POLITEKNIK KOTA BHARUDEPARTMENT OF MATEMATHICS, SCIENCES & COMPUTER
COURSE : BC101 COMPUTER APPLICATIONLAB WORK :
TOPIC : MS PROJECT
The end of session, the student should be :
OBJECTIVES:
(i) Know the MS Project Environment
(ii) Create a new project plan
(iii) Create a task list
8/8/2019 Ms Project Labsheets
2/6
1.1 Starting Project and create New Project Plan
PROCEDURES:
On the window taskbar, click Start > All Programs > click Microsoft Office Project 2003
On file menu, click New. In New Project task pane, click Blank Project.
On Project menu, click Project Information
8/8/2019 Ms Project Labsheets
3/6
8/8/2019 Ms Project Labsheets
4/6
Enter the task name Pre-implementation Study into the Task Name column.
Enter the following task name below:Develop frameworkMaking orderSimulationInstalling hardwareProgramming and SettingTestingDocumentationTraining
Press ENTER after each task name.
1.4 Estimating Duration
Click below the Duration column heading for task 2 , Develop framework, type 5d and press ENTER
Enter the following duration for the remaining tasks.
3 Making order 3dTask ID Task Name Duration
4 Simulation 2d5 Installing hardware 2d6 Programming and Setting ( ENTER to skip )7 Testing 2d
8 Documentation 2d9 Training 1d
1.5 Entering a MilestoneMilestone is required to track an important event for your project, such as when Pre-implementation study ofthe project will end.
On the Insert menu, click New Task. A new row will insert. Type Pre-implementation StudyComplete.
Enter 0d for duration of this task.
8/8/2019 Ms Project Labsheets
5/6
1.6 Organizing Tasks into PhasesTo create two summary tasks by indenting tasks.
Select the names tasks 2 through 6, on Project menu, point to Outline and then click Indent.
Repeat Outline and Indent for tasks 8 through 10.
1.7 Linking TasksTo create links between several tasks, thereby creating finish-to-start relationships.
Select the names of tasks 2 through 6, on the Edit menu, click Link Tasks.
Repeat Link Tasks for tasks 8 through 10.
To link the two summary tasks, select the name task 1 and, while holding down the CTRL key, selecttask 7, click Link Tasks from Edit menu.