  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    1/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    1

    1 Executive Summary

    1. Executive Summary

    1.1. General summary

    1.1.1.Project Name:400 Kv Cable Work Between TAWEELAH & EMAL Phase II

    1.1.2.Client: Abu Dhabi Transmission & Dispatch Company -TRANSCO

    1.1.3.Engineer: LAHMEYER INTERNATIONAL1.1.4.Contractor: PRYSMIAN POWERLINK SRL

    1.1.5.Details of all other subcontractors : Civil works and cable laying by Al Barrak

    1.2. Contract information

    1.2.1.Contract No.:N-7137

    1.2.2.Price: 69,222,263. AED

    1.2.3.Period:12 Months

    1.2.4.LOA date:27

    June 20121.2.5.Commencement Date: 27June 2012

    1.2.6.Effective completion Date (PAC): 25 August 2013

    1.2.7.Warranty period : 24 Months

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    2/20

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    3/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    3

    1.5. Change Orders Summary

    Sr. No.Change order

    DescriptionSubmission Date

    Reply

    DateRef No.

    Approval

    StatusCost Impact

    Time

    Impact

    1

    Instruction to

    delete all UCTMS

    (DTS) equipment

    N7137/0009/Ntr/Shn TBC TBC TBC TBC None

    2

    1.6. Areas of Concern

    Sr. No. Description Ref. Letter Action

    1

    2

    1.7. PROPOSED RECOVERY MEASURES

    Recovery Schedule Drafted and to be submitted officially once all parties

    agreed .

    Excavation of Trench to start immediately following trial pit work to reduce time foreach section.

    Documentation with AEN is acceptable for work to start as long as all notes are

    agreed.

    To recover time for production of precast trough, EPC is proposed as they can

    immediately supply to the required standard and specification of Transco.

    Increase number of jointing teams from two teams to three teams.

    Overlaps some activities with other to reduce the overall required time .

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    4/20

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    5/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    5

    1.9 Payment Summary

    Contract Value (including VOs) AED69,222,263

    Advance Payment, 15% (Received) AED10,383,339.45

    PAC Retention, 2% AED

    FAC Retention, 2% AED

    A. Net Payment Received By The Contractor (Cumulative) AED10,383,339.45

    A,1 Start of Mobilization payment (if payment applicable) AED

    A,2 Engineering Deliverables (if payment applicable) AED

    A.3 Equipment and Material Payment Received to date AED

    A.4 Construction Payment Received to date AED

    B. Summary of Value of invoices submitted duringREPORTING PERIOD(pendingpayment) AED 6,015,598.18

    B,1 Engineering Deliverables (if payment applicable) Advance Payment invoice AED 6,015,598.18

    B.2 Equipment and Material Payment Received to date AED

    B.3 Construction Payment Received to date AED

    C.Summary of Value Work Performed (pending submission of invoices) AED 0

    C,1 Engineering Deliverables (if applicable) AED

    C.2 Equipment and Material Payment Received to date AED

    C.3 Construction Payment Received to date AED

    D.Summary of OVERDUE payments (invoiced) submitted during PREVIOUS MONTHS(not including "B") 0

    D,1 Engineering Deliverables (if applicable) AED

    D.2 Equipment and Material Payment Received to date AED

    D.3 Construction Payment Received to date AED

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    6/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    6

    Monthly progress Narrative

    2 Monthly Progress Narrative

    2.1 Engineering

    2.1.1 General Requirements

    Preparation, resubmission for Final approval of Civil works Drawings anddocuments .

    2.1.2 Shop Drawings

    400kV cable route for EMAL Phase II

    Topographic survey drawing

    2.1.3 Method Statements

    - Nill

    2.2 Procurement

    All 400 kV cable accessories manufactured and FAT tested, and delivered .

    36 drums of 400 kV cable manufactured, 1stBatch , 2

    ndBatch And 3

    rd Batch

    FAT tested and delivered to Prysmian Lay down area .

    F.O Cable Drums delivered at store area

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    7/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    7

    2.3 Construction

    400kv power cable LV test started and Completed .

    400kv power cable HV testing and PD measurements Started and completed forall Phases .

    400kV cable route marker installed for span 1,2,3,4,5,6 .

