Muon g-2 Installation Schedule All Experimenters Meeting June 16, 2014 Aria Soha Muon g-2 I&I Manager

Embed Size (px)

Citation preview

  • Slide 1
  • Muon g-2 Installation Schedule All Experimenters Meeting June 16, 2014 Aria Soha Muon g-2 I&I Manager
  • Slide 2
  • Outline Ring Installation Schedule Progress to date Vacuum Chamber Sequencing Overall Schedule Summary Pictures 2 Aria Soha Muon g-2
  • Slide 3
  • Short-Term Ring Installation Schedule 3 Aria Soha Muon g-2 Link to Live Web DocumentLive Web Document
  • Slide 4
  • 4 Aria Soha Muon g-2 Progress to date & near-term TaskScheduled timeActual time Anchor angle bracket dams2 days1 week(Power Outages interferred) Base plate hole drilling2 weeks3 weeks(Power Outages interferred) Disassemble Prototype1 day2 days Electrical Panels on South wall5 weeks epoxy threaded rod2 days Fasten steel angle to the floor to create a dam1 day2 days Grout Cures24 hours Grout Round 21 week2 days Grout, Round 11 week2 days Iron stability Measurements (Capacitec) Measure Yoke-ear spacing1 day Paint Base plates1 week1 day Prep Bottom Yokes3 days Reference Bottom Yoke A1 day 5 days Reference Bottom Yoke C & B1 day Reference Bottom Yoke D & E1 day Reference Bottom Yoke F & G1 day Reference Bottom Yoke H & I1 day Reference Bottom Yoke J & K1 day Reference Bottom Yoke L1 day Set elevation and level base plates2 days1 day Set elevation and level base plates2 days Set Jack Stands to elevation1 day Install Bottom Yoke A2 days1 day Align Bottom Yoke A1 day Move C, D, E Bottom Yokes from ME71 dayDelayed due to asphalting
  • Slide 5
  • Vacuum Chamber Sequencing 5 Aria Soha Muon g-2 Link to Live Web DocumentLive Web Document
  • Slide 6
  • Installation is progressing well Cross coordination between WBS categories is planned and well in hand. Pictures. 6 Aria Soha Muon g-2 Summary
  • Slide 7
  • Delivery of Steel to MC-1 7 Aria Soha Muon g-2
  • Slide 8
  • Base Plate Installation 8 Aria Soha Muon g-2
  • Slide 9
  • Grouting 9 Aria Soha Muon g-2
  • Slide 10
  • Student Involvement 10 Aria Soha Muon g-2
  • Slide 11
  • First Yoke Placed! 11 Aria Soha Muon g-2
  • Slide 12
  • Current Status 12 Aria Soha Muon g-2 Aligning Bottom Yoke A Electrical Panels being installed on South wall Angle Brackets installation
  • Slide 13
  • Current Status 13 Aria Soha Muon g-2