4500059428 CASTWEL INDUSTRIES 976395.00 No 4

Supply 13 SUPPLY OF MS FASTENERS. 4500059605 ORION INDUSTRIES 616770.00manufacture or

supply4

Page 1 of 14

Page 2: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

Supply 14SUPPLY OF CAUSTIC SODA LYE 100 % BASIS AT

WTP-I KHAPERKHEDA TPS4500059569

SVS CHEMICAL

CORPORATION1049999.83

manufacture or

supply2

Supply 15

SUPPLY AND APPLICATION OF FIRE CREATE

REFRACTORY AND ALLIED WORKS OF BAH FOR

UNIT NO UNIT 4 AOH AT KHAPERKHEDA TPS

4500059592 M S ENTERPRISES 3481860.00 No 2

Supply 16

PROCUREMENT OF BOILER FEED GATE, APH

ACCESS DOOR & ELIPTICAL DOOR AT UNIT NO 3 &

4, TPS KHAPERKHEDA

4500059643 HI-TECH MACHINERY 1012914.00 No 2

Supply 17PROCUREMENT OF SS 304 BAH SEAL PLATES FOR

UNIT NO 1 TO 4, KHAPERKHEDA TPS4500059712 C B INDUSTRIES 496440.00 No 5

Supply 18

PROCUREMENT OF BAH SEAL TROUGH OF

CARBON STEEL MATERIAL FOR UNIT NO 4 AOH,

TPS KHAPERKHEDA

4500059758TUSHAR ENGINEERING

WORKS321930.00

manufacture &

supply6

Supply 19

SUPPLY OF SPARES FOR BOTTOM ASH HOPPER

REFRACTORY COOLING SYSTEM AT AHP-II,500

MW KHAPERKHEDA TPS.

4500059914VIDARBHA

ENGINEERING WORKS1218105.00 No 5

Supply 20

SUPPLY OF MOISTURE TESTING REAGENTS FOR

KITTIWAKE MAKES OIL ANALYZER TO WTP-500MW

KHAPERKHEDA TPS.

4500060380 PRAVEEN TRADERS 508296.60manufacture or

supply2

Supply 21

ANNUAL SUPPLY CUM WORKS CONTRACT FOR

CONVEYOR BELT JOINTING / PATCHING BY COLD /

HOT VULCANIZING PROCESS FOR CHP II,

KHAPERKHEDA TPS.

4500060376THEJO ENGINEERING

LIMITED3805188.45

manufacture &

supply2

Supply 22SUPPLY OF THREE PHASE POWER QUALITY &

ENERGY ANALYZER.4500060509 K P INSTRUMENTS 441000.00

manufacture or

supply2

Supply 23

PROCUREMENT OF BELT TRACKING SYSTEM FOR

1200 MM WIDE CON. BELT FOR CHP-II, 500 MW

UNIT, KHAPERKHEDA TPS

4500060459GLOBAL CONVEYOR

SYSTEMS PVT LTD399097.44

manufacture &

supply2

Supply 24

SUPPLY OF SEAL PLATES FOR SEAL TROUGH OF

BOTTOM ASH HOPPER AHP-II, 500 MW UNIT 5

KHAPERKHEDA TPS

4500060714 C B INDUSTRIES 328440.00 No 8

Supply 25 SUPPLY OF MS FASTENERS. 4500060597 SAIF TRADERS 1709032.50manufacture or

supply2

Supply 26

SUPPLY OF SPARES FOR HIGH VELOCITY &

MEDIUM VELOCITY WATER SPRAY SYSTEM 210

MW.

4500061104 NOBLE ENGINEERINGS 481950.00manufacture or

supply2

Supply 27

PROCUREMENT OF SLOW SPEED GEAR

COUPLINGS FOR BELT CONVEYOR SYSTEM FOR

CHP-II

4500061251GOKAC

TRANSMISSIONS338150.40

manufacture &

supply2

Supply 28

RATE CONTRACT FOR SUPPLY OF UNHYDROUS

AMMONI GAS TO UNIT NO.III & IV AT WTP-I

KHAPERKHEDA TPS

4500061072ADITYA AIR PRODUCTS

PVT LTD5213446.88

manufacture or

supply2

Page 2 of 14

Page 3: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

Supply 29PROCUREMENT OF MODIFIED RETURN ROLLERS

FOR APRON FEEDER CHAIN DRIVE IN CHP-II4500061252

BRAINER

INTERNATIONAL690375.00

manufacture &

supply3

Supply 30

RATE CONTRACT FOR DOSING OF UNHYDROUS

AMMONIA GAS TO UNIT III & UNIT IV AS PER MPCB

NORMS AT KHAPERKHEDA TPS.(210 DAYS)

4500061525 JUNIFAB FACTOTUM 1153055.74 No 2

Supply 31 SUPPLY OF VARIOUS CONSUMABLES. 4500061622T M ENGINEERING

COMPANY334231.56

manufacture or

supply2

Supply 32SUPPLY OF PRINTER TONER CARTRIDGES FOR

THE YEAR 2015-16 AT KHAPERKHEDA TPS.4500061964

UNIQUE TRADING

COMPANY884079.00

manufacture or

supply3

Supply 33

SUPPLY OF AERATION PAD & SEGMENT PLATES

FOR AIR LOCK VESSEL OF AHP II, U#5 ( 500 MW)

KHAPERKHEDA TPS.

4500061778

HINDUSTAN

ENGINEERING

CORPORATION

657909.00manufacture &

supply3

Supply 34 SUPPLY OF SWITCHGEAR SPARES FOR CHP-I. 4500061873VASHI ELECTRICALS

PVT LTD316127.70 No 4

Supply 35

SUPPLY OF SOLENOID VALVES FOR

MODIFICATION AT AHP FOR C&I-II 500 MW

KHAPERKHEDA TPS

4500062034PREET ENGINEERING

WORKS355168.80

manufacture &

supply5

Supply 36

SUPPLY OF PART MATERIAL, ERECTION,

COMMISSIONING & LOAD TESTING OF HOIST AT

FRF ROOM & CONDENSER VACUUM PUMPS

LOCATION AT THE RISK AND COST OF M/S. BHEL.

