12
Multi-Site Management System Implementation Managing from Afar

Multisite Project Management

Embed Size (px)

Citation preview

Multi-Site Management System Implementation

Managing from Afar

Develop a visit strategy

Set expectations for work completed

Define “work complete”

Detailed plans

Routine updates

Summary reports

Roll-up Summary tracker • Complete system look

Have complete sets of tools for training

Hands On Approach 1. Engagement, Planning, & Initial Start

2. Requirements Review

3. Business Process Training

4. CA/PA & HACCP Process Training

5. Operational Controls / GMP Training

6. Process Audit Training

7. Data/Results Analysis Training

8. Pre-assessment / Corrections Plan

5 Phases 1. Leadership focus

2. High level & department processes

3. System processes

4. Verification and validation

5. Structural issues

Summary Tracker • Leadership summary

• Roll-ups all projects

Item Description

% C

om

ple

te

Ow

ner

Sta

tus

Sta

rt

Co

mp

lete

Tar

get

4/21

/201

5

4/28

/201

5

5/5/

2015

5/12

/201

5

5/19

/201

5

5/26

/201

5

6/2/

2015

6/9/

2015

6/16

/201

5

6/23

/201

5

6/30

/201

5

7/7/

2015

7/14

/201

5

7/21

/201

5

7/28

/201

5

8/4/

2015

Total Projected Implementation Sat, 1/00/00 Sat, 1/00/00

1 Phase 1

Senior Leadership Training 0%

Management System Intro Training for Senior Leaders

Resource Allocation 0%

Identify Food Safey Team Leader / Management Rep

Identify Envirnomental Management System Rep

Identify OHSAS Management System Rep

Responsibility Matrix

Organization Chart

Skill Sets / Job Descriptions

Requirements Training 0%

ISO Requirements Training Management Rep

ISO Requirements Training Staff

PAS Requirements Training Management Rep

PAS Requirements Training Staff

General Workforce Communication

Gap Assessments 0%

Gap Assessment (Management System)

Gap Assessment (PAS/Operational Controls)

Process Flow 0%

Process Flow

Inventory Current Documents

Stage 1 Processes 0%

Establish Management Review (Project Review)

Management Policy Statement

Document & Record Control Processes (SOP)

Training Process (SOP)

Action Item Log Process

Verification Planning 0%

PRP Verification Plan (Work Aid) First Draft

PRP Verification Plan (Work Aid) FST Review

2 Phase 2

Risk Assessment Training 0%

HACCP Training

Risk Assessment & Business Plan Training

Perform Risk Assessments 0%

PRP Risk Assessment

HACCP Analysis

Business & Quality Assessment

Environmental Aspects & Impacts

Safety Risk Assessment

Certification Date Phase 1 Responsibility Date Due Status

Develop Plan

Senior Leadership Tra ining

Resource Al location

Requirements Tra ining

Team Names Signatures Gap Assessments

Sponsor: Process Flow

Lead: Stage 1 Processes

Member: Veri fication Planning

Member: Summary 0%

Member:

Member: Phase 2 Responsibility Date Due Status

RTM: Risk Assessment Tra ining

MSM: Perform Risk Assessments

Bus iness Planning & Management Review

Food Safety Processes

Status Item Expected Cost Environmental Processes

OHSAS Processes

Production Work

QA/Lab Work

Warehouse Work

Maintenance Work

Summary 0%

Phase 3 Responsibility Date Due Status

Management System Process Tra ining

Management System Processes

Bus iness System Processes

Maintenance System Processes

Management System Veri fication

Summary 0%

Phase 4 Responsibility Date Due Status

Analys is of Veri fication Results

Actions From Analys is

#DIV/0! Summary -$ How to use a Management System Tra ining

Preassessment

Corrections from Preassessment

Certi fication

Attendees Summary 0%

Roadblocks Next Steps Next Visit

CommentsProject Status #DIV/0!

