Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
For Proposed Expansion
“METALLURGICAL INDUSTRIES (FERROUS & NON FERROUS)” from 28,000 TPA to 90,000 TPA
By
M/s. Rajputana Stainless Ltd.
Plot No. 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330,
Gujarat, India
February– 2021
Baseline Period – Jan’2020 to March 2020
Conducted & Prepared By
Ambiental Global Private Limited
(NABET Accreditated EIA Consultant Organization) Plot No.16, 2nd Floor, Sector-4, Vaishali,
Ghaziabad, Uttar Pradesh- 201010
DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT
ii
DISCLAIMER
The consulting services conducted by Ambiental Global Private Limited (the “Company”)
were performed using generally accepted guidelines, standards, and/or practices, which
the Company considers reliable. Although the Company performed its consulting services
pursuant to reliable and generally accepted practices in the industry, the Company does
not guarantee or provide any representations or warranties with respect to Client’s use,
interpretation or application of the findings, conclusions, and/or suggestions of the
consulting services provided by the Company. Moreover, the findings, conclusions, and
the suggestions resulting from the consulting service are based upon certain
assumptions, information, documents, and procedures provided by the Customer. AS
SUCH, IN NO EVENT AND UNDER NO CIRCUMSTANCE SHALL THE COMPANY BE
LIABLE FOR SPECIAL, INDIRECT, PUNITIVE OR CONSEQUENTIAL DAMAGES OF
ANY NATURE WHATSOEVER, INCLUDING WITHOUT LIMITATION, ANY LOST
REVENUE OR PROFITS OF THE CUSTOMER OR ITS CUSTOMERS, AGENTS AND
DISTRIBUTORS, RESULTING FROM, ARISING OUT OF OR IN CONNECTION WITH,
THE SERVICES PROVIDED BYTHE COMPANY.
The Customer agrees that the Company shall have no liability for damages, which may
result from Client’s use, interpretation or application of the consulting services provided
by the Company. Client’s logo has been used for report purpose only.
iv
Table of Contents
Chapter 1 Introduction…………………………………………………………,……………1
Chapter 2 Project Description……………………………………………………………..24
Chapter 3 Description of the Environment…………………………………….……… 62
Chapter 4 Anticipated Impacts & Mitigation Measures…………………….………. 124
Chapter 5 Analysis of Alternatives…………………………………………………..….147
Chapter 6 Environment Monitoring Program…………………………………….……151
Chapter 7 Addition Studies……………………………………………………….….…..156
Chapter 8 Project Benefits…………………………………………………….…….…...180
Chapter 9 Environment Cost Benefit Analysis…………………………………..…...184
Chapter 10 Environment Management Plan…………………………………………..187
Chapter 11 Summary & Conclusion………………………………………………….…203
Chapter 12 Disclosure of Consultants…………………………………………………208
List of Annexure
Land Possession Document Annexure 1
Adequacy of Existing EMS Annexure 2
Environment Audit Report Annexure 3
Consolidated Consent & Authorization Annexure 4
Showcause Notice issued by GPCB Annexure 5
Bills of Raw Material Annexure 6
Occupational Health Impact Report Annexure 7
Treatability Report Annexure 8
Undertaking Form Annexure 9
HSE & Corporate Environment Policy Annexure 10
CGWA Letter Annexure 11
TSDF Letter Annexure 12
ToR Letter Annexure 13
v
Structure of the Report
Executive Summary: This chapter gives the Executive Summary of the EIA report.
Chapter 1 (Introduction): This chapter describes objectives and methodology for EIA.
Chapter 2 (Project
Description):
This chapter gives a brief description of the location, approachability,
manufacturing processes, and details of raw materials, amenities, layout
and utilities of the proposed project.
Chapter 3 (Description of the
Environment):
This chapter presents details of the baseline environmental status for
microclimate, air quality, noise, traffic, water quality, soil quality, flora,
fauna and socio-economic status etc.
Chapter 4 (Anticipated
Environmental Impact and
Mitigation Measures):
This chapter discusses the possible sources of pollution and
environmental impacts due to the project during construction and
operation phases and suggests the mitigation measures.
Chapter 5 (Analysis of
Alternatives):
This chapter covers analysis of technology alternatives and site
alternatives.
Chapter 6 (Environmental
Monitoring Programme):
This chapter discusses the details about the environmental monitoring
program during construction and operation phases.
Chapter 7 (Additional
Studies):
This chapter covers information about Risk Assessment Studies for the
construction and operation phase, the safety precautions that are taken
during construction phase and Disaster Management Plan and
Emergency Preparedness Plan onsite and offsite.
Chapter 8 (Project Benefits):
This chapter presents the benefits from this project.
Chapter 9 (Environmental
Cost Benefit Analysis)
If recommended by EAC at the scoping stage, this chapter shall include
the Environmental Cost benefit Analysis of the project.
Chapter 10 (Environmental
Management Plan):
This chapter deals with the Environmental Management Plan (EMP) for
the proposed Project and indicates measures proposed to minimize the
likely impacts on the environment during construction and operation
phases and budgetary allocation for the same.
Chapter 11 (Conclusion): This chapter presents the conclusion made by the project proponent
and developer.
Chapter 12 (Disclosure of
Consultants engaged):
This chapter presents the details of the consultant.
vi
List of Abbreviations
EIA Environmental Impact Assessment
MoEF&CC Ministry of Environment Forest & Climate Change
CPCB Central Pollution Control Board
ToR Terms of Reference
SPCB State Pollution Control Board
UTPCC Union Territory Pollution Control Board
D. G Set Diesel Generator Set
TFH Thermic Fluid Heater
AERB Atomic Energy Regulatory Board
DRDO Defence Research and Development Organization
DGFASLI Directorate General, Factory Advice and Labour Institutes
EMP Environment Management Plan
EAC Environment Appraisal Committee
DGFT Directorate General of Foreign Trade
GIDC Gujarat Industrial Development Cooperation
NH National Highway
EC Environment Clearance
ETP Effluent Treatment Plant
APC Air Pollution Control
GEB Gujarat Electricity Board
KVA Kilo Volt Ampere
KL Kilo Liter
IMD Indian Meteorological Department
CO Carbon Monoxide
PM Particulate Matte
SO2 Sulphur Dioxide
NOX Oxides of Nitrogen
DO Dissolved Oxygen
BOD Biochemical Oxygen Demand
COD Chemical Oxygen Demand
pH Power Of Hydrogen
SAR Specific Absorption Rate
ISR Institute Of Seismological Research
BGL Below Ground Level
LPM Liters Per Minute
KMPH Kilo Meter Per Hour
AAQM Ambient Air Quality Monitoring
NAAQS National Ambient Air Quality Standards
TVOC Total Volatile Organic Carbon
UV Ultra Violet
AAS Atomic absorption spectroscopy
dB Decibel
GW Ground Water
NTU Nephlometric Unit
Mg/L Miligram Per Liter
SW Surface Water
vii
µS/cm Microsiemens Per Centimeter
MPN/100
ml
Most Probable Number
mg/kg Milligram Per Kilogram
LC Letter of Credit
PCU Passenger Car Unit
ETP Effluent Treatment Plant
CETP Common Effluent Treatment Plant
CSR Cooperate Social Responsibility
NOC No Objection Certificate
CC&A Consolidated Con & Authorization
NABL National Accredited
CER Cooperate Environment Responsibility
QRA Quantitative Risk Assessment
MCLS Maximum Credible Loss Scenario
DALR Dry Adiabatic Lapse Rate
ELR Environmental Lapse Rate
BLEVE Boiling Liquid Expanding Vapor Explosion
VCE Vapor Cloud Explosion
ERPG Emergency Response Planning Guidelines
AIHA American Industrial Hygiene Association
TLV Threshold Limit Value
STEL Short Term Exposure Limit
IDLH Immediately Dangerous to Life Or Health
NIOSH National Institute For Occupational Safety And Health
INCOIS Indian National Centre For Ocean Information Services
GDP Greenbelt Development Plan
GST Good Service Tax
VAT Value Added Tax
EMS Environmental Management Systems
EHS Environmental, Health And Safety
EMC Environmental Management Cell
PPE Personal Protective Equipment
TSDF Transport Storage Disposal Facility
SOP Standard Operating Procedure
Executive Summary Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
viii
EXECUTIVE SUMMARY
PROJECT DESCRIPTION
M/s. Rajputana Stainless Ltd. located at 213/1 ,213/2 ,212/1 ,212/2 ,184 ,185 ,186/1 ,183/1
,183/2 ,183/3 ,182/1, 214/1, 214/3 - Madhwas, Halol Kalol road, Taluka: Kalol, Dist. Pachmahal
– 389330, Gujarat, is proposing expansion in their manufacturing unit of integrated steel from
capacity of 28,000 MTPA to 90,000 MTPA. It is outside of industrial estate. Proposed products
are SS.MS & Alloy, SS.MS & Alloy Steel (AS) Bars & Bright bars. Unit believes in sustainable
development and is equally concern about environment preservation and pollution control and
proposes to provide adequate Environmental Management System not only to meet desired
norms prescribed by statutory authority but also for sustainable development.,Due to the
increasing demand of this product, the company proposes to manufacture the same.
LIST OF PRODUCTS WITH CAPACITIES
Sr.
no.
Name of
the
Products
CAS no. /
CI no.
Quantity (MT/Annum)
End-use of the
products Existing Proposed Total
1
SS.MS &
Alloy
Steel(AS)
Ingots and
Billets
SS-65997-19-5 20000 20000 48000 SS-Chemical
Industries,
2
SS.MS &
Alloy Steel
(AS) Bars
AS-7440-44-0 5000 31000 36000 Furniture Industries
Engg.
3 Bright Bars MS-7429-90-5 3000 3000 6000
Utensil & Exports AS-
Engg & Machinery
Industries MS-
Construction &
Engineering
Total 28000 62000 90000
Executive Summary Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
ix
RESOURCE REQUIREMENT
The resource requirements of the proposed project are as below:
Resource
Type Requirement Source
Land 4300 m2
The project is sited at 213/1 ,213/2 ,212/1 ,212/2
,184 ,185 ,186/1 ,183/1 ,183/2 ,183/3 ,182/1, 214/1,
214/3 - Mahwas, Halol Kalol road, Taluka: Kalol,
Dist. Pachmahal – 389330, Gujarat, India.
Building 2600 m2 Building includes Production Area, Material Storage
and Utilities.
Raw-
materials
List of raw material is
mentioned as Section
2.6 pg. 36 in EIA
report.
Mostly all raw materials are available in local
market so, they are already purchased from local
market & so will be continued further.
Water
Domestic- 25.0 KLD
Gardening –33.0KLD
Industrial –70 KLD
Necessary water requirement will be fulfilled from
bore well.
Power 6000 KVA MGVCL (Madhya Gujarat Vij Company Ltd.)
Fuel HSD = 200 Lit/Hr
LDO = 150 Lit/Hr Local trader.
Manpower Total (Existing +
Proposed) = 546 Employment will be local people based on skills
POLLUTION POTENTIAL AND MITIGATION MEASURES
The summarized statement for proposed pollution load is provided in the following table.
POLLUTION REMARKS/MITIGATION
Wastewater
• Domestic: 20.0 KLD
• Industrial: 38.0 KLD
•
• The domestic wastewater at 20.0 KLD disposed through STP.
• Industrial wastewater will be generated from Boiler, Cooling tower,
Process & washing.
• Effluent will be given primary, secondary and tertiary treatment and
treated waste water will be reused for gardening.
Air Emission
Flue Gas Emission
Heating furnace of rolling
mill
HSD – 200 L/Hr will be used as fuel.
Bag filters will be will be installed as Air Pollution Control Measures
DG set LDO – 150 Lit/Hr will be used as fuel.
Stack height of 18m will be provided.
Executive Summary Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
x
Process Gas Emission
Stack attached to AOD
unit
• Adequate stack height of 36m is provided. Hood + heat exchanger
followed by Bag filter will be provided as APCM.
Hazardous Waste
Used oil (cat 5.1) – 0.5
MTA Collection, Storage and sell to Authorized User
Discarded Drums /Barrels
(cat 33.1)– 2 MTA
• Collection, storage, reuse and disposal at decontamination facility
or by sent to suppliers
ETP Sludge (cat 35.3) –
10 MTA • Collection, Storage, Transportation and Disposal at TSDF site
Fuel gas cleaning residue
(Cat 11.4) - 22 MTA • Collection, Storage, Transportation and Disposal at TSDF site
Acid residue from pickling
(Cat 12.1) – 0.175 MTA Collection, Storage, Transportation and Disposal at TSDF site
Noise
Inside the plant: <75
dB(A)
• Noise is generated due to the operation of D.G. set in the existing
project. However, D.G. set is kept as standby and no other source
of noise and vibration is generated from the manufacturing activity
except plant machineries.
Latest technology based low noise D.G. set with acoustic
enclosures is installed.
Machineries will be provided with anti vibration pads.
• Regular maintenance will be carried out.
BASELINE ENVIRONMENTAL STATUS
ENVIRONMENTAL
PARAMETER DETAILS
Physiography
The district has high variation in topography which represents the
diverse geological condition. The western part of the district constitute
Pediplain, composed of weathered, unconsolidated medium to coarse
grained material having gentle to moderate slope. There are scattered
alluvial deposits such as flood plain, valley fills etc formed along major
river courses composed of clay, silt, sand, gravel and kankar deposits
with gentle slope. There are small scattered sedimentary and volcanic
dissected hills. Pavagadh hills, south of the district near Halol, rises
abruptly to a height of 829.36m amsl and is with high relief and steep
slopes.
Executive Summary Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
xi
The area occupies by the quartzite has an undulating topography
where as phyllite and mica schist occupy broad intermontane valley.
The southern border of the district is marked by a hill range with
roughly east – west and forms a surface water divide particularly
between Narmada and Mahi basin.
Meteorology
Temperature: ranging from 17°C in winter to 42°C in summer.
Rainfall: annual rainfall is around 1431 mm
Winds are generally high to moderate in summer and the monsoon
season.
Ambient Air
Quality
Ambient air quality has been monitored at 8 locations in 10 km radial
periphery for PM10, PM2.5, SO2, NO2 & VOC
Range of values recorded in the study area during January 2020 to
March 2020
PM10 = 49.5 - 87.2 μg/m3
PM2.5 = 24.1- 37.7 μg/m3
SO2 = 4.2 – 9.8 μg/m3
NOx = 9.5 – 17.4 μg/m3
Noise Level
Range of recorded value during study period
Day time: Leq range – 48.6 – 69.4 dB(A)
Night time: Leq range – 37.3 – 65.4 dB(A)
Water
Resources &
Quality
8 groundwater samples have been drawn from 8 different villages
within the study area and 8 surface water samples have been drawn
from 8 different locations within the study area.
Ground water qualities and Surface water qualities in terms of various
essential and desirable characteristics are found within the limits
specified by IS 10500:1992.
Land use/ Land
Cover pattern.
The satellite imagery indicates major portion of the land-use in the 5
km radial periphery covered by Agricultural land 72.44%, followed by
Open scrub land 8.64%, followed by The industrial area
7.73%,followed by urban build up and settlement 5.2% and waterbody
3.11%.
Ecological
Layout
No significant wild life habitat is reported. There is no National Park in
the study area.
No endangered species of flora & fauna are observed or recorded in
the study area.
CONCLUSION
This proposed plant is for manufacturing of synthetic resin adhesives within plant premises.
There wastewater generated from manufacturing activities will be 42 KLD. The wastewater will
Executive Summary Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
xii
be generated from operation of boiler and cooling tower with low pollution potential stream. The
utility will be operated with proper Air Pollution Control Measure. There will be process gas
emission from AOD unit which will be provided with bag filters. The Hazardous waste will be
stored separately and disposed in proper manner. From the overall study and evaluation of
impacts, it can be concluded that the overall negative impact from various activities on different
environmental parameters is negligible with proper EMP in place. Even the negative impacts
can be converted into positive beneficial impact with proper and timely implementation of EMP.
Hence project can be considered environmentally safe & fit.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
1
TERMS OF REFERENCE (TOR) COMPLIANCE
Point wise compliance of the TOR points issued by MOEF, Gujarat vide Letter No. SEIAA/GUJ/TOR/3(a)/1803/2019 for setting up of expansion in manufacturing plant of
‘Metallurgical Industries’ at Survey No.-213/ 1,213/ 2,212/ 1,212/ 2,184, 185, 186/ 1,183/
1,183/2, 183/3, 182/1, 214/1, 214/3 at- Mahwas, Halol-Kalol Road, Taluka: Kalol, District:
Panchmahal.
A tabular chart with index for point wise compliance is as given below:
Sr.
No
ToR Points Brief description of
compliance
Reference in EIA
report
1. A tabular chart with index for
point-wise compliance of
below mentioned ToRs.
Complied -
2. Executive Summary of the
project- giving a prima facie
idea of the objectives of the
proposal, use of resources,
justification, etc. In addition, it
should provide a compilation
of EIA report, including EMP
and the post-project
monitoring plan I brief.
Executive summary has been
incorporated in the initial pages
of the EIA report.
Initial pages of EIA
report
3. Justification for selecting the
proposed product and unit
size.
Steel being one of the niche
commodities and most useful
and versatile material, steel is
considered to be the backbone
of human civilization. The
project site is in proximity of
Halol District of Gujarat State
and the fact is that the
proposed project is to be done
within the project area. Project
proponent is very well familiar
with the surrounding
environment therefore, it
becomes easy for the unit to
set up, operate & maintain the
project on above said location.
Refer Chapter 2,
section 2.2 ,Page
no. 13
4. Land requirement for the Total available land area of Refer Chapter 2,
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
2
project including its break up
for various purposes, its
availability and optimization.
premises is 43000 m2, out of
which 14200 m2 (33.02%) area
will be developed for greenbelt.
section 2.9.1, Page
no. 31
5. Land possession documents.
Copy of NA order showing
permission to use the project
land for industrial purpose.
- Attached as
annexure 1
6. Furnish status of all the
applicable rules, acts,
regulation, clearances in a
tabular form.
All applicable regulatory
framework are presented in
tabular form.
Chapter 1, section
1.5, Page no. 9
7. In case of expansion of the
project
Need for the proposed
expansion should be justified
in detail.
Steel has been one of the
oldest industrial sectors in
India. It has also been the first
to get liberalized and controls
lifted partially in 1991. There
have been massive capacity
additions by all steel majors
and several new groups made
foray into primary and
secondary steel market in the
first phase of liberalization in
early 90s. The major costs in
steel making are the costs of
Iron Ore, Metallurgical Coke,
Limestone, Coal and Power.
While the country is rich in iron
ore and limestone, its quality of
coal is poor and power costs
are high. The industry enjoys
inherent advantages in terms of
availability of raw material and
cheap labour.
Refer Chapter 2,
section 2.2
Page no. 13
Adequacy of existing EMS
(Environment Management
System)
Adequacy of existing EMS has
been attached as Annexure 2
Annexure 2
Explore the possibility to
achieve Zero Liquid
Discharge (ZLD) for existing
as well as proposed activity.
The Industrial effluent
generated from unit will be 38
KL/day. Hence, the suitability of
quality and quantity of process
effluent re-using into gardening.
The unit is proposing to
Refer Chapter 2,
section 2.9.8.2,
Page no. 36
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
3
maintain the adequate storage
capacity to handle for five days
generation of effluent from Iron
& Steel Billets manufacturing.
Hence it will be a ZLD plant.
Records of any legal breach
of Environment laws. i.e.
details of show-cause notices
, closure notices etc. served
by the GPCB to the existing
unit in last five years and
actions taken then after for
prevention of pollution.
Details of Show cause notices
received earlier and there
compliance status has been
incorporated.
Refer Chapter 2,
Section 2.13, Page
no. 43
Copies of Environment
Clearances obtained for the
existing plant, its point wise
compliance report.
As the plant was established in
the year 1991 i.e., before the
issuance of EIA Notification, EC
is not applicable for the existing
plant.
-
Environmental audit reports
for last 3 years and
compliance of its
recommendations /
Suggestions. (Include latest
audit report and its
compliance)
Environment audit reports has
been added as Annexure
Copy of Consent to Operate
(CC&A) obtained along with
point wise compliance status
of all the conditions stipulated
therein.
Copy of Consent to Operate
(CC&A) obtained along with
point wise compliance status of
all the conditions stipulated
therein attached as Annexure
In case of earlier EC
obtained: Certified
Compliance Report (CCR)
from the concern authority as
per the MoEF&CC’s Circular
no. J-11011/618/2010-IA (II)
(I) dated 30/05/2012 and
circular no. J-11013/6/2010-
IA-II (Part) vide dated
07/09/2017.
As the plant was established in
the year 1991 i.e, before the
issuance of EIA Notification, EC
is not applicable for the existing
plant.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
4
Copies of XGN generated
Inspection reports with
analysis reports of the
water/Air/Hazardous samples
collected by GPCB (Last 2
year). Copies of instructions
issued by GPCB in last 2 year
and point wise compliance
thereof.
Copies of XGN generated
Inspection reports with analysis
reports attached as Annexure.
All the SCN issued by GPCB
and its compliance s has been
attached as Annexure 6.
8. Exact details about
infrastructural facilities, plant
machineries etc. required for
the proposed project.
Since expansion will be carried
out in the existing plant
premises, no new land is
required. Details of
infrastructural facilities, plant
layout, plant machineries and
other relevant details
Incorporated
Refer Chapter 2,
section 2.9.6, Page
no. 36
9. Demarcation of proposed
project activities in layout
plan.
Detailed Plant layout
incorporated
Refer Chapter 2,
section 2.3, Page
no.16
10. Present land use pattern
within 10 km radius from the
project boundary based on
satellite imagery.
Land use pattern of study area
(10 KM) incorporated.
Refer Chapter 2,
section 3.3.4, Page
no.55
11. Provision of separate entry &
exit and undertaking for the
same. Provision of adequate
margin all-round the periphery
for easy unobstructed
movement of fire tender
without reversing.
Separate entry and exit
provided which is indicated in
the plant layout.
Refer Chapter 2,
section 2.3, Page
no.16
12. Technical details of Induction
Furnaces including its cooling
and interlocking systems
along with drawing of the
induction furnace. Details of
Air Pollution Control
Measures proposed for
Induction Furnace along with
its adequacy. Details of
specific measures to ensure
that emission from the
Technical details with
advantages of Induction
furnace has been provided.
Refer Chapter 2,
section 2.7.6 ,
Page no. 28
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
5
Induction Furnace will not
escape from the furnace.
Details of specific measures
to ensure that emission from
the Induction Furnace will not
escape from the furnace in
form of fugitive emission
bypassing the air pollution
control system.
13. Complete process flow
diagram describing each unit,
its processes and operations
along with material and
energy inputs & outputs
(material and energy
balance). (1) Details of Iron
and steel making plant
describing details on design
and manufacturing process
for all the units. (2) Details on
blast furnace/open hearth
furnace/basic oxygen
furnace/ladle refining , casting
and rolling plants etc.
Complete manufacturing
process with flow diagram and
material balance for products
has been incorporated.
Refer Chapter 2,
section 2.7.1 ,
Page no. 22
14. Characteristics of raw
material (scrap) to be
purchased as a raw material
in terms of presence of
foreign material like plastic,
rubber, dirt, oily residues,
paint etc. Details of scrap
cleaning/sorting process, if
any to be carried out, for
removal of foreign materials.
All raw materials like Iron ore,
MS scraps will be received and
stored in respected closed
storage shed. Scrap from ship is
low carbon and good quality. All
raw scraps are separated by
magnetic separator to remove
foreign particle. Separated scrap
is manually examined for
removal of painted, oily and dirty
residual scrap. Such scrap is
sorted out. After sorting scrap
will be sent for cleaning section
where scrap will be cleaned
manually by wire brush and
compress air. Separated scrap
is then crushed to make
homogeneous block. These
Refer Chapter 2,
section 2.7.5 ,
Page no. 28
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
6
block of metal finally feed to
induction furnace for melting.
Maximum one month raw
material inventory will be
maintained in the plant for
continuous operation.
15. Details of proposed source-
specific pollution control
schemes and equipment to
meet the national standards.
In this proposed project,
process gas and flue gas
emission will be the main
source of air pollution. There
will be chances of fugitive
emission due to raw material
handling and transportation and
manufacturing activity.
Refer Chapter 2,
section 2.9.9, Page
no. 39
16. Details on requirement of raw
materials, its source and
storage at the plant. Also, an
agreement for the supply of
the iron ore for the proposed
plant.
Details of raw material and its
quantity has been incorporated
in the report. Bills of raw
material has been attached as
Annexure.
Refer Chapter 2,
section 2.8, Page
no. 33
17. Assessment of source of the
water supply with adequacy of
the same to meet with the
requirements for the proposed
project. Permission from
concern authority.
Total water requirement for
fresh water after expansion is
128 KLD out of which 95 KLD
will be fresh water and 33 KLD
will be reused for gardening
after treatment in ETP. Water
requirement will be fulfilled by
Borewell for which permission
has been obtained vide NOC
no.
CGWA/NOC/IND/ORIG/2020/9
317 dated 26/11/2020.
Refer Chapter 2,
section 2.9.8.1,
Page no. 35
18. Submit CGWA permission for
ground water source from
competent authority.
Permission obtained for 95 KLD
from CGWA vide NOC no.
CGWA/NOC/IND/ORIG/2020/9
317 dated 26/11/2020 attached
as Annexure 12.
-
19. Submit adequate proposal for
APCM with pickling section
and its stack and scrubber
bleed liquor disposal.
Scrubber will be provided as
APCM for picking section. Acid
residue from pickling section
will be disposed as Hazardous
Refer Chapter 2,
section 2.9.9, Page
no. 39
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
7
waste
20. Detailed water balance
(including reuse-recycle,
evaporation if any)
Total 24 KLD domestic will be
generated which will be
disposed in soak pit & septic
tank.
Total 38 KLD will be generated
from industrial wastewater.
Detailed water balance has
been incorporated.
Refer Chapter 2,
section 2.9.8.1,
Page no. 35
21. Specific measures proposed
to conserve water and plans
for the future in this regard.
The effluent generated from
different processes will be
given Primary, Secondary and
Tertiary treatment.
The final neutralized treated
effluent will be then utilized for
gardening. 11584.02 KL/Year
rain water will be used to
recharge the ground water
aquifers through rain water
harvesting.
Refer Chapter 2,
section 2.9.8.1,
Page no. 35
Refer Chapter 10,
section 10.7.1,
Page no. 172
22. Detailed cleaner production
measures like energy
efficiency in the furnaces to
reduce emissions if possible
in the proposed project &
commitment of the
management on futuristic
development/implementation
for the same.
Technical details of induction
furnace and its benefits for
cleaner production have been
incorporated.
Refer Chapter 2,
section 2.7.6, Page
no. 30
Refer Chapter 10,
section 10.10,
Page no. 176
23. Explore the possibility of
reuse/recycle and other
cleaner production options for
reduction of wastes.
Adequate ETP of capacity 38
KLD has been provided with
primary, secondary and tertiary
treatment has been installed.
Detailed water balance has
been installed. Hazardous
waste generation and
management will be done
according to Hazardous and
other waste (Management and
Transboundary) rules, 2016.
Refer Chapter 10,
section 10.10,
Page no. 176
24. Generation, characteristics
and mode of the disposal of
The effluent generated from
different processes will be
Refer Chapter 2,
section 2.9.8.2,
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
8
wastewater in existing and
proposed scenarios. Details
of the wastewater treatment
facilities, if any proposed,
including its capacity, size of
each unit, retention time and
other technical parameters
along with adequacy and
efficacy report. Action plan for
Zero Liquid Discharge
concept.
given Primary, Secondary and
Tertiary treatment.
The final neutralized treated
effluent will be then utilized for
Gardening.
Detailed ETP diagram, details
of each unit and its volume
incorporated. The effluent
quality of process effluent from
Utilities incorporated.
Page no. 36
25. One season Site-Specific
micro-meteorological data
using temperature, relative
humidity, hourly wind speed
and direction and rainfall
should be incorporated.
Meteorological data within the
study area, during air quality
survey period has been
incorporated.
Refer Chapter 3,
section 3.5, Page
no. 65
26. Anticipated environmental
impacts due to the proposed
project/ production may be
evaluated for significance and
based on corresponding likely
impacts VECs (Valued
Environmental Components)
may be identified. Baseline
studies may be conducted
within the study area of 10 km
for all concerned/identified
VECs and likely impacts will
have to be assessed for their
magnitude & order to identify
mitigation measures.
Details of impacts and its
mitigation with matrix has been
incorporated.
AERMOD View – Lake
Environmental Software, which
is a Gaussian-Plume
atmospheric dispersion
algorithm for estimating
concentration of pollutant, has
been used to predict the
Ground Level Concentrations
(GLC’s) of PM10, SO2 and
NOx due to plant activity. The
GLC’s were predicted on 24
hourly average basis keeping in
view the prescribed national
ambient air quality standards
(NAAQS). Other likely impacts
on water, soil, ecology,
occupational health, etc has
also been discussed
thoroughly.
Refer Chapter 4,
section 4.8.1, Page
no. 124
27. One complete season base
line ambient air quality data
AAQM was carried out and
AAQM locations were
Refer Chapter 3,
section 3.6.3, Page
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
9
(except monsoon) to be given
along with the dates of
monitoring. The parameters to
be covered shall be in
accordance with the revised
National Ambient Air Quality
Standards as well as project
specific parameters.
Locations of the monitoring
stations should be so decided
so as to take into
consideration the pre-
dominant downwind direction,
population zone and sensitive
receptors. There should be at
least one monitoring station in
the upwind direction. There
should be at least one
monitoring station in the pre-
dominant downwind direction
at a location where maximum
ground level concentration is
likely to occur.
monitored on 24 hourly
average bases twice in a week
as per guidelines of CPCB and
NAAQS. The conventional and
project specific parameters
such as particulate matter
PM10 (size less than 10 µm),
particulate matter PM2.5 (size
less than 2.5µm), Sulphur
Dioxide (SO2) &Oxides of
Nitrogen (NOx) were monitored
for 10 locations. Locations
were Project site, Jetpur,
Kadanch, Muvala, Khakhariya,
Navaria, Chhabapur and
Ratanpura.
no. 69
28. Modeling indicating the likely
impact on ambient air quality
due to proposed activities.
The details of model used and
input parameter used for
modeling should be provided.
The air quality contours may
be shown on location map
clearly indicating the location
of sensitive receptors, if any,
and the habitation. The wind
rose showing pre-dominant
wind direction should also be
indicated on the map. Impact
due to vehicular movement
superimposed on Google
map/ geographical area map.
Isopleths of PM10, SO2 and
NOx has been incorporated
predicting the worst case
scenario by considering the
Maximum baseline result +
Maximum GLC value in the
study area.
Refer Chapter 4,
section 4.8.1, Page
no. 124
29. Specific details of (i) Details of
the furnaces & utilities
Plant machineries and utilities
have been incorporated.
Refer Chapter 2,
section 2.9.6, Page
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
10
required. (ii) Type and
quantity of fuel to be used in
each furnace and utility. (iii)
Gaseous emission from each
furnace and utility (iv) Air
pollution Control Measures
along with its adequacy to
achieve the GPCB Norms. (v)
Flue gas emission rate from
each utility (vi) List the
sources of fugitive emission
from the unit along with its
quantification and proposed
measures to control it.
Fuel used of DG set is LDO
(150L/Hr) and HSD for furnace
(200 L/Hr)
Type of emissions or air
pollutants from stacks are PM,
SOx, NOx.
Bag filters and adequate stack
height has been provided to
each stack.
Detailed information on fugitive
emissions has been
incorporated.
no. 36
Refer Chapter 2,
section 2.9.4, Page
no. 35
Refer Chapter 2,
section 2.9.9, Page
no. 41
30. Explore the possibility for
fume extraction system along
with primary and secondary
APCM for induction furnaces.
Fume extraction system has
been installed as hood which is
used over induction furnace
along with other APCM’s.
-
31. Details regarding D.G. Sets
including its capacities,
location, fuel consumption &
storage and acoustic
measures to abate noise
pollution.
DG set of capacity 1000 KVA is
proposed. LDO (150 L/Hr) will
be used as fuel. Specified
space has been provided for
Emergency DG set. Acoustic
enclosure will be provided to
minimize noise and adequate
stack height as APCM.
-
32. Base line status of the noise
environment, impact of noise
on present environment due
to the project and proposed
measures for noise reduction
including engineering
controls.
The ambient noise standards
are presented in Equivalent
noise levels (Leq.) have been
measured twice a week during
study period.The
measurements were carried out
at each monitoring location
during day time and night time
at total 10 location. Adequate
measure will taken to mitigate
noise pollution during
construction and operation
phase.
Refer Chapter 3,
section 3.7
Refer Chapter 4,
section 4.6
33. Details of generation and
management of the
hazardous wastes/Solid
Hazardous waste generation
and management will be done
according to Hazardous and
Refer Chapter 2,
section 2.9.13,
Page no. 43
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
11
wastes to be generated from
the project stating detail of
storage area for each type of
wastes, its handling and its
disposal. Details of slag
generation, its quality and
method of disposal/ reuse in
various applications, How
spillages/leakages of used oil
shall be managed.
other waste (Management and
Transboundary) rules, 2016.
The spillages from Diesel
storage will be prevented by
dyke wall. The spillage and
leakages from pumps, pipe
assembly and storage tank will
be transfer back to storage tank
or day tank. Solid waste
generation such as slag / iron
residue while using iron /
steel scrap will be @ 500/-
MT/year. it will be re-melt (as
possible) final residue be given
for filling up in low lying area,
construction or roads etc/ sale
to actual end users. The drums
will be collected by workers and
will be stored in storage yard in
stacking.
34. A detailed EMP including the
protection and mitigation
measures for the impacts on
human health and
environment as well as
detailed monitoring plan. The
EMP should also include the
concept of waste-
minimization, recycle/ reuse/
recover techniques, energy
conservation, and natural
resources conservation. Total
capital cost and recurring
cost/annum earmarked for
environment pollution control
measures. Environmental
management cell proposed
for implementation and
monitoring of EMP.
A well designed EMP plan has
been proposed including waste
minimization recycle/ reuse/
recover techniques and energy
conservation. Rain water
harvesting plan has also been
proposed. Total EMP Capital
cost is Rs. 116 Lakhs and
recurring is Rs. 56 Lakhs.
Proper Environmental
management cell proposed for
implementation and monitoring
of EMP and to obey well laid
EHS policy.
Chapter 10, section
10.5.1, 10.7.1,
10.11 & 10.5
35. Environment Management
Cell equipped with laboratory
Environment Management Cell
equipped with laboratory and
Chapter 6, section
6.4, Page no. 139
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
12
and qualified environment
engineer shall be established.
qualified environment engineer
has been established.
36. Occupational health impacts
on the workers and mitigation
measures proposed to avoid
the human health hazards
along with the personal
protective equipment to be
provided to the workers.
Detailed work area monitoring
plan. Plan for periodic medical
examinations of the workers
exposed.
Currently, Industry has adopted
all precautionary methods to
reduce the risk of exposure of
hazards to employees and
same will be continued after
proposed. Detailed work area
monitoring plan has been
incorporated. Regular health
checkup of works will be done
and reports of same has been
attached as Annexure 8.
Chapter 10, section
10.8
Chapter 7, section
7.1.5.1 & 7.1.5.2,
Page no. 150-156
37. Detailed work area monitoring
plan. Details of the activity
wise hazards, likely heat
stress to the workers,
radiation heat level in and
around the furnaces,
measures proposed for
reduction of heat stress
around furnaces and for safe
handling of the molten metal
considering the provision of
the Gujarat Factories Rules.
Details of automated systems
to be provided to avoid
manual handling/conveyance
of materials.
Working with molten metal
always has been, and always
will be, a dangerous
occupation. Hence, Induction
foundry safety fundamentals
has been incorporated.
Chapter 2, section
2.9.12, Page no. 42
38. Detailed risk assessment
report including identification
of the most hazardous
activity, its sub activity
predictions of the worst-case
scenarios and maximum
credible accident scenario
along with damage distances
and preparedness plan to
combat such situation and
risk mitigation measures.
Detailed HAZOP study was
carried out and observed that
major on-site emergency
situation may occur from the
organic coal chemicals storage
and handling, fuel gas handling,
molten metal and slag handling,
acids and alkali storage and
handling and electrical short-
circuit. The off-site
environmental disaster may
arise if large-scale fire or
explosion occurs, the effect of
Chapter 7, section
7.1.4, Page no. 143
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
13
which extends beyond the plant
boundary. The off-site
environmental disaster may
take place due to significant
environmental degradation for a
sustained period.
39. Details of firefighting system
including provision for flame
detectors, temperature
actuated heat detectors with
alarms, automatic sprinkler
system, location of fire water
tanks & capacity, separate
power system for firefighting,
details of qualified and trained
fire personnel & their job
specifications, nearest fire
station & time required to
reach the proposed site.
Submit line diagram of the fire
hydrant network.
Details of fire hydrant line,
sprinklers, and separate
underground tank of capacity
200 KLD will be provided.
Jockey pump of capacity 150
LPM will be provided and
separate pump which will be
diesel operated shall be
provided for stand by purpose.
Trained fire personnel will be
hired as fire & safety officer.
Fire hydrant line has been
marked in the detailed layout of
the plant.
40. Provision of qualified
industrial hygienist, safety
officer, factory medical officer
employed for hazardous
processes and monitoring of
the occupational injury to
workers as well as impact on
the workers.
Trained fire and safety officer
shall be hired with minimum 4
years of experience. OHC has
been developed in the plant
premises and qualified doctor
will be hired.
-
41. Impact of the transportation of
raw materials and finished
product on the transport
system should be assessed
and provided.
Total Truck load estimates will
be @ 22 nos. per day.
Periodical work zone
monitoring will be carried out
once in six months for 8 hrs
and 15 minutes for parameters
PM10, SO2 and other
parameters as per the
Factories Act.
Refer Chapter 2,
section 2.9.12,
Page no. 43
42. Details of possibility of
occupational health hazards
from the manufacturing
Several health related issues
can be occurred with the
workers of chemical industries
Chapter 10, section
10.8, Page no. 173
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
14
activities and proposed
measures to prevent it.
due to long term exposure in
dusting, noisy area, handling of
some hazardous chemicals,
gaseous emissions etc.
In the proposed unit, drinking
water and sanitation facilities
are provided to workers. All the
necessary personal protective
equipment’s are provided for
the respective works. The unit
has provided such
arrangements to minimize
manual handling of chemicals
and hazardous wastes. Regular
health check-ups are carried
out of all the workers and
record is maintained for the
same. Medical, fire and safety
trainings are given time-to-time.
Moreover, unit has provided
proper environmental
management system and
operates the same efficiently.
Thus, there will not be any
possibility of adverse impact on
workers’ health & the same
shall be continued further with
the upcoming proposed project.
Thus, no adverse impact is
expected on sanitation and
community health.
43. Ambient temperature in the
work zone and distance of the
workers from the furnaces.
Details of likely heat stress to
the workers involved in the
manufacturing process.
Radiation heat level in &
around the furnace,
monitoring and mitigation
measures for the same
Detailed HAZOP study has
been carried out for Identifying
the potential hazardous
areas so that adequate
design safety measures can
be adopted to reduce the
likelihood of accidental
events & Identifying the
stakeholders and evaluating
Chapter 7, section
7.1, Page no. 141
onwards
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
15
including barricading, if any to
be provided.
their risk along with
proposing adequate control
techniques.
44. Details of personal protective
equipments to be provided to
the workers. Plan for periodic
medical examination of the
workers.
Details of PPE to be used
during construction & operation
phase has been incorporated.
Annual medical checkup is
done of workers, reports of
which has been attached as
Annexure 8
Chapter 7, section
7.1.6, Page no. 153
45. Details of first-
aid/occupational health center
and arrangement of
ambulance van provided for
injured workers.
1 Ambulance van has been
provided for emergency
purpose and OHC center will
be developed as displayed in
the plant layout with basic
facilities.
