8/20/2019 MS & RA Combined
1/49
Pu b l i c W o r k s A u t h o r i t yD R A I N A G E A F F A I R S
DOHA WEST SEWAGE TREATMENT WORKSEXTENSION # 05
egis
CONTRACTOR
Suez Environment- Marubeni JV
8/20/2019 MS & RA Combined
2/49
8/20/2019 MS & RA Combined
3/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 3 / 23 Date: 31/12/2015
1. PURPOSE The purpose of this procedure/method statement is to provide the minimum requirements for the
handling&Installationof following GRP pipelinesof partial UG Network (Drawing shown below) at Doha West
Sewage Treatment Plant Extension 5 works as per project standard and specification:
a. 482B_ECA101A - Clarified water connection.
b. 482B_ECA101B - Clarified water connection.
c. 539_ESA008_ - Equalization tank - Waste water pump common header underground.
d. 488C_BAC011_ - SAS to Balancing Tank 610B.
g. 582_1ECA008_ - Line from PSF pumps to PSF header.
h. 582_2ECA008_ - Line from PSF pumps to PSF header.
i. 929_EID001_ - Industrial water supply to industrial water network.
j. 929_EID002_ - Industrial water supply to industrial water network.
8/20/2019 MS & RA Combined
4/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 4 / 23 Date: 31/12/2015
2. SCOPE The scope of this procedure describes the general requirements and procedure for the Transportation,
Offloading & Installation of following GRP pipelines:
a.482B_ECA101A
b. 482B_ECA101B
c. 539_ESA008_
d. 488C_BAC011_
g. 582_1ECA008_
h. 582_2ECA008_
i. 929_EID001_
j. 929_EID002_
as per the requirement of client for “Doha West Sewage Treatment Plant Extension 5 works”.
3. APPLICABLE CODES, STANDARDS AND REFERENCES
QCS 2010
General arrangement drawings:
DGT-M-DA-482-801
DGT-M-DA-581-801
DGT-M-DA-581-802
DGT M DA 581 803
8/20/2019 MS & RA Combined
5/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 5 / 23 Date: 31/12/2015
4. DEFINITIONS AND ABBREVIATIONS 1. Definition
Pipes : Circular tubes through which fluid can flow
Installation : Material transport and handling, pipe laying including the complete operationof laying, jointing and testing pipes in trenches.
Pipeline : long, continuous line of pipes and fittings including valves and ancillary structures
Plant : Doha West STP
Client : Suez Environment Marubeni JV
Consultant : Egis.
Contractor : Asiatech Engineering & Contracting WLL
2. Abbreviation
SUEZ : Suez Environment
HSE : Health, Safety & Environment
BLDG. : Building
GRP : Glass Reinforced Plastic
UG : Under Ground
PTW : Permit To work
QA/QC : Quality Assurance / Quality Control
5. RESPONSIBILITY
8/20/2019 MS & RA Combined
6/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 6 / 23 Date: 31/12/2015
Project Manager:Shallberesponsible for the execution of the projectactivities as per this procedure and to
ensure that works are taken in safe manner, to the requisite quality and to agreed time scale.
Site Engineer:Shallreview the work and liaises with QA/QC to jointly ensure that all the QC documents are
properly maintained.
Supervisor:Shall be responsible along with the safety officer to ensure the required compliance to safe
working practices. He shall arrange all necessary equipment, tools and tackles with the other related team
and direct /guide the work force.
QA/QC Engineer/Inspector : In conjunction with the Engineer, is responsible and dedicated for inspection
and quality control in accordance with the specification. Any non-compliance must be reported to the
concerned manager and be guided by him to resolve the same.
Safety Off icer:Shall be responsible for the implementation of safety procedures on site. And he will ensure
that the work will be proceeded in accordance with the safety procedure/policy and are undertaken in asafe and proper manner.
6. MATERIALSHANDLING AND STORAGE
1. Collect the required permanent materials from the client for the installation work.
2. Before receiving the material check for the permanent identification like nominal diameter, name of
manufacturer, iso number or any other references.
3. Transport, handling and storage of pipes and fittings shall be carried out as follows:
a) In accordance with the manufacturer’s recommendation.
b) Effective precaution shall be taken to prevent damage to the pipe and fitting.
