Upload
vantu
View
215
Download
1
Embed Size (px)
Citation preview
8/8/2014
1
More on Things that Go Bump in the Pipe: Implementing municipal storm sewer pipe condition rating
systems
Denise Nelson, PE, LEED AP, ENV SP
August 17, 2014
R C P C M P
• NASSCO PACP Pipe Defect Codes
• Why Change NASSCO PACP Pipe Defect Codes?
• NASSCO "QuickScore" application
• Sampling of other agencies
• Lessons Learned
• City of Chesapeake Pipe Condition Assessment Program
What Have We Learned?
Introduction
2
• Learning Objectives
• Implementation Challenges
• What We Are Finding
• Introduction to Pipe System Basics
Terminology and failure modes
• The WRc/NASSCO story
• Storm and Sanitary Differences
Pipe Material
Structural and O&M Differences
• Launch a standardized asset condition rating protocol for storm sewer maintenance and management
• Advocate for asset prioritization especially when scalable program elements (based on asset condition data) need to match fluctuating funding levels.
• Encourage asset condition ratings, and see the benefits from conducting routine storm sewer pipe condition assessments
Learning Objectives
3
8/8/2014
2
System Issues
4
Storm Pipe Issues
5 5
Voids* Missing Pipe*
Exposed
Rebar Spalling &
Chips
Utility Intrusion Unauthorized
Tap-ins Separated Joints
Misalignment
Dropped
Section Broken Pipe*
Fractured
Pipe*
Surface Damage
ASCE 2013 Infrastructure Report Card
6
8/8/2014
5
Transform from “reactive” to “proactive” mode
Maintain current inventory while inheriting additional facilities (School districts; Home owner
associations; State DOT, Parks Dept., conveyance system give-backs)
Confirming boundaries and pipe/structure ownership where others connect to system
Funding capital and O & M when funding levels fluctuate
Adequate MS4 program management resources (internal and external)
MS4 permit language may require development of an asset management plan
Storm Pipe Condition Rating Implementation Challenges
13 13
• Technically based, defensible approaches to expedite processing of inspection backlog
• Educate/require inspection contractors: – Software function, reliability, consistency and compatibility
– Agency acceptance of installations
– QA / QC procedures for renewal installations (independent testing laboratory)
• Different procurement for sanitary /storm systems – Trenchless technology using felt CIPPL
• Styrene controls – environmental discharge
– Sanitary rehabilitation contract pricing
• Geared toward laterals
• Some trenchless may not be suited to larger sized pipe
• Some agencies pre-determine CIPP liner thicknesses
Implementation Challenges (Cont’d)
14
• Most storm sewer system management programs operate in “reactive” mode
• Agencies have expressed desire to shift from “reactive” to “proactive” mode
• Threat of more MS4 permit requirements is driving physical condition assessments (PCAs) – "open" system –curb and yard inlets, storm drainage and infiltration
ditches and swales, detention and retention ponds
– “closed” system – pipes, manholes, junction boxes/chambers, storm outfalls, endwalls, headwalls
• Agencies recognize the importance of PCAs • PCA results provide infrastructure re-investment decision support
What we are finding…
15
8/8/2014
6
• Maintenance agreements between local municipality and state DOT attempt to address inter-connections and shared resource responsibilities
• Few agencies utilizing a structured pipe condition rating approach such as NASSCO PACP / MACP
• Pipe condition data management is overwhelming public agencies
• Subtle yet important differences between storm and sanitary piped conveyance
• Wide range of agency staff skill sets
What we are finding…
16
• Agency staff lack training, awareness and understanding of significance of pipe condition defects – Severity
– Extent
• Agency practices and procedures related to acceptance of new or rehabilitated storm sewer systems need to be enforced
– Development projects released from bond
– Internal inspection requirements
• DOTs concerned with use of laser scanning technology, post-construction inspections, and reporting of findings
– Plastic pipe materials subject to stretching, deformation, rebound
– Issue of ovality and deformation
What we are finding…
17
Intro to Pipe System
Basics
8/8/2014
7
Pipe Installation
Trench Width
Emb
edm
ent
zon
e -
bac
kfill
19
Emb
edm
ent
zon
e -
bac
kfill
19
Pipe Installation
20 20
Pipe Installation
Source: American Concrete Pipe Association - ACPA 21 21
8/8/2014
8
• Loss of soil surrounding pipe
• Groundwater fluctuations
• Hydraulic regime
• Physical loads on sewer pipe (live and “dead” loads)
• Methods and materials of construction
• 3rd party damage/intrusion
• Roots, grease, debris causing increased water depths and possibly blockages (may require more frequent maintenance and service calls)
22
Summary of Major Conveyance System Deterioration Factors
Source: Water Research Centre
Sewerage Rehabilitation Manual
Sewer Subsidence
23
STAGE 2: Infiltration of groundwater or infiltration/exfiltration caused by
surcharging of the sewer washes in soil particles. Loss of soil support around the sewer allows pipe to move, opening
joints and increasing the in wash of soil.
