MS for Ventilation .pdf

  • Upload
    agitent

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 7/30/2019 MS for Ventilation .pdf

    1/18

    Group Five Construction LLC

    METHOD STATEMENT

    _____________________________________________________________________________________________Page 1 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    PROJECTNUMBER: NDIA-2201-PRSSB

    SUBMITTALREF. No.:

    NDIA-2201-PRSSB/G5/MSS/MEP/V

    OL/005

    Rev No: 01 PROJECT

    NAME:Passenger Rail System Station Box

    Construction Package No: NDIA-2201-PRSSB

    Rev. Date: 14/05/2011

    METHOD STATEMENT TITLE:

    METHOD STATEMENT FOR INSTALLATION OF DUCT

    AND DUCT ACCESSORIES

    AMENDMENT RECORDS

    Rev. Date Changes Prepared by

    ReviewedMEP

    Manager

    ReviewedLogisticsManager

    ReviewedQA/QC

    Manager

    ReviewedHSE

    Manager

    ReviewedEng.

    Manager

    ReviewedProject

    Manager

    Issuedto

    0004

    Nov2010

    Issued forApproval PP

    MACEPM

    0114

    May2011

    Revised asper

    Comments

    Deepak

    CV

    MACE

    PM

  • 7/30/2019 MS for Ventilation .pdf

    2/18

    _____________________________________________________________________________________________Page 2 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    CONTENTS

    1.0 PURPOSE

    2.0 SCOPE OF WORK

    3.0 PROJECT ORGANISATION (INCL. HEALTH AND SAFETY CONTROL)

    4.0 HEALTH AND SAFETY RISKS AND CONTROLS

    5.0 WORKPLACE ACCESS AND EGRESS

    6.0 WORKPLACE LIGHTING

    7.0 PLANT AND EQUIPMENT

    8.0 PERSONNEL TRAINING CERTIFICATION

    9.0 HAZARDOUS MATERIALS AND SUBSTANCES

    10.0 WASTE MANAGEMENT

    11.0 SPECIAL CONTROL MEASURES

  • 7/30/2019 MS for Ventilation .pdf

    3/18

    _____________________________________________________________________________________________Page 3 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    1. PURPOSE :

    This Method Statement aims at ensuring that the installation of Ventilation Duct Work andAccessories for the NDIA Railway Station meets the requirements of ventilation Specification Section230000 and complies with Health and Safety procedures.

    REFERENCES :

    o Project Specifications Volume II, Part -1, Section: 23000.

    o Approved shop drawings (latest revision)

    o Duct Work standard DW/144 Spec.

    o Duct work Air leakage test Procedure DW-143 .

    o Method statement for Air Handling Unit ( MSS-MEP-VOL-004)- (Mace ref: MS-126)

    o NDIA Design Basis Documents rev H (25045-x-3dr-x-1000_001) Dated on 08.05. 2006

    2. SCOPE OF WORK :

    Ventilation Duct Work generally includes all types of Supply Air Duct, Fresh and Exhaust Air Duct

    and their accessories such as duct elbows, offsets, transformation pieces, and branch off pieces,

    tee connections, access doors, Fire Dampers, Volume Control Dampers and Sound Attenuators.

    All the ventilation Ducting and accessories are suitable against corrosion from saline environment.The ducting and accessories will be painted with rubber acrylated anti corrosion paint beforedelivery to the site.

    2.1 Pre Installation Procedures :

    1. Ensure that approved materials are available to carry out the work.

    2. Prior to Commencement of work , areas and access will be inspected to confirm that

    Site is ready to commence the work.

    3. Check all the Duct work are pre-fabricated with tag number labelled and received at

    site in accordance with specifications and correct dimensions as per approved

    drawings.

    4. All relevant documentation (Drawings) and Material applicable to particular section of

    works will be checked by Site Supervisor prior to commencement of work.

