Mrp Fall08

Embed Size (px)

Citation preview

  • 7/30/2019 Mrp Fall08

    1/35

    MRP

  • 7/30/2019 Mrp Fall08

    2/35

    Question: how do firms actually organize things

    to turn materials into finished products?

  • 7/30/2019 Mrp Fall08

    3/35

    Master Production Schedule (MPS)

    Time-phased plan specifying how many and

    when the firm plans to build each end item

    Aggregate Plan

    (Product Groups)

    MPS

    (Specific End Items)

  • 7/30/2019 Mrp Fall08

    4/35

    MPS ExampleMaine Woods Toy Co.

    41 42 43 44 45 46 47 48 49 50 51 52

    Tricycle 300 300 300 300 300 300 300 300 250 250 250 250Wagon 300 300 300 300 250 250

    Scooter 300 300 300 300 250 250

    Totals 2,000

    Week

    Produc

    t

    2,400 2,400

    October November DecemberMonth

    One possible MPS

  • 7/30/2019 Mrp Fall08

    5/35

    Products are combinations of parts

    Example: Bicycle

    Handle bars (1)

    Metal Frame (1)

    Wheels (2)

  • 7/30/2019 Mrp Fall08

    6/35

    Dependent vs Independent Demand

    Dependent Demand

    Demand for a

    component (raw

    material, part, sub-assembly) is dependent

    on the demand for the

    end-item into which the

    component goes. demand often occurs in

    batches

    Independent Demand

    Demand for an item is

    independent of the demand

    for other items. Thesedemands are typically

    determined by outside

    customers and are end-item

    demands

  • 7/30/2019 Mrp Fall08

    7/35

    Bill of Materials (BOM)

    Shows all the assemblies, subassemblies, components,

    and raw materials required to produce an item

    Shows way a finished product or parent item is put

    together from individual components Parent item shown at highest level or level zero

    Parts that go into parent item are called level 1

    components and so on Production planners explode BOM for level zero item

    to determine the number, due dates, and order dates of

    subcomponents

  • 7/30/2019 Mrp Fall08

    8/35

    Lets look at an example BOM...

    A

    B(2) C(1)

    D(3) E(3) D(1)

    Question:

    How many Ds we need in

    order to produce 50 As?

  • 7/30/2019 Mrp Fall08

    9/35

    Schematic of MRP System

  • 7/30/2019 Mrp Fall08

    10/35

    Material Requirements Planning (MRP)

    Computer-based information system that

    schedules and orders dependent-demand

    inventory components;

    Uses the master production schedule, bills of

    materials, and inventory records as inputs;

    Outputs recommendations:

    When to release new orders

    When to reschedule open orders.

  • 7/30/2019 Mrp Fall08

    11/35

    Lets look at an example BOM...

    A

    B(2) C(1)

    D(3) E(3) D(1)

  • 7/30/2019 Mrp Fall08

    12/35

    How do we manage order release?

    Parts-Product Process Lead TimeA 10

    B 15

    C 10D 15

    E 10

    We need information on delivery times!

  • 7/30/2019 Mrp Fall08

    13/35

    Lets look at an example BOM...

    A

    B(2) C(1)

    D(3) E(3) D(1)

    Question:

    When do we start

    producing/ordering eachpart?

    (10)

    (15) (10)

    (10)

    (15)

    (15)

  • 7/30/2019 Mrp Fall08

    14/35

    Lets assume that we need 50 units of A

    Parts-Products

    A

    B

    C

    D

    E

    Delivery date

    for final

    product

    5 days

  • 7/30/2019 Mrp Fall08

    15/35

    Lets assume that we need 50 units of A

    Parts-Products

    A

    B

    C

    D

    E

    Start

    assembly for

    50 units of A

  • 7/30/2019 Mrp Fall08

    16/35

    Lets assume that we need 50 units of A

    Parts-Products

    A

    B

    C

    D

    E

    Start

    assembly for

    100 units of B

  • 7/30/2019 Mrp Fall08

    17/35

    Lets assume that we need 50 units of A

    Parts-Products

    A

    B

    C

    D

    E

    Start

    assembly for

    50 units of C

  • 7/30/2019 Mrp Fall08

    18/35

    Lets assume that we need 50 units of A

    Parts-Products

    A

    B

    C

    D

    E

    Order 300

    units of D for

    Bs process

  • 7/30/2019 Mrp Fall08

    19/35

    Lets assume that we need 50 units of A

    Parts-Products

    A

    B

    C

    D

    E

    Order 50

    units of D for

    Cs assembly

  • 7/30/2019 Mrp Fall08

    20/35

    Lets assume that we need 50 units of A

    Parts-Products

    A

    B

    C

    D

    E

    Order 50

    units of E for

    Cs assembly

  • 7/30/2019 Mrp Fall08

    21/35

    Customer

    Assembly

    Assembly

    Production

    Production

    Production

    Units are PUSHED forward according to the plan!