Visible defects: Open and displaced joints, loss of line and level.
Infiltration. History of surcharge. NOTE: Care must be exercised
when viewing video tape recordings as displaced or slightly displaced joints can be overcompensated by the camera’s lighting
system.
STAGE 3: Uneven loading of pipes due to joint displacement causes cracking of
pipes. Process then accelerates and cracked pipes may also deform. Visible Defects: Open and displaced joints, cracked and fractured
pipes, loss of line and level. NOTE: The camera may be submerged
due to loss of gradient.
Development of Zones of
Loose ground or voids caused by loss of
soil into sewer
STAGE 1: Gap in sewer at joint or a poor lateral connection.
Visible defects: Offset joint, badly made connection. Infiltration, lack of long lived joint sealing method.
Source: Water Research Centre
Sewerage Rehabilitation Manual
24
Loss of Pipe Support
Source: Water Research Centre
Sewerage Rehabilitation Manual
STAGE 1 Initial defect, still intact, sewer/pipe is cracked but remains supported and held in position by the surrounding soil.
STAGE 2
Development of zones of loose ground or voids
caused by loss of ground; soil particles washed
away due to infiltration/exfiltration. Side support
is lost and allows deformation.
STAGE 3
Continued loss of support allows crown to drop.
This deformation leads to pipe collapse,
blockage and failure.
8/8/2014
9
Structural Related
Deterioration Mechanisms
Maintenance Related
Construction/Design Related
25
Structural Influences
• Cracks become fractures which become broken which could lead to collapse
• Open/offset joints allow root intrusion and/or soil wash-away which reduce support of pipe
• Surface damage can have exposed metal reinforcing which corrodes and reduces ability to support soil
• Improper repairs allow for root intrusion and soil subsidence
26 26
Infrastructure Needs-Structural
Pipe appears to be
deformed (out of round) 27 27
8/8/2014
10
Maintenance Influences
• Cleaning pipe can result in damage if improper tools are used
• Obstacles and debris – May cause flooding
– Erode inside wall of pipe
• Roots (typically chemical treatment in storm sewers not
allowed) and leaks can threaten surrounding soil support; if left unchecked could force joints apart
28 28
Infrastructure Needs – O&M
29 29
Construction & Design Influences
• Joint failures or gasket material failure can contribute to subsidence of soil
• Unauthorized lateral connections to pipe (hard-tap break-ins) jeopardize structural integrity
• Reverse and flat grades don’t allow system to clean itself (low scouring velocity)
30 30
8/8/2014
11
Infrastructure Needs – Construction Impacts
31 31
The WRc/NASSCO
Story
NASSCO Website
33 33
Primary purpose was to develop a
uniform approach based on
standard inspection observation
codes and ratings
8/8/2014
12
34
• Grade 5 – Collapsed or collapse imminent
• Grade 4 – Collapse likely in foreseeable future
• Grade 3 – Collapse un-likely in near future
• Grade 2– Minimal collapse risk
• Grade 1 - Acceptable structural condition
General Assignment of NASSCO Pipe Condition Grades
Based on internal inspection without consideration to external
consequence of failure, soil conditions, O&M impacts,
distribution of defects and maintenance history
35
General Pipe Condition Grades
• Infrastructure in failure; high consequence of failure
5 – Urgent Attention
• Severe defects that will become Grade 5 defects in near future; critical assets
