Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
PRE-FEASIBILITY REPORT
1.0 EXECUTIVE SUMMARY:
1.1 Project & Project Proponent
M/s Padmavati Steels Limited located at Trilokpur Road, Kala Amb, Village
Johron, Tehsil Nahan and Dist. Sirmaur, Himachal Pradesh, this plant
manufactures MS Bars, G I Pipes, ERW Pipes and M.S. Scaffoloding.
M/s Padmavati Steels Limited. is an existing composite Rolling Mills unit
which plans to install three Induction furnaces each with capacity of 15 MT in
addition to one Rolling Mill with production capacity of 36000 MTPA at
Trilokpur Road, Kala Amb, Village Johran, Tehsil Nahan and Dist Sirmaur,
H.P. making the total capacity 67500 MTPA of MS billets along with 45000 MT
capacities of rolled products.
Project falls under Category A due to interstate boundary of Haryana
within 10 Km as Metallurgical Industries (secondary metallurgical
processing) Item 3(a) of the schedule of EIA notification of Sept 14, 2006
issued by MOEF & CC.
Water for construction and domestic purpose will be drawn from Department
of Industries and Commerce (DIC). Approximately 14 KLD water will be used
for during operational phase. Existing Power load is 5,000 KW & additional of
4,800 KW will be required plant & machinery during Construction and
Operation Phase. Expected source is Himachal Pradesh State Electricity Board
(HPSEB). Total Plot Area: 4.77Ha
1
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
1.2 Salient Features of the Project
SALIENT FEATURES OF THE PROJECT
PROJECT PROFILE The steel plant will be expanded for
the projected production of 67,500 MT
/annum from the current production
of 36000 MTPA of Rolled products
after the expansion of current from
2.25 Hectares to 4.77Hectares.
LOCATION LATITUDE: 30O 31’ 05.84” E
LONGITUDE: 77 O 12’ 04.07” N
EXISTING CAPACITY: 36000 MTPA of Rolled Product
PROPOSED CAPACITY: 67,500 MTPA of Billets
PROPOSED ROLLING MILL SECTION MATERIAL REQUIRED
REQUIRED ROLLING MATERIAL 45000 MTPA
LESS WASTAGE @4% 1800.00
HOT ROLLED STRIPS/BARS 43200.00
BILLETS/INGOTS REQUIRED 45000.00
LESS
BILLETS/INGOTSINDEGENOUS
45000.00
PIPE MILL SECTION MATERIAL REQUIRED
HOT ROLLED STRIPS/BARS 43200.00
LESS WASTAGE @2% 900.00
PIPE MANUFACTURED 43200.00
GALVANISING SECTION MATERIAL REQUIRED
AVAIABLE ERW PIPES 42300.00
ADD. INC. IN WT. IN THE
PROCESS@3%
12600
G. I. PIPE 43500.00
2
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
ANNUAL RAW MATERIAL REQUIRMENT AT 100% CAPACITY
SCRAP REQUIRED 70875.00
BILLETS/INGOTS REQUIRED 0.00
SILICO MANGANESE 1063.125
ALUMINIUM SHOTS 708.750
ZINC 8.700
LAND AREA 4.77Hectares (56-14Bighas )
SCREENING CATEGORY 3(a) Category A as per EIA Notification
14th Sep, 2006 and amended thereof.
COST OF THE PROJECT Rs. 37.36 Crores
RESOURCE REQUIREMENT
SOURCE & QUANTITY OF
WATER
Source: DIC (Industries Department, and
Govt. of Himachal Pradesh).
Quantity : Currently Approximately 10
KLD is being utilized for domestic and
industrial purpose & Approximately 14
KLD water will be used after the proposed
expansion
POWER Existing Power load is 5,000 KW &
additional of 4,800 KW will be required for
plant & machinery during Construction
and Operation Phase
Total Power Load: 9800KW
Source: Himachal Pradesh State
Electricity Board (HPSEB)
MAN POWER Present Employees: 302
Proposed Employees after expansion: 635
ENVIRONMENTAL MANAGEMENT SYSTEM
WASTE WATER Domestic waste water generated will be
send to septic tank/ soak pit, hence no
generation of sewage sludge at site. Water
shall be used in boilers and also for
3
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
cooling purpose in proposed project
activity. The same shall be reused within
the plant premises after neutralization
FLUE GAS EMISSION Stack attached to induction furnace, boiler
and DG sets will lead to emission. Exhaust
emissions from the DG sets and stacks of
suitable height are provided as per
SPCB/CPCB guidelines.
Particulate matter, Sulphur Dioxide and
Nitrogen Oxides will be the major
pollutants.