4500061996 R S INDUSTRIALS 967614.75 No 2

Supply 37

PROCUREMENT OF ASH INTAKE VALVE 200 NB

AND VENT VALVE 100 NB, 50 NB RUBBER SEAT,

BODY & FLAPS FOR AHP-I

4500062142INNOVATIVE

ENGINEERS329175.00

manufacture &

supply3

Supply 38

SUPPLY OF BAG FILTER, CAGES AND LOCKING

PLATE FOR BUFFER HOPPER OF VACUUM BASED

DRY FLY ASH EVACUATION SYSTEM OF AHP II,

U#5 ( 500 MW) KHAPERKHEDA TPS.

4500062183

HINDUSTAN

ENGINEERING

CORPORATION

1701000.00 No 3

Supply 39SUPPLY OF DRAG CHAIN LINKS FOR R-600 COAL

FEEDERS AT UNIT NO 1 & 2, TPS KHAPERKHEDA4500062702

RAJU ENGINEERING

WORKS PVT LTD945172.80

manufacture &

supply3

Supply 40

PROCUREMENT OF CENTRIFUGAL CLUTCH

COUPLING SUITABLE FOR AIR PRE HEATER 31.5

VIMT 2000( 72 DEGREE PA) AT UNIT#5,500MW TPS

KHAPERKHEDA.

4500062164ORIENTAL FOUNDRY

AND ELECT INDU304500.00 No 2

Supply 41SUPPLY OF CAUSTIC SODA LYE 100 % BASIS AT

WTP-I KHAPERKHEDA TPS4500062460 PARSHVA ASSOCIATES 979200.00 No 2

Supply 42SUPPLY OF 25 METER HIGH MAST TOWERS WITH

ALLIED MATERIAL FOR KHAPERKHEDA TPS.4500062832

AKELECT

ENGINEERING1239000.00 No 2

Page 3 of 14

Page 4: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

Works 1

WORK OF OVERHAULING OF SUB ASSEMBLIES &

ITS COMPONENTS OF BULLDOZERS ON AS &

WHEN REQUIRED BASIS IN CHPVM-I, TPS

KHAPERKHEDA.

4500057717

NISHANT

AUTOMOVERS AND

ENGINEERING

2284969.60 No 2

Works 2

WORK OF ARRESTING FLUE GAS LEAKAGES IN

DOG HOUSE, PENT HOUSE & CAT HOUSE

OBSERVED DURING PRE PRESSURIZATION TEST

IN UNIT NO. 4 DURING AOH

4500058053 A G ZINGARE 536781.02 No 2

Works 3

FABRICATION & ERECTION OF STRUCTURAL

STEEL PEDESTALS FOR DIVERTING 1*500MW ASH

DISPOSAL PIPE LINE NEAR SHANTI BRICK

FACTORY,AT TPS KHAPERKHEDA

4500057796DAVID INDUSTRIAL

WORKS1034237.47 No 2

Works 4

MODIFICATION WORK OF FLUE GAS PATH &

PRIMARY AIR FLOW TRANSMITTER IMPULSE

LINES & DUST COLLECTORS IN UNIT NO. 1 & 2. (AS

& WHEN REQUIRED)

4500057896PRATIK INDUSTRIES,

KHAPERKHEDA367937.92 No 2

Works 5ARRESTING LEAKAGES IN SOFTEN WATER TANK

AT TPS KHAPERKHEDA4500058024

SHRIRAM

CONSTRUCTION3155951.00 No 2

Works 6

WORK OF STRENGTHENING OF TRAVEL TRACKS

FOUNDATION & SUPPORTING BEAMS FOR BOTH

SIDE ARM CHARGERS FOR CHPII 500 MW

KHAPERKHEDA TPS.

4500058257 S P KULKARNI 1754319.38 No 2

Works 7CLEANING & CLEARING OF PERENNIAL NALLAH

BY REMOVING ASH TPS,KHAPERKHEDA4500058239

B C BIYANI PROJECTS

P.LTD BHUSAWAL561617.53 No 3

Works 8

PROPOSED WORK OF EXTERNAL PAINTING TO

UNIT 2 & 4 BUILDING 210MW IN T.P.S

KHAPERKHEDA

4500058242 RAJU H. GABHANE 884863.99 No 2

Works 9

PROVIDING & REPAIRING CONCRETE BLOCK FOR

ENCASING BASE OF STEEL COLUMNS FOR TP

NO.102 TO 108 OF STRUCTURE 500MW TPS

KHAPERKHEDA

4500058273SHRI SAI

CONSTRUCTION1528800.32 No 2

works 10

ANNUAL RATE CONTRACT FOR SERVICING,

REPAIRING & MAINTENANCE OF AIR

CONDITIONERS AND WATER COOLERS FOR EM-II,

500MW, KHAPERKHEDA.