    5. The Site engineer/ Site Supervisor will give necessary instructions to tradesmen(Duct erectors) and provide necessary approved construction/shop Drawings of

    latest revision along with coordinated layouts.

    6. The Site Supervisor/Foremen will also check that proper tools and equipment are

    available to carry out the work and are in compliance with contract specification.

    7. The Site Supervisor also explains the tradesmen regarding safety precautions to

  • 7/30/2019 MS for Ventilation .pdf

    4/18

    _____________________________________________________________________________________________Page 4 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    be observed.

    8. Prior to Leak testing, Site Engineer will ensure that Calibrated test kit is available and in

    good condition.

    2.2 Installation and Inspection Procedure :

    1 Prior to commencement of work, coordination will be done with other services.

    2. Determine the position of duct supports as per approved construction drawing,

    coordinated layouts and specification.

    3. Prepare and fix the duct supports as per approved construction drawing and

    specification.

    4. Any cut edges of angles, channels or threaded rods will be touched up with Zinc rich

    paint.

    5. Transport the Duct pieces and fittings to final location.

    6. Pre-assemble the Duct pieces and fittings as per approved shop drawing, ensuring

    the alignment.

    7. Raise the duct work on to the supports ensuring that each length is aligned and

    levelled with preceding length as per dimensions shown on approved shop drawings.

    8. Approved duct sealant shall be applied on the joints. Any excess sealant shall be

    removed so that the joint is left in clean and tidy condition.

    9. Ensure that duct work is clean and no tool/construction debris exists within duct work

    before proceeding to next length.

    10. All open ends of the duct works shall be temporarily sealed with polythene

    sheets/plywood before leaving the job site to prevent moisture and dirt.

    11. Ensure that all accessories like Volume Control dampers, Fire dampers, Access

    doors, Test points, Sensors are installed in accordance with approved shop

    drawings.

    12. Install Sound Attenuators, Diffuser and Louvers according to approved shop

    drawings.

    13 Leak test will be carried out for duct work as applicable in DW144 standard.

    14. Where duct work passes through fire rated wall/partitions, the gap between sleeve

    and duct work shall be filled with approved fire barrier.

    15. Bottom of the duct should be maintained as per the levels marked on the drawings.

  • 7/30/2019 MS for Ventilation .pdf

    5/18

    _____________________________________________________________________________________________Page 5 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    16. All the ducts will be lifted by crane though the ventilation shaft opening to PRSSB and

    the horizontal movement will be carried by hand pallet track.

    17. Only trained workers will erect the scaffoldings and also the scissors lifts operators

    are to be trained , only trained work men should operate the scissors lifts.

    18. The ducting will be degreased inside and outside from the factory and the corrosive

    protection paint will be applied from factory itself before delivery to the site.

    19. The Painted duct work should be protected against damage in transit & storage .

    Touching up of paint to be done at site after delivery of the material if necessary.

    20. Duct work construction and installation should be as per the HVCA DW/144 & 143

    2.3. QUALITY CONTROL:

    1. QCE along with Project Engineer and Site Engineer will monitor that allcomponents are installed as per contract specifications and approved submittals

    and manufacturers recommendations.

    2. Duct work Material inspection will be done as per standard QA/QC inspection

    procedure. Touching up of the paint should be done at site if necessary

    3. Inspection Request (IR) shall be submitted to Main Contractor/Consultant for the

    following stages of work:

    After completion of installation before leak test

    Leak testing of Duct work (as applicable) as per DW 143.

    4. An activity specific Quality Control Plan (Inspection and Test Plans ITP) will be

    generated in accordance to this Method Statement and relevant Project

    Specifications, identifying suitable verification through Hold, Witness, Surveillance

    or Review points at appropriate stages of the process.

    The ITP will also indicate which records (relevant QC Forms) are to be

    generated to demonstrate that product realization has been achieved.

    The reference number for the relevant ITP is:

    QCP No.: NDIA-2201/ITP/026E

    This ITP will be submitted separately and will follow a separate approval process

    to that of this Method Statement.

