August 6, 2020
NAC Meeting
2
Opening of Meeting &Introduction of NAC Members
Chip Childs, NAC Chairman, SkyWest Airlines
3
Chairman’s ReportChip Childs, NAC Chairman, SkyWest Airlines
4
FAA ReportDan Elwell, Deputy Administrator, FAA
5
Public StatementsMembers of the Public
NAC Subcommittee (SC) Co-Chair’s Report
Craig Drew, NAC SC Co-Chair, Southwest Airlines
6
7
NAC Tasks 18-4 & 18-5: Focus Area Risks/Mitigations
Multiple Runway Operations (MRO)
Surface & Data Sharing
Performance Based Navigation (PBN)
Data Communications
Northeast Corridor (NEC)
FAA NIWG Subject Matter Experts (SMEs)
8
Multiple Runway Operations (MRO)Natee Wongsangpaiboon, FAA & Raul Zamora, Jr., FAA
Glenn Morse, United Airlines & Phil Santos, FedEx
MRO Update – Accomplishments
• Use of RNAV for SFO 7110.308 Procedures
‒ FAA pre-implementation milestone complete; preliminary analyses show some combinations may be feasible
‒ Industry discussions with AJT planned
• Reduced Minimum Radar Separation (MRS) – FAA/Industry Milestones Complete
‒ Industry comments delivered to FAA in June with implementation recommendations
‒ Additional FAA safety studies in progress; concurrence to pursue extension (2.5 nm w/in 20) before reduction (2.0 nm w/in 10)
‒ Identified by “Opportunities ad hoc” as game changing concept
• Wake Turbulence Encounter Reporting
‒ Industry Milestone Complete - Encouraged increased wake encounter reporting based on new FAA reporting guidance
• Converted 2 original 2.0/1.5 RECAT sites (DTW and IAH) to Consolidated Wake Turbulence (CWT)standards
• Integrated Arrival/Departure (IAD) concept for Closely-Spaced Parallel Runway (CSPR) Operations
‒ FAA pre-implementation milestone complete, additional FAA safety studies in progress
2 miles
< 2,500 feet
Release Distance < 2 miles
Currently Authorized “2 increasing to 3 rule” IAD Concept (reduced separation)
9
MRO Update – COVID Impacts and Looking Ahead
• CWT Implementation – FAA Milestone
‒ Remaining sites planned for conversion in 2020 and 2021 are delayed until facilities can accept CWT training
‒ New schedule TBD
• Consolidated Wake Turbulence (CWT) Separation Standards Benefit Analysis –Industry Milestone
‒ Assess benefits from implementation of CWT separations at initial CWT locations (Q4 2020)
‒ Preliminary discussions held to identify study locations (IAD, DFW, SEA, BOS) and carrier support
‒ Benefits related to fleet mix and traffic demand at each airport/runway; assessment will focus on CWT separation changes within aircraft pairs
‒ Potential Risk – Industry resources post-COVID to conduct detailed analysis. Industry may need JAT support for this task based on previous JAT analyses
10
11
Surface and Data SharingDoug Swol, FAA & Ayaz Kagzi, FAA
Rob Goldman, Delta Air Lines & Steve Vail, Mosaic ATM
COVID Impacts to Terminal Flight Data Manager
• All TFDM-related travel, since March 20th, has been restricted only to
activities related to sustainment of critical NAS systems.
• Limited access to the FAA Atlantic City tech center for testing
‒ Currently, no access to training academy (for training technicians)
• No access to air traffic facilities (to conduct installation, testing, training)
• NAC Milestones on “TBD” status until there is better fidelity of information
regarding re-planning efforts and COVID-related constraints.
‒ TFDM B1 IOC in PHX will postponed till 2021
• While TFDM deployment activities are restricted, FAA continues to make
progress:
‒ TFDM software development and adaptation continues
‒ TFDM software “remote testing” initiated
12
NAC Milestone Impact
SURFACE AND DATA SHARING
PRE-IMPLEMENTATION COMMITMENTS Old Date New Date
TFDM program will complete the operational testing for Build 1 Q2 CY2020 Q2 CY2021*
NASA ATD-2 interim technology transfer from Phase 2: Fused IADS at CLT Q4 CY2019 Complete
NASA ATD-2 final technology transfer from Phase 3: Terminal departure IADS at DFW/DAL
Q3 CY2020 Q4 CY2021
IMPLEMENTATION COMMITMENTS Old Date New Date
TFDM program will achieve key site IOC for Build 1 at PHX Q2 CY2020 Q2 CY2021*
TFDM program will achieve the in-service decision (ISD) for Build 1 to allow
additional TFDM system deployments into the NASQ4 CY2020 TBD
TFDM program will achieve IOC at 3 additional sites Q1 CY2021 TBD
TFDM program will achieve the key site IOC for Build 2 at CLT Q4 CY2021 TBD
TFDM program will achieve ISD for Build 2 to allow additional deployments of the full TFDM capabilities into the NAS
Q1 CY2022 TBD
TFDM program will achieve IOC at 5 additional sites Q1 CY2022 TBD
* Notional Dates dependent on ability of program to travel, access FAA facilities,
conduct training and conduct testing. If dependencies are not met, the program will
not meet these dates.
