Upload
agitent
View
215
Download
0
Embed Size (px)
Citation preview
7/30/2019 MS for Ventilation .pdf
1/18
Group Five Construction LLC
METHOD STATEMENT
_____________________________________________________________________________________________Page 1 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
PROJECTNUMBER: NDIA-2201-PRSSB
SUBMITTALREF. No.:
NDIA-2201-PRSSB/G5/MSS/MEP/V
OL/005
Rev No: 01 PROJECT
NAME:Passenger Rail System Station Box
Construction Package No: NDIA-2201-PRSSB
Rev. Date: 14/05/2011
METHOD STATEMENT TITLE:
METHOD STATEMENT FOR INSTALLATION OF DUCT
AND DUCT ACCESSORIES
AMENDMENT RECORDS
Rev. Date Changes Prepared by
ReviewedMEP
Manager
ReviewedLogisticsManager
ReviewedQA/QC
Manager
ReviewedHSE
Manager
ReviewedEng.
Manager
ReviewedProject
Manager
Issuedto
0004
Nov2010
Issued forApproval PP
MACEPM
0114
May2011
Revised asper
Comments
Deepak
CV
MACE
PM
7/30/2019 MS for Ventilation .pdf
2/18
_____________________________________________________________________________________________Page 2 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
CONTENTS
1.0 PURPOSE
2.0 SCOPE OF WORK
3.0 PROJECT ORGANISATION (INCL. HEALTH AND SAFETY CONTROL)
4.0 HEALTH AND SAFETY RISKS AND CONTROLS
5.0 WORKPLACE ACCESS AND EGRESS
6.0 WORKPLACE LIGHTING
7.0 PLANT AND EQUIPMENT
8.0 PERSONNEL TRAINING CERTIFICATION
9.0 HAZARDOUS MATERIALS AND SUBSTANCES
10.0 WASTE MANAGEMENT
11.0 SPECIAL CONTROL MEASURES
7/30/2019 MS for Ventilation .pdf
3/18
_____________________________________________________________________________________________Page 3 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
1. PURPOSE :
This Method Statement aims at ensuring that the installation of Ventilation Duct Work andAccessories for the NDIA Railway Station meets the requirements of ventilation Specification Section230000 and complies with Health and Safety procedures.
REFERENCES :
o Project Specifications Volume II, Part -1, Section: 23000.
o Approved shop drawings (latest revision)
o Duct Work standard DW/144 Spec.
o Duct work Air leakage test Procedure DW-143 .
o Method statement for Air Handling Unit ( MSS-MEP-VOL-004)- (Mace ref: MS-126)
o NDIA Design Basis Documents rev H (25045-x-3dr-x-1000_001) Dated on 08.05. 2006
2. SCOPE OF WORK :
Ventilation Duct Work generally includes all types of Supply Air Duct, Fresh and Exhaust Air Duct
and their accessories such as duct elbows, offsets, transformation pieces, and branch off pieces,
tee connections, access doors, Fire Dampers, Volume Control Dampers and Sound Attenuators.
All the ventilation Ducting and accessories are suitable against corrosion from saline environment.The ducting and accessories will be painted with rubber acrylated anti corrosion paint beforedelivery to the site.
2.1 Pre Installation Procedures :
1. Ensure that approved materials are available to carry out the work.
2. Prior to Commencement of work , areas and access will be inspected to confirm that
Site is ready to commence the work.
3. Check all the Duct work are pre-fabricated with tag number labelled and received at
site in accordance with specifications and correct dimensions as per approved
drawings.
4. All relevant documentation (Drawings) and Material applicable to particular section of
works will be checked by Site Supervisor prior to commencement of work.
5. The Site engineer/ Site Supervisor will give necessary instructions to tradesmen(Duct erectors) and provide necessary approved construction/shop Drawings of
latest revision along with coordinated layouts.
6. The Site Supervisor/Foremen will also check that proper tools and equipment are
available to carry out the work and are in compliance with contract specification.
7. The Site Supervisor also explains the tradesmen regarding safety precautions to
7/30/2019 MS for Ventilation .pdf
4/18
_____________________________________________________________________________________________Page 4 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
be observed.
8. Prior to Leak testing, Site Engineer will ensure that Calibrated test kit is available and in
good condition.
2.2 Installation and Inspection Procedure :
1 Prior to commencement of work, coordination will be done with other services.
2. Determine the position of duct supports as per approved construction drawing,
coordinated layouts and specification.
