MORTER LESS CONSTRUCTION DETAILS

Embed Size (px)

Citation preview

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    1/47

    mortarlessA masonry wall system specifically developed for

    load bearing structures.

    Substantial savings possible in both time and cost.

    Completed buildings superior.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    2/47

    200 mortarless product range:There are only four basic products in the 200 mortarless

    product range:

    The stretcher block for the bulk of any wall.

    The full end block for every course at a corner and foralternate courses at ends of walls.

    The half end block for alternate courses at ends ofwalls.

    The plastic connectorone for every block.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    3/47

    Stretcher block

    Dimensions: 400 long x 200 wide x 200 high

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    4/47

    Full end block

    Dimensions: 400 long x 200 wide x 200 high

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    5/47

    Half end block

    Dimensions: 200 long x 200 wide x 200 high

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    6/47

    Connector

    Secures blocks end to end resists hydrostatic forces when wallis being filled with grout.

    Helps align blocks in any course.

    Helps position and align blocks in the overlying course.

    Secures vertical and horizontal reinforcement in correct location.

    Helps stabilise walls during construction.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    7/47

    Mortarless walls are always reinforced and fully

    grouted with core-fill concrete.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    8/47

    Constructing mortarless walls: Accurately set out and install vertical starter bars

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    9/47

    Always set first course in a mortar bed to accommodate

    irregularities in the footings or base slab and to provide full width

    bearing. Simple packing or wedging may also be used in

    certain applications.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    10/47

    When first course is laid, install plastic connectors and andcommence laying subsequent courses working from each endand using a string line and spirit level to maintain straightnessand plumb.

    (Note that laying is a two handed operation. (With lighter blocksthis means less strain on the wrists.)

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    11/47

    Note horizontal bar snugly fits into

    notches in connectors and this helps

    secure blocks in horizontal alignmentduring construction.

    By correctly positioning the horizontal

    bars during construction of the wall, the

    vertical bars can readily be inserted in

    their correct position to comply with the

    structural design requirements.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    12/47

    Continue constructing the wall to a height of about 1.6 to 2mand then install vertical bars in the specified locations prior togrouting.

    Rod grout to remove any trapped air. Finish grout below top ofblock if wall is to continue on, or finish flush if wall is up toheight.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    13/47

    Proceed with the next lift of wall in the same way.

    Construct insitu slabs or install precast slabs as per the

    structural details. Anchor slab reinforcement into walls and vice

    versa for ductile connections.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    14/47

    Mortarless masonry is a strong, solid, load bearingwall system

    The floor slabs and roof slabs (either pre-cast or castinsitu) are supported directly on the walls.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    15/47

    Walls can be designed to resist all axial loads and shear loads.

    Walls can also be designed to resist both transverse and in-plane bending moments, hence many lintel beams can simply

    be incorporated in the design of the walls:

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    16/47

    MEP services can be installed as the work proceeds. This

    saves much of the chasing in normally required.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    17/47

    Concrete framed buildings: Masonry construction is widely used throughout the world,

    however in many parts of the world including India, masonry is

    merely used as infill for walling.

    Building are constructed with concrete columns, beams andslabs and the masonry walls are installed as cladding elements.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    18/47

    Residential development with masonry infill walls

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    19/47

    Masonry infill walls

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    20/47

    Advantages of mortarless: Substantially reduced construction time and cost.

    Unskilled labour used for much of the construction effort

    Not weather dependent mortarless can be laid in the rain

    Greatly reduced mess on site

    Certainty of reinforcing bar positioning

    Proper cover to reinforcement

    No mortar dags or droppings to clean out of cores

    No clean-out blocks required, hence no shutters

    Solid construction - concrete filled walls

    Reduced thickness of cement plaster finishes Ductile constructionreadily designed for earthquake loads

    Walls, footings and slabs fully tied - stronger buildings

    More even distribution of loads to the foundation

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    21/47

    MEP services can be installed as the wall is being constructed

    eliminating the need for much of the chasing-in normally

    required. Design made easy by the tables provided

    Simplicity of detailing

    Professional technical support provided to specifiers and users.

    Severe damage to villas under construction that could have been avoided with mortarless

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    22/47

    Detailing mortarless walls: When detailing any project for mortarless it is preferable to set

    the buildings out in 200mm increments both horizontally andvertically.

    Preferably set out all openings (doors, windows etc) to also suitthe 200mm module.