4500058358SAHIL FREEZING

WORKS441829.56 No 2

works 11

CLEANING OF PERIPHERAL TOE DRAIN BY

REMOVING ASH AT WAREGAON ASH

BUND,TPS,KHAPERKHEDA

4500058533 M F JAIN 896917.91 No 3

works 12

ARRESTING LEAKAGES THROUGH CONCRETE

SURFACE AT PTP AND WT PLANT AT TPS

KHAPERKHEDA

4500058362SHRIRAM

CONSTRUCTION379324.82 No 2

works 13MODIFICATION OF SPENT BACK WASH SUMP AT

WT PLANT AT TPS KHAPERKHEDA.4500058397

HARSH

CONSTRUCTION327657.90 No 4

Page 4 of 14

Page 5: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

Works 14

PROVIDING AND FIXING PAVEMENT BLOCKS AT

ENTERRENCE OF 1*500MW UNIT AT TPS

KHAPERKHEDA

4500058557 S R ENTERPRISES 1205345.75 No 2

Works 15

PROVIDING OIL PAINTING TO STEEL COLUMNS OF

STRUCTURE FOR TP NO.102 TO 108 OF 500MW

TPS KHAPERKHEDA

4500058407 RAJU H. GABHANE 1383084.99 No 2

works 16WORK OF SERVICING / MAINTENANCE OF AIR

COOLERS IN CHP- I & CHP-II.4500058707 D R CONSTRUCTION 313170.45 No 2

works 17

WORK OF PRE-MANSOON CLEANING OF

DRAINS,SEWER LINES AND CLEANING ROOF

TERRACE OF ALL AUXILLARY BUILDINGS IN

500MW UNIT PREMISES TPS,KHAPERKHEDA

4500058540 SANJAY V WAGHMARE 396622.42 No 3

works 18

FABRICATION AND ERECTION OF PLATFORMS

WITH RAILING AND SUPPORT STRUCTURES FOR

REGULAR OPERATION AND MAINTENANCE OF

AHP SYSTEM AND AUXILIARIES OF UNIT # 5

(500MW) AT KHAPARKHEDA TPS.

4500058715 S R ERECTORS 364800.00 No 3

Works 19

EXTRACTION OF DEPOSITED ASH/COAL FROM

EXISTING NALLAH INSIDE POWER HOUSE AREA IN

TPS KHAPERKHEDA

4500058727 RAJU H. GABHANE 453279.37 No 2

Works 20

REPAIR TO FLOORING,ENCASING STRUCTURAL

STEEL COLUMNS & ALLIED WORKS AT BOTTOM

ASH HOPPER AT 500MW TPS KHAPERKHEDA

4500058828DAVID INDUSTRIAL

WORKS2648842.31 No 4

Works 21

RECTIFICATION OF DRIBBLE CONVEYORS FOR

APRON FEEDER WITH SUPPLY OF REQUIRED

MATERIAL FOR CHP-II, KHAPERKHEDA TPS.

4500058900

VAISHNAVI

ENGINEERING

COMPANY

5299732.80 No 2

Works 22

WORK FOR HOT PA FAN & ID FAN MAINTENANCE

FOR UNIT NO. 1 TO 4 ON AS & WHEN REQUIRED

BASIS.

4500058862SHRI GAJANAN

ENGINEERING WORKS666505.97 No 2

Works 23

REPAIR OF BOILER EXPANSION MEASUREMENT

PROBES INCLUDING SERVICING / REPAIR OF

GUIDES, REPLACEMENT OF GUIDE &

RECTIFICATION / REPAIR OF BASE PLATES FOR

UNIT NO. 4 AOH

4500059013SEC PROJECTS PVT

LTD327337.61 No 2

Works 24SERVICING OF PA FANS / ID FAN DURING UNIT NO.

4 AOH4500058911

SHRI GAJANAN

ENGINEERING WORKS337644.47 No 4

Works 25

WORK OF UTILIZATION OF EXPERT SERVICES

FOR INSITU INSPECTION OF BOILER TUBE USING

RFET (REMOTE FIELD ELECTROMAGNETIC

TECHNIQUE) AT UNIT NO. 4 DURING AOH.

4500058923MRP NAIR ENGINEERS

AND CONTRACTORS1572915.00 No 2

Page 5 of 14

Page 6: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

Works 26

WORK CONTRACT FOR MAINTENANCE OF AIR

PRE-HEATERS INCLUDING BASKET CLEANING,

SEAL SETTING AND DRIVE UNIT REPAIR DURING

SHORT SHUT DOWN / FORCED BREAK DOWN

UNIT NO. 1 TO 4.

4500058901BHARTHI

CONSTRUCTION1066576.14 No 2

Works 27

WORK CONTRACT FOR BUNKER CHOKE UP

REMOVAL IN RAINY SEASON AT BOILER

MAINTENANCE OF UNIT # 5, 500 MW,

KHAPARKHEDA TPS.

4500058998 A G ZINGARE 654376.10 No 2

Works 28

WORK OF PROVIDING ASSISTANCE FOR COAL

STACK MANAGEMENT & VARIOUS WORKS

DURING RAINY SEASON , ROUND THE CLOCK BY

DEPLOYING UNSKILLED MANPOWER IN CHP-I.

4500059149 M F JAIN 1381040.36 No 2

Works 29

MEDICAL CHECKUP OF THE EMPLOYEE WORKING

IN KHAPERKHEDA TPS,KHAPERKHEDA FOR THE

YEAR 2014-15

4500059210 DR D P DEOTALE 547653.60 No 2

Works 30

WORK CONTRACT FOR REPLACEMENT OF 3 NO.

BUFFER HOPPER DOME & BAG HOLDING PLATE

(TUBE SHEET) IN AHP-II 500 MW, KHAPERKHEDA

TPS.

4500059147KUNAL

CONSTRUCTION815362.20 No 3

Works 31OIL FILTRATION AND ALLIED WORKS OF HT

TRANSFORMERS UNIT # 4, TPS KHAPERKHEDA.4500059177 ELMECH 459287.76 No 2

Works 32

APPLICATION OF CHEMICAL BONDED

REFRACTORY IN APH OUTLET TO ESP INLET

DUCT DURING UNIT NO. 4 ANNUAL OVERHAULS

4500059146 A G ZINGARE 642891.60 No 3

Works 33

WORK OF CONTRACT FOR CARRYING OUT COLD

AIR VELOCITY TEST (CAVT) SUPPLY &

INSTALLATION OF EXPANDED METAL SCREEN IN

BOILER AT UNIT NO. 4 DURING AOH.