8/20/2019 MS & RA Combined
7/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 7 / 23 Date: 31/12/2015
7. MANPOWER, TOOLS AND EQUIPMENT
1. Direct Manpower
- Supervisor - 01
- Safety Supervisor - 01
- QA/QC Inspector - 01
- Surveyor - 01
- Fitter - 04
- Helper - 06
- Rigger - 02
2. Tool s & Equipment
- Trailer - 01
- Crane 25T - 01
- Total Station - 01
- Fitter Tool Box - 04 set
- Chain puller - As per requirement
- Fabric slings- As per requirement
8. PROCEDURE
8/20/2019 MS & RA Combined
8/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 8 / 23 Date: 31/12/2015
Join ing of GRP pipes:
Joining of pipes shall be made as per the procedure and directions of pipe supplier. Thefollowing steps to be followed during installation of GRP pipes. There are different types methodof joining and the following joining method and procedure shall be applied;
All the pipes as per the required length shall be joined with coupling, which is called as double
bell coupling joint. The following steps shall be followed;
- Foundation & Bedding: The bed must be over excavated at each joint location to ensure
that the pipe will have continuous support and does not rest on the coupling. The
coupling area must be properly bedded and backfilled after the joint assembly completed.
- Cleaning of Coupling: All the coupling grooves and other parts shall be thoroughly
cleaned to ensure no dirt, presence of oil and any other unwanted particles inside thecoupling and its groove. (see below cleaning method)
8/20/2019 MS & RA Combined
9/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 9 / 23 Date: 31/12/2015
- Clean and Lubricate Spigots: Clean thoroughly the pipe spigots to remove any dirt, grit, grease and
other unwanted/foreign materials (see below picture). Inspect the spigot sealing surface for possible
damage and apply a thin layer of lubricant to the spigots from the end to the black alignment stripe.
Keep clean both the coupling and spigot until completion of insertion.
- Coupling shall be mounted on one pipe, prior join two pipes together, by using clamp or sling
around the pipe at a distance of 1 to 2 meter from the spigot on to which the coupling will be
mounted.
- Make sure that the coupling as well as the pipe should have enough gaps from the ground or at
least 100 mm above the ground level to keep away from dirt. Other techniques may also be used
8/20/2019 MS & RA Combined
10/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 10 / 23 Date: 31/12/2015
The final spool or the closure spool to be installed will be DSP spools, in some cases it will be the
rocker pipes with DSP.
Select two couplings to be installed and place one coupling square onto the end of closure pipe (with
8/20/2019 MS & RA Combined
11/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 11 / 23 Date: 31/12/2015
- Flanged Joints : GRP flanges shall be joined according to the following procedure;
1. Clean the flange face thoroughly and the O-ring groove as well
2. Ensure the sealing gasket / O-ring is clean and undamaged.
3. Position the sealing gasket/ O-ring in the cleaned groove and be secured with small strips of
tape or adhesive.
4. Align flanges to be joined and tightened with required bolts, nuts and washers.
5. Tighten all the bolts by using proper spanners/torque wrench and check the torque value with
Manufacturer.
6. Check all the bolts once again after one hour to ensure the bolts are properly tightened or to
adjust to get the required torque value if necessary.
8/20/2019 MS & RA Combined
12/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 12 / 23 Date: 31/12/2015
It is important that to control the bolting torque of the flexible steel coupling. Do not over
tight/torque these coupling bolts and follow only manufactures recommended assembly
instructions, but with the pipe supplier’s recommended bolt torque limits.
Mechanical Steel Couplings: Mechanical couplings have been successfully to join pipes ofdifferent materials and diameters, and to adapt to flange outlets. If a mechanical coupling is used
to join GRP to another pipe material then only mechanical coupling with dual independent bolting
system shall be used (see below picture). This allows for the independent tightening of the GRP
pipe side, which typically requires less torque than recommended by the coupling supplier.
8/20/2019 MS & RA Combined
13/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 13 / 23 Date: 31/12/2015
9. INSTALLATION SEQUENCE FOR PARTIAL UG NETWORK
Partial UG Network is divided into two zones as per the drawing shown.