46. Detailed work zone
environment plan. Details of
equipment/ instrument to
measure record and analyze
workplace exposure including
air quality, noise, vibration,
heat stress, ventilation,
illumination etc.
Periodical work zone
monitoring will be carried out
once in six months for 8 hrs
and 15 minutes for parameters
PM10, SO2 and other
parameters as per the
Factories Act. Monitoring for
noise, vibration, heat stress,
ventilation, illumination etc will
be done once in a year at
suitable locations.
Refer Chapter 2,
section 2.9.12,
Page no. 43
47. Provision of qualified
industrial hygienist, safety
officer, factory medical officer
employed for hazardous
operations and monitoring of
the occupational injury to
workers as well as impact on
the workers.
Trained fire and safety officer
shall be hired with minimum 4
years of experience. OHC has
been developed in the plant
premises and qualified doctor
will be hired.
-
48. A tabular chart for the issues
raised and addressed during
public hearing/consultation
and commitment of the
project proponent on the
same should be provided. An
action plan to address the
Noted & will be complied in the
Final EIA report
-
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
16
issues raised during public
hearing and the necessary
allocation of funds for the
same should be provided.
49. Ensure participation of people
during Public Hearing with
equality in gender so as to
encourage woman
participation in Public Hearing
& at the same time their
issues shall also be given
weightage. PP shall made
adequate efforts in this regard
and shall submit the relevant
documents.
Noted & will be complied in the
Final EIA report
-
50. Submit detailed treatability
report for ETP with stage wise
quality of pollutants and
treated effluent quantity which
is to be recycled and which is
to be used for gardening
purpose.
Treatability report has been
attached as Annexure 9
Annexure 9
51. Details of five year greenbelt
development program
including annual budget,
types & number of trees to be
planted, area under green belt
development (with map),
budgetary outlay; along with
commitment of the
management to carry out the
tree plantation activities
outside the premises at
appropriate places in
surrounding area.
Five year green development
plan has been included as an
integral part of EMP. Total of
14200 sqm area is to be
developed as green belt.
Refer Chapter 10,
section 10.6, Page
no. 170
52. Undertaking from the
management regarding
maximum employment to the
local people.
Undertaking regarding same
has been obtained and
attached as Annexure 10.
Annexure 10.
53. Submit checklist in the form of
Do’s & Don’ts of preventive
maintenance, strengthening
HSE policy and corporate
environment policy of the
Industry has been attached as
Annexure 15.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
17
of HSE, mfg. utility staff for
safety related measures.
Annexure 15.
54. Proposal for socio economic
upliftment activities along with
time bound action plan and
cost should be included.
Industry will provide 1 % of the
proposed expansion project
cost (i.e. 3.5 Lakh) towards the
Corporate Environment
Responsibility. Socio-economic
development activities will be
planned based on the as well
as general necessity in villages
Refer Chapter 8,
section 8.5, Page
no. 160
55. Details of any fatal and non-
fatal accidents and dangerous
occurrences under the
Gujarat Factories Rules 1963
(GFR) for factories for the last
three years.
An incident was reported on
16/11/2019 which resulted in
explosion of metal. Details of
same has been provided in EIA
report.
Refer Chapter 2,
section 2.14, Page
no.
56. Whether any litigation
pending and/or any
direction/order passed by any
Court of Law against the
company, if so, details
thereof.
No litigation is pending against
the company
-
57. Certificate of accreditation
issued by the NABET, QCI to
the environmental consultant
should be incorporated in the
EIA report.
NABET Accredited consultant:
Green Circle Inc. Vadodara
(Gujarat)
NABET/EIA/1720/IA0029
Valid up to –6th March 2021
Refer Chapter 12
58. An undertaking by the Project
Proponent on the ownership
of the EIA report as per the
MoEF&CC OM dated
05/10/2011 and an
undertaking by the Consultant
regarding the prescribed
TORs have been complied
with and the data submitted is
factually correct as per the
MoEF&CC OM dated
04/08/2009. (Compliance of
OM dated 05/10/2011 &
04/08/2009).
Complied
-
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
18
59. A tabular chart with index for
point-wise compliance of
above TORs.
Complied -
Table of Contents
1 CHAPTER 1 INTRODUCTION ........................................................................................... 1
1 CHAPTER 1 INTRODUCTION ........................................................................................... 3
1.1 Purpose of the report ................................................................................................ 3
1.2 Identification of the Project and Project Proponent ................................................ 3
1.2.1 Identification of the Project ................................................................................ 3
1.2.2 Identification of the Project Proponent ............................................................. 4
1.3 Brief description of Nature, Size and location of the Project and its importance to
the country, Region. ............................................................................................................. 4
1.3.1 Brief description of Nature, Size and location of the Project........................... 4
1.3.2 Importance of Project to the Country/Region ................................................... 5
1.4 Scope and Methodology of the study ....................................................................... 6
1.5 Regulatory Framework .............................................................................................. 9
1.6 Structure of the Report .............................................................................................10
List of Tables
Table 1-1-Details of Project Proponent .............................................................................................. 4 Table 1-2-Coordinates of the project location .................................................................................. 4 Table 1-3-Methodology of the study ................................................................................................... 8 Table 1-4 Regulatory Framework ......................................................................................................... 9 Table 1-5 - Structure of the Report .................................................................................................... 10 Table 1-6 TOR Compliance .................................................................................................................. 11
List of Figures
Figure 1-1- Project Location Map ......................................................................................................... 5 Figure 1-2- Scope & Methodology of the study ............................................................................... 8
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
3 | P a g e
1 CHAPTER 1 INTRODUCTION
1.1 Purpose of the report
Products falling under project/activities listed within the Schedule to the EIA notification dated
September 14th 2006 (amended till date) requires prior Environmental Clearance (EC) from the
Impact Assessment Authority (IAA) at the Ministry of Environment, Forests and Climate Change
(MoEF&CC) (for Category A project) or the State Level Environmental Impact Assessment
Authorities (SEIAA) (for Category B projects).
The products of the project are covered under Project /activity, 3(a) B, namely “Metallurgical
industries (ferrous & nonferrous)” requiring Environmental Clearance from SEIAA, Gujarat.
The TOR Presentation was made to State Level Expert Appraisal Committee on 17th April 2018.
Subsequently SEAC issued the TOR vide letter no. SEIAA/GUJ/TOR/3(a)/1803/2019 dated
11/12/2019 (Annexure 13). Based on the TOR points issued by SEIAA, Draft Environmental
Impact Assessment (EIA) report has been prepared.
The EIA study includes determination of baseline conditions, assessment of the Impacts on the
environment due to the construction and operation of the project and making recommendations
on the preventive measures to be taken, to minimize the impact on the environment to
acceptable levels. A suitable post-study monitoring program will be outlined. Environment
Management Plan will be given based on the emissions and feasibility report.
The purpose of the Environmental Impact Assessment study and report is to comply with the
ToR issued by the SEIAA as a part to obtain Environmental Clearance. Most importantly the
purpose of this EIA study is to identify and to suggest mitigative /preventive measures for
adverse environmental impacts in a timely manner.
1.2 Identification of the Project and Project Proponent
1.2.1 Identification of the Project
M/s. Rajputana Stainless Ltd. proposing industrial unit at Plot no. at 213- Madhwas, Halol
Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat, India for expansion of
integrated steel plant. The Unit has obtained the Consent to operate approval for manufacturing
Iron & Steel Billets of 28,000 MTPA.
Now, for catering the future market demand, the company proposes to set up manufacturing unit
of higher capacity from 28,000 MTPA to 90,000 MTPA. With this proposed capacity, the unit
intends to manufacture of Iron & Steel billet within the premises to cater the market requirement.
The part of the Iron & Steel billet production will be utilized for making TMT bars & other Steel
products manufacturing up to 90,000 MT, in Group Company as well as selling in to the market
as product.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
4 | P a g e
1.2.2 Identification of the Project Proponent
The details of the Promoters and their Background are given as below:
Table 1-1-Details of Project Proponent
Sr. No. Name of the Partner Designation
1. Shankar Lal Deep Chand Mehta
Partner
2. Babu Lal Deep Chand Mehta
Partner
3. Jayesh Natwar Lal Pithwa Partner
1.3 Brief description of Nature, Size and location of the Project and its
importance to the country, Region.
1.3.1 Brief description of Nature, Size and location of the Project
The proposed expansion project is to be located at Plot No. 213- Madhwas, Halol Kalol Road,
Taluka : Kalol, District: Panchmahal – 389330, Gujarat, India. It is situated at Latitude: 21° 77’
99.08” N & Longitude: 72° 82’ 23.10” E. Nearest major city is Halol which is 7.3 KM far from the
project site in direction SSE.
Table 1-2-Coordinates of the project location
Sr.No. Corners Latitude Longitude
1. A 22°34'10.10"N 73°27'29.43"E
2. B 22°34'6.19"N 73°27'29.49"E
3. C 22°34'6.02"N 73°27'21.53"E
4. D 22°34'9.80"N 73°27'20.74"E
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
5 | P a g e
Figure 1-1- Project Location Map
1.3.2 Importance of Project to the Country/Region
Main purpose of the proposed project is to cater the needs of the market for production of Iron &
Steel billet and future requirement.
With the increase in the industrialization & infrastructure development, there has been an
increase in the demand of steel products. The proposed product is Iron & steel Billets which will
be mainly used for making TMT bars & other steel products. It is used for feedstock to rolling
mills for production of products like wire rods, bars etc. Due to rapid industrial & infrastructure
development there is constant increase in need of steel in the market. Steel products are used
in various sectors of infrastructure development such as industrial establishments, schools
colleges, builders and general public at large. As there is rapid growth in these industrial sectors
within the country as well as globally, accordingly there has been increase in demand for alloy
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
6 | P a g e
steel product.
Being a core sector, steel industry tracks the overall economic growth in the long term. Also,
steel demand, being derived from other sectors like automobiles, consumer durables and
infrastructure, its fortune is dependent on the growth of these user industries. The Indian steel
sector enjoys advantages of domestic availability of raw materials. This provides major cost
advantage to the domestic steel industry. The Indian steel industry is largely iron-based through
the blast furnace (BF) or the direct reduced iron (DRI) route. About 60% of the crude steel
capacity is resident with integrated steel producers (ISP). But the changing ratio of hot metal to
crude steel production indicates the increasing presence of secondary steel producers (non-
integrated steel producers) manufacturing steel through scrap route, enhancing their
dependence on imported raw material. World crude steel production was 1547 million tonnes
(MT) in 2012, as per World Steel Association (WSA). China accounted for 46% of the world's
total crude steel production in 2012, reaching 716.5 MT. During 2012, India maintained its
ranking as the 4th largest steel producing country in the world behind China, Japan and the US
with a crude steel production of 76.7 MT. Global advisory firm Ernst &Young in its recent study
said that India's steel consumption would grow by over 5% in the calendar year 2014 to 83
million tonnes compared with 79 million tones the country consumed in the previous calendar
year. In general there is demand of steel products in the region as well as country and its
demand is increasing day by day due to developmental activities.
1.4 Scope and Methodology of the study
The EIA study includes determination of baseline conditions, assessment of the Impacts on the
environment due to the construction and operation of the project and making recommendations
on the preventive measures to be taken, to minimize the impact on the environment to
acceptable levels. A suitable post-study monitoring program will be outlined. Environment
Management Plan will be given based on the emissions and feasibility report. As per the
guidelines, the generic structure of EIA is considered as mentioned in EIA notification dated
14th September, 2006. The scope of study based on MoEF & CC/CPCB guidelines is tabulated
below:
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
7 | P a g e
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
8 | P a g e
Figure 1-2- Scope & Methodology of the study
Table 1-3-Methodology of the study
Environmental Aspects No. of
Locations Observations
Meteorology -
One season site specific meteorological status of the
study was carried out for prediction of ground level
concentration in All the direction (Up Wind, Down
Wind & Cross Wind).
Ambient Air Quality 8
The prevailing ambient air quality status was
established through a network of stations monitored
during the period of Jan 2020 – March 2020. The
ambient air quality monitoring as per the parameters
prescribed in TOR was carried out within the study
area of 10 km. Prediction of impacts on air quality due
to proposed operations were carried out through
application of air quality models.
Water 8
The water quality data with respect to
physicochemical, biological parameters and heavy
metals were analyzed to established baseline water
quality of study area of 10 km. The wastewater
generation, its characterization and management were
carried out which was used in assessing the impact of
the project on water environment.
Noise 8
Noise level measurements were carried out around
the project site, data were also analyzed for
establishing baseline status of noise and it was used
in assessing the impact of the project on noise &
vibration environment.
Soil 8
Soil samples were collected and have been analyzed
to understand nutrient status as well as assessing the
impact of the project on soil environment.
Ecology --
Flora and fauna species was listed based on the
available secondary information. Study of flora and
fauna was carried out within 10 km radius around the
proposed project.
Geology & Geohydrology --
Geological and geo-hydrological investigation work
has been carried out in and around the study area to
know the status of the study area.
Risk and Hazard Analysis --
Risk Assessment study has been carried out to
evaluate risk, assess its impact associated to the
proposed project activity --and plan the appropriate
action to control risk by the most economical means.
Socio-economic data --
Existing baseline status of the socio-economic profile
of the study area with reference to demographic
structure, provision of basic amenities, health status
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
9 | P a g e
Environmental Aspects No. of
Locations Observations
incorporating economic pattern in the nearby rural
areas (10 km radius) were undertaken, it was used in
assessing the impact of the project on socio-economic
environment.
1.5 Regulatory Framework
The proposed project will abide and function under the purview of the following Rules, Acts &
Regulations which are formulated by the government to protect environment and maintain good
environmental conditions.
Table 1-4 Regulatory Framework
Sr.
No.
Legal Instrument (Type, Ref.,
Year)
Concern Authority or
Bodies Applicability
1
Air (Prevention and Control of
Pollution) Act, 1981 and its
subsequent amendments
CPCB and SPCB
Air emission from stack
attached to Boiler, TFH &
D.G. set Process Gas
Emission from Laminated
Sheet Dryer
2
Water (Prevention and Control of
Pollution) Act, 1974 and its
subsequent amendments
CPCB and SPCB
Wastewater generation from
industrial activities as well as
from domestic activities.
3
Water (Prevention and Control of
Pollution) Rules, 1975 and its
subsequent amendments
CPCB and SPCB
Wastewater generation from
industrial activities as well as
from domestic activities.
4
The Environment (Protection) Act,
1986 & Environmental (Protection)
Rules, 1986 and their subsequent
amendments
Ministry of Environment
and Forests, & Climate
Change (MoEF&CC),
CPCB and SPCB
Production of Synthetic
Organic Chemicals (Resins)
5
Hazardous and Other Wastes
(Management and Trans boundary
Movement) Rules, 2016
MoEF & CC, CPCB,
SPCB/UTPCC, DGFT,
Port Authority and
Customs Authority
Generation of Solid &
Hazardous Wastes from
industrial activities.
6 EIA Notification, 2006 and its
subsequent amendments
MoEF&CC,
SPCB/UTPCC
Production of Synthetic
Organic Chemicals (Resins)
7
Public Liability Insurance Act, 1991
amended 1992 & Public Liability
Insurance Rules, 1991 and its
subsequent amendments
MoEF&CC, District
Collector
Industrial units manufacturing
chemical products and
requirement of 70 workers
8 The Factories Act, 1948
Ministry of Labour,
DGFASLI and Directorate
of Industrial Safety and
Health/ Factories
Inspectorate
Industrial units manufacturing
chemical products and
requirement of 70 workers
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
10 | P a g e
Sr.
No.
Legal Instrument (Type, Ref.,
Year)
Concern Authority or
Bodies Applicability
9
Noise Pollution (Regulation and
Control) Rules, 2000 and its
amendments
CPCB and SPCB/UTPCC Noise may be generated due
to industrial activities.
1.6 Structure of the Report
The data generated from various studies for EIA/EMP are presented and discussed in following
chapters of this report prepared as per Appendix-III of the EIA Notification, 2006.
Table 1-5 - Structure of the Report
Executive Summary: This chapter gives the Executive Summary of the EIA report.
Chapter 1 (Introduction): This chapter describes objectives and methodology for EIA.
Chapter 2 (Project
Description):
This chapter gives a brief description of the location, approachability,
manufacturing processes, and details of raw materials, amenities,
layout and utilities of the proposed project.
Chapter 3 (Description of
the Environment):
This chapter presents details of the baseline environmental status for
microclimate, air quality, noise, traffic, water quality, soil quality, flora,
fauna and socio-economic status etc.
Chapter 4 (Anticipated
Environmental Impact and
Mitigation Measures):
This chapter discusses the possible sources of pollution and
environmental impacts due to the project during construction and
operation phases and suggests the mitigation measures.
Chapter 5 (Analysis of
Alternatives):
This chapter covers analysis of technology alternatives and site
alternatives.
Chapter 6 (Environmental
Monitoring Programme):
This chapter discusses the details about the environmental monitoring
program during construction and operation phases.
Chapter 7 (Additional
Studies):
This chapter covers information about Risk Assessment Studies for
the construction and operation phase, the safety precautions that are
taken during construction phase and Disaster Management Plan and
Emergency Preparedness Plan onsite and offsite.
Chapter 8 (Project
Benefits): This chapter presents the benefits from this project.
Chapter 9 (Environmental
Cost Benefit Analysis)
If recommended by EAC at the scoping stage, this chapter shall
include the Environmental Cost benefit Analysis of the project.
Chapter 10 (Environmental
Management Plan):
This chapter deals with the Environmental Management Plan (EMP)
for the proposed Project and indicates measures proposed to
minimize the likely impacts on the environment during construction
and operation phases and budgetary allocation for the same.
Chapter 11 (Conclusion):
This chapter presents the conclusion made by the project proponent
and developer.
Chapter 12 (Disclosure of
Consultants engaged): This chapter presents the details of the consultant.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
11 | P a g e
TERMS OF REFERENCE (TOR) COMPLIANCE
Point wise compliance of the TOR points issued by MOEF, Gujarat vide Letter No.
SEIAA/GUJ/TOR/3(a)/1803/2019 for setting up of expansion in manufacturing plant of
‘Metallurgical Industries’ at Survey No.- 213/ 1,213/ 2,212/ 1,212/ 2,184, 185, 186/ 1,183/
1,183/2, 183/3, 182/1, 214/1, 214/3 at- Madhwas, Halol-Kalol Road, Taluka: Kalol, District:
Panchmahal.
A tabular chart with index for point wise compliance is as given below:
Table 1-6 TOR Compliance
Sr.
No
ToR Points Brief description of compliance Reference in EIA
report
1. A tabular chart with index for point-
wise compliance of below
mentioned ToRs.
Complied -
2. Executive Summary of the project-
giving a prima facie idea of the
objectives of the proposal, use of
resources, justification, etc. In
addition, it should provide a
compilation of EIA report, including
EMP and the post-project
monitoring plan I brief.
Executive summary has been
incorporated in the initial pages of
the EIA report.
Initial pages of EIA
report
3. Justification for selecting the
proposed product and unit size.
Steel being one of the niche
commodities and most useful and
versatile material, steel is
considered to be the backbone of
human civilization. The project site
is in proximity of Halol District of
Gujarat State and the fact is that
the proposed project is to be done
within the project area. Project
proponent is very well familiar with
the surrounding environment
therefore, it becomes easy for the
unit to set up, operate & maintain
the project on above said location.
Refer Chapter 2,
section 2.2 ,Page no.
38
4. Land requirement for the project
including its break up for various
purposes, its availability and
optimization.
Total available land area of
premises is 43000 m2, out of which
14200 m2 (33.02%) area will be
developed for greenbelt.
Refer Chapter 2,
section 2.9.1, Page no.
48
5. Land possession documents. Copy
of NA order showing permission to
use the project land for industrial
purpose.
- Attached as annexure
1
6. Furnish status of all the applicable All applicable regulatory framework Chapter 1, section 1.5,
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
12 | P a g e
rules, acts, regulation, clearances in
a tabular form.
are presented in tabular form. Page no. 9
7. In case of expansion of the project
Need for the proposed expansion
should be justified in detail.
Steel has been one of the oldest
industrial sectors in India. It has
also been the first to get liberalized
and controls lifted partially in 1991.
There have been massive capacity
additions by all steel majors and
several new groups made foray
into primary and secondary steel
market in the first phase of
liberalization in early 90s. The
major costs in steel making are the
costs of Iron Ore, Metallurgical
Coke, Limestone, Coal and Power.
While the country is rich in iron ore
and limestone, its quality of coal is
poor and power costs are high.
The industry enjoys inherent
advantages in terms of availability
of raw material and cheap labour.
Refer Chapter 2,
section 2.2, Page no.
28
Adequacy of existing EMS
(Environment Management System)
Adequacy of existing EMS has
been attached as Annexure 2
Annexure 2
Explore the possibility to achieve
Zero Liquid Discharge (ZLD) for
existing as well as proposed
activity.
The Industrial effluent generated
from unit will be 38 KL/day. Hence,
the suitability of quality and
quantity of process effluent re-
using into gardening. The unit is
proposing to maintain the
adequate storage capacity to
handle for five days generation of
effluent from Iron & Steel Billets
manufacturing. Hence it will be a
ZLD plant.
Refer Chapter 2,
section 2.9.8,Page no.
49
Records of any legal breach of
Environment laws. i.e. details of
show-cause notices , closure
notices etc. served by the GPCB to
the existing unit in last five years
and actions taken then after for
prevention of pollution.
Details of Show cause notices
received earlier and there
compliance status has been
incorporated.
Refer Chapter 2,
Section 2.13, Page no.
59
Copies of Environment Clearances
obtained for the existing plant, its
point wise compliance report.
As the plant was established in the
year 1991 i.e., before the issuance
of EIA Notification, EC is not
applicable for the existing plant.
Environmental audit
reports is attached as
Annexure 3
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
13 | P a g e
Environmental audit reports for last
3 years and compliance of its
recommendations / Suggestions.
(Include latest audit report and its
compliance)
Environment audit reports has
been added as Annexure 3
Copy of Consent to
Operate (CC&A) is
attached as Annexure
4
SCN is attached as
Annexure 5
Copy of Consent to Operate
(CC&A) obtained along with point
wise compliance status of all the
conditions stipulated therein.
Copy of Consent to Operate
(CC&A) obtained along with point
wise compliance status of all the
conditions stipulated therein
attached as Annexure 4
In case of earlier EC obtained:
Certified Compliance Report (CCR)
from the concern authority as per
the MoEF&CC’s Circular no. J-
11011/618/2010-IA (II) (I) dated
30/05/2012 and circular no. J-
11013/6/2010-IA-II (Part) vide dated
07/09/2017.
As the plant was established in the
year 1991 i.e, before the issuance
of EIA Notification, EC is not
applicable for the existing plant.
Copies of XGN generated
Inspection reports with analysis
reports of the water/Air/Hazardous
samples collected by GPCB (Last 2
year). Copies of instructions issued
by GPCB in last 2 year and point
wise compliance thereof.
Copies of XGN generated
Inspection reports with analysis
reports attached as Annexure 3. All
the SCN issued by GPCB and its
compliance has been attached as
Annexure 5.
8. Exact details about infrastructural
facilities, plant machineries etc.
required for the proposed project.
Since expansion will be carried out
in the existing plant premises, no
new land is required. Details of
infrastructural facilities, plant
layout, plant machineries and other
relevant details Incorporated
Refer Chapter 2,
section 2.9.6, Page no.
49
9. Demarcation of proposed project
activities in layout plan.
Detailed Plant layout incorporated Refer Chapter 2,
section 2.3, Page
no.29
10. Present land use pattern within 10
km radius from the project boundary
based on satellite imagery.
Land use pattern of study area (10
KM) incorporated.
Refer Chapter 3,
section 3.3.4, Page no.
71
11. Provision of separate entry & exit
and undertaking for the same.
Provision of adequate margin all-
round the periphery for easy
unobstructed movement of fire
tender without reversing.
Separate entry and exit provided
which is indicated in the plant
layout.
Refer Chapter 2,
section 2.3, Page
no.29
12. Technical details of Induction
Furnaces including its cooling and
Technical details with advantages
of Induction furnace has been
Refer Chapter 2,
section 2.7.6 , Page
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
14 | P a g e
interlocking systems along with
drawing of the induction furnace.
Details of Air Pollution Control
Measures proposed for Induction
Furnace along with its adequacy.
Details of specific measures to
ensure that emission from the
Induction Furnace will not escape
from the furnace. Details of specific
measures to ensure that emission
from the Induction Furnace will not
escape from the furnace in form of
fugitive emission bypassing the air
pollution control system.
provided. no. 43
13. Complete process flow diagram
describing each unit, its processes
and operations along with material
and energy inputs & outputs
(material and energy balance). (1)
Details of Iron and steel making
plant describing details on design
and manufacturing process for all
the units. (2) Details on blast
furnace/open hearth furnace/basic
oxygen furnace/ladle refining ,
casting and rolling plants etc.
Complete manufacturing process
with flow diagram and material
balance for products has been
incorporated.
Refer Chapter 2,
section 2.7.1 , Page
no. 37
14. Characteristics of raw material
(scrap) to be purchased as a raw
material in terms of presence of
foreign material like plastic, rubber,
dirt, oily residues, paint etc. Details
of scrap cleaning/sorting process, if
any to be carried out, for removal of
foreign materials.
All raw materials like Iron ore, MS
scraps will be received and stored
in respected closed storage shed.
Scrap from ship is low carbon and
good quality. All raw scraps are
separated by magnetic separator
to remove foreign particle.
Separated scrap is manually
examined for removal of painted,
oily and dirty residual scrap. Such
scrap is sorted out. After sorting
scrap will be sent for cleaning
section where scrap will be
cleaned manually by wire brush
and compress air. Separated scrap
is then crushed to make
homogeneous block. These block
of metal finally feed to induction
furnace for melting. Maximum one
month raw material inventory will
be maintained in the plant for
Refer Chapter 2,
section 2.7.5 , Page
no. 43
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
15 | P a g e
continuous operation.
15. Details of proposed source-specific
pollution control schemes and
equipment to meet the national
standards.
In this proposed project, process
gas and flue gas emission will be
the main source of air pollution.
There will be chances of fugitive
emission due to raw material
handling and transportation and
manufacturing activity.
Refer Chapter 2,
section 2.9.9, Page no.
54
16. Details on requirement of raw
materials, its source and storage at
the plant. Also, an agreement for
the supply of the iron ore for the
proposed plant.
Details of raw material and its
quantity has been incorporated in
the report. Bills of raw material has
been attached as Annexure 6.
Refer Chapter 2,
section 2.8, Page no.
46
17. Assessment of source of the water
supply with adequacy of the same
to meet with the requirements for
the proposed project. Permission
from concern authority.
Total water requirement for fresh
water after expansion is 128 KLD
out of which 95 KLD will be fresh
water and 33 KLD will be reused
for gardening after treatment in
ETP. Water requirement will be
fulfilled by Borewell for which
permission has been obtained vide
NOC no.
CGWA/NOC/IND/ORIG/2020/9317
dated 26/11/2020.
Refer Chapter 2,
section 2.9.8.1, Page
no. 49
18. Submit CGWA permission for
ground water source from
competent authority.
Permission obtained for 95 KLD
from CGWA vide NOC no.
CGWA/NOC/IND/ORIG/2020/9317
dated 26/11/2020 attached as
Annexure 11.
-
19. Submit adequate proposal for
APCM with pickling section and its
stack and scrubber bleed liquor
disposal.
Scrubber will be provided as
APCM for picking section. Acid
residue from pickling section will
be disposed as Hazardous waste
Refer Chapter 2,
section 2.9.9, Page no.
54
20. Detailed water balance (including
reuse-recycle, evaporation if any)
Total 24 KLD domestic will be
generated which will be disposed
through STP.
Total 38 KLD will be generated from
industrial wastewater.
Detailed water balance has been
incorporated.
Refer Chapter 2,
section 2.9.8.1, Page
no. 49
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
16 | P a g e
21. Specific measures proposed to
conserve water and plans for the
future in this regard.
The effluent generated from
different processes will be given
Primary, Secondary and Tertiary
treatment.
The final neutralized treated
effluent will be then utilized for
gardening. 11584.02 KL/Year rain
water will be used to recharge the
ground water aquifers through rain
water harvesting.
Refer Chapter 2,
section 2.9.8.1, Page
no. 49
Refer Chapter 10,
section 10.7.1, Page
no. 198
22. Detailed cleaner production
measures like energy efficiency in
the furnaces to reduce emissions if
possible in the proposed project &
commitment of the management on
futuristic
development/implementation for the
same.
Technical details of induction
furnace and its benefits for cleaner
production have been
incorporated.
Refer Chapter 2,
section 2.7.6, Page no.
43
Refer Chapter 10,
section 10.10, Page
no. 201
23. Explore the possibility of
reuse/recycle and other cleaner
production options for reduction of
wastes.
Adequate ETP of capacity 38 KLD
has been provided with primary,
secondary and tertiary treatment
has been installed. Detailed water
balance has been installed.
Hazardous waste generation and
management will be done
according to Hazardous and other
waste (Management and
Transboundary) rules, 2016.
Refer Chapter 10,
section 10.10, Page
no. 201
24. Generation, characteristics and
mode of the disposal of wastewater
in existing and proposed scenarios.
Details of the wastewater treatment
facilities, if any proposed, including
its capacity, size of each unit,
retention time and other technical
parameters along with adequacy
and efficacy report. Action plan for
Zero Liquid Discharge concept.
The effluent generated from
different processes will be given
Primary, Secondary and Tertiary
treatment.
The final neutralized treated
effluent will be then utilized for
Gardening.
Detailed ETP diagram, details of
each unit and its volume
incorporated. The effluent quality
of process effluent from Utilities
incorporated.
Refer Chapter 2,
section 2.9.8.2, Page
no. 49
25. One season Site-Specific micro-
meteorological data using
temperature, relative humidity,
hourly wind speed and direction and
rainfall should be incorporated.
Meteorological data within the
study area, during air quality
survey period has been
incorporated.
Refer Chapter 3,
section 3.5, Page no.
83
26. Anticipated environmental impacts
due to the proposed project/
Details of impacts and its
mitigation with matrix has been
Refer Chapter 4,
section 4.8.1, Page no.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
17 | P a g e
production may be evaluated for
significance and based on
corresponding likely impacts VECs
(Valued Environmental
Components) may be identified.
Baseline studies may be conducted
within the study area of 10 km for all
concerned/identified VECs and
likely impacts will have to be
assessed for their magnitude &
order to identify mitigation
measures.
incorporated.
AERMOD View – Lake
Environmental Software, which is a
Gaussian-Plume atmospheric
dispersion algorithm for estimating
concentration of pollutant, has
been used to predict the Ground
Level Concentrations (GLC’s) of
PM10, SO2 and NOx due to plant
activity. The GLC’s were predicted
on 24 hourly average basis
keeping in view the prescribed
national ambient air quality
standards (NAAQS). Other likely
impacts on water, soil, ecology,
occupational health, etc has also
been discussed thoroughly.
143
27. One complete season base line
ambient air quality data (except
monsoon) to be given along with the
dates of monitoring. The
parameters to be covered shall be
in accordance with the revised
National Ambient Air Quality
Standards as well as project
specific parameters. Locations of
the monitoring stations should be so
decided so as to take into
consideration the pre-dominant
downwind direction, population
zone and sensitive receptors. There
should be at least one monitoring
station in the upwind direction.
There should be at least one
monitoring station in the pre-
dominant downwind direction at a
location where maximum ground
level concentration is likely to occur.
AAQM was carried out and AAQM
locations were monitored on 24
hourly average bases twice in a
week as per guidelines of CPCB
and NAAQS. The conventional
and project specific parameters
such as particulate matter PM10
(size less than 10 µm), particulate
matter PM2.5 (size less than
2.5µm), Sulphur Dioxide (SO2)
&Oxides of Nitrogen (NOx) were
monitored for 10 locations.
Locations were Project site,
Jetpur, Kadanch, Muvala,
Khakhariya, Navaria, Chhabapur
and Ratanpura.
Refer Chapter 3,
section 3.6.3, Page no.
90
28. Modeling indicating the likely impact
on ambient air quality due to
proposed activities. The details of
model used and input parameter
used for modeling should be
provided. The air quality contours
may be shown on location map
clearly indicating the location of
sensitive receptors, if any, and the
Isopleths of PM10, SO2 and NOx
has been incorporated predicting
the worst case scenario by
considering the Maximum baseline
result + Maximum GLC value in
the study area.
Refer Chapter 4,
section 4.8.1, Page no.
143
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
18 | P a g e
habitation. The wind rose showing
pre-dominant wind direction should
also be indicated on the map.
Impact due to vehicular movement
superimposed on Google map/
geographical area map.
29. Specific details of (i) Details of the
furnaces & utilities required. (ii)
Type and quantity of fuel to be used
in each furnace and utility. (iii)
Gaseous emission from each
furnace and utility (iv) Air pollution
Control Measures along with its
adequacy to achieve the GPCB
Norms. (v) Flue gas emission rate
from each utility (vi) List the sources
of fugitive emission from the unit
along with its quantification and
proposed measures to control it.
Plant machineries and utilities
have been incorporated.
Fuel used of DG set is LDO
(150L/Hr) and HSD for furnace
(200 L/Hr)
Type of emissions or air pollutants
from stacks are PM, SOx, NOx.
Bag filters and adequate stack
height has been provided to each
stack.
Detailed information on fugitive
emissions has been incorporated.
Refer Chapter 2,
section 2.9.6, Page no.
49
Refer Chapter 2,
section 2.9.4, Page no.
48
Refer Chapter 2,
section 2.9.9, Page no.
54
30. Explore the possibility for fume
extraction system along with
primary and secondary APCM for
induction furnaces.
Fume extraction system has been
installed as hood which is used
over induction furnace along with
other APCM’s.
-
31. Details regarding D.G. Sets
including its capacities, location,
fuel consumption & storage and
acoustic measures to abate noise
pollution.
DG set of capacity 1000 KVA is
proposed. LDO (150 L/Hr) will be
used as fuel. Specified space has
been provided for Emergency DG
set. Acoustic enclosure will be
provided to minimize noise and
adequate stack height as APCM.
-
32. Base line status of the noise
environment, impact of noise on
present environment due to the
project and proposed measures for
noise reduction including
engineering controls.
The ambient noise standards are
presented in Equivalent noise
levels (Leq.) have been measured
twice a week during study
period.The measurements were
carried out at each monitoring
location during day time and night
time at total 10 location. Adequate
measure will taken to mitigate
noise pollution during construction
and operation phase.
Refer Chapter 3,
section 3.7, Page no.
94
Refer Chapter 4,
section 4.6, , Page no.
133
33. Details of generation and
management of the hazardous
wastes/Solid wastes to be
generated from the project stating
detail of storage area for each type
of wastes, its handling and its
Hazardous waste generation and
management will be done
according to Hazardous and other
waste (Management and
Transboundary) rules, 2016.
Refer Chapter 2,
section 2.9.13, Page
no. 57
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
19 | P a g e
disposal. Details of slag generation,
its quality and method of disposal/
reuse in various applications, How
spillages/leakages of used oil shall
be managed.
The spillages from Diesel storage
will be prevented by dyke wall. The
spillage and leakages from pumps,
pipe assembly and storage tank
will be transfer back to storage
tank or day tank. Solid waste
generation such as slag / iron
residue while using iron / steel
scrap will be @ 500/- MT/year. it
will be re-melt (as possible) final
residue be given for filling up in low
lying area, construction or roads
etc/ sale to actual end users. The
drums will be collected by workers
and will be stored in storage yard
in stacking.
34. A detailed EMP including the
protection and mitigation measures
for the impacts on human health
and environment as well as detailed
monitoring plan. The EMP should
also include the concept of waste-
minimization, recycle/ reuse/
recover techniques, energy
conservation, and natural resources
conservation. Total capital cost and
recurring cost/annum earmarked for
environment pollution control
measures. Environmental
management cell proposed for
implementation and monitoring of
EMP.
A well designed EMP plan has
been proposed including waste
minimization recycle/ reuse/
recover techniques and energy
conservation. Rain water
harvesting plan has also been
proposed. Total EMP Capital cost
is Rs. 86 Lakhs and recurring is
Rs. 34 Lakhs.
Proper Environmental
management cell proposed for
implementation and monitoring of
EMP and to obey well laid EHS
policy.
Chapter 10, section
10.5.1, 10.7.1, 10.11 &
10.5
35. Environment Management Cell
equipped with laboratory and
qualified environment engineer shall
be established.
Environment Management Cell
equipped with laboratory and
qualified environment engineer has
been established.
Chapter 6, section 6.4,
Page no. 154
36. Occupational health impacts on the
workers and mitigation measures
proposed to avoid the human health
hazards along with the personal
protective equipment to be provided
to the workers. Detailed work area
monitoring plan. Plan for periodic
medical examinations of the
workers exposed.
Currently, Industry has adopted all
precautionary methods to reduce
the risk of exposure of hazards to
employees and same will be
continued after proposed. Detailed
work area monitoring plan has
been incorporated. Regular health
checkup of works will be done and
reports of same has been attached
as Annexure 10.
Chapter 10, section
10.8, Page no. 150-
198
Chapter 7, section
7.1.5.1, Page no. 166
& 7.1.5.2, Page no.
166
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
20 | P a g e
37. Detailed work area monitoring plan.
Details of the activity wise hazards,
likely heat stress to the workers,
radiation heat level in and around
the furnaces, measures proposed
for reduction of heat stress around
furnaces and for safe handling of
the molten metal considering the
provision of the Gujarat Factories
Rules. Details of automated
systems to be provided to avoid
manual handling/conveyance of
materials.
Working with molten metal always
has been, and always will be, a
dangerous occupation. Hence,
Induction foundry safety
fundamentals has been
incorporated.
Chapter 2, section
2.9.12, Page no. 56
38. Detailed risk assessment report
including identification of the most
hazardous activity, its sub activity
predictions of the worst-case
scenarios and maximum credible
accident scenario along with
damage distances and
preparedness plan to combat such
situation and risk mitigation
measures.
Detailed HAZOP study was carried
out and observed that major on-
site emergency situation may
occur from the organic coal
chemicals storage and handling,
fuel gas handling, molten metal
and slag handling, acids and alkali
storage and handling and electrical
short-circuit. The off-site
environmental disaster may arise if
large-scale fire or explosion
occurs, the effect of which extends
beyond the plant boundary. The
off-site environmental disaster may
take place due to significant
environmental degradation for a
sustained period.
Chapter 7, section
7.1.4, Page no. 161
39. Details of firefighting system
including provision for flame
detectors, temperature actuated
heat detectors with alarms,
automatic sprinkler system, location
of fire water tanks & capacity,
separate power system for
firefighting, details of qualified and
trained fire personnel & their job
specifications, nearest fire station &
time required to reach the proposed
site. Submit line diagram of the fire
hydrant network.
Details of fire hydrant line,
sprinklers, and separate
underground tank of capacity 200
KLD will be provided. Jockey pump
of capacity 150 LPM will be
provided and separate pump which
will be diesel operated shall be
provided for stand by purpose.
Trained fire personnel will be hired
as fire & safety officer.
Fire hydrant line has been marked
in the detailed layout of the plant.
40. Provision of qualified industrial
hygienist, safety officer, factory
medical officer employed for
hazardous processes and
Trained fire and safety officer shall
be hired with minimum 4 years of
experience. OHC has been
developed in the plant premises
-
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
21 | P a g e
monitoring of the occupational injury
to workers as well as impact on the
workers.
and qualified doctor will be hired.
41. Impact of the transportation of raw
materials and finished product on
the transport system should be
assessed and provided.
Total Truck load estimates will be
@ 22 nos. per day.
Periodical work zone monitoring
will be carried out once in six
months for 8 hrs and 15 minutes
for parameters PM10, SO2 and
other parameters as per the
Factories Act.
Refer Chapter 2,
section 2.9.12, Page
no. 56
42. Details of possibility of occupational
health hazards from the
manufacturing activities and
proposed measures to prevent it.
