MRP lot for lot

Embed Size (px)

Citation preview

  • 8/17/2019 MRP lot for lot

    1/43

      5606 MANUFACTURING OPERATION MANAGEMENT

    NO.

    NAME MATRIC NO.

    1 Sarah Kanaan Hamzah GS446872 Ahmed Faisal Ahmed GS460193 Amin Shafanejad GS462364 Hussein Kadhim Sharaf GS45602

     Lecturer:

    Associate Professor Dr. Faiea !i"ti A#$u% Ai

    GROUP 6 

    MRP

  • 8/17/2019 MRP lot for lot

    2/43

     

    &ARA' (ANAAN 'AM)A'

  • 8/17/2019 MRP lot for lot

    3/43

    I"$e*e"$e"t De+a"$

    • It refers to the demand of finished goods, which are ordered by

    External Customers or manufactured for stock and sale.

    • Independent demands for inventories are based on confirmed

    Customer orders, forecasts, estimates and past historical data.

    De*e"$e"t $e+a"$

    • It refers to the demand for items that are subassemblies or

    component parts to be used in the production of finished goods. Theamount of dependent demand is the function of the amount of

    independent demand• For example, the parts and materials that go into the production of an automobile are examples of

    dependent demand, because the total amount of parts and raw materials needed during any time

     period is a function of the number of cars that will be produced. Conversely, demand for the

    finished cars is independent. car is not a component of another item

     I"$e*e"$e"t a"$ De*e"$e"t De+a"$ I",e"tories

  • 8/17/2019 MRP lot for lot

    4/43

    Material RequirementPlanning (MRP)

    It is a production planning process that starts from the demand for

    finished products and plans the production step by step of

    subassemblies and parts

    It is also a set of techni!ues that takes the "aster #roduction

    $chedule and other information from inventory records and

     product structure records as inputs to determine re!uirements and

    schedule of timing for each item.

  • 8/17/2019 MRP lot for lot

    5/43

    This inventory management system is appropriate for items

    that have a dependent demand.

    "%# is applicable for industries that offer variety of finished products where the customer is allowed to choose among

    many different options.

    "%# is most appropriate when the manufacturing environmentis complex and uncertain.

    -ere is MRP A**%ica#%e/

  • 8/17/2019 MRP lot for lot

    6/43

    Pur*ose of MRP

    !n"r!l in#en"!r$ le#els

    Assi%n !&era"in% &ri!ri"ies

    'lan (a&a(i"$ "! l!ad "he &r!du("i!ns$s"em

  • 8/17/2019 MRP lot for lot

    7/43

    MRP &tructure

  • 8/17/2019 MRP lot for lot

    8/43

    MRP INPUT&

  • 8/17/2019 MRP lot for lot

    9/43

    Te Master Pro$uctio" &ce$u%e

      "#$ is prepared based on actual customers orders

    and predicted demand. This schedule indicates

    exactly when each ordered item will be produced tomeet the firm and predicted demand& that is, it is a

    time'phased production plan.

  • 8/17/2019 MRP lot for lot

    10/43

    MPS Examle ! A"e#$me Sea%er Se&iali#t

    'r$## Requirement# $r Sea%er

    s shown on top this "aster #roduction $chedule shows

     planned output for end item speaker. The schedule indicate that

    () units needs on *th week, +)) unit needs on th week, -

    units needs on /th week and so on.

    The !uantities in a master schedule come from a number of

    different sources, including customer order, forecasts and other

    from warehouse to build up seasonal inventories.

  • 8/17/2019 MRP lot for lot

    11/43

    For each item in the "#$, a bill of material exists.

    The 01" file indicates all the raw materials,

    components, subassemblies and re!uired to producean item. The "%# computer system accesses the

    01" file to determine exactly what items, and in

    what !uantities, are re!uired to complete an order for

    a given item.

    !i%% of Materia% !OM1

  • 8/17/2019 MRP lot for lot

    12/43

    !OM E2a+*%e

  • 8/17/2019 MRP lot for lot

    13/43

    uantit* $n +een+ent art# t$ ,uilt t-e in+een+ent art (A)

    If tere is O"3'a"$ I",e"tor4: !0 7 C 80 E2a+*%e1

    !OM E2a+*%e co"t.1

  • 8/17/2019 MRP lot for lot

    14/43

    )" contains detailed information regarding thenumber of !uantity of each item on hand, on order,

    and committed to use in various time periods. The"%# computer system accesses the I% computer file

    to determine the !uantity available for use in a given

    time period and, if enough are available to meet the

    order needs, commits these for use during the time period by updating the inventory record. If sufficient

    items, as well as the usual lot si2e, on the planned

    order release report.

