Muon g-2 Installation Schedule All Experimenters Meeting June
16, 2014 Aria Soha Muon g-2 I&I Manager
Slide 2
Outline Ring Installation Schedule Progress to date Vacuum
Chamber Sequencing Overall Schedule Summary Pictures 2 Aria Soha
Muon g-2
Slide 3
Short-Term Ring Installation Schedule 3 Aria Soha Muon g-2 Link
to Live Web DocumentLive Web Document
Slide 4
4 Aria Soha Muon g-2 Progress to date & near-term
TaskScheduled timeActual time Anchor angle bracket dams2 days1
week(Power Outages interferred) Base plate hole drilling2 weeks3
weeks(Power Outages interferred) Disassemble Prototype1 day2 days
Electrical Panels on South wall5 weeks epoxy threaded rod2 days
Fasten steel angle to the floor to create a dam1 day2 days Grout
Cures24 hours Grout Round 21 week2 days Grout, Round 11 week2 days
Iron stability Measurements (Capacitec) Measure Yoke-ear spacing1
day Paint Base plates1 week1 day Prep Bottom Yokes3 days Reference
Bottom Yoke A1 day 5 days Reference Bottom Yoke C & B1 day
Reference Bottom Yoke D & E1 day Reference Bottom Yoke F &
G1 day Reference Bottom Yoke H & I1 day Reference Bottom Yoke J
& K1 day Reference Bottom Yoke L1 day Set elevation and level
base plates2 days1 day Set elevation and level base plates2 days
Set Jack Stands to elevation1 day Install Bottom Yoke A2 days1 day
Align Bottom Yoke A1 day Move C, D, E Bottom Yokes from ME71
dayDelayed due to asphalting
Slide 5
Vacuum Chamber Sequencing 5 Aria Soha Muon g-2 Link to Live Web
DocumentLive Web Document
Slide 6
Installation is progressing well Cross coordination between WBS
categories is planned and well in hand. Pictures. 6 Aria Soha Muon
g-2 Summary
Slide 7
Delivery of Steel to MC-1 7 Aria Soha Muon g-2
Slide 8
Base Plate Installation 8 Aria Soha Muon g-2
Slide 9
Grouting 9 Aria Soha Muon g-2
Slide 10
Student Involvement 10 Aria Soha Muon g-2
Slide 11
First Yoke Placed! 11 Aria Soha Muon g-2
Slide 12
Current Status 12 Aria Soha Muon g-2 Aligning Bottom Yoke A
Electrical Panels being installed on South wall Angle Brackets
installation