    SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 1 of 5

    Client Originator

    Location Project

    Title:

    SITE SPECIFIC ACTIVITY METHOD STATEMENTBULK EARTHWORK

    Format Document Number Revision

    A4 00

    The original master of this document is retained on the Document Management & Collaboration Database.Copies produced from the master, by whatever means, are deemed uncontrolled.

  • 7/29/2019 Mst Prj 201 Stab 1

    2/5

    SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 2 of 5

    You must confirm that you hold the latest version, before using this document for its intended

    purpose.

    REVISION HISTORY

    Rev Rev Date Comments Revised By Issued date

    Revision History & References

    Revision 00 incorporates:

    Original File Location

    This document is saved as: Macintosh SSD:Users:bekk71:Downloads:Method:NAIRDA-MST-PRJ-201-EAW.docx

    This document will be updated where necessary by distribution of a completereplacement.

    Document revisions

    Short Notice Change Order

    Method Statements are subject to amendment depending on how site works

    progress and if a new element of site works are required.

    A new risk assessment must be done for any new tasks.

    Where the need for a revision to a signed-off method statement is identified, therevision may be implemented as either an amendment sheet (Short NoticeChange Order) to be included after the front sheet, or as a material revision tothe method statement.

    Where the revision does not materially alter quality, time or risk to health andsafety, the Project Manager may sign off the change or authorize a competentperson to sign it off on their behalf. In the case of a material revision, thedocument must be forwarded to the reviewers for sign-off.

    It is the responsibility of the Project Manager or Construction Manager to informthe Client and supervision of any revisions to the Method Statement. The PMmust ensure that any paper copy of the Method Statement held on site or byaffiliates is the most recent version, and to implement the use of the revisedversion.

  • 7/29/2019 Mst Prj 201 Stab 1

    3/5

    SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 3 of 5

    1. Purpose

    This document describes the procedure to carry out the construction of

    Subgrade in the project.

    2. Scope

    The following document covers the construction phases to carry out theearthworks for the subgrade in line with the provisions of the generalspecifications for roads and bridges.

    3. Definitions

    N/A

    4. Responsibilities

    4.1 Project Director

    Ensure that the works are done in accordance to the contractualdocuments, namely the Project Specifications, and other relevantdocuments issued by the Engineer as long as these documentshave been the object of discussion and approval between theconcerned parties.

    4.2 Production Manager

    Provide the necessary resources to ensure the works are carriedout according to the contract specifications and other relevantcontractual documents.

    Provide the resources to ensure the works are carried out in duetime, in compliance with the Activity Time Schedule approved bythe Engineer.

    Provide the resources to ensure the works are carried out withinthe budget approved by the client.

    4.3 Laboratory Manager

    Provide laboratory technicians to follow-up the works. Ensure that all the equipment used in the test are calibrated and

    in accordance to the specifications requirements.

    Ensure the materials used in the earthworks are in compliancewith the client contract specifications.

    5. Resources

  • 7/29/2019 Mst Prj 201 Stab 1

    4/5

    SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 4 of 5

    5.1 Human Resources

    Surveyor Team Laboratory Technician in numbers appropriate to the works. Laboratory assistants in number appropriate for the works; Operators for compaction, material transportation and material

    leveling equipment, in number appropriate for the works;

    Laborers in number appropriate for the works.5.2 Equipments

    Compaction Equipment, steel roller and sheep foot in numbersappropriate for the works

    Excavators in number appropriate for the works. Bulldozer in number appropriate for the works.Trucks in number appropriate for the works. Grader in number appropriate for the woks. Water tanks.

    5.3 Materials

    The embankments material shall be free from topsoil, organicmatter, shale and other unacceptable material as specified in theGeneral Specifications.

    Quarry Sand as per General Specification6. Methodology

    6.1 The existing material within the cut section will be excavated to-550mm from the finished level and stockpiled.

    6.2 Material at the excavated depth( -550mm) will be compacted toachieve 100% of British standard compaction,

    6.3 Water may be added to achieve the compaction if the naturalmoisture content is not up to the OMC determined from the

    laboratory control density test. However if the natural moisture

    determined with a speedy moisture tester is more than the

    OMC, the material will be spread with the grader and allowed to

    dry to the OMC, after which it will be mixed with the grader and

    compacted.

  • 7/29/2019 Mst Prj 201 Stab 1

    5/5

    SPECIFIC ACTIVITY Originally issued on date 27-Feb-2013METHOD STATEMENT This Revision 11, July,2013 No.00BULK EARTHWORK Page 5 of 5

    6.4 When this layer is certified ok by the chief surveyor and thelaboratory manager, the 150mm to the formation level will be

    constructed with 80% of lateritic material from the cut,

    stabilized with 20% quarry dust and compacted to achieve

    100% of British standard compaction in line with clauses 6005

    (xiii) and 6102 of the general specification. This combination

    will improve the quality of the local material to the suitable for

    the construction of the subgrade layer.

    6.5 On completion of the subgrade layer and certified ok by thechief surveyor and the laboratory manager, sub base material

    will be placed immediately to protect it from hash weather

    conditions.

    6.6 Note: where unsuitable material is located below the formation,this material will be excavated to a depth jointly agreed and

    backfilled with suitable material. According to the general

    specification Unsuitable material shall include the following:-

    oMaterial from swamps, marshes and bogs.

    o Peat, logs, stumps, roots and other perishable orcombustible material.

    o Topsoil and highly organic clay and silt.o Clay having a liquid limit exceeding 80% or plasticity index

    exceeding 55.

    o Highly micaceous materials.