Several health related issues can
be occurred with the workers of
chemical industries due to long
term exposure in dusting, noisy
area, handling of some hazardous
chemicals, gaseous emissions etc.
In the proposed unit, drinking
water and sanitation facilities are
provided to workers. All the
necessary personal protective
equipment’s are provided for the
respective works. The unit has
provided such arrangements to
minimize manual handling of
chemicals and hazardous wastes.
Regular health check-ups are
carried out of all the workers and
record is maintained for the same.
Medical, fire and safety trainings
are given time-to-time. Moreover,
unit has provided proper
environmental management
system and operates the same
efficiently. Thus, there will not be
any possibility of adverse impact
on workers’ health & the same
shall be continued further with the
upcoming proposed project. Thus,
no adverse impact is expected on
sanitation and community health.
Chapter 10, section
10.8, Page no. 198
43. Ambient temperature in the work
zone and distance of the workers
from the furnaces. Details of likely
heat stress to the workers involved
in the manufacturing process.
Detailed HAZOP study has been
carried out for Identifying the
potential hazardous areas so that
adequate design safety measures
Chapter 7, section 7.1,
Page no. 159 onwards
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
22 | P a g e
Radiation heat level in & around the
furnace, monitoring and mitigation
measures for the same including
barricading, if any to be provided.
can be adopted to reduce the
likelihood of accidental events &
Identifying the stakeholders and
evaluating their risk along with
proposing adequate control
techniques.
44. Details of personal protective
equipments to be provided to the
workers. Plan for periodic medical
examination of the workers.
Details of PPE to be used during
construction & operation phase
has been incorporated. Annual
medical checkup is done of
workers, reports of which has been
attached as Annexure 8
Chapter 7, section
7.1.6, Page no. 173
45. Details of first-aid/occupational
health center and arrangement of
ambulance van provided for injured
workers.
1 Ambulance van has been
provided for emergency purpose
and OHC center will be developed
as displayed in the plant layout
with basic facilities.
-
46. Detailed work zone environment
plan. Details of equipment/
instrument to measure record and
analyze workplace exposure
including air quality, noise, vibration,
heat stress, ventilation, illumination
etc.
Periodical work zone monitoring
will be carried out once in six
months for 8 hrs and 15 minutes
for parameters PM10, SO2 and
other parameters as per the
Factories Act. Monitoring for noise,
vibration, heat stress, ventilation,
illumination etc will be done once
in a year at suitable locations.
Refer Chapter 2,
section 2.9.12, Page
no. 56
47. Provision of qualified industrial
hygienist, safety officer, factory
medical officer employed for
hazardous operations and
monitoring of the occupational injury
to workers as well as impact on the
workers.
Trained fire and safety officer shall
be hired with minimum 4 years of
experience. OHC has been
developed in the plant premises
and qualified doctor will be hired.
-
48. A tabular chart for the issues raised
and addressed during public
hearing/consultation and
commitment of the project
proponent on the same should be
provided. An action plan to address
the issues raised during public
hearing and the necessary
allocation of funds for the same
should be provided.
Noted & will be complied in the
Final EIA report
-
49. Ensure participation of people
during Public Hearing with equality
in gender so as to encourage
Noted & will be complied in the
Final EIA report
-
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
23 | P a g e
woman participation in Public
Hearing & at the same time their
issues shall also be given
weightage. PP shall made adequate
efforts in this regard and shall
submit the relevant documents.
50. Submit detailed treatability report for
ETP with stage wise quality of
pollutants and treated effluent
quantity which is to be recycled and
which is to be used for gardening
purpose.
Treatability report has been
attached as Annexure 8
Annexure 8
51. Details of five year greenbelt
development program including
annual budget, types & number of
trees to be planted, area under
green belt development (with map),
budgetary outlay; along with
commitment of the management to
carry out the tree plantation
activities outside the premises at
appropriate places in surrounding
area.
Five year green development plan
has been included as an integral
part of EMP. Total of 14200 sqm
area is to be developed as green
belt.
Refer Chapter 10,
section 10.6, Page no.
195
52. Undertaking from the management
regarding maximum employment to
the local people.
Undertaking regarding same has
been obtained and attached as
Annexure 9.
Annexure 9.
53. Submit checklist in the form of Do’s
& Don’ts of preventive maintenance,
strengthening of HSE, mfg. utility
staff for safety related measures.
HSE policy and corporate
environment policy of the Industry
has been attached as Annexure
10.
Annexure 10.
54. Proposal for socio economic
upliftment activities along with time
bound action plan and cost should
be included.
Industry will provide 1 % of the
proposed expansion project cost
(i.e. 3.5 Lakh) towards the
Corporate Environment
Responsibility. Socio-economic
development activities will be
planned based on the as well as
general necessity in villages
Refer Chapter 8,
section 8.5, Page no.
183
55. Details of any fatal and non-fatal
accidents and dangerous
occurrences under the Gujarat
Factories Rules 1963 (GFR) for
factories for the last three years.
An incident was reported on
16/11/2019 which resulted in
explosion of metal. Details of same
has been provided in EIA report.
Refer Chapter 2,
section 2.14, Page no.
61
56. Whether any litigation pending
and/or any direction/order passed
by any Court of Law against the
No litigation is pending against the
company
-
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
24 | P a g e
company, if so, details thereof.
57. Certificate of accreditation issued by
the NABET, QCI to the
environmental consultant should be
incorporated in the EIA report.
NABET Accredited consultant:
AMBIENTAL GLOBAL PRIVATE
LTD. Ghaziabad (U.P)
Refer Chapter 12
58. An undertaking by the Project
Proponent on the ownership of the
EIA report as per the MoEF&CC
OM dated 05/10/2011 and an
undertaking by the Consultant
regarding the prescribed TORs
have been complied with and the
data submitted is factually correct
as per the MoEF&CC OM dated
04/08/2009. (Compliance of OM
dated 05/10/2011 & 04/08/2009).
Complied
-
59. A tabular chart with index for point-
wise compliance of above TORs.
Complied -
26 | P a g e
Table of Contents
2 CHAPTER 2 PROJECT DESCRIPTION ...............................................................................
2.1 Type of Project ..........................................................................................................28
2.2 Need for the project ..................................................................................................28
2.3 Project Location ........................................................................................................29
2.4 Site Photographs ......................................................................................................32
2.5 Justification of Site Selection ..................................................................................33
2.6 Size or Magnitude of the project ..............................................................................35
2.6.1 Details of Products & Raw Material Consumption ..............................................35
2.7 Process technology and Manufacturing Process Description ..............................36
2.7.1 Manufacturing Process .........................................................................................37
2.7.2 Manufacturing Procure: ........................................................................................40
2.7.3 Mass Balance.........................................................................................................41
2.7.4 Scrap Purchase Management ...............................................................................42
2.7.5 Standard Procedures for handling Scrap cleaning/sorting process for removal
of foreign materials ..........................................................................................................43
2.7.6 Technology Advantage of Induction Furnace: ....................................................43
2.7.7 Solvent Management Plan ....................................................................................46
2.8 Raw Materials Requirement with Storage and Transportation Details .................46
2.9 Project Description ...................................................................................................46
2.9.1 Details of Project Land and Plant Layout Capital................................................46
2.9.2 Electricity/Power ...................................................................................................47
2.9.3 Water ......................................................................................................................48
2.9.4 Fuel .........................................................................................................................48
2.9.5 Manpower ..............................................................................................................48
2.9.6 Plant Machineries & Utilities .................................................................................49
2.9.7 Potential and Proposed Control Measures ..........................................................49
2.9.8 Water Pollution ......................................................................................................49
2.9.9 Air Pollution ...........................................................................................................54
2.9.10 Process Emission ..............................................................................................54
2.9.11 Flue Gas Emission .............................................................................................54
2.9.12 Fugitive Emissions ............................................................................................56
2.9.13 Solid/Hazardous Waste .....................................................................................57
2.9.14 Noise & Vibration ...............................................................................................58
2.10 Analysis of alternatives (technology & site) ...........................................................58
27 | P a g e
2.11 Fire & Safety details ..................................................................................................59
2.12 Odour Source and its Control ..................................................................................59
2.13 Records of any legal breach of Environmental laws & GFR1963 ..........................59
2.14 Incident occurred in last 3 years .............................................................................61
List of Tables Table 2-1-Environmental Aspects ..........................................................................................34
Table 2-2 – List of industries ..................................................................................................34
Table 2-3- Capital Cost of Proposed Project .........................................................................35
Table 2-4-Details of Products .................................................................................................35
Table 2-5-Details of Raw Materials .........................................................................................36
Table 2-6-Area Break Up .........................................................................................................46
Table 2-7-Details of Power Consumption ..............................................................................47
Table 2-8- Fuel Consumption Details ....................................................................................48
Table 2-9- Details of Manpower ..............................................................................................48
Table 2-10- Details of Plant Machineries ...............................................................................49
Table 2-11- Stream wise fresh water consumption & wastewater generation ....................50
Table 2-12-Details of Effluent Treatment Units .....................................................................52
Table 2-13-Details of process emissions ..............................................................................54
Table 2-14- Details of Flue Gas Stacks ..................................................................................55
Table 2-15-Details of Hazardous waste .................................................................................57
Table 16 – Show cause notices & its compliance status .....................................................59
List of Figures Figure 2-1-Google Map Showing 5 & 10 km radius from the Project Site ...........................29
Figure 2-2- Google Map Showing Project Site ......................................................................30
Figure 2-3-Plant Layout ..........................................................................................................31
Figure 2-4 - Water Balance Diagram ......................................................................................51
Figure 2-5-Schematic Flow Diagram of Effluent Treatment Plant ........................................53
Figure 2-6-Schematic Diagram of Industrial Effluent Management: ....................................53
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
28 | P a g e
2 CHAPTER 2 DESCRIPTION OF THE PROJECT
2.1 Type of Project
M/s. Rajputana Stainless Ltd. is large-scale unit located at .The proposed project is about the
expansion in Iron & Steel billet production capacity of 90,000 MTPA from 28,000 MTPA.
The stated project will be carried out within the premises. Thus, this is a brown field project
where unit intends to manufacture products covered under Category 3(a)-B as per EIA
Notification of Ministry of Environment & Forest (MoEF & CC), dated.14-Sep-06.
2.2 Need for the project
The demand for products intended to be manufacture is increasing in the country. By setting
up this unit M/s. Rajputana Stainless Limited will be able to meet the demand of various
products locally. One of the most useful and versatile material, steel is considered to be the
backbone of human civilization. As the steel industry has tremendous forward and backward
linkages in terms of material flow, income and employment generation, the growth of an
economy is closely related to the quantity of steel used by it.
Steel has been one of the oldest industrial sectors in India. It has also been the first to get
liberalized and controls lifted partially in 1991. There have been massive capacity additions by
all steel majors and several new groups made foray into primary and secondary steel market in
the first phase of liberalization in early 90s. The major costs in steel making are the costs of
Iron Ore, Metallurgical Coke, Limestone, Coal and Power. While the country is rich in iron ore
and limestone, its quality of coal is poor and power costs are high. The industry enjoys
inherent advantages in terms of availability of raw material and cheap labour.
India is the 3rd largest producer of steel in the world accounting for production of 89.58 million
tons of crude steel in the Calendar year 2015. It also holds the third position in consumption of
steel. Thus there is great potential of steel industry in India. Honourable Prime Minister Shri
Narendra Modi has envisaged the growth of steel sector to attain a production capacity of 300
Million Tonnes by 2020, hence in order to achieve this capacity, it is essential to create the
facilities based on local resources to produce steel.
In view of these facts, the proposed project is envisaged as an Integrated Steel Plant with
Coke Oven plant, Blast Furnace, E.O.F., Ladle Furnaces, Vacuum Degassing, Billet/Bloom
Continuous Casting Machine, Wire Rod cum Bar Mill and Captive Power Plant. All these
production technologies make the project a better energy efficient project due to which a
substantial amount of Green House Gas (GHG) emissions would be avoided or reduced than
the baseline emission.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
29 | P a g e
2.3 Project Location
The proposed project is to be located at 213 - Madhwas, Halol Kalol Road, Taluka : Kalol,
District: Panchmahal – 389330, Gujarat It is situated at Latitude: 21° 77’ 99.08” N & Longitude:
72° 82’ 23.10” E. Nearest major city is Halol which is 7.3 km far from the project site in direction
SSE.
Google map showing surrounding areas in 10 km radius from the project site are given as
Figure 2-2.
(Source: Google Earth) Figure 2-1-Google Map Showing 5 & 10 km radius from the Project Site
Sr. No. Corners Latitude Longitude
1. A 22°34'10.10"N 73°27'29.43"E
2. B 22°34'6.19"N 73°27'29.49"E
3. C 22°34'6.02"N 73°27'21.53"E
4. D 22°34'9.80"N 73°27'20.74"E
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
30 | P a g e
(Source: Google Earth) Figure 2-2- Google Map Showing Project Site
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
31 | P a g e
Figure 2-3-Plant Layout
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
32 | P a g e
2.4 Site Photographs
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
33 | P a g e
2.5 Justification of Site Selection
The unit is located at 213/1 ,213/2 ,212/1 ,212/2 ,184 ,185 ,186/1 ,183/1 ,183/2 ,183/3 ,182/1, 214/1,
214/3 - Madhwas, Halol Kalol road, Taluka: Kalol, Dist. Pachmahal – 389330, Gujarat, India and site
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
34 | P a g e
selection was guided by many factors like infrastructure, availability of land, water sources, fuel,
transportation, power availability etc.
Proposed project site is approximately 20 m east away from State Highway No. SH-75 which is well
connected to other state highways as well as national highway. Transport facilities for all over India
are sound at project site.
It is an expansion project/ brown field and thus no displacement of population will take place. There is
no protected area notified under the Wild Life (Protection) Act (1972) &Eco sensitive area notified
under the Environment (Protection) Act- 1986 exists within 10 km radius areas from the project site.
The requisite skilled, semi-skilled and unskilled labour from local area would be easily available.
Salient features in the surroundings area of the site as well as infrastructure availability with
approximate aerial distance and direction are as given below:
Table 2-1-Environmental Aspects
Sr. No. Features Particulars
1 Nearest village Alindra -1.96 KM (NE)
2 Nearest Town/City Halol - 7.3 KM
3 Nearest Railway Station Derol Railway Station - 5.0 KM (W)
4 Nearest Hospital Community Health Centre Kalol -3.0 KM
5 Nearest Highway SH-75 (20 meter East)
6 Nearest Airport Vadodara Airport -39 KM (SSW)
8 Nearest Water Body Mesri River -1.0 KM (S) [Inundation River]
9 Ecologically sensitive zones
within 10 Km Not Applicable
10 Historical/ Archaeological places Not Applicable
11 National Parks/Wild Life
Sanctuary Not Applicable
12 Seismic Zone Seismic Zone III
Table 2-2 – List of industries
Sr/No. Name of Industry Distance & Direction Type of Industry
1. Amartara Pvt. Ltd. 0.2 Km, NW PVC film manufacturers
2. Core Drilling Chemicals 0.47 Km, N Chemical Industry
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
35 | P a g e
3. Endurance
technologies ltd. 0.33 Km, SE
Aluminium dye casting
manufacturers
4. Varroc Engineering 0.53 Km, S Automotive component
manufacturers
5. Virtuous core &
engitech 0.60 Km, E Engineering industry
2.6 Size or Magnitude of the project
The total land area of the plot is 43000 m2
The breakup of the Total Capital Cost is given in Table 2.4 and the time of completion of the project after getting EC is for 6-8 month.
Table 2-3- Capital Cost of Proposed Project
Sr.
No.
Particulars
Cost (In Rupees)
Existing Proposed Total
1. Land Plot At…(Based On Land
Acquisition Agreement) 10129041 0/- 10129041
2. Factory Building (Based On
Estimated By Engineer) 101755008 1, 50,00,000/- 116705008
3. Plant & Machinery (Based On
Quotation From Various Suppliers) 858555520 2, 00, 00,000/- 878555520
4 Others 13386857 0/- 13386857
Total 983826426 3,50,00,000/- 1018776426
2.6.1 Details of Products & Raw Material Consumption
2.6.1.1 Details of Products:
The unit intends to manufacture Iron & Steel billet with the total capacity of 90,000 MTPA. The details
of proposed products along with the capacity are listed below in Table
Table 2-4-Details of Products
Sr.
no.
Name of
the
Products
CAS no. /
CI no.
Quantity (MT/Annum)
End-use of the
products Existing Proposed Total
1 SS.MS &
Alloy
Steel(AS)
Ingots and
Billets
SS-65997-19-5 20000 20000 48000 SS-Chemical
Industries,
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
36 | P a g e
2
SS.MS &
Alloy Steel
(AS) Bars
AS-7440-44-0 5000 31000 36000 Furniture Industries
Engg.
3 Bright Bars MS-7429-90-5 3000 3000 6000
Utensil & Exports
AS-Engg &
Machinery
Industries MS-
Construction &
Engineering
Total 28000 62000 90000
2.6.1.2 Details of Raw Materials:
The raw materials used for the production are given in Table 2-6.
Table 2-5-Details of Raw Materials
2.7 Process technology and Manufacturing Process Description
The Iron & Steel billet products are manufactured by proven process optimally available from
academic sources. The Best Available Technology for the said products is through the
production experience by technocrats. The Induction furnaces powered by energy efficient
furnaces are adopted as the best available technology for manufacturing process. The melting
Sr.
no.
Name of the
Products
Name of the Raw
Materials
CAS no. / CI
no. of raw
materials.
Quantity
MT/Annum
Existing Proposed Total
1 MS/AS/SS
Billets/Ingots
Waste & Scrap NA
23500 MTA 32900 MTA 56400 MTA
Nickel 7440-02-0
Chrome 7440-47-3
Molybdum 7439-98-7
Silicon 7440-21-3
Silico Manganese 77439-93-5
Vanadium 7440-62-2
Aluminium 7429-98-7
2 MS/AS/SS MS/AS/SS
Billets/Ingots
AS-7440-44-0
5263 MTA
32630.6
MTA
37893.6
MTA
3 MS/AS/SS
Bright Bars MS/AS/SS Bars MS-7429-90-5 3050 MTA 3050 MTA 6100 MTA
Total 31813 MTA 68580.6
MTA
100393.6
MTA
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
37 | P a g e
of metals is through furnaces achieving the best thermal efficiency. The Company has adopted
the best available technology and also formulated the Energy Saving Policy statement.
2.7.1 Manufacturing Process
The main raw material in Billet Manufacturing process is mild steel scrap which is
procured from local and international markets.
The scrap is mixed in pre-determined proportions in the scrap yard and fed to the
Furnaces in charging buckets and melted by Electric Arc using Graphite Electrodes.
The molten metal is processed through Argon Oxygen Decarburization (AOD)process
where in gases such as Argon and Inert Oxygen are passed through the molten metal to
remove the impurities from it and then the molten metal is further refined by adding Ferro
alloys and other fluxes to bring it to the required standard specifications.
Liquid metal samples are analyzed at frequent intervals to ensure quality if the product
as per I.S.
The molten steel is tapped at the required temperature to the pre-heated ladles.
Steel ladles are equipped with latest slide gate opening system. Temperature of the
molten metal in the ladle is measured to ensure correct temperature at the continuous
casting machine.
The liquid metal is then poured from ladle to the tundish and then to the water cooled
copper mold on continuous casting machine.
The billet formation takes place by solidification of the molten steel due to water cooling.
Billets of 100 mm square comes out of the continuous casting machine which are cut to
the required length by gas cutting and are again subjected to stringent quality inspection
and stacked according to color codes specified by BIS.
The Billets are further rolled and converted into constructional steel of various Sections
at Rolling Mills.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
38 | P a g e
Process flow diagram – Billets
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
39 | P a g e
Process Flow Diagram of Bar:
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
40 | P a g e
2.7.2 Manufacturing Procure:
Basic raw materials i.e. Iron/steel Scrap are sourced from other manufacturing units with scrap as a
by-product and suppliers & vendors of market. Inspection of incoming raw material is conducted in
the inspection yard and rejection are returned to the vendors and accepted material is stored in the
respective raw material yard in order to make the particular lot / batch as per the demand of the
market. The scrap is then charged into the Induction Furnace. The scrap in the induction furnace is
heated till its 1600 degree Celsius. At this temperature, the scrap is now converted into liquid mass
form and during this process the slag and other impurities/ foreign materials are being removed
which is floating on top of the melted mass. Rich minerals such as aluminium, silicon, manganese, etc
are added at this stage to make the metal of the desired grade at this stage. Liquid mass is
transferred to ladle followed by Continuous Casting Machine where hot billets are formed. After
cooling the finished product i.e. Iron & steel Billets are shifted to storage and then it goes to the rolling
mill for further process.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
41 | P a g e
2.7.3 Mass Balance
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
42 | P a g e
2.7.4 Scrap Purchase Management
As MS scrap is a by-product, it's been procured from various manufacturers like casting,
forging, machining and other units. Therefore, the scraps procured from these factories are of
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
43 | P a g e
top quality and is clean and ready to be used. The ratio of this would be 90%. The material
procured from small to medium scrap collectors has some dust and other undesired materials
in them like plastic, rubber and paint. The quantity of the same is negligible and is cleaned in
the scrap cleaning phase.
2.7.5 Standard Procedures for handling Scrap cleaning/sorting process for removal of
foreign materials
Unskilled labours are employed directly or indirectly in the company to segregate the 20% scrap
procured from small & medium collectors of scrap. The steps of the same go as follows: (SOP)
A. Scrap is to be primarily inspected in vehicle before unloading.
B. The scrap to be unloaded into the observation area if the material is found as per
standards. If not, return the material.
C. Detailed observation is to be made and all the undesired material to be identified and
red tagged.
D. Identified undesired material to be removed and stored in waste storage area and the
clean scrap should be stored in the respective raw material storage yard space
depending on the size and nature of the material.
E. The waste storage area is to be cleaned and the undesired material to be sold back into
the market on a regular basis.
All raw materials like Iron ore, MS scraps will be received and stored in respected closed storage
shed. Scrap from ship is low carbon and good quality. All raw scraps are separated by magnetic
separator to remove foreign particle. Separated scrap is manually examined for removal of
painted, oily and dirty residual scrap. Such scrap is sorted out. After sorting scrap will be sent for
cleaning section where scrap will be cleaned manually by wire brush and compress air.
Separated scrap is then crushed to make homogeneous block. These block of metal finally feed
to induction furnace for melting. Maximum one month raw material inventory will be maintained in
the plant for continuous operation.
2.7.6 Technology Advantage of Induction Furnace:
Technology provides Iron shunts which cover up to 60% of the outside of the coil to ensure
adequate control of the magnetic field and direct mechanical support of the coil. Furnace coil is
manufactured from heavy wall copper tubing to provide strength and large water paths to
ensure adequate cooling to the back of the refractory lining
Furnace coils incorporate low loss stainless steel cooling coils above and below the power coil
to ensure adequate cooling to the back of the refractory lining through the full height. Low
conductivity stainless steel is used to construct the cooling coils to reduce the amount of energy
induced in to cooling section thereby increasing the energy available for melting and reducing
the losses to cooling system. Spacers placed between the coil turns in 16 positions around the
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
44 | P a g e
circumference of the coil ensure rigidity of the coil in the vertical and provide a means for the coil
to “breath”. The coils ability to breath ensures the free passage of moisture from the refractory
lining during the sinter cycle.
Coils are insulated with a proprietary material. The use of this material allows operating with
elevated coil voltages. High coil voltages mean lower currents for the same kilowatt draw
resulting in lower electrical loses. It also means higher voltages are induced into the charge
which enhances the “contact” within the charge levels of power draw.
The power supplies are built into steel enclosures. This ensures all the components,
interconnecting cables and bus bars are installed in the factory prior to delivery. This design
enables to simplify the installation of the equipment and shorten the onsite installation and
commissioning period. This construction ensures the power supply sits on a flat floor and does
not require any trenches.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
45 | P a g e
Induction furnaces offer certain advantages over other furnace systems. They include:
Higher Yield. The absence of combustion sources reduces oxidation losses that can be
significant in production economics.
Faster Startup. Full power from the power supply is available, instantaneously, thus
reducing the time to reach working temperature. Cold charge-to-tap times of one to two
hours are common.
Flexibility. No molten metal is necessary to start medium frequency coreless induction
melting equipment. This facilitates repeated cold starting and frequent alloy changes.
Natural Stirring. Medium frequency units can give a strong stirring action resulting in a
homogeneous melt.
Cleaner Melting. No by-products of combustion means a cleaner melting environment
and no associated products of combustion pollution control systems.
Compact Installation. High melting rates can be obtained from small furnaces.
Reduced Refractory. The compact size in relation to melting rate means induction
furnaces require much less refractory than fuel-fired units
Better Working Environment. Induction furnaces are much quieter than gas furnaces,
arc furnaces, or cupolas. No combustion gas is present and waste heat is minimized.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
46 | P a g e
Energy Conservation. Overall energy efficiency in induction melting ranges from 55 to 75
percent, and is significantly better than combustion processes.
2.7.7 Solvent Management Plan
There is no solvent used in the process for any of the above products. There is no VOC source
from the manufacturing process and raw materials being used and proposed to be used in the
operation.
2.8 Raw Materials Requirement with Storage and Transportation Details
Mostly all raw materials are available in local market so, they will be purchased from local
market. The convenient transportation medium is used for the transportation of raw materials.
2.9 Project Description
2.9.1 Details of Project Land and Plant Layout Capital
M/s. Rajputana Stainless Ltd. has obtained project land in Halol. Land possession document
and non-agricultural (NA) land certificate is enclosed as Annexure. Total available land area of
premises is 43000 m2, out of which 14200 m2 (33.02%) area will be developed for greenbelt. It
may be noted that no additional land will be required for proposed project. Detailed break-up of
land area is given in Table 2-9 and Plant Lay-out is shown in Figure
Table 2-6-Area Break Up
Sr/No. Description Existing Area Proposed Area Percentage (%)
1. Canteen 84.36 - 0.196186
2. Security cabin 72.20 - 0.167907
3. Weigh bridge area 89.33 - 0.207744
4. Admin building 159.10 - 0.37
5. Raw material storage area-2 - 239.44 0.556837
6. Parking area - 163.17 0.379465
7. LPG gas plant 54.56 - 0.126884
8. Production area – 1 722.0 - 1.67907
9. Production area – 2 899.56 - 2.092
10. Raw material storage area - 4 264.25 - 0.614535
11. Raw material storage area – 3 419.025 - 0.974477
12. Production area – 4 265.86 - 0.618279
13. Raw material storage area – 1 - 95.89 0.223
14. DG set area - 44.10 0.102558
15. Pump house area - 39.20 0.091163
16. Cooling tower - 19.72 0.04586
17. RCC water tank area - 12.95 0.030116
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
47 | P a g e
18. RO system area - 22.88 0.053209
19. Scrap yard storage area – 1 185.70 - 0.43186
20. Air & water pollution control
system area
385.70 -
0.896977
21. Scrap yard storage area – 2 150.48 - 0.349953
22. Hazardous waste storage area –
2
192.28 -
0.447163
23. Hazardous waste storage area –
1
90.48 -
0.210419
24. Production area – 6 424.71 - 0.987698
25. Storage area - 121.67 0.282953
26. Toilet existing area - 24.00 0.055814
27. OBC Existing area 262.73 - 0.611
28. Finished goods area – 2 - 1238.30 2.879767
29. Production area – 8 2357.70 - 5.483023
30. Finished goods area – 1 - 1014.37 2.359
31. Production area – 5 472.59 - 1.099047
32. Raw material storage area – 3 - 319.59 0.743233
33. Storage area – 1 - 34.64 0.080558
34. Storage area – 2 - 103.23 0.24007
35. DG set and Electric panel area –
1
- 106.20
0.246977
36. Production area – 3 3295.95 - 7.665
37. Production area – 7 1730.61 - 4.024674
38. Toilet area 31.95 - 0.074302
39. Rest area - 119.14 0.27707
40. Greenbelt 500 13700 33.02
41. Open area 12459 - 28.97442
Total 43000 m2 100 %
There are requirement of resources like water, power, fuel, manpower, plant & machineries,
utilities etc. Details of requirement of such resources for project are described in subsequent
sections under respective headings.
2.9.2 Electricity/Power
Total power requirement for the project will be about 6000 KVA which will be procured from
Madhya Gujarat Vij Company Ltd. (MGVCL).
Table 2-7-Details of Power Consumption
Sr. No. Source Total
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
48 | P a g e
1. MGVCL 6000 KVA
2. D.G. Set 1000 KVA x 1 Nos
2.9.3 Water
For the proposed project, water is required/ used for domestic activities, greenbelt development
and industrial operations. For the project, water is required for cooling, domestic activities, and
greenbelt development and utility operations. Total water requirement after expansion will be
128 KLD which will be fulfilled by Borewell water.
2.9.4 Fuel
HSD is proposed to be used for heating furnace of rolling mill (Capacity- 15 MT). LDO will be
used as fuel in D. G. Set. The D.G. set shall be operated only during power failure and
emergency. A D.G. set of capacity 1000 KVA has been proposed which will be sufficient to meet
the emergency power requirement for the proposed project. The fuel consumption for the
proposed project is anticipated to be as follows:
Table 2-8- Fuel Consumption Details
Sr. No. Fuel Quantity
1 HSD 200 Litre/Hr
2 LDO 150Litre/Hr.
2.9.5 Manpower
The details of the manpower requirement are anticipated as follows:
Table 2-9- Details of Manpower
Description
Management
Staff
Supervisory
Staff Clerks Worker Total
E P E P E P E P E P
Administration 07 02 04 01 10 03 350 133 375 139
Plant (Production &
other service
personnel)
10 03 15 08 0 0 0 0 21 11
Total 17 05 19 09 10 03 350 133 546
Note: E: Existing
P: Proposed
T: Total
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
49 | P a g e
2.9.6 Plant Machineries & Utilities
List of plant machineries required for the proposed project is given in Table
Table 2-10- Details of Plant Machineries
Sr. No.
Equipment Quantity
Type Capacity Existing Proposed
1 Induction Furnace
01 Nil Medium
Frequency induction furnace
15 MT
2 A.O.D 02 Nil - 25 MT
3 C.C.M 01 Nil - 25 MT
4 Cranes 03 01 EOT Existing –50 MT/ 10
MT/ 30 MT Proposed - 40 MT
5 Rolling Mill 01 Nil - 18 inch
6 Gas Plant 01 Nil - To manufacture
oxygen and nitrogen
7 Wind Mills for
Power Generation
03 Nil Suzlon Co. 0.6MW+1.5MW+2.1
MW
2.9.7 Potential and Proposed Control Measures
There are possibilities of pollution from the proposed project due to domestic & industrial
wastewater generation & disposal, gaseous emission from process, flue gas emission from
utilities, fugitive emission, noise and hazardous waste generation &disposal. The said probable
pollutions are described below under respective heading with necessary details and mitigation
measures.
2.9.8 Water Pollution
The source of water is Bore well. Total fresh water requirement for the proposed project after
expansion will be 95.00 KLD out of which 25.0 KLD will be used for domestic use and 70 KLD for
industrial purposes. About 20 KLD of sewage will be generated, which will be disposed through
STP. Total water requirement for Gardening is 33 KLD, Hence 33 KLD of waste water generated
from process will be treated and reused for gardening.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
50 | P a g e
2.9.8.1 Water Balance
Domestic Wastewater: About 20 KLD of sewage will be generated, which will be disposed
through STP.
Industrial Wastewater: Total 38 KLD will be generated from industrial wastewater.
Table 2-11- Stream wise fresh water consumption & wastewater generation
Sr.
No. Purpose
Water Consumption, KLD Wastewater Generation, KLD
Existing Proposed Total Existing Proposed Total
1 Domestic 10.0 15.0 25.0 8.0 12.0 20.0
2 Gardening/Dust
suppression - - - 0.0 0.0 0.0
3 Industrial
a. Process 5.0 20.0 25.0 3.0 20.0 23.0
b. Washing 5.0 10.0 15.0 5.0 7.0 12.0
c. Cooling 10.0 20.0 30.0 1.0 2.0 3.0
Total (Industrial) 20.0 50.0 70.0 9.0 29.0 38.0
Total (1+2+3) 30.0 65.0 95.0 17.0 41.0 58.0
*Total water requirement for Gardening is 33 KLD, Hence 33 KLD of waste water
generated from process will be treated and reused for gardening.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
51 | P a g e
Figure 2-4 - Water Balance Diagram
2.9.8.2 Industrial Wastewater Treatment
Details of Effluent Treatment Plant
M/s. Rajputana Stainless Ltd. shall have an Effluent treatment plant consisting of primary,
Secondary & Tertiary units with the capacity of treating effluent up to 38 KLD. The treated
effluent shall be reused for gardening purpose. The details of ETP are as follows.
As can be seen from the manufacturing process of the course of waste water generation
is from pickling process and cooling blow-down along with softening regeneration water.
Stream from rinsing of pickling bath will be collected in separate acid proof brick lined
collection cum equalization tank.
The stream will be then subjected to physico –chemical treatment for precipitation of
metallic salts in its hydroxide form through raising the pH to @ 9 to 9.5.
The physico chemically treated mass will be pumped to plate and frame type filter-press
to remove the hydroxide of metals.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
52 | P a g e
The wet cake from the filter press will be periodically removed and it will be dried and
stored in a sludge storage area for the final disposal to authorized TSDF site.
The clear supernatant from the filter press will be collected in intermediate treated water
sump and where stream or cooling bleed-off along with softening regeneration water will
be received and pH of waste water will be corrected to neutral by addition of mineral
acid, in case of need.
The final neutralized treated effluent will be then utilized as makeup water of direct
cooling of sections of rods from rolling mill.
Table 2-12-Details of Effluent Treatment Units
Sr.
No. Name of Unit Nos. Effective Volume
1 Collection tank 01 5.0 x 2.5 x 3.5m depth
2 Dosing tank 02 1 m3 each
3 Hopper Bottom Settling Tank (Primary) 01 1.5 x 1.5 x 3.05 m depth
4 Aeration Tank with MBBR media 01 3.0 x 3.0 x 4.5 m depth
5. Hopper Bottom Settling Tank
(Secondary) 01 1.5 x 1.5 x 3.05 m depth
6. Final Collection tank (Treated) 01 1.5 x 1.5 x 2.0 m depth
7. Sludge Drying Beds 03 3.0 x 2.0 x 1.0 m each
8. Sand/Activated carbon filter 02 1.0m dia x 2.0m Height each
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
53 | P a g e
Figure 2-5-Schematic Flow Diagram of Effluent Treatment Plant
The Industrial effluent generated from unit will be 38 KL/day. Hence, the suitability of quality and
quantity of process effluent re-using into gardening. The unit is proposing to maintain the
adequate storage capacity to handle for five days generation of effluent from Iron & Steel Billets
manufacturing. The schematic flow diagram is shown here for process effluent management.
Figure 2-6-Schematic Diagram of Industrial Effluent Management:
The effluent quality of process effluent from Utilities is summarized below in Table
Sr. No Parameters Primary Treatment
Secondary Treatment
Tertiary Treatment
Final
Inlet Outlet Inlet Outlet Inlet Outlet
1. pH 5.9 7.2 7.2 7.3 7.3 6.9 6.9
2. TDS 713 950 950 940 940 600 600
3. Suspended Solids
85 45 45 35 35 20 18
Effluent Generation from
industrial processes
37 KL/Day: Low TDS
Directly reused for gardening
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
54 | P a g e
4. COD 405 235 235 24 24 16 15
5. BOD 78 58 58 18 18 12 11
6. NH-N 3.50 0.50 0.50 ND ND ND ND
7. Heavy Metal 8.5 0.5 0.5 0.5 0.5 0.5 0.5
NOTE
Alkali Dosing up to pH 9 to 10 than add and PAC up to pH 7 to 8 than settling and separate sludge if any
Prior sludge process adopting MBBR Technology
Sand and carbon filter system
Details of hazardous wastes enclosed herewith (Schematic)
2.9.8.3 Spillage & Waste streams Management:
The spillages from Diesel storage will be prevented by dyke wall. The spillage and leakages
from pumps, pipe assembly and storage tank will be transferred back to storage tank or day
tank.
2.9.9 Air Pollution
In this proposed project, process gas and flue gas emission will be the main source of air
pollution. There will be chances of fugitive emission due to raw material handling and
transportation and manufacturing activity.
2.9.10 Process Emission
Process emissions are from AOD unit.
Table 2-13-Details of process emissions
Sr. no.
Specific Source of emission (Name of the Product & Process)
Type of emission
Stack/Vent Height (meter)
Air Pollution Control Measures (APCM)
1 Stack Attached to AOD unit
Particulate matter
36 Hood + heat exchanger followed by Bag filter
2.9.11 Flue Gas Emission
Gaseous emissions from Heating furnace of rolling mills anticipated. HSD shall be used as fuel.
The other gaseous emission from the proposed project is the flue gas emission from the stack
attached to D. G. Set. LDO Will be used as fuel for D. G. Set. However, the D. G. Set shall be
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
55 | P a g e
used during emergency purposes only. The table below shows the sources of the air pollution
with the air pollutant emitted from the sources.
Table 2-14- Details of Flue Gas Stacks
Sr. no.
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel
MT/Day
Type of emissions i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
1 Heating furnace of rolling mill
36 HSD 200L/Hr
PM, SOx, NOx
Bag Filter
2 D.G. Set (1000 kVA)
18 LDO 150L/hr Acoustic Enclosure with stack
2.9.11.1 Details of Air Pollution Control Measures
Details of scrubber for pickling section
Type of Scrubber
Height (in
MM)
Diameter (in MM)
Pack Column (in MM)
Media Flow Rate
(LPM)
Gas Inlet (m3)
Absorbing Media
Final Concentration
Tank Volume (in KL)
MOC
Primary 3000 300 2500 200 5.0 Water 20-24% and to be sold
10 - 15 M.S
Secondary 2000 100 1600 30 0.1 Water
10% to be taken in primary scrubber
0.5 M.S
Details of Bag Filters (APCM):
Sr. No Details Quantity
1. No of bags 528
2. Modules arrangements 4 compartments
3. Material of bags Polyester Needle Felt
4. Gas Handling Capacity 16200m3/hr
5. Inlet Concentration of dust PM10‐1600 PPM
6. Stack concentration of dust 80 PPM
7. Inlet Temperature before air cooler 200‐250°C
8. Inlet Temperature after air cooler 100‐120°C
9. On air supply 50 m3/hr
10. Length of duct line 80 m
11. Motor capacity 200 kW
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
56 | P a g e
2.9.12 Fugitive Emissions
There are two sources of fugitive emission (1) from process and (2) Vehicular emission, hence,
the suction hood on each induction furnace will be provided with duct guided to proposed
Reverse Pulse jet Bag filters to each induction furnace. The suction hood will be guided to top
of the induction furnace Crucible lid. The air above lid will be under pressure to suction hood to
control the fugitive emission beyond the work zone area.
Fugitive emission from (2) Vehicular emission due to Nos. of vehicles transportation per day
for handling raw materials and finished products, Slags, Dust bags from Bag Filters
A. Finish Goods: Equivalent vehicles per day: 10 Trucks per day
B. Raw Material: 100393 MT/ 25 MT truck = (4016 trucks/Year)/12 Months/30 Days
=11-12 Trucks per day.
C. Slag: 1 Truck load every fifteen days
D. Dust Bags:1 Truck load every fifteen days
Total Truck load estimates will be @ 22 nos. per day.
Periodical work zone monitoring will be carried out once in six months for 8 hrs and 15 minutes
for parameters PM10, SO2 and other parameters as per the Factories Act.
