Upload
amin-shafanezhad
View
216
Download
0
Embed Size (px)
Citation preview
8/17/2019 MRP lot for lot
1/43
5606 MANUFACTURING OPERATION MANAGEMENT
NO.
NAME MATRIC NO.
1 Sarah Kanaan Hamzah GS446872 Ahmed Faisal Ahmed GS460193 Amin Shafanejad GS462364 Hussein Kadhim Sharaf GS45602
Lecturer:
Associate Professor Dr. Faiea !i"ti A#$u% Ai
GROUP 6
MRP
8/17/2019 MRP lot for lot
2/43
&ARA' (ANAAN 'AM)A'
8/17/2019 MRP lot for lot
3/43
I"$e*e"$e"t De+a"$
• It refers to the demand of finished goods, which are ordered by
External Customers or manufactured for stock and sale.
• Independent demands for inventories are based on confirmed
Customer orders, forecasts, estimates and past historical data.
De*e"$e"t $e+a"$
• It refers to the demand for items that are subassemblies or
component parts to be used in the production of finished goods. Theamount of dependent demand is the function of the amount of
independent demand• For example, the parts and materials that go into the production of an automobile are examples of
dependent demand, because the total amount of parts and raw materials needed during any time
period is a function of the number of cars that will be produced. Conversely, demand for the
finished cars is independent. car is not a component of another item
I"$e*e"$e"t a"$ De*e"$e"t De+a"$ I",e"tories
8/17/2019 MRP lot for lot
4/43
Material RequirementPlanning (MRP)
It is a production planning process that starts from the demand for
finished products and plans the production step by step of
subassemblies and parts
It is also a set of techni!ues that takes the "aster #roduction
$chedule and other information from inventory records and
product structure records as inputs to determine re!uirements and
schedule of timing for each item.
8/17/2019 MRP lot for lot
5/43
This inventory management system is appropriate for items
that have a dependent demand.
"%# is applicable for industries that offer variety of finished products where the customer is allowed to choose among
many different options.
"%# is most appropriate when the manufacturing environmentis complex and uncertain.
-ere is MRP A**%ica#%e/
8/17/2019 MRP lot for lot
6/43
Pur*ose of MRP
!n"r!l in#en"!r$ le#els
Assi%n !&era"in% &ri!ri"ies
'lan (a&a(i"$ "! l!ad "he &r!du("i!ns$s"em
8/17/2019 MRP lot for lot
7/43
MRP &tructure
8/17/2019 MRP lot for lot
8/43
MRP INPUT&
8/17/2019 MRP lot for lot
9/43
Te Master Pro$uctio" &ce$u%e
"#$ is prepared based on actual customers orders
and predicted demand. This schedule indicates
exactly when each ordered item will be produced tomeet the firm and predicted demand& that is, it is a
time'phased production plan.
8/17/2019 MRP lot for lot
10/43
MPS Examle ! A"e#$me Sea%er Se&iali#t
'r$## Requirement# $r Sea%er
s shown on top this "aster #roduction $chedule shows
planned output for end item speaker. The schedule indicate that
() units needs on *th week, +)) unit needs on th week, -
units needs on /th week and so on.
The !uantities in a master schedule come from a number of
different sources, including customer order, forecasts and other
from warehouse to build up seasonal inventories.
8/17/2019 MRP lot for lot
11/43
For each item in the "#$, a bill of material exists.
The 01" file indicates all the raw materials,
components, subassemblies and re!uired to producean item. The "%# computer system accesses the
01" file to determine exactly what items, and in
what !uantities, are re!uired to complete an order for
a given item.
!i%% of Materia% !OM1
8/17/2019 MRP lot for lot
12/43
!OM E2a+*%e
8/17/2019 MRP lot for lot
13/43
uantit* $n +een+ent art# t$ ,uilt t-e in+een+ent art (A)
If tere is O"3'a"$ I",e"tor4: !0 7 C 80 E2a+*%e1
!OM E2a+*%e co"t.1
8/17/2019 MRP lot for lot
14/43
)" contains detailed information regarding thenumber of !uantity of each item on hand, on order,
and committed to use in various time periods. The"%# computer system accesses the I% computer file
to determine the !uantity available for use in a given
time period and, if enough are available to meet the
order needs, commits these for use during the time period by updating the inventory record. If sufficient
items, as well as the usual lot si2e, on the planned
order release report.
