19
-~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department - Atomic Energy Division Pug,e 1

MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

-~ MONTHLY REPORT - PROCESS SECTION

I

JULY 15, 1956

E. 1. duPont de Nemours & Co. (Inc.) Explosives Department - Atomic Energy Division

Pug,e 1

Page 2: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

DISCLAIMER

This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, make any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Page 3: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

DISCLAIMER

Portions of this document may be illegible in electronic image products. Images are produced from the best available original document.

Page 4: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

U NCLASSI FI ED DPW-56-7-6

COPY NO . 1. 2.

3-8 . 9-11 n

12 0

13 14. 15 16

19 . 20 . 21 . 22 . 23 24 25 P 26 . 27 . 28 P 29 30 0

DPW-56 -7-6-R (100 Area SRP)

DISTRIBUTION

B, H. Mackey - R. M. Evans - H, F, Brown R, C, B l a i r - AEC - Aiken Winston Davis - AEC - Aiken Jean O'Leary - AEC - Washington C. W. R e i l l y - AEC - Terre Haute J. A , Burns - Engineering S. I. Winde - Engineering D o A , Miller - SRP D. A , Miller - W , P . Overbeck - SRP C. P , Kidder - SRP

H, Worthington - AED - Wilmington V, R. Thayer - S. A. McNeight - AED - Wilmington D. *F. Babcock - J. C . Woodhouse - AED J, E. Cole - AED - Wilmington J. B, T inke r - AED - Wilmington M. S. Bloomsburg - AED - Wilmington H. W:Bellas - AED -- Wilmington R. J. C h r i s t 1 - AED - Wilmington Process Sec t ion F i l e - AED - Wilmington Process Sec t ion F i l e - AED - Wilmington "W" F i l e - AED - Wilmington "SP" F i l e '- AED - Aiken

M, H, Wahl - SRL

1. A , D. D u f f - Engr,

2. J , W , Croach - SRL

DISTRIBUTION - PARTIAL REPORTS

DPW-56-7-6-S (200 Area SRP)

1, E, E , Wilson - Engr.

2 , J, W , Morris - SRL

DPW-56-7-6-MET 7300 Area SRP)

1, A, D, Duf'f - Engr,

2 , J. W e Croach - SRL

DPW-56-7-6-HW-D 300 Area SRP and

Dana Only)

1, R , P , Kel ly - Dana

2, H, 0, Aaron - Engr,

e UNCLASSIFIED

5

. .a..- ....- -..

Page 5: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

UNCLASSIFIED DPW-56-7-6

TABLE OF CONTENTS

Pages

100Area-Reac tors . . . . . . . . . . . . . . . . . . . . 4 - 6

200 Area . Separations Plants . . . .- . . . . . . . . . . . . . -7 . - 10

300 Area - Reactor Fuels Fabrication . . . . . . . . . . . . . 11 - 13

400 Area - H e a v y Water . . . . . . . . . . . . . . . . . . . ..14 Util i t ies and General Services . . . . . . . . . . . . . . . . 1 5 - 1 7

l J NCLASSI FI ED --, , . . _ -

Page 6: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

SAVANNAH RIVER PLANT

100 AREA - REACTORS

POWER ASCENSION PROGRAM

1. Fuel Rupture Location System

The six-cyclone pro to type of the rupture l o c a t i n g system pro- posed for n a t u r a l f u e l r e a c t o r s has been rece ived and is being i n s t a l l e d a t Savannah River Laboratory f o r hydraul ic t e s t i n g . Cyclones have now been ordered f o r the 25-cyclone prototype to be i n s t a l l e d i n "R" r e a c t o r f o r performance t e s t i n g during r e a c t o r opera t ion ,

Design of the automatic device f o r r a d i a t i o n scanning of banks of cyclones has been completed i n the Mechanical Assis tance Sec t ion a t the Savannah River P lan t , and the AC photomulti- p l i e r c i r c u i t r y proposed f o r the de tec t ion system is under t es t i n "L" r e a c t o r .

2. Increased Pressure of Blanket Gas

An inc rease i n pressure of the b lanket gas system t o 5 psig is being considered w i t h the ob jec t ive of i nc reas ing the hydraulic ( temperature) l i m i t s on the r e a c t o r s . However, i n order t o avoid l i f t i n g 'the plenum during opera t ion w i t h l i g h t - weight enr iched loads, the plenum must be f a s t ened t o the floor or t o the r e a c t o r s t r u c t u r e , Holding the plenum down by means of the f o r e s t s t r u c t u r e appears impract icable because of the large f o r c e s involved. Study by the Engineering Department has shown tha t f a s t e n i n g the plenum a t i t s periphery would s-till permit enough c e n t r a l d e f l e c t i o n t o cause b inding on the semi- permanent s l eeves . The proposed method of f a s t en ing , t he re fo re , i s t o i n s t a l l t i e b o l t s i n 30 t o 50 of the a v a i l a b l e instrument holes , to t i e the plenum t o the top shield. The gas pressure r equ i r ed t o l i f t the plenum and shield toge the r would.be about 13 ps ig with a n a t u r a l load of about 8 ps ig w i t h an enriched load , A c o s t estimate has been requested for i n s t a l l a t i o n of the t i e b o l t s .