  • 7/30/2019 MS for Ventilation .pdf

    6/18

    _____________________________________________________________________________________________Page 6 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    2.4. SAFETY:

    1. Work will commence as per safety regulations laid down in the contract

    specification and project safety plan.

    2. Proper safety harness to be used and secured as required or as instructed by

    safety officer.

    3. All personal protective equipment shall be used as appropriate according to thenature of the job.

    4. Housekeeping shall be of good standard and all cut pieces and debris shall

    be removed.

    5. Ensure that all lifting operations are carried out as per approved procedures

    and safety regulations.

    2.5. LIGHTING:

    1. Workplace Lighting - G5 will have in place a temporary lighting system and

    ventilation system for other works to take place.

  • 7/30/2019 MS for Ventilation .pdf

    7/18

    _________________________________________________________________________________Page 7 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    3.0 PROJECT ORGANIZATION

    3.1 Group Five Construction - Organizational Chart

  • 7/30/2019 MS for Ventilation .pdf

    8/18

    _________________________________________________________________________________Page 8 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    3.2 Voltas Ltd. - Organizational Chart

    ProjectDirector

    Mr. A. Tyler

    SecretaryMrs. L.Pineda

    Doc. ControlMr. R.

    Pontillias

    Admin.Manager

    Mr. V. Guha

    PlanningEng. Mr.S. Haneef

    QSMr. J.

    McMillan

    QA/QC Eng.Mechanical

    Mr. R. Juelar

    Project Mgr.(Plumb) Mr.D. Suresh

    MEP ProjectManager

    Mr. P. Vlaicu

    QA/QC Eng.Electrical

    Mr. R. Addatu

    DraughtsmanPlumbing

    Mr. M. Karki

    HR ManagerMr. R.

    Mazumdar

    FinanceMr. M.

    Deshmukh

    ContractsMr. A.Robertson

    ProcurementCell

    RegionalDirector

    Mr. C.D. Pant

    PMOMr. I. West

    VOLTAS LIMITEDInternational Operations Business GroupPO Box 23458Doha, Qatar

    ORGANISATION CHART FOR MEP WORKSPROJECT: NDIA-2201-PRSSB (PASSENGER RAIL SYSTEM STATION BO

    DOHA BRANCH OFFICE BASED NDIA SITE BASED

    QS Asst.Mr. T.Kumar

    Project Eng.(Plumb) Mr.

    D. Veettil

    Site Superv.Plumbing

    Mr. Malkayah

    Project Eng.(Ventilat) Mr.P. Thangavelu

    DraughtsmanVentilation

    Mr. T. Baby

    Site Eng.(Ventilat)

    TBA

    Site Superv.Ventilation

    TBA

    Seepage WaterDrainage Works

    VentilationWorks

  • 7/30/2019 MS for Ventilation .pdf

    9/18

    ________________________________________________________________________________Page 9 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    4.0 HEALTH AND SAFETY RISKS AND CONTROLS

    Below is an assessment of the risks involved for the surveying works?

    To evaluate risk: Likelihood (L) Severity (S) = Risk (R)Defined as High (11 - 25), Medium (6 - 10) or Low (1 - 5)

    Activity/Element

    PotentialHazards

    Consequence Risk Rating Control Measures Specified

    L S R Work duringsummertime.

    Heat stress / Heat strokeduringsummer.

    Workersovercome byheat problems,sunstrokes etc.

    3 3 9 1. All workers to be advised to drink at leaminimum requirement of water per daysolutions are highly recommended durstress periods).

    2. Rest hours during peak hot time, seasobreak hours will be implemented.Work at night (ifrequired).

    Little light. Injuries due toinadequate/ poorlighting.

    3 3 9 1. Provision of adequate lighting.2. In some circumstances, intrinsically sa

    be required.