3. Prepare and fix the duct supports as per approved construction drawing and
specification.
4. Any cut edges of angles, channels or threaded rods will be touched up with Zinc rich
paint.
5. Transport the Duct pieces and fittings to final location.
6. Pre-assemble the Duct pieces and fittings as per approved shop drawing, ensuring
the alignment.
7. Raise the duct work on to the supports ensuring that each length is aligned and
levelled with preceding length as per dimensions shown on approved shop drawings.
8. Approved duct sealant shall be applied on the joints. Any excess sealant shall be
removed so that the joint is left in clean and tidy condition.
9. Ensure that duct work is clean and no tool/construction debris exists within duct work
before proceeding to next length.
10. All open ends of the duct works shall be temporarily sealed with polythene
sheets/plywood before leaving the job site to prevent moisture and dirt.
11. Ensure that all accessories like Volume Control dampers, Fire dampers, Access
doors, Test points, Sensors are installed in accordance with approved shop
drawings.
12. Install Sound Attenuators, Diffuser and Louvers according to approved shop
drawings.
13 Leak test will be carried out for duct work as applicable in DW144 standard.
14. Where duct work passes through fire rated wall/partitions, the gap between sleeve
and duct work shall be filled with approved fire barrier.
15. Bottom of the duct should be maintained as per the levels marked on the drawings.
7/30/2019 MS for Ventilation .pdf
5/18
_____________________________________________________________________________________________Page 5 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
16. All the ducts will be lifted by crane though the ventilation shaft opening to PRSSB and
the horizontal movement will be carried by hand pallet track.
17. Only trained workers will erect the scaffoldings and also the scissors lifts operators
are to be trained , only trained work men should operate the scissors lifts.
18. The ducting will be degreased inside and outside from the factory and the corrosive
protection paint will be applied from factory itself before delivery to the site.
19. The Painted duct work should be protected against damage in transit & storage .
Touching up of paint to be done at site after delivery of the material if necessary.
20. Duct work construction and installation should be as per the HVCA DW/144 & 143
2.3. QUALITY CONTROL:
1. QCE along with Project Engineer and Site Engineer will monitor that allcomponents are installed as per contract specifications and approved submittals
and manufacturers recommendations.
2. Duct work Material inspection will be done as per standard QA/QC inspection
procedure. Touching up of the paint should be done at site if necessary
3. Inspection Request (IR) shall be submitted to Main Contractor/Consultant for the
following stages of work:
After completion of installation before leak test
Leak testing of Duct work (as applicable) as per DW 143.
4. An activity specific Quality Control Plan (Inspection and Test Plans ITP) will be
generated in accordance to this Method Statement and relevant Project
Specifications, identifying suitable verification through Hold, Witness, Surveillance
or Review points at appropriate stages of the process.
The ITP will also indicate which records (relevant QC Forms) are to be
generated to demonstrate that product realization has been achieved.
The reference number for the relevant ITP is:
QCP No.: NDIA-2201/ITP/026E
This ITP will be submitted separately and will follow a separate approval process
to that of this Method Statement.
7/30/2019 MS for Ventilation .pdf
6/18
_____________________________________________________________________________________________Page 6 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
2.4. SAFETY:
1. Work will commence as per safety regulations laid down in the contract
specification and project safety plan.
2. Proper safety harness to be used and secured as required or as instructed by
safety officer.
3. All personal protective equipment shall be used as appropriate according to thenature of the job.
4. Housekeeping shall be of good standard and all cut pieces and debris shall
be removed.
5. Ensure that all lifting operations are carried out as per approved procedures
and safety regulations.
2.5. LIGHTING:
1. Workplace Lighting - G5 will have in place a temporary lighting system and
ventilation system for other works to take place.
7/30/2019 MS for Ventilation .pdf
7/18
_________________________________________________________________________________Page 7 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
3.0 PROJECT ORGANIZATION
3.1 Group Five Construction - Organizational Chart
7/30/2019 MS for Ventilation .pdf
8/18
_________________________________________________________________________________Page 8 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
3.2 Voltas Ltd. - Organizational Chart
ProjectDirector
Mr. A. Tyler
SecretaryMrs. L.Pineda
Doc. ControlMr. R.
Pontillias
Admin.Manager
Mr. V. Guha
PlanningEng. Mr.S. Haneef
QSMr. J.