3 0 Shipment of Mark VI11 Slugs t o Arc0

According t o the cu r ren t f o r e c a s t for Mark VI11 s l u g loadings, production w i l l cease i n e a r l y calendar 1958, bu t w i t h the p resen t f o u r casks the shipments t o Arc0 would continue u n t i l early 1961, A p r o j e c t has been submitted t o purchase f o u r a d d i t i o n a l casks of t h i s type, so tha t shipment may be completed by early 1959. With eight casks i n se rv i ce , the expected maxi- mum inventory of cooled s l u g s will be three r e a c t o r charges, equiva len t t o about fou r months product ion of two r e a c t o r s .

Page 4

Page 7: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

POWER ASCENSION PROGRAM (Continued)

3, Shipment of Mark VI11 Slugs t o Arc0 (Continued) '

S l i g h t changes i n the cask design are contemplated, t o reduce r a d i a t i o n leakage and f a c i l i t a t e handling, scheduled f o r cask Cielivery during the t h i r d q u a r t e r of FY 1957, i n time f o r the first shipment of s lugs .

The work w i l l be

PRODUCTIVITY IMPROIIE~NT PROGRAM

1,

2.

Increased Moderator C i rcu la t ion

Bingham Pump Company's production schedule on the f i r s t set of l a r g e r moderator c i r c u l a t i n g pumps now shows the first pump scheduled f o r shipment i n September and the seventh pump i n e a r l y November 1956., T h i s schedule is about 30 days l a t e r than the o r i g i n a l quoted schedule f o r shipment of the seventh pump. Manufacturing techniques appear t o be s a t i s f a c t o r i l y developed t o make poss ib l e adherence t o t h i s schedule.

Sha f t seal design of the Bingham pump i s d i f f e r e n t from that now used on the Byron-Jackson pumps only i n the method of support of the s t a t i o n a r y carbon r i n g . I n the e x i s t i n g B-J pumps t h i s r i n g is seated on a rubber r i n g , It w a s thought that the seal could be improved i f the r i n g were held i n bet ter alignment, and a carbon-to-metal back-up was designed i n t o the seal f o r the Bingham pump. The seal i s now undergoing p roof - t e s t ing under s imulated opera t ing condi t ions . The latest series of tests i n d i - c a t e tha t abso lu te f l a t n e s s of the metal back-up su r face and of the back face of the carbon r i n g play a major r o l e i n reducing seal leakage. T h i s development stems from recen t experience a t SRP b

I n connection w i t h the inc rease i n moderator c i r c u l a t i o n , there w i l l be some a l t e r a t i o n s t o power c a l c u l a t o r ins t rumenta t ion made necessary. New flow meters and t ransducers w i l l be i n s t a l l e d and the r e l i a b i l i t y of the temperature measuring c i r c u i t s w i l l be improved, Experience w i t h the e x i s t i n g .system has shown the p r i - mary source of e r r o r t o be in:changes i n system r e s i s t a n c e a t s o l d e r Jo in t s , e t c , A r ev i sed c i r c u i t which i s self-compensating f o r these changes has been designedland tested a t SRP. system w i l l be made a part of t h i s p r o j e c t .

Such a

New Fuel Elements

General arrangement drawings covering W E handling i n Build- i n g 105-C Assembly Area have been approved. changes l o r the assembly area have been reviewed and only a f e w of these designs are y e t t o r ece ive formal approval , Mock-up of equipment f o r t e s t i n g p r i o r t o f i n a l design w i l l be confined t o a few t o o l items only,

A l l major equipment

Page 8: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

PRODUCTIVITY IMPROVEMENT PROGRAM (Continued)

2. Mew Fuel Elements (Continued)

A l l maJor changes and a d d i t i o n s t o the disassembly areas have been reviewed, a t least i n the rough design stage, The p r i n c i p a l area which l a c k s design development i s i n shipping, Prel iminary r e s u l t s of the s u b - e r f t i c a l i t y tests a t SRL confirm the previous c a l c u l a t i o n s that with s u i t a b l e conf igura t ion , which would be a hexagonal array very n e a r l y c l o s e packed, as f e w as 18 t o 20 un- irradiated Mark V I elements would be c r i t i c a l , Further tests are i n progkess t o determine the requi red spacing between stacks for s i n g l e - f i l e stacks of t e n elements each, s i n c e t h i s arrange- ment may permit safe loading of 50 t o 60 elements per cask.

