Upload
velusankar
View
213
Download
0
Embed Size (px)
Citation preview
8/20/2019 Motor Operaed Valve Analysis
http://slidepdf.com/reader/full/motor-operaed-valve-analysis 1/6
MOTOR-OPERATED VALVE ANALYSIS PROGRAM
TO ADDRESS
THE DESIGN BASIS REVIEW REQUIREMENTS
OF
THE US NRC's GENERIC LETTER 89-10
M. Recinella and F. Isaac
(Westinghouse Energy Systems International, Brusssels)
T. Matty
(Westinghouse Nuclear and Advanced Technology Division, Pittsburgh)
1.0 INTRODUCTION
The EPRI sponsored PORV block valve testing conducted at the Marshall S team
Station in 1980 following the Three Mile Island accident provided the first
indications o f a potential motor-operated valve (MOV) problem in the nuclear
industry. A three inch 1500 class Westinghouse Electromechanical D ivision (EMD)
MOV failed t o fully close against high pressure and high temperature steam flow .
Shortly thereafter, valves of the same size were tested against high pressure, low
temperature water flow in the safety injection system o f a european nuclear power
plant and some of these valves also failed to close completely.
In November 1980 Westinhgouse initiated a MOV flow testing program to investigate
the required operating loads and the crit ical parameters 1).
On June 9 ,1 985, a loss-of-feedwater event occured at the Davis-Besse nuclear
power plant. The MOVs in the Auxiliary Feedwater (AFW) system could no t be
reopened electrically from the c ontrol room after having them inadvertently
closed. It was later found that the MOVs failed to open because of inadequate
torque switch bypass.
As a
onsequen e
of these and other related events the NRC staff issued in
November 1985 Bulletin 85-03 (2) and in April 1988 a Supplement 1 to Bulletin
85-03 to ensure that switch settings on all safety-related M OVs and on the MOVs
that cou ld be inadvertently mispositioned in the High-Pressure C oolant Injection
(HPCI) and Emergency Feedwater Systems (EFS) were selected, set, and maintained
proper ly.
Tests performed as part of the RES (NRC Office of Nuclear Regulatory Research)
effort to resolve Generic Issue 87 (3) have reinforced concerns for the
operability of MOVs under design-basis condit ions.
Generic Issue 87 (GI-87) issued in December 1985 covers three Boiling Water
Reactor (BWR) process lines: the HPCI turbine steam supply line, the reactor core
isolation cooling (RCIC) turbine steam supply line, and the reactor Water Cleanup
(RWCU) process line. All three of the BWR process lines comm unicate w ith the
primary system , pass through containment, and normally have open isolation valves.
The concern w ith the isolation valves is whether they will close in the event o f a
pipe break outside of the containment.
Motor-Op erated Valve A nalysis Program to address the D esign Basis R eview
Requirements of the US NRC's Generic Letter 89-10
16
8/20/2019 Motor Operaed Valve Analysis
http://slidepdf.com/reader/full/motor-operaed-valve-analysis 2/6
The NRC-sponsored testing of MO Vs has been conducted in tw o phases by the Idaho
National Engineering Laboratory (INEL). Phase I was performed in 19 88 at the W yle
Laboratory fatifty. Hot wate r b bw do wn tests were performed on tw o flexible wedge
gate valves typical of those used for containm ent isolation in the su pply line to
the RW CU . The results are documented in NUREG/CR-54O6 (4). The phase II wa s
performed in 19 89 at the Kraftwerk Union facility, iix valves, were tested typical
of those used in RW CU and HPCI applications. One of the valves was also tested at
RCIC test conditions. The test results are documented in NURE G/C R-55 58 (5) .
The tests revealed that more thrust w as required to operate the valves under
design-basis conditions than would have been predicted from standard industry
calculations and typical friction factors.
In June 1 98 9 the NR C issued Generic Letter 89 -1 0 ( 6). By this letter the NRC
extends the scope o f the program outlined in Bulletin 85- 03 and Supplement 1 of
Bul let in 85-03 to include al l safety-related MOVs as wel l as al l
position-changeable MOVs. Later supplements to Generic Letter 89-10 changed the
position-changeable M OV s to only those valves that can be controlled from the
control room; and fbrBW Rs the mispositioning of M O Vs don't need to be considered.
Generic Letter 89 -1 0 requires mainly that each licensee develop a program that
provide a review o f the M O V design basis, methods for correct sw itch settings,
field testing a t design-basis conditions, procedures to ensure sw itch setting is
maintained, . . .