McMillan
QA/QC Eng.Mechanical
Mr. R. Juelar
Project Mgr.(Plumb) Mr.D. Suresh
MEP ProjectManager
Mr. P. Vlaicu
QA/QC Eng.Electrical
Mr. R. Addatu
DraughtsmanPlumbing
Mr. M. Karki
HR ManagerMr. R.
Mazumdar
FinanceMr. M.
Deshmukh
ContractsMr. A.Robertson
ProcurementCell
RegionalDirector
Mr. C.D. Pant
PMOMr. I. West
VOLTAS LIMITEDInternational Operations Business GroupPO Box 23458Doha, Qatar
ORGANISATION CHART FOR MEP WORKSPROJECT: NDIA-2201-PRSSB (PASSENGER RAIL SYSTEM STATION BO
DOHA BRANCH OFFICE BASED NDIA SITE BASED
QS Asst.Mr. T.Kumar
Project Eng.(Plumb) Mr.
D. Veettil
Site Superv.Plumbing
Mr. Malkayah
Project Eng.(Ventilat) Mr.P. Thangavelu
DraughtsmanVentilation
Mr. T. Baby
Site Eng.(Ventilat)
TBA
Site Superv.Ventilation
TBA
Seepage WaterDrainage Works
VentilationWorks
7/30/2019 MS for Ventilation .pdf
9/18
________________________________________________________________________________Page 9 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
4.0 HEALTH AND SAFETY RISKS AND CONTROLS
Below is an assessment of the risks involved for the surveying works?
To evaluate risk: Likelihood (L) Severity (S) = Risk (R)Defined as High (11 - 25), Medium (6 - 10) or Low (1 - 5)
Activity/Element
PotentialHazards
Consequence Risk Rating Control Measures Specified
L S R Work duringsummertime.
Heat stress / Heat strokeduringsummer.
Workersovercome byheat problems,sunstrokes etc.
3 3 9 1. All workers to be advised to drink at leaminimum requirement of water per daysolutions are highly recommended durstress periods).
2. Rest hours during peak hot time, seasobreak hours will be implemented.Work at night (ifrequired).
Little light. Injuries due toinadequate/ poorlighting.
3 3 9 1. Provision of adequate lighting.2. In some circumstances, intrinsically sa
be required.
L = Likelihood S = Severity1 Very Unlikely2 Unlikely3 Likely4 Very Likely5 Certain
1 Minor Injury2 Lost Time Injury3 Major Injury4 Single Fatality5 Multiply Fatalities
Assessed by: AC Checked by: PB
7/30/2019 MS for Ventilation .pdf
10/18
________________________________________________________________________________Page 10 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
Activity/Element
PotentialHazards
Consequence Risk Rating Control Measures Specified
L S R Energising(connectingAHU controlpanel or powertools to thetemporarypower source).
ElectricalShock.
Burns, injury andelectrocution.
2 2 4 1. Instruction and toolbox talks given on u2. Operatives to be tested for competence
the tools.3. Only double insulated reputable, brand
manufactured tools to be used.4. Conduct weekly tool inspections.5. Functioning ELCB (earth-leakage circu
required on all circuits.6. Ensure supply voltage conforms to ope
(240V single-phase or 415V three-phasite).
Connectingextension leadsfor the powertools used forinstalling theAHUs
ElectricalShock.
Burns, injury andelectrocution.
2 2 4 1. Use only matching colour coded industsockets.
2. Regular checks for polarity and service3. Ensure that electrical equipment/tools
prior to connecting to power supply.4. Ensure 415V and 240V supply circuits
functioning ELCB.5. Protect extension leads against damage6. Conduct relevant toolbox talks.7. Conduct regular inspections.
7/30/2019 MS for Ventilation .pdf
11/18
________________________________________________________________________________Page 11 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
Activity/Element
PotentialHazards
Consequence Risk Rating Control Measures Specified
L S R Welding (ifany).
Fire. Burns.Damage toproperty.
2 1 2 1. Hot Work Permit (Authority or Client) t2. Welding area to be free of flammable s3. Ensure appropriate housekeeping pract
are followed.4. Accessible fire extinguisher required.
Hot welding (ifany), cutting,grinding, drillingand handling oftools duringinstallation ofAHU andaccessories ortheir supports
Hot work andimproperhandling oftools.
Fire hazard,electric shockand personalinjury.Hit by sharpedges/ flying
objects.
3 4 12 1. Qualified personnel only to be involvedgrinding activities with appropriate PPkeeper to ensure good condition of all equipment before issue to site. Hot perExtinguisher required at working area.