    If the builder is unfamiliar with mortarless it is advisable toelevate the walls, or at least some typical walls. This will reducethe possibility of the builder making mistakes on site.

    Most walls will have typical reinforcement specified (e.g. N12-800 vertical and horizontal bars throughout). On any wallelevations therefore it should only be necessary to show theadditional bars trimming openings etc.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    23/47

    Example of plan showing setout of walls and starter bars

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    24/47

    Example of wall elevation drawing showing additional bars

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    25/47

    Show typical details for corners, wall intersections etc.

    Preferably provide a starter bar set-out plan for each level. This

    will minimise the risk of bars beings installed in the wrong

    locations, or bars being omitted.

    Adequately detail any mortarless lintels or beams with specialreinforcement.

    Show any special details for wall/slab junctions etc.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    26/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    27/47

    Designing mortarless walls:

    Design manuals are provided on the mortarless websitewww.mortarless.com.au. At present the manuals providecomprehensive design aids for design in accordance with AS3700 and BS 5628.

    BS 5628 Design Manual Part 1 provides a detailed look at the

    three parts of the Code, establishes the applicability of the Codeto the design of mortarless masonry, and provides thebackground information on the Code rules that were used in thepreparation of the design aids in Part 2.

    Part 2 contains the various design aids for the mortarlessproducts generally available. It is essential to check that anyparticular mortarless product selected for a project in the designphase is readily available for the project.

    http://www.mortarless.com.au/http://www.mortarless.com.au/http://www.mortarless.com.au/
  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    28/47

    Worked example for wall in compression:Clear height of wall = H = 3200

    Length of wall = L = 7000

    Design load on wall = 294 kN/m

    Concrete slabs top and bottom, therefore enhanced lateral restraint

    top and bottom, therefore av = 0.75

    e = 30mm (eccentricity calculated as shown in Part 2a Section 2)

    If in doubt as to whether length or height governs the design of the

    wall in compression, use the table in Part 2a Section 2 Page 4to determine. In this case height clearly governs the design.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    29/47

    Select 200 mortarless Grade 20 non-chamfered blocks for the

    project.

    From Table CH200-20-1, maximum design load in compression =(375+263)/2 = 314kN (interpolation for 30mm eccentricity),

    therefore the wall is adequate for the maximum design load of

    294kN.

    The above worked example shows how quick and easy it is tocheck the adequacy of a load bearing wall in compression.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    30/47

    Designing for earthquake

    Ductile construction helps minimise the design requirements.

    Horizontal and vertical regularity is also an important factor for

    earthquake design.

    Any load bearing masonry structures in excess of 3 storeysgenerally have to be in reinforced masonry construction. This

    means that there is an even stronger case formortarlessconstruction in buildings of 4 or more storeys if they are of load

    bearing wall construction.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    31/47

    Cost comparison - case study:

    This case study is for the Al Ghadeer villa in Abu Dhabi, UAE.Several demonstration villas were constructed for comparisonpurposes primarily to study the construction process, theconstruction time, the construction cost, and all aspects of thefinished villa.

    The demonstration villas included several different metal studframing systems, a plastic framing system, load bearingmortarless, and load bearing precast concrete.

    Load bearing mortarless was selected by the developer, Sorouh

    Real Estate, as one of the preferred systems to be used in thedevelopment which comprised approximately 4,500 villas.

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    32/47

    Mortarless demonstration villa nearing completion (Al Ghadeer project)

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    33/47

    Al Naboudah, one of the major builders in the UAE, prepared atender for construction of at 500 villas in the Al Ghadeer project.

    They tendered for construction of the villas in any of three

    different structural framing systems: Post and beam (concrete frame) with masonry infill walls

    Load bearing mortarless

    Load bearing precast concrete

    Their tender prices for the structural shells were as follows: Post & Beam UAE 403,429 dhs

    MortarlessUAE 329,940 dhs Precast UAE 400,262 dhs

    The load bearing mortarless structure was found to be at least18% less than the other two framing systems.

    The Al Naboudah priced BoQ summary sheet follows:

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    34/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    35/47

    Photo Gallery Mortarless projects under construction:

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    36/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    37/47

    Blocks F to W were constructed with mortarless common walls

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    38/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    39/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    40/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    41/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    42/47

    Load bearing masonry buildings in Australia:

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    43/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    44/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    45/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    46/47

  • 7/28/2019 MORTER LESS CONSTRUCTION DETAILS

    47/47

    Thank you