Te I",e"tor4 Recor$s
8/17/2019 MRP lot for lot
15/43
AMIN &'AFANE9AD
8/17/2019 MRP lot for lot
16/43
MRP Processi":
3ross %e!uirement4 The total expected demand for an item or raw materialduring each time period without regard to the amount on hand.
$chedule %eceipt4 Existing orders that arrive at beginning of period.
#ro5ected on 6and4 Inventory balance that will be on hand at the beginning ofeach time period.
7et %e!uirement4 The actual amount needed in each time period.
#lanned'order %eceipts4 The !uantity expected to be received by the beginning of the period.
#lanned'order %elease4 Indicate a plan amount to order in each time period oroffset by lead time.
8/17/2019 MRP lot for lot
17/43
Week
1 2 3 4 5 6 7 8 Lead Time
A. Required date 50Order release date 50 1 week
B. Required date 100Order release date 100 2 weeks
C. Required date 150Order release date 150 1 week
. Required date 200 300Order release date 200 300 2 weeks
!. Required date 300Order release date 300 3 weeks
". Required date 600 200Order release date 600 200 1 week
". Required date 300Order release date 300 2 weeks
Gross Re;uire+e"ts P%a"
8/17/2019 MRP lot for lot
18/43
$tarts with a production schedule for the end item 8 ()units of Item in week
9sing the lead time for the item, determine the week in
which the order should be released 8 a + week lead timemeans the order for () units should be released in week
This step is often called :lead time offset; or :time phasing;
From the 01", every Item re!uires < Item 0s 8 +))Item 0s are re!uired in week to satisfy the order releasefor Item
Deter+i"i" Gross Re;uire+e"ts
8/17/2019 MRP lot for lot
19/43
The lead time for the Item 0 is < weeks 8 release an orderfor +)) units of Item 0 in week (
The timing and !uantity for component re!uirements are
determined by the order release of the parent=s> The process continues through the entire 01" one level
at a time 8 often called :explosion;
0y processing the 01" by level, items with multiple
parents are only processed once, saving time andresources and reducing confusion
?ow'level coding ensures that each item appears at onlyone level in the 01"
Deter+i"i" Gross Re;uire+e"ts co"t.1
8/17/2019 MRP lot for lot
20/43
T#e l$%i& $' (et requireme(ts
A)aila*le i()e(t$r+
,etrequireme(ts
O(#a(d
-eduledre&eits
/ 0
T$tal requireme(ts
"r$ssrequireme(ts All$&ati$(s/
Net Re;uire+e"ts P%a"
8/17/2019 MRP lot for lot
21/43
Net Re;uire+e"ts P%a"
8/17/2019 MRP lot for lot
22/43
Net Re;uire+e"ts P%a" co"t.1
8/17/2019 MRP lot for lot
23/43
$tarts with a production schedule for the end item 8 () units ofItem in week
0ecause there are +) Item s on hand, only -) are actually
re!uired 8 =net re!uirement> @ =gross re!uirement ' on' handinventory>
The planned order receipt for Item in week is -) units 8 -)@ () 8 +)
Following the lead time offset procedure, the planned orderrelease for Item is now -) units in week
Deter+i"i" Net Re;uire+e"ts
8/17/2019 MRP lot for lot
24/43
The gross re!uirement for Item 0 is now ) units in week
There are +( units of Item 0 on hand, so the net re!uirement is*( units in week
planned order receipt of *( units in week generates a planned order release of *( units in week (
planned order receipt of *( units in week generates a planned order release of *( units in week (
The on'hand inventory record for Item 0 is updated to reflectthe use of the +( items in inventory and shows no on'handinventory in week
This is referred to as the 3ross'to'7et calculation and is the
third basic function of the "%# process
Deter+i"i" Net Re;uire+e"ts co"t.1
8/17/2019 MRP lot for lot
25/43
U*$ati" te MRP s4ste+
• The two basic systems used to update "%#
records are4
%egenerative system4 pproach that
updates "%# records periodically
7et change system4 approach that updates
records continuously
8/17/2019 MRP lot for lot
26/43
A'MED FAI&AL
8/17/2019 MRP lot for lot
27/43
Lot &ii" the process of modifying the net re!uirement !uantities before
they are translated into planned orders in an "%# system.
