Prepared by Construction Supervision Consultant for JUFMP/JEDI. Main works of the project are to dredge
Citation preview
Ministry of Public Works and Housing Affair World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)
www.jufmp.com 1
Korea Engineering Consultant Corp of Korea,
in association with
PT. Puser Bumi Mekon
PT. Tetira International Consultants
PT. Duta Cipta Mandiri Engineering Consultants 1
Prepared by
1. JUFMP/JEDI Information
2. Consultant Services
3. Executive Summary
4. Issues
5. Ongoing Construction Packages
Package 1
Package 2A
Package 2B
Package 3
Package 5
6. Photo Gallery
2
Table of Contents
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Project Information
Project Name : JUFMP/JEDI
Loan Agreement : 8121 ID
Date of Loan Sign : February 17, 2012
Effective Date : August 8, 2012
Closing Date : March 31, 2017
Loan Amount : USD 139,640,000
Executing Agency : 1. Directorate General Water Resources, MoPW
2. Directorate General Cipta Karya, MoPWHA
3. Provincial Government of DKI Jaya
3
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
1. Reduce the frequency and extend of flooding in Jakarta through
dredging, and rehabilitation and construction of embankment of key
waterways and flood retention basins;
2. Establishing institutional coordination between, and strengthening
their capacity of the three responsible agencies, to improve the
operations, maintenance and management of Jakartas flood management system.
The project is intended to reduce the economic and social cost of
flooding by partially restoring the capacity of the citys flood control system to its original design level.
Project Development Objective (PDO)
4
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
1. Dredging and rehabilitation of selected key floodways, canals
and retention basins.: This component support the dredging and
rehabilitation of 11 floodways/canals and 4 retention basins which
have been identified as a priority sections of Jakarta flood
management system in the need of urgent rehabilitation and
improvement in flow capacities (USD 176.1 million)
2. Technical assistance for project management, social
safeguards, and capacity building: The component will support
contracts managemnt, engineering design review, construction
supervision engineers for dredging and rehabilitation works and
technical assistance for implementation of the project, including
Resettlement Policy Framework, Resettlement Plan and Grievance
Redress System (USD 13.4 million)
Project Components
5
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Project Organization
6
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Project Location
7
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Subprojects and PIU
8
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Construction Supervision Consultant (CSC) for JUFMP/JEDI
Project Name : Construction Supervision Consultant for JUFMP/JEDI
Source of Fund : World Bank
Addendum No.1 : 1,784,300 USD + 38,494,770,000 IDR
Contract Amount : 2,072,400 USD + 38,153,170,999 IDR
Engineer : Directorate of River and Coastal, Directorate General Water Resources, Ministry of Public Work and Housing
Contractor : Korea Engineering Consultants Corporation with PT. Puser Bumi Mekon joint venture and sub consultancy PT. Tetira International Consultant and PT. Duta Cipta Mandiri Engineering Consultant
Contract No. : 06/KTR/PPK-Ad-Satker/X/2013 September 11, 2013
Notice to Proceed : HI.0102-Ad/496 October 18, 2013
Time Period : 40.5 months Adendum No.1, originally 60 months
9
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
The main services of the Consultant for JUFMP/JEDI are:
Supervision of Dredging Work and Construction/Rehabilitation of Embankment
Quality Assurances and Quality Control Assist in Implementation of Environmental Management (RKL/RPL) Assist in Implementation of Resettlement Plans (RPs) Implementation of Grievance Redress System (GRS) and Complaint
Handling Mechanism
Monitoring, Reporting and Recording Assist CPMU, CPIU and PIUs in Project Management
Outline of Consultant Services
10
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Executive Summary
11
103.5 58%
53.0 30% 22.3
12%
Total Budget 178.7
Prov Gov of DKI (37%) + IBRD (67%)
DG Water Resources (20%) + IBRD (80%)
DG Cipta Karya (20%) + IBRD (80%)
