CONSTRUCTION MANAGEMENT
TERMS OF REFERENCE FOR
Planning, designing & Feasibility of the Project
FEASIBILITY, PLANNING, DESIGN AND
FINANCIAL SERVICES FOR MULTI-STOREY
RESIDENTIAL COMPLEX AT VIT CHENNAI
CAMPUS
Name of Consultants: -Prof. Ramesh Kannan
GROUP MEMBERS:-
SHAIK KHAZAMOHIDDIN -11BCL1012SATYA GANESH -11BCL1047
8/14/2019 ms project report.pdf
2/7
Introduction:
The feasibility studies stage considers the options for satisfying the client's needs, enabling
the client to prepare a business case for the preferred option and deciding whether to proceed
with the project. It is possible to make an outline planning application during this stage if
the risk to the project of not receiving planning permission is high, or if delays inreceiving planning permission would be problematic.
MS project is designed to assist a project manager in developing a plan, assigning resources to
tasks, tracking progress, managing the budget, and analyzing workloads, Cost Estimation can be
done in feasibility report.
Objective:-
To prepare feasibility report,
Planning, design and financial services for Multi-Storey Residential-cum-Commercial
Building at vit campus site Chennai.
Sub Activities:
Survey and soil investigation
Preparation of Feasibility Report and financial viability of Project.
Master Plan and Conceptual Plan
Design Development & tender Documents
Invitation of Tenders and evaluation of Bids
Detailed design & Construction drawings
Top Supervision
TIME SCHEDULE
CONSULTANTS FEE STRUCTURE
REMUNERATION OF SERVICES
Complete Final Inspections
8/14/2019 ms project report.pdf
3/7
Methodology
SEQUENCE of MS Project:-
1. Set overall project information: goals, scope, assumptions, start date, manager
2. Create a Base Calendar, assign it to the project and to the Gantt chart.
3. List tasks and milestones, estimate durations
4. Outline the project (create Summary Tasks)
5. Link the tasks
6. Assign resources
7. Evaluate and refine the project
8. Save a Baseline
9. Track and update the projectActuals
10.Communicate progressReports
11.Close the project
TASK Allocation:
1. Commercial Construction 11.General Conditions
2. Long Lead Procurement 12.Mobilize on Site
3. Grading and Utilities 13. Foundations
4. Steel Erection 14.Form and Pour Concrete Floors and Roof
5. Carpentry Work 15. Masonry Work
6. Roofing 16. Window wall and
7. Store front closure 17.Building Finishes
8. Elevators 18.Plumbing
9. Electrical 19.Heating and Ventilating - AC
10. Final Clean-up and Occupancy 20.Complete Final Inspections
8/14/2019 ms project report.pdf
4/7
RESULTS AND DISCUSSIONS: Task and Resource sheet Gantt chart:
8/14/2019 ms project report.pdf
5/7
Resource and Cost Allocation:-
8/14/2019 ms project report.pdf
6/7
GANTT CHART VIEW:-
8/14/2019 ms project report.pdf
7/7
References: -
http://www.designingbuildings.co.uk/wiki/Construction_management:_feasibility_studies
Construction management basics byDaniel W. Halpin Construction Management Fundamentals byClifford,Richard Mayo
http://www.designingbuildings.co.uk/wiki/Construction_management:_feasibility_studieshttp://www.designingbuildings.co.uk/wiki/Construction_management:_feasibility_studieshttp://www.google.co.in/search?tbo=p&tbm=bks&q=inauthor:%22Daniel+W.+Halpin%22http://www.google.co.in/search?tbo=p&tbm=bks&q=inauthor:%22Daniel+W.+Halpin%22http://www.google.co.in/search?tbo=p&tbm=bks&q=inauthor:%22Daniel+W.+Halpin%22http://www.google.co.in/search?tbo=p&tbm=bks&q=inauthor:%22Richard+Mayo%22http://www.google.co.in/search?tbo=p&tbm=bks&q=inauthor:%22Richard+Mayo%22http://www.google.co.in/search?tbo=p&tbm=bks&q=inauthor:%22Daniel+W.+Halpin%22http://www.designingbuildings.co.uk/wiki/Construction_management:_feasibility_studies