MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

Embed Size (px)

DESCRIPTION

PROJECTS TRAC REQUEST US-35 Widening from Livingston Avenue to I-675 (MOT-35) $29.52M Construction US-35 Improvements from Shakertown Road to Xenia Bypass (GRE-35) $6M Right of Way $26M Construction TOTAL$61,520,000 MVRPC TRAC Projects

Citation preview

Page 1: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

MVRPC TRAC Project OverviewBrian O. Martin Executive Director

October 13, 2015

Page 2: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

11

22

MVRPCTRAC PRIORITIES

2. US-35 Improvements from Shakertown Road to Xenia Bypass

1. US-35 Widening from Livingston Avenue to I-675

Page 3: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

PROJECTS TRAC REQUESTUS-35 Widening from Livingston Avenue to I-675 (MOT-35)

$29.52MConstruction

US-35 Improvements from Shakertown Road to Xenia Bypass (GRE-35)

$6M Right of Way$26M

ConstructionTOTAL $61,520,000

MVRPC TRAC Projects

Page 4: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

Video

Page 5: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

Miami Valley Region: What has changed Since 2014?

• MVRPC SIB Loan Repayment Policy Adopted (April 2014)– Up to $775,000 of annual MVRPC STP (7% of annual STP)– $400,000 max per project– $15M minimum construction cost– Construction Only– Requires MVRPC Board Approval

Page 6: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

Miami Valley Region: What has changed Since 2014?

• Collaboration among local jurisdictions– Greene US 35

• Beavercreek, Beavercreek Township, Xenia, Greene County, ODOT D8

• Inclusive design process Business, Government, and Others

• $800,000 local investment for Right of Way

• Tier 2 Right of Way for Factory/Orchard; Tier 1 Construction for Valley/Trebein

• Right of Way donation from private partner

– MOT US 35

• Dayton, Riverside, Montgomery County, ODOT D7

• Shovel Ready Project

• Letters of Support – Businesses, Chamber, WPAFB

Page 7: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

Total project cost: $38.04M

TRAC request: Tier 1 fundingNew TRAC amount: $29.52M Construction

Construction: SFY 2012 – SFY 2019

US-35: Livingston Avenue to I-675

Presentation by:Ben Wiltheiss, ODOT District 7 Planner

Page 8: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

Total project cost: $125.74M

TRAC request: Tier 2 Right of Way for Factory/Orchard; Tier 1 Construction for Valley/Trebein

New TRAC amount: $6M Right of Way & $26M Construction

Begin Construction in: SFY 2018

US-35 Improvements from Shakertown Road to Xenia Bypass

Presentation by:

Keith Smith, Environmental Engineer District 8

Page 9: MVRPC TRAC Project Overview Brian O. Martin Executive Director October 13, 2015

PROJECTS TRAC REQUEST

US-35 Widening from Livingston Avenue to I-675 (MOT-35)

$29.52MConstruction

US-35 Improvements from Shakertown Road to Xenia Bypass (GRE-35)

$6M Right of Way & $26M Construction

TOTAL $61,520,000

MVRPC TRAC Projects