HAZARDOUS WASTE Sludge, Used oil, Discarded containers /
liners.
Environmental control measures
Air pollution Bag filters for emissions from
Induction Furnaces
Wet scrubbers for emissions from
Re-heating Furnace
Provision of stack of 30 m height for
discharge of emissions as per CPCB
guidelines
Water pollution Quantitative recycle of effluents to
maintain “Zero effluent discharge”
Domestic wastewater treated in
septic tanks with soak pit disposal.
Noise: Acoustic enclosures for DG set and
other noise generating machines
Hazardous wastes Slag from induction furnaces, dust
collected in bag filters and sludge
from wet scrubber will be collected,
stored and sent to authorized TSDF
site
Green belt Available vacant land shall be
utilized for plantation and
development of lawns.
4
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION:
Ferro-alloys are among the essential inputs required for steelmaking. It
improves the quality of steel, by controlling the harmful impurities and at the
same time improves the mechanical properties of steel through alloying.
Growth in Global as well as domestic steel industry directly drives the demand
of Ferro-alloys. Since Indian steel industry is under massive expansion, there
is a tremendous potential for investment in Ferro-alloy production.
Steel being a basic commodity for all industrial activities, quantum of its
consumption is considered an index of industrial prosperity. Since
independence, there has been a substantial growth in the steel sector in India
from 1.5 Million Tons in 1950-51 to about 31 Million Tons at present.
Additional steelmaking capacity of about 8 to 10 Million Tons /year exists in
the secondary steel sector. Despitethe above growth in the steel sector, the
per capita steel consumption continues to remain at a level of about 27 kg
only, compared to about 350 to 450 kg in the developed countries and 40 to
100 kg in some of the developing countries. Further, with nearly 20% of the
world population, India’s contribution is only of the order of 3.4% of world
steel production. Hence, short-term and long-term strategies are necessary in
planning the development of the steel industry in the country to improve the
level of per capita steel consumption. It is expected that with the measures
taken by Govt. of India for promotion consumption of iron and steel and
expected growth of Indian economy the requirement of steel will significantly
increase and accordingly the domestic manufacturing capacity needs to be
increase.
The details of the project proponent are given below: Land Revenue record is
attached as Annexure IV.
5
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT
M/s Padmavati Steels Limited Located at Village Johran, Trilokpur Road, Kala
Amb, Tehsil Nahan and Dist. Sirmaur, Himachal Pradesh
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT
M/s Padmavati Steels Limited is an existing composite Rolling Mills unit
which plans to install three Induction furnaces each with capacity of 15 MT in
addition to one Rolling Mill with production capacity of 36000 MTPA at Village
Johran Trilokpur Road, Kala Amb, Tehsil Nahan and Dist Sirmaur, H.P.
making the total capacity 67500 MTPA of Billet.
2.3 NEED OF THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY
AND/ OR REGION
The Indian steel industry has entered into a new development stage from
2007-08, riding high on the resurgent economy and rising demand for steel.
While plant closures and privatization are rare in India, the private sector is
considered to be the engine of growth in the steel industry and technological
changes and modernization are taking place in both the public and the private
sector integrated steel plants in India. Steel production of India accounted for
14.33 million tons in 1990-91, which gradually increased to 36.12 million tons
in 2003-04. Rapid rise in production has resulted in India becoming the 3 rd
largest producer of crude steel in 2015 and the country continues to be the
largest producer of sponge iron or DRI in the world. As per the report of the
Working Group on Steel for the 12th Five Year Plan, there exist many factors
which carry the potential of raising the per capita steel consumption in the
country. These include among others, an estimated infrastructure investment
of nearly a trillion dollars, a projected growth of manufacturing from current
8% to 11-12%, increase in urban population to 600 million by 2030 from the
current level of 400 million, emergence of the rural market for steel currently
consuming around 10 kg per annum. At the time of its release, the National
6
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
Steel Policy 2005 had envisaged steel production to reach 110 million tonnes
(mt) by 2019-20. However, based on the assessment of the current ongoing
projects, both in greenfield and brownfield, the Working Group on Steel for the
12th Five Year Plan has projected that domestic crude steel capacity in the
county is likely to be 140 MT by 2016-17 and has the potential to reach 149
MT if all requirements are adequately met. The National Steel Policy 2005 is
currently being reviewed keeping in mind the rapid developments in the
domestic steel industry (both on the supply and demand sides) as well as the
stable growth of the Indian economy since the release of the Policy in 2005.