13
Engagement and Commitment Remains Strong:
• NIWG meetings provide programmatic and operational updates as well as
exploration of virtual opportunities
• NASA ATD-2 phase 3 extended from Q4 FY2020 to Q4 FY2021
• SWIFT quarterly (virtual) meetings continue to address SWIM and the
data/information sharing needs of the entire community to support iTBO /
TBO, Future Flow Management, actionable analytics and more
• TFDM connection testbed option available later this Fall
• FAA will sustain NASA ATD-2 in Charlotte until TFDM is deployed
• FAA will lead Collaborative Site Implementation Team (CSIT) Meetings
14
TFDM Build 1 Program Status
Build 1 Status (Key Site: PHX)
– TFDM Vendor delivered Software
v1.1a to FAA’s WJHTC (“Tech
Center”)
– FAA will initiate formal
Development Test (DT) on 1.1a
on 7/20/2020
– FAA implemented remote
viewing capability to conduct DT
remotely (due to COVID-19)
– Evaluating if Operational Testing
(OT) at the WJHTC can be done
remotely
15
TFDM Build 2 Program Status
Build 2 Status (Key Site: CLT)
– B2 software development continues
– First version of B2 software available
for use in TFDM labs at the WJHTC in
Fall 2020
– Authorized Leidos to develop
TTP/TFCS testbed
– Planning initial kickoff meetings with
airlines in July
– Briefed SWIFT on TFDM Program
• Developing TFDM Use Cases
and Operational Context
Documents
16
TFDM Testbed
• Flight Operators connect to a Simulated NEMS node and SWIM cloud
to connect to TFDM’s TTP and TFCS services
• Allows flight operators to understand new TFDM data and how that
data is interfaced to flight operator systems
• To help flight operators prepare for TFDM and new data flows, TFDM
program will offer a testbed to connect with
• Testbed will start in Fall 2020
17
SWIM Industry FAA Team (SWIFT)
• SWIFT addresses our industry’s evolution toward actionable data and insight
• Collaborative Decision Making (CDM), admittedly the gold standard in traffic flow
management, began with a simple premise on exchanging data to better manage
the NAS.
• Designed to address a NAC request to provide operational context to the IT-centric
documentation for information available on SWIM, SWIFT has grown to improve
communications across a broader set of NAS stakeholders needs with NAS SWIM
producer systems
• As the aviation community becomes more data-centric, operationally and analytically,
the SWIFT forum is evolving to capture the myriad needs of industry and FAA alike as
a clearinghouse for collaborative engagement around NAS information and data
sharing and producer system data requirements
• SWIFT supports digital collaboration across the traditional aviation community as
well as new NAS entrants, enabling iTBO/TBO and Future Flow Management
• SWIFT Meetings are held quarterly and are included in the industry NJIP
commitments
18
19
20
21
Performance Based Navigation (PBN)
Juan Narvid, FAA; Aaron Wilkins, FAA; Wendy O’Connor, FAA
Brian Townsend, American Airlines & Bill Whyte, RAA
PBN Key Issues
• COVID-19 impacts are affecting JIP due to travel restrictions,
training and access facility
‒ Annual update to JIP is in DRAFT with new JIP dates
• EoR
‒ Barriers to EoR report complete
‒ Industry assessing ways to further next steps
• VNAV
‒ VNAV issue continues to impact EoR implementation
‒ FAA continuing work with ALPA
22
PBN NIWG Commitment StatusMilestone Date Status (New updated JIP dates)
CLE/DTW Post-impl. phase complete 1QCY20 Completed - 10/10/19
DEN Implementation phase startImplementation phase completePost-impl. phase complete
1QCY202QCY201QCY21
Completed - ACM 1/28/20Completed - 3/26/20TBD
LAS Implementation phase startImplementation phase completePost-impl. phase complete
2QCY203QCY202QCY21
Completed – 7/7/201QCY21 - Targeting 11/2020TBD
Florida Implementation phase startImplementation phase complete
4QCY203QCY21
On Track - Expect to commence 10/2020On Track - Expect to publish procedures 8/2021
Provide input, validate data, review findings and confirm conclusions to post-impl.analyses for implemented PBN procedures.
CLE/DTW Q3CY20DEN Q3CY21LAS Q4CY21
On Track – FAA delivered data to Industry focalsTBDTBD
Implement select iTBO capabilitiesin NEC and Denver
NEC Q4CY21
DEN Q4CY21
On track - Currently maturing the time-based metering design and coordinating with field facilities to prepare for departure scheduling from multiple ARTCCs.
On track - Currently planning the implementation of enroute metering improvements in 2020.