    Summary: How does MRP work?

    Material Requirements Planning

  • 7/30/2019 Mrp Fall08

    22/35

    Customer

    Assembly

    Assembly

    Production

    Production

    Production

    Units are PULLED forward only when needed!

    What about JIT/Lean Production?

  • 7/30/2019 Mrp Fall08

    23/35

    Forecast

    HamburgerPatties

    Chicken

    Patties

    Cheeseburger

    Hamburger

    Chicken

    Sandwich

    Push/Pull Decoupling Point

    Material Requirements Planning

    Units are PUSHED forward to a certain point. Final

    configuration (PULL) occurs only when the actual

    customer demand occurs.

  • 7/30/2019 Mrp Fall08

    24/35

    Lot Sizing in MRP Systems

    Lot-for-lot (L4L):

    Produce to cover next period

    EOQ:

    Apply the EOQ approximation for yearly demand

    Least Unit Cost:

    Minimize total cost (order + carry) per unit

    These are all approximate methods, none is guaranteed to be

    optimal. We can apply all of them and find the least-cost one

    to implement.

    MRP generates material orders

    Order sizes/lots can be chosen according to various objectives

  • 7/30/2019 Mrp Fall08

    25/35

    Example

    Cost per item: $10Order/setup cost: $47

    Inventory carrying cost/month 2%

    Starting inventory: 50

    Production lead time 1 month

    Monthly requirements1 2 3 4 5 6

    100 50 80 120 70 80

    For the solution, see file mrp_methods.pdf

  • 7/30/2019 Mrp Fall08

    26/35

    MRP Evolution

    MRP

    Closed Loop

    MRP

    MRP II

    ERP

    Schedule Materials

    Schedule Materials

    Incorporate Feedback

    Schedule & Purchase Materials

    Coordinate w/ Mfg Resources

  • 7/30/2019 Mrp Fall08

    27/35

    Closed-Loop MRP

    Production Planning

    Master Production Scheduling

    Material Requirements Planning

    Capacity Requirements Planning

    Realistic?No

    Feedback

    Execute:

    Capacity Plans

    Material Plans

    Yes

    Feedback

  • 7/30/2019 Mrp Fall08

    28/35

    Goal: Plan and monitor all resources of amanufacturing firm (closed loop):

    manufacturing marketing

    finance

    engineering

    Simulate the manufacturing system

    Manufacturing Resource Planning

    (MRP II)

  • 7/30/2019 Mrp Fall08

    29/35

  • 7/30/2019 Mrp Fall08

    30/35

    Typical ERP System

  • 7/30/2019 Mrp Fall08

    31/35

    Video: ERP at Hillerich & Bradsby

    Notes:

  • 7/30/2019 Mrp Fall08

    32/35

    Major ERP Providers

    Firm HQ Acquisitions 2004 Shareof $23.6B

    Market

    SAP Germany 40%

    Oracle US People Soft

    JD Edwards22%

    Sage Group UK 7%

    Microsoft US 3%

    Infor US SSA

    Baan

    Source: AMR Research

  • 7/30/2019 Mrp Fall08

    33/35

    Desire to standardize and improveprocesses

    To improve the level of systemsintegration

    To improve information quality

    Reasons to Implement ERP

  • 7/30/2019 Mrp Fall08

    34/35

  • 7/30/2019 Mrp Fall08

    35/35

    Summary and Conclusions

    Master Production Schedule (MPS)converts aggregate plan to a detailedschedule

    Primary inputs to MRP are MPS, BOMs

    (for part relationships) and InventoryRecords (for lead times and inventoryposition)

    MRP is a push system but can be used inconjunction with pull systems

    MRP grew and evolved to include closed-loop, Manufacturing Resource PlanningMRP II d t ll ERP