4500059163MECH-WELL

INDUSTRIES LIMITED4254862.50 No 2

works 34

WORK OF INSITU REPAIR OF CRITICAL VALVE,

INSITU RECONDITIONING OF MAIN STEAM STOP

VALVE & LEGA TEST OF SAFETY VALVE DURING

UNIT NO. 4 AOH

4500059214BROSCO VALVES PVT

LTD1350128.22 No 3

works 35HIRING OF DOZER (HEAVY EARTH MOVER ) FOR

DOZING THE COAL.4500059189 M F JAIN 7519580.64 No 2

works 36

WORK OF CONCRETE BREAKING AND

MODIFICATIONS AT ALL

LOCATIONS,HEIGHTS,DEPTHS & LEVELS ON AS

AND WHEN REQUIRED BASIS IN 500MW PLANT

PREMISES TPS KHAPERKHEDA

4500059342DAVID INDUSTRIAL

WORKS323995.99 No 5

Works 37

MAINTENANCE CONTRACT FOR VARIOUS

ELECTRICAL WORKS OF ESP DURING AOH OF U-

5(500MW) 2015-16.

4500059547 ADITYA ENTERPRISES 330008.51 No 2

Page 6 of 14

Page 7: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

works 38WORK OF BUNKER NECK CHOKE UP REMOVAL &

ALLIED WORKS IN UNIT NO. 1 TO 4.4500059557 A G ZINGARE 928324.80 No 2

works 39

PROPOSED WORK OF PRE-MONSOON CLEANING

OF DRAINS & PROVIDING R.C.C CHAMBERS ON

EXISTING UNDERGROUND SURFACE WATER LINE

AND SEWAGE DISPOSAL LINE AT VARIOUS

LOCATIONS IN POWER HOUSE AREA, AND CHP-I

IN TPS, KHAPERKHEDA.

4500059564 P. R. Chandekar, 402760.60 No 3

works 40

TRANSFER CHUTE CHOKE UP REMOVAL & ALLIED

WORKS FOR AREA A AT WAGON TIPPLER TO

CRUSHER HOUSE AND FOR AREA B CRUSHER

HOUSE TO BUNKER IN CHP 500MW, TPS

KHAPERKHEDA.

4500059682

S R GAWANDE

CONTRACTER

KHAPERKHEDA

474611.18 No 3

works 41OVERHAULING OF HP / LP VALVES DURING

ANNUAL OVERHAUL OF UNIT NO. 4.4500059636 RAJESH ENTERPRISES 340062.57 No 3

works 42

STRENGTHENING OF BOTTOM ASH HOPPER

INCLUDING REPLACEMENT OF M.S. PLATES,

BEAMS AND CHANNELS IN UNIT NO. 4 DURING

AOH.

4500059603SUNIL HITECH

ENGINEERS LTD.1909573.21 No 2

works 43

WORK CONTRACT FOR REMOVAL & REFITTING OF

INSULATION OF FURNACE, DUCTS, PIPELINES,

VALVES OF UNIT NO. 5 (500 MW) AT

KHAPERKHEDA TPS. AS & WHEN REQUIRED

BASIS.

4500059604MRP NAIR ENGINEERS

AND CONTRACTORS827640.00 No 2

works 44

HIRING OF EXPERT SERVICES FOR MONITORING

& VERIFICATION (M&V) FOR PAT CYCLE AS PER

BEE AT KHAPERKHEDA TPS (4X210MW)

4500059609STEAG ENERGY

SERVICES (INDIA)436848.00 No 1

works 45

PREMANSOON WATER PROOFING TREATMENT

TO MULTISTORIED BUILDING & OVERHEAD

WATER TANKS IN TPS COLONY,KHAPERKHEDA

4500059614MANORAMA

CONSTRUCTION781071.03 No 3

works 46WORK OF FABRICATION OF COLD END BASKETS

SUPPORT GRATING FOR UNIT NO. 4 APH 'A' & 'B'4500059683 FRIENDS SKILLS 322897.80 No 2

works 47CLEANING OF NDCT POND / BASIN DURING

ANNUAL OVERHAUL OF UNIT NO.5(500 MW).4500059869 M T DAHAKE 306658.86 No 2

works 48

CONTRACT FOR REPLACEMENT COMPLETE SET

OF BEATER HEADS, ARMS & JIBS OF IMPACT

CRUSHERS FOR CHP-II, 1X500 MW UNIT,

KHAPERKHEDA TPS.

4500060159 ORION INDUSTRIES 523501.68 No 2

works 49

WORK OF REJECT BELT JOINTING & CONVEYOR

PULLEY LAGGING OF COAL MILL REJECT

HANDLING SYSTEM FOR UNIT NO. 1 TO 4.

4500060204THEJO ENGINEERING

LIMITED789840.97 No 2

Page 7 of 14

Page 8: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

works 50

WORK OF COAL NOZZLE ASSY. REPLACEMENT

DURING AOH OR SHORT SHUTDOWN AS & WHEN

REQUIRED BASIS.

4500060288BHARTHI

CONSTRUCTION1457339.52 No 2

Works 51

PROVIDING BUFFER WALL FOR ARRESTING

ASH/COAL SLURRY FROM EXISTING NALLAH

INSIDE POWER HOUSE AREA IN TPS

KHAPERKHEDA

4500060322 RAJU H. GABHANE 304242.47 No 5

Works 52

WORK CONTRACT FOR ERECTION & REMOVAL OF

CUP LOCK SCAFFOLDING INSIDE THE BOILER AND

FURNACE CLEANING BY HYDRO JETTING

MACHINE DURING AOH OF U#5, 500 MW, TPS

KHAPERKHEDA

4500061219MRP NAIR ENGINEERS

AND CONTRACTORS2987547.84 No 5

Works 53

WORK CONTRACT FOR ONLINE FILTRATION FOR

LUBRICATION OIL OF COAL MILL (SP320) & ID, FD,

PA (SP68) AT UNIT#5, 500 MW, TPS,

KHAPERKHEDA.