Figure 1. Budget Allocation for Component 1of JUFMP (in million USD)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Executive Summary
12
Executing Agencies/ Packages Budget (Loan +
APBN/D) Loan Allocation APBD/N Sharing
USD USD USD
DKI Jakarta 103,492,537 69,340,000 34,152,537
Package 1 36,716,418 24,600,000 12,116,418
Package 4 47,014,925 31,500,000 15,514,925
Package 7 19,761,194 13,240,000 6,521,194
DGWR 53,000,000 42,400,000 10,600,000
Package 2A 31,000,000 24,800,000 6,200,000
Package 2B 8,125,000 6,500,000 1,625,000
Package 6 13,875,000 11,100,000 2,775,000
DGCK 22,250,000 17,800,000 4,450,000
Package 3 6,717,421 5,373,937 1,343,484
Package 5 15,532,579 12,426,063 3,106,516
TOTAL 178,742,537 129,540,000 49,202,537
Table 1. Budget Allocation for Component 1
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Executive Summary
13
Items Total Loan IBRD
APBD/N Sharing
Bilateral Grant
USD USD USD USD
Supervision Consultant 10,100,000 10,100,000 - - Flood Management Information System
500,000 - - 500,000
Panel of Experts 500,000 - 500,000 - Resetlement Cost (DKI Jaya) 2,800,000 - 2,800,000 -
Total Component 2 13,900,000 10,100,000 3,300,000 500,000 Total Project Cost (Comp 1+2) 192,642,537 139,640,000 52,502,537 500,000
Table 2. Budget Allocation for Component 2
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Executive Summary
14
Table 3. Contract Amount by Packages (IDR)
Executing Agencies/ Packages
Contract Amount Loan APBN/D Sharing
DKI Jakarta 284,180,000,000 190,400,600,000 93,779,400,000
Package 1 284,180,000,000 190,400,600,000 93,779,400,000
Package 4 - - -
Package 7 - - -
DGWR 334,965,463,260 267,972,370,608 66,993,092,652
Package 2A 260,000,000,000 208,000,000,000 52,000,000,000
Package 2B 74,965,463,260 59,972,370,608 14,993,092,652
Package 6 - - -
DGCK 208,214,431,000 166,571,544,800 41,642,886,200
Package 3 68,514,386,000 54,811,508,800 13,702,877,200
Package 5 139,700,045,000 111,760,036,000 27,940,009,000
TOTAL 827,359,894,260 624,944,515,408 202,415,378,852
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Executive Summary
15
Figure 4. Financial Progress (in billion IDR)
-
50
100
150
200
250
300
Package 1 Package 2A Package 2B Package 3 Package 5
163.6 148.6
33.9 19.8 22.2
208.7 201.5
54.9 54.0
32.9
284.2
260.0
75.0 68.5
139.7
Disbursed Disbursement + Un-disbursement Contract Amount
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Executive Summary
16
Table 4. Volume of Dredge Material of On-going Packages
Package Sign Date Notice to Proceed
Period
Volume (thousand m3)
Weight Garbage Sludge
Garbage + Sludge
(days) (m3) (m3) (m3) (%)
Package 1 Nov 26,2013 Dec 02,2013 730 2.8 165.6 168.4 8.3
Ciliwung-Gn. Sahari 1.5 85.1 86.6 4.2
Waduk Melati 1.4 80.5 81.9 4.0
Package 2A Nov 11,2013 Nov 11,2013 730 18.8 1,007.3 1,026.1 50.4
Package 2B Nov 11,2013 Nov 11,2013 730 20.0 513.7 533.7 26.2
Package 3 Nov 15,2013 Nov 15,2013 730 0.8 48.4 49.2 2.4
Package 5 Sep 3,2014 Sep 3,2014 730 6.2 253.0 259.2 12.7
Tanjungan Drain 0.0 11.2 11.2 0.6
Lower Angke Drain 6.2 241.8 248.0 12.2
T O T A L 48.7 1,988.0 2,036.7 100.0
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Executive Summary
17
Table 5. Progress of Dredging Works (On-going Packages)
Package Trip of Truck
Volume (thousand m3)
Garbage Sludge Garbage + Sludge
Package 1 8,765 - 160.5 160.5 95.3%
Ciliwung-Gn.Sahari 4,644 - 84.3 84.3 97.4%
Waduk Melati 4,121 - 76.2 76.2 93.0%
Package 2A 48,407 - 806.7 806.7 78.6%
Package 2B 21,968 - 376.6 376.6 70.6%
Package 3 209 - 3.6 3.6 7.3%
Package 5 144 - 2.4 2.4 0.9%
Tanjungan Drain 144 - 2.4 2.4 21.7%
Lower Angke Drain - - - - -
T O T A L 79,493 - 1,349.8 1,349.8 66.3%
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Executive Summary
18
Figure 5. Schedule and Progress of Construction Works (%)
0 10 20 30 40 50 60 70 80 90
Package 5
Package 3
Package 2B
Package 2A
Package 1
16.9
86.5
78.5
69.6
75.8
14.1
82.7
78.7
82.3
74.2
Progress Schedule
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
1. Package 1 Ciliwung-Gunung Sahari and Waduk Melati
a) Waduk Melati: (i) construction schedule for Waduk Melati
pump station needs to be precisely managed to complete
within the contract period, and (ii) guard rail as an
additional work will be installed around the Waduk (fencing
in original contract was changed to guard rail in MC 0).