Calcu la t ions r e l a t i n g t o heat removal from a cask conta in ing 60 Mark VI-A elements irradiated a t 2000 MW t o 40% burnout i n d i c a t e that water i n the cask would b o i l even w i t h the cask immersed i n water. However, it appears from l i m i t e d observa t ions w i t h pres- e n t LMF casks that a c t u a l temperatures are much lower than pre- dicted. observa t ions of the e x i s t i n g LMF casks are planned.

I n view of the importance of t h i s design f e a t u r e , f u r t h e r

FEACTOR DESIGN STUDY

Evaluat ion c o s t estimates have been completed f o r two r e a c t o r bu i ld ings of 105-C design i n one area t o compare w i t h the c o s t of two separate r e a c t o r areas. Also, c o s t estimates are essen- t i a l l y complete of a r e a c t o r area conta in ing two r e a c t o r s i n one bui ld ing . Active work is now directed toward more ex tens ive re- design of the r e a c t o r i n Phase I11 of t h i s study.

Page 6

Page 9: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

SAVANNAH RIVER PLANT

SEPARATIONS PLANTS - 200 AREAS

" A " LINE

1, 221-F "A" L ine - Bulk Handling s8-1021

I n s t a l l a t i o n of the bulk handl ing equipment i s now 99% complete. Oxide Leakage a.6 the end bearings of the new screw conveyor is delaying s ta r t -up . delayed but arrangements have been made t o borrow one so t r i a l runs may s ta r t early i n July.

Del ivery of the continuous sampler has been

A wonak reques t has been au thor ized t o provide funds f o r Engineer- i n g t o s tudy changes t o t h i s equipment t o increase the n e t load from 5 t o 6 tons per container .

WASTE DISPOSAL

1. 241-F - Addit ional Low Level Waste Storage - ~8-1.030

The scope of! work for t h i s p r o j e c t was based on s t o r i n g either fresh low l e v e l wastes from 221 Building o r accumulated low l e v e l wastes transferred from e x i s t i n g s torage . c r i v e r i a as tank operat ing temperature, s o l u t i o n s p e c i f i c g rav i ty and. a c t i v i t y were spec i f i ed f o r that concept of operat ion. sequent ly , the concept of a d d i t i o n a l waste concentrat ion, from 35 t o TO$ s o l i d s i n the tank farm, was advanced and it now appears that a review of design c r i t e r i a is required t o deter- mine the adequacy of the present proposed design f o r the rev ised opera t ing concept.

Such design

Sub-

The Engineering Department w i l l review the new tank design con- s i d e r i n g the fol lowing:

a.

C O

d.

Wastes t o be s t o r e d w i l l have been evaporated t o about 70$ s o l i d s (Spec i f i c Gravi ty 1.8)* The temperature a t which wastes w i l l be introduced t o the s to rage tank w i l l be about 275"F0 bulk tank temperature of about 200°F.

T h i s may r e s u l t i n a

The rate of concentrated waste add i t ion t o the s torage tank w i l l be about 270o#/hr. Only low l e v e l wastes and decayed high l e v e l wastes w i l l be concentrated.

AED w i l l advise concerning the s p e c i f i c a c t i v i t y of wastes t o be processed so that s h i e l d i n g ca l cu la t ions can be checked, A r a d i a t i o n l e v e l of 25 MR/hr above the tanks can be t o l e r - ated.

Page 10: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

WASTE DISPOSAL (Continued)

1. 241-F - Addit ional Low Level Waste Storage-S8-1030 (Continued)

A s p rev ious ly reported, it is feasible s t r u c t u r a l l y t o i n s t a l l an "in-tank" evaporator by suspending it from the dome of the new tanks. It has now been determined that it is desirable and economically j u s t i f i a b l e t o have the large c e n t r a l - t a n k opening (approximately $-foot diameter) whether it i s used f o r i n s t a l l i n g the "in-tank" evaporator o r no t . An opening t h i s s i z e w i l l reduce cons t ruc t ion c o s t s for the i n s t a l l a t i o n and removal of concrete forms and shoring, The large c e n t r a l opening w i l l be included i n the new t ank design.

2. 242-F - Waste Tank Farm Evaporation

The Griscom-Russell "bent tube" model evapora tor i n s t a l l a t i o n was inspec ted during the month. A t the t i m e , automat2.c opera t ion had been maintained s u c c e s s f u l l y f o r about a week feed ing simu- lated low l e v e l waste a t 30$ s o l i d s and evaporat ing to'70$ s o l i d s , The rated capac i ty of t h i s evaporator is 400,000 BTU/hn?.

A few minor design changes were discussed and the f u t u r e program ou t l ined . t o r y opera t ion i s aga in demonstrated, freeze-up problems will be simulated and means compatible wi th the remote opera t ion necessary i n t h i s s e r v i c e w i l l be sought t o resume opera t ion after such a freeze-up. of s imulated tank #1 waste w i l l be started'.