2.4 DEMAND –SUPPLY GAP
Steel production of India accounted for 14.33 million tons in 1990-91, which
gradually increased to 36.12 million tons in 2003-04. Rapid rise in production
has resulted in India becoming the 3 rd largest producer of crude steel in 2015
and the country continues to be the largest producer of sponge iron or DRI in
the world. As per the report of the Working Group on Steel for the 12th Five
Year Plan, there exist many factors which carry the potential of raising the per
capita steel consumption in the country. These include among others, an
estimated infrastructure investment of nearly a trillion dollars, a projected
growth of manufacturing from current 8% to 11-12%, increase in urban
population to 600 million by 2030 from the current level of 400 million,
emergence of the rural market for steel currently consuming around 10 kg per
annum. At the time of its release, the National Steel Policy 2005 had envisaged
steel production to reach 110 million tonnes (mt) by 2019-20. However, based
on the assessment of the current ongoing projects, both in green field and
brown field, the Working Group on Steel for the 12th Five Year Plan has
projected that domestic crude steel capacity in the county is likely to be 140
MT by 2016-17 and has the potential to reach 149 MT if all requirements are
adequately met. The National Steel Policy 2005 is currently being reviewed
keeping in mind the rapid developments in the domestic steel industry (both
7
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
on the supply and demand sides) as well as the stable growth of the Indian
economy since the release of the Policy in 2005.India is expected to become
the world's second largest producer of crude steel in the next 10 years, moving
up from the third position, as its capacity is projected to increase to about 300
MT by 2025. Huge scope for growth is offered by India’s comparatively low per
capita steel consumption and the expected rise in consumption due to
increased infrastructure construction and the thriving automobile and
railways sectors.
2.5 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE
PROJECT
The project is currently providing direct employment to 302 persons which will
be increased to 635 after the proposed expansion . Local workers will be hired
from the nearby villages.
3.0 PROJECT DESCRIPTION
3.1 Type of Project
This project is for expansion of existing steel plant for proposed capacity of
67,500 MTPA from existing capacity of 36000 MTPA of Rolled Product The
Metallurgical Industries (secondary metallurgical processing) is listed at serial
no. 3(a) of the Schedule of EIA Notification 2006 and falls under Category A
due to existence of interstate boundary with Haryana at a distance of 1 Kms.
The project is not interlinked with any other project.
3.2 Location:
The proposed location of the project is situated at village Johran, Trilokpur
road Tehsil Nahan, District Sirmaur, Himachal Pradesh.
The location details are mentioned below:-
Latitude : 30O 31’ 05.84” E
Longitude : 77 O 12’ 04.07” N
8
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
The vicinity map is given below:
Fig: 3.1 Vicinity Map of the Project Site
Project Site
9
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
Fig 3.2 Project Site
PROJECT SITE
10
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
Fig 3.3 10 Km Buffer map
11
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
Fig 3.4 Lay Out Plan
12
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
3.3 Details of Alternate Sites
No alternative site has been considered for the project, & the project will be
expanded in the land adjoining the current project site
Site Selection Criteria
Major techno-economic feasibility considerations
Land requirement and availability:
Private land owned by M/s. Padmavati Steels Limited 4.77 Hectares (56-14
Bighas
Land ownership Details:
Land is already available with M/s Padmavati Steels Limited at village
Johran, Trilok pur road Tehsil Nahan, District Sirmaur, Himachal Pradesh.
3.4 Size or magnitude of operation
The proposed project is to expand the capacity of currently existing steel
plant to 67,500 MTPA from 36000 MTPA of Rolled Product. At present there
are about 16 member units. The plant will consist of treatment units
comprising physical, chemical and biological treatment including dewatering
of sludge and other required infrastructure. The project outlay is estimated to
be around Rs. 37.36 Crores
3.5 Project description with process details
3.5.1 Manufacturing process of M.S. /S.S. Billets
(a) The Preparation of Charge
In general, induction furnaces use pig iron, sponge iron and/or iron scrap
as raw material for making steel. However, in the present case, only scrap
iron will be use as raw material. for steel making in the induction furnace.
Selected scrap of consistent quality is to be used. This is because
elimination of some elements from the molten metal is difficult in an
induction furnace and in the case where these are present in high
13
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
quantities; a secondary metallurgical unit is required to refine the metal up
to the desired extent. As soon as the furnace is charged, the switches
admitting power current to the induction coil are closed.