4 – Poor
• Moderate defects that will continue to deteriorate; moderate criticality
3 – Fair
• Infrastructure defects that have not begun to deteriorate; low criticality
2 – Good
• Minor defects with little consequence of failure
1 – Acceptable
5.1 – Immediate Action
• Portions have failed and will continue to fail if left un-corrected
Use the
rating system to prioritize
maintenance and capital
projects
Pipe Defect Coding & Rating Process
Collect/Record Internal Pipe Defects
Evaluate Internal Pipe Defects; Assign Modified PACP Defect Codes
Apply PACP “QuickScore” to Defect Code Results
Structural O & M
Prioritize and Program for CIP
and O&MReview “QuickScore” Pipe Rating Results
36
8/8/2014
13
• As defined by NASSCO, on a per defect basis:
– Grade 5 – Pipe has failed or will likely fail within 5 years
– Grade 4 - Pipe will probably fail in 5 - 10 years
– Grade 3 – Pipe may fail in 10 – 20 years
– Grade 2 - Pipe unlikely to fail for at least 20 years
– Grade 1 – Failure unlikely in foreseeable future
Likelihood of Failure
37
Storm and Sanitary
System Differences
Pipe Material
39
8/8/2014
14
Pipe Material
40
H D P E
Structural Differences Between Storm and Sanitary Pipe Systems
41
Feature Wastewater Collection System Stormwater Conveyance System
Construction Quality High Stretched inspection forces, reliance on
contractor
Pipe section lengths Longer (10', 12', 20') pipe sections have fewer
joints Shorter (4', 6' & 8') pipe sections have many
joints
Lateral connections Essential Not permitted, treated as unauthorized
connection
Lift holes None, use slings or pipe hooks 18" dia. and above may have them; if not properly sealed, may leak or allow root
intrusion. May lead to pipe crack/fracture.
System depth Deeper, below storm, force main may be
shallower than gravity lines Shallower, above sanitary, exposed to vehicular
loads
Acceptance Tests Mandatory to protect health, welfare and
water quality, leaks not tolerated Not required, might have visual inspection
Chemical breakdown Constant flows (diurnal) with chemicals and
gaseous exposure and possible corrosive attack on pipe walls
Episodic flows with storm events. Water usually free of contaminants and not contributing to
deterioration.
Structural Differences Between Storm and Sanitary Pipe Systems (Cont’d)
42
Feature Wastewater Collection System Stormwater Conveyance System
Other utility intrusions
Susceptible. Not included under programs to locate underground utilities prior to
digging.
Susceptible, higher occurrence due to shallower nature. Not included under programs to locate
underground utilities prior to digging.
Infiltration type
Groundwater infiltration is more likely as system is deeper in the ground;
Stormwater from defects or deterioration in system
Shallower pipe is subjected to saturating water infiltration, less soil overburden so voids surface
quicker and easier
Infiltration leaks Impacts capacity and increases treatment
costs
Carries soil from pipe envelope, creating or causing voids, sink holes and safety concerns to citizens.
Increased standards for mastic, gaskets, etc.
Abrasive flow
Turbulence associated with pumping and elevation and directional changes
Debris in flow may scour pipe walls; debris particles are generally larger, more dense
Pressure flow
Yes Not usually; prevalent more in coastal areas
Gravity flow
Yes Yes
Destination Treatment plant Stream (Waters of the U.S.)