    L = Likelihood S = Severity1 Very Unlikely2 Unlikely3 Likely4 Very Likely5 Certain

    1 Minor Injury2 Lost Time Injury3 Major Injury4 Single Fatality5 Multiply Fatalities

    Assessed by: AC Checked by: PB

  • 7/30/2019 MS for Ventilation .pdf

    10/18

    ________________________________________________________________________________Page 10 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    Activity/Element

    PotentialHazards

    Consequence Risk Rating Control Measures Specified

    L S R Energising(connectingAHU controlpanel or powertools to thetemporarypower source).

    ElectricalShock.

    Burns, injury andelectrocution.

    2 2 4 1. Instruction and toolbox talks given on u2. Operatives to be tested for competence

    the tools.3. Only double insulated reputable, brand

    manufactured tools to be used.4. Conduct weekly tool inspections.5. Functioning ELCB (earth-leakage circu

    required on all circuits.6. Ensure supply voltage conforms to ope

    (240V single-phase or 415V three-phasite).

    Connectingextension leadsfor the powertools used forinstalling theAHUs

    ElectricalShock.

    Burns, injury andelectrocution.

    2 2 4 1. Use only matching colour coded industsockets.

    2. Regular checks for polarity and service3. Ensure that electrical equipment/tools

    prior to connecting to power supply.4. Ensure 415V and 240V supply circuits

    functioning ELCB.5. Protect extension leads against damage6. Conduct relevant toolbox talks.7. Conduct regular inspections.

  • 7/30/2019 MS for Ventilation .pdf

    11/18

    ________________________________________________________________________________Page 11 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    Activity/Element

    PotentialHazards

    Consequence Risk Rating Control Measures Specified

    L S R Welding (ifany).

    Fire. Burns.Damage toproperty.

    2 1 2 1. Hot Work Permit (Authority or Client) t2. Welding area to be free of flammable s3. Ensure appropriate housekeeping pract

    are followed.4. Accessible fire extinguisher required.

    Hot welding (ifany), cutting,grinding, drillingand handling oftools duringinstallation ofAHU andaccessories ortheir supports

    Hot work andimproperhandling oftools.

    Fire hazard,electric shockand personalinjury.Hit by sharpedges/ flying

    objects.

    3 4 12 1. Qualified personnel only to be involvedgrinding activities with appropriate PPkeeper to ensure good condition of all equipment before issue to site. Hot perExtinguisher required at working area.

    2. Defective/ damaged tools [broken hand

    edges, worn out heads, cracked parts emade tools, make shift hand tools shouimmediately & destroyed.

    3. Technicians will be reminded regularlybox talks about perils of misusing hannecessity of informing the defects founimmediately.

    4. Wear goggles while carrying out Chippor similar operations.

    5. Using proper tools for the right jobs toworks. Do not use unsafe defective tooworks.

  • 7/30/2019 MS for Ventilation .pdf

    12/18

    ________________________________________________________________________________Page 12 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    Activity/Element

    PotentialHazards

    Consequence Risk Rating Control Measures Specified

    L S R Operate anangle grinderfor adjusting thelength ofthreaded rods.

    Hot sparksbeing airborne.

    Eye injuries.Minor burnwounds to thebody.

    3 3 9 1. PPE - Clear face shield visor.2. Eye protection to be worn.

    Operate anangle grinderfor installing thesupports forAHU or itsaccessories.

    Hot sparksbeing airborne.

    Ignition ofcombustiblematerials,resulting indamage andloss of lifethrough a fire.

    4 3 12 1. Areas are cleared of combustible materi2. Fire wardens do inspect the areas to en

    cleared.3. Site emergency plan deals with fire inc

    Cutting andGrinding withabrasivewheels.

    Flyingparticles androtatingblade.Sparksgenerated.Disc disinte-gration.

    Eye and bodyinjury.Start a fire.