(b) Melting the Charge in Induction furnace
Working of Induction Furnace After the furnace is switched on; current
starts flowing at a high rate and a comparatively low voltage through the
induction coil of the furnace, producing an induced magnetic field inside
the central space of the coils where the crucible is located. The induced
magnetic fluxes thus generated cut through the packed charge in the
crucible. As the magnetic fluxes cut through the scraps and complete
the circuit, they generate an induced current in the scrap. This
induced current, as it flows through the highly resistive path of the
scrap mix, generates tremendous amounts of heat and melting of scrap
starts. As soon as the charge has melted clearly, any objectionable slag
is skimmed off, and the necessary alloying elements are added. When
these additives have melted completely, the power input may be increased
to bring the temperature of metal up to the point most desirable for
pouring. The current is then turned off and the furnace is tilted for pouring
into a ladle. As soon as pouring has ceased the crucible is cleaned
completely from any slag or metal droplets adhering to the wall of the
crucible and the furnace is now ready for charging again.
(c) Continuous Casting of Billets/Blooms
One (1) No. 4-strand continuous casting machine for casting of billets will
be used. The main operations involved in the whole process of turning out
billets/blooms are:
Checking the individual major components of the casting machine
and their synchronized operation.
Insertion of a dummy bar to close the bottom end of the mould;
14
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
Accurate centering of the tundish over the mould;
Transferring the ladle to the casting aisle and placing it on the ladle
stand of the casting machine;
Pouring of liquid steel from the ladle through a slide gate
mechanism into the lined tundish;
Pouring of liquid steel into the water cooled mould through tundish;
Passage of liquid steel through water cooled mould tubes initiated
by withdrawing dummy bar;
Oscillation of the mould
Maintaining a constant level of liquid steel in the mould and introducing
lubricants into the mould throughout the casting process;
Controlling the intensity of cooling of the emerging billets in the primary
and secondary cooling areas;
Straightening and cutting of billets.
(d) Billet Cutting
The automatic gas cutting torches are provided for cutting billets to a
desired length. The equipment comprises a water cooled structure for
trolley support, Auto cutter trolley with drive mechanism, a gas and
pneumatic panels suitable for both the strands. The trolley moves on
the rails above the hot strand in the direction of discharge. During cutting,
torch swings like a pendulum across the hot strand at a
predetermined cutting speed. In the forward direction trolley moves
at casting speed swing to the clamping of the hot strand whereas
retracting the trolley to the home position is carried out by motorized drive.
15
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
(e) Billet Processing
The billets from a particular cast are lifted from the cooling bank
and stored separately. When cooled, they are inspected on each face
for defects; surface defects are normally removed by a swing frame
grinder, etc
16
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
17
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
3.5.2 Details of Expansion Capacity
A. Proposed Melting Section
Number of Furnace 3
Capacity of Each Furnace 15 MT
Number of Heats per day 5
Number of working Hours 15 Hrs
Number of working Days 300
Capacity of Ingots 3x5x15 225 Tonnes /Day
Annual Capacity/
Production
225 × 300 Appx 67500MT/Annum
Source: Project Report
B. Rolling Mill Section
ROLLING MILL SECTION EXISTING
TONS/ DAY
PROPOESED TOTAL
TONS /ANNUM
Required Rolling Material 150 45000
Less : Wastage@ 4% 6 1800
Hot Rolled Strips/ Bars 144 43200
Billets / Ingots Required 150 45000
Less : Billets / Ingots In
House
150 45000
Balance Purchases From
Open Market
0
18
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
C. Pipe Mill Section
PIPE MILL SECTION EXISTING
TONS/ DAY
PROPOESED TOTAL
TONS /ANNUM
Hot Rolled Strips/ Bars 144 43200
Less : Wastage@ 2% 3 900
Pipe Manufactured 141 42300
D. Galvanising Section
GALVANISING SECTION EXISTING
TONS/ DAY
PROPOESED
TOTAL
TONS /ANNUM Available ERW Pipes 141 42300
Add. Inc. in Wt. in the process
@3%
4.20 1260.00
G. I. Pipe 145 43500
3.5.3 Annual Raw Material Requirement
Annual Raw material requirement at 100 % capacity is as follows
Discipline Quantity in MT
Scrap Required 70875.00
Billets/Ingots Required 0.00
Silico Manganese 1063.125
Aluminum Shots 708.750
G I Moulds 2126.250
Zinc 8.700
19
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
Raw Material Consumption at Different Capacity Levels:
Year of
Operation
Capacity
Utilization
1st Year 60%
2nd Year 70%
3rd Year 80%
Source: Project Report
3.5.3 Pollution : Source and Control Management
Flue Gas management
The flue gases generated during melting of scrap are the major source of air
pollution. Quality and Characteristics of flue gas shall be required during
dispersion modeling. Flue gas from Re-heating furnace in the Re-heating
Furnace should also be taken into account. mainly depends upon type of
Scrap used in Furnace, i.e. degree of contamination in the Scrap. These
flue gases need proper treatment for removal of dust particles before being
discharged into the atmosphere. Major pollutants generated in the process
will be Carbon Dioxide, Carbon Monoxide, Suspended dust (PM 10, PM
2.5), Sulphur Dioxide (traces), Oxides of Nitrogen (in low concentration) and
Emissions from DG sets. Currently the air Pollution Control Device (APCD)
unit i.e. bag filters is installed after the induction furnace at the facility &
its capacity will be increased in accordance with the proposed
modernization to control the emissions within permissible limit will be let-
out through stack.