8/8/2014
15
O & M Differences Between Storm and Sanitary Pipe Systems
43
Feature Wastewater Collection System Stormwater Conveyance System
Capacity Critical; overflows are regulatory violations Overland relief can be incorporated into design
Joints Watertight, minimizes root intrusion, joints
are subject to acceptance tests Lack of joint seals may result in root intrusion,
especially in shallow installations
Line Maintenance and Monitoring
Fat, oil and grease accumulation requires frequent cleaning. Cleaning can damage pipe
walls.
Heavy debris and deposition can clog system resulting in flooding. Debris is generally larger
which can clog pipes easier.
Surface Impacts Force mains typically shallower than gravity
sewers
Shallower pipe systems are susceptible to damage from vehicular loads and other utility
intrusions
Flow pattern Stable with diurnal swings Episodic. Supplemented with overland relief.
Usually free of contaminants. Usually does not contribute to pipe deterioration.
Vermin Roaches, spiders, snakes Nocturnal mammals, crickets, frogs, critters ….
Alligators are not unheard of.
Closed and Open Characteristics
Closed system, may have lift stations Open and transitional system, open channels to
pipe then to open channel. Some submerged outlets to impoundments
Security Intrusion alarms typically installed on critical
assets; SCADA, telemetry Difficult to keep secure and free of vandalism,
critters and person entries
Trenchless Differences Between Storm and Sanitary Pipe Systems
44
Feature Wastewater Collection System Stormwater Conveyance System
Lateral connections Many None to few
Bypass flows
Requires on-site pump operations during installation; may need a pipe de-
commissioning and sanitizing step prior to dis-assembly
Rehab installation can be scheduled during 'dry' days, eliminating need for pump and bypass
Styrene Curing and contaminated flows are treated
at POTW
Not permitted in discharge to stream; requires new liner to be flushed and contact flows are pumped
into sanitary sewer, treated at POTW
Spatial Distribution of Priority Pipes
45
NASSCO PACP Defect Code Results
Priority One - Urgent corrective
measures required.
Priority Two - Near term corrective
measures required 2 – 3 years
Priority Three - Rehab/Repair
recommended, asset failure possible
in within 5 years
“Maintenance“ - No structural
defects or maintenance issues; re-
inspect asset approximately every 20
years
8/8/2014
16
NASSCO PACP Pipe
Defect Codes
Why Inspect Storm Pipe?
• Be responsive to citizen complaints and service calls
• MS4 annual and other agency reporting
• Accurately record and archive descriptive data
• Develop and maintain pipe condition rating for each pipe segment
• Provide results in format for use by field staff and independent contractors (Hard copy and electronic)
• Establish condition benchmark to compare with future pipe segment inspections
• Estimate probability of failure & remaining service life
• Acceptance of new construction 47 47
NASSCO PACP Coding (Version 6.0.2)
48
8/8/2014
17
Sample Index of Defect Codes
49
PACP Pipe Defect - Example
50
Structural Deformed (D) (Pipe) D < 10% = 4
D > 10% = 5
R C P
Why Change
NASSCO PACP Pipe Defect Codes?