b) Gunung Sahari drain: remaining works such as gaps
between embankment edge and bridges, U-ditch along the
right bank and side walk along Jl. Gunung Sahari drain
should be completed as scheduled. DKI requested to
heighten the side walk.
Issues
19
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
2. Package 2A Cengkareng Floodway
a) Contractor proposed embankment work at both sides of the
floodway between bridges at STA 2+250 - STA 2+500 to use
stone masonry rather than piles for the reason of working space
limitation.
b) STA 3+400 - STA 5+050: several missing portion (gaps) on the
presence of road crossings and culverts.
c) Remedial works have not been started.
3. Package 2B Lower Sunter Floodway a) Temporary disposal of dredge material at some places not
applied.
4. Package 3 Cideng-Thamrin Drain
Issues
20
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
5. Package 4 Sentiong Sunter, Waduk Sunter Utara, Waduk Sunter Selatan and Waduk Sunter Timur III
a) Bid opened on March 24, 2015. PT. Adhi Karya has the lowest
bidding price of 296.9 billion IDR
6. Package 5 Lower Angke and Tanjungan Drain
a) Not sufficient storage space available for CCSPs and heavy
equipment (such as crane) at Lower Angke Drain.
7. Package 6 Banjir Kanal Barat (BKB)and Upper Sunter
a) Dredge from Karet to river mouth proposed to add to Package 6.
b) Bidding is delayed due to LARAP.
Issues
21
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
8. Package 7 Grogol Seketaris, Pakin, Kali Besar, Jelakeng and Krukut.
a) Bid opened March 10, 2015. PT. Waskita Karya has the lowest
bidding price of 226.8 billion IDR.
9. LARAP
a) Houses and buildings along Upper Sunter Floodway (Package 6) in Kayu Putih village of Pulo Gadung sub-district have been
demolished by DKI Jaya Government. PAPs of JUFMP/JEDI
located on Jatinegara Kaum were not affected by the demolition.
b) Due to problem at Lower Angke Muara, Dinas Tata Air DKI,
embankment work at Kel. Kapuk Muara modified to stone
masonry instead of concrete piles.
Issues
22
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
c) LARAP reports for Sentiong Sunter, Waduk Sunter Utara and
Waduk Sunter Selatan were prepared and second socialization
is planned.
10. Construction Supervision Consultant
a) Staff of site offices have faced difficulties due to shortage of
transportation (mainly motor cycles).
b) Overtime payment for enumerators, surveyors and drivers not
yet settled.