2. Defective/ damaged tools [broken hand
edges, worn out heads, cracked parts emade tools, make shift hand tools shouimmediately & destroyed.
3. Technicians will be reminded regularlybox talks about perils of misusing hannecessity of informing the defects founimmediately.
4. Wear goggles while carrying out Chippor similar operations.
5. Using proper tools for the right jobs toworks. Do not use unsafe defective tooworks.
7/30/2019 MS for Ventilation .pdf
12/18
________________________________________________________________________________Page 12 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
Activity/Element
PotentialHazards
Consequence Risk Rating Control Measures Specified
L S R Operate anangle grinderfor adjusting thelength ofthreaded rods.
Hot sparksbeing airborne.
Eye injuries.Minor burnwounds to thebody.
3 3 9 1. PPE - Clear face shield visor.2. Eye protection to be worn.
Operate anangle grinderfor installing thesupports forAHU or itsaccessories.
Hot sparksbeing airborne.
Ignition ofcombustiblematerials,resulting indamage andloss of lifethrough a fire.
4 3 12 1. Areas are cleared of combustible materi2. Fire wardens do inspect the areas to en
cleared.3. Site emergency plan deals with fire inc
Cutting andGrinding withabrasivewheels.
Flyingparticles androtatingblade.Sparksgenerated.Disc disinte-gration.
Eye and bodyinjury.Start a fire.
2 1 2 1. Only fit good quality discs/wheels.2. Avoid discs coming into contact with s
when not cutting/grinding.3. Guards to be fitted.4. Eye protection to be worn.5. Keep work area clear of flammable ma
Cutting thesupport with ahand-heldcircular saw.
Flyingparticles.Rotating
blade.
Eye and bodyinjury / cut / amputation.
2 1 2 1. All power electrical tools to be fitted wswitch (trigger disconnecting the powreleased). Trigger switch-lock not to b
2. Inspect tools regularly.3. Guards are to be fitted and eye protect
7/30/2019 MS for Ventilation .pdf
13/18
________________________________________________________________________________Page 13 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
Activity/Element
PotentialHazards
Consequence Risk Rating Control Measures Specified
L S R Drilling, cutting,grinding andchipping forProperinstallation ofAHU andAccessories
Dustgeneration.
Lung damageand eye injury.
2 1 2 1. Use of PPE to be enforced and controll2. Operatives are to be issued with dust m
protection.
Drilling, cutting,grinding andchipping forProperinstallation ofAHU and
Accessories
Noisegeneration.
Loss of hearing. 2 1 2 1. Operatives to be issued with eye protectio2. Limit / control the duration of noise ex3. Noise levels to be checked at regular in
especially in confined spaces.
Drilling, cutting,grinding andchipping Properinstallation ofAHU andAccessories
Vibration. Hand / ArmVibrationSyndrome(HAVS).White finger -ReynaudsDisease.
1 1 1 1. Limited exposure duration to vibration.2. Make use of relieve operator and rotate
basis.3. Use of heavy duty gloves is compulsor4. Inspect anti-vibration rubbers on equip
applicable.5. Monitoring of operators by Site Nurse
basis.
Transportation& Storage of
AHU andaccessories .
ImproperTranspor-tation &Storage.
Damage ofmaterials/ workmen/ vehicle.
2 1 2 1. Projections from vehicles will not be pered flag/lamp tied to the projection beh
2. Materials shall be stacked properly & sobstruct the access of others.
7/30/2019 MS for Ventilation .pdf
14/18
________________________________________________________________________________Page 14 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
Activity/Element
PotentialHazards
Consequence Risk Rating Control Measures Specified
L S R Manual lifting ofAHU andaccessories.
IncorrectManuallifting.
Muscular -skeletal injury.
4 3 12 1. Wherever possible mechanical handlingbe used.
2. Size of load shall be reduced when it iswalk considerable distance in confined
3. Heavy load shall be assessed before lifobtained from other members of the si
Lifting of AHUandaccessoriesand control
panels bycranes or fromvehicles.
ImproperLifting / Loading andoff loading
of tools &materials.
Lifting gear &loads / Workerstruck by Fallingobject.
3 4 12 1. Working area to be barricade with warnsignage.
2. Clearly identify lifting capacity of planLifting plan to be uses/operated by com
3. Check at regular intervals chains, slingwill be certificated and colour coded.
4. Slung loads to be secure and balanced,ropes use hard standing for reception.
5. Keep clear of slung loads; keep hands loads especially at point of landing.
6. Wear suitable PPE.7. Use banks man. Maintain communica
banks man and driver.8. Operatives to police the working area a
of movements of public at all times.