    Te I",e"tor4 Recor$s

  • 8/17/2019 MRP lot for lot

    15/43

    AMIN &'AFANE9AD

  • 8/17/2019 MRP lot for lot

    16/43

    MRP Processi":

    3ross %e!uirement4 The total expected demand for an item or raw materialduring each time period without regard to the amount on hand.

    $chedule %eceipt4 Existing orders that arrive at beginning of period.

    #ro5ected on 6and4 Inventory balance that will be on hand at the beginning ofeach time period.

     7et %e!uirement4 The actual amount needed in each time period.

    #lanned'order %eceipts4 The !uantity expected to be received by the beginning of the period.

    #lanned'order %elease4 Indicate a plan amount to order in each time period oroffset by lead time.

  • 8/17/2019 MRP lot for lot

    17/43

    Week 

    1 2 3 4 5 6 7 8 Lead Time

     A. Required date   50Order release date   50 1 week 

    B. Required date   100Order release date   100 2 weeks

    C. Required date   150Order release date   150 1 week 

    . Required date 200 300Order release date   200 300 2 weeks

    !. Required date   300Order release date   300 3 weeks

    ". Required date 600 200Order release date   600 200 1 week 

    ". Required date 300Order release date   300 2 weeks

    Gross Re;uire+e"ts P%a"

  • 8/17/2019 MRP lot for lot

    18/43

    $tarts with a production schedule for the end item 8 ()units of Item in week

    9sing the lead time for the item, determine the week in

    which the order should be released 8 a + week lead timemeans the order for () units should be released in week

    This step is often called :lead time offset; or :time phasing;

    From the 01", every Item re!uires < Item 0s 8 +))Item 0s are re!uired in week to satisfy the order releasefor Item

    Deter+i"i" Gross Re;uire+e"ts

  • 8/17/2019 MRP lot for lot

    19/43

    The lead time for the Item 0 is < weeks 8 release an orderfor +)) units of Item 0 in week (

    The timing and !uantity for component re!uirements are

    determined by the order release of the parent=s> The process continues through the entire 01" one level

    at a time 8 often called :explosion;

    0y processing the 01" by level, items with multiple

     parents are only processed once, saving time andresources and reducing confusion

    ?ow'level coding ensures that each item appears at onlyone level in the 01"

    Deter+i"i" Gross Re;uire+e"ts co"t.1

  • 8/17/2019 MRP lot for lot

    20/43

    T#e l$%i& $' (et requireme(ts

     A)aila*le i()e(t$r+ 

    ,etrequireme(ts

    O(#a(d 

    -eduledre&eits

    / 0

    T$tal requireme(ts

    "r$ssrequireme(ts  All$&ati$(s/

    Net Re;uire+e"ts P%a"

  • 8/17/2019 MRP lot for lot

    21/43

    Net Re;uire+e"ts P%a"

  • 8/17/2019 MRP lot for lot

    22/43

    Net Re;uire+e"ts P%a" co"t.1

  • 8/17/2019 MRP lot for lot

    23/43

    $tarts with a production schedule for the end item 8 () units ofItem in week

    0ecause there are +) Item s on hand, only -) are actually

    re!uired 8 =net re!uirement> @ =gross re!uirement ' on' handinventory>

    The planned order receipt for Item in week is -) units 8 -)@ () 8 +)

    Following the lead time offset procedure, the planned orderrelease for Item is now -) units in week

    Deter+i"i" Net Re;uire+e"ts

  • 8/17/2019 MRP lot for lot

    24/43

    The gross re!uirement for Item 0 is now ) units in week

    There are +( units of Item 0 on hand, so the net re!uirement is*( units in week

    planned order receipt of *( units in week generates a planned order release of *( units in week (

    planned order receipt of *( units in week generates a planned order release of *( units in week (

    The on'hand inventory record for Item 0 is updated to reflectthe use of the +( items in inventory and shows no on'handinventory in week

    This is referred to as the 3ross'to'7et calculation and is the

    third basic function of the "%# process

    Deter+i"i" Net Re;uire+e"ts co"t.1

  • 8/17/2019 MRP lot for lot

    25/43

    U*$ati" te MRP s4ste+

    • The two basic systems used to update "%#

    records are4

    %egenerative system4 pproach that

    updates "%# records periodically

     7et change system4 approach that updates

    records continuously

  • 8/17/2019 MRP lot for lot

    26/43

    A'MED FAI&AL

  • 8/17/2019 MRP lot for lot

    27/43

    Lot &ii"  the process of modifying the net re!uirement !uantities before

    they are translated into planned orders in an "%# system.