Date Last

Reviewed

Facility Name

Current Plant Status

Plan Goal

Operational Controls & PAS Required Corrections

ISO 22000, ISO 9001, ISO 14001, & OHSAS 18001 Approach/Process Records/Evidence Notes

4 Management System

4.1 General requirements

ISO 22000 § 4.1 ISO 9001 § 4.1

ISO 14001 § 4.1 OHSAS 18001 § 4.1

The organization shall establish, document, implement and

maintain and continually improve an effective management

system, which includes quality, food safety, environmental and

safety management. The management system shall be updated

when necessary in accordance with the requirements of the

International Standards of ISO 22000, ISO/TS 22002-1, ISO

9001:2008, ISO 18001:2007, and OHSAS 14001:2004, and shall

determine how it will fulfill these requirements.

Management System

Manual

Manual

Master Document List

Records / Records List

Management Review

The organization shall define and document the scope of its

management system for quality, environmental, and safety.

Management System

Manual

Section 2 of Manual -

Scope

The organization shall define the scope of the food safety

management system. The food safety scope shall specify the

products or product categories, processes and production sites

that are addressed by the food safety portion of the management

system.

Management System

Manual

Section 2 of Manual -

Scope

ID Clause RequirementProcesses used to control

Requirement

Verification

ActivityFrequency

Evidence

Record

FST Verification

Method

1

4 Construction and layout

of buildings

4.1 General requirements

Bui ldings are des igned, constructed

and maintained in a manner

appropriate to the nature of the

process ing operations that are

carried out, the food safety hazards

associated with those operations ,

and the potentia l sources of

contamination from the plant

environs . Bui ldings are of durable

construction which presents no

During normal management

routines i tems are identi fied

and corrected

GMP

Inspection

Monthly GMP Record Food Safety

Coordinator

Review

2

4.2 Environment Cons ideration is given to potentia l

sources of contamination from the

loca l environment.

During the annual ri sk

assessment process , FST wi l l

perform a PRP Risk Assessment

to identi fy changes

PRP Risk

Assessment

Annual ly Assessment FST Approval

3

4.2 Environment Food production is not carried out in

areas where potentia l ly harmful

substances could enter the product

During the annual ri sk

assessment process , FST wi l l

perform a PRP Risk Assessment

to identi fy changes

PRP Risk

Assessment

Annual ly Assessment FST Approval

4

4.2 Environment The effectiveness of measures taken

to protect against potentia l

contaminants are periodica l ly

reviewed.

During the PRP Risk Assessment

Process , the controls are rated

and rerated as needed

PRP Risk

Assessment

Annual ly Assessment FST Approval

5

4.3 Locations of

establishments

The s i te boundaries are clearly

identi fied.

Curb, RR Tracks , Outer Wal ls , Map GMP

Inspection

Monthly GMP Record Food Safety

Coordinator

Review

6

4.3 Locations of

establishments

Access to the s i te i s control led. Locked doors , gates , e-cards ,

receptionis t

GMP

Inspection

Monthly GMP Record Food Safety

Coordinator

Review

7

4.3 Locations of

establishments

The s i te i s maintained in good order.

Vegetation is tended or removed.

Roads , yards and parking areas are

dra ined to prevent standing water and

are maintained.

Vegetation is maintained by

intera l persons

Standing water i ssues are

identi fied during normal

management routines and action

i tems are discussed and

corrected

GMP

Inspection

Monthly GMP Record Food Safety

Coordinator

Review

#ID'd

From

Date

OpenArea Item Name Category Sub-Category Item Description Owner Date Due Date Closed

12038 G Mar-12 Quality Bev QC lab Building Materials Ceiling Tiles replace soiled ceiling tiles Steve 4/20/2012 5/11/2012

12016 A Mar-12 Production Floor around can line Building Materials Floors worn down to aggregate Steve 4/15/2012 5/1/2012

12024 G Mar-12 Sugar Room Floor needs repaired Building Materials Floors Sugar Room Steve12/31/201

25/9/2012

12039 G Mar-12 Quality Micro lab Building Materials Lights replace cracked light cover Steve 4/20/2012 5/11/2012

12023 G Mar-12 Warehouse Spot Light Out Building Materials Lights No Dock door #8 Steve 4/20/2012 5/11/2012

12017 A Mar-12 Maintenance Drain cleaning. Documentation Missing no documentation for how to clean and verification Randy 4/15/2012 5/11/2012