4500060465SUNITI ENTERPRISES

NAGPUR411768.00 No 3

Works 54WORK CONTRACT FOR STACK YARD COAL

MANAGEMENT IN CHP-II TPS KHAPERKHEDA4500060732

S R GAWANDE

CONTRACTER

KHAPERKHEDA

1444301.57 No 2

works 55

SHIFTING AND RE-LAYING OF 3 NOS. ASH SLURRY

LINES OF 500 MW UNIT 5 FROM OVERLAPPING

ZONE OF LINES BELOW CULVERT NEAR SHANTI

BRICK FACTORY ON PEDESTAL OF AHP-II (500MW)

KHAPARKHEDA TPS.

4500060750K M ADHAU

CONTRACTORS345762.00 No 2

Works 56

WORK CONTRACT FOR PATROLLING &

MAINTENANCE OF ASH SLURRY DISPOSAL (ASP

SERIES DISCHARGE) & HCSD (GEHO PUMP

DISCHARGE) PIPE LINES FROM PUMP HOUSE TO

WAREGAON ASH BUND FOR ASH HANDLING

PLANT UNIT # 5, 500 MW KHAPARKHEDA TPS.

4500060915K M ADHAU

CONTRACTORS6027574.09 No 2

Works 57

WORK CONTRACT FOR DEPLOYMENT OF

RETIRED RAILWAY LOCO OPERATORS /

EXPERIENCED LOCO OPERATORS FOR SHUNTING

OF COAL / OIL RAKES AT CHP I & II, TPS

KHAPERKHEDA.

4500060866TECHNOHIGH

ENTERPRISES1374429.60 No 2

works 58

REPAIR AND RECONDITIONING OF WORN OUT PA

FAN NDV 18 TIEFSTACK IMPELLER SHAFT

ASSEMBLY OF UNIT NO. 1 & 2.

4500061054 HI-TECH MACHINERY 570069.54 No 3

works 59

CONTRACT FOR RESTORATION OF DAMAGED ESP

FIELDS AND SERVICING OF ESP FIELDS IN AHP

500 MW, KHAPERKHEDA TPS

4500061187SUNIL HITECH

ENGINEERS LTD.9714170.19 No 2

Page 8 of 14

Page 9: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

works 60

WORK CONTRACT FOR LIFTING &

TRANSPORTATION OF STONES, SHALE &

METTALIC PARTICLES FOR CHP-II, 500 MW

KHAPERKHEDA TPS.

4500061315 M F JAIN 347757.00 No 2

works 61

WORK OF SERVICING, STRENGTHENING AND

OTHER ALLIED WORKS OF R-600 COAL FEEDERS

OF UNIT NO. 1 & 2 ON AS AND WHEN REQUIRED

BASIS.

4500061464SWAPNIL

ENTERPRISES663069.87 No 3

works 62

WORK CONTRACT FOR VARIOUS MAINT. WORKS

OF ID, FD, PA ON AS AND WHEN REQUIRED BASIS

AT BOILER MAINT-II (500MW).

4500061580BHARTHI

CONSTRUCTION974948.52 No 2

works 63

REPLACEMENT OF WORN OUT PLATES OF

TRANSFER CHUTES FOR CONVEYOR SYSTEM

FOR CHP-II, KHAPERKHEDA TPS

4500061487 S R ERECTORS 443667.71 No 3

works 64HIGH PRESSURE WELDING AT TURBINE

MAINTENANCE - I.4500061568

MINU ENGINEERS AND

ERECTORS764275.04 No 2

works 65

THE WORK OF REPLACEMENT OF PANS, DECK

ROLLERS AND RETURN ROLLERS OF APRON

FEEDERS IN CHP-II.

4500061572 ORION INDUSTRIES 466847.10 No 2

works 66WORK CONTRACT FOR OVERHAULING OF

WOBBLER FEEDER INSTALLED AT CHP2 500 MW4500061870

VAISHNAVI

ENGINEERING

COMPANY

2109000.00 No 2

works 67WORK OF OVERHAULING OF TIME ENGINEERS -

MAKE WOBBLER FEEDER IN CHP-I.4500062189 THE TIME ENGINEERS 912000.00 No 2

works 68

WORK CONTRACT FOR HIRING THE HEAVY

VEHICLE FOR COAL LOADING IN COAL HANDLING

PLANT 500 MW KHAPERKHEDA. [ON AS AND

WHEN REQUIRED BASIS ]

4500062143 M F JAIN 3870054.90 No 2

works 69

WORK OF RUBBER LAGGING OF CONVEYOR

PULLEY BY COLD VULCANIZING PROCESS ( ON AS

& WHEN REQUIRED BASIS ) IN CHP-I, TPS

KHAPERKHEDA.

4500062239THEJO ENGINEERING

LIMITED1304327.14 No 3

works 70

WORK OF TREE PLANTATION AND MAINTENANCE

OF PLANT,ORNAMENTAL PLANTS AND GARDEN

LAWN AT VARIOUS LOCATIONS IN 500MW PLANT

PREMISES AT TPS KHAPERKHEDA

4500062448HOSSAIN

CONSTRUCTION398182.38 No 3

works 71

REPAIRING & LAYING OF RCC PIPE & DRAIN NEAR

SOFT WATER TANK,AT 500MW TPS

KHAPERKHEDA

4500062464SHRI SAI

CONSTRUCTION408808.21 No 3

works 72PROVISION OF LIGHTING SYSTEM AT INTAKE

PUMP HOUSE TO NANDA ROAD.4500062561 D R CONSTRUCTION 555679.50 No 2

works 73ERECTION ,COMMISSIONING OF 25 METER HIGH

MAST TOWER AT TPS KHAPERKHEDA.4500062956

AKELECT

ENGINEERING570672.71 No 4

Page 9 of 14

Page 10: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

works 74

PROVIDING RCC PRECAST DRAIN COVERS OVER

SURFACE DRAINS AND CHAMBERS AT ALL

LEVELS AT VARIOUS LOCATIONS AT 500 MW

PLANT PREMISES TPS KHAPERKHEDA

4500063006SHRI SAI

CONSTRUCTION458775.01 No 6

works 75

WORK CONTRACT FOR CARRYING OUT CAVT IN

BOILER AT U#5 ,500 MW ,TPS, KHAPERKHEDA

DURING AOH.