    2 1 2 1. Only fit good quality discs/wheels.2. Avoid discs coming into contact with s

    when not cutting/grinding.3. Guards to be fitted.4. Eye protection to be worn.5. Keep work area clear of flammable ma

    Cutting thesupport with ahand-heldcircular saw.

    Flyingparticles.Rotating

    blade.

    Eye and bodyinjury / cut / amputation.

    2 1 2 1. All power electrical tools to be fitted wswitch (trigger disconnecting the powreleased). Trigger switch-lock not to b

    2. Inspect tools regularly.3. Guards are to be fitted and eye protect

  • 7/30/2019 MS for Ventilation .pdf

    13/18

    ________________________________________________________________________________Page 13 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    Activity/Element

    PotentialHazards

    Consequence Risk Rating Control Measures Specified

    L S R Drilling, cutting,grinding andchipping forProperinstallation ofAHU andAccessories

    Dustgeneration.

    Lung damageand eye injury.

    2 1 2 1. Use of PPE to be enforced and controll2. Operatives are to be issued with dust m

    protection.

    Drilling, cutting,grinding andchipping forProperinstallation ofAHU and

    Accessories

    Noisegeneration.

    Loss of hearing. 2 1 2 1. Operatives to be issued with eye protectio2. Limit / control the duration of noise ex3. Noise levels to be checked at regular in

    especially in confined spaces.

    Drilling, cutting,grinding andchipping Properinstallation ofAHU andAccessories

    Vibration. Hand / ArmVibrationSyndrome(HAVS).White finger -ReynaudsDisease.

    1 1 1 1. Limited exposure duration to vibration.2. Make use of relieve operator and rotate

    basis.3. Use of heavy duty gloves is compulsor4. Inspect anti-vibration rubbers on equip

    applicable.5. Monitoring of operators by Site Nurse

    basis.

    Transportation& Storage of

    AHU andaccessories .

    ImproperTranspor-tation &Storage.

    Damage ofmaterials/ workmen/ vehicle.

    2 1 2 1. Projections from vehicles will not be pered flag/lamp tied to the projection beh

    2. Materials shall be stacked properly & sobstruct the access of others.

  • 7/30/2019 MS for Ventilation .pdf

    14/18

    ________________________________________________________________________________Page 14 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    Activity/Element

    PotentialHazards

    Consequence Risk Rating Control Measures Specified

    L S R Manual lifting ofAHU andaccessories.

    IncorrectManuallifting.

    Muscular -skeletal injury.

    4 3 12 1. Wherever possible mechanical handlingbe used.

    2. Size of load shall be reduced when it iswalk considerable distance in confined

    3. Heavy load shall be assessed before lifobtained from other members of the si

    Lifting of AHUandaccessoriesand control

    panels bycranes or fromvehicles.

    ImproperLifting / Loading andoff loading

    of tools &materials.

    Lifting gear &loads / Workerstruck by Fallingobject.

    3 4 12 1. Working area to be barricade with warnsignage.

    2. Clearly identify lifting capacity of planLifting plan to be uses/operated by com

    3. Check at regular intervals chains, slingwill be certificated and colour coded.

    4. Slung loads to be secure and balanced,ropes use hard standing for reception.

    5. Keep clear of slung loads; keep hands loads especially at point of landing.

    6. Wear suitable PPE.7. Use banks man. Maintain communica

    banks man and driver.8. Operatives to police the working area a

    of movements of public at all times.

  • 7/30/2019 MS for Ventilation .pdf

    15/18

    ________________________________________________________________________________Page 15 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    Activity/Element

    PotentialHazards

    Consequence Risk Rating Control Measures Specified

    L S R General activity. Improper

    general sitework.

    Injury andtools/materialsdamage.

    3 3 9 1. Attend site safety induction & method sbriefing to be given by G5 Engineer.

    2. Comply with site rules and G5 safety p3. Wear high visibility coat/waistcoat and4. Carry out Daily STARRT talks for spe5. Maintain exclusion zone around worki6. Do not permit public to enter site comp

    General work. Noisepollution.