Sr.No. Name of
location
No. of
location
Frequency Parameter
Time
duration
of
sampling
Benefit of
workplace
monitoring
1. Raw material
storage area-1 1
Six
monthly
Total dust ,
SO2 ,NO2 8 hrs
Periodic check
of pollutants in
work place
environment to
control the
pollution and
to ensure that
working
environment is
safe to work
2. Raw material
storage area-2 1
Six
monthly
Total dust ,
SO2, NO2 8 hrs
3. Production
Area-1 1
Six
monthly
Total dust ,
SO2, NO2 8 hrs
4. Production
Area-2 1
Six
monthly
Total dust ,
SO2, NO2 8 hrs
5. Production
Area-3 1
Six
monthly
Total dust ,
SO2, NO2 8 hrs
6. Production
Area-4 1
Six
monthly
Total dust ,
SO2, NO2 8 hrs
Fugitive emission is air pollutants released to the air other than those from stacks or
vents; typically releases from leaks in plant equipment, etc. Typical sources of fugitive
emissions are,
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
57 | P a g e
- Loading and Unloading operations of materials
- Raw material, waste and product storage area
- Transfer of raw materials from the point of extraction to storage, handling and processing
locations along roads
- Wind blow across exposed surfaces – inactive or undisturbed wind erosion
- Internal roads
Following are the control measures will be adopted to prevent secondary fugitive emission,
Enclosures for all unloading operations
Spraying of water prior and during loading
Fully enclosed transfer point
Dust extraction system at all transfer points
All the internal road will be paved
Limiting the vehicles speed
Proper housekeeping
Airborne dust shall be controlled through wetting of road
Green belt will be developed in and around the plant area to arrest the fugitive emissions.
All the workers shall be provided with disposable dust mask.
2.9.13 Solid/Hazardous Waste
The details of hazardous waste generation and handling / management are given in Table
Table 2-15-Details of Hazardous waste
Sr. no.
Type/ Name of Hazardous waste
Specific Source of generation (Name of the Activity, Product etc.)
Category and Schedule as per HW Rules.
Quantity (MT/Annum)
Management of HW
Existing Proposed
Total
1 Used oil
Machinery Lubrication
5.1 0.5 MT/year
- 0.5 MT/year
Collection, Storage and sell to Authorized User
2
Discarded container/ Barrel/ Liner
From Raw Material Section
33.1 2 MT/Year
- 2 MT/Year
Collection, storage, reuse and disposal at decontamination facility or by sent to suppliers
3. Acid residue from
Pickling Section
12.1 0.1 MT/Year
0.075 MT/ Year
0.175 MT/Year
Collection, Storage, Transportation and
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
58 | P a g e
pickling Disposal at TSDF site
4. Fuel gas cleaning residue
From heating
11.4 12 MT/Year
10 MT/ Year
22 MT/Year
Collection, Storage, Transportation and Disposal at TSDF site
5. ETP Sludge From ETP 35.3 0 10 MT/Year
10 MT/Year
Collection, Storage, Transportation and Disposal at TSDF site
Solid waste generation such as slag / iron residue while using iron / steel scrap will be @
500/- MT/year. it will be re-melt (as possible) final residue be given for filling up in low lying
area, construction or roads etc/ sale to actual end users. The drums will be collected by workers
and will be stored in storage yard in stacking.
2.9.14 Noise & Vibration
Noise is generated due to the operation of D.G. set in the proposed project. However, D.G. set
is kept as standby and no other source of noise. However, unit has taken following adequate
precautionary measure for noise and vibration control.
Latest technology based low noise D.G. set with acoustic enclosures is installed.
All the vibrating parts are checked periodically and serviced to reduce the noise generation. The
equipment, which generates excessive noise, is provided with enclosures.
Proper and timely oiling, lubrication and preventive maintenance is carried out for the
machineries and equipment’s to reduce noise generation.
Ear muffs/ earplugs are also provided to the workers working under high noise area to minimize
the adverse effect on their health.
To reduce the noise generation during the transportation activities the transport contractor is
instructed to keep vehicle periodically serviced and maintain as per the requirement of latest
trend in automobile industry. Only those vehicles with valid PUC’s will be allowed for the
transportation purpose.
The transport contractor is also informed to avoid unnecessary speeding of vehicles inside the
premises.
Noise monitoring is done regularly at prominent places in the plant.
The proposed greenbelt area helps to prevent the noise pollution outside the premises.
2.10 Analysis of alternatives (technology & site)
The project proponent is in the business of manufacturing Steel Billets at premises 213/1, 213/2,
212/1, 212/2, 184, 185, 186/1, 183/1, 183/2, 183/3, 182/1,214/1,214/3 At Madhwas, Halol Kalol
Road, Taluka: Kalol, Dist. Panchmahal – 389330, Gujarat .M/s. Rajputana Stainless Ltd. has
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
59 | P a g e
already obtained the Consent to Operate for manufacturing 28,000 MTPA for Integrated steel.
Now, with the same location with advantages of vicinity to Steel markets, raw materials
availability, infrastructure facilities, connectivity with National & State Highways, the proposed
project activity will have advantage over green Field Project activity.
2.11 Fire & Safety details
Unit proposed the fire water storage tank and water hydrant system in the proposed plant area
to control the fire emergency. The PPEs will be provided to the work zone area with adequate
numbers with first aid facilities at work place and office area.
2.12 Odour Source and its Control
No specific chemical or group of chemicals is having potential odour sources.
2.13 Records of any legal breach of Environmental laws & GFR1963
The unit will be establishing in Madhwas, Halol Kalol Road, Taluka: Kalol, Dist. Panchmahal –
389330. The unit has obtained the Consent to operate approval from Gujarat Pollution Control
Board for manufacturing integrated steel of 28,000 MTPA capacity. The Compliance for CCA
conditions is addressed in Table 7.1 of Chapter 7. The valid CCA documents are annexed as
Annexure
Following were the Show cause notices received earlier and there compliance status
Table 2-16 – Show cause notices & its compliance status
Sr. No. Notices Status
1. Show cause Notice dated 08.09.2016 Replied on 20.09.2016
2. Show Cause Notice dated 27.10.2016 Replied on 28.11.2016
3. Show Cause Notice dated 17.07.2017 Replied on 16.08.2017
4. Show Cause Notice dated 08.11.2017 Replied on 26.12.2017
5. Show Cause Notice dated 23.05.2018 Replied on 29.06.2018
6. Show Cause Notice dated 12.04.2019 Replied on 01.05.2019
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
60 | P a g e
Sr. No. Reasons of Show cause Notice Remedial measures taken Status
1. During visit we examine that there
are many breakages in induction
furnace and fugitive emission.
We have repaired to Induction
Furnace Hood.
We have cleared all the fugitive
emissions.
Further we assure you that we will
take care of this in future.
Completed
2. During our visit we found that
suction hood is not in working
condition. Heating furnace of rolling
mill is not working along with the
APCM. Fugitive emission due to
pouting and tapping operation is
found out.
Suction Hood was not working
due to breakdown of motor, which
we have now repaired.
Necessary steps have been taken
to avoid the fugitive emission
during pouring and tapping
operations.
Heating furnace APMC of rolling
mill was under break-down during
visit of the GPCB officials, which
is now repaired.
Completed
3. Analysis report of Ambient air
sample shows parameters are not
within the permissible limit.
Analysis report of ambient air
samples were not found within
permissible limit, because some
of the air bags were damaged,
which are now replaced.
Completed
4. During visit, fugitive emission was
observed during pouring and
tapping operation.
Provided shed was found damaged
at certain places resulting into
fugitive emissions even outside the
shed.
Necessary steps have been taken
to avoid the fugitive emission
during pouring and tapping
operations.
Some of the sheets of the melting
shed were damaged, which are
now replaced.
Completed
5. You have no CCA for electric
induction furnace of 12MT
capacities.
Flooring of all around the pickling
are is found with acidic patches due
to leakage/spillages of acid.
We have two crucibles with one
electric panel at our factory. At a
time we can operate only one
crucible. And we have already
covered one furnace in our CCA.
If it is required, we will apply for
amendment in the CCA for
additional crucible.
Completed
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
61 | P a g e
6. During visit it was observed that :
You have not provided secondary
fume extraction system for control
fugitive emission, hence fugitive
emission is observed from furnace
and AOD converter section.
Generated slag from furnaces is
stored in huge quantity in various
area, within premises and not
disposed to TSDF as per consent
condition.
Oil spillages near compressor area
is observed and @5 drums of 200 lit
filled of waste oil/used oil and @400
lit waste oil/used oil in R.C.C.
storage tank near compressor area
are observed and disposal record of
same is not maintained.
You have not obtained CCA for
electric induction furnace of 12MT
and 15 MT capacities.
Work regarding providing
secondary fume extraction system
for control fugitive emission is in
progress and will complete within
this month.
Now slag does not falls under the
Hazardous/Solid waste.
Spillage of oil is rectified.
We have only one Induction
furnace but crucible is two having
capacity of 12 MT and 15MT, but
casting capacity is not changed.
i.e.2.5MT/Hrs.
Environmental Clearance
Application work is in progress.
Completed
2.14 Incident occurred in last 3 years
Date of incident 16.11.19
Time: - 11:15 PM
The temperature of liquid
metal: - 1400 degree
Description of Accident
On dated 16.11.19 at about 11:15 pm the metal was
transferred from induction to the ladle while transferring the
metal from ladle to the AOD the rope of the EOD broke due to
which the ladle along with the metal fell over the AOD which
resulted in the explosion of the metal
Cause Accident
The rope lost its strength and it broke which lead to ladle
instability which caused liquid metal eventually few in the pit
and coursed blast and fire.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
63 | P a g e
Table of Contents
3 CHAPTER 3 DESCRIPTION OF THE ENVIRONMENT ...................................................... 1 3 Chapter 3 Description of the Environment ..................................................................... 66
3.1 Introduction ............................................................................................................. 66 3.2 Methodology ............................................................................................................ 66 3.3 Geology .................................................................................................................... 68 3.3.1 Introduction ............................................................................................... 68 3.3.2 Geological Formations.............................................................................. 69 3.3.3 Geomorphology ......................................................................................... 70
3.3.4 Drainage ..................................................................................................... 71
3.3.5 Soils ............................................................................................................ 71 3.3.6 Climatology ................................................................................................ 72
3.3.7 Land use ..................................................................................................... 72
3.3.8 Seismicity of the Study Area .................................................................... 75 3.3.9 Ground Water Scenario ............................................................................ 75
3.3.10 Ground Water Monitoring ......................................................................... 76 3.4 Meteorology ............................................................................................................. 80 3.4.1 Met Data generated at site ........................................................................ 81 3.4.2 Wind Rose .................................................................................................. 81 3.5 Ambient Air Quality ................................................................................................. 82 3.5.1 Reconnaissance: ....................................................................................... 82 3.5.2 Methodology for air Monitoring: .............................................................. 83 3.5.3 Selection of Stations for Sampling: ......................................................... 83
3.5.4 Observations on Ambient Quality ............................................................ 87 3.6 Noise Environment .................................................................................................. 90 3.6.1 Reconnaissance ........................................................................................ 90
3.6.2 Methodology for Noise Monitoring .......................................................... 90 3.6.3 Noise Monitoring Locations ..................................................................... 90 3.7 Water Environment .................................................................................................. 93 3.7.1 Ground Water Quality: .............................................................................. 94
3.7.2 Surface Water Quality: .............................................................................. 98 3.8 Soil Environment ................................................................................................... 103 3.8.1 Methodology ............................................................................................ 103 3.8.2 Soil Sampling Locations ......................................................................... 103 3.8.3 Analysis of Soil Samples ........................................................................ 104 3.9 Biological Environment ......................................................................................... 106 3.9.1 Flora & Fauna observed in the Study area ............................................ 106 3.9.2 Wildlife and Protected Area Network:.................................................... 111 3.10 Socio Economic Environment .............................................................................. 113 3.10.1 Population and Sex Ratio ....................................................................... 115 3.10.2 Social Structure: ...................................................................................... 116 3.10.3 Literacy..................................................................................................... 117 3.10.4 Occupational Pattern .............................................................................. 118 3.11 Traffic Study........................................................................................................... 122
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
64 | P a g e
List of Tables Table 3-1 Location Details, Period and Methodology of Baseline Data Generation ...........66 Table 3-2 Lithological Description of the Area ......................................................................69 Table 3-3 Geological Formations ...........................................................................................70 Table 3-4 LULC classification of the Study area ...................................................................72 Table 3-5 Meteorological Data 2019 .......................................................................................80 Table 3-6 Ambient Air Quality Monitoring Locations ...........................................................84 Table 3-7 Ambient Air Quality Monitoring Results (24-hour average) .................................85 Table 3-8 National Ambient Air Quality Standards and Methods of Measurement ............87 Table 3-9 Ambient Noise Quality Monitoring Locations .......................................................91 Table 3-10 Applicable Noise Standards .................................................................................93 Table 3-11 Ground Water Sampling Locations .....................................................................95 Table 3-12 Ground Water Quality in the Study Area .............................................................96 Table 3-13 Surface Water Sampling Locations .....................................................................99 Table 3-14 Surface Water Quality in the Study Area ........................................................... 100 Table 3-15 Standard Water Quality Criteria ......................................................................... 102 Table 3-16 Soil Sampling Locations .................................................................................... 104 Table 3-17 Physiochemical Characteristics of Soil ............................................................ 105 Table 3-18 List of Trees in the Study Area .......................................................................... 106 Table 3-19 List of Fauna in study area ................................................................................. 109 Table 3-20 List of National Park of Gujarat.......................................................................... 112 Table 3-21 List of Sanctuaries of Gujarat ............................................................................ 112 Table 3-22 List of villages present in the study area .......................................................... 115 Table 3-23 Village-wise details of Population ..................................................................... 115 Table 3-24Social Distribution ............................................................................................... 116 Table 3-25 Literacy Rate ....................................................................................................... 117 Table 3-26 Occupational Pattern .......................................................................................... 120 Table 3-27 Traffic Study Report ........................................................................................... 123
List of Figures Figure 3-1Location Map of Study area ...................................................................................68 Figure 3-4Wind rose diagram (Jan '20 to Mar '20) ................................................................82 Figure 3-5Environment Monitoring Location Map ................................................................84 Figure 3-6Graphical representation of PM10 concentration at different locations ............88 Figure 3-7Graphical representation of PM2.5 concentration at different locations .............88 Figure 3-8Graphical representation of SO2 concentration at different locations ...............89 Figure 3-9Graphical representation of NO2 concentration at different locations ...............90 Figure 3-10Google Image showing Ambient Noise Monitoring Locations ..........................91 Figure 3-11Graphical Representation of Day time Noise Level in the study area ..............92 Figure 3-12 Graphical Representation of Night time Noise Level in the study area ...........93 Figure 3-13 Google Image showing Ground Water Monitoring Locations ..........................95
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
65 | P a g e
Figure 3-14Google Image showing Surface Water Monitoring Locations...........................99 Figure 3-15Google Image showing Soil Sampling Location .............................................. 104 Figure 3-16Forest Vegetation Map of Gujarat ..................................................................... 112 Figure 3-17Villages within 10 km radius .............................................................................. 114 Figure 3-18Population of the study area ............................................................................. 116 Figure 3-19Social profile of the study area ......................................................................... 117 Figure 3-20Population Literacy of the study area ............................................................... 118 Figure 3-21Occupational Pattern of the study area ............................................................ 122
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
66 | P a g e
3 Chapter 3 Description of the Environment
3.1 Introduction
The baseline environmental qualities of various environmental components like air, noise,
water, land, flora and fauna and socio-economic form an important and integral part of an EIA
study. The baseline data forms the basis for predicting/assessing the environmental impacts of
the proposed project. The baseline environmental quality is assessed through field surveys
within the impact zone as well as the secondary data for various components of the
environment, viz., air, noise, water,land and socio-economic.
The proposed project is to be located 213/ 1, 213/2, 212/1, 212/2, 184, 185, 186/1, 183/1,
183/2, 183/3, 182/1, 214/1, 214/3 - Madhwas, Halol Kalol Road, Taluka : Kalol, District :
Panchmahal – 389330, Gujarat. Nearest town is Halol @ 7.3 Kms.
The report presents the data collected during the sampling period of three months during post
monsoon season from January ’2020 to March’2020 by Green Circle Inc. Various
environmental components were monitored and samples were analyzed.
The baseline quality of various components of the environment viz., air, noise, water, land,
biology, meteorological and socio- economic was assessed within the impact zone of about 10
km around the proposed site. Secondary data has also been incorporated from authentic
sources viz., Government/Non-Governmental Agencies, Universities, Indian Meteorological
Department (IMD), Ground Water Board etc. Various environmental components were
monitored and samples were analyzed.
3.2 Methodology
The methodology for conducting the baseline environmental survey has been obtained from
the guidelines provided in the “EIA Guidance Manual for Synthetic Organic Chemicals Industry”
issued by the Ministry of Environment Forest and Climate Change (MoEF&CC). Environmental
attributes and frequency of monitoring is given below in table:
Table 3-1 Location Details, Period and Methodology of Baseline Data Generation
Sr.
No. Attribute Parameters
No. of
Sampling
Locations
Frequency of
Monitoring / Data
Collection
1 Meteorology
Wind speed & direction,
temperature, relative
humidity, rainfall.
Project Site Data collected from
IMD
2 Ambient air
quality
PM10,PM2.5, SO2, NOX, CO,
NH3, HC, Pb, Ozone,
Benzene, Benzopyrene,
Arsenic, Nickel.
8
24 hourly samples
twice a week. CO and
O38 hourly samples
twice a week.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
67 | P a g e
Sr.
No. Attribute Parameters
No. of
Sampling
Locations
Frequency of
Monitoring / Data
Collection
3 Noise levels Noise levels in dB(A) Leq 8
At least one day in a
season for day time
and night time on a
working & nonworking
day.
4 Surface water
quality
Physical, chemical and
bacteriological parameters
including pH, temperature,
turbidity, magnesium
hardness, total alkalinity,
chloride, sulphates, fluoride,
salinity, DO, BOD, COD,
Heavy metals, Total
coliforms, fecal coliforms,
8 Once in a Monitoring
Period.
5 Groundwater
quality
Physical, chemical and
bacteriological parameters
including pH, temperature,
turbidity, magnesium
hardness, total alkalinity,
chloride, sulphates, fluoride,
salinity, DO, Heavy metals,
Total coliforms, Fecal
coliforms,
8 Once in a Monitoring
Period.
6 Biological
environment Existing flora and fauna. Study Area
Through field visits and
substantiated through
secondary data
sources.
7 Soil
characteristics
Physical, chemical and
biological parameters to
assess agricultural and
afforestation potential
including pH, Permeability,
Electrical conductivity,
Nitrites,
Phosphates, TPH, Fluorides,
Heavy metals, SAR, Total
hydrocarbons and cat-ion
exchange capacity.
8 Once in a Monitoring
Period.
8 Land use /
Land Cover
Land use for different land
use Classifications. Study Area
Land use / Land Cover
Analysis using satellite
imaging and GIS
Technique
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
68 | P a g e
Sr.
No. Attribute Parameters
No. of
Sampling
Locations
Frequency of
Monitoring / Data
Collection
9 Socio-economic
Environment
Socio-economic
characteristics, labourforce
characteristics, population
statistics proposed amenities
in the study area and quality
of life.
Study Area
Based on field survey
and data collected from
Census of India
(Source: Google Earth Image)
Figure 3-1 Location Map of Study area
3.3 Geology
3.3.1 Introduction
Geologically the Panchmahal District comprises of Igneous & Metamorphic rocks viz. Phyllites,
Quartzites & Schists, which are seen towards the Northern Eastern & Southern part of the
district, whereas Granite & Deccan Trap Basalt is exposed in the Central, Western & South-
Eastern part of the District. Deccan Trap at some places is overlain by alluvium.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
69 | P a g e
The study area comprises of Flood plain and channel deposits of Katpur formation. Figure 3.10
depicts the general surface geology of the study area and Table 3.10 shows the lithological
description.
Table 3-2 Lithological Description of the Area
Formation Age Lithology Katpur Holocene Flood plain and channel fill deposits
Figure 3-2 Lithology of the Area
3.3.2 Geological Formations
Geologically, Panchamahal district is the manifestation of diverse geological extension from
Lower Proterozoic to Holocene with different rock types such as granitic to basalt and
limestone to alluvium. The oldest formation in the area is Aravalli Supergroup comprises of
various meta-sediments belongs to Lower Proterozoic. The post-Delhi intrusive, Godhra granite
and gneisses were intruded into older Aravalli. Both Aravallis and granite-gneiss have
undergone many orogenic movement. They are overlain at places by Lower cretaceous fluvial
and marine sequences, namely Bagh beds and Lametas. Lower Cretaceous rocks are overlain
by Deccan basalts, extrusive rock formation; occur as sporadic exposure in the form of
cappings over older rocks. The youngest formation found in the district is the alluvium, occur as
pediments, sand dunes, valley fills and flood plain as isolated patches.
Aravalli Supergroup: It comprises of Meta sediments, divided in to three major group such as:
Udaipur group, Lunawada group, Champaner group.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
70 | P a g e
The Udaipur group of rocks (Balicha formation) is exposed in the east of the Santrampur as a
narrow belt and comprises of Phyllite, mica schist and quartzite. It is overlain by Lunawada
group of rocks, which comprises of Phyllite, mica schist, meta-sub-greywacke, chlorite schist,
phyllite quartzite, protoquartzite and minor bands of dolomite.
Table 3-3 Geological Formations
3.3.3 Geomorphology
Panchmahals is a district in the western India and in the eastern part of Gujarat state. The district
can be divided into two main physiographical sub-divisions. The entire northern and eastern
portion comprising mainly of Jhalod, Dohad, Lunavada, Santampur, Limkheda and Devgad-
Bariatalukas and Jambughoda, covered by hills and forests and interspersed by plain cultivable
land. Kalol, Shehera, Godhra and Halol talukas and parts of Lunavada taluka are the plains rising
gradually to the east and is drained by rivers and interspersed by sprinklings of low hills. Below
figure shows various geomorphic units in the study area. The district has high variation in
topography which represents the diverse geological condition. The western part of the district
constitute Pediplain, composed of weathered, unconsolidated medium to coarse grained material
having gentle to moderate slope. There are scattered alluvial deposits such as flood plain, valley
fills etc formed along major river courses composed of clay, silt, sand, gravel and kankar deposits
with gentle slope. There are small scattered sedimentary and volcanic dissected hills. Pavagadh
hills, south of the district near Halol, rises abruptly to a height of 829.36m amsl and is with high
relief and steep slopes. The northern, eastern and southern part of the district have undulated
topography ranging the elevation more than 400m, constitute moderately to highly dissected hills
of Aravallis range. They have high relief and steep slopes. The area occupies by the quartzite
has an undulating topography where as phyllite and mica schist occupy broad intermontane
valley. The southern border of the district is marked by a hill range with roughly east – west and
forms a surface water divide particularly between Narmada and Mahi basin. As represented by
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
71 | P a g e
the map, kalol mostly has alluvium or alluvial plains. Nearby area has either alluvium, sandstone
or Mica phyllite schist.
Figure 3-3 Geomorphology of the study area
3.3.4 Drainage
The entire district except parts of the Jambughoda and Halol talukas, forms a part of the Mahi
river basin. The Mahi is a perennial river, enters the district from North West near Khedapa and
departs near Timba in the western part. It has a length of about 126m in the district. Almost
other rivers are namely Panam, Hadap, Goma, Kharad, Mesari, Chikni, Kun, Anas, Kali,
Machchhan Chibata and Suki river are tributary of the mahi river. Out of these, only Panam and
Hadaf are only perennial. All the rivers originate in the eastern highland and flow towards west
direction to the Arabian Sea. The flow of the water in the rivers is more during the rainy season.
The drainage is dendrite to sub-dendrite type. A dendritic drainage pattern is the most common
form and looks like the branching pattern of tree roots. It develops in regions underlain by
homogeneous material. That is, the subsurface geology has a similar resistance to weathering
so there is no apparent control over the direction the tributaries take.
3.3.5 Soils
The soil of the district can be divided broadly into three categories depending upon the source
rock, namely the phyllite, granites and basalts. The granite normally gives rise to sandy soil but
where weathering is intense, sandy loam is produced. The phyllite produced yellowish brown
light soils but where weathering is deep, black soil produced. The basaltic rock gives rise to
variegated soil depending upon the degree of weathering. The first stage of weathering
produce light soil with splinters of murum where as in the second stage medium soil of light
brown to brownish black color are produced. These medium soils are more than a meter depth.
The black cotton soils produced by intense weathering of basalts are however deep, heavy and
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
72 | P a g e
become sticky when saturated. They have high fertility value. In the study area, mostly alluvium
is present.
3.3.6 Climatology
Panchmahal district is located in east of Gujarat, comes under heavy rainfall areas in Gujarat,
having sub-tropical climate with moderately low humidity. The main seasons prevailing in the
district are (a) monsoon - mid of June to October, (b) winter - November to February, and (c)
summer – March to June. The maximum daily temperature during the year ranges from 27.7 °C
in January to 39.7 °C in May while minimum temperature ranges from 11.9 °C in January to
25.6°C in May. Maximum humidity ranges from 98.2 % to 79.6 % while minimum range is from
28 to 83.5 %. The wind speed ranges from 105.2 to 479.6 km/day, whereas evapo -
transpiration ranges from 3.4 to 11.1 mm/day.
3.3.7 Land use
The basic purpose of land use pattern and classification in an EIA study is to identify the
manner in which different parts of land in an area are being utilized or not utilized. Remote
sensing data provides reliable accurate baseline information for land use mapping, as it is a
rapid method of acquiring up to date information of over a large geographical area.
A systematic digital image interpretation approach was used to delineate the land use
classes. The present study was focused on demarcating boundaries of different land use
and land cover unit from an analysis of different types of colour registrations of land use and
land cover unit s from satellite imagery. Data used in the land use map preparation is the
satellite imagery of Indian Remote Sensing Satellite (IRS-ID, sensor P6, LISS III) of 24 m
resolution.
Table 3-4 LULC classification of the Study area
LULC Class Area in Ha. % of Area
Agriculture Land 22322.52 71.08%
Canal 277.31 0.88%
Pond/Lake 154.70 0.49%
Settlement 917.07 2.92%
Urban Built Up 714.83 2.28%
River 546.39 1.74%
Open Scrub Land 2714.69 8.64%
Fallow Land 1331.75 4.24%
Industry 2426.93 7.73%
Total 31406.19 100 %
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
73 | P a g e
71%1%
0%
3%
2%
2%9%
4%8%
LULC Classification
Agriculture Land
Canal
Pond/Lake
Settlement
Urban Built Up
River
Open Scrub Land
Fallow Land
Industry
Figure 3-4 LULC Classification
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
74 | P a g e
Figure 3-5 LULC Map of the Study Area
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
75 | P a g e
3.3.8 Seismicity of the Study Area
In seismology, a seismic zone or seismic belt is an area of seismicity potentially sharing a
common cause. It may also be a region on a map for which a common areal rate of seismicity
is assumed for the purpose of calculating probabilistic ground motions. An obsolete definition is
a region on a map in which a common level of seismic design is required. The study area falls
in Zone III in seismic zoning map of India, which is classified as moderate damage risk zone
(Institute of Seismological Research (ISR), Govt. of Gujarat. Zone III is defined as having a
maximum intensity expected of around MSK Vll, described as “Most people are frightened and
try to run outdoors. Furniture is shifted and may be overturned. Objects fall off the shelves.
Water splashes from containers. Serious damage to older buildings, masonry chimneys
collapse. Small landslides may take place.” This zone is third in severity to zone V (the
highest). Zone III is also referred to as the low to medium damage risk zone. Earthquake is
highly probable in this area primarily attributed to plate tectonic and fault rupture induced by
continuing drift of Indian plate towards the Asian plate. The tectonic elements of the area are
considered capable of generating an earthquake of magnitude 4 on Richter scale.
(Source: www.gujarat.earthquake.gov.in)
3.3.9 Ground Water Scenario
The groundwater in Panchmahal district occurs under confined and unconfined condition.
Unconsolidated shallow alluvium and weathered, jointed and fractured rock support unconfined
aquifers whereas interflow zones of basalts, inter trappean beds, encountered at depth, deep
seated fractures and shear zones give rise to confined conditions. Generally, water level
follows topographic configuration. The hot springs at Tuwa is associated with deep seated
shear zones in the granitic rock with several pegmatite intrusive. The shearing of pegmatites
indicate post pegmatite tectonic activity. As part of the hard rock, phyllites, quartzites, schists,
Figure 3-6 Seismicity of the Study Area
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
76 | P a g e
basalts, sandstone and limestones are forming aquifers. Alluvium and valley fills materials form
potential aquifers in the vicinity of rivers and piedmont zone but their distribution is patchy with
limited extension, rarely exceeding a few square kilometer in area.
3.3.10 Ground Water Monitoring
Ground water regime monitoring is the basic component of groundwater management and it is
carried out in parts of Panchmahal district through National Hydrograph Network Stations
(NHNS or NHS). NHSs are observation wells, comprising of dug wells and purpose built bore
wells – known as piezometers. There are 19 NHS and 9 piezometers as part of the NHS.
Depth to water level map of pre monsoon and post monsoon period and annual fluctuation of
water level are prepared with data of NHS for year 2012. With available data of systematic and
9 reappraisal hydrogeological surveys carried out in the district. Hydrogeological map is given
below
Figure 3-7 Hydrogrological Map of Panchmahal District
Source: CGWB
3.3.10.1 Depth to water level (Pre Monsoon)
Depth to water level map of Panchmahal district, prepared on the basis of NHS data of May
2012. In most part of the district, the water level ranged in between 5 to 10m, western part of
the Shehra and Godhra taluka has the water level range in between 2 to 5m. On the northern
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
77 | P a g e
part of the Kadana, Khanpur taluka, eastern part of the Morva and parts of the Kalol and
Ghoghamba taluka ranged in between 10 to 20m. An isolated patches in Ghoghamba
talukashown the water level in between 20 to 40m.
Source: CGWB
Figure 3-8 Depth to Water Level (Pre-Monsoon)
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
78 | P a g e
3.3.10.2 Depth to water level (Post Monsoon)
The northern and northwestern part of the district underlain by hard rock formation have water
level in range of 0 to 5m bgl while western part of Lunavada taluka of the district ranged within
5 to 20m bgl. Areas along eastern part of the district from north to south have water levels of 5
to 20m bgl. Isolated patches of 10 to 20m bgl water level observed in the southern part of the
Ghoghamba taluka, western part of the Kalol and Lunawada taluka.
Source: CGWB
Figure 3-9 Depth to Water Level (Post Monsoon)
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
79 | P a g e
3.3.10.3 Water level fluctuation
Water level fluctuation map of the district for May- November 2012 period. In the fluctuation
map, it shown rise in water level in all parts of the district. In the range of morethan 4m shown
in northern part of the Kadana and Khanpur taluka, eastern part of the Santrampur and Morva
Hadaf taluka. Rest part of the district has a rise in water level ranged within 0 to 2 m and 2 to
4m.
Source: CGWB
Figure 3-10 Water Level Fluctuation
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
80 | P a g e
3.4 Meteorology
Micro meteorological data within the study area, during air quality survey period. Meteorological
data recorded during the monitoring period is very useful for proper interpretation of the
baseline information as well as for the input to the predictive air pollutants dispersion models.
Historical data on meteorological parameters will also play an important role in identifying the
general meteorological status of the region. Site specific data can be compared with the
historical data in order to identify changes, which may have taken place due to the rapid
industrialization in the area.
The micro-meteorological parameters regulate the transport and diffusion of pollutants released
into the atmosphere. The principle variables which affect the micrometeorology are horizontal
connective transport (average wind speed and direction), vertical connective transport
(atmospheric stability and inversion conditions) and topography of the area.
The year may broadly be divided into four seasons.
Winter season : December to February
Pre-monsoon season : March to May
Monsoon season : June to September
Post Monsoon season : October to November
Table 3-5 Meteorological Data 2019
Month Maximum
temperature (Deg. C)
Minimum temperature
(Deg. C) Humidity
(%)
Wind Speed
m/s Rainfall
(mm)
January 29 17 30 2.91 0
February 31 19 29 3.19 0
March 36 24 22 3.19 0
April 42 29 22 3.63 2.6
May 42 29 30 5.02 0.4
June 39 29 52 5.44 332.8
July 32 26 73 5.08 517.4
August 29 24 86 4.41 1098.9
September 29 24 87 3.27 896.9
October 32 24 65 2.77 95.6
November 32 23 53 2.25 31.7
December 29 18 43 3.33 0
(Source: https://www.timeanddate.com/weather/)
Observation on Meteorology: The meteorological parameters play a vital role in transport and
dispersion of pollutants in the atmosphere.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
81 | P a g e
3.4.1 Met Data generated at site
Site specific climatic condition refers to weather conditions comprising of temperature, relative
humidity, wind speed, rainfall, cloud cover etc. This determines the baseline conditions and
probable impacts on environmental parameters with respect to the Project. The site specific
climatic conditions are given below in below table:
Ambient Temperature:
Monthly variations of monthly highest and monthly lowest temperature recorded are as
followed:
- Temperature (oC)
January 2020 February 2020 March 2020
Maximum 28 33 36
Minimum 15 17 20
Average 22 27 29
Precipitation:
Month Precipitation (mm)
January 2020 February 2020 March 2020
Maximum
0.0 0.0 0.0 Minimum
Average
Humidity
Month Humidity (%)
January 2020 February 2020 March 2020
Average 43 27 32
Wind Speed
Month Wind Speed (km/hr)
January 2020 February 2020 March 2020
Maximum 4.3 4.5 5.1
Minimum Calm Calm Calm
Average 3.0 3.1 3.3
(Source: https://www.timeanddate.com/weather/)
3.4.2 Wind Rose
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
82 | P a g e
Wind blowing from NE to SW direction (during Jan 2020 to March 2020).
Blowing from NE to SW
Figure 3-11 Wind rose diagram (Jan '20 to Mar '20)
3.5 Ambient Air Quality
3.5.1 Reconnaissance:
The quality of ambient air depends upon the background concentrations of specific
contaminants, the emission sources and meteorological conditions. The study on baseline
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
83 | P a g e
ambient air quality status in the project area is an essential and primary requirement for
assessing the impacts on air environment due to any proposed developmental activity.
The baseline studies on air environment include identification of specific air pollution
parameters expected to have significant impacts and assessing their existing levels in ambient
air within the impact zone. To assess the baseline status of ambient air quality in the study
area, monitoring is undertaken to ascertain the baseline pollutant concentrations in ambient air.
3.5.2 Methodology for air Monitoring:
AAQM was carried out and AAQM locations were monitored on 24 hourly average bases twice
in a week as per guidelines of CPCB and NAAQS. The conventional and project specific
parameters such as particulate matter PM10 (size less than 10 µm), particulate matter PM2.5
(size less than 2.5µm), Sulphur Dioxide (SO2) & Oxides of Nitrogen (NOx) were monitored.
3.5.3 Selection of Stations for Sampling:
Depending upon the purpose of the study IS: 5184 (part XIV) lays down various criteria for
selection of sampling stations. For EIA/ EMP, the purpose is to ascertain the baseline pollutant
concentrations in ambient air. Accordingly, the criterion can be selected to ascertain quality of
air on human settlements or environmentally sensitive areas if any located in the 10 km radius
study area.
The locations for AAQM study were selected within the 10 km radius of the proposed plant
installation. Ambient air quality was monitored on 8 locations to generate representative
ambient air quality data.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
84 | P a g e
(Source: Google Earth Image)
Figure 3-12 Environment Monitoring Location Map
Table 3-6 Ambient Air Quality Monitoring Locations
Location code
Name of Location
Distance & Direction from site
Justification Coordinates
AAQ-1 Project site - Project site 22°34'7.37"N, 73°27'25.30"E
AAQ-2 Jetpur 4.11 Km, NNE Upwind 22°36'4.51"N, 73°28'42.09"E
AAQ-3 Kandach 7.84 Km, NE Upwind 22°36'52.79"N, 73°30'54.67"E
AAQ-4 Muvala 2.05 Km, SW Downwind 22°33'9.43"N, 73°26'51.18"E
AAQ-5 Khakhariya 6.95 Km, SW Downwind 22°32'12.13"N, 73°24'0.69"E
AAQ-6 Navaria 3.84 Km, E Lateral 22°34'9.64"N, 73°29'41.26"E
AAQ-7 Chhabapura 6.83 km, SE Cross Wind 22°32'23.29"N, 73°30'55.45"E
AAQ-8 Ratanpura 6.63 Km, NW Upwind 22°35'44.63"N, 73°23'55.49"E
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
85 | P a g e
Table 3-7 Ambient Air Quality Monitoring Results (24-hour average)
Table 3-8 Ambient Air Quality Monitoring Results (24 hour Avg.)
Locations PM 10
(µg/m3) PM 2.5
(µg/m3) SO2
(µg/m3) NOx
(µg/m3) CO
(mg/m3) NH3
(µg/ m3) Pb
(µg/m3) O3
(µg/m3) C6H6
(µg/m3) As
(ng/m3)
Ni (ng/m3)
Benzo (a)
Pyrene (ng/m3)
TVOCs (ppm)
AAQ 1
Maximum 75.3 32.5 6.3 12.0 0.27 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Minimum 62.4 25.4 4.6 10.0 0.18 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Average 68.8 31.4 5.9 11.0 0.20 <20 <0.01 <20 - <5 <1.0 <0.01 BDL
98percentile 74.4 31.8 5.8 11.4 0.23 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
AAQ 2
Maximum 70.8 29.7 7.1 11.3 0.34 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Minimum 61.3 27.3 6.1 9.7 0.21 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Average 66.8 28.5 6.7 10.7 0.23 <20 <0.01 <20 - <5 <1.0 <0.01 BDL
98percentile 70.1 29.1 6.6 10.8 0.33 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
AAQ 3
Maximum 65.3 35.9 7.4 11.8 0.28 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Minimum 54.1 29.8 4.6 9.9 0.16 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Average 60.6 33.3 6.1 11.0 0.21 <20 <0.01 <20 - <5 <1.0 <0.01 BDL
98percentile 64.5 34.5 9.4 11.2 0.24 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
AAQ 4
Maximum 81.2 35.1 8.9 15.4 0.30 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Minimum 65.3 25.4 7.2 12.4 0.21 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Average 71.3 31.9 7.8 13.6 0.26 <20 <0.01 <20 - <5 <1.0 <0.01 BDL
98percentile 80.8 34.5 8.2 14.9 0.28 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
AAQ5
Maximum 87.2 37.7 9.8 17.4 0.29 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Minimum 69.3 25.4 8.1 13.9 0.17 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Average 73.2 32.0 9.1 14.6 0.23 <20 <0.01 <20 - <5 <1.0 <0.01 BDL
98percentile 86.2 37.2 9.2 17.2 0.25 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
AAQ6
Maximum 65.5 32.4 6.3 13.1 0.28 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Minimum 54.3 25.4 4.7 10.9 0.17 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Average 60.8 29.7 5.3 12.2 0.23 <20 <0.01 <20 - <5 <1.0 <0.01 BDL
98percentile 64.8 32.1 5.9 12.8 0.24 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
AAQ7 Maximum 59.8 32.4 6.5 12.0 0.22 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
86 | P a g e
Table 3-8 Ambient Air Quality Monitoring Results (24 hour Avg.)