23
Barriers to EoR Work Group
• Barriers to EoR WG met June 23rd to discuss the following:
‒ Review of FAA’s response to Dec 2019 report
‒ Attempt to determine the relevance of the “VNAV Issue” to the
Barriers Report
• Next Rolling Plan
‒ Identify what aspects of Barriers to ER should be considered for the
2022-2024 Rolling Plan
‒ This is vital to moving EoR forward in the NAS
24
VNAV Way Forward – Next Steps
• FAA initiating a meeting with ALPA Safety Leadership – Anticipated
for July
• FAA will complete a Safety Risk Management (SRM) on proposed
changes
• PBN NIWG will continue to support and engage
• The VNAV concerns continue to impact progress with certain EoR
applications and has been raised within the PBN Clarification Ad Hoc
discussions
25
26
Data CommunicationsJesse Wijntjes, FAA
Chris Collings, L3 Harris & Chuck Stewart, United Airlines
Data Comm Accomplishments
• Activated Data Comm services at first 3 En Route Centers
‒ En Route services exceeding operational performance targets – best performing
data link capability in the world
• Air-ground interop issues fault isolated & addressed
‒ Avionics software updates delivered and/or in development for all identified
issues
‒ Implemented fixes and upgrades to air-ground networks
‒ ERAM system performance & enhancements have been and continue to be
critical to program success
• Operators purchased & installed upgrades to enhance air to ground system
performance
• Business/General aviation & DoD communities addressing avionics issues and
resuming En Route participation
27
Data Comm Operational Status
28
Data Comm Critical
Path Action
Operating, no action
required
Operating, pending
actionPlanned Delayed/ Not operating
Completed Actions
Operator & Fleet Actions Complete Status
American Airlines: B777 Operating en route, no action required
FedEx: B777 Operating en route, no action required
Southwest Airlines: B737 Operating en route, no action required
UPS: B744, B757, B767, MD11 Operating en route, no action required
Avionics Actions In Progress
Avionics Action Operator/Fleet Status
Collins CMU 900 Core 16 FedEx In progress
Collins VDR Update FedEx In progress
Boeing 777 AIMS 2 BP17B United In progress
Boeing 787 CMF BP6 American, United In progress
Pending Avionics Actions
Avionics Action Operator/Fleet Status
Collins CMU 900 Core 16 Alaska, American, Delta, United Delayed – On hold due to COVID
Collins VDR Update Alaska, American, United Delayed – Installs slowed due to COVID
Airbus ATSU CSB 7.5 Alaska, American, Delta, JetBlue Delayed – Release delayed Q3 2020 due to COVID
Boeing Pegasus 1 Fix FedEx, UPS, United Planned – February 2021
Boeing 747-8 ATN-204 UPS Planned – Q2 2021
Industry Avionics Accomplishment
29
Data Comm COVID-19 Impacts
FAA
• COVID-19 caused the suspension
of all En Route facility training and
testing activities beyond site 3
Industry
• Installation of avionics updates
delayed or slowed by COVID-19
o Collins CMU 900 Core 16
o Collins VDR update
o B787 & B777 updates
• Airbus delayed A320/330 ATSU
release 7.5
30
Data Comm Forward Plan
FAA
• The team continues to focus on
reducing implementation risks
once we restart the waterfall
• Completion of the waterfall will be
executed as safely and efficiently
as possible
Industry
• Despite the impacts from COVID-
19, multiple operators continue to
make plans to resume avionics
updates
• Boeing and Honeywell are in
development on a fix for the B757
& B767 FMS
Industry & FAA Data Comm team is ready to resume the
national deployment of En Route services
31
Data Comm Metrics
32
Data Comm Tower by the Numbers
65 Non-US
Air Carriers(Part 129)
67
Aircraft
Types
1,900+
Business Aviation
Operators(Parts 91, 91K, 135)
16 US Air
Carriers(Part 121)
Over 5,900
Equipped
Aircraft
62
Airports
33
Data Comm Tower Benefits
34
Prevented 124,330+ readback
errors
Saved 2.19M minutes of
radio time
Saved 1,569,285+ minutes of
airspace user time
Served 1.09B+ passengers
Cleared 8,105,045+ flights
Prevented 18.7M Kgs of CO2
Emissions
Departure Clearance Benefits Realized Since 2016
Data Comm En Route by the Numbers
2,022,391
transactions
330,136
sessions
22
aircraft types
17
operators
36,102 readback
errors mitigated
136,155 minutes of
comm time saved
En Route Data Comm Since 2019
35
Data Comm Avionics Status
36
Action Status
Collins Core 16 Collins: Delivered Core 16, demonstrating strong performance
Operators: UPS complete; FDX: 55% complete; 4 delayed due to COVID-19
Pegasus I Mitigation Interim Procedure Mitigation; expires 12/2/20; 2 operators using
Stale message point fix to Peg 1 – Feb 2021
Address gap between procedure mitigation & Peg 1 fix
Honeywell Mark II+ v523 Delivered, installed and, demonstrating strong performance
Boeing 787 BP6 Service Bulletin released on 20 December 2019, installs progressing
Airbus ATSU CSB 7.5 Service Bulletin delayed from June 2020 to Q3 2020
Boeing B748 ATN-204 Service Bulletin planned from Boeing Q2 2021
Boeing 777 BP17B Service Bulletin released on 16 December 2019, installs progressing
Business Aviation Initial fleets re-started en route ops; Targeting September 2020 to publish
acceptable avionics for G/BA fleet types
Revise NOTAM – Planned September 2020
Data Comm Avionics AvailabilityCommitments and Risks
Pri
ori
ty I
tem
s
Complete & Operating Available for Install Planned Delayed
37
Data Comm Operator Status
Operator Fleet Avionics Action Action Complete by Action Status Action Risk Active En Route