Hazardous Waste Management
Slag from furnace, dust from Bag house are hazardous materials generated
on site which will be stored and transported to authorized TSDF site
located at Nalagarh Himachal Pradesh at a distance of 81 Kms from
20
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
project site .
Green Belt
Green belt will be developed according to CPCB guidelines. Plants of the
various species will be developed in the plant and peripheral areas.
Selection Criteria of plant species for Green Development Plant
The selection of plant species for the development depends on various factors
such as climate, elevation and soil. Area falls under the tropical region and
thus the plants that area adapted to this condition should be selected.
The plant should exhibit following characteristics in order to be selected for
plantation.
The species should be fast growing and providing optimum penetrability.
2. The species should be wind firm and deep rooted
3. The species should form a dense canopy.
4. As far as possible, the species will be locally available
5. Species tolerance to air pollutants like PM, SO2, and NOx should be
preferred.
6. The species should be permeable to help create air turbulence and mixing
within the belt.
7. There should be no large gaps for the air to spill through.
8. Tree with high foliage density, leaves with larger leaf area and hairy
on both the surface.
9. Ability to withstand conditions like inundation and drought.
10. Soil improving plants (Nitrogen fixing, rapidly decomposable leaf litter).
11. Attractive appearance with good flowering and fruit bearing.
12. Bird and insect attracting tree spacing
3.6 Collection and Transportation of Waste
Hazardous materials generated on site will be stored and transported to
authorized TSDF site at Nalagarh Himachal Pradesh at a distance of 81 Kms
from project site .
21
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
3.7 Resource optimization/Recycling and reuse
Various steps shall be taken for recycle/ reuse in the proposed project is as
mentioned below:
Waste water generated shall be mainly from cooling and same shall be
reused within the plant premises.
Slag from furnaces, Dust from Bag house are hazardous materials
generated on site which will be stored and transported to authorized
TSDF site as per Hazardous Waste Management and Handling Rules
2008 & amended thereof.
3.8 Availability of Water Its Source, Energy/ Power Requirement and
Source
3.8.1 Water Requirement
Currently approximately 10 KLD is being utilized for domestic and
industrial purpose & approximately 14 KLD water will be used after the
proposed expansion. Water will be provided from DIC (Industries
Department, and Govt. of Himachal Pradesh).
3.8.2 Power Requirement
Power requirement 9800 KW will be sourced from Himachal Pradesh State
Electricity Board (HPSEB). In case of power failure D.G. set will be used having
capacity of 125 KVA.
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for
their Management / disposal
Solid waste management will be done as per MSW 2000 rule & amended
thereof. Water shall be for cooling purpose in proposed project activity. Waste
water generated shall be mainly from cooling shall be reused within the plant
premises. Domestic waste water generated will be send to septic tank / soak
pit. About 10-15 m% of the total raw material used will get converted into slag
22
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
which is a hazardous waste. Slag,Dust from Bag house are hazardous
materials generated on site will be stored and transported to TSDF site.
4.0 SITE ANALYSIS
4.1 Connectivity
The Plant site is situated in Village Johron Trilokpur road, Kala Amb, Nahan
Road, Tehsil Nahan and Dist. Sirmaur. Himachal Pradesh. It is about 2.15 Km
from National Highway-72 at Kala Amb, Tehsil Nahan. The soil of the block is
sandy to sandy loam. It lies near Long 77° 12' 04.07" East and Lat: 30°31'
05.84" North and is at an Altitude of about 350 m. above mean sea level.
The site is well connected by road to neighboring city Naraingarh & Nahan
.Development of Communication systems is good in the region. Sources of
water in the region include river and ground water resources. Nearest village is
Johron which is about 0.25 Km away from the project site. The nearest
railway station is Ghaggar Railway station about 35.2 Km in the WNW
direction. The project site is located about 2.15 Km away from National
Highway No. 72. Nearest Airport is Chandigarh Airport about 43 Km in NW
direction, from project site.