8/8/2014
18
Structural
– Installation defects (Improper handling and storing; joint damage; lack of gaskets-joint material)
– Greater potential for shallower system with severe defects (lift holes, cracks, fractures, and corrosion of metal pipes)
– “Reinforcement visible” is downgraded because the corrosivity potential isn’t as great and the flow episodic
– Infiltration/exfiltration more likely with storm – may be cause for defect scoring change, soil erosion causes or leads to more severe defects
– Presence of roots – shallow storm depth more susceptible to root intrusion; pipe joints not airtight like sanitary
Why Change PACP Scoring
52
O&M
– Roots and leaks must be accompanied with the defect coding through which the intrusion (pipe barrel vs. joint) is occurring
– Defect severity ratings were increased on some roots (barrel) and leaks to reflect seriousness affecting shallower piping
52
NASSCO “Scoring” – Sampling of Modified PACP Structural Defect Codes
53
Family Group Descriptor Modifier Code Structural Grade
Structural Crack (C) Circumferential ( C) CC 1
Longitudinal (L) CL 2 (3)
Multiple (M) CM 3 (4)
Hinge (CH2) CH2 4
Hinge (CH3) CH3 5
Hinge (CH4) CH4 5
Spiral (S) CS 2 (3)
Structural Fracture (F) Circumferential ( C) FC 2
Longitudinal (L) FL 3 (4)
Multiple (M) FM 4
Hinge (H2) FH2 4
Hinge (H3) FH3 5
Hinge (H4) FH4 5
Spiral (S) FS 3
Structural Joint (J) Offset (displaced) (O) Med (M) JOM 1
Large (L) JOL 3 (4)
Separated (open) (S) Med (M) JSM 1
Large (L) JSL 3 (4)
Angular (A) Med (M) JAM 1
Large (L) JAL 2 (3)
Structural Joint (J) Offset (displaced) (O) Med (M) JOM 1
Large (L) JOL 3 (4)
Separated (open) (S) Med (M) JSM 1
Large (L) JSL 3 (4)
Angular (A) Med (M) JAM 1
Large (L) JAL 2 (3) 53
Rating Parameter Modified PACP Rating Justification
Cracks (CL CM, CS) Increase rating value by 1 Shallower, concrete pipe more susceptible to influences that could potentially cause further damage.
Fractures (FL) Increase rating value by 1 Shallower concrete piping more susceptible
Broken pipe (B) No change from default value
1 clock pos – 3; 2 clock pos – 4;
> 3 clock pos - 5
Representative rating accounting for shallower concrete piping
Deformed pipe (D) No change from default value
< 10% = 4; > 10% = 5 Lift holes may exhibit additional stress and be coded separately
Collapsed pipe (X) No change from default value Score
of “5”
High score representative of severity
Holes (H) No change from default value
1 clock pos – 3; 2 clock pos – 4;
> 3 clock pos - 5
High score representative of severity
Joint Offset (JOL) Increase rating value by 1 Large offset by definition is 1.5 times the pipe wall thickness and warrants the increase
Damaged or defective joint gasket material
No change from default value
Change from Construction Defects to Structural
Defective point repairs No change from default value Scores are representative of severity
Potential Pipe Defect Coding
Adjustments – Structural
54 54
8/8/2014
19
Potential Pipe Defect Coding Adjustments – Structural
Rating Parameter Modified PACP Rating Justification
Joint Angular Large
(JAL)
Increase rating value by 1 By definition, a JAL is greater than 1.5 times the
pipe wall thickness
Surface Reinforcement
Chemically Affected
Retain or Reduce from 5 to 4
(concrete pipes)
Chemical attack in storm pipe would be an
extenuating circumstance.
Surface Reinforcement
Mechanically Affected
Retain or Reduce from 5 to 4
(concrete pipes)
Mechanically damaged reinforcement in storm pipe
would be an extenuating circumstance.
Surface Reinforcement
Affected, Not Evident
No change from default value Cause of defect is unknown
Evidence of infiltration
Increase value of weeper from 2 to 3 and add rating of 1 for evidence of staining
Relates to eroding bedding and fill materials around pipe resulting in settlement and collapse
Evidence of exfiltration
New field – addition as “5”
Relates to eroding bedding and fill materials around pipe resulting in settlement and collapse
Unauthorized connections
New field – addition as “5”
By definition they may be unauthorized. If defective include related defect code as well.