A320 ATSU CSB 7.5 Plans to installRelease delayed to Q3
2020Delayed Operating
B737
Collins CMU 900 Core
1631 August 2020
Negotiations with Collins
ongoingDelayed
Operating
Collins VDR SB 30 March 202012% installed
Working supplier issueDelayed
A320 ATSU CSB 7.5 Plans to installRelease delayed to Q3
2020Delayed Operating
B737
Collins CMU 900 Core
16
80% 3 months from
release, full fleet by
August 2020
TBD
Delayed due to COVID-
19Delayed
Operating
Collins VDR SB31 December 2019
30 April 2020Complete Complete
B777 AIMS 2 BP17B30 March 2020
31 August 2020
All operating aircraft
updated
Nearing
completionOperating
B787 CMF BP630 March 2020
Delayed
10.3 pre-req – 90%
10.4/BP6 0% -- Starting
after 10.3 complete
PlannedPlanned:
TBD 2021
Data Comm Critical
Path Action
Operating, no action
required
Operating, pending
action
At Risk/Planned Delayed/ Not operating
38
Data Comm Operator Status
Operator Fleet Avionics Action Action Complete by Action Status Action Risk Active En Route
A320 ATSU CSB 7.5 TBD Operating
A350 None Operating
B737
Collins CMU 900 Core
16
80% 3 months from
release, full fleet by
August 2020
TBD
Delayed due to COVID-
19Delayed
Operating
Collins VDR SB 31 Dec 2019 All VDRs corrected Complete
B757/67
Collins CMU 900 Core
1631 August 2020
B757: 44% installed Install in
progress
Planned: August
2020
B767: 75% installed
Collins VDR SBB757 – 31 July 2020 B757: 85% complete On plan
B767 – Complete B767: Complete Complete
Peg I Mitigation 31 August 2020Plan to implement
procedure mitigationPlanned
B777
AIMS 2 BP17B 30 June 2020 Complete
Complete Operating
Collins VDR SBFebruary 2020
30 April 2020 Complete
MD11
Collins CMU 900 Core
1631 August 2020 45% installed
Install in
progress Planed: August
2020Collins VDR SB
March 2020
31 August 202057% complete On plan
Data Comm Critical
Path Action
Operating, no action
required
Operating, pending
action
At Risk/Planned Delayed/ Not operating
39
Data Comm Operator Status
Operator Fleet Avionics Action Action Complete by Action Status Action Risk Active En Route
A320 ATSU CSB 7.5 6 months from release Release delayed to
Q3 2020Delayed Operating
B737 Honeywell Mark II+
CMU v52330 April 2020
All operating aircraft
updated
Nearing
completionOperating
B744
B757
B767
MD11
Collins CMU 900 Core
16
70% 3 months from
release, full fleet by 31
August 2020
Complete
Complete Operating
B748 Collins CMU 900
ATN-204
70% 3 months from
release, full fleet 6
months from release
Awaiting release from
Boeing
(Q2 2021)
Pending
releaseOperating
Data Comm Critical
Path Action
Operating, no action
required
Operating, pending
action
At Risk/Planned Delayed/ Not operating
Data Comm Operator Status
Operator Fleet Avionics Action Action Complete by Action Status Action Risk Active En Route
B737
Collins CMU 900 Core
16
October 2020
TBD
Delayed due to COVID-
19Delayed
OperatingCollins CMU 900 VM
update30 Apr 2020 92% installed
Nearing
Completion
Collins VDR SB 30 Apr 2020 82% installed On plan
B757/67
Peg I Mitigation29 Feb 2020
TBD
Pending approval of
alternate approachDelayed
Very few B757/67
Ops due to
COVID
Collins CMU 900 Core
16
October 2020
TBD
Delayed due to COVID-
19Delayed
Collins CMU 900 VM
update
30 Apr 2020
TBD18% installed Planned
Collins VDR SB30 Apr 2020
TBD
88% installed Nearing
Completion
B777 AIMS 2 BP17BMarch 2020
August 2020Installs started On plan Operating
B787 CMF BP6March 2020
Fall 2020
10.3 pre-req 51%
10.4/BP6 20%On plan Operating
Data Comm Critical
Path Action
Operating, no action
required
Operating, pending
action
At Risk/Planned Delayed/ Not operating
41
BA/GA Return to En Route Data Comm Operations
42
Data Comm NJIP Milestones CY19-21
43
Data Comm – NJIP CY19-21 Milestones (1 of 2)
MilestoneFAA
or
Industry
Milestone Date
Q/CYStatus
Airlines to Equip 1,900+ Aircraft Industry 4Q2019 Complete
Deploy Tower Services to an additional
seven towersFAA 3Q2019 Complete
Baseline additional Data Comm capabilities
for En Route utilizing the existing FANS
message set
FAA
Industry
3Q2021
3Q2022
Deferred to 2022 to align with
deployment of initial and full
services en route and funding
constraints.
IOC for Initial En Route Services at all
CONUS ARTCCsFAA
4Q2019
4Q2021
4Q2022
Milestone impacted by
COVID-19;
Remainder of waterfall to be
re-planned.
Resolution of avionics/Pegasus 1
interoperability issueIndustry 4Q2021 Extension requested
With the impacts from COVID-19, the last site IOC milestone
needs to be adjusted based on when the program can
restart the waterfall once facility access restrictions are lifted.44
Data Comm – NJIP CY19-21 Milestones (2 of 2)
MilestoneFAA
or
Industry
Milestone Date
Q/CYStatus
Recommendation for target equipage
rates for follow-on capabilities
FAA
Industry
1Q2019
2Q2019Complete
Recommendation for the equipage
strategy for Regional Jet equipageIndustry
1Q2019
2Q2019Complete
Loadability Solution for Runway SID/STAR FAA 3Q2019
Complete – Plan developed
for future TFDM
implementation
Solution for Full Automation for the
Confirm Assigned Route CapabilityFAA 3Q2019 Removed
45
Northeast Corridor (NEC)
Aaron Wilkins, FAA; Juan Narvid, FAA; & Wendy O’Connor, FAA
Mark Hopkins, Delta Air Lines & Ralph Tamburro, PANYNJ
46
Northeast Corridor - Key Issues and Status
• 2020/2021 Commitments
‒ Due to COVID-19, facility access limitations, travel restrictions and fiscal
austerity will delay completion of several commitments (e.g. ACR and GBAS)
‒ Virtual meetings allow continuation of coordination and planning (e.g.