12018 A Mar-12 Maintenance Maintenance records Documentation No Records no doc rec for release equip from Maint to prod Joe 4/15/2012 5/11/12

12033 G Mar-12 Premix Premix NW corner stand Equipment Needs Replacing replace rusty stand with stainless/aluminum Steve 4/20/2012 4/12/2012

12011 A Mar-12 KOCON Syrup on ceiling Housekeeping Ceiling Tiles KOCON room Randy 4/7/2012 3/27/2012

12031 G Mar-12 Premix Premix fan Housekeeping Fans south fan needs cleaning Steve 4/20/2012 4/12/2012

12034 G Mar-12 Packaging btl line video jet Housekeeping Not Clean clean ink from around the reflector Steve 4/20/2012

12037 G Mar-12 Packaging can line traymore Housekeeping Not Clean ink stain on floor and railing around coder Steve 4/20/2012

12022 G Mar-12 Warehouse North Dock debris Housekeeping Not Clean Doors #1, 2, 3 Steve 4/20/2012 3/27/2012

12036 G Mar-12 Filler Room Can filler/seamer Housekeeping Panels tile SW corner by elec panel needs cleaning Randy 4/20/2012 4/12/2012

12030 G Mar-12 Production Sledge Blow off panel Housekeeping Panels needs cleaned Randy 4/20/2012 3/27/2012

12019 G Mar-12 KOCON KOCON room Housekeeping Piping pipe above coke tank needs cleaning Randy 4/20/2012 4/5/12

12035 G Mar-12 Packaging case washer Housekeeping Piping white exhaust pipes need to be wiped off Steve 4/20/2012 5/11/2012

12021 G Mar-12 Warehouse Area below roll down rack Housekeeping Racks Needs to be cleaned Steve 4/20/2012 3/27/2012

12025 G Mar-12 Water Treatment RO Softener Housekeeping Tanks/Covers salt tank top is dirty Steve 4/20/2012 3/27/2012

12026 G Mar-12 Water Treatment West Water tmt covers & top Housekeeping Tanks/Covers all need cleaning Randy 4/20/2012

12027 G Mar-12 Water Treatment Ferric Sulfate container Housekeeping Tanks/Covers container and area around it need cleaning Steve 4/20/2012 5/3/2012

12028 G Mar-12 Water Treatment East Water Tmt Housekeeping Tanks/Covers Sand filters tops need cleaning Randy 4/20/2012 4/12/2012

12029 G Mar-12 Water Treatment Lime tank, east water Housekeeping Tanks/Covers top needs scraped…lime build-up Randy 4/20/2012 4/12/2012

12032 G Mar-12 Premix Premix filling area Housekeeping Walls false wall needs cleaning; handprint Steve 4/20/2012 3/27/2012

12015 A Mar-12 Premix Eye wash bottles in premix Materials Containers Not Controlled sitting on top of cabinet…need a rack/holder Joe 4/7/2012 3/27/2012

12014 A Mar-12 Can Crushing Wrongly labeled spray bottles Materials Containers Not ID'd Can crushing room Steve 4/7/2012 3/27/2012

12012 A Mar-12 Production Oil drain jug not labeled Materials Containers Not ID'd Alvey Steve 4/7/2012 3/27/2012

12013 A Mar-12 Production PF&B extension cords Materials Damaged one pulled out and two without caps Steve 4/7/2012 3/27/2012

12010 A Mar-12 Sanitation CIP room outdated bottles Materials Incorrect bottles are refilled Randy 4/7/2012 3/27/2012

12020 G Mar-12 Warehouse DrP not put away at E.O.S Storage Not Stored Prod by no. end of 12-pk rack Steve 4/20/2012 3/27/2012

12040 FSL Mar-12 Admin Bioterrorism Training Missing add to new employee training Joe 4/29/2012 4/13/2012

Jules Fijux, MBA

ASQ Certified Manager of Quality / OE

[email protected]