8/20/2019 MS & RA Combined
14/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 14 / 23 Date: 31/12/2015
General Layout
8/20/2019 MS & RA Combined
15/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 15 / 23 Date: 31/12/2015
Zone 1 installation sequence:
Station A-A:
C O P
+ 3 9 3 5 0
C O P
+ 4 0 5 0 0
B O P
+ 4 0 4 5 5
C O
P + 3 9 5 0 0
B O P + 3 9 0 9 0
B O P + 3 8
6 3 4
B O P + 4 0 2 8 7
SECTION : A-A
Ø 1 4 0 0
Ø 1 4 0 0
Ø 8 0 0
Ø 4 0 0
Ø 8 0
Ø 8 0
488C_BAC011
539_ESA 008 929_EID001 929_EID002
482B_ECA101B
2150
482B_ECA101A
2500
1500
1450
1510
Station A-A location:
53,600 mm from 482 B (puddle included).
North coordinate: 505000.
8/20/2019 MS & RA Combined
16/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 16 / 23 Date: 31/12/2015
Station B-B:
C O P + 3 9 3 5 0
B O P
+ 3 8 6 3 4
SECTION : B-B
Ø 1 4 0 0
Ø 1 4 0 0
482B_ECA101B 482B_ECA101A
3000
Station B-B:
49.515 mm from 581(puddle pipe included)..
E t di t 631550
8/20/2019 MS & RA Combined
17/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 17 / 23 Date: 31/12/2015
1. 482B_ECA101A/B: the installation of both the lines will be carried out in parallel
a. General Installation Procedure will be followed to install both the pipelines
b. The sequence of installation of pipes will be based on the attached drawing AQAP-0501-15-JC& AQAP-0502-15-JC
c. After completing the installation of the both pipeline carry out visual inspection and proceed to installnext line in the sequence.
2. 539_ESA008 (Approx. 162 mtr)
a. General Installation Procedure will be followed to install the pipelines
b. The sequence of installation of pipes will be based on the attached drawing AQAP-0504-15-JC
c. After completing the installation of the pipeline carry out visual inspection and proceed to install
8/20/2019 MS & RA Combined
18/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 18 / 23 Date: 31/12/2015
c. After completing the installation of the both pipeline carry out visual inspection and for carrying outthe various test based on line list DGT-X-LT-000-801-B and inspection based on approved ITP.
Line will be partially backfilled keeping coupling area clear for the hydro-test.Hydro-test and deflection test procedures are submitted separately.
Backfilling sequence will be part of civil works method statement
Zone 2 installation sequence:
Station C-C:
Ø 1 4 0 0
Ø 1 4 0 0
Ø 8 0 0
Ø 8 0
Ø 8 0
B O P
+ 3 6 7 7 9
C O P
+ 3 7 1 8 9
C O P
+ 3
7 5 0 0
B O P
+ 3 6 7 8 4
C O P + 3 9 5 0 0
B O P
+ 3 9 3 6 4
929_EID001
929_EID002
539_ESA 008
582_2ECA 008
582_1ECA 008
3000 2500 1000
500
8/20/2019 MS & RA Combined
19/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 19 / 23 Date: 31/12/2015
1. 582_1ECA008 / 582_2ECA008 :The installation of both the lines will be carried out in parallel
a. General Installation Procedure will be followed to install both the pipelines
b. The sequence of installation of pipes will be based on the attached drawing AQAP-0507-15-JC& AQAP-0508-15-JC
b. After completing the installation of the both pipeline carry out visual inspection and proceed toinstall next line in the sequence.
2. 539_ESA008 (Continuation from Zone 1 to Trench li mit
a. General Installation Procedure will be followed to install the pipelines
c. The sequence of installation of pipes will be based on the attached drawing AQAP-0504-15-JC
d. After completing the installation of the pipeline carry out visual inspection and proceed to installnext line in the sequence.
8/20/2019 MS & RA Combined
20/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 20 / 23 Date: 31/12/2015
& AQAP-0522-15-JC
c. After completing the installation of the both pipeline carry out visual inspection and for carrying outthe various test based on line list DGT-X-LT-000-801-B and inspection based on approved ITP.
Lines will be partially backfilled keeping coupling area clear for the hydro-test.Hydro-test and deflection testprocedures are submitted separately.Hydro-test and deflection test procedures are submitted separately.
Backfilling sequence will be part of civil works method statement.