4500063319MECH-WELL

INDUSTRIES LIMITED627000.00 No 2

works 76

AWORK OF HOT P.A. FAN & I.D. FAN

MAINTENANCE FOR UNIT NO. 1 TO 4 ON AS &

WHEN REQUIRED BASIS AT TPS KHAPARKHEDA

4500063503SHRI GAJANAN

ENGINEERING WORKS527463.75 No 2

AMC 1

ANNUAL WORKS CONTRACT FOR MECHANICAL

MAINTENANCE OF COAL MILLS, COAL FEEDERS,

SEAL AIR FAN AND COAL DUST LEAKAGES

ATTENDING WORK AT U#5, 500 MW, TPS,

KHAPERKHEDA.

4500059022MRP NAIR ENGINEERS

AND CONTRACTORS6994619.13 No 2

AMC 2

ANNUAL WORK CONTRACT FOR MAINTENANCE

OF VARIOUS AUXILIARIES IN AHP STAGE-I, ETP2 &

WAREGAON WATER RECOVERY PUMP HOUSE

(AHP-I).

4500059085ADORECONTRACTORS

PRIVATELIMITED3702510.47 No 2

AMC 3WORK OF CLEANING ON ANNUAL BAISI AT

MAJORE STORES,KHAPERKHEDA4500058496 LUCKY ENTERPRISES 1263635.12 No 2

AMC 4

ANNUAL WORK CONTRACT FOR OPERATION &

MINOR MAINTENANCE OF VARIOUS DE SYSTEM &

OPERATION OF AIR COMPRESSOR FOR BOBR

EVACUATION, HPDS SYSTEM FOR WAGON

TIPPLER NO. 1 & 2 AND ALLIED WORKS IN CHP-I.

4500058792 D R CONSTRUCTION 5051374.14 No 2

AMC 5

ARC FOR MAINTENANCE OF MAIN PLANT

LIGHTING, STREET LIGHTING, LT MOTOR

MAINTENANCE & ALLIED WORKS & CABLE LAYING

WORK OF MAIN PLANT & ODP FOR EM-II.

4500059079 D R CONSTRUCTION 2919723.83 No 2

AMC 6

ANNUAL CONTRACT FOR THE WORK OF

OPERATION & MINOR MAINTENANCE OF STONE

GRAPPLE UNIT AT WAGON TIPPLER NO. I & II IN

CHP-I.

4500058885

VAISHNAVI

ENGINEERING

COMPANY

2446189.56 No 2

AMC 7AWC FOR VARIOUS WORK IN ESP INTERNAL

DURING ANNUAL OVERHOUL OF UNIT NO. 1 TO 44500059560 DEWAJI N KUBDE 2359255.54 No 2

AMC 8

ANNUAL CONTRACT FOR MAINTENANCE &

SERVICING OF FLAME SCANNERS, IGNITORS AND

HPBP SERVO VALVE AS AND WHEN REQUIRED

FOR C&I-II, 500MW KHAPERKHEDA TPS.

4500058931PRATIK INDUSTRIES,

KHAPERKHEDA685620.72 No 2

Page 10 of 14

Page 11: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

AMC 9

ANNUAL CONTRACT FOR ASSISTANCE TO C&I

STAFF FOR MAINTENANCE OF C&I SYSTEM OF

500MW UNIT KPKD TPS.

4500059110 D R CONSTRUCTION 4477960.01 No 2

AMC 10

AWC FOR VARIOUS WORKS IN ESP, BOTTOM ASH

CLINKER GRINDER DISCHARGE LINE DURING

SHORT SHUTDOWN AND RUNNING MAINTENANCE

OF UNIT NO. 1 TO 4

4500059759 DEWAJI N KUBDE 2303062.54 No 2

AMC 11

ANNUAL MAINTENANCE WORK CONTRACT FOR

VARIOUS WORKS OF BFPS AND OTHER

AUXILIARIES (AS AND WHEN REQUIRED BASIS) AT

TURBINE MAINTENANCE-II (500MW) YR.2014-15.

4500059232 S K CONSTRUCTION 1494275.08 No 2

AMC 12

WORK CONTRACT FOR THE WORK OF MANUAL

PICKING UP & DISCHARGING AWAY OF STONES,

IRON PIECES, OVERSIZE COAL LUMP, WOODEN

LOGS ETC. FROM INDIGENOUS COAL FROM THE

CONVEYOR BELTS OF CHP-II, 500 MW, AT T.P.S.

KHAPERKHEDA

4500059024PRINCE THERMAL

INDIA PVT LTD22373685.00 No 3

AMC 13

ANNUAL WORK CONTRACT FOR ASSISTANCE TO

EM-I STAFF TPS, KHAPERKHEDA FOR THE YEAR

2015-16.