A f t e r the recommended changes are made and satisfac-

Following t h i s demonstration the evaporat ion

A s yet, s c a l i n g of the evaporator tubes has no t occurred. Since bottoms and process condensate are r e c o n s t i t u t e d f o r reuse and the amount of feed is small, however, t h i s test a t Griscom- Russe l l is not considered a demonstration of the s c a l i n g charac- te r i s t ics of low l e v e l waste, Foaming has been encountered, but only dur ing evaporator s t a r t -up . After about 50$ s o l i d s concen- t r a t i n n i s reached, foaming subsides .

Engineering has been requested t o inc lude i n their c o s t evalua- t i o n f o r an "in-tank" evaporator , s h i e l d i n g of the condenser and the condensate r e c e i v e r s f o r r a d i a t i o n p r o t e c t i o n i n the event tha t inadve r t en t foam-over contaminates t h i s equipment.

3. 2 4 1 4 - Waste Pumps

Tes t ing of the first waste pump a t TNX i s cont inuing, has been run about 160 hours continuously, p l u s 400 on-off cyc le s which is equiva len t t o about a year's opera t ion . No defects have appeared to date, designed t o give a more n e a r l y ideal curve has been ordered.

The pump

A cast i r o n tes t impel ler

Page 8

Page 11: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

WASTE DISPOSAL (cont inued)

3. 241-H - Waste Pumps (Continued)

When it is received, the l i f e t e s t i n g a t TNX w i l l be terminated. The pump w i l l be disassembled and inspec ted f o r wear. It w i l l then be reassembled, and tests on the new impel ler w i l l be run by the Engineering Department.

TRITIUM SEPARATION

1. 232-H - R e h a b i l i t a t i o n

Drawings have been approved covering the p ip ing diagrams, the a i r monitoring, and the gas sampling arrangement. It has been agreed tha t space w i l l be l e f t f o r the a d d i t i o n of boos ter pumps or o t h e r pumps t o inc rease the capac i ty of the f irst l i n e t o the l i m i t of the e x i s t i n g d i f f u s e r capac i ty , assuming that the c u r r e n t furnace capac i ty l i m i t a t i o n may be e l imina ted i n the f u t u r e . T h i s would approximately double i t s rated capac i ty . F a c i l i t i e s t o accomplish the capac i ty inc rease w i l l no t be pro- vided a t p re sen t s i n c e they would-delay completion of the l i n e ,

2. 232-H - Second Line

A scope of work covering a high capacity second l i n e for 232-H has been prepared a t SRP. It assumes that a high capacity dif- f u s e r w i l l be used and is s i z e d t o a l low maximum f o r e c a s t p l a n t production of t r i t i u m t o be processed i n one l i n e . The use of such a large capac i ty l i n e . w i l 1 be evaluated and compared w i t h opera t ion of a l l three l i n e s w i t h such modif icat ion as may be r equ i r ed f o r moderate inc reases i n their .capacity.

3. Building 234-H

The prototype o i l - ac tua t ed mercury compressor has been fabricated and i n s t a l l e d a t the Mechanical Development Laboratory, opera t ion i s scheduled t o begin the f irst week of J u l y t 9 demon- strate o p e r a b i l i t y of the machine. The diaphragm type com- pressor being b u i l t by Pressure Products I n d u s t r i e s i s expected t o be complete the week of J u l y 9 . .

T e s t

The bu i ld ing frame has been completed and i n s t a l l a t i o n of under- floor ducts and pipes is i n progress . The concre te f i n i s h was inspec ted and it has been agreed that only minor a d d i t i o n a l f i n i s h i n g w i l l be requi red t o obta in a su r face s u i t a b l e for p a i n t i n g .

Page 12: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

INCREASED CAPACITY

1. 221-F and Related F a c i l i t i e s

A l l f lowshee ts and diagrams have been approved by the AED and r e tu rned t o the Engineering Department w i t h comments.

A temporary "hold" has ,been placed on the i n s t a l l a t i o n o f the t h i r d d i s s o l v e r and i ts as soc ia t ed off-gas system. f a c i l i t i e s are t o be designed and AED n o t i f i e d a t least two weeks before the latest date tha t cons t ruc t ion must proceed t o maintain the p r o j e c t schedule. under p re sen t production f o r e c a s t s the t h i r d s l u g d i s s o l v e r may no t be requi red p r i o r t o the time when new long element d i s s o l v e r s are needed.