10. SAFETY PRECAUTIONS
a) Isolate the area with proper barrier and warning tape in order to control unauthorized entry to the
working area.
b) Provide common safety equipment at site (fire extinguisher, bucket with sand, fire watch etc.) in
accordance with fire and safety regulations.
c) Prior to start the activity; ensure that all work permit have been obtained from concerned authorities as
per the general site requirements.
d) Ensure that all lifting equipment shall be certified and the lift/drop zone shall be barricaded with warning
tape and sign boards.
e) Daily tool box talk shall be conducted by the supervisor prior to commencement of each day activity.
8/20/2019 MS & RA Combined
21/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 21 / 23 Date: 31/12/2015
LIFTING ARRANGEMENT
8/20/2019 MS & RA Combined
22/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 22 / 23 Date: 31/12/2015
C C
8/20/2019 MS & RA Combined
23/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OFGRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 03
Page 23 / 23 Date: 31/12/2015
Typical Sections.
ASIATECH
9500
SECTION : X-X
Ø 1 4 0 0 Ø 1 4 0 0
Ø 8 0 0
Ø 4 0 0 Ø 8 0
Ø 8 0
8500 8500
639929_EID002
482B_ECA101A 482B_ECA101B
488C_BAC011
539_ESA 008
929_EID001
8/20/2019 MS & RA Combined
24/49
8/20/2019 MS & RA Combined
25/49
8/20/2019 MS & RA Combined
26/49
8/20/2019 MS & RA Combined
27/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OF
GRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 02
Date: 13/12/2015
SEQUENCE OF INSTALLATION
8/20/2019 MS & RA Combined
28/49
8/20/2019 MS & RA Combined
29/49
8/20/2019 MS & RA Combined
30/49
8/20/2019 MS & RA Combined
31/49
8/20/2019 MS & RA Combined
32/49
8/20/2019 MS & RA Combined
33/49
8/20/2019 MS & RA Combined
34/49
8/20/2019 MS & RA Combined
35/49
8/20/2019 MS & RA Combined
36/49
8/20/2019 MS & RA Combined
37/49
8/20/2019 MS & RA Combined
38/49
8/20/2019 MS & RA Combined
39/49
8/20/2019 MS & RA Combined
40/49
8/20/2019 MS & RA Combined
41/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
8/20/2019 MS & RA Combined
42/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OF
GRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 02
Date: 13/12/2015
INSPECTION & TEST PLAN
8/20/2019 MS & RA Combined
43/49
Doc. No.:
Rev. No.:
Date:
PIPING
DGT-ME-0-IT-0028
0
26/11/2014
Inspection Test Plan
Doha West Sewage Treatment Works Ext 4
UNDERGROUND GRP PIPING INSTALLATION
Activity:
Location / WorkLot
TypeName /
SignatureType
Name /
SignatureType
Name /
Signature
0
0.1 100%Lamination procdure
No
Manufacturer
recommendation, project
specification
Approved lamination
procedureH A R
0.2 100%Lamination procdure
Manufacturer
recommendation, projectLaminator Qualification
H A R
Fit up training
certifciate to be
RFI is not resquested
RFI is resquested
Equipment / Tag N° or Line Ref.:
Subcontractor/ N°:
SUEZ
Inspection
SUBCONTRACTOR
InspectionInspection / Test Activity
EGIS
InspectionITP Item No. Frequency ITR N° applied Acceptance criteria Documentation Comments
Review of Procedures & Qualifications
Lamination procedure
GRP Laminators Qualificationo
,
specificationecor
included as well
1
1.1 100% DGT-ME -0-TR-001
Approved drawing &
applicable material
specification, relevant
project specification
Material Delivery Note H M -
1.2 100% DGT-ME -0-TR-003
Relevant project
specification,
manufacturer standards
Material Delivery Note H R -
2
2.1 100% DGT-ME -0-TR-004
Manufacturer
recommendation, project
specification
H W W** For puddle pipe only
other wise blank
Lamination kits and consumables inspection
Trench readiness inspection and Puddle Survey
Free issue material inspection
Material Control
Pipe and Spool Erection
2.2 100% DGT-ME -0-TR-005Project specification,
scope of workIsometric Drawing H W R
First spool to be
installed to be inspected
2.3 100%DGT-ME-0-TR-002
DGT-ME-0-TR-007
Manufacturer
recommendation, project
specification
Approved lamination
procedureH W R
Inspection during
jointing, edge
preparation, bevels,
cleaning, root gap,
composition and layers,
lamination length,
thickness, Barcol test
2.4 100%DGT-ME-0-TR-006
DGT-ME-0-TR-012
Check Coordonates,
Spool N° Location as per
Isometrics.