4500059143 DEWAJI N KUBDE 5275946.05 No 2

AMC 14

ANNUAL CONTRACT FOR MECHANICAL

MAINTENANCE OF VARIOUS AUXILIARIES FOR

CHP II, T.P.S. KHAPERKHEDA

4500059693LONARE BROTHRES

CONTRACTORS5593315.95 No 2

AMC 15AMC FOR COLONY LIGHTING MAINTENANCE FOR

THE YEAR 2015-16.4500059743 JOY CONSTRUCTION 899477.67 No 1

AMC 16

ANNUAL CONTRACT FOR MISC CIVIL WORKS IN

POWER HOUSE AREA & OTHER ANCILLARY

BUILDINGS AT ALL LEVEL & LOCATION AT

TPS,KHAPERKHEDA

4500059958 RAJU H. GABHANE 436864.81 No 2

AMC 17

ANNUAL CONTRACT FOR MISCELLANEOUS CIVIL

WORKS AT ALL LEVELS & LOCATIONS FOR

MODIFICATION & MAINTENANCE OF VARIOUS

STRUCTURES & BUILDINGS ON AS & WHEN

REQUIRED BASIS AT TPS KHAPERKHEDA

4500060068 P. R. Chandekar, 601435.87 No 2

AMC 18

ANNUAL CONTRACT FOR SEALING HOLES OF

MASONARY WALL, REPAIRING OF SECURITY

GATES AT VARIOUS LOCATIONS & ALLIED WORKS

IN TPS KHAPERKHEDA (AS & WHEN REQUIRED

BASIS)

4500060032 RAJU H. GABHANE 488532.65 No 2

AMC 19

WORK CONTRACT FOR ROUTINE MAINTENANCE

WORKS AT TURBINE & TURBINE AUX INCLUDING

ODP PLANTS FOR UNIT 500MW KHAPERKHEDA

T.P.S

4500062041 S K CONSTRUCTION 4063118.85 No 2

Page 11 of 14

Page 12: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

AMC 20

CONTRACT FOR HOUSEKEEPING & ALLIED

WORKS FOR ASH HANDLING PLANT UNIT #5, 500

MW AT KHAPARKHEDA TPS

4500060476DEEPAK

CONSTRUCTION2297597.04 No 2

AMC 21

ANNUAL WORK CONTRACT FOR THE REGULAR

WORK OF B.G WAGONS UNLOADING AT WAGON

TIPPLERS AND OCCASIONAL WORK OF

UNLOADING OF BTPN OIL WAGONS (OIL

TANKERS) AND ASSOCIATED WORK AT CHP II ,

TPS KHAPERKHEDA.

4500062153 THE TIME ENGINEERS 432496.51 No 2

AMC 22

ANNUAL CONTRACT FOR WORK OF

REPLACEMENT OF WORN OUT MOTHER PLATES

OF TRANSFER CHUTES OF CONVEYORS

SYSTEMS IN CHP-I.

4500060361 ORION INDUSTRIES 433200.00 No 2

AMC 23

ANNUAL WORK CONTRACT FOR HOUSEKEEPING

& ALLIED WORKS FOR AREA I & II FOR CHP II TPS

KHAPERKHEDA

4500060359

S R GAWANDE

CONTRACTER

KHAPERKHEDA

10300255.32 No 2

AMC 24

AMC FOR PROVIDING GENERAL SERVICES OF

MAN POWER IN OPERATION & MISC. WORK IN

AHP-I

4500061401 DEWAJI N KUBDE 3951062.70 No 2

AMC 25

ANNUAL WORK CONTRACT FOR LIFTING,

LOADING & TRANSPORTATION OF COAL MILL

REJECT & COAL OF UNIT NO. 1 TO 4,

KHAPERKHEDA TPS.

4500060580PUNYA COAL

ROADLINES2944620.00 No 2

AMC 26

ANNUAL WORK CONTRACT FOR DOZING THE

STACKED COAL PROPERLY IN COAL PILES

ROUND THE CLOCK & OTHER RELATED

MISCELLANEOUS EMERGENCY WORKS IN CHP-

I,CHP-II & PLANT TPS KHAPERKHEDA.

4500060448 M F JAIN 2250743.04 No 2

AMC 27

ANNUAL WORK CONTRACT FOR OPERATION,

SERVICING, CO-ORDINATION & MINOR

MAINTENANCE OF BEETLE CHARGER FOR CHP-I.

4500060810 ORION INDUSTRIES 4295766.24 No 2

AMC 28

ANNUAL WORK CONTRACT FOR L. P. WELDING OF

TURBINE MAINTENANCE ON AS & WHEN

REQUIRED BASIS FOR UNIT NO. 5 (500 MW) - YEAR

2015-16.

4500061038PRATIK INDUSTRIES,

KHAPERKHEDA663082.82 No 3

AMC 29

ANNUAL CONTRACT FOR THE WORK OF

COLLECTING AND DISPOSING OFF

GARBAGE/KITCHEN WASTE FROM DOOR TO

DOOR & OPERATING SOLID WASTE DISPOSAL

SCHEME IN ENTIRE COLONY AT TPS

KHAPERKHEDA

4500061561 P. R. Chandekar, 1198902.32 No 3

Page 12 of 14

Page 13: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

AMC 30ANNUAL WORK CONTRACT FOR MECHANICAL

MAINTENANCE IN CHP-I, AT TPS, KHAPERKHEDA4500060914 ORION INDUSTRIES 6512682.57 No 2

AMC 31

ANNUAL WORK CONTRACT FOR CARRYING OUT

DAY TO DAY GLASS FIXING TO STEEL WINDOWS

OF QUARTERS IN TEMPORARY COLONY AND

A,B,C,D,E & F TYPE PERMANENT COLONY TPS

KHAPERKHEDA

4500060912 P. R. Chandekar, 490465.54 No 2

AMC 32ANNUAL MAINTENANCE CONTRACT FOR AC

PLANT TM-I KHAPERKHEDA T.P.S4500061406

PRATIK INDUSTRIES,

KHAPERKHEDA1084333.80 No 2

AMC 33

ANNUAL MAINTENANCE CONTRACT FOR AIR

COMPRESSORS ( ST-II UNITS/ WTP) AND

INSTRUMENT AIR DRYERS.