Industry TOS discussions)
• Advancing pre-implementation milestones
‒ LGA Runway 31 RNAV GPS collaborative meetings are continuing
‒ High-performance escape routes for TEB/HPN
• Looking ahead – meetings planned thru Nov NAC
‒ Additional discussion on pre-implementation milestones
‒ Support to Ad Hoc Teams and other NIWGs
‒ Focus on priorities that support agile recovery, specifically within the NEC
47
Outlook for CY2020 Commitments
Type Commitment/Milestone NJIP Date Status
Implementation*Improved departure management for flights
destined for LGAQ3 CY2020 TBD
Implementation* DSP enhancements Q4 CY2020 TBD
Implementation* Atlantic Coast Routes Q4 CY2020 Q4 CY2021
Implementation* PDRR/ABRR Enhancements Q4 CY2020 TBD
Pre-implement* FIM review and analyses Q3 CY2020 Completed**
Industry GBAS evaluation at BOS Q2 CY2020 Q4 CY2021
Industry DCA north end hold pads Q3 CY2020 TBD
Industry PHL 27R analyses Q3 CY2020 Completed
Industry GBAS at LGA Q4 CY2020 TBD
* Implementation and Pre-implementation milestones are all jointly shared by FAA and Industry for the NEC efforts
** Additional coordination between NEC NIWG and Equip2020 WG4 expected
48
Task 18-4: Northeast Corridor: Implementation Risks and Mitigations of the NextGen Priorities Joint Implementation Plan
“The FAA requests that the NAC identify Northeast Corridor risks and
mitigations to the successful operational implementation of industry
commitments with respect to the NextGen Priorities Joint Implementation
Plan through calendar year 2021. This should also include any needed
industry mitigations to support successful operational integration of the
joint commitments.”
49
Accomplishments (since Dec 2019 NAC)
• Several commitments from CY2019 and CY2020 completed on time or early
‒ High speed exits for JFK Rwy 31R implemented
‒ ZNY PBN offshore routes implemented
‒ CRDA and .308 feasibility studies for EWR
‒ EFVS benefits and applicability studies
‒ Expanded use of CDTI-applications beyond CAVS
‒ Data-driven TFM analysis
‒ Gate docking technology assessment
‒ Data sharing commitments from FedEx and Southwest
‒ FIM NEC benefits study
‒ Publication of new GLDMN/NTHNS departures*
* Pre-implementation commitment completed in 2019; implementation
of the modified procedures was not a formal NJIP commitment
50
Summary of Activities (since Dec 2019 NAC)
• Ongoing Industry discussions on multi-route trajectory option sets (TOS)
‒ To respond to NEC Industry commitment due in Q4 CY2021
‒ Objective of Industry meetings is to level set expectations around
TOS applications and build consensus Industry perspective for the
NEC
‒ Received overview from CDM Flow Evaluation Team on their
recommendations for TOS
‒ Received update from NASA ATD-2 Phase 3 team on experiments
and research ongoing in Dallas
51
Summary of Activities (since Dec 2019 NAC)
• Multiple Airport Route Separation (MARS)
‒ Follow-up to the pre-implementation milestone completed in
Q2CY2019
‒ Update provided by the MARS project team
o Operations concept has been updated (includes feedback
from completed milestone)
o Additional geometries and applications have been included
o Current focus is on safety analysis and data collection to
support safety study
52
Summary of Activities (since Dec 2019 NAC)
Objectives:
• Enhance safety with repeatable
ground track
• High operator participation
• Reduce noise complaints from
the city of Flushing
RNAV GPS Instrument Approach
Procedure for LGA Rwy 31
53
COVID-19 Impacts
• Access to FAA and Industry facilities severely restricted
‒ Operational facilities are most impacted
‒ Simulators and laboratories also impacted
• FAA and Industry training impacted
‒ Access to training labs and availability of personnel
• Travel has been suspended for FAA and Industry
• Fiscal austerity impacting investment
• Dramatic reduction in traffic levels across US but very pronounced in
the Northeast
54
COVID Impact on Initiatives Highlighted at December 2019 NAC
Atlantic Coast Routes (original Nov 2020, now late 2021):
• Meetings with flight planners can continue virtually
(e.g. briefing to JetBlue in March 2020)
• Controller training and facility access are challenges
• Aligning with other project waterfalls
Philadelphia Metering Initiatives
(still late 2021):
• SW development can continue
• Controller training and facility
access are challenges
Washington Center Redesign
(original Oct 2020, now late 2021):
• Controller training and facility access
are challenges
55
Impact on Remaining 2019-2021 NJIP Commitments
• Five remaining NEC implementation commitments
‒ Four in CY2020: Delays expected for all remaining CY2020
commitments
o Improved departure management for flights destined to LGA
o DSP enhancements
o Eastern seaboard high-altitude routes (Atlantic Coast Routes)
o PDRR/ABRR
‒ One in CY2021: No delay reported yet
o Arrival time-based metering (TBFM) for PHL
56
Impact on Remaining 2019-2021 NJIP Commitments
• Eleven remaining NEC Industry commitments
‒ Seven in CY2020:
o PHL airport infrastructure assessments completed early
o Delays expected for four CY2020 commitments
GBAS implementation at LGA
GBAS evaluation at BOS
DCA north end hold pad evaluation
Industry support to ACR implementation (tied to FAA delay)
‒ Four in CY2021:
o Delays expected for one commitments
GBAS implementation at JFK
57
Unique Circumstances Leading to Unique Opportunities in NEC
• Lower traffic levels may provide opportunities to introduce concepts and revisit completed post-implementation milestones
• Returning fleet may have different characteristics
• Focus on operational priorities that support agile recovery
Core 30 Airports
Operations
NY3 Airports
Operations
58
NEC Inputs to “Opportunities” Discussion
LGA RNAV GPS approach to Rwy31: public instrument approach procedure that can
provide a stable and guided path to the threshold of RWY31, enhancing the safety
• LGA GLDMN and JFK 31L SKORR departures: use altitude separation to allow
simultaneous departures; dispersal headings from LGA 13 provide departure
efficiency; also improves efficiency by providing JFK with opportunities to utilize 31L
for departures
• EWR 22L/29 operation: address the loss of a second landing runway at EWR during
southwest to west winds, enabling a significant reduction in minutes of arrival delay
• LGA ILS 13 approach deconflicting TEB/EWR/LGA: deconflicts the three airports, to
improve overall airspace operations and reduce the number of configuration
changes
TEB/HPN escape route: provides for an alternate route out of the airspace for
capable business aviation aircraft
FAA has agreed to pursue
59
60
NAC Task 19-1: Minimum Capabilities List (MCL)
Ron Renk, United Airlines
Greg Young, Delta Air Lines
How We Got Here...