Isometric Drawing H H WRelease for Pipe partial
bacfilling
Line Setting out and Survey for first spool locations and
identification.
Line installation completness check (including valves,
instruments….)
Field Butt-Wrap & Coupling joins (when cuttings are done at
site).
8/20/2019 MS & RA Combined
44/49
Doc. No.:
Rev. No.:
Date:
PIPING
DGT-ME-0-IT-0028
0
26/11/2014
Inspection Test Plan
Doha West Sewage Treatment Works Ext 4
UNDERGROUND GRP PIPING INSTALLATION
Activity:
Location / WorkLot
TypeName /
SignatureType
Name /
SignatureType
Name /
Signature
RFI is not resquested
RFI is resquested
Equipment / Tag N° or Line Ref.:
Subcontractor/ N°:
SUEZ
Inspection
SUBCONTRACTOR
InspectionInspection / Test Activity
EGIS
InspectionITP Item No. Frequency ITR N° applied Acceptance criteria Documentation Comments
3
3.1 100% DGT-ME -0-TR-008Proper Isolation and
Safe condition provided
Isometric Drawing and
P&IDH W -
Not apply for Visual
inspection
3.2 100%DGT-ME-0-TR-009
DGT-X-LT-000-801, Pipe
Testin rocedures, H H W
Release for Pipe testing
Pipe Testing: Pressure Test, Visual Inspection, Deflection
Flushing & Pipe Testing
.DGT-ME-0-TR-013
,
Project Specification
3.3 100% DGT-ME -0-TR-010 H W -
3.4 100% DGT-ME -0-TR-011 P&IDIsometric Drawing and
Red Mark up drawingsH H W
4
4.1 100%
As per Hand Over
Procedure
DGT-Z-IA-000-001
ITP Signed off with all
ITR uploaded to PWWorkpack procedure H R R
Once to worklot is
completed
4.2 100%Red Mark up
DrawingsRed Mark up Drawings H R R
Flushing of process line (or cleaning when flushing is not
appicable).
TYPE OF INSPECTIPONComment:
Test, Air test.
QA/QC documentation
Documentation
Final Installation after reinstatement
Red Mark up Drawings
M: Monitor
R: Review of document
A: Approval
H: Hold point
W: Witness
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
8/20/2019 MS & RA Combined
45/49
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
METHOD STATEMENT FOR THE INSTALLATION OF
GRP PIPELINES FOR PARTIAL UG NETWORK
Doc No: AT-SUEZ-MS-0017/15
Rev. 02
Date: 13/12/2015
RISK ASSESSMENT
8/20/2019 MS & RA Combined
46/49
RISK ASSESSMENT
Risk Assessment Area Risk Assess ment DOC NO: RA-AT-SUEZ-019
Occupational Health &safety S
GRP PARTIAL UG PIPE INSTALLATION
Contract No. DW5-001-2015
Environment E Date : 31/12/2015Quality Q
SlNo
Description of Act ivi ty
Hazard Potential andConsequences
P C RiskL/M/H
Precautionary Measures and Safeguardsto control the risk
P C RiskL/M/H
1. SitePreparation
Personal Injury/ SeriousInjury / Property Damageand Heat Stress thepersonals / Personal Injuryduring Manual handling /Slips, trips and falls due to
Uneven ground surface orslippery surface / SharpObject in leveled area couldcause Foot injuries.
3 2 Med Obtain PTW and prepare JSA prior to start thework.
Before Start of the work conduct the Tool boxTalk Meeting
Ensure First Aid kit should be available alwaysduring the work period.
Ensure emergency contact numbers should bedisplayed
Ensure all personals to be instructed as to thesymptoms of Heat Stress and how to deal withsuspected cases.
Employees to wear mandatory PPE all timeduring work and has to wear task oriented PPEif it is required.
All the Personnel involved must be trained andcompetent
Access should check before enter inside thechamber
Access and egress must be clear all timeduring work and suitable lights need to beprovided in access and egress area for thenight shift.