    400kV cable route marker for span 7,8,9,10,11 and 12 in progress.

    Final Compaction and leveling completed for span 1- 11 .

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    8/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    8

    3 Monthly Progress Curves

    3.1.1 Overall S Curve

    Description June 12 July 12 Aug 12 Sept 12 Oct 12

    Planned (Incr.)

    Actual(Incr.)

    Forecast (Incr.)

    Planned (Cum.)

    Actual(Cum.)

    Forecast (Cum.)

    3.1.2 Construction S Curve

    Description June 12 July 12 Aug 12 Sept 12 Oct 12

    Planned (Incr.)

    Actual(Incr.)

    Forecast (Incr.)

    Planned (Cum.)

    Actual(Cum.)

    Forecast (Cum.)

    3.1.3 Procurement S Curve

    Description June 12 July 12 Aug 12 Sept 12 Oct 12

    Planned (Incr.)

    Actual(Incr.)Forecast (Incr.)

    Planned (Cum.)

    Actual(Cum.)

    Forecast (Cum.)

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    9/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    9

    3.1.4 Engineering S Curve

    Description June 12 July 12 Aug 12 Sept 12 Oct 12

    Planned (Incr.)

    Actual(Incr.)

    Forecast (Incr.)

    Planned (Cum.)

    Actual(Cum.)

    Forecast (Cum.)

    3.1.5 Payment S Curve

    Description June 12 July 12 Aug 12 Sept 12 Oct 12

    Planned (Incr.)

    Actual(Incr.)

    Forecast (Incr.)

    Planned (Cum.)

    Actual(Cum.)

    Forecast (Cum.)

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    10/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    10

    4 Document SubmittalLog

    Detailed document submittal log As attached

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    11/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    11

    5 Technical Query Control Log

    None reported this month

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    12/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    12

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    13/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    13

    6 Variation Registers

    No Variation orders received to date

    Expected future variations

    VO1 Metal Price Adjustment

    VO2 Removal of UCTMS (DTS) equipment

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    14/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    14

    7 Variation Order Registers:

    1-

    2-

    3- Register for Notices of intention for variation:

    S.No. Description

    of

    intentionvariation

    Contractors Request for

    confirmation of variation

    Estimated effect on TRANSCO / Engineers

    confirmation on intentions to

    proceed

    Current

    Status

    Letter Ref. Letter

    Date

    Contract

    Price

    Schedule Letter

    Ref.

    Letter

    Date

    Response

    4- Register for requests for confirmation of variation:

    S.No. Description

    of variation

    Contractors Request for

    confirmation of variation

    Estimated effect on TRANSCO / Engineers

    Response

    Curren

    t

    Status

    Letter Ref. Letter

    Date

    Contract

    Price

    Schedule Letter

    Ref.

    Letter

    Date

    Response

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    15/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    15

    8 HSE Report

    As attached Monthly HSE Report

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    16/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    16

    9 Risk Register Submitted Via

    Risk Assessment for Topographic survey DTS 0091

    Risk Assessment for Trench Excavation, Trough Installation, Cable Laying,

    Backfilling and ReinstatementDTS 0032

    Risk Assessment for Trench Excavation, Pre cast Trough,link box Installation,

    Backfilling and Reinstatement

    DTS 0077

    Risk Assessment for FO/DTS Cable Installation DTS 0037

    Risk Assessment for Fibre Optic Cable Installation DTS 0100

    Risk Assessment for Cable Outer Sheath Repair DTS 0073

    Risk Assessment for Soil Thermal Resistivity Test DTS 0056

    Risk Assessment for 400kV Cable Laying DTS 0099

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    17/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    17

    10 Organization Chart

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    18/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    18

    11 Photos

    Pic.1 Compaction Test at span 1

    Pic. 2 Compaction Test span 4

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    19/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    19

    Pic.3 Warning Tape installation span 11

    Pic.4 Warning tape installation span 10

  • 8/14/2019 N-7137 MonthlyReport #13 August 2013)

    20/20

    CONTRACT No: N-7137

    PROJECT: 400kV Cable Work Between TAWEELAH& EMAL Phase II

    TRANSCO| [Type the company address]

    20

    Pic.5 400 kV cable HV Test

    Pic. 6 400 kV Cable HV Testing