55 55
Potential Pipe Defect Coding Adjustments – O&M
Rating Parameter Modified PACP Rating Justification
Deposits No change from default values
Considers reduced cross sectional area of piping; may be due to pipe sagging
Debris / Obstruction No change from default values
Considers reduced cross sectional area of piping; may be due to pipe sagging
Encrustation No change from default values Considers reduced cross sectional area of piping
Roots – Heavy (Ball) @ Joint
Increase from 4 to 5
Increased Root Ball at Joint value to reflect same score as Root Ball at Barrel; should also be accompanied by score associated with whatever structural defect is allowing root penetration
Roots – Medium @ Joint
Increase from 3 to 4
Increased Root Medium at Joint value to reflect same score as Root Medium at Barrel; should also be accompanied by score for whatever defect is allowing root penetration
Roots – Light (Fine) on pipe barrel
Increase from 2 to 3 Increased value by one due to represent severity of root intrusion in shallow pipe.
Roots – Light (Fine) on pipe barrel
Increase from 2 to 3 Increased value by one due to represent severity of root intrusion in shallow pipe.
56 56
Example Modified PACP Pipe Defect
57
Structural Joint (J) : Offset (displaced) (O) Large (L) JOL (3) – now “4”
Separated (open) (S) Large (L) JSL (3) – now “4”
Angular (A) Large (L) JAL (2) – now “3”
RCP
8/8/2014
20
NASSCO PACP Coding
58
HOLE – is it a lift hole? Utility intrusion?
(Commonly found with concrete pipe)
If Lift Hole, are there associated defects
(cracks, fractures, staining)
Insert related pipe
defect here
Insert related pipe
defect here
Insert related pipe
defect here
R C P
NASSCO PACP Pipe
“QuickScore”
60
Pipe Defect Inspection Data
8/8/2014
21
NASSCO PACP Quick Score Example
61
A four digit result representing:
Digit 1 – Greatest defect score found in that pipe = 5 (on a 1-5 scale)
Digit 2 – The frequency of the greatest defect score = 2
Digit 3 – The second greatest score found in that pipe = 2 (on a 1-5 scale)
Digit 4 – The frequency of the second greatest score = 6
Example, for structural assessment, a segment with 2 grade 5’s, 0 grade 4’s, 0 grade 3’s and 6 grade 2’s, result would be:
PACP Quick Score Example
62
Inspection Number
Inspected Length
(ft)
Material Listed in Video
Diameter (inches) Listed
in Video
Structural Quick Score
O & M Quick Score
5 151 CMP 48 5E00 0000
8 109 RCP 15 5436 4122
7 143 RCP 15 5144 2100
29 226 RCP 15 5111 2300
99 195 RCP 4E3G 0000
66 167 RCP 33 4D32 0000
37 233 RCP 30 4A3Y 0000
110 70 RCP 24 4A00 0000
34 102 RCP 24 4936 0000
94 242 RCP 21 3H21 0000
54 135 RCP 21 3211 1200
83 93 RCP 48 3200 1A00
4 147 CP 15 1100 312C
63
PACP Quick Score Defect Count and Corresponding Characters
Defect Count Corresponding
Character
1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8
9 9
10 - 14 A
15 - 19 B
20 - 24 C
25 – 29 D
30 – 34 E
35 – 39 F
40 – 44 G
45 – 49 H
50 – 54 I
Defect Count Corresponding
Character
55 – 59 J 60 – 64 K
65 – 69 L
70 – 74 M
75 – 79 N
80 – 84 O
85 - 89 P
90 - 94 Q
95 - 99 R
100 - 104 S
105 - 109 T
110 - 114 U
115 - 119 V
120 - 124 W
125 - 129 X
130 - 134 Y
>= 135 Z
8/8/2014
22
Typical Structural Score Priorities
Modified NASSCO PACP Defect Code Results
Greatest Structural Score – “5” - Urgent corrective measures required.