These

T h i s a c t i o n was taken s i n c e

The Engineering Department has been requested t o s tudy an a l t e r n a t e type of continuous canyon evaporator i n which the de-entrainment column and the r e b o i l e r are an i n t e g r a l u n i t t o e l imina te the large f langed j o i n t s ; i n the p resen t design. Savings from the s impl i f i ed design are estimated t o o f f s e t the c o s t s of abandoning the p resen t design and the redesigned u n i t is expected t o fac i l i t a te maintenance s i n c e it can be handled w i t h e x i s t i n g type l i f t i n g yokes and s impl i f i ed jumper arrange- ment . A meeting was held w i t h p l a n t Operating and Engineering Con- s t r u c t i o n personnel t o def ine the r a d i a t i o n l e v e l s and condi t ion of equipment i n var ious s e c t i o n s of the area as it w i l l be turned over t o Construction f o r r e l o c a t i o n or modif icat ion. A l i s t of equipment which can be r e loca ted t o avoid the purchase of new equipment was a l s o developed.

2. "Brr Line

A l e t t e r summarizing the basis f o r design and the estimated c o s t of the proposed new "B" Line was i ssued June 18, is cont inuing pending a dec i s ion on the proposal submitted.

Design work

Page 10

Page 13: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

SAVANNAH RIVER PLANT

REACTOR FUELS FABRICATION - 300 AREA

INCREASED PRODUCTIVITY PROGRAM

1. Extended SzarPzce Enriehed Elements - Mark V I Program

a , General

P a r t I of the p r o j e c t covering design and cons t ruc t ion of facilities i n the 300-M Area f o r f a b r i c a t i o n of extended su r face enriehed uranium f u e l t ubes and l i t h i u m aluminum target s l u g s has now been ap roved by the Atomic Energy Commission. The au thor ized f 5,OOO,OOO is intended t o cover t he c o s t of design, procurement of c r i t i c a l equip- ment and partial i n s t a l l a t i o n of f a c i l i t i e s p a r t i c u l a r l y needed f o r i n t e r im production of Mark V I assemblies p r i o r t o completion of the f i n a l production opera t ions . It is a n t i c i p a t e d that the cons t ruc t ion c o s t estimate w i l l be completed and ready f o r release t o AED by September 1. Current schedul ing c a l l s ' f o r approval of the P a r t I1 by November 1 . Engineering has been requested t o proceed wi th a s tudy of a d d i t i o n s and/or modif icat ions t o Bui ldings 320 and 321-M necessary f o r conversion t o production of Mark VI-A f u e l assemblies, T h i s conversion involves manufacture of two r ibbed f u e l and one unribbed target tubes, a l l by coextru- s i o n cladding, whereas, the Mark V I f u e l element i s com- prised of one unribbed coextruded f u e l tube conta in ing a s i n g l e column of target s lugs .

b. Fue l Fac i l i t y - IBui ld ing 321-M

General arrangement drawings f o r Bui lding 321-M have been formal ly approved . arrangements i n ind iv idua l areas is progress ing w i t h par- t i c u l a r emphasis on l o c a t i o n of equipment foundat ions and sub-f loor p ip ing and e l e c t r i c a l work i n e f for t t o f i r m up the f l o o r slab design, already been released t o the F ie ld f o r pre l iminary construc- t ion .

D e t a i l i n g of equipment and p ip ing

Concrete f o o t i n g details have

P r i o r t o the tube drawing opera t ion r equ i r ed t o f i n a l l y s i z e the extruded f u e l tubes it is necessary t o "point" the ex- t r u s i o n f o r i t s attachment t o the drawing f ix ture . ' Suc- c e s s f u l demonstration of the po in t formed on both smooth and ribbed f u e l t ubes by a Stevens and Bu l l ivan t fixed head r o t a r y po in t ing machine has resulted i n agreement t o pro- cure one of these machines f o r Bui lding 321.

i,

Page 11

Page 14: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

INCREASED PRODUCTIVITY PROGRAM (Continued)

1, ( b ) Fuel F a c i l i t y - Building 321-M (Continued)

Prel iminary information on the over -a l l problem of s t r a i g h t e n i n g of unribbed f u e l tubes and 12-foot extruded L i A l rods i n d i c a t e s that a two-roll r o t a r y s t r a i g h t e n e r may be the most e f f e c t f v e device f o r bo th opera t ions . Present p lans c a l l for t e s t i n g of SRP elements on t h i s type s t r a i g h t e n e r i n the near f u t u r e . r o l l e r s t r a i g h t e n i n g t o r ibbed f u e l tubes does no t appear promising , however.

Successful adapta t ion of

c. Target F a c i l i t y - Building 320-M

A design data r e p o r t d e t a i l i n g a d d i t i o n a l equipment requi re - ments for expansion of LiAl s l u g production f a c i l i t i e s i n Bui lding 320-M has been received from SRP and forwarded t o Engineering. Similar information on the Building 320-M a n a l y t i c a l l abo ra to ry wing expansion has a l s o been received from SRP.

General agreement has been reached on the l o c a t i o n of both exis t ing and new equipment wi th in the p resen t bu i ld ing area and on ,genera l arrangement of the furnace room expan- s i o n . equipment l ayou t s awaits receipt of approved drawings from National Research Corporation and Stokes Machine Company.

