Upload
memekenya
View
218
Download
0
Embed Size (px)
Citation preview
7/29/2019 Mst Prj 201 Stab 1
1/5
SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 1 of 5
Client Originator
Location Project
Title:
SITE SPECIFIC ACTIVITY METHOD STATEMENTBULK EARTHWORK
Format Document Number Revision
A4 00
The original master of this document is retained on the Document Management & Collaboration Database.Copies produced from the master, by whatever means, are deemed uncontrolled.
7/29/2019 Mst Prj 201 Stab 1
2/5
SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 2 of 5
You must confirm that you hold the latest version, before using this document for its intended
purpose.
REVISION HISTORY
Rev Rev Date Comments Revised By Issued date
Revision History & References
Revision 00 incorporates:
Original File Location
This document is saved as: Macintosh SSD:Users:bekk71:Downloads:Method:NAIRDA-MST-PRJ-201-EAW.docx
This document will be updated where necessary by distribution of a completereplacement.
Document revisions
Short Notice Change Order
Method Statements are subject to amendment depending on how site works
progress and if a new element of site works are required.
A new risk assessment must be done for any new tasks.
Where the need for a revision to a signed-off method statement is identified, therevision may be implemented as either an amendment sheet (Short NoticeChange Order) to be included after the front sheet, or as a material revision tothe method statement.
Where the revision does not materially alter quality, time or risk to health andsafety, the Project Manager may sign off the change or authorize a competentperson to sign it off on their behalf. In the case of a material revision, thedocument must be forwarded to the reviewers for sign-off.
It is the responsibility of the Project Manager or Construction Manager to informthe Client and supervision of any revisions to the Method Statement. The PMmust ensure that any paper copy of the Method Statement held on site or byaffiliates is the most recent version, and to implement the use of the revisedversion.
7/29/2019 Mst Prj 201 Stab 1
3/5
SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 3 of 5
1. Purpose
This document describes the procedure to carry out the construction of
Subgrade in the project.
2. Scope
The following document covers the construction phases to carry out theearthworks for the subgrade in line with the provisions of the generalspecifications for roads and bridges.
3. Definitions
N/A
4. Responsibilities
4.1 Project Director
Ensure that the works are done in accordance to the contractualdocuments, namely the Project Specifications, and other relevantdocuments issued by the Engineer as long as these documentshave been the object of discussion and approval between theconcerned parties.
4.2 Production Manager
Provide the necessary resources to ensure the works are carriedout according to the contract specifications and other relevantcontractual documents.
Provide the resources to ensure the works are carried out in duetime, in compliance with the Activity Time Schedule approved bythe Engineer.
Provide the resources to ensure the works are carried out withinthe budget approved by the client.
4.3 Laboratory Manager
Provide laboratory technicians to follow-up the works. Ensure that all the equipment used in the test are calibrated and
in accordance to the specifications requirements.
Ensure the materials used in the earthworks are in compliancewith the client contract specifications.
5. Resources
7/29/2019 Mst Prj 201 Stab 1
4/5
SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 4 of 5
5.1 Human Resources
Surveyor Team Laboratory Technician in numbers appropriate to the works. Laboratory assistants in number appropriate for the works; Operators for compaction, material transportation and material
leveling equipment, in number appropriate for the works;
Laborers in number appropriate for the works.5.2 Equipments
Compaction Equipment, steel roller and sheep foot in numbersappropriate for the works
Excavators in number appropriate for the works. Bulldozer in number appropriate for the works.Trucks in number appropriate for the works. Grader in number appropriate for the woks. Water tanks.
5.3 Materials
The embankments material shall be free from topsoil, organicmatter, shale and other unacceptable material as specified in theGeneral Specifications.
Quarry Sand as per General Specification6. Methodology
6.1 The existing material within the cut section will be excavated to-550mm from the finished level and stockpiled.
6.2 Material at the excavated depth( -550mm) will be compacted toachieve 100% of British standard compaction,
6.3 Water may be added to achieve the compaction if the naturalmoisture content is not up to the OMC determined from the
laboratory control density test. However if the natural moisture
determined with a speedy moisture tester is more than the
OMC, the material will be spread with the grader and allowed to
dry to the OMC, after which it will be mixed with the grader and
compacted.
7/29/2019 Mst Prj 201 Stab 1
5/5
SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 5 of 5
6.4 When this layer is certified ok by the chief surveyor and thelaboratory manager, the 150mm to the formation level will be
constructed with 80% of lateritic material from the cut,
stabilized with 20% quarry dust and compacted to achieve
100% of British standard compaction in line with clauses 6005
(xiii) and 6102 of the general specification. This combination
will improve the quality of the local material to the suitable for
the construction of the subgrade layer.
6.5 On completion of the subgrade layer and certified ok by thechief surveyor and the laboratory manager, sub base material
will be placed immediately to protect it from hash weather
conditions.
6.6 Note: where unsuitable material is located below the formation,this material will be excavated to a depth jointly agreed and
backfilled with suitable material. According to the general
specification Unsuitable material shall include the following:-
oMaterial from swamps, marshes and bogs.
o Peat, logs, stumps, roots and other perishable orcombustible material.
o Topsoil and highly organic clay and silt.o Clay having a liquid limit exceeding 80% or plasticity index
exceeding 55.
o Highly micaceous materials.