1
Municipal Solid Waste
Power Plant Project
2014. 4.
DL ENT Co., Ltd.
- 2 -
01
02 Construction Plan
03 Government’s Scope
Project Overview
04 Master Plan
- 3 -
01 Project Overview
- 4 -
Project Project • MSW (Municipal Solid Waste) Power Plant Project (BOT)
Construction
Terms
Construction
Terms• 14 months after start up • BOT (Build – Operation – Transfer) : 20 years
Target of
the Project
Target of
the Project
1.Hygienic and economical processing of waste disposal facility for the installation of public
2. Using waste heat to ensure the development of renewable energy, such as crude oil expected
substitution effect
3.On fossil fuels, the substitution effect of CDM projects to reduce greenhouse gas emissions,
such as the UN Framework Convention on Climate Change active coping
4.Load reduction in eco-friendly to the environment and the installation of local residents improve
health care plan
CapacityCapacity
• MSW Capacity: 300 ton/day (1st stage)
• Incinerator : 150 ton/day (× 2 Facilities), STG 7.0MWh (× 1 Facility)
* 2nd stage (700 ton/day) will be discussed later on
AreaArea • 10,000 ㎡
1. Project Overview
- 5 -
2. Project Structure
DL ENT Co., ltd.
1. PPA : Power Purchase Agreement
Government
ProjectFinancing
1) EPC(Engineering, Procurement & Construction)
FinancialShareholder
KothaiTechnology
EPC 1)
Turn-key
* Scope of Government
1. MSW Supplying Contract
2. Related Certificates / Public Complaints
3. MSW : 300 ton/day (more than 52% of Combustibles)
4. Free treatment for Waste Water / Ash (Incombustibles)
5. Free usage of Running water
6. MSW price : 350 THB/ton(1st year),
450 THB/ton(from 2nd year)
PEA
- 6 -
02 Construction Plan
- 7 -
Incineration
Type
Incineration
Type Stoker (with Heat Recovery Boiler)
Operating
hours
Operating
hours
Steam
Production
Steam
Production
Incineration
Capacity
Incineration
Capacity 300 ton/day (150 ton/day * 2 Facilities)
24 hr/day (Continuous)Annual
Operating hours
Annual
Operating hours 7,680 hr/year (320 days)
47.0 Steam Ton/hr Electricity
Production
Electricity
Production 7.0 MWh
Type of Waste
Quantity(kg/hr)
Ratio(%)
Com-bustibles
(%)
Water(%)
Ash(%)
MSW
(Incoming)13,750 100 41.3 49.3 9.4
Low Quality : 2,677 kcal/kg
2. Waste Characteristics and Design Crite-ria
1. EquipmentTo be fixed after
Basis Design
- 8 -
Steam turbine gen-set
Induced draft fan
Ash bunker
Bag filerBoilerIncinerator
Refuse hopper
Electric crane
Refuse bunker
Ash discharger
Acid gas treatment sys.
Reception hall
3. Equipment Model (Concep-tual)
- 9 -
Consump-tion
Quantity PressureSteam Temp.
Equipment 45 ton/hr39 –
40kg/㎠ 350℃
350
4. Heat Recovery system To be fixed after Basis Design
- 10 -
5. Layout (Main Process - Conceptual)
To be fixed after Basis Design
- 11 -
공 종
Construction Schedule
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1. Detail Engineering
2. Fabrication (M)
3. Civil Work
4. Installation (M)
5. Architecture
6. Piping
7. Electricity Incoming
8. Insulation
9. Start up – Test run
10. Inspection(Environ)
12. Commercial Run & Generation of Elec-tricity
Total duration 14 Months
6. Master Schedule (Esti-mated)
(Unit : Month)To be fixed after Basis Design
- 12 -
5. Financing Summary (Unit : 100M Kwon)
Description Cost Note
Direct Cost
1. Incinerator with Heat Recovery Boiler sys-tem
25,500
2. Turbine Generator 4,500
3. Civil Work 8,200
4. Design 800
Summary 39,000 -
Indirect Cost(Administrative)
1. Insurance for EPC 1,700
2. 사전개발비 1,750
3. Feasibility Study 500
4. Cost for Law Firm 300
5. Cost for Financing 200 6. Supervision Management for the Con-struction
150
7. Administrative Cost 800
8. Contingency 2,100
Summary 7,500
Total Summary 46,500 -
- 13 -
03 Scope of Government’s
- 14 -
Scope of
Rayong
Government
Scope of
Rayong
Government
1. MSW Supplying Contract
2. Related Certificates / Public Complaints
3. MSW : 300 ton/day (more than 52% of Combustibles)
4. Free treatment for Waste Water / Ash (Incombustibles)
5. Free usage of Running water
6. MSW price limitation : 350 THB/ton(1st year),
450 THB/ton(from 2nd year and further)
- 15 -
04 Master Plan
- 16 -
Description Main Subject Dead line Note
1st Proposal(Brief)
Project Inquiry Finished
Site Survey Finished
Project Proposal ~ `14. 4.10
MOU Agree-ment
MOU check / Agreement ~ 4.30
Project Financing Financing Agency Contract ~ 5.10
Feasibility Study Financial/Legal Consultant / Reports ~ 8.30
Certificates
Supplying of MSW ~7.30
BOI Certificates / PPA Agree-ment
~ 8.30
Project Financing Financial Shareholders ~ 9.20
Construction
Bidding for Construction Com-pany
~ 9.30
Start up of the Construction ~ 10.1
1. Master Schedule (Esti-mated)
- 17 -
- 18 -