• NextGen Integration Working Groups (NIWGs):
‒ Northeast Corridor (NEC)
‒ Performance Based Navigation (PBN)
‒ Data Comm
‒ Surface
‒ Multiple Runway Operations (MRO)
• Many had a common thread in their reports:
*MIXED EQUIPAGE impedes NextGen*
61
Refresher – What is MCL?
The Minimum Capabilities List is a forward-fit list of equipage
that was created by a large segment of the aviation industry to
avoid mixed-equipage issues when implementing NextGen in
the National Airspace System.
62
Tasking:
NAC Task 19-1:
NAS Aircraft Minimum Capability List (MCL) Oct 4th, 2019
Sub-Task #1
Collaborative analysis of current fleet equipage with respect to the MCL capabilities
Sub-Task #2
Socialization of the MCL with additional stakeholder groups, including aircraft and
equipment manufacturers and regional airlines not involved in discussions to date
Sub-Task #3
Recommendations on steps to encourage MCL adoption and commitments to equip aircraft
with the associated capabilities
63
Sub-Task #1: Analysis
Air Transport
AircraftTotal Count
Baseline MCL
Approach Terminal En Route
RNP AR
A-RNP RNAV (GPS)
RNP-1 w RF RNP-2Capable Ops Spec
Coupled VNAV
Advisory VNAV only
WB/NB 5,355 4,827 4,859 4,088 5,130 225 4,859 5,303
Regional 2,033 702 887 509 1,106 927 887 2,021
WB/NB 5,355 90% 91% 76% 96% 4% 91% 99%
Regional 2,033 35% 44% 25% 54% 46% 44% 99%
Air Transport
AircraftTotal Count
Baseline MCL
Data Comm
DCL Enroute CPDLC
WB/NB 5,355 3,603 3,134
Regional 2,033 34 31
WB/NB 5,355 67% 59%
Regional 2,033 2% 2%
Air Transport Aircraft
Total Count
Baseline MCL
Resiliency
DME/DME/IRU
WB/NB 5,355 5,242
Regional 2,033 705
WB/NB 5,355 98%
Regional 2,033 35%
* Pre-COVID numbers, Regional = 90 seats or less
64
Sub-Task 2: Socialization
• Baseline and Supplemental matrices complete
NextGen Enabling
Category
Aircraft Enabling
Capability
Key Missing
ComponentsBenefit Example Use Cases Areas Receiving Benefit Ground Investment Risks to ROI
Performance Based
Navigation
• RNP-2 (Enroute)
• RNP-1 w/ RF (Terminal
SID/STAR)
• RNP APCH w/ RF
(Approach)
• A-RNP or RNP AR 0.3 w/
RF (Approach)
• RNP Scalability
• Autopilot-coupled VNAV
• RF Leg Type
• Autopilot-coupled
VNAV
• Auto-throttle
• RNP AR capability
• FMC database size
• Precise deconflicted arr and dep with
reduced separation reqs
• Shorter track miles
• Reduced fuel burn
• Maximize poor weather capacity
• Predictable flows
• Increased access
• Reqd for Trajectory Based Operations
(TBO)
• Established on RNP (EoR)
• RNAV/RNP arrivals/departures
• Optimum Profile Descents (OPD)
• Q/T/Y routes
• LNAV/VNAV apch minima
• Apchs where ground based navaid
does not exist or is being removed.
• North East Corridor (NEC)
• NSG-1/NSG-2 Airports
• Terminal Airspace
• GA Airports with restricted
access due to conflicts with
terrain or other airports
○ SMO, G3ADS, PWK
HHR, MRI, OPL
• Enroute (more efficient
routing)
• Maintain access after NAVAID
decommissioning
• Airspace and procedures
enhancements
• Reduced lateral separation
between routes
• Controller training
•Procedure implementation
process (IAP, EoR)
• FAA Policy
• Reqd environmental work
• Non-equipped a/c
• Decision Support Tools
• Automation enhancements
• Requires pre-conditioned flows
• Right sizing development
• Maintenance and removal of
procedures
• FMC database size to support
new procedures & wpts
Data Comm
• FANS-1/A with "Push to
Load" over VDL Mode 2
with multi-frequency
• CMU/CMF/ATSU
• VHF Digital Radios
• FANS 1/A capable
FMC/FMGC
• Shorter ground delay for clearances
• Reduced communication errors
• Efficient delivery of complex clearances
• Reduce long voice communications
• Reduced freq congestion
• Accurate re-route
• Weather avoidance
• Pilot requested re-routes
• Enables Trajectory Based Operations
(TBO)
• CTOP/TOS
• High rate clearances during SWAP
• Efficient wx re-route
• Improved human factors (errors in
re-route entries)
• More efficient routing
• NAS ground ops
• Enroute ops
• Development / delivery of
Data Comm svcs
• Enhanced automation and
Decision Support tools
• Controller training
• Pilot/Controller training during
implementation
• Non-equipped a/c
• Actual system performance
• Conformity of equipment to use
FANS messages (older spec being
adapted for modern use)
• Partially equipped aircraft -
Meets some but not all FANS 1/A
requirements
Surveillance
• ADS-B Out - Mandate • Transponder
• Highly accurate
position source with
integrity
• Enables 3NM enroute separation
• Reduced separation in select situations
• Improved surveillance in non-radar
areas (including surface)
• More accurate position; more frequent
update rate
• Enables improved safety via ATC
automation and TFM Decision Support
tools
• Improved Planning and TFM Services
• Improved SAR
• Enables ADS-B IN applications
• 3NM enroute separation
• Western Atlantic Route System
(WATRS) operations surveillance
• Reduced terminal vectoring due to
conflict
• Enhanced SAR
• Enroute
• Terminal
• Non-radar environments
• Mountainous terrain
• Ground infrastructure
• ERAM/STARS enhancements
• Controller training
• Reduced Spacing
Performance Based
Navigation, Low Vis
Ops, Surveillance
• Resilient NextGen Ops
(DME/DME/IRU)
• Airworthiness approval
for DME/DME, IRU
Hardware
• Resilient terminal and enroute ops with
GPS loss (Jamming or hardware failure)
• Q/T/Y Routes
• RNAV SIDs and STARs
• Navigation and surveillance
resilience for all NAS ops;
needed most in remote areas.