7/30/2019 MS for Ventilation .pdf
15/18
________________________________________________________________________________Page 15 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
Activity/Element
PotentialHazards
Consequence Risk Rating Control Measures Specified
L S R General activity. Improper
general sitework.
Injury andtools/materialsdamage.
3 3 9 1. Attend site safety induction & method sbriefing to be given by G5 Engineer.
2. Comply with site rules and G5 safety p3. Wear high visibility coat/waistcoat and4. Carry out Daily STARRT talks for spe5. Maintain exclusion zone around worki6. Do not permit public to enter site comp
General work. Noisepollution.
Hearingdamage.
3 3 9 1. Noise should be reduced whenever posslow noisy machines & shielding mach
2. Ear protectors must be provided for noabove 85 dbA.
Generaloperation.
Improperoperation ofPlant andequipment.
Plant andequipmentdamage.
3 4 12 1. All plant and equipment to be suitably smaintained by competent fitters.
2. Check all plant certification.3. Inspect equipment at the start of each s4. Secure equipment in compound at the
shift.
7/30/2019 MS for Ventilation .pdf
16/18
_____________________________________________________________________________________________Page 16 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
5.0 WORKPLACE ACCESS AND EGRESS5.1 All employees entering the construction area will do so by making use of the access
provided. Only authorized employees will be allowed to gain access onto the construction
site.
5.2 All employees will attend the NDIA health and safety induction prior to entering the area of
operation. Access permits will only be issued to employees on completion of the induction.
5.3 Employees will be transported to the area of work and then back.
6.0 WORKPLACE LIGHTING
6.1 Installation and commissioning works will be conducted in day light; no work will be
conducted after sunset unless during emergencies.
6.2 Proper lighting shall be provided when working in the night. Sufficient tower lights shall be
operated should it be necessary.
6.3 Working hours will be from 07h00 to 18h00.
7.0 PLANT AND EQUIPMENTThe following plant and equipment shall be used during the plumbing works:
Light torch
Portable lights
Extension leads
Portable generator
Portable drill machine
Portable grinding machine
Powder-actuated gun
Electric cutter
Tap & die set
Hacksaw frame with blade
Combination pliers
Screwdriver set
Spanner set
7/30/2019 MS for Ventilation .pdf
17/18
_____________________________________________________________________________________________Page 17 of 18
G5C.IMS.001 Rev. 05 Dated: 26/11/2010
Marker pen
Measuring tape
Spirit level
Knife with retractable snap-off blade
Vertical hydraulic jack 3 ton
Ladder
Scaffolding set
Fork lift
8.0 PERSONNEL TRAINING CERTIFICATIONCopies of all relevant competency certificates will be kept on file in the G5C site HSE Advisorsoffice. These documents will be made available for inspection on request from MACE Project
Manager.
9.0 HAZARDOUS MATERIALS AND SUBSTANCESMaterials and substances used for the installation of Seepage Water Drainage System are non-toxic and non- hazardous.
10.0 WASTE MANAGEMENT10.1 Waste management will be done as per the procedure set out in the G5C Project Health and
Safety Plan.
11.0 SPECIAL CONTROL MEASURES
11.1 The safety of all personnel and other employees shall always be a high priority during all field
operations conducted on the project.
11.2 All site operatives and staff working for this project shall attend the Main Contractors safety
induction training / seminar prior to working at site.
11.3 The responsible supervisor will conduct a Safety Task Analysis Risk Reduction Talk(STARRT card) prior to start of work daily. The method statement shall also be discussed to
all site operatives before commencing work.
11.4 Contractor is committed to ensure minimal risk for its employees, for the employees of
subcontractors and consultants, and to protect the public exposed to construction operations.
7/30/2019 MS for Ventilation .pdf
18/18
_____________________________________________________________________________________________Page 18 of 18
G5C IMS 001 Rev 05 Dated: 26/11/2010
11.5 At a minimum, each site operative member will be equipped with PPE such as: high visibility
reflective vest, safety shoes, hard hat, safety glasses.
11.6 When any operation becomes hazardous beyond reason due to unforeseen or uncontrollable
circumstances, all affected operations will cease until safe working conditions have been
restored. No operation will be considered as too important or urgent as to compromise the
health and safety of any employee on site.
----- END -----