4.2 LANDFORM, LANDUSE AND LAND OWNERSHIP
Land is the expansion of current area from 2.25 Hectares to 4.77 hectares.
available with M/s Padmavati Steels Limited at Village Johran Trilokpur
Road, Kala Amb, , Tehsil Nahan and Dist Sirmaur, H.P.
4.3 Topography
Sirmour district lies in the outer Himalayan ranges commonly called as
Shivaliks between 77°01’12” and 77°49’40” east longitude and 33°22’30” and
31°01’20” north latitude. The district is predominantly mountainous with deep
valleys lying between ranges of varying elevations. The district has hilly and
mountainous topography with intermontane valleys, the most prominent
23
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
being the Paonta valley. Longest length from west to east is 77 kms. and the
maximum width from north to south is 80 kms. The district is bounded by
Shimla district in the north Uttarakhand in the east, Yamuna Nagar district of
Haryana in the south and west and solan district in the north-west. The
geographical area of the district is 2825 Sq. Km. which is almost 5.07% of the
total geographical area of the state Area wise it is the fifth smallest district of
the state after Hamirpur, Bilaspur, Una and Solan districts.
Source:http://dcmsme.gov.in/dips/District%20Industrial%20Potential%2
0of%20sirmaur.pdfDistrict
Climate:
The climate of the district is sub-tropical to temperate depending upon the
elevation. Four major seasons that is the winter season extends from Nov to
February; summer season from March to June followed by the monsoon
period extending from July to September end. Maximum precipitation in the
form of rain occurs during July to September. Average annual rainfall in the
district is about 982 mm with average of 60 rainy days. In the non monsoon
season precipitation as snowfall also occurs in the higher reaches above 1500
m amsl, the peaks of Chaurdhar remains covered by snow. During winter
period rainfall also occurs in lower hills and valleys parts. Mean maximum
and minimum temperature of 30°C and 0°C respectively.
Source : http://cgwb.gov.in/district_profile/hp/sirmour.pdf
Geology:
Sirmour Distt. falls in Himalayan and Shiwalik ranges which are fairly rich in
mineral wealth covering an area of 2670 sq. kms. The important minerals
found are lime stone and gypsum. These are being used as a raw material by
the local industries as well as by the adjoining states. Soil strata here lack salt
24
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
and mineral constituents. Because of these characteristics around this town
the soil is unique for the cultivation of vegetables and for Pine (Chil) trees.
Due to youthful stage of rivers and khads on two sides and a good ration of
rainfall causes soil erosion. The soil erosion gets intensified in case of heavy
rainfall in the catchment area of “Markanda” and its surrounding khads due
to such soil conditions. No building shall exceed three storey above natural
ground level. An additional floor can be permitted purely for parking purpose
along vehicular road. The measure is expected to solve the problem of parking
of vehicle in a big way. Even if the building height is to go to more than 2
stories or otherwise all building within the planning area are to be planned
and designed keeping in view siesmic consideration as per the latest “Indian
standard codes of practice”
4.4 Existing Land Use pattern
Land is the expansion of current from 2.25 Hectares to 4.77 hectares.
available with M/s Padmavati Steels Limited at Trilokpur Road, Kala Amb,
Village Johran, Tehsil Nahan and Dist Sirmaur, H.P.
4.5 Existing Infrastructure
The infrastructure amenities available in the area denote the economic
wellbeing of the region. The project area is connected to nearest NH-72.
Educational facilities up to Senior School, College, Hospital & Banking
facilities are available at Kala Amb about 1.6 kilometers from the Site area.
The existing building comprise of rolling mill shed, Workshop shed &
Competitive administrative block With expansion, construction of furnace
Shed & concast Shed, Furnace platform, raw material shed & office quarters
are proposed in the existing premises .
4.6 Soil Classification
25
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
The soil in the district varies from thin and bare soil of high mountains to rich
deep alluvial soil of the valleys. In the hilly area i.e. northern part soils are
veneer and brown in colour, these are high base status soil of humid regions.
In the southern part, combination of shallow black, brown and alluvial soils
are found.
Source : http://cgwb.gov.in/district_profile/hp/sirmour.pdf
Soil testing will be done and will be submitted at EIA (Baseline study) stage.
4.7 Social Infrastructure available
The infrastructure amenities available in the area denote the economic
wellbeing of the region. The project area is connected by MDR-4 road to
nearest NH-72. Educational facilities up to Senior School, College, Hospital &
Banking facilities are available at Kala Amb about 2 kilometers from the
plant area.