Work area must be clean from all obstructions Area should be barricade Select proper suitable certified Cranes Check the work permit Supervision is mandatory during the activity Entry for Un-authorized personnel must be
prohibited in the working area
3 1 Low
8/20/2019 MS & RA Combined
47/49
Appropriate signage must be placed.
2. Critical Lifting Boom truck failure/Riggergear failure, lift due to strongwind/stand storm poorvisibility, /Serious Death,Serious injury, PropertyDamage.
3 4 High Use proper Use PPE ‘s at all times Ensure all riggers should be certified by
approved third party rigging and slingingtraining.
Crane operator must be trained, competentand certified by third party.
Adequate access at lifting vicinity should bemaintained
Safety Officer should closed monitoring ofErection of Structure erection activity closely incase any problems he can stop the work
Certified cranes shall be used. PTW must be implemented. Critical or common lifting must be carried out
under the supervision of trained and competentlifting supervisor and supervisor must bepresent all time during the activity.
Critical lifting must be carried out as per the
lifting plan and lifting procedure. Over sized slings and shackles are used to
minimize rigging gear failure. All personnel involved in lifting must be
properly instructed and familiarized with alllifting plan details.
Crane boom swing movement should notobstruct other facilities.
Site pro-lift meeting will be held for finalinstructions and personnel conditionverification.
Only personnel involved in the lifting will be
present at site. Under no circumstances lifting will be started if
wind speed is higher than 30km/h All lifting activities will be carried out during day
time to ensure best visibility. Don’t allow people to work directly below load
being lifted or under suspended load Tag line should tied at both end of lifting
objects Tool box talk should be conducted before
proceeding to work.
3 1 Low
8/20/2019 MS & RA Combined
48/49
Lifting area must be segregated andbarricaded with appropriate signage.
3. Climate(WeatherCondition)
Property Damage / PersonalInjury
3 2 Med Ensure Weather condition is good beforestarting the job
In case rain / sand storm will comes we shouldproperly cover any electrical, Electronic
equipment and stop the all cranes for the windspeed above 30 km/h.
Ensure while raining time to stop any liftingactivity.
3 1 Low
4. ElectricalCables
Personal Injury / SeriousInjury / Property Damage
3 4 High Electrical Cables should be free of any wear ordamages.
MCB & RCCB is required. Every week Electrical Supervisor or Electrician
Should check/inspect visibly and it should berecorded.
3 1 Low
5. Lifting
Operation indark time
Personal Injury / Serious
Injury / Property Damage
3 4 High Any lifting activity in evening (Dark time) time
should provide proper lighting. Lifting of materials in vertical position or
horizontal position by crane only Ensure trained rigging crew required All lifting Equipments should Certified by third
party.
3 1 Low
6. Cutting &Grinding
Personal injury / Burninginjury/ Property damage
3 4 High Ensure check the Hot work permit with validdate
Provide proper Fire Extinguisher (ABC) Ensure cutter should use face shield, apron,
etc... & proper PPE’s. Arrangement for sufficient passage of air Ensure work area always keep clean tied. Ensure any combustible materials area fire
watch person required Ensure Electrical cables are in good condition Check the Grinding machine in good condition Ensure grinding m/c have safety guard , handle Any electrical problems inform to maintenance
Electrician or Electrical Supervisor Maintain good house keeping
3 1 Low
8/20/2019 MS & RA Combined
49/49
Ensure any flammable liquid in cutting areashould be removed and then start the job
7. Bolt Nut Fixing Falling Hazards/ PersonalInjury
3 2 Med Ensure bolt nuts tighten only using CalibratedTorque wrench
Ensure use of correct size nut bolts. Ensure use of appropriate PPEs
3 1 Low
8. Use of PPE Personal Injury 3 3 Med Ensure that all persons using proper PPE suchas Safety helmet, goggles, hand gloves, safetyshoes,
Personnel should wear necessary safetyprotective Equipment during work and it shouldbe related to that particular activity.
3 1 Low
Prepared By : EMMANUEL-HSE SUPERVISOR
Checked By : BIJU PONNAN-WORK SUPERVISOR
Approved By : NIDHIN THAMPY-SITE MANAGER
Signature :
Signature :
Signature :
Date : 31/12/2015
Date : 31/12/2015
Date : 31/12/2015
LOW = GREEN P = Probability
MED = ORANGE C = Consequence
HIGH = RED R = Risk Level