Locations PM 10
(µg/m3) PM 2.5
(µg/m3) SO2
(µg/m3) NOx
(µg/m3) CO
(mg/m3) NH3
(µg/ m3) Pb
(µg/m3) O3
(µg/m3) C6H6
(µg/m3) As
(ng/m3)
Ni (ng/m3)
Benzo (a)
Pyrene (ng/m3)
TVOCs (ppm)
Minimum 49.5 24.1 4.2 9.5 0.15 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Average 55.5 28.6 5.0 11.0 0.19 <20 <0.01 <20 - <5 <1.0 <0.01 BDL
98percentile 59.4 31.8 6.1 11.9 0.20 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
AAQ8
Maximum 63.6 32.9 6.3 12.7 0.26 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Minimum 52.7 25.4 4.5 10.5 0.19 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Average 59.1 29.4 5.2 11.8 0.23 <20 <0.01 <20 - <5 <1.0 <0.01 BDL
98percentile 63.1 32.1 5.9 12.2 0.24 <20 <0.01 <20 <3.0 <5 <1.0 <0.01 BDL
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
87 | P a g e
Table 3-8 National Ambient Air Quality Standards and Methods of Measurement
Table 3-8 National Ambient Air Quality Standards and Methods of Measurement
S. No.
Pollutants Time
Weighted Average
National Ambient Air Quality Standards (NAAQS)
Industrial, Residential, Rural and other area
Ecologically Sensitive
Area
Methods of measurement
1 SO2 (µg/m3) 24 hours 80 80 Improved West and Gaeke method.
2 NOx (µg/m3) 24 hours 80 80 Modified Jacob & Hochheiser (Sodium Arsenite).
3 PM10 (µg/m3) 24 hours 100 100 Gravimetric Method
4 PM2.5 (µg/m3) 24 hours 60 60 Gravimetric Method
5 CO (mg/m3) 8 hours 2 2 Non Dispersive Infra-Red Spectroscopy
6 Ammonia (µg/m3)
24 hours 400 400 Indophenol Blue Method
7 Ozone (µg/m3) 8 hours 100 100 UV Photometric Chemical Method
8 Lead (µg/m3) 24 hours 1.0 1.0 AAS
9 Arsenic (ng/m3)
Annual 6.0 6.0 AAS
10 Nickel (ng/m3) Annual 20.0 20.0 AAS
11 Benzene (µg/m3)
Annual 5.0 5.0 Gas Chromatography
12 Benzopyrene
(ng/m3) Annual 1.0 1.0 Gas Chromatography
(Source: http://cpcb.nic.in/National_Ambient_Air_Quality_Standards.php)
3.5.4 Observations on Ambient Quality
3.5.4.1 Particulate Matter (PM10):
PM10 levels were ranging from 49.5 to 87.2 µg/m3. The highest PM10 level was
found at Khakhariya and lowest PM10 level were observed at Chhabapura PM10
concentration was within the NAAQS level (i.e.100 µg/m3) at all locations.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
88 | P a g e
(Source: Analysis GCI)
Figure 3-13 Graphical representation of PM10 concentration at different locations
3.5.4.2 Particulate Matter (PM2.5):
(Source: Analysis GCI)
Figure 3-14 Graphical representation of PM2.5 concentration at different locations
0
20
40
60
80
100
120
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
Maximum(µg/m3)
Minimum(µg/m3)
Average(µg/m3)
98% tile
CPCB Limit(µg/m3)
PM10
0
10
20
30
40
50
60
70
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
Maximum(µg/m3)
Minimum(µg/m3)
Average(µg/m3)
98% tile
CPCB Limit(µg/m3)
PM2.5
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
89 | P a g e
PM2.5 levels were ranging from 24.1 to 37.7 µg/m3. The highest PM2.5 level was found
at Khakhariya and lowest PM2.5 level was observed at Chhabapura PM2.5
concentration was found within the NAAQS level (i.e.60 µg/m3) at all the locations.
3.5.4.3 Sulphur Dioxide (SO2):
SO2 levels were ranging from 4.2 to 9.8 µg/m3. The highest SO2 level was found at
Khakhariya and lowest SO2 level was observed at Chhabapura. The SO2 level in all
the monitoring locations is within permissible limit i.e. NAAQS level 80 µg/m3.
(Source: Analysis GCI)
Figure 3-15 Graphical representation of SO2 concentration at different locations
3.5.4.4 Oxides of Nitrogen (NO2):
NOx levels were found ranging from 9.5 to 17.4 µg/m3. The highest NOx level were
found at Khakhariya and lowest NOx level were observed at Chhabapura. The NOx
level in all monitoring locations was under permissible limit i.e. NAAQS level 80
µg/m3.
0
10
20
30
40
50
60
70
80
90
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
Maximum(µg/m3)
Minimum(µg/m3)
Average(µg/m3)
98% tile
CPCB Limit(µg/m3)
SO2
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
90 | P a g e
(Source: Analysis GCI)
Figure 3-16 Graphical representation of NO2 concentration at different locations
3.6 Noise Environment
Noise can be defined as an unwanted sound. The definition of noise as unwanted sound
implies that it has an adverse effect on human beings and their environment. Noise can also
disturb natural wildlife and ecological system.
The objective of the noise pollution survey in the study area was to identify existing noise
sources and to measure background noise levels. The collection of baseline noise environment
data included following steps:
3.6.1 Reconnaissance
In order to measure the existing noise sources and to identify the background noise levels, the
noise pollution survey around the proposed site was carried out. The collection of baseline
noise environment data included identification of noise sources and to measure background
noise levels due to transportation and other local activity.
3.6.2 Methodology for Noise Monitoring
Noise standards have been designated as per the Noise pollution (Regulation & Control)
Rules, 2000 Notified by Ministry of Environment and Forests, New Delhi, February 14, 2000.
The ambient noise standards are presented in Equivalent noise levels (Leq.) have been
measured twice a week during study period.The measurements were carried out at each
monitoring location during day time and night time.
3.6.3 Noise Monitoring Locations
A total of 8 locations were identified for ambient noise monitoring in the study area. The noise
monitoring locations are given in Table 3.11.
0
10
20
30
40
50
60
70
80
90
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
Maximum(µg/m3)
Minimum(µg/m3)
Average(µg/m3)
98% tile
CPCB Limit(µg/m3)
NO2
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
91 | P a g e
(Source: Google Image)
Figure 3-17 Google Image showing Ambient Noise Monitoring Locations
Table 3-9 Ambient Noise Quality Monitoring Locations
Location Code
Name of Location
Leq (dB A) (Day)
Leq (dB A) (Night)
Category Distance & Direction from site
Coordinates
N-1 Project Site 69.4 65.4 Industrial - 22°34'7.37"N, 73°27'25.30"E
N-2 Jetpur 50.1 41.5 Residential 4.11 Km, NNE 22°36'4.51"N,
73°28'42.09"E
N-3 Kandach 52.4 43.4 Residential 7.84 Km, NE 22°36'52.79"N,
73°30'54.67"E
N-4 Muvala
51.0 40.2 Residential 2.05 Km, SW 22°33'9.43"N,
73°26'51.18"E
N-5 Khakhariya 49.7 37.3 Residential 6.95 Km, SW 22°32'12.13"N,
73°24'0.69"E
N-6 Navaria 53.2 42.1 Residential 3.84 Km, E 22°34'9.64"N,
73°29'41.26"E
N-7 Chhabapura 48.6 41.0 Residential 6.83 km, SE 22°32'23.29"N,
73°30'55.45"E
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
92 | P a g e
Location Code
Name of Location
Leq (dB A) (Day)
Leq (dB A) (Night)
Category Distance & Direction from site
Coordinates
N-8 Ratanpura 52.3 39.7 Residential 6.63 Km, NW 22°35'44.63"N,
73°23'55.49"E
(Source: Analysis during study period, GCI)
(Source: Analysis during study period, GCI)
(Source: Monitoring during Study period by GCI)
Observation and Discussion:
Day Time:
The noise levels varied in the study area during day time from 48.6dB(A) Leq at Chhabapura to
69.4 LeqdB(A) at Project site.
(Source: Analysis GCI)
Figure 3-18 Graphical Representation of Day time Noise Level in the study area
Night Time:
The night time noise level in the study area is in the range of 37.3 dB (A) Leq at
Khakhariya to 65.4 Leq dB (A) at Project Site. The night time noise was also within
stipulated standards of CPCB.
01020304050607080
Pro
ject
Sit
e
Jetp
ur
Kan
dac
h
Mu
vala
Kh
akh
ariy
a
Nav
aria
Ch
hab
apu
ra
Rat
anp
ura
N-1 N-2 N-3 N-4 N-5 N-6 N-7 N-8
(dB
A)L
eq
SAMPLING LOCATION
Day time Noise level in Study areaLeq (dB A) (Day)
CPCB LIMIT (dB A)Leq
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
93 | P a g e
(Source: Analysis GCI)
Figure 3-19 Graphical Representation of Night time Noise Level in the study area
Table 3-10 Applicable Noise Standards
Area Code Category of Area Limit in dB (A) Leq
Day Time Night Time
A Industrial area 75 70
B Commercial area 65 55
C Residential area 55 45
D Silence zone 50 40
(Source: Noise Pollution Rules, 2000)
Note:
Day time is reckoned in between 6 am and 10 pm.
Night time reckoned in between 10 pm and 6 am.
Silence zone is defined as areas up to 100 meters around such premises as hospitals,
education, institutions and courts. The silence zones are to be declared by the Component
Authority.
Mixed categories of areas should be declared as one of the four above-mentioned
categories by the Component Authority and the corresponding standard shall apply.
3.7 Water Environment
0
10
20
30
40
50
60
70
Pro
ject
Sit
e
Jetp
ur
Kan
dac
h
Mu
vala
Kh
akh
ariy
a
Nav
aria
Ch
hab
apu
ra
Rat
anp
ura
N-1 N-2 N-3 N-4 N-5 N-6 N-7 N-8
Night Time Noise Level Leq (dB A) (Night)
CPCB LIMIT (dBA)Leq
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
94 | P a g e
In order to establish the baseline water quality, ground water and surface water sampling
locations were selected based on availability, following standard norms and requirement.
Ground water samples were collected from the identified hand pumps and bore wells for the
characterization of water quality. Selection of surface water sampling locations has been
considered as per the utilization pattern of the villagers for domestic/ drinking purposes.
The samples collected were preserved, stored and analyzed as per standards methods of
Analysis of Water and Waste Water (APHA, 2017).
Reconnaissance Survey
Reconnaissance survey has been done for water quality monitoring in the study area. The
baseline water quality of ground water/surface water in the region is obtained by collecting
sample from villages in the area considering the 10 km radius for the baseline study.
Methodology of Monitoring
In order to establish the baseline water quality, ground water and surface water sampling
locations were selected based on availability, following standard norms and requirement.
Ground water samples were collected from the identified hand pumps and bore wells for the
characterization of water quality. Selection of surface water sampling locations has been
considered as per the utilization pattern of the villagers for domestic/ drinking purposes.
The samples collected were preserved, stored and analyzed as per standards methods of
Analysis of Water and Waste Water (APHA, 2017).
3.7.1 Ground Water Quality:
Ground water samples were collected from 8 locations during the study period and analyzed for
a number of physico-chemical parameters.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
95 | P a g e
(Source: Google Earth Image)
Figure 3-20 Google Image showing Ground Water Monitoring Locations
Table 3-11 Ground Water Sampling Locations
(Source: Analysis during study period, GCI)
Location code
Name of
location Source
Distance & direction
Coordinates
GW -1 Kalol Borewell Water 4.35 Km, NNE 22°36'27.91"N, 73°27'47.81"E
GW -2 Boru Borewell Water 5.29 Km, NNW 22°36'29.59"N, 73°25'41.87"E
GW -3 Delol Borewell Water 8.25 Km, NNE 22°37'51.50"N, 73°30'11.16"E
GW -4 Muvala Borewell Water 2.05 Km, SW 22°33'9.43"N, 73°26'51.18"E
GW -5 Khakhariya Borewell Water 6.95 Km, SW 22°32'12.13"N, 73°24'0.69"E
GW -6 Varsada Borewell Water 8.71 Km, E 22°33'47.67"N, 73°32'31.38"E
GW -7 Abhetwa Borewell Water 5.66 Km, SSE 22°31'9.82"N, 73°28'11.06"E
GW -8 Nevariya Borewell Water 7.03 Km, W 22°34'15.11"N, 73°23'18.94"E
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
96 | P a g e
Table 3-12 Ground Water Quality in the Study Area
S. No.
Parameter Units Result
Permissible Limit as Per
IS 10500:2012
Reference Method
Sample Identification GW1 GW2 GW3 GW4 GW5 GW6 GW7 GW8
1. pH --- 7.39 7.44 7.53 7.70 7.22 7.50 7.15 7.10 6.5-8.5 APHA 4500 H+
2. Conductivity µS/cm 598.4 658.4 541.5 636.9 729.2 775.3 944.6 752.3 - APHA 2510
3. Turbidity NTU <2 <2 <2 <2 <2 <2 <2 <2 5 APHA 2130
4. Color Hazen <5 <5 <5 <5 <5 <5 <5 <5 15 APHA 2120
5. Odor - Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable APHA 2150
6. Total Dissolved Solid mg/L 889 728 752 614 674 704 614 589 2000 APHA 2540 C
7. Total Suspended Solid mg/L 3 4 6 2 8 3 6 2 - APHA 2540 B
8. Sulphate mg/L 86.2 50.4 73.4 108.2 57.5 84.3 51.2 60.5 400 APHA 4500- SO42
9. Chloride mg/L 203 198 210 134 186 159 163 207 1000 APHA 4500 - Cl
10. Total Hardness mg/L 363 340 331 251 307 358 292 183 600 APHA 2340
11. Calcium as Ca mg/L 80 92.4 79.6 67.6 78.4 88 73.2 50 200 APHA -3500 Ca
12. Magnesium Mg mg/L 39.6 26.5 32.1 19.9 26.9 33,5 17.8 14.1 100 APHA 3500-Mg
13. Alkalinity mg/L 202 226 136 197 157 200 268 318 600 APHA 2320
14. Copper mg/L <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 1.5 APHA 3500-Cu
15. Zinc mg/L <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 15 APHA 3500-Zn
16. Iron mg/L <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 0.3 APHA 3500-Fe
17. Lead mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01 APHA 3500-Pb
18. Nickel mg/L <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 0.02 APHA 3500-Ni
19. Cadmium mg/L <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 0.003 APHA 3500-C
20. Calcium Hardness as CaCO3
mg/L 200 231 199 169 196 220 183 125 - APHA 3500-Ca
21. Magnesium Hardness as CaCO3
mg/L 163 109 132 82 111 138 109 58 - APHA 3500-Mg
22. Phenolic compound mg/L <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 0.002 APHA 5530
23. Fluoride mg/L 0.25 0.24 0.30 0.28 0.18 0.3 0.25 0.28 1.5 APHA 5400-F
24. Salinity mg/L 365.4 356.4 378 241.2 334.8 286.2 293.4 372.6 - APHA 2520 B
25. Pesticides P/A Absent Absent Absent Absent Absent Absent Absent Absent Absent Gas Chromatography
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
97 | P a g e
Source: Water Analysis during study period
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
98 | P a g e
Observation of ground water monitoring results:
All the samples were colorless meeting desirable norms (<5 Hazen).
All the samples meet the desirable standards (pH ranges from 7.10 to 7.70).
TDS in samples ranges from 352 mg/L (Delol) to 614 mg/L (Abhetwa). All the
samples meet the permissible limit of 2000 mg/L.
Total Hardness in the water ranges from 251 mg/L (Muvala) to 363 mg/L (Kalol).
All the samples meet the permissible limit of 600 mg/L.
Calcium content in the water ranges from 50 mg/L (Nevariya) to 92.4 mg/L (Boru)
all the samples meet the permissible limit of 200 mg/L.
Magnesium content in the water ranges from 14.09 mg/L (Nevariya) to 39.6 mg/L
(Kalol). All the samples meet the permissible limit of 100 mg/L.
Sulphate content in the water ranges from 50.4 mg/L (Boru) to 154 mg/L
(Muvala). All the samples meet the permissible limit of 400 mg/L for drinking
water.
Fluoride content in the water ranges from 0.39 mg/L (Delol) to 0.90 mg/L
(Varsada). All the samples meet the permissible limit of 1.5 mg/L for drinking
water.
Total alkalinity in the water samples ranges from 136 mg/L (Delol) to 318 mg/L
(Nevariya). All the samples are within the permissible limit of drinking water (600
mg/L).
Chlorides range from 134 mg/L (Muvala) to 210 mg/L (Delol), which are below
permissible limits (1000 mg/L).
Heavy metals like Copper, Nickel, Cadmium, Lead and Zinc are well below the
limit in all samples
Hence, it can be observed that ground water qualities in terms of various
essential and desirable characteristics are found within the limits specified by IS
10500:2012.
3.7.2 Surface Water Quality:
Surface water samples were collected from 8 locations during the study period and analyzed
for a number of physico-chemical parameters.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
99 | P a g e
(Source: Google Image)
Figure 3-21 Google Image showing Surface Water Monitoring Locations
Table 3-13 Surface Water Sampling Locations
Location Code
Name of Location
Source Distance & Direction from site
Coordinates
SW -1 Halol Lake 7.72 Km, SSE 21°45'56.68"N 72°38'40.49"E
SW-2 Kanjari Lake 7.44 Km, SSW 22°30'5.27"N, 73°28'10.98"E
SW -3 Boru Narmada Cannel 5.29 Km, NNW 22°36'30.63"N, 73°26'8.62"E
SW-4 Alindra Karad River 1.89 Km, NNE 22°34'52.37"N, 73°27'41.33"E
SW-5 Palasa Lake 7.90 Km, NW 22°35'32.03"N, 73°23'18.66"E
SW-6 Medapur Lake 4.84 Km, ENE 22°35'8.09"N, 73°30'11.15"E
SW-7 Sathrota Lake 3.80 Km, SE 22°32'45.93"N, 73°29'12.01"E
SW-8 Khakhariya Lake 6.95 Km, SW 22°32'22.92"N, 73°24'23.62"E
(Source: Analysis during study period, GCI)
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
100 | P a g e
Table 3-14 Surface Water Quality in the Study Area
S. No Parameter Units Result Reference Method Sample Identification SW1 SW2 SW3 SW4 SW5 SW6 SW7 SW8
1. pH --- 7.78 7.56 7.49 7.80 7.71 7.65 7.54 7.48 APHA 4500 H+
2. Conductivity µS/cm 243.0 213.8 735.3 367.6 520 443.0 487.6 633.8 APHA 2510
3. Turbidity NTU <2 <2 <2 <2 <2 <2 <2 <2 APHA 2130
4. Color Hazen <5 <5 <5 <5 <5 <5 <5 <5 APHA 2120
5. Odor - Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable APHA 2150
6. Total Dissolved Solid mg/L 458 439 578 639 538 488 417 412 APHA 2540 C
7. Total Suspended Solid mg/L 28 30 46 33 25 21 16 23 APHA 2540 B
8. Sulphate
mg/L 15.2 20.3 15.4 25.3 28.5 15.6 25.4 20.5
APHA 4500- SO42-
9. Chloride mg/L 109 97 143 120 156 48 112 88 APHA 4500 - Cl-
10. Total Hardness mg/L 149 128 254 335 272 271 187 153 APHA 2340
11. Calcium as Ca mg/L 34 22.4 44.8 63.6 45.6 62.8 34 41.6 APHA -3500 Ca
12. Magnesium Mg mg/L 7.77 8.74 17.25 21.38 19.19 13.85 12.39 11.9 APHA 3500-Mg
13. Alkalinity mg/L 175 130 185 240 197 210 89 108 APHA 2320
14. Copper mg/L <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 APHA 3500-Cu
15. Zinc mg/L <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 APHA 3500-Zn
16. Iron mg/L <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 APHA 3500-Fe
17. Lead mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 APHA 3500-Pb
18. Nickel mg/L <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 APHA 3500-Ni
19. Cadmium mg/L <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 APHA 3500-C
20. Total Coliform MPN/100 ml 120 230 220 150 170 230 170 230 APHA 9221 B
21. Fecal Coliform MPN/100 ml 36 40 70 35 36 70 50 100 APHA 9221 E
22. E. Coli MPN/100 ml Absent Absent Absent Absent Absent Absent Absent Absent APHA 9221 F
23. Calcium Hardness as CaCO3
mg/L 117 92 183 247 193 214 136 153 APHA 3500-Ca
24. Magnesium Hardness as CaCO3
mg/L 32 36 71 88 79 57 51 49 APHA 3500-Mg
25. Phenol mg/L <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 APHA 5530
26. Fluoride mg/L 0.64 0.70 0.58 0.43 0.49 0.75 0.54 0.71 APHA 5400-F-
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
101 | P a g e
(Source: Water Analysis by GCI Laboratory)
27. Salinity mg/L 196.2 174.6 257.4 216 280.8 86.4 201.6 158.4 APHA 2520 B
28. Pesticides P/A Absent Absent Absent Absent Absent Absent Absent Absent Gas Chromatography
29. Chemical Oxygen Demand
mg/L 6 12 10 8 10 15 8 8 APHA 5220
30. Biochemical Oxygen Demand
mg/L 2 2 4 2 3 4 3 2 APHA 5210
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
102 | P a g e
Table 3-15 Standard Water Quality Criteria
Class of
Water Designated best use Criteria
A Drinking Water Source
without conventional
treatment but after
disinfection
Total Coliforms Organism MPN/100ml shall be 50 or
less. pH between 6.5 and 8.5. Dissolved Oxygen 6mg/l
or more, Biochemical Oxygen Demand 5 days 20°C
2mg/l or less.
B
Outdoor bathing
(Organized)
Total Coliforms Organism MPN/100ml shall be 500 or
less. pH between 6.5 and 8.5. Dissolved Oxygen 5mg/l
or more, Biochemical Oxygen Demand 5 days 20°C
3mg/l or less
C Drinking water source
after conventional
treatment and
disinfection
Total Coliforms Organism MPN/100ml shall be 5000 or
less. pH between 6 to 9. Dissolved Oxygen 4mg/l or
more, Biochemical Oxygen Demand 5 days 20°C 3mg/l
or less
D Propagation of Wild life
and Fisheries
pH between 6.5 to 8.5 Dissolved Oxygen 4mg/l or more,
Free Ammonia (as N) 1.2 mg/l or less.
E Irrigation, Industrial
Cooling, Controlled
Waste disposal
pH between 6.0 to 8.5. Electrical Conductivity at 25°C
Max.2250 µS/cm .
(Source: http://cpcb.nic.in/Water_Quality_Criteria.php)
Observation on Surface water Quality: The baseline quality of water based on the results of the surface water quality
monitoring within the study area, it is observed that,
All the samples meet the desirable standards (pH ranges from 7.48 to 7.80).
TDS in samples ranges from 139 mg/L (Boru) to 478 mg/L (Delol).
Fluoride content in the water ranges from 0.23 mg/L (Alindra) to 0.80 mg/L
(Kanjari).
COD ranges from 12(Kanjari)to 40 mg/L (Palasa)
BOD ranges from 2 (Kanjari) to 10 mg/L(Palasa)
Chlorides range from 88 mg/L (Khakhariya) to 156 mg/L (Palasa)
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
103 | P a g e
3.8 Soil Environment
Soil is the most important natural resource and a natural resource is anything that comes from the
earth and is used by us. We depend on the soil for food, clothing, shelter, minerals, clay and water.
Soil is the seat of many macro and micro flora like algae, fungi, earthworms, bacteria etc. These
are very beneficial in promoting soil reactions and decomposing the organic matter by which
essential nutrients for plants are liberated. Most of the soil is made up of two main parts:
A. Tiny bits of mineral particales which come from larger rocks, and humus, which is dark brown
in color and consists of decaying remains of plants and animals.
B. Soil also contains water, air and living organisms, such as fungi, bacteria, earthworms, round
worms, insects, etc. Actually more organisms live in the soil than above it.
3.8.1 Methodology
The soil samples were collected from 8 selected locations during pre monsoon season. The
samples collected were homogeneous representative of each sampling location. At random
sub locations were identified at each location and soil samples were collected from 5 to 15 cm
below the surface. It was uniformly mixed before homogenizing the soil samples. The samples
about 500 gm were packed in polythene bags labelled in the field with location number and
sent to the laboratory for the analysis of physicochemical parameters.
3.8.2 Soil Sampling Locations
Soil sampling was conducted once during the study period of Pre-monsoon season. 8 soil
samples were collected from selected locations in the vicinity of the proposed project. For
studying soil quality environment in the study area, sampling locations were selected to assess
the existing soil conditions in and around the existing plant area representing various land use
conditions. The homogenized samples were analyzed for physicochemical characteristics.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
104 | P a g e
Source: Google image
Figure 3-22 Google Image showing Soil Sampling Location
Table 3-16 Soil Sampling Locations
Location
Code
Sampling
Locations
Distance &
Direction
Coordinates
S-1 Project Site - 22°34'7.37"N, 73°27'25.30"E
S-2 Kalol 4.27 Km, NNE 22°36'30.67"N, 73°27'47.63"E
S-3 Delol 8.25 Km, NNE 22°37'51.50"N, 73°30'11.16"E
S-4 Muvala 2.05 Km, SW 22°33'9.43"N, 73°26'51.18"E
S-5 Khakhariya 6.95 Km, SW 22°32'12.13"N, 73°24'0.69"E
S-6 Varsada 8.71 Km, E 22°33'47.67"N, 73°32'31.38"E
S-7 Maswad 5.16 Km, ESE 22°33'1.35"N, 73°30'13.36"E
S-8 Ratanpura 6.63 Km, NW 22°35'44.63"N, 73°23'55.49"E
(Source: Analysis during study period, GCI)
3.8.3 Analysis of Soil Samples
The soil samples were examined for various physicochemical parameters, to determine the
existing soil characteristics of the study area. Physicochemical characteristics of soil are
presented as follows
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
105 | P a g e
Table 3-17 Physiochemical Characteristics of Soil
Sr.
No. Parameters Unit
Results Reference Method
S1 S2 S3 S4 S5 S6 S7 S8
1. 1 pH - 7.40 7.51 7.82 7.37 7.40 7.58 7.73 7.22 IS 2720 : Part 26 : 1987
2. 2 Electrical Conductivity ms/cm 0.35 0.44 0.30 0.32 0.21 0.32 0.36 0.27 IS 14767: 2000
3. 3 Soil Moisture Content % 17.5 18.2 13.6 15.2 11.7 9.5 14.8 10.7 IS 2720 – Part – 2
4. 4 Water Holding Capacity % 43.8 35.7 41.2 37.4 25.3 30.1 42.4 45.6 APHA 3111 -B
5. 5 Bulk Density gm/cm3 1.30 1.41 1.74 1.50 1.54 1.60 1.22 1.39 -
6. 6 Organic Carbon % 0.84 0.33 0.37 0.71 0.42 0.57 0.46 0.40 IS 2720 : Part 22 : 1972
7. 7 Organic Matter % 1.44 0.56 0.63 1.22 0.72 0.98 0.79 0.68 IS 2720 : Part 22 : 1972
8. 8 Phosphorus mg/kg 30.5 27.6 33.4 42.3 37.1 45.4 30.3 45.4 APHA 4500 – P
9. 9 Total Nitrogen % 0.17 0.15 0.14 0.26 0.37 0.16 0.11 0.33 APHA 4500-NORG
10. 10 Potassium as K mg/kg 0.010 0.024 0.018 0.020 0.012 0.016 0.022 0.028 APHA 3500 – K - B
11. 11 Calcium mg/kg 184 175 150 137 146 169 173 149 APHA 3500 –Ca– B
12. 12 Magnesium mg/kg 74 65 71 52 47 60 78 58 APHA 3500 –Mg
13. 13 Chloride mg/kg 150 212 170 132 185 170 154 163 IS 6925: 1973
14. 14 Copper as Cu mg/kg <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 APHA 3111 B
15. 15 Zinc as Zn mg/kg <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 APHA 3111 B
16. 16 Iron as Fe mg/kg <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 APHA 3111 B
17. 17 Lead as Pb mg/kg <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 APHA 3500-Pb
18. 18 Nickel as Ni mg/kg <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 APHA 3500-Ni
(Source: Analysis by GCI Laboratory)
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
106 | P a g e
3.9 Biological Environment
Ecological communication presents the highest level of commitment to the environment, to
personal and community ecology and to a sustainable way of life for us and for the next
generation.
Environment consists of all living and nonliving factors which balance the weather conditions
and may be disturbed by some mechanical activities. Due to introduction of such activities,
the surrounding water, air and habitats may disappear or some new species may appear.
By conducting ecological studies, we may be able to understand the pattern of change in
weather condition, appearance or disappearance of flora and fauna, changes in vegetation
pattern in respect of their quantity and quality. The future industrial activities may be so
planned in such a way that the existing ecosystem may not get disturbed beyond
sustainable limits. Hence, ecological studies form a part of environmental monitoring studies
required for Environmental Management Plan.
The ecological study was undertaken to understand the present status of ecosystem of the
area, to predict changes as a result of proposed activities and to suggest measures for
maintaining the conditions. This carried through primary survey and secondary data
collected from various Government agencies like Forest Department, Agriculture
Department, Scientific literatures etc. Ecological survey is aimed to assess the existing flora
and fauna components in the study area. Considering the rich bio diversity of organisms and
their role in productivity and their importance in human livelihood, it is vital to project and
safeguard this dynamic ecosystem.
3.9.1 Flora & Fauna observed in the Study area
Floral Compositions
The floristic survey was carried out in and around the project site. Overall structure of the
vegetation in this area was scattered forest patches intercepted with scrubland and
grassland. Most of the study area is under human settlement and agricultural practice. The
grasses were found growing on open places, agricultural area and near human settlements.
The agricultural practice is mainly depending on monsoon water.
Heavy rainfall, moderate and humid climatic condition favors the richness of flora in study
area.
Table 3-18 List of Trees in the Study Area
Common Name Scientific name
Arduso Ailanthus excelsa
Aslan Elacodendronglacucum
Aledi Morindatinctorial
Ambedo Magniferaindica
Amla Emblicaofficinaallis
Amli Tamarindusindica
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
107 | P a g e
Common Name Scientific name
Aniya Acacia leucophloea
Anjan Hardwickiabinata
Baval Acacia niloticaindica
Bahedo Terminaliabellerica
Charoli Buchananiaiarizan
Ganiyari Colchlospermumreligiosum
Gol Tremaorientalis
Gugal Boswelliaserrata
Gundi Cordiadichotoma
Jambu Syzgium
Kadayo Sterculiaurens
Kusum Schleicheraoleosa
Limdo Azadirachtaindica
Monia Lanneacoromandlica
Papal Ficusreligiosa
Tad Borassusflabellifer
Vad Ficusbenghalensis
Sitafal Anonasquamosa
Amarvel Cuscutareflexa
Arun Cocculuslabea
Asan Cocculushirsutus
Parijat Nytanthusarbortristis
Baru Sorghum halepense
Bhathdu Themedatriandra
Pusha Cymbopogoncitratus
Shulki Panicumantidotale
Zill Indigoferapulchella
Nagod Vitexnegundo
Dhatura Daturainoxia
MotiKakari Combretumovaliforlium
Nilgiri Eculyptus spp.
Dodi Demiaextensa
Karamdo Carrissaconjesta
Malkakani Celastruspaniculate
Sisoo Dalbergiasisso
Sargwo Moringaoleifera
Kagar Acacia ferruginea
Ashotri Bahuhiniarecemosa
Bor Zizphusmauritiana
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
108 | P a g e
Common Name Scientific name
Aritha Sapnidusemarginatus
Dhavdo Anogeissuslatifolia
Dudhi Wrightiatinctoria
Nilgiri Trees
Amla Tree
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
109 | P a g e
Fauna
The various animal species in the study area are reported in Table below. The richness of
plant species of the region is the prime cause for animal richness.
Table 3-19 List of Fauna in study area
Common name Scientific name
Birds
Shikra Accipiter badius
Black winged kite Elanuscaerulus
Pariah kite Milvusmigrans
Pond heron Ardeolagravii
Indian Koel Eudynamysscolopaceae
Black drongo Dicrurusadsimilis
Indian robin Saxicoloidesfulicata
Babbler Timaliidae spp.
Common sandpiper Tringahypoleucos
Spotted owlet Ethane brama
Bank myna Acredotheresginginianus
Fantail flycatcher Rhipiduraaureola
Jungle Babbler Turdoidesstriatus
Dhatura
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
110 | P a g e
Common name Scientific name
Purple sunbird Nectariniaasiatica
Magpipe robin Copsychussaularis
Hoopoe Upupidaeepopus
Red vented bulbul Pycnonotuscafer
Reptiles
Common Indian Krait Bungaruscaeruleus
Garden lizard Calotesversicolor
House Gecko Hemidactylusbrooki
Cobra NajaNaja
Checkered Keel black Natrixpiscator
Rat Snake Ptyas mucous
Mammals
Indian Mole Rat Bandicotabengalensis
Blue Bull Boselaphustragocamelus
Indian Five Striped squirrel Funambuluspennanti
Common Mongoose Herpesteedwardsii
Indian Hare Lepusnigricollis
Monkey Macacamulatta
Common Langur Presdbytis entellus
Indian Flying Fox Pteropusgiganteus
Rats Rattus sp.
Cobra
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
111 | P a g e
3.9.2 Wildlife and Protected Area Network:
Forests & Wildlife
There are 4 National Parks and 23 Wildlife Sanctuaries in Gujarat; however, none of them are
falling in the study area. The Forest Vegetation Map of Gujarat is shown in Figure 3.17, and
National Parks with Wildlife Sanctuaries Map of Gujarat is show
Shikra
Blue-Bull
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
112 | P a g e
(Source: https://www.mapsofindia.com/maps/wildlife/wildlife-gujrat.htm)
Figure 3-23 Forest Vegetation Map of Gujarat
Table 3-20 List of National Park of Gujarat
Sr. No.
National Park Distance &
Directions from Project site
Coordinates
1 Gir Forest National Park 218.64km ,SW 21°7'27.66"N70°49'27.00"E
2 Blackbuck National Park ( Velavadar)
85.31km, WNW 22° 2'38.60"N72° 1'15.83"E
3 Marine National Park 376.51km, WNW 22°24'1.06"N69°12'8.30"E
4 Vansda(Bansda) National Park 134.64km, SSE 20°45'50.14"N73°29'9.96"E
Table 3-21 List of Sanctuaries of Gujarat
Sr. No.
Sanctuaries Distance &
Directions from Project site
Coordinates
1 Kutch Desert Wildlife Sanctuary 371.58km,NW 23°44'32.19"N 69°53'24.87"E
2 Indian Wild Ass Sanctuary 208.46km, NW 23° 8'10.81"N 71°23'36.52"E
3 Girnar Wildlife Sanctuary 237.69km,WSW 21°30'30.60"N 70°31'33.59"E
4 Shoolpaneshwar Wildlife
Sanctuary 102.87km,ESE
21°45'34.48"N 73°47'40.54"E
5 BalaramAmbaji Wildlife Sanctuary 282.49km,NNW 24°19'42.52"N 72°27'46.82"E
6 Narayan Sarovar Sanctuary 484.57km,NW 23°40'24.60"N 68°32'23.96"E
7 Mitiyala Wildlife Sanctuary 174.95km,SW 21°11'29.93"N 71°15'34.79"E
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
113 | P a g e
Sr. No.
Sanctuaries Distance &
Directions from Project site
Coordinates
8 Barda Wildlife Sanctuary 321.03km, W 21°51'3.59"N 69°41'56.41"E
9 Jessore Sloth Bear Sanctuary 291.11km,NNW 24°25'0.53"N 72°29'58.04"E
10 Purna Wildlife Sanctuary 134.51km,SE 20°56'35.72"N 73°43'27.10"E
11 Jambughoda Wildlife Sanctuary 108.65km,NE 22°21'38.98"N 73°39'55.18"E
12 NalSarovar Bird Sanctuary 137.13km,NW 22°49'2.50"N 72° 2'42.12"E
13 Ratanmahal Sloth Bear Sanctuary 160.11km,NE 22°34'29.27"N 74° 6'36.92"E
14 Rampara Wildlife Sanctuary 207.02km,NW 22°31'48.09"N 70°57'19.32"E
15 Thol Bird Sanctuary 154.37km,NNW 23° 8'24.16"N 72°23'34.89"E
16 Hingolgadh Sanctuary 158.33km,WNW 22° 9'10.85"N 71°19'1.74"E
17 Khijadiya Bird Sanctuary 284.59km,NW 22°30'52.30"N 70° 9'6.70"E
18 Gaga Wildlife Sanctuary 352.08km,W 22° 0'33.79"N 69°23'53.07"E
19 Kutch Bustard Sanctuary 446.21km,NW 23°10'56.74"N 68°43'55.00"E
20 Porbandar Bird Sanctuary 329.81km,WSW 21°38'13.40"N 69°37'5.11"E
21 Gir Wildlife Sanctuary 218.64km ,SW 21°'27.66"N
70°49'27.00"E
22 Marine Sanctuary 377.85km,WNW 22°23'6.57"N 69°11'48.30"E
23 Paniya Wildlife Sanctuary 211.61km,WSW 21°11'53.00"N 70°51'22.69"E
(Source: https://forests.gujarat.gov.in/writereaddata/images/pdf/GFS-2017-18-PCCF-20122018.pdf) Protected Areas: There are no protected areas in the vicinity of the project area. There are also no monuments of historical and archaeological importance within the study area.
3.10 Socio Economic Environment
This chapter analyses the socio economic conditions of the people residing in the area. With
the help of the data collected, the problems that might be faced by the residents of the area are
identified and according to that, the CSR and CER activities are collectively designed. Keeping
in mind, the socio economic status of the area, better plans for the community can be
developed as a part of CSR and CER activities to benefit the vulnerable groups.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
114 | P a g e
Methodology
Detailed socio-economic data were collected within 10 km radius of the Project site.
Preliminary information was collected during field investigation followed by secondary data
from the census of India 2011. Random sampling method was used to survey the households
in the village. Also, from the google earth imagery, villages were identified that might be
affected directly by the project. Survey method has been designed keeping this in mind. Key
informants and local leaders were identified and data was collected with their help.
Socio-economic Assessment
Socio-economic status of the population is the indicator of the change in the life style due to the
developmental activities taking place in the region. The villages which appears within the 10 km
radius from the centre of the proposed Project site are considered for socioeconomic study.
Demography
The study there is 15 villages in the study area. The demographic pattern of all the settlements
as per 2011 census is given in below table:
(Source: Google Image)
Figure 3-24 Villages within 10 km radius
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
115 | P a g e
Table 3-22 List of villages present in the study area
Sr. No. Name of village Distance from the
Project Site
Direction from the
Project Site
1. Alindra 1.89 Km NNE
2. Jetpur 4.11 Km NNE
3. Kalol 4.27 Km NNE
4. Bakrol 4.74 Km WSW
5. Maswad 5.16 Km ESE
6. Delol 8.25 Km NNE
7. Derol 6.86 Km NNW
8. Ratanpura 6.63 Km NW
9. Nevariya 7.03 Km W
10. Khakhariya 6.95 Km SW
11. Kanjari 7.44 Km SSW
12. Abhetwa 5.66 Km SSE
13. Halol 7.72 Km SSE
14. Radhanpur 8.68 km SE
15. Tarkhanda 8.25 Km ESE
3.10.1 Population and Sex Ratio
Sex ratio is number of females per 1000 males. As per the census 2011, the number of females per 1000 males is around 941. This is considerably less. The male population is 52% while female population is 48% of the total population. There are 77307 households in the study area consisting of total population of 392547. A group of persons who normally live together and take their meals from a common kitchen are called a household. Persons living in a household may be related or unrelated or a mix of both. However, if a group of related or unrelated people live in a house but do not take their meals from the common kitchen, then they are not part of a common household. Each such person is treated as a separate household. There may be one member households, two member households or multimember households. Average number of people in one household is 5 in the study area. Village wise details of the population are given in table 3-21.
Table 3-23 Village-wise details of Population
S.
No Village
No of
Households
Total
Population Male Female
Sex Ratio
(females/males)*1000
1 Alindra 125 641 327 314 960
2 Jetpur 295 1544 799 745 932
3 Kalol 36701 183839 95101 88738 933
4 Bakrol 1179 6018 3134 2884 920
5 Maswad 505 2569 1334 1235 926
6 Delol 1579 7154 3746 3408 910
7 Derol 1022 4774 2446 2328 952
8 Ratanpura 357 1729 899 830 923
9 Nevariya 134 582 304 278 914
10 Khakhariya 185 747 388 359 925
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
116 | P a g e
S.
