DAILY WORK DONE
DATECommon Embankment (M³)
MAIN Taxiway EMR MAIN EMR MAIN EMR MAIN Taxiway EMR MAIN1-Feb-09 SUNDAY NO WORK
2-Feb-09 1,185 750 3,197 7,747 554
3-Feb-09 142.5 487.5 7,409 4,530 6,367 923
4-Feb-09 593.1 2310 6654.9 3519 5,264 554
5-Feb-09 2773.5
6-Feb-09 3,510 3,962 10,616
7-Feb-09 1,538 2,175 1,729 16,663
8-Feb-09 21,833
9-Feb-09 3,310 5,189 12,005
10-Feb-09 2,944 750 3,609 16,401 554
11-Feb-09 950 822 2,444 19,305
12-Feb-09
13-Feb-09
14-Feb-09
15-Feb-09
16-Feb-09
17-Feb-09
18-Feb-09
19-Feb-09
20-Feb-09
21-Feb-09
22-Feb-09
23-Feb-09
24-Feb-09
25-Feb-09
26-Feb-09
27-Feb-09
28-Feb-09
QUANTITY (M³)142.5 593.1 8927 0 0 487.5 0 28154.32 0 28178.742
116201.513 2584.59662.6 0 487.5 56333.062
Select Embankment (90%) (M³)
Select Embankment (93%)
( M³)
Select Embankment (95%)
(M³)Excavation
(M³)
Sub Base Course
(M³)
AMOUNT (Rs.) 1,642,642 0 112,125 6,196,637 20,916,272 2,693,049
DAILY WORK DONE
2,607,348
3,557,466
3,136,957
305,085
2,732,802
3,690,226
3,929,940
3,095,762
4,509,445
3,995,695
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
AMOUNT (Rs.)
31,560,725
ESTIMATED QUANTITY FOR NEXT MONTH
January 2009
Sr.# DESCRIPTION UNIT AMOUNT REMARKS
1 Select Embankment Cum 6,400 192,000 170 32,640,000
2 Common Embankment Cum 25,000 750,000 110 82,500,000
3 Excavation Cum 40,000 1,200,000 180 216,000,000
4 Sub Base Course Cum 1,500 45,000 1,042 46,890,000
5 Agg. Base Course Cum 200 6,000 1,358 8,148,000
6 UPVC Pipe crossing L.M 319 9,570 1,610 15,407,700
GRAND TOTAL 401,585,700
PER DAY QUANTITY
MONTHLY QUANTITY
BOQ RATE