If net re!uirements were translated directly into planned orders,
it would result in manufacturing component schedules and
purchasing schedules that did not take any account of the cost
of machine setups or the cost of ordering.
8/17/2019 MRP lot for lot
28/43
. Lot for Lot
It is called A1B =Aiscrete 1rder Buantity>, and is a method for
lot si2ing, where the net re!uirements occurring for each period
are the !uantity of order. This method is often used mainly forexpensive items and the items whose demand occurs
intermittently. In this case the !uantity is the same as that of the
case in which one period is specified in the fixed period
re!uirements.
Lot &ii" Tec"i;ues
8/17/2019 MRP lot for lot
29/43
•
*+am&le,The company that makes a table want to ship +)) units at the beginning of theday -,+() units at the beginning of day (, and
8/17/2019 MRP lot for lot
30/43
• *+am&le (!n"
8/17/2019 MRP lot for lot
31/43
as"er a$ 1 2 3 4 5 6 7
S(hedule f!r"ale
ale 100 150 200
ale.!" size , .!" f!r l!"
e% in# 1 2 3 4 5 6 7
Gr!ss reuiermen" 100 150 200
S(heduled re(ie&"s
'r!je("ed !n hand 0 0 0 0 0 0 0 0
e" reuiermen" 100 150 200
'lanned/!rder/re(ie&"s 100 150 200
'lanned/!rder/releases 100 150 200
!!d se("i!n :2;.!" size , .!" f!r l!"
e% in# 1 2 3 4 5 6 7
Gr!ss reuiermen" 200 300 400
S(heduled re(ie&"s 100'r!je("ed !n hand 0 0 100 100 0 0 0 0
e" reuiermen" 100 300 400
'lanned/!rder/re(ie&"s 100 300 400
'lanned/!rder/releases 400 400
*+am&le (!n"
8/17/2019 MRP lot for lot
32/43
ra(es :3;.!" size , .!" f!r l!"
e% in# 1 2 3 4 5 6 7
Gr!ss reuiermen" 300 450 600
S(heduled re(ie&"s 100
'r!je("ed !n hand 60 60 60 60 0 0 0 0
e" reuiermen" 240 450 600
'lanned/!rder/re(ie&"s 240 450 600
'lanned/!rder/releases 240 450 600
.e%s:4;
.!" size , .!" f!r l!"e% in# 1 2 3 4 5 6 7
Gr!ss reuiermen" 400 600 800
S(heduled re(ie&"s
'r!je("ed !n hand 120 120 120 120 0 0 0 0
e" reuiermen" 280 600 800
'lanned/!rder/re(ie&"s 280 600 800'lanned/!rder/releases 880 800
*+am&le (!n"
8/17/2019 MRP lot for lot
33/43
8. Eco"o+ic Or$er
8/17/2019 MRP lot for lot
34/43
=. Fi2e$ Perio$ Or$eri" &4ste+
It is an inventory control method where orders are periodically placed, but the
order !uantity is different every time, and is also called Fixed #eriod Aeficit
1rdering $ystem. The method has the following features4
D n order is periodically placed.
D The order !uantity is different every time.
D Even relatively large fluctuations in demand can be handled properly.
D Even seasonal variation can be handled modestly.D The inventory volume can be reduced compared with ordering point system.
D 'group items are usually best for this method.
D ?onger lead time is acceptable.
D ?onger time for paperwork is needed.
Lot &ii" Tec"i;ues co"t.1
8/17/2019 MRP lot for lot
35/43
'U&&EIN (AD'IM &'ARAF
8/17/2019 MRP lot for lot
36/43
MRP OUTPUT
8/17/2019 MRP lot for lot
37/43
Pri+ar4 re*orts
8/17/2019 MRP lot for lot
38/43
&eco"$ar4 re*orts
8/17/2019 MRP lot for lot
39/43
&afet4 &toc>
8/17/2019 MRP lot for lot
40/43
!e"efits of MRP
8/17/2019 MRP lot for lot
41/43
!ac>f%usi"
Exploding an end items todetermine the !uantities of the
component that were used to
make item
8/17/2019 MRP lot for lot
42/43
Re;uire+e"ts of MRP
8/17/2019 MRP lot for lot
43/43
han< =!u