Mu2e WBS 2 Accelerator Progress Report
Mu2e WGM
6/15/2011
Steve Werkema
L2 Manager for the Accelerator Systems
S. Werkema 2
Mu2e Accelerator Organization2 Mu2e Accelerator
S. WerkemaV. Nagaslaev (Deputy)
FNAL
2.01 Project ManagementS. Werkema
V. Nagaslaev (Deputy)FNAL
2.02 RecyclerI. Kourbanis
FNAL
6/15/2011
2.03 Transport to Storage Rings
J. MorganB. Drendel (Deputy)
FNAL
2.04 Storage RingsJ. Morgan
B. Drendel (Deputy)FNAL
2.10 Target StationR. Coleman
FNAL
2.11 Operations Prep.B. Drendel
FNAL
2.07 RF SystemsJ. DeyFNAL
2.05 Radiation SafetyA. Leveling
FNAL
2.08 External BeamlineC. Johnstone
FNAL
2.09 ExtinctionE. Prebys
FNAL
2.06 Resonant ExtractionL. Michelotti
FNAL
All level 3 managers have been named
S. Werkema 3
Significant Issues
• Antiproton Source service building shielding
• Antiproton Source service building space
• Costs higher than expected
• Human Resources
6/15/2011
S. Werkema 4
Service Building Shielding
6/15/2011
Original Service Building
Shielding Cap• Shielding design criteria:
< 1 mRem/yr to public at 175 m (considered negligible).
• Need an overall reduction factor of >500 relative to the
existing shielding.*
Shielding Cap: additional ~160X(from MARS simulations in progress)
Require additional factor of 4 to 5 from: interlocked detectors, eberm, or long detectors (Total Loss Monitors)
*Assumes total beam loss of 2%.
Work in progress:MARS simulations to calculate shielding factors are in progress
FNAL Accelerator and ES&H personnel are studying the possible use of eberms and TLMs at Fermilab
S. Werkema 5
Service Building Space
• Service building space requirements are still being compiled
• g-2 service building space requirements not known
• Need more space in AP30 and AP50
Some of the equipment that will be required for the Accumulator injection kicker.
Not shown: Fluorinert skid, electronics racks.6/15/2011
S. Werkema 6
High Costs
• Much work on BOEs remains. Total Accelerator Systems cost is not yet known.
• Total will be much higher than Accelerator + Target estimate for the Mu2e proposal ($21.74M includes base & contingency)
– Having difficulty determining what went into this estimate
• Several big ticket items with costs greater than expected: kicker magnets, pulsed power supplies, beam absorbers, RF, extraction septum, PS heat & radiation shield
• Likely service building expansion or construction
6/15/2011
S. Werkema 7
Personnel Issues
• Received temporary engineering support from AD/ME, AD/EE, AD/Instrumentation, and Tech. Div. for BOEs
– Big effort – much accomplished– Work still in progress
• The issue of long term mechanical and electrical engineering support remains
• Radiation Safety level 3 manager (Tony Leveling) is over committed (Pbar Target station, JASMIN, Mu2e)
• Many AD people associated with Mu2e are still primarily working on Collider Run II
• Possible loss of one level 3 manager in coming months
6/15/2011
S. Werkema 8
New People
Gerry Annala (AD/TeV)• Help Carol Johnstone with external beamline• Coordinate overall accelerator mechanicals systems
development (cooling, vacuum, magnet stands, etc.)
Curtis Baffes (AD/ ME Support)• Target station integration engineer
Ron Moore (AD/TeV)• Assistant Division Head/Coordination of Mu2e and g-2
6/15/2011
S. Werkema 9
What’s Going on Now
• Big effort to finish BOEs
• Several changes must be made to the CDR
• MARS simulations for service building shielding studies
• Planning for beam studies that need to be done before the beam goes off in September.
• Trying not to think about g-2
• Run II (complete on September 30)