None
65
Sub-Task 2: Socialization (cont.)
66
Sub-Task 3: Adoption and Commitment
• Scope – To whom does the MCL apply? (DONE)
• Retrofit – “If I took delivery of airplanes just last year, what items would I
need to buy so as not to become an impediment to NextGen?” (DONE)
• Cost/Benefit – “What will this cost me and what will I get in return?”
(INCOMPLETE)
67
Conclusion
• 2 year effort: Level of interest and collaboration was robust
• The Baseline and Supplemental matrices are complete
• No doubt a “WIN” for all stakeholders
‒ Path forward to use technology to improve NAS operations
• In order to assure MCL success, it needs:
‒ High level of participation/adoption from Industry, and
‒ Corresponding FAA investment response
68
Conclusion
• Best outcome – Airlines and General Aviation Operators, that are within
scope, elect to use the MCL to establish aircraft equipage specifications
for OEMs (MCL Baseline becomes standard equipment).
• Though NAC tasking, in spirit, is “complete;” completion of the final
three issues are critical to its success. Due to COVID issues we request
one additional meeting cycle to finalize the effort and provide the NAC
a more detailed conclusion.
69
70
NAC Task 19-3: Joint Analysis Team (JAT)
David Knorr, FAA
Alex Burnett, United Airlines
NEC Phase 1 Implementations
Implementations with measurable quantitative benefits in bold
Note: 1 & 2 will be studied together as systems combine to produce measurable benefit
*
InitiativeInitial Ops Availability
SupportingOrg.
Study Periods Benefits Assessment
1 Implement EDC at ZNY Q1 2018 FAAMITREAA, DL, UA, JB
Mar-Sep 2017 vs.
Mar-Sep 2018
Preliminary: Oct 2018Initial: Feb 2019Final: Apr 20192 Implement TBFM IDAC at 4 NY Towers Q1 2018
3 Implement BOS SWIM Visualization Tool at ZBW Q2 2018
4 Implement SCIA to PHL 9R/17 Q3/Q4 2018FAAMITREAA
Jan -Jun 2018 vs.
Jan -Jun 2019
Preliminary: Apr 2019Initial: Oct 2019Final: Jan 2020
5Implement CRDA DCIA application for PHL 27R/35 for RNAV approaches
Q1 2019FAAMITREAA
Apr -Oct 2018 vs.
Apr -Oct 2019
Preliminary: Oct 2019Initial: Feb 2020Final: Apr 2020
6 Improve airborne metering to PHL Q1 2019FAAMITREAA
7
Expand consistent usage of defined and existing capping and tunneling for departures/arrivals to/from the NEC through required advisories
Q1 2019FAAMITREDL,AA,UA,othr
8Implement TBFM Pre-Departure Scheduling at selected airport
Q1 2019
71
Background
• JAT Tasking:
‒ Evaluate expanded consistent usage of defined and existing capping and
tunneling (escape routes) for departures/arrivals to/from the NEC through
required advisories
• What is an escape route?