F i n a l d e t a i l i n g of the new furnace and a u x i l i a r y

With some minor r e v i s i o n s the e x i s t i n g a i r condi t ion ing equipment i n the f i n a l s l u g machining area should adequately se rve the expanded process ing room requirements. To i n s u r e c o n t i n u i t y of opera t ion , one of the two e x i s t i n g 100 HP u n i t s s e rv ing t h e . l a b o r a t o r y wing w i l l be piped i n as a standby supply of 40°F chi:led w a t e r ! f o r the s l u g processing areaq 100 HP u n i t w i l l be fu rn i shed i n the f u t u r e by 45°F c h i l l e d water obtained from the c e n t r a l r e f r i g e r a t i o n p l a n t , Build-

Laboratory requirements o r i g i n a l l y served by t h i s

i n g 7890 2. Extended Surface Natura l Uranium Elements

a. Extrusion Cladding F a c i l i t i e s - Building 773-A

Engineering i s c u r r e n t l y completing equipment design for the ex t rus ion cladding press, Design of the material handling equipment is scheduled f o r completion the end of July. Pro- curement of a l l l i m i t i n g equipment i s e s s e n t i a l l y complete w i t h the except ion of tliat for, material handling which' i's p r e s e n t l y being designed. Del ivery of the ma jo r i ty of the equipment i s scheduled by early September. Drawings for

Page 12

Page 15: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

INCREASED PRODUCTIVITY PROGRAM (Continued)

2 . (a ) Extrusion Cladding F a c i l i t i e s - Building 773-A (Continued)

f i e l d f a b r i c a t i o n of a u x i l i a r y equipment have been issued. Construct ion work on t h i s f a c i l i t y is scheduled t o begin i n e a r l y J u l y and t o be complete i n October.

b. Pneumatic Pressing F a c i l i t i e s - Prototype Autoclave - Bui ld ing T-1001

Engineer ing i s c u r r e n t l y comparing three a l t e r n a t e systems f o r t he f l u i d pressure bonding of Mark V and Mark I11 f u e l elements. The systems under s tudy are as follows:

(1) Preheat ing the f u e l element p r i o r t o t r a n s f e r t o a cold w a l l autoclave equipped w i t h gas c i r c u l a t i o n and i n t e r n a l e l e c t r i c a l hea t e r s .

( 2 ) Preheating the f u e l element p r i o r t o t r a n s f e r t o a cold wall autoclave containing i n t e r n a l e l e c t r i c a l heaters and a hot r e s e r v o i r but without gas c i rcu- l a t i o n .

(3) Preheating the f u e l element w i t h i n the autoclave proper using a hot r e s e r v o i r ,

c. Mark V I 1 Hot P res s ing Faci l i t ies - Building 313-M

Work Request No. 50207 has been au thor ized early i n June f o r $5,000 t o prepare pre l iminary designs and an eva lua t ion estimate of fac i l i t i es i n Bui ld ing 313-M f o r hot press ing Mark V I 1 f u e l e lements , Prel iminary layout of the f a c i l i t y has been prepared u t i l i z i n g present 313-M cleaning and inspec t ion equipment wherever appl icable . necessary f o r the i n s t a l l a t i o n has been determined and an estimate is c u r r e n t l y being prepared, 'Scheduled completion of the eva lua t ion estimate i s i n early July.

The new equipment

3. Consolidated Meta l lurg ica l Control Laboratory

The general arrangement of l abora to ry modules wi th in the 50' x 120' Bu t l e r Building, which w i l l house these f a c i l i t i e s , has been firmed up. It i s a n t i c i p a t e d tha t preliminary cons t ruc t ion work on Bui ld ing 322-M w i l l s t a r t sometime during August of t h i s year.

GENERAL

V e r t i c a l Sal t B a t h I n s t a l l a t i o n - Building T-1001

Check-out and run-in of equipment by Construct ion i s c u r r e n t l y i n p rogres so It i s a n t i c i p a t e d that turnover t o SRL w i l l take p lace by the middle of July.

Page 13

Page 16: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

HIEATTY WATER

DANA PLANT

1. GS Unit Bubble Cap Tray Replacement Program

I n s t a l l a t i o n of a t o t a l of 230 replacement Type 304 s t a i n l e s s steel bubble tray assemblies i n Unit 201 has been s u c c e s s f u l l y completed and the u n i t is again f n opera t ion , A l l necessary material is now on hand, inc luding a complete set of experimental s i e v e trays f o r one first stage tower pair, f o s part ia l r e t r a y i n g of Unit 202 during July.