5.0 PLANNING BRIEF
5.1 Planning Concept (type of industries, facilities, transportation etc.)
Town and Country Planning/Development authority Classification
The expansion of steel plant unit is proposed for production of 67,500
MT/annum of steel related products namely Ms Flat/Bar/Patra, ER W(Black),
GI Pipes & MS Scaffoldings .The Plant currently exists in the area of 26 Bigha
14 Biswa (2.25 Hect) with production capacity 36000 MTPA of rolled product.
5.2 Population projection
There would not be any significant development / increase in the population of
surrounding area. Workers for the proposed project will come from the local
residents in the surrounding villages. There won’t be any influx of people in
the area due to proposed project.
5.3 Land use planning
The Plant currently exists in the area of 26 Bigha 14 Biswa (2.25 Hect). For
additional production 30 Bighas (2.52 Hect) of land will be acquired alongside
26
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
the current project land. Green Belt area will be developed as per the CPCB
guidelines.
Land Revenue Records as Annexure II
5.4 Assessment of Infrastructure Demand (Physical & Social)
All facilities / amenities like medical, educational, housing, transportation,
communication, shopping etc are available nearby places from the project area
.Since, local workers will be employed for the construction during proposed
expansion ; no long term infrastructure will be required.
5.5 Amenities/Facilities
Major basic facilities are available for the proposed project. Road, electricity,
water, transportation facility etc are well developed in the surrounding area.
All the amenities related to project on the site will be installed.
5.5.1 Man Power
Man power will be required on permanent and temporary basis. A total of 635
persons will be employed after the proposed expansion. Details are mentioned
as follows
ADMINISTRATIVE STAFF
General Manager 2
Finance manager 1
Accountants 2
Purchase Manager 3
Marketing executives 2
Peon Cum Watchman 5
Security Guards 10
Total 25
27
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
FACTORY STAFF & LABOUR
Production Manager 5
Metallurgist 2
Chemist/Technician 1
Laboratory Assistant 2
Electrician 5
Skilled workers 45
Unskilled Workers 550
Total 610
Source : Project Report
5.5.2 Common Facilities
In order to meet the repair and maintenance needs of the various plant units,
the following facilities would he provided.
— Repair shop
— Servicing garage
The common facilities such as Administrative Building, Laboratory, Water
Pump house, Workshop Building, Water Storage Reservoir, and Raw Water
Pump House have already been provided in the existing plant.
5.5.3 Pollution Control Measures
The pollutants in the form of solids, liquids and gases are generated
from various technological units and, if let out as such, will have
hazardous effects on the environment. Pollution of the environment, not
only adversely affects the flora and fauna, but also shortens the life of plant
and equipment. This vital aspect, therefore, has been taken into account
while planning the plant and equipment and adequate measures have
been taken to limit the emission pollutants within the stipulations of statutory
norms. Air pollution control devices namely Wet scrubber & Bag house is
already installed with furnace. Stack of 20 meter & 30 meter height is
28
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
attached to electric arc furnace & re heating furnace for efficient dispersion of
pollutants . Acoustic enclosures have been installed in DG set.
However, before starting the plant, the detailed Environmental
Management Plan (EMP) needs to be prepared based on the findings of
an Environmental Impact Assessment study which will cover monitoring
of existing environment at site, assessment of pollution likely to be caused
by the proposed plant and its impact on the socioeconomic, flora & fauna,
demography, land use, etc.
6. PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
Being a steel producing plant adequate infrastructural facilities such as office
space, laboratory, storage area as well as production units comprising
induction unit & reheating furnace exists in the plant premises . The
expansion will make use of the facilities for land, storage of raw material and
handling, additional water & power demand, and use of road and rail network
for transportation.
6.2 Residential Area (non- Processing area)
The employees will make their own arrangements for their housing & allied
amenities in nearby area. There is no need for any additional facilities. No
labor colony is envisaged in the existing as well as proposed project.
6.3 Green Belt
Apart from the aforesaid pollution control measures the management has
decided to develop green belt covering more than 33% of total acquired
area. During plantation landscaping pattern will be considered. The
plantation scheme covers the plantation of ornamentals plants and some local
fruit bearing species. At present M/s Padmavati Steels Limited has planted
over 25000 no. of trees/saplings.
29
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
Green belt will be developed according to CPCB guidelines. Plants of the
various species will be developed in the plant and peripheral areas.
Selection Criteria of plant species for Green Development Plant .The selection
of plant species for the development depends on various factors such as
climate, elevation and soil. Area falls under the tropical region and thus the
plants that area adapted to this condition should be selected. The plant
should exhibit following characteristics in order to be selected for plantation.