No Village
No of
Households
Total
Population Male Female
Sex Ratio
(females/males)*1000
11 Kanjari 296 1513 795 718 903
12 Abhetwa 579 2935 1508 1427 946
13 Halol 33343 173694 89798 83896 934
14 Radhanpur 87 428 215 213 991
15 Tarkhanda 920 4380 2277 2103 924
Total 77307 392547 203071 189476 13994
Figure 3-25 Population of the study area
3.10.2 Social Structure:
The study area has a predominant Hindu and Muslims population. Hindus in the project area
as elsewhere, is based on the traditional four-fold caste system of Brahmin, Kshatriya,
Vaishyas and Shudras. The first three categories belong to higher caste whereas the last
category generally belongs to Scheduled caste and Tribes. As per Census 2011, average SC
population in the study area is 4.72% of the total population. In case of ST population, this
number has gone up and reached to 22.32% of the total population. The statistics regarding
the Social Characteristics of villages in the study area are given in Table 3-22.
Table 3-24Social Distribution
Sr/no. Name
Total
Population
Person Scheduled
castes
population
person
Scheduled
castes
population
Male
Scheduled
castes
population
Female
Scheduled
Tribes
population
person
Scheduled
castes
population
Male
Schedul
ed
castes
populati
on
Female
1 Alindra 641 43 23 20 72 39 33
52%48%
POPULATION OF STUDY AREA
Total Male Population Total Female Population
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
117 | P a g e
2 Jetpur 1544 61 36 25 260 126 134
3 Kalol 18383
9 12311 6255 6056 21936 11163 10773
4 Bakrol 6018 471 242 229 927 473 454
5 Maswad 2569 205 102 103 343 179 164
6 Delol 7154 452 238 214 215 106 109
7 Derol 4774 291 138 153 674 347 327
8 Ratanpura 1729 430 227 203 80 36 44
9 Nevariya 582 21 10 11 0 0 0
10 Khakhariya 747 0 0 0 355 183 172
11 Kanjari 1513 144 74 70 256 135 121
12 Abhetwa 2935 107 54 53 174 93 81
13 Halol 17369
4 4005 2027 1978 61628 31743 29885
14 Radhanpur 428 0 0 0 91 50 41
15 Tarkhanda 4380 179 86 93 495 257 238
Total 39254
7
18720
9512 9208 87506 44930 42576
Figure 3-26Social profile of the study area
3.10.3 Literacy
According to the Census 2011, it is calculated that average literacy rate in the study area is
60.35% percent of which male literacy rate is 60.49 percent and female literacy rate is 39.50
percent of total population. Approx. 39.65% Population is illiterate in the study area. The female
literacy rate is significantly low. Some of the community threatens to send their adolescent girls
for higher education due to lack of an education system in their villages.
Table 3-25 Literacy Rate
72.96%
4.72%
22.32%
Proportional representation of SC/ST population
other Scheduled castes population person Scheduled Tribes population person
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
118 | P a g e
Sr. No.
Name Total
Population Person
Literates Population
Person
Literates Population
Male
Literates Population
Female
Illiterate Persons
Illiterate Male
Illiterate Female
1 Alindra 641 418 241 177 223 86 137
2 Jetpur 1544 1092 613 479 452 186 266
3 Kalol 183839 114556 69051 45505 69283 26050 43233
4 Bakrol 6018 3506 2142 1364 2512 992 1520
5 Maswad 2569 1545 956 589 1024 378 646
6 Delol 7154 4854 2858 1996 2300 888 1412
7 Derol 4774 3338 1871 1467 1436 575 861
8 Ratanpura 1729 1191 709 482 538 190 348
9 Nevariya 582 338 223 115 244 81 163
10 Khakhariya 747 386 257 129 361 131 230
11 Kanjari 1513 935 568 367 578 227 351
12 Abhetwa 2935 1790 1070 720 1145 438 707
13 Halol 173694 99780 60854 38926 73914 28944 44970
14 Radhanpur 428 248 149 99 180 66 114
15 Tarkhanda 4380 2921 1738 1183 1459 539 920
Total 392547 236898 143300 93598 155649 59771 95878
Figure 3-27 Population Literacy of the study area
3.10.4 Occupational Pattern
The overall percentage of workers in the area is 33.76%. Male working population is significantly
higher than the female working population. Out of total working population 97.27% are main
workers whereas 2.7% are marginal working population. Out of total working population, 92.12%
population is male whereas 7.87% is female working population.
60.35%
39.65%
Literacy
Literate Population Illiterate Population
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
119 | P a g e
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
120 | P a g e
Table 3-26 Occupational Pattern
Sr. No.
Name
Total Population Person
Total Worker Population Person
Total Worker Population Male
Total Worker Population Female
Main Working Population Person
Main Cultivator Population Person
Main Agricultural Labourers Population Person
Main Household Industries Population Person
Main Other Workers Population Person
Marginal Worker Population Person
Non-Working Population Person
Non-Working Population Male
Non-Working Population Female
1 Alindra 641 212 188 24 209 131 31 1 46 3 429 139 290
2 Jetpur 1544 573 498 75 565 436 85 1 43 8 971 301 670
3 Kalol 18383
9 78959 55942 23017 56265 24185 19597 340 12143 22694 104880 39159 65721
4 Bakrol 6018 2127 1721 406 1919 875 809 9 226 208 3891 1413 2478
5 Maswad 2569 1363 782 581 768 372 159 2 235 595 1206 552 654
6 Delol 7154 3063 2224 839 1923 692 540 4 687 1140 4091 1522 2569
7 Derol 4774 2080 1480 600 1783 346 769 6 662 297 2694 966 1728
8 Ratanpura 1729 679 552 127 625 131 458 0 36 54 1050 347 703
9 Nevariya 582 278 196 82 277 113 162 0 2 1 304 108 196
10 Khakh
ariya
747 436 238 198 429 98 326 0 5 7 311 150 161
11 Kanjari 1513 530 436 94 458 30 231 0 197 72 983 359 624
12 Abhetwa 2935 991 913 78 964 408 413 0 143 27 1944 595 1349
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
121 | P a g e
Sr. No.
Name
Total Population Person
Total Worker Population Person
Total Worker Population Male
Total Worker Population Female
Main Working Population Person
Main Cultivator Population Person
Main Agricultural Labourers Population Person
Main Household Industries Population Person
Main Other Workers Population Person
Marginal Worker Population Person
Non-Working Population Person
Non-Working Population Male
Non-Working Population Female
13 Halol 173694 81101 53545 27556 55904 23907 20597 309 11091 25197 92593 36253 56340
14 Radhanpur 428 197 148 49 100 9 57 0 34 97 231 67 164
15 Tarkhanda 4380 1891 1384 507 1464 818 559 9 78 427 2489 893 1596
Total 392547 17448
0 120247 54233 123653 52551 44793 681 25628 50827 218067 82824
135243
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
122 | P a g e
Figure 3-28 Occupational Pattern of the study area
3.11 Traffic Study
The traffic survey to ascertain the traffic density in the study area was conducted on the road
near the project site. The composition of Traffic includes Two Wheelers, Three Wheelers
(Goods & Passenger Autos), Four Wheeler (Passenger cars) and Four Wheeler Heavy
Vehicles like Trucks, Lorries, Buses etc.
Traffic survey of the Study Area
The traffic survey, to ascertain the traffic density in the study area was conducted on the road
near to the project site and also to evaluate the impacts of the increased traffic due to the
proposed activity. The methodology adopted for carrying out the traffic study was to select
the major road around the project site and count the various categories of vehicles moving
on these roads given in the below table
Location: (Halol-Kalol Road)
31%
13%
56%
OCCUPATIONAL DISTRIBUTION
Main Worker Marginal Worker Non Worker
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
123 | P a g e
Table 3-27 Traffic Study Report
Vehicle Type
Equivalent
PCU factor
During
peak Hrs
(No. of
Vehicles/
hr)
No. of
vehicles in
PCU During
peak Hrs
(Equivalent
PCU factor*
No. of
vehicles)
During lean
Hrs (No. of
Vehicles/hr)
No. of vehicles in
PCU During Peak
Hrs (Equivalent PCU
factor* No. of
vehicles)
Two wheelers
Motor cycle
or scooter
etc.
0.75 200 150 184 138
Passenger
car, pick up
van
1.0 58 58 50 50
Auto
rickshaw 2.0 69 138 45 90
Light
commercial
vehicle
2.0 84 168 72 144
Trucks/Bus 3.7 60 222 52 192
Agricultural
tractor trailor 5.0 37 185 25 125
Cycles 0.5 20 10 40 20
Carts 2.0 41 82 63 126
Cycle
rickshaw 2.0 30 60 40 80
Total 599 1073 571 965
Existing Traffic Scenario and Level of Services
State Highway 87 is a Highway within the state of Gujarat. All types of vehicles move on the
road
Capacity of road as per IRC= 2400 PCU’s/hr
Total volume during peak hours=599
Existing volume/capacity ratio= 599/2400= 0.24. The level of service is “B” that is Very Good
Total Volume during lean hours= 571
Existing volume/capacity ratio= 238.5/2400= 0.23
The level of service is “B” that is Very Good.
Sr No. Existing Volume/Capacity Ratio Level of Services
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
124 | P a g e
1 0.0 to 0.2 “A” (Excellent)
2 0.2 to 0.4 “B” (Very Good)
3 0.4 to 0.6 “C” (Good)
4 0.6 to 0.8 “D” (Fair)
5 0.8 to 1.0 “E” (Poor)
Table of Contents
4 CHAPTER 4 ANTICIPATED IMPACTS & MITIGATION MEASURES ..................................
4 Chapter 4 Anticipated Impacts & Mitigation Measures ................................................ 127
4.1 Prelude .................................................................................................................... 127
4.2 Identification of EnvironmentalImpacts ................................................................ 127
4.3 EnvironmentalParameters ...................................................................................... 127
4.3.1 Air Environment .................................................................................................. 127
4.3.2 Water Environment.............................................................................................. 128
4.3.3 Land Environment ............................................................................................... 128
4.3.4 Noise Environment .............................................................................................. 128
4.3.5 Occupational Health & Safety ............................................................................. 128
4.3.6 Ecology ................................................................................................................ 128
4.3.7 Socio Economic Environment ............................................................................ 129
4.4 Project Activities and Components ....................................................................... 129
4.4.1 Construction Phase............................................................................................. 129
4.5 Prediction of Environmental Impacts .................................................................... 131
4.6 Impacts during construction phase and its mitigative measures ....................... 133
4.7 IMPACTS DURING OPERATION PHASE AND ITS MITIGATIVE MEASURES ...... 138
4.8 Air Environment ...................................................................................................... 138
4.8.1 Noise Environment .............................................................................................. 143
4.8.2 Water Environment.............................................................................................. 144
4.8.3 Land Environment ............................................................................................... 144
4.8.4 Socio-Economic Environment ............................................................................ 145
4.8.5 Ecology and Biodiversity .................................................................................... 146
4.8.6 Occupational Health ............................................................................................ 146
List of Tables
Table 4-1- Identification of Impacts during Construction Phase ....................................... 130
Table 4-2- Identification of Impacts during Operation Phase............................................. 131
Table 4-3- Prediction of Impacts during Construction Phase ............................................ 132
Table 4-4- Prediction of Impacts during Operation Phase ................................................. 133
Table 4-5- Impacts & Aspect Analysis during Construction Phase ................................... 134
List of Figures
Figure 4-1 Ground level Concentration of PM10 ................................................................. 139
Figure 4-2 Ground Level Concentration of SO2 .................................................................. 140
Figure 4-3 Ground Level Concentration of NOX ................................................................. 141
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
127 | P a g e
4 Chapter 4 Anticipated Impacts & Mitigation Measures
4.1 Prelude
This chapter identifies and predicts the potential impacts on different environmental components
due to the construction and operation of the proposed project. It details all the potential impacts
on biophysical and socio-economic components of the local environment due to the proposed
activities and sub-activities.
This chapter presents identification and appraisal of the likely impacts due to the proposed
expansion of M/s. Rajputana Stainless Ltd. Prediction of impacts is the most important
component in the Environmental Impact Assessment studies. Several qualitative and
quantitative techniques and methodologies are used to conduct analysis of the potential impacts
likely to build up as a result of the proposed development activities on physico-chemical,
ecological and socio-economic environments. Such predictions are superimposed over the
baseline (pre-project) status of the environmental quality to derive at the ultimate (post-project)
scenario of environmental conditions. The prediction and identification of impacts helps to
minimize the adverse impacts and maximize the beneficial impacts on environmental quality
during pre and post project execution.
4.2 Identification of Environmental Impacts
The identification of environmental impacts has been made, based on the understanding of
cause-condition-effect relationship between an activity and the impact component. To identify
and predict overall impact on environmental attributes, assessment task is performed for both
the phases i.e. Construction Phase and Operation Phase. Various techniques are available
for impact identification, out of which matrix method has been used to identify the impacts due
to the activities for the proposed project.
4.3 Environmental Parameters
For the purpose of the assessment of anticipated environmental impacts, some of the
environmental regimes are selected considering the probable impacts. The environmental
regimes along with the parameters predicted for the study area are given below;
4.3.1 Air Environment
Ambient air quality
Sources of emission and its quantity
Emission control measures / technology
Environment, health and safety management strategies
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
128 | P a g e
4.3.2 Water Environment
Water consumption and waste water generation
Water and wastewater quality
Water and wastewater management system / technology
Environment, health and safety management strategies
4.3.3 Land Environment
Potential of land use and land cover change
Potential of land contamination sources and control measures
Potential change in soil quality
4.3.4 Noise Environment
Major sources of noise from project activities
Control measures for noise
Environment, health and safety management strategies
4.3.5 Occupational Health & Safety
Nature and type of operation works
Raw material and its management (handling, storage and transportation)
Operation hazard and control measures (precaution and prevention)
Management for safety of employees, welfare and health
Occupational health and safety plan
Emergency measures and action plan
Disaster management plan
4.3.6 Ecology
Flora and fauna of study area
Change in habitat and vegetation
Control measures for ecology and environment management strategies
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
129 | P a g e
4.3.7 Socio Economic Environment
Demographic characteristics
Employment potential and allied issues
Basic amenities and infrastructure
Management strategies and social / community welfare plan
Occupational health and safety management plan
4.4 Project Activities and Components
The following project related activities identified as sources having potential to cause impact
upon various environmental attributes;
4.4.1 Construction Phase
All the impacts due to following activities during construction phase will be short term and limited
up to plot area.
Site cleaning
Levelling and road laying
Earthwork comprising of excavation, grading, trenching
Transportation of construction materials
Civil work
Mechanical erection
Employment
Domestic activities by workers
Greenbelt development
Operation Phase:
Each individual activity listed has its own impact on each environmental parameter. After
commissioning of the proposed project, operation phase will have permanent (long term) impact
due to said activities.
Raw material & product storage, handling and transportation
Manufacturing process & utility operations (consumption of resources & emission of
liquid effluent, flue & process gas, generation of solid/hazardous waste and Noise)
Employment
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
130 | P a g e
Green Belt Development
Infrastructure development & CER activities
Other factors/situation such as breakdown of critical systems, induced growth in the vicinity of
factory etc. will influence the environmental parameters. During an emergency situation, the
impact scenario will be completely different from normal operation and the impact on the
surrounding environment will be adverse. To make sure that the proposed project does not
leave behind any negative impacts, the adverse impacts are also identified for emergency
during EIA study.
Table 4-1- Identification of Impacts during Construction Phase
Sr.
No.
Parameter
Activity A
ir
Wate
r
Lan
d
No
ise
Eco
log
y
Healt
h &
Safe
ty
So
cio
Eco
no
mic
1. Site Cleaning X X
2. Leveling & road laying X X X X
3. Earthwork comprising of
excavation, guarding
trenching
X X X
4. Transportation of
construction materials
X X
5. Civil work X X X
6. Mechanical erection X X X X X
7. Employment X X X X
8. Domestic Activities by
workers
X X X X
9. Greenbelt development
Note: () Possibility of Impact (x): No impact will occur
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
131 | P a g e
Table 4-2- Identification of Impacts during Operation Phase
Sr.
No.
Parameter
Activity Air
Wa
ter
Lan
d
No
ise
Ec
olo
gy
He
alt
h &
Sa
fety
So
cio
Eco
no
mic
1. Raw material & product
storage and handling
X X X X X
2. Transportation of raw
materials and finished
products
X X X X
3. Production & Utilities X X
4. Emergencies or disaster X
5. Breakdown of critical
systems
X X
6. Employment X X X X X
7. Greenbelt development X X
8. Infrastructure development
& CER activities
X X X X X
Note: ( ) Possibility of Impact (x): No impact will occur
4.5 Prediction of Environmental Impacts
Prediction of impacts involves determination of nature and extent of impacts due to the various
activities to be involved in the proposed project. Generally, impacts are classified as follows;
1. Positive or Negative
2. Short term or Long term
3. Significant or insignificant or moderate
4. Direct or indirect
5. Reversible or irreversible
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
132 | P a g e
6. Quantifiable or non-quantifiable
7. Acceptable or conditionally acceptable or unacceptable
Looking to the project site, magnitude of project and pollution potential, impacts have been
predicted for following two classifications;
1. Positive or Negative
2. Short term or Long term
3. Significant or insignificant or moderate
Environmental Impacts are identified and assessed quantitatively and qualitatively. Prediction of
impacts for the both construction & operation phase is given in Table
Table 4-3- Prediction of Impacts during Construction Phase
Parameter
Activity
Air
Wa
ter
Lan
d
No
ise
Ec
olo
gy
He
alt
h &
Sa
fety
So
cio
Ec
on
om
ic
Site cleaning (-ve)
ST – (-ve)
ST
(-ve)
ST
(-ve)
ST
(-ve)
ST –
Leveling and road
laying
(-ve)
ST – – (-ve)
ST – (-ve)
ST –
Earthwork comprising of excavation, grading, trenching
(-ve) ST
–
(-ve) ST
(-ve) ST
–
(-ve) ST
–
Transportation of
construction materials
(-ve)
ST – (-ve) ST
(-ve)
ST
(-ve)
ST
(-ve)
ST –
Civil construction (-ve)
ST
(-ve)
ST – (-ve)
ST – (-ve)
ST –
Mechanical erection (-ve)
ST – – – – (-ve)
ST –
Employment - (-ve) ST
_ _ _ (-ve)
ST (+ve) ST
Greenbelt development (+ve)
LT (+ve)
LT (+ve)
LT (+ve)
LT (+ve)
LT
(+ve)
LT (+ve)
LT
Note:(+ve): Positive Impact; (-ve): Negative Impact; ST: Short Term; LT: Long Term
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
133 | P a g e
Table 4-4- Prediction of Impacts during Operation Phase
Parameter
Activity Air
Wa
ter
Lan
d
No
ise
Ec
olo
gy
He
alt
h &
Sa
fety
So
cio
Ec
on
om
ic
Raw material & Product storage and handling
(-ve) ST
– – – – (-ve) ST
–
Transportation of raw materials and finished products
(-ve) ST
– – (-ve)
ST – (-ve)
ST
–
Production & utilities (-ve)
LT
(-ve)
LT
(-ve)
LT
(-ve)
LT
– (-ve)
LT
–
Emergencies or disaster (-ve) ST
(-ve) ST
(-ve) ST
(-ve) ST
(-ve) ST
(-ve) LT
–
Breakdown of critical systems
(-ve) ST
(-ve) ST
(-ve) ST
(-ve) ST
– (+ve) LT
-
Employment – – – – – (+ve) LT (+ve)
LT
Greenbelt development (+ve)
LT
– (+ve)
LT
(+ve)
LT
(+ve)
LT
– (+ve)
LT
Infrastructure development & CSR activities
– – – – – (+ve) LT (+ve)
LT
Note: (+ve): Positive Impact; (-ve): Negative Impact; ST: Short Term; LT: Long Term
4.6 Impacts during construction phase and its mitigative measures
Identification and prediction of impacts during construction phase of the proposed project are
discussed in Table 1. There shall be no significant impact during the construction phase. The key
problem anticipated would be increase in dust contamination and noise. However, these impacts
would be for a limited period i.e. up to construction period only. Impact aspect analysis during
construction phase and its mitigation measures are given in Table
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
134 | P a g e
Table 4-5- Impacts & Aspect Analysis during Construction Phase
Attribute Aspects Impact Evaluation&
Impact Zone Mitigation Measures EMP Scope
Site Cleaning, Excavation, Foundation and Construction activities
Air
Quality
Dusting due
to site
cleaning,
excavation,
foundation
and
construction
Deterioration of ambient air quality
Negative,
Short term
Insignificant (as it
will be for short
duration and will
regain back on
completion of
construction
activities).
Confined to project site and vicinity
Storage of sand and other such
dispersible material by covering with
tarpaulin sheet
Keeping minimum inventory/stock of
sand and other such dispersible
material at site
Proper storage of excavated
materials with use of protective
sheets
Periodical water sprinkling to prevent dusting
Storage of topsoil in covered and
isolated area for its replenishing and
reuse for green belt development
Use of RMC to possible extent
Excavated materials to transporting
sound manner to prevent dust
spread during movement
Workers to be given proper training
Supervision of mitigation
measures to ensure its
effectiveness
Water
Quantity
Use of water
during
Construction
activity
Wastage of
water
Negative,
Short term
Moderate
Use of water shall be done in optimal way
Installation of water meter and record keeping of water consumption
Supervision of mitigation measures to ensure its effectiveness
Domestic
Sewage
generation
Disposal of
sewage
(treated)
Negative,
Short term
Insignificant
Prevent contamination of storm
water drain with sewage disposal
Regular inspection of STP for
sewage disposal
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
135 | P a g e
Attribute Aspects Impact Evaluation&
Impact Zone Mitigation Measures EMP Scope
Land /
Soil
Quality
Removal of
top soil as a
part of
construction
activity
Loss of topsoil Negative,
Short term
Insignificant
Confined to project
site
Top soil removed during construction
will be collected and stored in
covered and isolated area for its
replenishing and reuse for greenbelt
development
Planning and commencement
of green belt / area
development along with
construction phase
Noise Generation of
noise and
vibration due
to operation /
working of
construction
machineries
Hearing
defects in
workers /
employees
working with
the
machineries
Disturbance to local population
Negative,
Short term
Moderate and direct
Confined to project site and vicinity
Avoid construction activities during nighttime
Periodical servicing and lubrication
of moving parts of machineries for
reducing tear and wear
Provision of PPEs (ear muffs, ear plug) to workers working with machineries generating loud noise
For effective implementation,
these shall be made part of
contract conditions
Training to be imparted to
workers for use of PPEs and
motivate them to use the same
Ecology Site cleaning,
excavation
Nuisance to local flora and fauna
Negative,
Short term
Confined to project
site
Expert horticulturist will be deployed
to take care of green belt
development planning to enhance
the native species population
Planning and commencement
of green belt / area
development along with
construction phase
Occupational
Health &
Safety
Working at
height,
construction
of building,
use of lift
and
elevators
Chances of
accidents to
workers
/labors
Negative,
Short term
Confined to project site
Impart adequate training to workers/ labors working onsite
Make them aware about risks involved
Provision of required PPEs for the
workers.
Preparation and implementation
of safe work procedures
Training to be imparted to workers for use of PPEs
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
136 | P a g e
Attribute Aspects Impact Evaluation&
Impact Zone Mitigation Measures EMP Scope
Socio-
economic
Labor force
requirement Employment
opportunity to
local people
Positive,
Short term
Quantifiable
Local residents in
the vicinity
- Ensure employment to local people as per requirement
Transportation of Materials
Air
Quality
Transportation
as well as
loading /
unloading of
construction
materials,
equipment and
machineries
Local
ambient air
quality
deterioration
due to
increased
vehicular
traffic
Negative,
Short term
Moderate
Transportation route
All transportation vehicles will be
suitably covered with tarpaulin &
overloading of the vehicles will be
avoided.
PUC certified vehicles will be used to avoid the exhaust emission.
Keeping minimum
inventory/stock of sand and
other such dispersible material
at site
Transport contract to the
agencies having properly
maintained & PUC certified
vehicles to avoid the
exhaust emission
Noise Transportation
as well as
loading /
unloading of
construction
materials,
equipment and
machineries
Disturbance to local population
Negative,
Short term
Moderate
Transportation route
Vehicular movement will be preferred during daytime
Occupational
Health &
Safety
Traffic
movement Chances of
accidents to
local people
Negative,
Short term
Moderate
To avoid unnecessary speeding of
vehicles on road as well as inside
the premises.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
137 | P a g e
Attribute Aspects Impact Evaluation &
Impact Zone Mitigation Measures EMP Scope
Socio-
economic
Contract to
transport
agencies
Chances of
contract to
local people
Negative,
Short term
Moderate
Transportation route
Ensure contract to local
agency / people as per
requirement
Installation of plant equipment and machineries
Water
Quantity
Installation,
testing and
commissioning of
plant equipment
and machineries
Water
consumption for
hydraulic testing
of machineries
Negative,
Short term
Insignificant
Possible reuse of water will be
made during equipment and
machineries testing
Optimal usage of water
Noise Installation,
testing and
commissioning of
plant equipment
and machineries
Chances of
hearing defects
to workers
engaged
inactivity
Disturbance to local people
Negative,
Short term
Insignificant
(short term and
temporary in nature)
Confined to project
site
Provision of PPEs (ear muffs, ear
plug) to workers working with
machineries generating loud noise
Information to nearby community heads about plant commencement
Provision of acoustic
enclosures and vibrating
absorbance pads
Occupational
Health &
Safety
Installation,
testing and
commissioning of
plant equipment
and machineries
Chances of
accidents to
workers /
employees /
personnel
working
Negative,
Short term
Insignificant
Confined to project
site
- -
Socio-
economic Unskilled,
Semis skilled
and Skilled
Work force
requirement
Opportunities of
employment
generation for
local people /
agencies
Positive,
Short term
- Employment opportunities to local people
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
138 | P a g e
4.7 IMPACTS DURING OPERATION PHASE AND ITS MITIGATIVE MEASURES
The proposed expansion activity will have the environmental impact due to the operation of the
project on environment due to the various industrial activities like, raw-materials handling,
Induction Furnace operation, thermal radiation, vehicular movement, finished product handling,
labors activity, electrical installation etc. The potential environmental impact identified due to
proposed expansion will be on environmental parameters
Ambient air
Noise due to the metal materials movement
Water environment
Soil
Land use
Socio-economic impacts
Ecology & Biodiversity
4.8 Air Environment
Long term impacts on the air quality are anticipated due to operational activities. The baseline
ambient air quality status in the study area during post monsoon season indicates that all the
criteria pollutants (gaseous as well as particulates), viz., PM10, PM2.5, SO2, NOx, CO, etc. are
well within the prescribed National Ambient Air Quality Standards (NAAQS set by CPCB).
Stack monitoring for AOD unit, Induction furnace and DG set is carried out regularly. Air
pollution control measures like Bag filter is provided in the stack. Maintenance is and will be
done for good performance of APCM’s. The emissions are maintained as per CPCB limit.
4.8.1 Air Quality Modelling
AERMOD View – Lake Environmental Software, which is a Gaussian-Plume atmospheric
dispersion algorithm for estimating concentration of pollutant, has been used to predict the
Ground Level Concentrations (GLC’s) of PM10, SO2 and NOx due to plant activity. The GLC’s
were predicted on 24 hourly average basis keeping in view the prescribed national ambient air
quality standards (NAAQS).
Data used for Modeling
The hourly meteorological data along with emission rate for individual pollutants used for
prediction of air quality impacts as given in chapter 2 has been taken into consideration.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
139 | P a g e
Particulate matter (PM10)
The predicted concentrations of PM10 for Post Monsoon season are shown in the form of
isopleths in Figure 4-1
Figure 4-1 Ground Level Concentration of PM10
The maximum Ground Level Concentration for PM 10 GLC was found to be 1.205
μg/m3
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
140 | P a g e
Sulphur dioxide (SO2)
The predicted concentrations of SO2 for study period are shown in the form of isopleths in
Figure 4-2
Figure 4-2 Ground Level Concentration of SO2
The maximum Ground Level concentration for SO2 GLC was found to be 0.306μg/m3
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
141 | P a g e
Oxides of Nitrogen (NOx)
The predicted concentrations of NOx for study period are shown in the form of isopleths in
Figure 4-3.
Figure 4-3 Ground Level Concentration of NOX
The maximum Ground Level concentration for NO2 GLC was found to be 0.681 μg/m3
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
142 | P a g e
Sr.
No.
Parameter Location
Code
Name of
Location of
Baseline
study with
maximum
result
Distance &
Direction of
the
maximum
predicted
incremental
GLC from
Project Site
Maximum
Predicted
GLC
μg/m3 in
study
area
Baseline
Result
(Max.)
μg/m3
Incremental
result after
development
of Project
1 PM 10 AAQ-5 Khakhariya 700m, W 1.205 87.2 88.40
2 PM 2.5 AAQ-5 Khakhariya 700m, W 0.542 37.7 38.242
3 SO2 AAQ-5 Khakhariya 600 m , W 0.306 9.8 10.10
4 NOx AAQ-5 Khakhariya 600 m , W 0.681 17.4 18.081
The prediction results corresponding to PM10, SO2 and NOx as shown above indicate that the air
quality impacts with respect to pollutants exclusively from the proposed expansion projects
would be insignificant and the post-project status shall remain under prescribed NAAQS for
Industrial, Residential and other areas.
Also, during the operation phase of the project, the impacts on air quality due to vehicular
emissions will be very less. Considering the nature of activities, which the proposed expansion
project will result, less number of vehicular movements within the site and low threshold values,
air pollution is not expected to be a major concern. It is for these reasons that the ambient air
quality predictions using models have not been carried out for fugitive emissions from vehicles.
4.8.2 Effect of Particulate Matters on Materials, Vegetation, Animals and Human
Being
The size of particles is directly linked to their potential for causing health problems. Small
particles less than 10 micrometers in diameter pose the greatest problems, because they can
get deep into your lungs, and some may even get into your bloodstream.
Exposure to such particles can affect both your lungs and your heart. Numerous scientific studies
have linked particle pollution exposure to a variety of problems, including:
Premature death in people with heart or lung disease
Non fatal heart attacks
Irregular heartbeat
Aggravated asthma
Decreased lung function
Increased respiratory symptoms, such as irritation of the airways, coughing or difficulty in
breathing.
People with heart or lung diseases, children, and older adults are the most likely to be affected
by particle pollution exposure.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
143 | P a g e
Environmental damage Particles can be carried over long distances by wind and then settle on ground or water.
Depending on their chemical composition, the effects of this settling may include:
Making lakes and streams acidic
Changing the nutrient balance in coastal waters and large river basins
Depleting the nutrients in soil
Damaging sensitive forests and farm crops
Affecting the diversity of ecosystems
Contributing to acid rain effects.
Materials damage
PM can stain and damage stone and other materials, including culturally important objects such
as statues and monuments. Some of these effects are related to acid rain effects on materials.
Particulate matter (PM) alone or in combination with other pollutants constitutes a very serious
health hazard. PM enters the human body mainly via the respiratory system. Damage to the
respiratory organs may follow directly, since it has been observed particles having size between
0.01 to 0.1 µm which penetrate pulmonary compartment and deposit in it. It is extremely difficult
to obtain a direct relationship between exposure to various concentrations of PM and the
resulting effects upon human health.
Hence vehicular emissions will principally arise out of emissions from the exhausts of vehicles
used for the transport of Raw materials, fly ash and the transport of the workers. All vehicles
shall have Pollution Control Certificate (PUC) with regular maintenance check. However, their
effects are highly localized. In the dry season, there will also be some air pollution caused by re-
entrainment dust caused by operation of vehicles on dry roads and it’s proposed to control the
same by sprinkling on regular interval. Either covered dumpers shall be used or trucks shall be
covered through tarpaulin to prevent fugitive emissions.
4.8.3 Noise Environment
There will be chances of increase in noise level due to the operation of plant and machineries
for manufacturing activities, utility operations and transportation of products, raw materials and
fuel.
Exposure to continuous and extensive noise at a level higher than 85 dBA may lead to hearing
loss. Continuous hearing loss differs from person to person with the level, frequency and
duration of the noise exposed. Negative effects of noise on human beings are generally of a
physiological and psychological nature. Hearing losses are the most common effects among the
physiological ones. Blood pressure increases, heart beat accelerations, appearance of muscle
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
144 | P a g e
reflexes, sleeping disorders may be considered among the other physiological effects. The
psychological effects of noise are more common compared to the psychological ones and they
can be seen in the forms of annoyance, stress, anger and concentration disorders as well as
difficulties in resting and perception.
Main source of noise in proposed plant is D. G. Set. However, the same will be stand by and
operated only in case of main power failure. Proper and timely lubrication, oiling
and maintenance is carried out for all plant and machineries. Thus, there will not be any major
source of higher noise generation which can be propagated in vicinity. Ear plugs and ear muffs
are provided to the workers working in high noise area. Greenbelt will act as a barrier to the
spread of noise in the vicinity.
Regular noise monitoring will be carried out at the prominent place in the premises. As far as
the noise that will be generated due to the transportation is concerned, the same will be
minimized through transportation only in day time and by maintaining transportation vehicles
properly.
4.8.4 Water Environment
Domestic wastewater generated will be treated in unit’s own STP. The major waste water
generation during operation phase will be from cooling tower blow down, boiler blow down and
domestic purpose. The waste water generated will mainly consist of high TDS level. The same
shall be neutralized in the ETP and reused within the plant premises for green belt development
and water sprinkling for dust separation.
Pucca flooring is done in ETP area to avoid any type of leakage that can be percolated into soil
and contaminated ground water. Thus, there will not be any adverse impact on Ground water as
well as Surface water during construction & operation phase.
4.8.5 Land Environment
During operation activity the impact of air, water and solid waste pollution on soil causes direct
and indirect effect on soil. For this, all the necessary air pollution control system will be
provided. So that there will not be any adverse impact on soil.
There will be no adverse effect of wastewater on soil since the treated effluent generated from
the ETP is evaporated in an evaporator.
All necessary control steps/measures will be provided in proposed plant for handling, storage
and disposal of solid/ hazardous waste generated. Industry has also developed greenbelt within
the premises which prevent soil erosion which may change the land use
Soil Quality
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
145 | P a g e
Impact: There are no major sources of land contamination from waste spillage. The used oil
shall be collected in drums and shall be sold to the authorized recyclers identified by the GPCB/
CPCB. The proposed project is within the existing industrial premises and do not involve much
resettlement and rehabilitation problems.
Solid and Hazardous Waste Generation
The major solid waste generated during the construction phase will be construction/ concrete
debris. Also domestic waste shall be generated. The same shall be disposed off through
municipality facility.
During operation phase, waste generated can be categorized as hazardous waste, Non
Hazardous Waste and Domestic Solid Waste. Used oil, ETP sludge, Acid residue from pickling,
etc will be mainly generated as hazardous waste which will be disposed as per Hazardous
waste rules, 2016.
Solid waste generation such as slag / iron residue while using iron / steel scrap will be @
500/- MT/year. it will be re-melt (as possible) final residue be given for filling up in low lying
area, construction or roads etc/ sale to actual end users.
Slag composition analysis as below:
Content Percentage
CaO 32-35%
SiO2 33-36%
Al2O3 15-20%
MgO 8-10%
FeO <1%
MnO <1.5%
S <1% Moisture 5-10%
4.8.6 Socio-Economic Environment
Proposed project will have long term positive impact on socio-economic environment due to
generation of direct employment for about 546 People, out of which 150 people will be
employed for proposed expansion. Preference will be given to the local people from then nearby
villages as per the requirement. In addition, secondary job will be increased because of the day-
to-day needs with the upcoming proposed the project. This will increase the employment
opportunity in the area as well as improve the living standard of the people in the area which
also will help in improving educational, medical, health and sanitation awareness in the people.
Local employees will get benefited by facilities like drinking water, sanitation, first aid etc.
provided by client.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
146 | P a g e
Moreover, unit carries out CER activities in the nearby area in the field of health, sanitation,
medical aids, educational aids and contribution in infrastructural development which has
beneficial impacts on socio-economic environment.
4.8.7 Ecology and Biodiversity
There is no sanctuary and national park within the 10 km area from the proposed project site.
Also no rare and endangered flora and fauna have been reported during study in 10km area
surrounding to the project site. Proposed project will be carried out in the owned land and no
vegetation will be required to be cleared.
Chances of adverse effect on ecology due to the proposed project may be occurred due to air
pollution caused by flue gases emission. However, unit has adequate environmental
management systems. Regular monitoring of various parameters will be carried out. Thus, there
will not be any adverse impact occurred on surrounding ecology due to the proposed project.
Greenbelt development will have positive impact on flora and fauna.
4.8.8 Occupational Health
Several health related issues can be occurred with the workers of chemical industries due to
long term exposure in dusting, noisy area, handling of some hazardous chemicals, gaseous
emissions etc.
In the proposed unit, drinking water and sanitation facilities are provided to workers. All the
necessary personal protective equipment’s are provided for the respective works. The unit has
provided such arrangements to minimize manual handling of chemicals and hazardous wastes.
Regular health check-ups are carried out of all the workers and record is maintained for the
same. Medical, fire and safety trainings are given time-to-time. Moreover, unit has provided
proper environmental management system and operates the same efficiently. Thus, there will
not be any possibility of adverse impact on workers’ health & the same shall be continued
further with the upcoming proposed project. Thus, no adverse impact is expected on sanitation
and community health.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
148 | P a g e
Table of Contents 5 CHAPTER 5 ANALYSIS OF ALTERNATIVES .....................................................................
5 Chapter 5 Analysis of Alternatives ............................................................................... 149
5.1 Introduction ............................................................................................................. 149
5.2 Project Details ......................................................................................................... 149
5.3 Site Alternative ........................................................................................................ 149
5.4 Alternative for Technologies .................................................................................. 149
List of Tables Table 5-1 Particular Proposed Technology Alternatives .................................................... 149
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
149 | P a g e
5 Chapter 5 Analysis of Alternatives
5.1 Introduction
Alternative analysis is the process of analyzing the project’s location for suitability of basic
necessities to operate the plant safely this analysis also covers the environmental aspect of
pollution prevention and improvement in quality of life near to the project vicinity. The project
alternative is the course of action in pace of another, that would meet the same purpose and
need, but which would avoid or minimize negative impacts and enhance project benefits. Such
projects may result in specific impacts which can be avoided or mitigated by adherence to
certain predetermined performance standards, guidelines or design criteria. Alternative
approaches may therefore be more effective integrating environmental and social concerns into
the project planning process.
5.2 Project Details
M/s Rajputana Stainless Ltd. Is proposing expansion of integrated steel plant at 213- Madhwas,
Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat.
The proposed project falls under the item no. 3(a) under Category B1 as per the EIA
notification-2006 (as amended timely).
5.3 Site Alternative
The project site is in proximity of Halol District of Gujarat State and the fact is that the proposed
project is to be done within the project area. Project proponent is very well familiar with the
surrounding environment therefore, it becomes easy for the unit to set up, operate & maintain
the project on above said location.
The other supporting features are briefly summarized hereunder:
Availability of adequate land; Availability of all basic facilities like infrastructure,
communication, transportation, medical facilities, fuel, water, power, unskilled & skilled
manpower, raw materials, road network etc.
Proximity of market; Nearest town Halol is 7.3 km away from the project site which is
very well connected with other parts of the country by road & rail
No R & R will be required as it’s an expansion project; Easy availability of manpower.
No national park or wildlife habitats fall within 10 km radial distance from the project site.
The location of project is best suited to expand the manufacturing activities. So no
alternative for site is analyzed.
5.4 Alternative for Technologies
Table 5-1 Particular Proposed Technology Alternatives
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka
:Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
150 | P a g e
Sr.
No. Particular Proposed technologies Alternatives
1. Manufacturing
Process
The unit will adopt latest and best
technology available so far in the
market for the manufacturing of
proposed products to achieve
maximum yield with minimum
pollution generation and fugitive
emission.
The unit is very concerned and
conscious about the product quality and
equally about the environmental
protection & resource conservation.
Hence, unit will put continuous efforts
for replacing / upgrading plant and
machineries from time to time with the
best available technology.
2. Water
Wastewater treatment plant
consisting of primary, secondary
& tertiary treatment and reused
for gardening.
Domestic wastewater will be
treated in unit’s own STP.
-
3. Air
Bag filters for secondary
emissions and wet scrubber for
pickling section are provided.