‒ Escape routes offer a means to increase departure capacity during
significant Severe Weather Avoidance Plan (SWAP) events and during
special events or holiday traffic volume situations
72
Escape Routes - Summary Findings
• Escape route usage increased 92% from 2016/2017 baseline to 2019
• Additional average flight time of ~11 minutes for each escape route
flight
• System delay savings estimated at 10 times the average additional flight
time for escape route usage. Additionally, estimated a savings of one
cancellation for every four escape routes used
• Conservative estimate of achieved benefits delivers increase from
baseline
‒ Baseline: 2016/2017 is $15.5M
‒ 2018 resulted in $8.7M additional savings over Baseline
‒ 2019 resulted in $14.6M additional savings over Baseline
73
Escape Route Usage
74
JAT Goal and Approach
• Evaluate the savings from delay and cancellations enabled by ESCAPE
routes compared to the additional flight time and fuel cost
• Agree on methodology to both determine escape routes flown and
model the expected delay if they were not able to be used
‒ Perform sensitivity analysis to account for uncertainty with weather
events
‒ Calculate change in escape routes flown from 2016/2017 baseline to
2018/2019
‒ Apply standard FAA/JAT valuation for delay and fuel by phase of flight,
and cancellations
• Present final findings to NEC and NAC SC
75
JAT Estimated Annual Benefits
Year 2016 2017 2018 2019
Escape Route Usage 3,224 4,762 6,371 7,684
Excess Flight Time Generated (min) 35,786 52,858 70,718 85,292
Est. System Ground Delay Savings (min) 313,373 394,294 475,277 603,962
Est. Cancellations Avoided 759 1,246 1,649 1,990
Year 2016 2017 2018 2019
Escape Route Usage 3,224 4,762 6,371 7,684
Excess Flight Time Generated ($M) ($1.2) ($2.0) ($3.0) ($3.9)
Est. System Ground Delay Savings* ($M) $6.1 $8.1 $10.7 $14.1
Est. Cancellations Avoided ($10k per) ($M) $7.6 $12.5 $16.5 $19.9
Est. Net Savings ($M) $12.5 $18.6 $24.2 $30.1
• Baseline: 2016/2017 average is $15.5M • 2018 resulted in $8.7M additional savings over Baseline• 2019 resulted in $14.6M additional savings over Baseline
76
Queue Model: Delay Savings
2016: 313k Minutes of Delay Avoided2017: 394k Minutes of Delay Avoided2018: 475k Minutes of Delay Avoided2019: 604k Minutes of Delay Avoided
Total: 1.79M Minutes of Delay Avoided
77
NAC Task 19-4: PBN Clarification
Ad Hoc Co-Chairs: Steve Brown, Brian Townsend, & Bill Whyte
FAA SMEs: Clark Desing, Wendy O’Connor, & Aaron Wilkins
78
Task 19-4: Performance Based Navigation (PBN) Clarification
The NAC is asked to provide aviation community consensus advice by:
• Developing consensus agreement on a PBN baseline
‒ FAA Procedures
‒ Industry Equipage;
• Developing consensus agreement on a joint definition of a PBN NAS; and
• Developing consensus agreement based on gaps in baseline analysis at Core 30 airports (minus HNL, plus TEB), on a list of specific desired outcomes.
79
Aviation Community Representatives
• The Airline Co-Chair for the PBN NextGen Integration Working Group (NIWG)
• A representative from Regional Aviation
• A representative from Business/ General Aviation
Brian Townsend, American Airlines
Bill Whyte, Regional Airline Association (RAA)
Steve Brown, National Business Aviation Association (NBAA)
• Additional support provided by A4A with member and non-
member airlines with carrier provided Air Traffic Management
and Technical Pilot expertise
• Also included participation from RAA and NBAA
80
FAA Support
• FAA Subject Matter Experts (SMEs) from the Air Traffic
Organization (ATO)
‒ Wendy O’Connor
‒ Aaron Wilkins
‒ Clark Desing
• Additional invited technical support
‒ NATCA
‒ MITRE
81
PBN Baseline for Procedures
• Existing procedures in the NAS
RNAV SIDs and STARs
RNAV GPS Approaches
RNP AR Approaches
RNP to xLS (ILS/GLS)`
Advanced RNP (A-RNP) (SIDs, STARs, Approaches)
Ground Based Augmentation System Landing System (GLS)
Approaches
RNAV Visual Flight Procedures (RVFP)
• A-RNP exists in the NAS but is in various stages of development and
maturity
• All but RNAV Visuals are part of the NAS NAV Strategy
82
PBN Baseline Equipage
• NAC Minimum Capabilities List (MCL) was used to identify the PBN
capabilities for Approach and Terminal phases
• Information from Table 1 from Operations Specifications (Ops Specs)
C052, C063 and C384 were used along with the total fleet size to calculate
equipage percentages
• Updated in June 2020, but subject to change
83
Consensus Agreement on a PBN NAS
• The Ad Hoc Team endorses the 2016 NAS NAV Strategy as the
definition of a PBN NAS
‒ Including the “Key Principles” and “Navigation Strategy
Overview”
• The introductory remarks of then-FAA Administrator Michael P.
Huerta are still relevant and are an accurate reflection of the
definition of a PBN NAS:
“A truly PBN-centric NAS, that is, a NAS where PBN is used as the basis for daily operations. It charts a course that will allow the public and private sectors to advance the NAS collaboratively and constructively for the benefit of all aviation stakeholders, including aircraft operators, the traveling public, as well as new entrants such as unmanned aircraft systems and commercial space vehicles.”
84
Consensus Agreement On Specific Desired Outcomes
• Identify gaps in baseline analysis at Core 30 airports (minus HNL, plus
TEB)
• Post tasking airport considerations
‒ Cargo Carrier airports and other vital airports outside of the Core 30
‒ DEN, LAS and Florida Metroplex excluded
• Airports were individually prioritized by the operators
‒ Desired PBN outcomes proposed for each airport
• Ranking the procedures was based on Readiness and Return scoring
metrics
85
Summary of Aviation Community Readiness and Return
NOTE: This is the list the FAA will work from to
determine what procedures are within scope and
can feasibly be developed
86
FAA Procedures Analysis and Final Outcome
• The Aviation Community has submitted 48 proposals as “Desired Outcomes” from the modified Core 30 airports and some airports not included in the tasking letter
• The FAA SMEs have conducted an initial internal analysis to determine the status of some recommendations. Further FAA analysis needs to be conducted regarding scope, feasibility, environmental considerations, and available resources to provide a final list of procedures consistent with FAA planning.
• The PBN Clarification Ad Hoc Report contains the list of recommendations to move PBN development forward in the near term
87
88
Summary of Meeting & Action Item Review
Greg Schwab, FAA
NextGen Advisory Committee (NAC) Upcoming Meetings
• Winter 2020
• Spring 2021
• Summer 2021
89
Closing Comments & Adjourn
90
Chip Childs, NAC Chairman, SkyWest Airlines