The present paper describes the elements and the methodologies used by
Westinghouse to address the M O V Design Basis Review requirements of the NRC
Gener ic Let ter 89-10 .
2 . 0 PRO G RAM DESCRI PT IO N
2.1 Da ta col lection
Gathering data is time consuming and the related effort is often unde restimate d.
How ever this is the first and probably the m ost important step in the M O V design
basis review program and therefore major attention should be given to this task.
The information wh ich is needed in a first place are the pressure and temperature
conditions w hich the valve must stroke against for all modes of o peration. This
data is the result of a fluid system evaluation.
Since the am ount of M O V 's in a Nuclear Power Plant is considerable it is wise t o
review the valve inventory and to group M O V s in order to reduce duplication of
analysis.
Further in order to bs able to perform thrust and torque calculations and valve
we ak link analysis, drawings of the valve internals an d valve design reports are
necessary. How ever in most cases this information, except a M O V general assembly ,
drawing, is not in the possession of the utilities and will have to be requested >;.
from the valve manufacturer. '
Motor-Operated Valve Analysis Program to address the Design Basis Review
Requirements of the US NRC's Generic Letter 89-10
8/20/2019 Motor Operaed Valve Analysis
http://slidepdf.com/reader/full/motor-operaed-valve-analysis 3/6
especially for older plants, the general assembly drawing may be th e only piece o f
existing information. In such cases an approach of measuring on available va lve
spare parts or a disassembly of the valve itself may be required.
To assess the operator capabilities a series of operator characteristics are
needed. These are l isted in paragraph 2.4 of this paper.
2. 2 Thrust and torque calculation
Th e seco nd e lement in the analysis involves the calculation of the required thru st
and/or torque to op en and close the valve a t the defined pressure conditions.
In the thru st and torque calculation equations there are, w her e applicable
depending on the type of valve and operator, three variables which are o f
importance because they are difficult to define and w hich c an o nly be determined
by test ing .
The first is the V alve Factor defined by the s eat friction coefficient. The second
is the S tem Factor which contains the stem /stem nut friction coefficient as a
variable; and the last one is the Packing Load.
Westinghouse has performed extensive flow testing (1) to determine the critical
parameters that effect the required operating toads for th e Westinghouse gate
valves.
The results of the testing performed in the early 1 98 0 's recognized tha t
the calculations could be under predictive of the actua l required thrusts bec ause
the valve factors ma y be greater than the standard valve factors. In addition t he
test program included, amoung oth ers, investigation of th e s tem/stem nut friction
coeff icient and packing drag loads.
2.3 Va lve W ea k Link Analysis
This analysis consists in determining the va lve w eak est part or parts w hich are
subjected to the operating thrust and/or torque.
In general the valve pans, where applicable depending o n the type of va lve, wh ich
are affected by the thrust and/or torque are :
- valve stem
- stem nut
- valv e disc
- stem /disc l ink
- valve main seat
- back seat
- valve yoke
- yok e to bonn et bolts
- yok e to actuator bol ts
• valve bonnet
- valve body
- bonne t/body bolts
Motor-Operated Valve Analysis Program to address the Design Basis Review
Requirements of the US NRC's Generic Letter 89-10
162
8/20/2019 Motor Operaed Valve Analysis
http://slidepdf.com/reader/full/motor-operaed-valve-analysis 4/6
In order to perform th e analysis of th e above p a rs some detailed dimensional
information is required as w e* as the parts material specification. As men tioned
in the v alve data collection task, this information is not a lway s available and
cannot be readi ly obtained.
However to reduce the impacts of the limited information and so to limit the
amount o f calculations, the above valve part list can be reduced based on valve
engineering experience.
The valve w eak ink evaluation consists in calculating backwards in the compo nents
stress formulas w here by th e material allowables are considered as applied stress.
In this w ay for eac h valve part under analysis a maximum allowable thrust and/or
torque is calculated. Th e lesser of these maximum values w i determine the valve
weakest part (Valve W ea k Link Analysis) and so determine the valve capability to
suit for the speci f ied pressure condit ions.
2 .4 Mo tor Operator Evaluation
Th e objective of this evaluation is to summ arize relevant operator characteristics
in order to determine operator capabilities to suit for the specified pressure
condit ions.
For this evaluation important operator parameters are :
- Mo tor size, speed, performance curve, operator unit gear ratio and operator
efficiency in order to estimate the operator torque ou tput capabilities an d
to estimate stroke t imes and to compare to requirements.