2, Gas Generation P l a n t Scrubber B l i s t e r i n g

Three blisters, ranging from c i r c u l a r t o ova l i n shape and from roughly 3 t o ' 2 0 square inches i n area, were observed during in spec t ion of the Gas Generation p l a n t scrubber-cooler. height of the blisters above the genera l scrubber wall su r face was approximately 1/8". Minimum sound wall t h i ckness measured

The

i n the affected areas was O.3l" compared w i t h a design th ickness of 0.56".

A l l three bl is ters were vented by d r i l l i n g completely through the v e s s e l w a l l , then plugged by i n s e r t i n g a shielded s t a i n l e s s steel pipe p lug i n t o the ho le s from the outs ide .

-been reduced i n proport ion t o the reduct ion i n sound w a l l thick- ness. during next year's t e s t ' a n d in spec t ion program.

The RV s e t t i n g has

Condition of the blistered areas w i l l be c a r e f u l l y examined

Page 14

Page 17: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

SAVANNAH RIVER PLANT

UTILITIES AND GENERAL SERVICES

ADMINISTRATIVE, TECHNICAL AND GENERAL SERVICES

A supplement t o the Power Contract was executed providing f o r the pur- chase of an a d d i t i o n a l 65,000 KW of power from the U t i l i t y . plement a l s o provides f o r the e r e c t f o n of a new t i e - l i n e from Urquhart S t a t i o n t o the Savannah River P l a n t .

The sup-

A drawing was approved f o r the new bridge on Road No. 3 where it c rosses the 1 0 0 - C Area ' e f f luen t stream. P r o j e c t N o , ~8-1.035 - "Increased River Water Flows" t o r e p l a c e the exist- ing c u l v e r t s t r u c t u r e which had inadequate capaci.ty t o c a r r y the increased e f f l u e n t .

The new bridge is being i n s t a l l e d on

A meeting was held with AEC t o review the design and Order-of-Magnitude E s t i m a t e f o r the proposed a d d i t i o n a l High Level Caves f a c i l i t i e s a t the Main Technical Laboratory,Building 773-A. The OME c o s t of the a d d i t i o n a l f a c i l i t i e s is $l,5OO,OOO. The P a r t I of t h i s p r o j e c t (~8-1051.) i s cir- c u l a t i n g f o r du Pont approval. Design i s approximately 3% complete. Arch i t ec tu ra l and. e l e v a t i o n drawings have been reviewed and r e tu rned w i t h comments to the Engineering Department f o r r e v i s i o n and submittal f o r f i n a l approval.

Construction is cont inuing on the Engineering Assis tance F a c i l i t y , Build- i ng 723-A, cealed wir ing and p ip ing are e s s e n t i a l l y complete and i n t e r i o r p a r t i t i o n s are approximately 95% complete

The e x t e r i o r of the bu i ld ing i s e s s e n t i a l l y complete. Con-

A reques t was rece ived from the Technical Divis ion t o prepare design and estimates for two ( 2 ) in te rmedia te l e v e l chemistry cells and one (1) mini- mixer ce l l t o be i n s t a l l e d i n the basement of the Main Technical Laboratory, Bui lding 773-A. Basic data f o r use i n prepar ing a Design Data Report i s

' being prepared, No a s s i s t a n c e has been requested as yet from the Engineer- i ng Department.

Arrangements have been made w i t h ORNL t o conduct tests of var ious manu- f a c t u r e r ' s p a i n t s i n an attempt t o develop a lower c o s t a l t e r n a t e for Amercoat. p repara t ion now specified f o r Amercoat.

ConsideratAon w i l l a l s o be given to r e l a x i n g the r i g i d su r face

100 AREA UTILITIES

A meeting was held w i t h AEC to d i scuss progress t o date on the s tudy of evaporat ive cool ing f o r a d d i t i o n a l cool ing water t o the 100 Areas. Evalu- a t i o n s were presented covering the i n s t a l l a t i o n of cool ing towers versus a cool ing pond on Lower Three Runs Creek. Subsequent to the meeting the Engineering Department was requested by AED t o prepare an eva lua t ion es t i - mate f o r a cool ing pond t o be loca ted on Tinker Creek j u s t above i t s junc- t i o n wi th Upper Three Runs. The Tinker Creek pond would provide a larger and deeper r e s e r v o i r than the previous ly evaluated Lower Three Runs site.