    Hearingdamage.

    3 3 9 1. Noise should be reduced whenever posslow noisy machines & shielding mach

    2. Ear protectors must be provided for noabove 85 dbA.

    Generaloperation.

    Improperoperation ofPlant andequipment.

    Plant andequipmentdamage.

    3 4 12 1. All plant and equipment to be suitably smaintained by competent fitters.

    2. Check all plant certification.3. Inspect equipment at the start of each s4. Secure equipment in compound at the

    shift.

  • 7/30/2019 MS for Ventilation .pdf

    16/18

    _____________________________________________________________________________________________Page 16 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    5.0 WORKPLACE ACCESS AND EGRESS5.1 All employees entering the construction area will do so by making use of the access

    provided. Only authorized employees will be allowed to gain access onto the construction

    site.

    5.2 All employees will attend the NDIA health and safety induction prior to entering the area of

    operation. Access permits will only be issued to employees on completion of the induction.

    5.3 Employees will be transported to the area of work and then back.

    6.0 WORKPLACE LIGHTING

    6.1 Installation and commissioning works will be conducted in day light; no work will be

    conducted after sunset unless during emergencies.

    6.2 Proper lighting shall be provided when working in the night. Sufficient tower lights shall be

    operated should it be necessary.

    6.3 Working hours will be from 07h00 to 18h00.

    7.0 PLANT AND EQUIPMENTThe following plant and equipment shall be used during the plumbing works:

    Light torch

    Portable lights

    Extension leads

    Portable generator

    Portable drill machine

    Portable grinding machine

    Powder-actuated gun

    Electric cutter

    Tap & die set

    Hacksaw frame with blade

    Combination pliers

    Screwdriver set

    Spanner set

  • 7/30/2019 MS for Ventilation .pdf

    17/18

    _____________________________________________________________________________________________Page 17 of 18

    G5C.IMS.001 Rev. 05 Dated: 26/11/2010

    Marker pen

    Measuring tape

    Spirit level

    Knife with retractable snap-off blade

    Vertical hydraulic jack 3 ton

    Ladder

    Scaffolding set

    Fork lift

    8.0 PERSONNEL TRAINING CERTIFICATIONCopies of all relevant competency certificates will be kept on file in the G5C site HSE Advisorsoffice. These documents will be made available for inspection on request from MACE Project

    Manager.

    9.0 HAZARDOUS MATERIALS AND SUBSTANCESMaterials and substances used for the installation of Seepage Water Drainage System are non-toxic and non- hazardous.

    10.0 WASTE MANAGEMENT10.1 Waste management will be done as per the procedure set out in the G5C Project Health and

    Safety Plan.

    11.0 SPECIAL CONTROL MEASURES

    11.1 The safety of all personnel and other employees shall always be a high priority during all field

    operations conducted on the project.

    11.2 All site operatives and staff working for this project shall attend the Main Contractors safety

    induction training / seminar prior to working at site.

    11.3 The responsible supervisor will conduct a Safety Task Analysis Risk Reduction Talk(STARRT card) prior to start of work daily. The method statement shall also be discussed to

    all site operatives before commencing work.

    11.4 Contractor is committed to ensure minimal risk for its employees, for the employees of

    subcontractors and consultants, and to protect the public exposed to construction operations.

  • 7/30/2019 MS for Ventilation .pdf

    18/18

    _____________________________________________________________________________________________Page 18 of 18

    G5C IMS 001 Rev 05 Dated: 26/11/2010

    11.5 At a minimum, each site operative member will be equipped with PPE such as: high visibility

    reflective vest, safety shoes, hard hat, safety glasses.

    11.6 When any operation becomes hazardous beyond reason due to unforeseen or uncontrollable

    circumstances, all affected operations will cease until safe working conditions have been

    restored. No operation will be considered as too important or urgent as to compromise the

    health and safety of any employee on site.

    ----- END -----