Same will be upgraded after
expansion of Project. Adequate
stack height will be provided for
DG set with acoustic enclosure.
Proposed technology is suitable to
control emission of process gases &
adequately designed, considering the
pollution load, to maintain prescribed
norms of GPCB.
4.
Solid/
Hazardous
waste
Solid & Hazardous Waste is
stored in separate storage area
and Hazardous. Waste finally
disposed to approved TSDF site,
reuse of waste & disposal by
selling to registered recycler.
As disposal facilities are safe and also
guided by authority. No new changes
are required for switching on to other
alternative
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka:
Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
152 | P a g e
Table of Contents
6 CHAPTER 6 ENVIRONMENTAL MONITORING PROGRAM ..............................................
6 Chapter 6 Environmental Monitoring Program ............................................................ 153
6.1 Environmental Monitoring Program ...................................................................... 153
6.2 Objectives of Monitoring ........................................................................................ 153
6.3 Environmental Monitoring Program ...................................................................... 153
6.3.1 Monitoring and Reporting Procedure ............................................................. 153
6.4 Monitoring Equipment and Consumables ............................................................. 154
6.5 Environmental Budget ............................................................................................ 155
List of Tables
Table 6-1 Environmental Monitoring Plan (During Operational Phase) ............................ 154
Table 6-2 Budget Allocation for Environmental Management ........................................... 155
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka:
Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
153 | P a g e
6 Chapter 6 Environmental Monitoring Program
6.1 Environmental Monitoring Program
Environmental monitoring describes the processes and activities that need to take place to
characterize and monitor the quality of the environment. Environmental monitoring is used in the
Preparation of environmental impact assessments, as well as in many circumstances in which
human activities carry a risk of harmful effects on the natural environment. All monitoring
strategies and programs have reasons and justifications which are often designed to establish
the current status of an environment or to establish trends in environmental parameters.
Environmental Monitoring Network is operation phase of the project for monitoring of various
environmental parameters like air, water, noise, soil etc.
6.2 Objectives of Monitoring
To comply with the statutory requirements of monitoring for compliance with conditions of
EC, NOC and CC&A.
To comply with the provision of factory Act.
To verify the result of the impact assessment study in particular with regards to new
development.
Identification of any significant adverse transformation in environmental condition to plan
additional mitigation measures; if & as required.
To check or assess the efficiency of the controlling measures.
To ensure that new parameters, other than those identified in the impact assessment
study, do not become critical through the commissioning of new project.
To establish a data base for future impact assessment studies for new project.
6.3 Environmental Monitoring Program
Environmental Monitoring should be carried out during operation phase of the project.
6.3.1 Monitoring and Reporting Procedure
Regular monitoring of important and crucial environmental parameters is of immense
importance to assess the status of the environment during operational phase. With the
knowledge of baseline condition, the monitoring program can serve as an indicator for any
deterioration in environmental conditions due to operational phase and suitable mitigation steps
could be taken in time to safeguard the environment. Monitoring is as important as that of
control of pollution since the efficiency of control measures can only be determined by
monitoring. The proposed monitoring program gives below:
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka:
Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
154 | P a g e
6.3.1.1 Ambient Air Quality Monitoring
Both ambient air quality and stack emission will be monitored. The ambient air quality with
respect to NOx, SO2, suspended particulate matter (PM10 and PM2.5) will be monitored in at
least 3-4locations in and around the project site through a reputed environmental laboratory
recognized by MoEF/NABL. Monitoring will be carried out for a period of 24 hours, every month
during construction phase and quarterly in operation phase. Similarly, all the stacks in the
proposed unit will be monitored once in three months with respect to NOx, SO2, Suspended
particulate matter (SPM).
6.3.1.2 Water monitoring
Ground water monitoring locations will be identified and periodically check the Physical,
chemical as well as biological parameter as per drinking water standard IS 10500: 2012.
6.3.1.3 Noise level monitoring
Monitoring of the noise level is essential to assess the effectiveness of Environmental
Management Plan implemented to reduce noise levels. A good quality sound level meter and
noise exposure meter may be procured for the same. Audiometric tests shall be conducted
periodically for the employees working close to the high noise sources. The noise levels due to
machines and equipments will be monitored regularly.
6.4 Monitoring Equipment and Consumables
A well-equipped laboratory with consumable items will be provided for monitoring of important
environmental parameters. Alternatively, monitoring can be outsourced from MoEF/NABL
recognized laboratory.
Table 6-1 Environmental Monitoring Plan (During Operational Phase)
Component Parameters Location Frequency Duration
Ambient Air Quality
PM10, PM2.5, SO2,NOx,
Minimum 3-4 locations with one on upwind side, one on downwind and one on lateral side and one at project site.
Quarterly 24 hrs
Point Source Emissions
Particulates, SO2,NOx,
Each stack – for flue gas
Quarterly As per the
CPCB guidelines
Noise level Leq day, Leq
night, L10, L50, L90 dB(A)
In and around the work zone
Quarterly
24 hour reading with a frequency of 10 minutes every hour
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to 90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka:
Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
155 | P a g e
Soil Quality Physico-chemical
characteristics At relevant locations Quarterly
Sample every season
Ecology Survival rate of
plantation
At locations of compensatory plantation and landscaping
Annually
For 3 years after
operation starts
Health All relevant parameters
Every 15 days Regular check ups
As per requirement
Solid waste Depending on type of wastes
Solid waste disposal location
Once during each season
One time sample
Ground & Drinking water
As per IS 10500:2012
Adjoining village Quarterly At least at
three Locations.
6.5 Environmental Budget
For environment protection and management and pollution control and treatment and
monitoring systems, appropriate budgetary provision would be made and provision for recurring
expenditure for environment management of the project would be made. The details of budget
allocation during operation phase are given in below Table:
Table 6-2 Budget Allocation for Environmental Management
Capital cost = Rs. 86 Lakhs
Recurring cost = Rs. 34 Lakhs
Operation Phase (Rs.) in Lakhs
S.No. Pollution Control Measures Capital cost
per annum Rs. (Lakhs)
Recurring Cost Rs.
(Lakhs/Annum) 1 Air Pollution Control 40 10
2 Water Pollution Control 15 5
3 Noise Pollution Control 2 1
4 Occupational Health & safety,
firefighting system 20 10
5 Green Belt 4 2
6 Hazardous waste 3 4
7 AWH Monitoring Cost 2 2
Total 86 34
158 | P a g e
Table of Contents 7 Chapter 7 Additional Studies ...................................................................... 159
7.1 Risk Assessment ......................................................................................... 159
7.1.1 Introduction ........................................................................................... 159
7.1.2 Objectives .............................................................................................. 159
7.1.3 Definition of Environmental Risks ......................................................... 160
7.1.4 Identification of Hazards ........................................................................ 161
7.1.5 Environmental Risk Evaluation .............................................................. 166
7.1.6 Risk Management Measures .................................................................. 173
7.2 On-Site Emergency Plan ............................................................................. 175
7.1.7 Accident Statistics ................................................................................. 176
7.1.8 Safety Inspections ................................................................................. 176
7.3 Off-Site Emergency Planning ...................................................................... 176
7.1.9 Testing of Emergency Planning ............................................................. 177
7.4 DISASTER MANAGEMENT PLAN (DMP) .................................................... 177
List of Tables
Table 7-1 Hazard Identification Of The Proposed Steel Plant ............................................ 161
Table 7-2- Determination of risk potential ............................................................................. 168
Table 7-3-District Level Government Authorities ............................................................... 179
Table 7-4- Nearest fire station/Police station ...................................................................... 179
Table 7-5- Nearby hospitals & nursing homes .................................................................... 179
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
159 | P a g e
7 Chapter 7Additional Studies
7.1 Risk Assessment
7.1.1 Introduction
It is essential to apply modern approaches to safety practices based on good design,
management and operational control. It is essential to identify potential hazards while
assessing design and development proposals which handle hazardous materials. Risk
assessment techniques have been recognized as an important tool for integrating and
internalizing safety in plant operation and production sequencing. So the risk assessment is
mandatory for all new projects process industries dealing with hazardous materials and severe
operating conditions.
In the below sections, identifications of various hazardous, probable risks in the storage and
handling of hazardous materials are addressed which gives a broad identification of risks
involved in proposed manufacturing plant. The Disaster Management Plan is prepared
considering the hazard and risk involved in proposed manufacturing activity.
We here address the basic hazard process involved in the Induction furnace. Let’s understand
the process involved: Induction furnaces produce their heat cleanly, without burning fuel.
Alternating electric current from an induction power unit flows into a furnace and through a coil
made of hollow copper tubing. Electrical current flowing in one direction in the induction coil
creates an electromagnetic field that induces an electrical current flow in the opposite direction
in the metal charge inside the furnace, producing heat that rapidly causes the metal to melt.
7.1.2 Objectives
The objectives of environmental risk assessment are governed by the following, which
excludes natural calamities:
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
160 | P a g e
a) Identifying the potential hazardous areas so that adequate design safety
measures can be adopted to reduce the likelihood of accidental events.
b) Identifying the stakeholders and evaluating their risk along with proposing
adequate control techniques.
c) Identifying the probable areas of environmental disaster which can be
prevented by proper design of the installations and its controlled operation.
d) Managing the emergency situation or a disastrous event, if any, during the
plant operation.
Environmental risk assessment is a systematic approach for identification, evaluation,
mitigation and control of hazards that could occur as a result of failures in process,
procedures, or equipment. Increasing industrial accidents, loss of life & property, public
scrutiny, statutory requirements and intense industrial processes, all contribute to a growing
need to ensure that risk management is conducted and implemented.
Managing a disastrous event would require prompt action by the operators and plant
emergency staff using all their existing resources like deployment of firefighting equipment,
operation of emergency shut off valves, water sprays etc.
Minimising the immediate consequences of a hazardous event include cordoning off,
evacuation, medical assistance and providing correct information to the families of the
affected persons and local public to avoid rumours and panic.
Lastly, an expert committee is required to probe the cause of such an event, even if it is a
"near miss" situation, note the loss incurred/would have been incurred, and suggest
remedial measures for implementation so that in future such events or similar events do not
recur.
7.1.3 Definition of Environmental Risks
The following terms related to environmental risks are defined before reviewing the
environmental risks:
Harm Damage to person, property or environment.
Hazard Situation that poses a level of threat to life, health, property,
or environment. A hazardous situation that has come to pass
is called an incident. Hazard and possibility interact together
to create risk. An environmental hazard is thus going to be a
set of circumstances, which leads to direct or indirect
degradation of environment and damage to the life and
property.
Risk The probability of harm or likelihood of harmful occurrence
and its severity. Environmental risk is a measure of the
potential threats to the environment, life and property.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
161 | P a g e
Consequence Effect due to occurrence of the event, which may endanger
the environment permanently or temporarily and, or, loss of
life and property.
Environmental The consequence can extensively disaster damage any one
or all the four components of the environment, namely, (i)
physico-chemical, (ii) biological, (iii) human and (iv)
aesthetics.
7.1.4 Identification of Hazards
This is an early check of major hazards, which are of risk potential - including the potential for
disastrous interactions of the various plant operational activities. This checklist, though not
strictly speaking a Hazard and Operability Study (HAZOP) would considerably facilitate a full
scale HAZOP Study for final drawing up of risk management.
Measures when the ‘design-freeze’ stage commences. The identification of hazards
anticipation for the proposed project activities are presented below.
Table 7-1 HAZARD IDENTIFICATION OF THE PROPOSED STEEL PLANT
Group Item Nature of
Hazard
Hazard
Potential Remarks
Raw materials
handling
Coal for coking Fire Moderate Fire hazard
Water treatment
chemicals like
acids/alkalis
Toxic Major Bio-Corrosive
Production
units
Coke Plant
Dusts and fumes Asphyxiation Moderate Air pollution
VOC emission from
battery Toxic Moderate Health Hazard
Coke Oven Gas Fire & Toxic Major Fire and CO
hazard
Tar Fire & Toxic Moderate Flammable
Agglomeration
(Sintering) Dusts Respiratory Moderate
Ambient air
pollution
Iron making in
Release of untreated BF
water Toxic Major
Severe pollution
of surface water
BFG handling Fire Major Fire Hazard
Hot metal & slag
handling Fire Major Fire Hazard
Steel making in Release of untreated
BOFs wastewater Toxic Major
Severe pollution
of surface water
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
162 | P a g e
BOFG handling Fire Major Bio-corrosive
Hot liquid steel & slag
handling Heat Radiation Major Fire Hazard
Rolling Mills
Gas firing Fire Major Fire Hazard
Release of untreated
wastewater Toxic Major
Severe pollution
of surface water
Captive Power
Plant (CPP) TRT Fire Major Fire Hazard
Utilities
-Fuel gas Gas leaks Fire & Toxic Major
Fire & CO
pollution
Electric Power
supply Short Circuit Fire Major Fire hazard
Liquid Fuel Fuel handling and
storage area Fire & Toxic Major Fire Hazard
Hydraulic oil
and lubricants
Accidental discharge of
hydraulic oil under
pressure
Fire & Toxic Moderate Fire and
personal injury
From the Table, it may be observed that major on-site emergency situation may occur from the
organic coal chemicals storage and handling, fuel gas handling, molten metal and slag handling,
acids and alkali storage and handling and electrical short-circuit. The off-site environmental
disaster may arise if large-scale fire or explosion occurs, the effect of which extends beyond the
plant boundary. The off-site environmental disaster may take place due to significant
environmental degradation for a sustained period.
7.1.4.1 Hazards due to handling of molten metal
Wet material charging and failure of refractory are common cause of molten metal spillage /
splashing in induction furnace. Wet charge materials are a serious safety hazard in all
foundries. Water, moisture, or any liquid-bearing material instantaneously turns to steam when
coming in contact with molten metal — expanding to 1,600 times its original volume and
producing a violent explosion. This occurs without warning and throws molten metal and
possibly high-temperature solids out of the furnace, putting workers, the furnace itself, and
nearby plant and equipment at risk.
A water/molten metal explosion can occur in any type of furnace. For an induction furnace,
however, the may be more serious, including the possibility of additional explosions caused by
liquid in a ruptured cooling system coming in contact with molten metal in the bath. Molten
metal need not be present in the furnace for a water/molten metal explosion to occur.
Explosions also can occur if sealed drums or containers containing water are charged into an
empty but hot furnace. In this case, the force of the explosion will eject the newly charged
material and quite likely damage the refractory lining as well. Human interference are
eliminated near the Furnace during the operations.
Eliminating Wet Scrap
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
163 | P a g e
In foundries where most of the charge originates as scrap, wet charge materials pose the
greatest cause for concern.
Some foundries reduce the possibility of water/molten metal explosions by storing scrap under
cover for at least one day and then carefully inspecting the charge for any residual moisture. A
more reliable solution being used by an increasing number of foundries today is to use remote
charging systems with charge dryers or pre heaters.
Remote charging systems permit the operator to be away from the furnace or behind protective
screens during charging. Dryers and pre heaters maximize the removal of water and moisture
before the scrap enters the bath.
Sealed Containers
An easily overlooked danger is posed by sealed containers and sections of tubing or piping
that are sheared, closing the ends. Containers holding combustible liquids or their fumes will
explode long before the scrap itself melts. Pre- heating sealed materials will not prevent this
hazard. Aerosol cans, oxygen cylinders, propane tanks, acetylene tanks and shock absorbers
must never be used as charge material.
In fact, there is a risk that a sealed container will explode in- side the preheating systems.
Operator vigilance is the only preventive measure.
Cold charges, tools, cold aluminium “sow” moulds and easily fragmented materials pose a
special hazard for induction furnaces and their operating personnel because they may contain
a thin layer of surface or absorbed moisture. On contact with the bath, the moisture turns to
steam, causing spitting or splashing.
Appropriate protective clothing and face and eye protection normally will protect the operator.
Preheating the charge and tools helps prevent many splashing injuries.
In ferrous metal foundries the greatest splashing risk occurs toward the end of the melt, when a
foundry worker adds ferroalloys or introduces tools into the melt. Ferro-alloy materials can
absorb moisture from their surroundings. Sampling spoons and slag rakes collect moisture as
a thin film of condensation. Following manufacturers’ instructions for storing alloying materials
and preheating tools minimizes moisture accumulation, reducing the risk of splashing.
Since it is impossible to wring every bit of humidity from the open air, there is always a potential
for moisture condensation and splashing. Moisture condensation and absorption tend to
increase with time between melts. Therefore, the greatest splashing hazards are likely to occur
at the beginning of the work week or workday, or after a furnace have been taken out of service
for maintenance.
Allowing more time for the initial melt during this start- up periods can help to reduce the
potential for splashing hazards. During normal pours, sparks can ignite flammable clothing,
causing serious injury if workers are not properly protected.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
164 | P a g e
7.1.4.2 Bridging Hazard
It is important that care be taken when charging the furnace so that charge continues to feed
into the molten pool properly. If it hangs up due to interlocking or bridging, superheating below
can erode the refractory, causing molten metal to penetrate to the coil.
This results in loss of the melt and loss of the lining, and represents a very dangerous
condition. Should the molten metal burn through the coil, the water in the coil can cause an
explosion, causing serious injury or death.
When material charged into the top portion of the furnace is not in contact with the molten
metal in the bottom of the furnace, the condition known as “bridging” exists.
When bridging occurs, unmelted charge material is no longer serving to moderate the
temperature of the bath during the melting cycle. Also, the air gap between the molten metal
and the bridge acts as an insulator. The molten metal in the bottom of the furnace, under the
impact of melting power, will superheat.
This superheating in an induction furnace will occur very rapidly and will soon raise the
temperature of the bath above the maximum temperature rating of the refractory.
Also, excessive stirring in the bottom of the furnace, due to the small metal mass and high
power density will combine with the high metal temperature to cause rapid lining erosion or
possibly complete refractory failure.
Without immediate attention to a “bridging” condition, a run-out or explosion will occur. If the
run out is through the bottom of the furnace, it can cause a fire under the furnace and in the pit
area with loss of hydraulics and water cooling.
If the molten metal melts through the furnace coil and water comes in contact with the molten
metal, the water instantaneously turns into steam with an expansion rate of 1600 to 1.
If the water gets under the molten metal, this instantaneous expansion will produce an
explosion which could cause injury or death and extensive damage to equipment.
Be sure to keep the furnace pit area clean and dry because it is designed to hold molten metal
in case of an emergency.
Bridging can occur in any induction furnace and all furnace operators must be trained to be
able to recognize bridging and its dangers. All operators must be trained how to solve a bridging
problem.
Warning Signs of Bridging
Bridging may reveal itself with one of several warning signs. The clearest warning sign that
bridging has occurred is that the melt is taking longer than expected. Rather than increase the
power, the operator must switch off power and evacuate all personnel from the area
immediately. Under no circumstances should the operator increase power.
If ferrous metal is being melted, the chemical reaction which it creates on contact with the
furnace lining wills, under superheated conditions, produce carbon monoxide.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
165 | P a g e
This gas may reveal itself as small blue flames on or in the bridge. The appearance of these
flames indicates the bridge may be pressurized, and it must not be breached. In the case of a
nonferrous charge, gas production will also occur, but there are no flames or other visible
indications.
In the event of a Bridge
Bridging can be minimized by using proper charge material and by making sure the different
sizes of charge material are added correctly. If a bridge occurs, power must be turned off
immediately. All personnel must be evacuated from the furnace area until enough time has
elapsed to allow the molten metal to solidify.
7.1.4.3 Ground & Leak Detection Systems
The ground detector is a primary safety device. Never operate the unit with a faulty ground
detection system. Many factors (lining condition, etc.) influence the operation and speed of
operation of the ground leak detector. If a leak is suspected at any time, cease operation, clear
the melt deck area of all personnel and empty the furnace.
The ground and leak detector system for use with most coreless induction furnaces and power
supply units is crucial to safe melting and holding operations. The system, which includes both a
ground detector module associated with the power supply and a ground leak probe, located in
the furnace (except in removable crucible furnaces), is designed to provide important protection
against electrical shock and warning of metal to coil penetration, a highly dangerous condition
that could lead to a furnace eruption or explosion.
Ground Leak Probe Key to Protection
Key to this protection in furnaces with rammed linings or conductive crucibles is the ground leak
probe in the bottom of the furnace. This probe is composed of an electrical ground connected to
several wires extending through the refractory and in contact with the molten bath or
conductive crucible. This system serves to electrically ground the molten bath.
Both of these probe configurations are designed to provide shock protection to melt deck
workers by helping to en- sure that there is no voltage potential in the molten bath. If molten
metal were to touch the coil, the ground leak probe would conduct current from the coil to
ground.
This would be detected by the ground detector module and the power would be shut off to stop
any coil arcing. This also would prevent high voltage from being carried by the molten metal or
furnace charge.
Such high voltage could cause serious or even fatal electrical shock to the operator if he/she
were to come into conductive contact with the bath. Coil cooling sections in the top and bottom
of a steel shell furnace serve to maintain uniform refractory temperatures throughout the
furnace to maximize lining life. In steel shell furnaces, these cooling sections are electrically
isolated from the active coil, principally to insulate the active coil from ground leakage at the
top and bottom of the furnace. If a fin of metal reaches the cooling coil, the metal simply
freezes. The ground and leak detector system can sense metal penetration to the cooling
sections while maintaining AC isolation of these cooling sections from the active coil. This
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
166 | P a g e
improved arrangement is accomplished by incorporating a simple device in all new steel shell
furnaces to put low-level DC voltage on the top and bottom cooling coils. With this voltage, a
metal fin touching a cooling section will trip the ground leak detector, turning off the power to
the furnace and alerting the operator to the problem. And since the voltage on the cooling coil
is low, the fault will generate only extremely low current, upto 150 milli amperes.
Unlike systems which directly connect their cooling coil sections to the active coil to provide
ground fault detector protection, this low current poses no risk to the coil. It avoids the danger
of a large fault blowing a hole in the tubing used for cooling coils.
The coreless furnace must not be operated without a functioning ground detector and ground
leak probe. The ground leak probe may not be required in removable crucibles and some
special vacuum furnaces. As a normal safety precaution, power to the furnace must always be
turned off during slagging, sampling and temperature measuring.
7.1.5 Environmental Risk Evaluation
From environmental hazards point of view, risk analysis (RA) acts as a scrutinizing vehicle for
establishing the priority in risk management that concerns human health and environmental quality
in general. Though the proposed facilities are not manufacturing, storing or handling any potentially
hazardous/toxic chemicals as scheduled in Manufacture, Storage and Import of Hazardous
Chemicals (MSHC) Rules, 1989 and its amendments thereof, the proposed facility would have
installations, such as, storage and handling of fuel oil.
Environmental Qualitative Risk Analysis Flow Chart Procedure is explicitly depicted on the next
page.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
167 | P a g e
Evaluation of Risk potential helps to rank the risks, so that the
management actions can be developed to address the most
significant risks
These three parameters are combined in a ‘Risk matrix’ to
evaluate Risk potential , that determine the overall assessment
of the risk that pose threats to the various elements of the
environment
Determination of
‘Severity of
Consequence’
Determination of
‘Likelihood of
Detection’
Determination of
‘Likelihood of
Occurrence’
Environmental Risk Qualitative Analysis
ENVIRONMENTAL RISK QUALITATIVE ANALYSIS FLOW SHEET
As revealed in the chart in the preceding page, raw materials & consumable chemicals, and
processing of the same in various production units, along with relative risk potential analysis is
made on the following three factors using a P/I (Probability/ Impact) analysis methodology:
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
168 | P a g e
i) likelihood of occurrence
ii) likelihood of detection
iii) severity of consequence
Each of these factors is graded and compiled to determine the risk potential. The factors
governing the determination of relative risk potentials are presented below.
Table 7-2- Determination of risk potential
(A) (B) (C)
Likelihood of
occurrence
Likelihood of
detection
Severity of
consequence
Criteria Rank Criteria Rank Criteria Rank
Very High 5 Very High 1 None 2
High 4 High 2 Minor 4
Moderate 3 Moderate 3 Low 6
Low 2 Low 4 Moderate 8
Very Low 1 Very Low 5 High 10
RISK POTENTIAL (RP) = (A + B) x C
Based on the above stated criteria for assessing the risk, each probable event has been evaluated
by addressing several questions on the probability of event occurrence in view of the in-built
design features, detection response, operational practice and its likely consequence.
A HAZOP Study for the selected units/areas needs to be undertaken at the ‘design-freeze’
stage, when P&I diagrams, shop layout drawings, control logic diagrams, technical
specifications etc are made ready. For these areas, ‘Fault Tree Analysis’ of the failure of
equipment/valve component or due to human error can be carried out to assess more
realistically the risk involved and draw up final management measures. It is also suggested to
conduct HAZOP/HAZID Study for the fuel gas distribution network to incorporate last minute
corrections in the design of the system from fail-safe angle, prior to commissioning.
7.1.5.1 Safety During Construction
Safety during construction would be an important aspect with regards to risk analysis of the
project. The safety during construction would be prescribed as follows:
i) Ensure that all employees and contract workers are well versed with the safety
guidelines of the organisation and well equipped with the Personal Protective
equipments (PPEs) such as safety helmets, safety shoes, goggles, hand
gloves, safety jackets, earmuffs, etc.
ii) Ensure that Construction Safety Manual elaborating all the safety
rules/guidelines is in place and is followed by all concerned directly or indirectly
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
169 | P a g e
involved in construction.
iii) Ensure that Safety gears like Fall arresters, lifelines etc are used compulsorily for
height work
iv) Ensure that the Operating procedures and control management system is in
place and meticulously followed by all workers.
v) Ensure regular safety suit, identify and analyse hazards to reduce risk associated
with the particular operation.
vi) Arrange display signs for material strictly prohibited inside any work premises like
inflammable materials, firearms, weapons & ammunitions, etc.
vii) Arrange display signs for restricted area
viii) Arrange direction signs (night glowing) and speed limit signs along the
construction roads.
ix) Arrange clear demarcation of passage within Construction area with proper safety
arrangements,
x) Developing ‘Dos’ &‘Don’ts’ during various types of works like working at heights,
etc.
xi) Ensure that emergency control mechanisms like switch, valve and emergency
lamp are covered with shield, water & shock resistance cover during rain etc
and peddle switch for bigger rotating machinery mixer etc. There should be no
temporary cable joints and open air working switch yard at enriched level.
xii) Adequate information about emergency numbers shall be displayed
everywhere. There would be emergency control room, emergency controller,
shift emergency controller to take proper control of any unwanted situation and
have an overall control.
Following the above measures would ensure that safety is being strictly followed during all
construction activities.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
170 | P a g e
7.1.6 Safety during Operation
PPEs requirement for head to toe protection is described in the following subsection.
i) Head Protection
Purpose: To protect the head from injury due to falling or moving objects, impact on stationary
objects and from impact due to falls. Requirements:
a) Safety helmets must be worn where recognized potential for the injuries described above
exists.
b) Safety helmets shall not be modified or painted as this may affect the integrity of the helmet
c) In order to allow safety helmet colours to be used to differentiate personnel and visitors from
other personnel and to make personnel visibility different colours should be reserved and
followed
d) Helmet should be made up of FRP which should meet the standard IS: 2925 or EN 397. e)
Helmets should be cleaned by dipping in hot water (140 0 F) with good detergent for 1 minute
and scrub.
f) It should be periodically inspected for any scratches, wear and tear.
ii) Eye Protection
Purpose: To protect eyes from damage due to impact, penetration, burns, splashes and flying
particles and ultra violet radiation.
a) Safety goggles must be worn at all times in all secure boundary areas except while inside an
office, amenity, cabin or fully enclosed vehicle. If the employee has power in eyes (myopic/
hypermetropic), power industrial glasses shall be used. In absence of well suited power
industrial goggles, over goggles with prescription glasses shall be used.
b) Selection of goggles must be done on the basis of type of job/ environment.
c) Different type of goggles should be used for chemical splashes, dusty environment, heat
prone areas, for oven inspection or while looking at the red molten metals.
d) Safety Goggles should be made up of polycarbonate material & meet the Standard ANSI
Z87.1 2003 or EN166.
e) For cleaning Polycarbonate glasses, they should be washed with water and then wiped off to
avoid scratches.
iii) Hearing Protection
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
171 | P a g e
Purpose: To conserve the hearing of personnel by use of hearing protection appropriate for
reducing the received sound energy levels of noisy equipment and processes to acceptable
levels.
Requirement:
a) Specified hearing protection i.e. ear plug or ear muff shall be worn if the noise level is above
85 decibel. All areas requiring the wearing of hearing protection shall be clearly sign posted.
b) Ear muff & Ear plug should meet the Standard EN 352.
c) Disposable ear plugs should be discarded after every use or as it gets dirty.
iv) Hand Protection
Purpose: To protect the hand from injuries such as cuts, grazes, burns, ingress of chemicals &
electric shock.
Requirements:
a) The personnel should wear hand gloves as per the hazard other than general purpose
cotton hand gloves or knitted hand gloves while performing their job/ task as mentioned in the
SOP.
b) Hand Gloves should meet the standard EN 420 for general requirement, EN 388 for
mechanical hazard, EN 407 for molten metal splashes and heat applications.
c) Selection of hand gloves should be done on basis of application.
d) Before use, they should be checked for punctures, tears or other defects and discarded if
found not OK. Chemical-use gloves should be tested for leaks periodically by inflation with air
and immersion in water. Do not use this test for polyvinyl alcohol gloves as they are water
soluble.
e) Disposable gloves should not be reused. Contaminated gloves must be disposed in an
appropriate manner and should not be placed in the regular trash. Always store gloves in a
clean, accessible area. Never store contaminated gloves – dispose of them in the appropriate
manner.
v) Foot Protection
Purpose: To protect the feet from risks ranging from crush and impact injuries to slips, cuts,
penetration wounds, electric shock and splashes with liquids and molten metal.
Requirements:
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
172 | P a g e
a) Personnel working inside the plant must wear ISO /EN approved safety footwear, in good
condition.
b) To ensure footwear quality, personnel are required to wear prescribed company issued
safety footwear, in good condition, while working in the plant.
c) The personnel should worn Heat resistance boot if the surface temperature is more than 100
Degree Celsius in their work place.
d) The personnel should wear PVC Gum boot if they have to perform their job in muck/ mud or
leg can dip into above the ankle.
e) Safety shoes meet the standard ISO 20345.
vi) Respiratory Protection
Purpose: To protect all employees (of the company as well as of the contractors) against
respiratory hazards through the use of respiratory protective equipment.
Requirements:
a) The primary control of contaminated air shall be maintained through engineering methods by
confining processes, providing exhausts, or providing substitution of less toxic materials.
Where engineering remedies are not feasible or are not available, or while they are being
evaluated or implemented, and when the atmospheric exposure to a toxic material may exceed
the recommended ceiling or time-weighted average limit for a given pollutant, respiratory
protection will be required to protect the health of employees.
b) Suitable respirator will be provided to the employee by the department in consultation with
Safety expert and manufacturer (if required).
c) While selecting a respirator for a particular job environment following factors to be
considered
Severity of hazard
Expected activity of the wearer
Degree of protection required
Ease and comfort with which it can be worn
People using the equipment should understand its operation and necessity of use.
vii) Body Protection
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
173 | P a g e
Purpose: To protect the body from injuries such as cuts, grazes, burns and the effects of
exposure to heat, cold and ultra violet radiation & collision from moving machines.
Requirements:
a) Persons working in the plant are required to wear right industrial clothing in good condition.
Clothing must fully cover the legs and arms. If specified in Departmental Standard Operating
Procedure (SOP), it may be acceptable to wear short sleeved shirts in specific plant areas or
for specific tasks.
b) Specific PPE should be used if person is exposed to hazard of molten metal splashes,
electric flash, high heat, radiation, chemical splash complying with relevant EN/ ANSI
standards. Clauses like E for molten spatter protection in EN 11612 shall be applicable.
c) Chemical protective clothing should be used when there may be exposure to chemicals
presenting a skin contact hazard, for example, when transferring chemicals from one container
to another, when opening or entering systems such as pipelines, reactors, filters, or storage
tanks, or when connecting or disconnecting cargo tanks.
d) When working with mixture of chemicals, the best material for some components of the
mixture may be totally inadequate for one or more of the remaining components. TECP (Totally
Encapsulating Chemically Protective suits), face shields, goggles, aprons, foot wears shall be
adopted as per application.
e) High visibility jacket complying to EN 471 or equivalent should be used to make personnel
more visible to avoid collision from heavy vehicles and moving equipment Machines. f) Rail
crew jackets should be worn for people working on or near rail tracks. g) Double Lanyard Full
Body Harness to be used while working at height.
7.1.7 Risk Management Measures
The risk management measures for the proposed project activities require adoption of best
safety practice at respective construction zones within the Works boundary. In addition, the
design and engineering of the proposed facilities would take into consideration proposed
protection measures for air and water environment as outlined in earlier Chapter.
7.1.7.1 Electrical Safety
Adequately rated quick-response circuit breakers, aided by reliable, selective
digital/microprocessor-based electro-magnetic protective relays would be incorporated in the
electrical system design for the proposed Project. The metering instruments would be of
proper accuracy class and scale dimensions. Appropriate use of ELCBs shall be ensured for
all construction related low voltage work.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
174 | P a g e
7.1.7.2 Fire Prevention
In addition to the yard fire hydrant system, each individual shop would be provided with fire
and smoke detection alarm system. Fire detection system would be interlocked with
automated water sprinklers.
The use, storage and handling of hazardous materials in unit require special care for its
receipt to end use by storages, transfer of hazardous materials at premises. The hazardous
materials storages, handling, use and produce require understanding the hazard
characteristics, storage property, handling precautions, preventive measures during the
handling.
Safety Measures
Details of flame proof electrical fittings, DCP extinguishers and other safety measures:
Thermal Suits
Flame proof electrical motors, pump and switches are provided.
Separate storage of flammable materials with proper labelling and
marking with authorized entry.
No Smoking - board
Safe Operating Procedure for each operation
Train and qualified manpower for hazardous materials handling with knowledge of
hazards and precautions
Water Shower off-Production area
Flameproof fittings at solvent usage area.
Use of proper PPEs for relevant activity.
Availability of First-Aid box with required
contents
Premedical and periodical medical examination of
worker
Inspection and checking of fire extinguishers, cranes, pressure vessels, hoist, chain
pulley, etc. at periodic intervals.
Maintain proper housekeeping
7.1.7.3 CO Detection and Prevention
Carbon Monoxide (CO), a potential toxic gas, is produced due to incomplete combustion of
carbonaceous fuel. Exposure to CO, due to leakage and other accidental causes, is
associated with headache, dizziness, fatigue, and even death at elevated concentration.
Hence, it is important to install carbon monoxide detector/alarm in BF areas and pipelines to
detect the presence of carbon monoxide (CO) and sounds an alarm to alert personnel in
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
175 | P a g e
case there is CO leakage. This would immediately stir probe and management of the
scenario. Proper maintenance of the detector system is crucial.
7.2 On-Site Emergency Plan
Emergency planning is an integral part of the environment and safety management of an
organisation. Emergency may arise due to manmade reasons resulting in heavy leakage,
fire, explosion, failure of critical control system, design deficiency, unsafe acts, etc, and
natural causes like earthquake, flood, cyclone, excessive rain, etc. It is crucial for effective
management of an accident to minimize the losses to the people and property, both in and
around the facility, termed as on-site and off-site emergency plan.
The vital aspect in emergency management is to prevent accidents and losses by technical
and organizational measures. Emergency planning demonstrates the organizational
commitment to the safety of employees and adds to the organization’s safety awareness.
The objective of the on-site emergency plan is to make maximum use of the combined
resources of the factory and the outside services to:
i) Initially contain and ultimately bring the incident under control
ii) Minimize damage to property and environment
iii) Effective rescue and treatment of casualties
iv) Safeguard personnel in the premises (Provision of safe assembly points and
escape route)
v) Provide information to relatives
vi) Identify any casualty
vii) Provide authoritative information to news/media
viii) Secure safe rehabilitation of affected areas
ix) Preserve relevant records and equipment for
subsequent inquiry into the cause and circumstances of emergency
The on-site emergency plan relates to a laid-down procedure after taking care of all
precautionary measures at the time of design-freezing and plant trial testing. The Operations
General Manager would have the responsibility to implement this procedure manual.
Implementation involves the following:
i) The Environment Management Division (EMD) would have separate group
manned by only those persons, who are capable of keeping themselves
unperturbed and cool during emergency. They would be fast in taking decision
and implementation of the same.
ii) The command area, duties and responsibilities to the assigned person would
be defined as-
iii) These key personnel of Rajputana Stainless Steel would work as ‘Works
Incident Controller’ for respective areas and one man as ‘Works Main
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
176 | P a g e
Controller’.
iv) These key personnel would be trained with various simulated cases, if
necessary, and how the problems need to be tackled.
v) Rajputana Stainless Steel Ltd. would be equipped with communication and
public alarm system.
vi) Assessment of the size and nature of the events foreseen, its probability of
occurrence and if happens, the advanced action plan.
vii) Liaison with the outside local authorities including the
emergency services.
viii) Rehearsing emergency procedures.
7.1.8 Accident Statistics
The section of EMD dealing with Emergency would record the events of both minor and
major accidents, listing all the details such as place, date &time, duration, probable cause,
extent of damage, personnel affected, man-hours lost, medical assistance provided etc so as
to analyse these data for drawing up necessary corrective measures.
7.1.9 Safety Inspections
Monthly safety inspection of all departments would be carried out by Health & Safety
Department. Additionally, half-yearly Safety Audit is performed including all aspects of
Occupational Health &Safety for all the areas
7.3 Off-Site Emergency Planning
The off-site emergency plan is also an integral part of any major hazard control system. This
particular plan relates to only those accidental events, which could affect people and the
environment outside the plant boundary. Incidents, which would have very severe
consequences, yet have a small probability of occurrence would be in this category
The implementing authority of the off-site plan is the local authority and not the plant
authority. But Rajputana Stainless Steel Ltd. would have a written document on how to ask
for off-site plan implementation in case the consequence of any event escalates to such an
extent that it goes beyond the plant authority’s jurisdiction. Probability of such occurrence is
though remote, but still there remains a probability.
The Rajputana Stainless Steel would therefore have laid down procedure covering the
following:
i) Identification of local authorities like civil defence, police, district collectors,
their names, addresses and communication links.
ii) Details of availability and location of heavy duty equipment like bull dozers, fire-
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
177 | P a g e
fighting equipment etc.
iii) Details of specialist agencies, firms and people upon whom it may be
necessary to call.
iv) Details of voluntary organisation.
v) Meteorological information.
vi) Humanitarian arrangements like transport, evacuation centres, first aid,
ambulance, community kitchen etc.
vii) Public information through media, informing relatives, public address system
etc.
7.1.10 Testing of Emergency Planning
The plant authority would test from time to time the efficacy of off-site emergency plan in
conjunction with on-site emergency plan. One essential component of this mock drill is to see
that whether procedures related to communication, mobilization of equipment and overall co-
ordination to face the crisis is in order or not.
7.4 DISASTER MANAGEMENT PLAN (DMP)
A disaster is a catastrophic event that causes serious injuries, loss of life &extensive damage to
Plant & property. It is a situation which goes beyond the control of the available resource of any
authority or organization. A number of factors could trigger accidents leading to a disaster, some
of which are as follows: (a) Process and safety system failures - Technical errors - Human
errors (b) Natural Calamities: earthquake, Tsunami etc.
The DMP is formulated with an aim of taking precautionary measures to control the hazard
propagation and to take such action that the damage following a disaster is the minimum.
The objective of the DMP is to make use of the combined resources of the plant and the outside
services to achieve the following:
i) Effective rescue and medical treatment of casualties
ii) Safeguard other people
iii) Minimize damage to property and the environment
iv) Initially contain and ultimately bring the incident under control
v) Identify any dead
vi) Provide for the needs of relatives
vii) Provide authoritative information to the news media
viii) Secure the safe rehabilitation of affected area
ix) Preserve relevant records and equipment for the subsequent inquiry into the
cause and circumstances of the emergency.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
178 | P a g e
In effect, DMP helps to optimize operational efficiency to rescue rehabilitation and render
medical help and to restore normalcy
The following hazards for disaster management have been considered:
i) Fire
ii) Explosion &Toxic release
iii) Oil spillage/liquid metal spillage
iv) Electrocution
v) Accident
These hazards and the events that can lead to these hazards have already been discussed in
the preceding sections.