Page 15

Page 18: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

100 AREA UTILITIES (Continued)

The i n s t a l l a t i o n of new 25-1/4" impellers i n t h e 3.90 Bui ld in cont inuing with seven ( 7 ) already i n s t a l l e d i n L Area, s ix (6 s ix ( 6 ) i n R Area and f o u r ( 4 ) i n K Area, rece ived from the vendor and are being i n s t a l l e d . provide the a d d i t i o n a l head required f o r pumping cool ing water t o the twelve heat exchangers now i n series arrangement i n the Re P, L, and K Areas A strike a t the Vendor's p l a n t delayed shipment of these impellers and it is now estimated that e ight (8) impe l l e r s w i l l be i n s t a l l e d i n each of the 100 Areas, except C Area, by the end of July. The eight (8) impellers f o r C Area are scheduled f o r delivery. July 21, 1956, but w i l l not be in - s ta l led u n t i l the modified but terf ly valves are i n s t a l l e d about September 1, 1956 e

Six more impel lers have been The larger impellers

600 AFEA UTILITIES

I n s t a l l a t i o n of the new 38" impeller i n the No. 7 pump i n Building 681-1~ has been completed, i n s t a l l e d , J u l y 5, 1956, revamping of the 681-16 and 3 G pump houses as related t o the P roduc t iv i ty Improvement Progv.ams

The No. 7 motor has been rece ived and i s now being Check-out and run-in of the motor and pump are scheduled f o r

T h i s is the f irst i n s t a l l a t i o n , as a prototype, f o r the

900 AREA UTILITIES

A repor t was presented by the Engineering Department on the a d d i t i o n a l water hammer p r o t e c t i o n r equ i r ed on the r iver water pipe l i n e s to handle the increased water requirements i n connection w i t h the P roduc t iv i ty Improvement Program, and d iscuss ion of the more feasible a l t e r n a t e s .

The r e p o r t included a d e s c r i p t i o n of a l t e r n a t e p lans

PROJECT AND WORK REQUEST AUTHORIZATIONS

The fol lowing p r o j e c t s and work r eques t s were approved and/or au thor ized during the month:

Savannah River P l a n t s8-1013-11 Addit ional Breathing A i r Packs $ 6,400 To ta l Parts 1&2

~8-1044-1 Addit ional Manufacturing Faci l i -

S8-1047 Carrying Account f o r Future

Bldgs. 411-1D, 412-1D and 413-D Reduction $41,300

t i e s (LW&T) 300-M Area 5, 000,000 S8-1045 D r y Chemical Faci l i ty , 773-A 57,000

s8-1050 Secondary Road Bridges & Culvert 37,000

Bldg. 722-A 7,800

P r o j e c t s 6,000 , 000

Crossings, Bldg , 6 0 3 - ~ ~8-3007 Automatic Radio Repair Fac i l i ty

Page 16

Page 19: MONTHLY REPORT PROCESS SECTION/67531/metadc708579/m2/1/high_res... · -~ MONTHLY REPORT - PROCESS SECTION I JULY 15, 1956 E. 1. duPont de Nemours & Co. (Inc.) Explosives Department

" ,.* UNCLASSIFIED PROJECT AND WORK REQUEST AUTHORIZATIONS (Continued)

s8-3022

~ 8 - 3 0 2 3 Sg-1027

S9-1043

S9-1046

s9-3543

s 9 - 3 5 3 3

DANA PLANT

C-55-11

WORK REQUESTS

Addftional V e n t i l a t i o n F a c i l i t i e s $ 8,500 Bldgi 313-M Addftfonal Light ing f o r Bldg, 6 7 8 - ~ 9,300 Replacement of E x i s t i n g Chlorine 62 , 500 F a c i l i t i e s , Bldgs. 183-1R & 183-4PLKC Replacement of General Purpose Gas 20,500 Masks I n s t a l l . Pure Steam F a c i l i t y , 40,000.

Addit ional F i l t e r Boats "B" Lines, 82 , 000 Bldg. 221-F and H Procure Addit ional Shipping Casks 52,000 l o 0 Area F a c i l i t i e s f o r Loading & Unloading 5,600

Thermocouple Instrument Rods, 18,000

Bldg, 105-R,P,L9K,C

Trucks, Bldg. 313-M

Bldgs. R,P,L,K;C

Al loca t ion of Funds f o r Small P r g j e c t s Year Ending September 30, 1955 Reduction $133,830

58,170 To ta l P a r t s 1&2

25924 V 50080 v 50117-11 50142-11

50162-11 50170-11 50178-11 50204 50205

50206

50207 50209 50210 50214

Handling NFE 100 Areas Extrusion Design F l u i d Flow T e s t Program Inspec t ion of Tubes f o r 100 Area Condensers NFE (LM) B i l l e t Welding Prototype Re to r t Furnace NFE (LM) Cast ing F ix tu re Mechanized Coining Press - 320-M Completion of F a c i l i t i e s - Process Line 2, Bldg. 232-H Rod Deburring and Coddng Table Bldg. 320-M Manufacturing Mark V I 1 Run-Out Table & Feeder Mechanism lrFtt Area Through-Put S tud ie s Bulk Handling Capacity 221-F "A" Line

20,000 15,000

3,000 1 , 000

5,300 75,000

5,500 4,500

35,000

5,600

5,000 15,000 75,000

800

"P" Work Order - PWO-1 (S8-1041) A i r Conditioning f o r Offices, A l l Areas, $100,000, was approved during t h e month,

Page 17

U NCLASSI FI ED!