MSU/MCTC Law Enforcement and Criminal Justice Center
March 10, 2010
Agenda- Schedule- Quality- Financial-Literary Quotations-Monument Sign-Spandrel Panel Issue-Additional Contracts- Progress Photos
Activity Date
Start Construction May 7, 2009
Substantial Completion June 19, 2010*
Inspections/Punchlist Work June 20 – July 20, 2010
FF&E Installation June 20 – July 20, 2010
Move-in July 20 – August 9, 2010
Fall Semester Begins August 21, 2010
Master Schedule Milestone Dates
* Excludes pending request for time extension
Activity Scheduled Completion % Done/anticipated completion
Curtainwall March 12 75%/March 19
Ceramic Tile March 26 65%/March 26
Plumbing Fixtures March 23 5%/March 23
Architectural Casework March 15 5%/March 15
Ceiling Grid Installation May 11 20%/May 11
Contractor’s Schedule – Activity Comparison Dates:
UPCOMING WORK-Complete Curtain wall Installation- Mechanical and Electrical Equipment - Soffit Framing- Painting- Ceiling Grid/Light Fixtures/Diffusers- Ceramic Tile- Firing Range Equipment
QUALITY Material TestingWindow TestingRoof Inspections/TestingWaterproofing InspectionGeneral ConformanceCommissioning
Literary Quotations
Monument Sign
Option A
Option B
Spandrel Panel Thermal Barrier
Additional Contracts
• Elert & Associates- $8,250 – Commissioning of technology systems
• Midwave- $34,750 – Design of the building’s LAN
• Intereum – Furniture plan and installation coordinator- $14,100
Acoustic Separation of Private Offices
Overview
South Curtain Wall
Casework Delivered
Ceiling Grid Installation
Main Street Corridor
2nd Floor Mechanical Room
Overlooking Main Street
1st Floor Restroom