Structural Score – “4” - Near term
corrective measures required within 2 - 5
years
Structural Score – “3” - Rehab/Repair
recommended, asset failure possible in
within 5 - 10 years 64
64
Typical O&M Score Priorities
Modified NASSCO PACP Defect Code Results
Greatest O&M Score – “5” - Urgent
corrective measures required.
O&M Score – “4” - Near term corrective
measures required within 2 years
O&M Score – “3” - Rehab/Repair
recommended, asset failure possible in
within 5 years
65
Other Programs
8/8/2014
23
67
Summary of Other Agency Practices
NASSCO PACP Default Method Modified PACP Other
City of Chesapeake, VA Fairfax County Stormwater
Cobb County, GA ; Grand Rapids, MI– Business Risk Exposure, similar to PACP
City of Virginia Beach, VA Fairfax County Wastewater Collection Division
Aurora Water, Colorado – Project specific based on RedZone Robotics condition rating - similar to PACP
City of Newport News, VA City of St. Albert, Alberta, Canada
Australia - Auburn, Mitchell Shire Council, Wagga Wagga – each similar to PACP
Hampton Roads Sanitation District and other Public Wastewater Agencies (Norfolk, Chesapeake, Portsmouth)
DC Water Houston, TX – CIP Process Manual for Infrastructure Plans
Olympia, WA - relies on pipe material and age to prioritize storm system assets Cities of Gary, IN and
Fort Wayne, IN
Cincinnati, OH
Sacramento County, CA
Municipality of Anchorage, AK
Seattle, WA (Combined Sewers)
67
Lessons Learned – Shifting to an Effective Condition Assessment Program
68
FROM: Reactive mode and “fix worst first” Culture of individual specific project needs Cost administration based on historical needs and trends Capital planning strictly as en engineering function O&M staff disconnected from asset decisions Technology as barrier
TO: Proactive mode and continuous and improved service delivery Customer service driven practices and asset life cycle valuation Financial management based on structured condition approach Capital planning as a collaborative opportunity; recognize O&M elements and needs O&M staff are indispensable asset experts Technology as enabling
• Iterative pipe defect coding process, for storm systems, still evolving from NASSCO aspect
• Pipe inspection database management crucial - avoid data “sitting on shelf” with no review and related action
• Many differences between types of pipe systems
• Need to establish cultural change incorporating system condition assessment practices and infrastructure re-investment justification
Lessons Learned
69
8/8/2014
24
• Be flexible, responsive and adaptive – Changed direction (accommodate citizen expectations)
– Fluctuating and scalable funding/budgets
– Don’t be afraid to customize defect codes for your system
• Simple, defensible and ease of implementation (pipe defect coding method)
• On-going need to invest in staff training and technology
• Pipe installation, inspection and acceptance method is critical
• System interconnections with other agencies and private systems
Lessons Learned – 2
70
City of Chesapeake,
VA Storm Condition
Assessments
• 351 sq. miles • 228,500 million population
• Phase I MS4
• TMDLs
Chesapeake, VA
72
8/8/2014
25
Public drainage system
1,200 miles of gravity storm pipe Ranges 12” to 66” dia.
30% of system is tidally influenced
2200 miles Public Storm Drain Ditches
61,613 drainage structures
540 Detention / Retention Basins
Ground elevations range from 1 to 28-feet above sea level
Sampling of Maintenance Responsibilities
73
What is City Responsibility?