- Operator rated torque and thrust for a specified number of cyc les.
It has been experienced that the outpu t thrust of som e operators has
exceeded the operators' nominal thrust ratings because they w ere set too
high or additional thrust is required to operate the valves. Due to the
overthrust operating conditions, a qualification tes t program wa s developed
and rnptememed by W estinghouse in order to increase the present nominal
ttvuft ratings of iheSMBOOO, SMBOO, SMB O, SMB-1, SMB-2, SBOOand SBO
Limitorque operators.
- Operator stall torque considering voltage variations. Th e stall torq ue is
whether obtained by calculation or from manufacturer shop tes ting, or from
in si tu bench test.
- The operator torque switch setting range and torque switch repeatability.
Motor-Operated Valve Analysis Program to address the Design Basis Review
Requirements of the US NRC's Generic Letter 89-10
163
8/20/2019 Motor Operaed Valve Analysis
http://slidepdf.com/reader/full/motor-operaed-valve-analysis 5/6
Inertia of the operator and the increase in thrust du e to torque sw itch
delay times are important parameters because they can be excessive large.
This information can be easily obtained during in situ testing of th e M O V s
by measuring thrust, motor current and torque sw itch close coil current.
Rate of Loading .
One of the conclusions of the NRC sponsored testing (4) (5 ) w as that s tem
factor changes with loading or loading rate resulting in less thrust being
delivered at higher differential pressures (slower load rate) for the sam e
torque switch setpoint.
While the changes observed w ere aH attributed to stem factor ch ang es, it
wa s recognized that some of the changes may be caused by differences in
torque output for a given spring pack displacement. The term Ra te of
Loading
has been used to categorize this variation in output thrust. Rate
of Loading ef fects o f about 2 0 % were measured.
The Westinghouse com pany m -M O VA TS has performed testing to study this
pnenomenum (7) and is currently performing further investigation on this
field.
2 .5 M O V recommended torque swi tch set ting
Whether the MOV will succesfully operate under the specified pressure and
temperature conditions depends on the relative importance of the required
operating thrust/torque, va lve maximu m allowable thrust/torque and the operator
thrust/torque capabil i ties.
It is the purpose of this task to point out th e upper and the lower bound of the
thrust and torque setting, to identify the margins to consider; and so to
determine the available thrust and torque setting range. A setting range which
wi l l assure proper and safe functioning of the MOV.
It is evident that the lower bound is determined by the maximum required thrust
and torque under the specified pressure conditions. The upper bound is the lesser
of the m aximum allowable valve thrust and torque, the operator rated thrust an d
torque; and operator stall torque at reduced voltage conditions.
The margins to consider on the upper and lower bound values are torque switch
repeatability, torque and thrust measurements errors, operator inertia, torque
switch delay t imes and Rate of Loading phenom ena.
Motor-Operated Valve Analysis Program to address the Oesign Basis Review
f, Requirements of the US NRC's Generic Letter 89 -1 0
I,
164
8/20/2019 Motor Operaed Valve Analysis
http://slidepdf.com/reader/full/motor-operaed-valve-analysis 6/6
3.0 REFERENCES
(1 ) Westinghouse B v D report EM 56 72
Rev.
1 :
Motor Operated Gate Valveaosure
Problem F low Test ing Program, September 23 , 1982.
(2) NRC Buletin85<X3:Mo<a<3peratBdVate common n r ^
transients due to improper switch sett ings.
(3) NRC Generic Issue 8 7 : Failure of HPCI Stea m Line W ithou t Isolation.
(4 ) NURE G/CR-5406: BWR Reactor WaterCleanup System Flexible Wedge Gate
Isolation Valve Qualification and High Energy Flow Interruption Test,
O c to b er 1989 .
(5 ) NUR EG/CR -5558: Generic Issue 8 7 Flexible Wedge Gate Valve Test Program,
J a n u a r y 1 9 9 1 .
(6 ) NRC Generic Letter 8 9 -1 0 : Safety-Related Motor-Operated Valve Testing and
Survei l lance.
(7) mMOVATSEnoneeririg Report B ^ 5 .0 F ^ 3 : m MOVATS Equipment Accuracy
S u m m a r y , O c t o b e r 1 9 9 1 .
Motor-Operated Valve Analysis Program to address the Design Basis Review
Requirements of the US NRC's Generic Letter 89-10
6