    If net re!uirements were translated directly into planned orders,

    it would result in manufacturing component schedules and

     purchasing schedules that did not take any account of the cost

    of machine setups or the cost of ordering.

  • 8/17/2019 MRP lot for lot

    28/43

    . Lot for Lot

    It is called A1B =Aiscrete 1rder Buantity>, and is a method for

    lot si2ing, where the net re!uirements occurring for each period

    are the !uantity of order. This method is often used mainly forexpensive items and the items whose demand occurs

    intermittently. In this case the !uantity is the same as that of the

    case in which one period is specified in the fixed period

    re!uirements.

    Lot &ii" Tec"i;ues

  • 8/17/2019 MRP lot for lot

    29/43

    *+am&le,The company that makes a table want to ship +)) units at the beginning of theday -,+() units at the beginning of day (, and

  • 8/17/2019 MRP lot for lot

    30/43

    • *+am&le (!n"

  • 8/17/2019 MRP lot for lot

    31/43

    as"er a$ 1 2 3 4 5 6 7

    S(hedule f!r"ale

     ale 100 150 200

     ale.!" size , .!" f!r l!"

    e% in# 1 2 3 4 5 6 7

    Gr!ss reuiermen" 100 150 200

    S(heduled re(ie&"s  

    'r!je("ed !n hand 0 0 0 0 0 0 0 0

    e" reuiermen"   100 150 200

    'lanned/!rder/re(ie&"s   100 150 200

    'lanned/!rder/releases   100 150 200

    !!d se("i!n :2;.!" size , .!" f!r l!"

    e% in# 1 2 3 4 5 6 7

    Gr!ss reuiermen" 200 300 400

    S(heduled re(ie&"s   100'r!je("ed !n hand 0 0 100 100 0 0 0 0

    e" reuiermen"   100 300 400

    'lanned/!rder/re(ie&"s   100 300 400

    'lanned/!rder/releases   400 400

    *+am&le (!n"

  • 8/17/2019 MRP lot for lot

    32/43

    ra(es :3;.!" size , .!" f!r l!"

    e% in# 1 2 3 4 5 6 7

    Gr!ss reuiermen" 300 450 600

    S(heduled re(ie&"s 100

    'r!je("ed !n hand 60 60 60 60 0 0 0 0

    e" reuiermen" 240 450 600

    'lanned/!rder/re(ie&"s 240 450 600

    'lanned/!rder/releases 240 450 600

    .e%s:4;

    .!" size , .!" f!r l!"e% in# 1 2 3 4 5 6 7

    Gr!ss reuiermen" 400 600 800

    S(heduled re(ie&"s

    'r!je("ed !n hand 120 120 120 120 0 0 0 0

    e" reuiermen" 280 600 800

    'lanned/!rder/re(ie&"s 280 600 800'lanned/!rder/releases 880 800

    *+am&le (!n"

  • 8/17/2019 MRP lot for lot

    33/43

    8. Eco"o+ic Or$er

  • 8/17/2019 MRP lot for lot

    34/43

    =. Fi2e$ Perio$ Or$eri" &4ste+

    It is an inventory control method where orders are periodically placed, but the

    order !uantity is different every time, and is also called Fixed #eriod Aeficit

    1rdering $ystem. The method has the following features4

    D n order is periodically placed.

    D The order !uantity is different every time.

    D Even relatively large fluctuations in demand can be handled properly.

    D Even seasonal variation can be handled modestly.D The inventory volume can be reduced compared with ordering point system.

    D 'group items are usually best for this method.

    D ?onger lead time is acceptable.

    D ?onger time for paperwork is needed.

    Lot &ii" Tec"i;ues co"t.1

  • 8/17/2019 MRP lot for lot

    35/43

    'U&&EIN (AD'IM &'ARAF

  • 8/17/2019 MRP lot for lot

    36/43

    MRP OUTPUT

  • 8/17/2019 MRP lot for lot

    37/43

    Pri+ar4 re*orts

  • 8/17/2019 MRP lot for lot

    38/43

    &eco"$ar4 re*orts

  • 8/17/2019 MRP lot for lot

    39/43

    &afet4 &toc> 

  • 8/17/2019 MRP lot for lot

    40/43

    !e"efits of MRP

  • 8/17/2019 MRP lot for lot

    41/43

    !ac>f%usi"

    Exploding an end items todetermine the !uantities of the

    component that were used to

    make item

  • 8/17/2019 MRP lot for lot

    42/43

    Re;uire+e"ts of MRP

  • 8/17/2019 MRP lot for lot

    43/43

     han< =!u