• NASSCO PACP “QuickScores” – Issue Work Orders based on urgency
• Residential Areas • Private Drainage • City Roads & Ditches • Driveway Culverts • Integrated Road Drainage System
74
City’s Use of NASSCO PACP
• City plans to inspect 1,200 miles of storm pipe – Inspection frequency: once
every 3-4 years
• First seven months: – CCTV’d 23,000 LF – Peak day 827 LF
• NASSCO PACP “QuickScores” – CCTV inspections completed
in two storm drainage basins – Evaluating other technologies
(under water camera systems)
75
8/8/2014
26
Example of City’s NASSCO PACP Results
76
Address PACP QuickScore
Overall Rating 1335 Lindale Dr 5221
4001 Grant Ct 5121
565 Saddlehorn Dr 4131
1204 Woodstream 4121
3021 Oak Dr 3228
2901 Sir Thomas crossing Sir
Thomas 3111
3241 Bruin Dr 3111
Shadyside @ Wisteria Ct 3111
4224 Foxxglen Run 2400
Grant Ct to 3108 Tyre Neck 231A
Grant Ct 2312
Oak Dr E. 2300
905 Saddleback Trail Ct 2211
Meadowbrook to Pineridge 2211
Wythe Ln 2200
2505 Foreman Lndg 2112
Address PACP QuickScore
Overall Rating 3500 Avondale Ct 2111
3117 Dean 2100
102 American Legion Rd 2100
Mapleton Cres at Shadyside 1500
Foxgrove Ln 1500
Woodcroft Ln 1500
Western Branch Blvd at Dunedin
Dr 1400
2017 Phyllis Dr 1300
3537 Kentucky Trl 1200
Hawksley 1200
Poplar Hill /Kenley Ct 1200
3221 PineridgenDr 1100
713 Sparrow Rd 1100
Helensburgh Dr 1100
853 Woodstream Way 1100
608 Guisborne Ct 0000
816 Dawson Cir 0000
Example City’s NASSCO PACP Inspection Observations
77
So, what did we find?
FROG INSPECTOR WOOD
78
8/8/2014
27
79
So, what did we find? (Cont’d)
So, what did we find? (Cont’d)
80
• City assessing storm pipe inspection results to determine prioritization and resource needs
• Match “renewal” need with available funding
• Coordinate with City’s CIP and implementation schedule
• Address processing of inspection backlog
– Incorporate findings with CIP and maintenance plan
• Learn from other agencies’ related experiences
• Get City DPW staff trained as NASSCO PACP users
NASSCO PACP QuickScore Role
81
8/8/2014
28
• NASSCO PACP storm pipe defect coding and the resulting scores provide a good screening tool
• Follow-on engineering evaluation and judgment is needed to confirm the extent and severity of the inspection condition observations.
• Need to have staff and contractors certified as NASSCO PACP users in order to provide compliant and consistent pipe defect condition observations
So, What Have We Learned?
82
• Produce a program schedule that is realistic, train staff, and deploy inspection equipment capable of doing the work
– 1.5 CCTV trucks cannot reasonably be expected to do what we set out to do even averaging 1,000 LF/day
– With the purchase of 2 fully equipped new CCTV trucks (out of funding cycle), need to decommission the oldest truck
– Rolling stock – Total of 2.5 CCTV trucks
– Need to verify CCTV inspection NASSCO-compliant software produces reliable pipe condition scores
So, What Have We Learned (cont’d)?
83
• Communicate with staff, superiors, Council, and citizens:
– The importance of the inspection and assessment program and
– The benefits to be derived.
• Update your constituents regularly with current information.
– We brief our Stormwater Committee (includes Council Liaisons, Citizens, and staff) bi-monthly
– We advise staff and superiors monthly
So, What Have We Learned (cont’d)?
84
8/8/2014
29
• Investigate what your neighboring localities and other involved agencies are doing to avoid their implementation issues (Don’t repeat them).
– Talk with your counterparts and visit their operation
– Talk to your suppliers and consultants
– Get the equipment that best fits your needs. Don’t be sold on anything less
So, What Have We Learned (cont’d)?
85
One last learning item!
Cement matrix from exposed aggregate
driveway (since removed by replacing pipe)
86
And just one other last learning item!
87
8/8/2014
30
Questions?
Pete Fortin, PE, CSM
[email protected] (757) 382-3321
Ken Eyre, PE, PACP [email protected]
(571) 581-3011
Thank you
greeley-hansen.com