1. The species should be fast growing and providing optimum penetrability.
2. The species should be wind firm and deep rooted
3. The species should form a dense canopy.
4. As far as possible, the species will be locally available
5. Species tolerance to air pollutants like PM, SO2, and NOx should be
preferred.
6. The species should be permeable to help create air turbulence and mixing
within the belt.
7. There should be no large gaps for the air to spill through.
8. Tree with high foliage density, leaves with larger leaf area and hairy
on both the surface.
9. Ability to withstand conditions like inundation and drought.
10. Soil improving plants (Nitrogen fixing, rapidly decomposable leaf litter).
11. Attractive appearance with good flowering and fruit bearing.
12. Bird and insect attracting tree spacing
6.4 Social Infrastructure
Schools, colleges, hospitals & healthcare centers, shops & bazaars,
community centers, etc. are all available in nearby area.
6.5 Connectivity
The Plant site is situated in Village Rampur Jattan, Kala Amb, Nahan Road,
Tehsil Nahan and Dist. Sirmaur. Himachal Pradesh. It is about 2.15 Km from
30
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
National Highway-72 at Kala Amb, Tehsil Nahan. The soil of the block is sandy
to sandy loam. It lies near Long 77° 12' 04.07" East and Lat: 30°31' 05.84"
North and is at an Altitude of about 350 m. above mean sea level.
The site is well connected by road to neighboring city Naraingarh & Nahan
.Development of Communication systems is good in the region. Sources of
water in the region include river and ground water resources. Nearest village is
Rampur Jattan which is about 0.25 Km away from the project site. The
nearest railway station is Ghaggar Railway station about 35.2 Km in the WNW
direction. The project site is located about 2.15 Km away from National
Highway No. 72. Nearest Airport is Chandigarh Airport about 43 Km in NW
direction, from project site.
6.6 Drinking water management
Currently Approximately 10 KLD is being utilized for domestic and industrial
purpose & Approximately 14 KLD water will be used after the proposed
expansion. Expected Source of the water is DIC (Industries Department, and
Govt. of Himachal Pradesh).
6.7 Sewerage system
Toilets are constructed at the site which are connected with the septic tanks
within the site itself which are further connected to the municipal sewerage
system of Kala Amb.
6.8 Industrial waste management
Sludge generated from treatment units would be sent to TSDF site located at
Nalagarh. Hazardous waste like used oil & containers/liners will be sent to the
authorized recyclers.
6.9 Solid Waste Management
During the processing only slag will be generated as a waste which will be
disposed off in the authorized TSDF site located at Nalagarh. Canteen waste
will be generated which shall be sold to recycler. Solid waste management will
be done as per MSW 2000 rule & amended thereof.
31
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
6.10 Power requirement & supply/source
Existing Power Load :5,000 KW
Additional Load Requirement : 4,800KW
Power supply source Himachal Pradesh State Electricity Board (HPSEB)
In case of power failure, D.G. set will be used of capacity 125 KVA.
7.0 Rehabilitation and Resettlement (R&R) Plan
There is no need of displacement of the people for proposed project, hence, not
applicable.
8.0 PROJECT SCHEDULE & COST ESTIMATES
The Project is envisaged to be undertaken immediately after getting necessary
statutory approvals.
Cost Estimates
The total cost of project is estimated about Rs. 37.36 Crores
Proposal details are as follows
S.No Existing (in Lacs)
Additional Proposed (in Lacs)
Total
1 Land 80.58 0.00 80.58
2 Building 527.47 200.00 727.47
3 Plant & Machinery 741.79 235.90 977.69
4 Misc. Fixed Assest 59.32 0.00 59.32
4 Other Non Current
Assets
266.34 0.00 266.34
5 Margin Money for
Working Capital
570.33 1053.92
1624.25
TOTAL 2245.83 1489.82 3735.66
6 Employment 302 333 635
7 Power 5000 KW 4800KW 9800 KW
8 Water 10 KL/day 4KL/day 14 KL/day
32
M/s Padmavati Steels Limited
Shivalik Solid Waste Management Ltd
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
This project is for expansion of currently existing steel plant for or the
production of steel related products. With the implementation of the proposed
project, the socio-economic status of the local people will improve
substantially. The land rates in the area will improve in the nearby areas due
to the proposed activity. This will help in up liftment of the social status of the
people in the area. Educational institutions will also come-up and will lead
to improvement of educational status of the people in the area. Primary
health centre will also be developed by us and the medical facilities will
certainly improve due to the proposed project
33