4500061129BALAJI

CONSTRUCTION1170318.02 No 2

AMC 34

ANNUAL WORK CONTRACT FOR BUNKER

SCRAPPING OF UNIT 1TO 4 ( AS & WHEN

REQUIRED BASIS ) IN CHP-I

4500062280 M F JAIN 702545.98 No 2

AMC 35

ANNUAL CONTRACT FOR PREVENTIVE

MAINTENANCE AND MINOR MECHANICAL

MAINTENANCE OF HYDRAULIC SYSTEMS FOR

WAGON TIPPLERS, S.A.C, S/R, AND APRON

FEEDER

4500061226 ORION INDUSTRIES 1163289.06 No 3

AMC 36AMC FOR STRAINERS AT NAVEGAON / KORADI

AND C.T. NOZZLES.4500061246

KORADI BEROJGAR

BOHUUDESHIYA SEVA736657.85 No 2

AMC 37

AMC FOR COMPUTER, PRINTER, SCANNER AND

NETWORKING COMPONENT 2015-16, AT TPS,

KHAPERKHEDA.

4500061225 KEY COMPUTERS 910801.27 No 2

AMC 38ANNUAL WORK CONTRACT FOR CHP-I

HOUSEKEEPING AND ALLIED WORKS AT AREA - I.4500061424

S R GAWANDE

CONTRACTER

KHAPERKHEDA

22150234.82 No 2

AMC 39ANNUAL WORK CONTRACT FOR CHP-I

HOUSEKEEPING AND ALLIED WORKS AT AREA - II.4500061407 M F JAIN 17185751.94 No 2

AMC 40

ANNUAL WORK CONTRACT FOR MAINTENANCE,

STAMPING & VERIFICATION OF WEIGH BRIDGES

AND BELT WEIGHERS IN CHP-I.

4500061397 WEIGHTECH 2045474.50 No 1

AMC 41

ANNUAL WORK CONTRACT FOR HOUSEKEEPING

OF CONVEYOR 102 A/B WITH MINOR MECHANICAL

MAINTENANCE WORK AT CHP-II 500MW TPS.

4500061725 ORION INDUSTRIES 3635264.11 No 2

AMC 42

ANNUAL CONTRACT FOR PREVENTIVE

MAINTENANCE OF CLINKER GRINDER AT U 1 TO U

4

4500062018KUNAL

CONSTRUCTION1012829.76 No 3

Page 13 of 14

Page 14: Name of TPS-Khaperkheda TPS TP… · name of tps-khaperkheda tps ... procurement of boiler feed gate, aph ... unit 2 & 4 building 210mw in t.p.s khaperkheda

Name of TPS-Khaperkheda TPSList of PO proceesed in SETs from Aril 2015 to October 2015

Contract Sr. No. Description of Contracts Order No Name of Agency Value of Order QR Deviation if

any

No. of Qualifying

Bidders

AMC 43

ANNUAL WORK CONTRACT FOR MECHANICAL

MAINTENANCE OF COAL MILLS, COAL FEEDER &

SEAL AIR FANS AT UNIT NO. 1 & 2

4500062797BHAVANA ENERGY

INFRA PVT LTD10487249.22 No 2

AMC 44

ANNUAL WORK CONTRACT FOR LIFTING,

LOADING & TRANSPORTATION OF FLY ASH

COLLECTED AT THE FLOOR AREA OF BOILER TO

AHP U-1 & 4 DISPOSAL OF SAME TO WAREGAON

ASH BUND

4500062866 M F JAIN 435981.60 No 2

AMC 45AMC FOR HT MOTOR OVERHAUL U#1 TO 4 AS AND

WHEN REQUIRED BASIS.4500062345

JAI BHAWANI AIR

CONDIT & MECH WORK329228.35 No 2

AMC 46

ARC FOR MAINTENANCE OF MAIN PLANT

LIGHTING , MAINTENANCE OF MAIN PLANT &

COLONY STREET LIGTTING , HT/LT CABLE LAYING

WORK IN PLANT & COLONY AT KHAPERKHEDA

TPS.

4500063022 D. R. Constructions., 5154112.37 No 2

AMC 47

ANNUAL WORK CONTRACT FOR FABRICATION &

ERECTION OF PLATFORM, LOW PRESSURE

WATER LINES & L.P. WELDING WORKS AT BM-2

AS AND WHEN REQUIRED

4500062566LAXMI ENGINEERING

WORKSHOP308750.19 No 4

AMC 48

PROVIDING SERVICES OF OFFICE ASSISTANTS

AND OFFICE ATTENDANTS IN MPD SECTION,

FQAD SECTION, MAJOR STORE, WELFARE

OFFICE, ACCOUNTS SECTION & SECURITY AT

KHAPERKEHDA TPS

4500062707BALAJI

CONSTRUCTION987306.67 No 2

AMC 49

ANNUAL WORK CONTRACT FOR MAINTENANCE

OF BOTTOM ASH, COARSE ASH, TUBE SETTLER,

WATER & ASH SLURRY PUMPS OF AHP II, UNIT

NO. 5 (500 MW) KHAPARKHEDA TPS.

4500062690G Y LONARE

CONTRACTORS4523360.69 No 3

AMC 50

ANNUAL MAINTENANCE CONTRACT FOR PLC

BASED PRESSURISED AIR CLOSE COAL MILLS

REJECT HANDLING & CONVEYING SYSTEM AT

U#5, 500 MW, TPS, KHAPERKHEDA.

4500062661 A B U CONSTRUCTION 1981464.04 No 2

AMC 51

ANNUAL CONTRACT FOR MECHANICAL

MAINTENANCE WORK OF COAL MILL REJECT

BELT BC1 TO BC4 AT UNIT NO. 1 TO 4.

4500062653 RAJESH ENTERPRISES 2751657.46 No 2

AMC 52

ANNUAL CONTRACT FOR OPERATION OF PLC

BASED PRESSURISED AIR CLOSE COAL MILLS

REJECT HANDLING & CONVEYING SYSTEM AT

U#5, 500 MW, TPS, KHAPERKHEDA.

4500062820 A B U CONSTRUCTION 5882642.88 No 2

AMC 53ANNUAL WORK CONTRACT FOR OPERATION OF

'D' - POINT AT TPS KHAPERKHEDA.4500063151 M F JAIN 2003180.30 No 3

Page 14 of 14