Few elementary disaster management measures to prevent disaster due to the above
mentioned hazards are as follows:
i) Design, manufacture, operation and maintenance of all plant
machineries/structures as per applicable national and international standards
as laid down by statutory authority.
ii) Intelligent formulation of layout to provide ‘Assembly Point’ and safe access
way for personnel in case of a hazardous event/disaster, as can be inferred
from Risk & Consequence modelling.
iii) Proper emergency (both on site & off-site) preparedness plan, emergency
response team, emergency communication, emergency responsibilities,
emergency facilities, and emergency actions shall be developed.
iv) Proper Alarm system and training the personnel for appropriate response
during disastrous situation.
v) Complete fire protection coverage for the entire plant as per regulatory
stipulations.
vi) Creation and maintenance of Disaster Management cell with adequately
trained personnel who can handle all sorts of emergency situation.
i) Provision of funds for prevention of disaster, mitigation, capacity-building and
preparedness.
It would be advisable to carry out a detail DMP at the design stage itself to frame a proper
scheme for disaster management. However, this would be subjected to subsequent
improvements as and when required for safe and efficient operation of the plan.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
179 | P a g e
Table 7-3-District Level Government Authorities
1. DISTRICT COLLECTOR Collector office Compound Godhra,
Dist. Panchmahal, Phone No. (02672) 242800 / 242900
2. Asst. Director, Industrial Safety & Health Office of Asstt. Director, Ind. Safety & Health
Fourth Floor, Multi-storied Building Collector Office Compound Godhra, Dist. Panchmahal.
Phone No. (02672) 241870 (R) 265415
3. DISTRICT SUPRENTENDENT OF POLICE Godhra, Dist. Panchmahals
Phone no. (02672) 242200 (R) 242629
4. GUJARAT POLLUTION CONTROL BOARD 20, Haidari Society, Opp: DSP Bungalow,
CIVIL Lines road Godhra. Dist : Panchmahals Phone No: (02672)245869/245991
5. CENTRAL POLLUTION CONTROL BOARD Western zonal office, Synergy house-2,Gorwa
Subhanpura road, Vadodara-390023 Phone no. (0265) 2283226, 2283239
Table 7-4- Nearest fire station/Police station
Sr/No. Name Phone nos.
1. Kalol Nagar Panchayat Fire Service station 02676- 235101
2. Kalol Nagar Police Station 02676- 235100
Table 7-5- Nearby hospitals & nursing homes
Sr/No. Name Phone Nos.
1 Dr. D.K. Supeda. 02676- 235817
2 Referral Hospital, Kalol 02676- 235937
3 ESI Hospital, Kalol 02676- 235390
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
181 | P a g e
Table of Contents 8 CHAPTER 8 PROJECT BENEFITS ................................................................................... 1
8 Chapter 8 Project Benefits ............................................................................................ 182
8.1 Introduction ............................................................................................................. 182
8.2 Employment Potential ............................................................................................ 182
8.3 Improvement in Physical & Social Infrastructure ................................................. 182
8.4 Other Tangible Benefits .......................................................................................... 182
8.5 Corporate Environment Responsibility (CER) ...................................................... 183
List of Tables Table 8-1 CER Budget ........................................................................................................... 183
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
182 | P a g e
8 Chapter 8 Project Benefits
8.1 Introduction
Project benefits focus on those points which become beneficial to the surrounding area or
community in terms of infrastructural development, Social development, employment and other
tangible benefits due to project. Proposed expansion project has a potential for employment of
skilled, semi-skilled and unskilled employees during construction phase as well as operational
phase.
8.2 Employment Potential
Total 546 persons will be employed, potential for skilled & unskilled, for the operation and
maintenance in efficient way. First Preference will be given to the local people from nearby
villages according to the skill as well as requirement which will increase employment opportunity
in the surrounding area. Secondary jobs and indirect employment are also bound to be
generated to provide day-to-day needs and services to the work force and industrial activity.
The employed people are benefited financially as this financial growth fulfills their economic
requirements, which in turn will increase their standard of living.
8.3 Improvement in Physical & Social Infrastructure
Following will be other improvements in the physical infrastructure:
Adoption of new technology.
Awareness in local educated people for new technology.
Improvement in local amenities facilities.
Improvement in road link facilities as transportation through truck and other vehicles will
increased due to proposed project.
Improvement in local civilization.
Increase income of local population
Increase requirement of man power
Due to proposed project activity, social infrastructure will be improved by means of
civilization, vocational training and basic amenities.
Civilization: Due to the project, employment and other infrastructural facilities will boost up
income of surrounding people and improve quality of life. This will indirectly boost up the
civilization of the surrounding people.
Basic Amenities: Better education facilities, proper healthcare, road infrastructure and
drinking water facilities are basic social amenities for better living standard of any human
being which will further increase the above amenities directly/indirectly either by providing
or by improving the facilities in the area, which will help in uplifting the living standards of
local communities.
8.4 Other Tangible Benefits
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213 - Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
183 | P a g e
Employment & trade opportunities will be generated with the starting of the proposed expansion
activities. Thus, these considerable employment & trade opportunities will eventually result in
appreciable economic benefits to the local people & businesses/contractors. Proposed
expansion project will also contribute revenue to the State exchequer in the form of GST –goods
& services tax which includes excise duty, income tax, state sales tax or VAT, tax for interstate
movement, etc. Direct GST contribution to the State exchequer will be there due to Income by
way of registration of trucks, payment of road tax, income tax from individual as well as taxes
from associated units. Thus, the proposed expansion project will help the Government by
paying GST from time to time, which is a part of revenue and thus, will help in developing the
area.
Benefits of GST implementation in the country will reduce manufacturing costs due to lower
burden of taxes on the manufacturing sector. Hence prices of consumer goods will be likely to
come down causing increased demand and consumption of goods leading to increase in supply.
Hence this will ultimately lead to rise in the production of goods & increase growth in both
domestic and international trade. Thus, it would bring an increase in the GDP.
The CSR activities by the company can be considerably beneficial for the health, education,
upliftment of poor people, welfare of women & labors, assistance to the disabled people etc.
These all together with the economic benefits of the proposed project will result in further
benefits in terms of the literacy level, primary and middle level education and on health facilities.
8.5 Corporate Environment Responsibility (CER)
Industry will provide 1 % of the proposed expansion project cost (i.e. 3.5 Lakh) towards the
Corporate Environment Responsibility. Socio-economic development activities will be planned
based on the as well as general necessity in villages
Table 8-1 CER Budget
Type of Activities
Total amount to be spent (Rs.)
1st Year 2nd Year 3rd Year Total amount
Awareness Programme to nearby people
regarding basic sanitation/hygiene and rain
water conservation
46,100 46500 23,400 1,16,000
Mosquito fogging during mosquito breeding
season at villages 49000 49000 24,500 1,22,500
Provision of medical equipments like stretcher,
wheel chair, BP monitoring machines, blood
testing kits at villages
44,500 44,500 22,500 1,11,500
Total 1,39,600 1,40,000 70,400 3,50,000
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
185 | P a g e
Table of Contents 1 CHAPTER 9 ENVIRONMENTAL COST BENEFIT ANALYSIS ..................................................
9 Chapter 9 Environmental Cost Benefit Analysis ................................................................. 186
9.1 Environmental Cost Benefit Analysis .................................................................................. 186
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka :Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
186 | P a g e
9 Chapter 9 Environmental Cost Benefit Analysis
9.1 Environmental Cost Benefit Analysis
As per EIA Notification 2006, this Chapter of the ‘Environmental Cost Benefit Analysis’ is
applicable only if it is recommended at the Scoping stage. However, as per the TOR points
issued by SEIAA, Gujarat vide File No. SEIAA/GUJ/TOR/3(a)/1803/2019 dated11/12/2019, the
Environmental Cost Benefit Analysis is not applicable and hence it has not been prepared.
188 | P a g e
Table of Contents 10 CHAPTER 10 ENVIRONMENTAL MANAGEMENT PLAN ...............................................
10 Chapter 10 Environmental Management Plan .......................................................... 189
10.1 Introduction ......................................................................................................... 189
10.2 Objective of Environmental Management Plan ................................................. 189
10.2.1 Components of EMP ........................................................................................ 190
10.3 Environmental Management Systems (EMS) .................................................... 190
10.4 Environmental, Health and Safety (EHS) ........................................................... 190
10.5 Environmental Management Cell (EMC) ............................................................ 191
10.5.1 Environmental Management Plan of Proposed Project ................................ 192
10.5.2 Environment management during operational phase for proposed ............ 192
10.6 Greenbelt Development Plan .............................................................................. 195
10.7 Rain Water Harvesting Scheme .......................................................................... 196
10.7.1 Runoff Calculation & Provision of Rainwater Tanks: .................................... 198
10.8 Occupational Health Management Plan ............................................................. 198
10.8.1 Induction Foundry Safety Fundamentals ....................................................... 199
10.8.2 Induction Electrical System Safety ................................................................. 200
Safety Recommendations for Supervisors & Managers .............................................. 200
10.9 Fire & Safety Management Plan ......................................................................... 201
10.10 Cleaner Production Technologies ...................................................................... 201
10.11 Budget for Environment Protection Measures .................................................. 202
List of Tables Table 10-1EMP for construction phase ................................................................... 192
Table 10-2EMP for Operational phase ..................................................................... 192
Table 10-3Details of Plant Species in Greenbelt .................................................... 196
Table 10-4Proposed Five Years Program for Greenbelt Development ................. 196
Table 10-5 Details of Rain Water Harvesting .......................................................... 198
Table 10-6 Budgetary allocation towards Environmental Management for
proposed project ....................................................................................................... 202
List of Figures Figure10-1 Environmental Management Cell ...................................................................... 191
Figure 2- Typical Diagram of artificial aquifer recharge through RWH ............................. 197
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
189 | P a g e
10 Chapter 10 Environmental Management Plan
10.1 Introduction
To formulate and monitor Environmental Protection measures during and after commissioning
of project, preparation of Environmental Management Plan (EMP) is required. The development
of sound Environment Management Plan is important to mitigate any adverse impacts of the
proposed expansion project. The plan should indicate the details as to how various measures
have been or are being proposed to be taken including cost components as may be required.
Cost of measures for environmental safeguards should be treated as an integral component of
the project cost and environmental aspects should be taken in to account at various stages of
the project.
Conceptualization: Preliminary Environmental Assessment.
Planning: Detailed studies of Environmental Impacts and design of safe
Guards
Execution: Implementation of Environmental safety measures
Operation: Monitoring of effectiveness of built in safe guards
The maximum amount of pollution load that can be discharged in the environment without
affecting the designated use and is governed by dilution, dispersion and removal due to natural
physico-chemical and biological processes is the Assimilative capacity of the study area. The
main objective of Environmental Management Plan is to warrant that the industrial development
in an identified particular study area needs to be entangled with judicious utilization of non-
renewable resources and to ensure that the stress/load on the ecosystem is within its
permissible assimilative capacity i.e. its carrying capacity.
The Environment Management Plan (EMP) is required to ensure sustainable development in
the area of the proposed expansion plant. Hence, it needs to be an all encompass plan for
which the proposed industry, Government, Regulating agencies like Pollution Control Board
working in the region and more importantly the affected population of the study area need to
extend their co-operation and contribution. The identification and quantification of impacts based
on scientific and mathematical modelling.
The Environmental Management Action Plan aims at controlling pollution at the source level to
the possible extent with the best available technology followed by treatment measures before
they are discharged. The recycling and re-use of industrial waste not only reduces the waste
generated but can be an economic gain to the industry.
10.2 Objective of Environmental Management Plan
The objective of the Environmental Management Plan is summarized as under:
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
190 | P a g e
To limit/reduce the degree, extent, magnitude or duration of adverse impacts.
To treat all the pollutants i.e. liquid effluent, air emissions and hazardous waste with adoption
of adequate and efficient technology.
To comply with all the norms and standards stipulated by Gujarat Pollution Control
Board/Central Pollution Control Board.
To create good working conditions.
To reduce any risk hazards and design the disaster management plan.
Continuous development and search for innovative technologies for a cleaner and better
environment.
10.2.1 Components of EMP
EMP for the proposed project covers following aspects:
Description of mitigation measures which are proposed for project operation phase only.
Description of monitoring program.
Institutional arrangements.
Implementation schedule and reporting procedures.
All above aspects and objectives are kept in the view and considering the same EMP is
prepared for two major fields.
10.3 Environmental Management Systems (EMS)
Unit is well aware of environmental requirements for planning and implementation of the project
and Unit has set up a department with trained personnel headed under the qualified EHS
officer. As indicated in the impact and mitigation chapter of this report, the environmental impact
after proposed activity is very marginal release of pollutants due to the same.
10.4 Environmental, Health and Safety (EHS)
Unit has make environmental management a part of overall Environment, Health and Safety
(EHS) Management system. This model EHS system suggests and addresses EMS issues
such as:
Management system expectation
Management leadership, responsibilities and accountability
Risk assessment and management
Compliance and other requirements
Personnel, training and contractor services
Documentation and communications
Facilities design and construction
Operation, maintenance and management
Community awareness and emergency response
EHS performance monitoring and measurement
Incident investigation reporting and analysis
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
191 | P a g e
EHS management system audit
Management review and audit
10.5 Environmental Management Cell (EMC)
For effective implementation of the monitoring program, Unit has a permanent organizational
set-up as it is proposed expansion unit. Thus, unit has set-up permanent Environmental
Management Cell (EMC) for the effective implementation and monitoring of environmental
management system as given below.
EMC is regularly monitoring all project activities to ensure the appropriate implementation of all
environmental mitigation activities and to identify areas where environmental management plan
compliance is not satisfied. Responsibilities have been assigned to officer from various
disciplines to perform and co-ordinate the activities concerned with management and
implementation of environmental control measures. Partners of the company will be responsible
for overall environmental management. EHS officer will inform all the matter regarding
environmental management including reporting of non compliances / violations of environmental
norms.
Figure10-1 Environmental Management Cell
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
192 | P a g e
10.5.1 Environmental Management Plan of Proposed Project
Table 10-1EMP for construction phase
Description Source
Type of Pollutant/
Pollution
Potential
Control Measures
Various
Environmental
Parameters
such as
air, water,
noise, land/soil,
flora, fauna,
socio
economic,
Occupational
health & safety
There will not be any
major construction
activities carried out for
proposed expansion
project. There will be
only construction
activities related to
installation of
machineries for the
proposed expansion
project.
Particulate matter,
Fugitive
Emissions,
Domestic
Wastewater,
Noise,
Municipal waste,
hazardous waste
etc.
Regular sprinkling of the water
will be recommended during
the construction phase.
Tarpaulin sheet will be used to
cover the materials during
transportation.
Preventing maintenance of
machinery and transportation
vehicles should be carried out
regularly.
Regular use of PPE like nose
masks, gum-boots & hand
gloves while working.
Adequate space will be
provided for construction of
temporary sheds for
construction workers mobilized
by the contractors. Unit will
also supply potable water for
the construction workers.
10.5.2 Environment management during operational phase for proposed
The EMP for the proposed expansion project during its operational phase has been prepared for
the various environmental attributes like Air, Water, Land, Noise, Ecology, Socio-Economic etc
Table 10-2EMP for Operational phase
Description Source
Type of
Pollutant/Pollution
potential
Control Measures
Air Environment
Stack attached
to Induction
furnace, AOD
PM, SO2 and NOx
Bag filter has been
provided to the stack
attached to induction
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
193 | P a g e
unit
and D.G. Sets
(Stand By)
furnace and AOD unit.
LDO will be used as fuel for
D.G. Set.
Proposed adequate stack
height will be provided for
the proposed AOD unit,
induction furnace and DG
set to control & disperse
the air pollutants within the
stipulated norms.
Water
Environment
Domestic
wastewater
Low Pollution
Potential
The domestic wastewater
generated will be treated in
unit’s own STP.
Industrial
wastewater
Slightly High
Pollution Potential
Industrial wastewater will be
generated from pickling process
and cooling blow-down along
with softening regeneration
water.
Stream from rinsing of pickling
bath will be collected in
separate acid proof brick lined
collection cum equalization
tank.
The stream will be then
subjected to physico –chemical
treatment for precipitation of
metallic salts in its hydroxide
form through raising the pH to
@ 9 to 9.5.
The physico chemically treated
mass will be pumped to plate
and frame type filter-press to
remove the hydroxide of metals.
The wet cake from the filter
press will be periodically
removed and it will be dried and
stored in a sludge storage area
for the final disposal to
authorized TSDF site.
The clear supernatant from the
filter press will be collected in
intermediate treated water
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
194 | P a g e
sump and where stream or
cooling bleed-off along with
softening regeneration water
will be received and pH of
waste water will be corrected to
neutral by addition of mineral
acid, in case of need.
The final neutralized treated
effluent will be then utilized as
makeup water of direct cooling
of sections of rods from rolling
mill.
Solid/
Hazardous
Waste
Management
Manufacturing
Activity,
Wastewater
Treatment
ETP Sludge +
Evaporation Residue,
Used Oil, &
Discarded Plastic
Bags/Drums
The ETP Sludge so
generated will be disposed-
off to the approved TSDF
site.
Used Oil will be sold to
registered recycler.
Discarded Plastic
Bags/Drums will be sold to
authorized vendor.
Hazardous waste storage
area is adequate for storing
additional waste generated
due to proposed project
activities.
Noise
Environment
Plant
Equipments and
various
Machinery
Low Pollution
Potential
In proposed unit all Noise
suppression measures
such as enclosures, buffers
and/or protective measures
will be provided, if required
necessary arrangement will
be made after proposed
(wherever noise level is
more than the prescribed
norms).
Same as proposed
practices employees will be
provided with ear protection
measures like earplugs or
earmuffs. Earplug will be
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
195 | P a g e
provided to all workers
where exposure is 85 dB
(A) or more.
The transportation
contractor will be informed
to avoid unnecessary
speeding of the vehicles
inside the premises.
Regular oiling, lubrication
and preventive
maintenance will be carried
out for the machineries and
equipments to reduce noise
generation.
Unit will develop the
greenbelt area, within
industrial premises and
around the periphery to
prevent the noise pollution
in surrounding area.
10.6 Greenbelt Development Plan
The main objective of the green belt is to provide a barrier between the plant and the
surrounding areas. The green belt helps to halt soil erosion, make the eco-system more
sustainable, make the climate more conductive and restore water balance. The green belt helps
to capture the fugitive emissions and to attenuate the noise generated in the plant apart from
improving the aesthetics of the plant site.
Unit will develop the greenbelt area, which will be upgraded greenbelt within industrial premises
and around the periphery.
Out of total plant area 43000 m2, the 14200 m2 (33%) area will be developed into greenbelt
areas. Considering the environmental status of project area four main parameters like salinity,
draught, fire resistance, species with faster growth rate and ever green nature have been
considered while selecting the species.
Facts considered during selection of plant species for greenbelt development are:
Agro climatic zone (dry sub humid – as per CPCB) of the project area
Evergreen species to mitigate cumulative impacts due to other industries also.
Type of pollutant (mainly air) likely to disperse from project activities.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
196 | P a g e
Biological–filter Efficiency: Absorption of gases, Dust capturing and noise control.
Details of the selected plant species for greenbelt area up gradation are given in the Table.
Table 10-3 Details of Plant Species in Greenbelt
Common Name of Trees Scientific Name Number of Species
Neem Azadirachta Indica 500
Gulmohar Delonix Regia 200
Asopalav PolyalthiaLongifolia 100
Mango Mangifera Indica 500
Shisham Dalbergia sissoo 300
Garmalo Cassia Fistula 200
Teak Tectono Grandis 300
Shirish AlbizioLebbeck 100
Total species 2000
Table 10-4 Proposed Five Years Program for Greenbelt Development
Proposed Five Years Program for Greenbelt Development
Plantation
Details
1st
Year
2nd
Year
3rd
Year
4th
Year
5th
Year Total
No. of plants 800 360 360 360 120 2000
Yearly
Percentage of
plantation to
be done
40 % 18 % 18 % 18 % 6 % 100 %
10.7 Rain Water Harvesting Scheme
Rain water harvesting is the technique of collection and storage of rain water at surface or in
sub surface aquifer, before it is lost at surface run off. The augmented resource can be
harvested in the time of need. Artificial recharge to ground water is a process by which the
ground water reservoir is augmented at a rate exceeding that under conditions of replishment.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
197 | P a g e
Tips for Maintenance of the R H S
Always keep the surroundings of the tank clean and hygienic.
Remove Algae from the roof tiles and asbestos sheets before the monsoon.
Drain the tank completely and clean from inside thoroughly before the monsoon.
Clean the water channels (Gutters) often during rainy season and definitely before the first
monsoon rain.
Avoid first 15 or 20 minutes of rain fall depending on the intensity of rain. Use the first flush
arrangement to drain off this first rain water.
Change the filter media every rainy season.
In coastal area the tank may be painted outside by corrosion resistant paint once in 3 years and
in other areas lime (Calcium Carbonate) based white wash may be applied not only for beauty
but also for cleanliness.
Withdraw water from the system at the rate of 5 lits/head/day.
This will ensure availability of water throughout the water scarcity period.
Cover all inlet and outlet pipes with closely knife nylon net or fine cloth or cap during non-rainy
season to avoid entry of insects, worms and mosquitoes.
The substances that go into the making of the roof should be nontoxic in nature.
Figure 2- Typical Diagram of artificial aquifer recharge through RWH
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
198 | P a g e
10.7.1 Runoff Calculation & Provision of Rainwater Tanks:
The dependable rainfall of the project area is 792.61 mm. Calculation of rain water to be
harvested based on yearly rainfall and runoff is given in Table 10.5.
Table 10-5 Details of Rain Water Harvesting
Particular Details
Roof top area Open area Greenbelt area
Annual rainfall (m) 0.792
Catchment area available
(m2) 11770 12459 14200
Coefficient of runoff (as
per CGWB guideline) 0.85 0.20 0.15
Area wise volume of rain
water can be
harvested (Kilo Liter/year)
7923.56 1973.5 1686.96
Total volume of rain water
can be harvested
(KL/year)
11584.02
11584.02 KL/Year rain water will be used to recharge the ground water aquifers.
10.8 Occupational Health Management Plan
Currently, Industry has adopted all precautionary methods to reduce the risk of exposure of
hazards to employees and same will be continued after proposed, specifically:
Pre-employment and periodical medical examinations will be carried out to assess the health
status of the workers and medical records for the same will be maintained for each
employee.
A qualified doctor will be appointed on casual basis and required medicines, antidotes and
first-aid box will be procured under the guidance of appointed doctor as per guidelines of
Factory Act.
Personal Protective Equipment’s (PPEs) like helmet, goggles, hand gloves, safety shoes,
nose masks and ear protecting devices like ear plugs/ear muffs will be provided to all the
workers.
Adequate numbers of firefighting equipment and extinguishers will be installed as per
requirement of the fire risk in the proposed plant.
Proper training will be imparted to employees for use of safety appliances & first aid.
All workers will be trained on respective Standard Operating Procedure (SOP) so as to
enable them to prevent any possible mishaps.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
199 | P a g e
All loading/unloading will be carried out under technical guidance as per the Standard
Operating Procedure (SOP) generated for the particular raw material/product.
All pollution control equipment are periodically checked and maintained.
The work place area monitoring will be carried out for Particulate Matters (PM), VOCs &
Noise on regular basis.
Good housekeeping, proper and adequate ventilation and lighting will be arranged for better
workplace area as per guidelines of Factory Act.
Water purification and water cooler will be provided for safe drinking water.
10.8.1 Induction Foundry Safety Fundamentals
Working with molten metal always has been, and always will be, a dangerous occupation. An
induction furnace is a place where three ingredients that are not otherwise brought together –
water, molten metal and electric current – are in close proximity to each other.
The quality of the components that make up an induction furnace system and the care that goes
into its assembly and maintenance are the foundry worker’s first line of defense against
accidents.
While it is impossible to remove the risk from melting metal, it is possible to make the melt shop
an accident-free workplace. It requires management to make safety a key corporate value, then
to communicate that to the foundry workers both by selecting the safest available equipment
and by expending every possible effort to assure that workers are instructed in its proper use. The only way to assure that no one is ever injured in the melt shop is to keep all personnel
away from molten metal, furnaces and holding and pouring equipment.
While this may seem like a farfetched solution, leading furnace manufacturers have actually
made considerable progress in designing remote furnace charging, operating and pouring
systems. Until these technologies are in common use, there are several steps foundry
supervisors can take to minimize worker contact with high risk areas.
Furnace manufacturers and other foundry equipment suppliers are continually attempting to
make the melt shop the safest possible work environment. That’s why virtually all induction
melting systems today include safety features such as ground leak detectors and backup cooling
systems.
Selecting the proper furnace, power supply or preheating and charging system is, of course, a
complex technical task. Frontline supervisors who become involved in equipment selection,
however, are in a good position to also evaluate a system’s safety features, safety certifications,
overall quality and operational efficiencies.
To avoid any occupational health hazards workers involved for handling of hazardous Materials
are trained for proper handling of materials as per standard operating procedure with safety
measures and aware about characteristics of hazardous materials with display of do’s and
don’ts at handling area, as well as provided required PPES and not allow to work without PPEs.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
200 | P a g e
Periodic training and awareness regarding handling of Hazardous materials and induction
training for new workers. Periodic medical examination carried out at frequency of 6 months
for any occupational diseases through registered hygienist and records shall be kept in form 33
& 34.
10.8.2 Induction Electrical System Safety While induction systems present more exposed conductive surfaces than other industrial
equipment, they are designed with a variety of safety systems to deal with these hazards. For
example, current handling bus bars and components are surrounded by enclosures.
Safety interlocks turn off power if power supply access panels (except bolted-on panels) or
doors are opened while the unit is running. They are also designed to prevent accidental starting
if access panels or doors are open.
The following are basic rules for electrical safety on the melt deck:
Only trained and qualified personnel who have read and understood the equipment
manuals are to be permitted to run induction melting equipment. A trained operator must
be fully knowledgeable about the system’s controls, alarms and limits, diagnostic functions
and safety features, and must be fully versed in the rules and procedures related to the
system’s operation.
Induction melting equipment must not be run if any safety systems are inoperable or
bypassed.
Unless a system operator is also a trained and qualified electrical service technician, he
must never open the power supply cabinet doors or gain access to any secured high
voltage area.
Power to the furnace must be turned off whenever any process involving contact with the
metal bath is taking place, such as taking samples, checking metal temperature or
slagging. This is to prevent electrocution if safety systems should fail and the bath is in
conductive contact with the induction coil.
Keep cabinet doors and access panels locked and bolted- on panels in place at all times.
Safety Recommendations for Supervisors & Managers
Supervisors need to be especially aware of electrical safety. Increased use of induction furnace
technology has made it necessary for a growing number of maintenance and repair workers to
come into close proximity to high current conductors.
Many maintenance technicians, particularly those who work with low-voltage devices, such as
control systems, do not fully appreciate the risk posed by the high levels of voltage and current
used in induction melting.
It is imperative these individuals be impressed with the fact that shortcuts, such as overriding
safety interlocks during troubleshooting, are absolutely unacceptable when working with even
the smallest induction furnaces and power supplies.
Only trained and qualified personnel are to have access to high-risk areas. A safety lockout
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
201 | P a g e
system is another effective measure to prevent electrical shock.
The following procedures can help minimize the risk of electrical accidents while servicing
induction furnace coils, power supplies and conductors:
Post warning notices for all systems operating at high voltages as required by OSHA and
local codes.
Allow only trained and qualified personnel to perform maintenance or repair. Disconnect
and lockout/ tag-out the power supply during maintenance.
Forbid entry into any enclosures until the main circuit interrupter is locked in the OFF
position and circuit interrupter poles are confirmed to be open.
Wait 5 minutes after opening a circuit interrupter before opening cabinet doors. This
allows capacitors time to discharge.
Test all bus bars for residual voltage before touching.
If the power supply energizes more than one furnace, leads to the furnace undergoing
maintenance or repair must be disconnected from the power supply and the furnace
induction coil grounded
10.9 Fire & Safety Management Plan
Currently the company has provided sufficient fire extinguishers and fire hydrant systems for
protection of the plant building against fire due to electrical spark and short circuit. After
proposed the same will be upgraded in which automatic type fire extinguishing system will be
provided to protect the control and computer room areas from fire hazards.
Qualified and trained officers are managing the environment and safety department in the plant
and all persons in operation and maintenance of the plant have been given basic firefighting
training and after proposed the same will be maintained.
To avoid short-circuiting an earthing system will be designed and installed for a ground fault
short circuit. Grid resistance will be decided based on soil resistively and allowance for
corrosion. Electrical equipment will be flame proof. To avoid road accident due to spillage of
fuels and blockages of road, proper parking and road safety signs both inside and outside the
plant will be displayed. DCP, fire hydrant line, Foam, ABC & CO2 will be provided as fire fighting
instruments.
Good housekeeping, proper and adequate ventilation and lighting has been arranged for better
workplace area as per guidelines of Factory Act.
10.10 Cleaner Production Technologies
Currently, unit has adopted following cleaner production techniques:
Measured quantities of raw materials to minimize waste.
Automated and enclosed filling system is used to minimize spillage.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
202 | P a g e
Regular preventive maintenance for avoiding leakage, spillage etc. Is being carried out. After
proposed unit will upgrade cleaner production techniques for water conservation, hazardous
waste minimization, good housekeeping practices, maximum reuse/recycle, energy saving
etc. wherever possible;
Carrying out energy audit at regular time interval.
Installation and efficient use of rain water harvesting system.
Reusing treated industrial effluent in industrial activities.
Reusing spent/waste oil for lubrication in machineries and equipments within the premises.
Adopting good housekeeping practices by maintaining cleanliness in premises and providing
regular training and giving instructions for the same.
10.11 Budget for Environment Protection Measures
Unit will regularly and efficiently operate environmental management systems and keep
provision for fund for meeting expenses for the same. The budgetary allocation towards
Environmental Management for the proposed project is presented in the Table.
Table 10-6 Budgetary allocation towards Environmental Management for proposed
project
Operation Phase (Rs.) in Lakhs
S.No. Pollution Control Measures Capital cost
per annum Rs. (Lakhs)
Recurring Cost Rs.
(Lakhs/Annum) 1 Air Pollution Control 40 10
2 Water Pollution Control 15 5
3 Noise Pollution Control 2 1
4 Occupational Health & safety,
firefighting system 20 10
5 Green Belt 4 2
6 Hazardous waste 3 4
7 AWH Monitoring Cost 2 2
Total 86 34
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
204 | P a g e
Table of Contents 1 CHAPTER 11 SUMMARY & CONCLUSION ..................................................................................
11 Chapter 11 Summary & Conclusion .................................................................................... 205
11.1 Introduction ........................................................................................................................... 205
11.2 Air Environment ................................................................................................................... 205
11.3 Water Environment .............................................................................................................. 205
11.4 Noise Environment .............................................................................................................. 206
11.5 Land/Soil Environment ....................................................................................................... 206
11.6 Socio-Economic Environment .......................................................................................... 206
11.7 Conclusion ............................................................................................................................. 206
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
205 | P a g e
11 Chapter 11 Summary & Conclusion
11.1 Introduction
Generally any project or action includes various impacts, which vary in magnitude as their
beneficial or adverse classification. At the same time it is very important to conclude that the
“overall” or “collective” impact of the proposed expansion project is beneficial or detrimental.
In case of the proposed expansion project, impacts are evaluated with respect to various
activities during operational phase.
11.2 Air Environment
The general meteorological data collected during the study period confirms that climatic status
of the study area is consistent with the regional meteorology. Baseline AAQ data indicates that
98th percentile concentration of PM10, PM2.5, SO2, NOX, CO & VOCs in the study area are well
within the permissible limits as prescribed in the National Ambient Air Quality (NAAQ)
standards.
Based on the ground level concentration evaluated by Dispersion Modelling, it is found that due
to the operation of proposed expansion project incremental values of various parameters are
well within the permission limits as prescribed in the National Ambient Air Quality (NAAQ)
standards. Hence, it may be concluded that there would not be any adverse impacts on
surrounding air environment within the study area due to the proposed project.
11.3 Water Environment
Baseline data reveal that as per drinking water quality standards (IS 10500) overall quality of
both surface & ground water is suitable for domestic activity including agricultural activity.
Ground water quality in the area meets the Water Quality Standards (IS 10500) for drinking
water except for parameters like Chloride, Calcium, Magnesium and coliforms whereas surface
water quality in the area meets the Water Quality Standards (IS 10500) for drinking water
except for parameters like TDS, Turbidity, Chloride, Total Hardness, Magnesium and coliforms.
The total water requirement for proposed expansion will be 128 KL/Day. Water will be obtained
through bore well to fulfil such requirements. However, industry proposed to install rainwater
harvesting system to collect the rain water and use in the domestic purpose.
Domestic wastewater will be treated in the treated in unit’s own STP and industrial wastewater
will be collected and treated in ETP. Treated effluent will be reused for gardening. Thus, it can
be concluded that there would not be any significant adverse impact on the water environment
due to the proposed project.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
206 | P a g e
11.4 Noise Environment
Noise level in the project premises will be controlled at the source itself by appropriate use of
noise suppressing systems. Noise level in the surrounding study area is well within the
permissible limits as prescribed in the National Noise Quality Standards. Thus, noise generated
due to the project activity shall create negligible impact in surrounding environments. This shall
further be attenuated by a barrier of plantation at the periphery of the plant.
11.5 Land/Soil Environment
The soil pollution is generally due to wastewater and solid waste. There will be no industrial
wastewater discharge as treated effluent will be ultimately evaporated off in an evaporator. Solid
waste generation will be very less during operation phase of the proposed project. Hazardous
waste will be properly collected, stored & ultimately disposed off to secured landfill/TSDF site.
All the solid/hazardous wastes generated from the unit after proposed will be properly collected,
stored & ultimately disposed off as per the applicable Act/Rules prescribed by statutory
authority. Therefore, there would be no adverse impact on the land environment due to the
proposed project.
11.6 Socio-Economic Environment
The proposed expansion project will generate employment during operation phase. The indirect
employment will also be generated by way of transportation, shopkeepers and other casual
employment for many people during operation phase as well as construction phase. Local
people will be given preference for the jobs in the proposed expansion project. Economic status
of the local people will improve due to the increased business opportunities, thereby making a
positive impact. Educational, medical and housing facilities in the study area will considerably
improve. Thus, the proposed expansion project will have significant positive impact on the
employment pattern of the study area.
11.7 Conclusion
Negligible impacts will occur on air quality. However, all the necessary air pollution control
measures will be provided.
No ecological damage will occur.
No adverse impacts will occur on water environment.
Local employment opportunities will increase.
Various other environment parameters like Forest/ National Park/ Sanctuary and Religious /
Historical Places will not be affected.
Environment Management Plan has been formulated to control all the pollutant parameters
and Environment Management Cell has been set-up to ensure that these parameters do not
exceed the norms set out by the concerned authorities.
Draft Environment Impact Assessment Proposed expansion of integrated steel manufacturing plant with production capacity of 28,000 MTPA to
90,000 MTPA, Area 43000 m2 at Plot no. at 213- Madhwas, Halol Kalol Road, Taluka: Kalol, District: Panchmahal – 389330, Gujarat by M/s. Rajputana Stainless Ltd.
207 | P a g e
After commissioning of the proposed expansion project the Environmental Management Cell
will take care of all the pollution control measures.
It can be concluded on a positive note that after the implementation of the mitigation
measures and environmental management plan during the construction &operational phase,
there will be negligible impact on the environment.
CHAPTER- 12
DISCLOSURE OF CONSULTANTS ENGAGED
11.1 ORGANIZATIONAL PROFILE
Ambiental Global Private Limited is a leading environmental consulting organization promoted
by young professionals with experience and expertise in diverse sectors, thereby providing viable
solutions and professional services to promote environmental sustainability.
Apart from its own resources, Ambiental Global Private Limited also has association with
several leading consultancy firms who have competency and expertise in other areas. The
associations with these firms have helped to address the deliverables in an integrated fashion.
Each project is a value addition to the organization and hence results in environmental, economic
and social upliftment.
Ambiental Global Private Limited is accredited by QCI/NABET having certificate no.
NABET/EIA/1922/IA0047 valid till dated 17th June, 2022 for carrying out EIA/EMP study of
seven sectors as per EIA Notification, 2006 released by Ministry of Environment Forest &
Climate Change (MoEF & CC).
Ambiental Global Private Limited provides integrated solutions to complex problems in diverse
business areas of EIA, environment planning and site management. We thrive on quality, cost,
effectiveness and timely delivery of projects and have hence in a short span of time, successfully
accomplished a number of projects.
Consultancy Services
Environmental Impact Assessment HAZOP Study
Air Quality Assessment and Control
Measures
Environmental Remediation Consulting
Engineering
Water and Waste Water Quality
Assessment, Treatment and Management
EHS& Occupational Safety Management
Consulting
Soil Quality Assessment Preparation and Implementation for Various
sectors
Source apportionment Study Remediation Construction & Site Restoration
Carrying Capacity Study Solid Waste Management Services
Environmental Management Plan Natural resource management
Consent Management ETP & STP Establishment and Operation
Socioeconomic & Impact Assessment Environmental Research and Development
Environmental Legal Advice Training and Skill Development
Declaration by Experts contributing to the EIA: For Proposed Expansion
“METALLURGICAL INDUSTRIES (FERROUS & NON FERROUS)” located at 213/1 ,213/2
,212/1 ,212/2 ,184 ,185 ,186/1 ,183/1 ,183/2 ,183/3 ,182/1, 214/1, 214/3 - Mahwas, Halol Kalol
road, Taluka: Kalol, Dist. Pachmahal – 389330, Gujarat. I, hereby, certify that I was a part of the
EIA team in the following capacity that developed the above EIA.
EIA coordinator:
Name Akansha Rampuria
Signature
Period of involvement Dec 2019 to till date
Contact Information R/o Plot no. 16, Second floor, Sector-04, Vaishali, District:
Ghaziabad, State: Uttar Pradesh, Pin Code- 201010.
Following Coordinators & Functional Area Experts:
S.No. Name of Person EC/FAE/FAA/TM Area of Expertise Signature
1. Praveen Singh EIA Coordinator & FAE EB
2. Laxmi Singh EIA Coordinator & FAE WP, SW
3. Punit Lal Mahto EIA Coordinator & FAE GEO, LU, HG
4. Aakanksha Rampuria EIA Coordinator & FAE AQ, SHW, WP,
AP
5. Pawan Kumar Bharti FAE NV, RH, AP, SC
6. Neha Singh FAE NV
7. Jaya Singh FAE SHW, RH
8. Ajeet Prasad FAE SE
9. Akash Gupta Assistant Manager Team
Member
Declaration by the Head of the accredited consultant organization/ authorized
person: I, Sourabh Tyagi, hereby, confirm that the above mentioned experts prepared the EIA:
Proposed Expansion “METALLURGICAL INDUSTRIES (FERROUS & NON FERROUS)”
located at 213/1 ,213/2 ,212/1 ,212/2 ,184 ,185 ,186/1 ,183/1 ,183/2 ,183/3 ,182/1, 214/1, 214/3 -
Mahwas, Halol Kalol road, Taluka: Kalol, Dist. Pachmahal – 389330, Gujarat. I also confirm that
EIA Coordinator (EC) and experts has gone through the report, and the consultant organization
shall be fully accountable for any misleading information.
It is certified that no unethical practices, plagiarism involved in carrying out the work and external
data / text has not been used without proper acknowledgement while preparing this EIA report.
Name: Mr. Sourabh Tyagi,
Designation: Director
Name of the EIA consultant organization: M/s Ambiental Global Private Limited
NABET Certificate No.& Issue Date: NABET/EIA/1922/IA0047