07/19/2022 MOP NETWORK CHANGE REQUEST / NEW MOP FORM A. ACTIVITY DESCRIPTION NMC Control No: MOP Status Open Other Ref No Activity Name/Description: DY2842 Justification: Activity Date & Time 21/5/2015 12:00:AM Duration: 360 Minutes Date Rqstd: 20-May Intiated by: Osama Noori Company / Titl Halabja telecom servic PTW NO : B. TECHNICAL DESCRIPTION Technical Description / Details of the activity : Change Category No: Network Element/s Involved Perform by: Korek Team Company / Titl Korek Resources Needed (Tools / Test Equipment / Personnel / Others ) Persoanl and other Supervision Required: Risk Assesment by Roll Back Plan Roll Back Trigger / Criter C. NETWORK / SERVICE IMPACT Affected Service/s Full Outage Affected Region / Are Estimated Outage Duration Actual Outage Duration 120 Minu Planned Outage Start Planned Outage End Actual Outage Start (NMC Use) Actual Outa Date Time Date Time Date Time Date 21-May-15 12:00 AM 21-May-15 6:00 AM 21-May-15 4:00 AM 21-May-15 clear alarms on the Node that may cause any negative result fo link (Rashdya – REP 3). clear alarms on the Node that may cause any negative result for the link (Rashd 3). DY2842-DY2837+ DY2826+DY2953+DY2867+ CW3041+DY2839+DYDY2856+DY2825+DY2827+DY2836+DY2824+DY2851+DY2 7+CW3039+CW3038+DY2854+DY2885+DY2833+DY2829+DY2830+DY2832+DY2 5+DY2831+DY2828+DY2853+DY2863+DY2852+DY2849+DY2848+DY2846+D DY2875+DY2838+DY2841+DY2840+DY2874+DY2865 With Planned Outage Required Skill Center Approval Required PTW (Permit To Work or access Korek facilities) Hardware Change Software Change Routine Mainten With Attachment /s ( Please attach necessary documents including Roll Back Plan )

MOP 21-05-2015- DY2842

Embed Size (px)

DESCRIPTION

MOP

Citation preview

MOPNETWORK CHANGE REQUEST / NEW MOP FORM

A. ACTIVITY DESCRIPTION

NMC Control No:MOPStatusOpenOther Ref NoActivity Name/Description:DY2842

Justification:clear alarms on the Node that may cause any negative result for the link (Rashdya REP 3).Activity Date & Time:21/5/2015 12:00:AMDuration:360 MinutesDate Rqstd:20-May-15Intiated by:Osama NooriCompany / Title:Halabja telecom servicesPTW NO : B. TECHNICAL DESCRIPTION

Technical Description / Details of the activity :clear alarms on the Node that may cause any negative result for the link (Rashdya REP 3).

Change Category No:Network Element/s InvolvedPerform by:Korek TeamCompany / Title:KorekResources Needed (Tools / Test Equipment / Personnel / Others )Persoanl and otherSupervision Required:Risk Assesment byRoll Back PlanRoll Back Trigger / Criteria

C. NETWORK / SERVICE IMPACT

Affected Service/sFull Outage Affected Region / AreaDY2842-DY2837+ DY2826+DY2953+DY2867+ CW3041+DY2839+DYDY2856+DY2825+DY2827+DY2836+DY2824+DY2851+DY2868+CW3037+CW3039+CW3038+DY2854+DY2885+DY2833+DY2829+DY2830+DY2832+DY2834+DY2835+DY2831+DY2828+DY2853+DY2863+DY2852+DY2849+DY2848+DY2846+DY2876+ DY2875+DY2838+DY2841+DY2840+DY2874+DY2865

Estimated Outage DurationActual Outage Duration120 MinutesPlanned Outage StartPlanned Outage EndActual Outage Start (NMC Use)Actual Outage EndDateTimeDateTimeDateTimeDateTime21-May-1512:00 AM21-May-156:00 AM21-May-154:00 AM21-May-156:00 AM

D. APPROVAL AND NOTIFICATION

ApproverNameApproveSignatureDateRequiredSKILL CENTEROperations ManagerMohamed A.AzizNMC ManagerRegional DirectorWaleed AlheetyCTIO

Notification To