Issues
23
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
24
PACKAGE 1
CILIWUNG-GUNUNG SAHARI DRAIN AND WADUK MELATI
PT. Brantas Abipraya (Persero)
Contractor:
City Gov of DKI World Bank
General Information
25
P I U : DPU - DKI
Contractor : PT. Brantas Abipraya
No Objection Letter : No. JUFMP 1
Letter of Acceptance : No. 14705/-7.793.2
Contract No. : 15380/-1.793.2 dated Nov 26, 2013
Contract Amount : IDR 284,180,000,000 (incl. PPN)
Signed Date : Nov 26, 2013
Notice to Proceed : 15452/-1.793.2 dated Nov 26, 2013
Completion Day : 730 Calendar days
Elapsed Days : 514 days (70.4%)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
General Information
26
ISTIQLAL MOSQUE
SHEET PILE
4,832 m
Dredging Volume: 86,557 m3
Progress : 78,185 m3 or 90.3%
Embankment Repair : 4.600 m
LENGTH
OF DREDGING
5,100 m
Ciliwung Gunung Sahari Drain
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
27
Ciliwung Gunung Sahari Drain
a) Dredging Work: total = 86,557 m3, progress = 84,279 m3 (97.4%)
STA 0+500 - STA 5+100 (Martadinata Bridge - Istiqlal - Pasar Baru)
b) Concrete Work
volume = 2,681 m3 , length = 4,300 m reinforcement bar, deformed = 91.04 ton
c) Pilling Work
Furnishing of CCSP W-450, total = 5,178 units L 12 m = 2,442 units, L 14 m = 1,582 units, L 17 m = 1,154 units
Furnishing of square pile 40x40 cm, total = 392 units Driving of CCSP W-450, total = 5,178 units
d) Miscellaneous Works
Demolishing and disposal of existing concrete, total = 12.8 m3 Demolishing and disposal stone masonry, total = 2,088 m3
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
28
Waduk Melati
a) Dredging Works: total = 81,878 m3, progress = 76,167 m3 (93.0%)
b) Concrete Work
Total concrete = 570.25 m3, length = 1,229 m Reinforcement bar, deformed = 30.95 ton
c) Pilling Works
Furnishing of CCSP W-450, total =1,208 units 10 m = 959 units, L 12 m = 249 units
Driving of CCSP W-450, total = 1,208 units
d) Miscellaneous Work
Demolishing and disposal of stone masonry, total = 1,021 m3
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
29
Package 1: Progress of Dredging Works (thousand m3)
May 2014 Apr 2015
0.1 0.1 0.1
2.3
27.3
55.8
81.3
97.6 116.6
132.3 149.2
160.4
0
20
40
60
80
100
120
140
160
180
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
30
Package 1: Schedule and Progress of Construction Work (%) May 2014 Apr 2015
0 2
6 10
14
19 23
29
36
44
51
58
65
72
77
72 76
3 4 6 9
15
20
30
37
43
53
58
62 67
69 71
73 74
0
10
20
30
40
50
60
70
80
90
Schedule Progress
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
31
Package 1: Financial Progress (billion IDR)
Apr 2015
163.6 58%
45.1 16%
75.5 26%
Disbursed Undisbursed Remaining
Contract Value = 284.2
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
32
PACKAGE 2A - CENGKARENG FLOODWAY
Contractor:
Adhi Karya-Hutama Karya-Jaya Konstruksi JV
BBWS CILCIS World Bank
General Information
33
P I U : BBWS Ciliwung-Cisadane, DGWR
Contractor : Adhi Karya-Hutama Karya-Jaya Konstruksi (JV)
No Objection Letter : No. JUFMP/107 dated Sep 7, 2013
Letter of Acceptance : No.KU.03.01/PPK SP-SNVT PJSA CC/XI/310.1 dated Nov 6, 2013
Contract No. : HK.02.03/PPK SP-SNVT PJSA CC/XI/315.4 dated Nov 11, 2013
Amendment IV : IDR 260,000,000,000 incl. 10% tax
Amendment II : IDR 234,627,368,750 incl. 10% tax
Original Contract : IDR 209,808,000,000 incl. 10% tax
Signed Date : Nov 11, 2013
Completion Day : 730 Calendar days
Elapsed Days : 535 days (73.3%)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Location and Scope of Works
34
Sta 7+800
Sta 6+750
Sta 5+000
Sta 3+750
Replacement
of Water Gates Sta 4+500
Sta 5+875
W : 325 ; B : 1000 L : 14 meter
KAPUK
PULO
BRIDGE
KEMBANGAN
BRIDGE
KAPUK
RAYA
DREDGING WORK
Target
Length = 8,380 m
Volume=1,026,125 m3
Finished
Length = 4+700 m
Volume= 711,684 m3
PILLING WORK
Target
Length = 5,700 m
CCSP W-325 = 5,700 units
Pile 30x30 = 1,425 units
Finished
Length = ... m CCSP W-325 = 5,703 units
Pile 30x30 = 1,203 units
PILLING WORK
Length = 4,600 m
CCSP W-325 = 110,699 units
Pile 30x30 = 390,000 units
PILLING WORK
Target
Length = 2,100 m
CCSP W-325 = 2,100 units
Pile 30x30 = 525 units
Finished
Length = 1,000 m
CCSP W-325 = 1,071 units
Pile 30x30 = 175 units
Cengkareng Floodway
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
35
Cengkareng Floodway
a) Dredging Work: total = 1,026,125 m3, progress = 806,700 m3 (78.6%)
STA 0+500 - STA 7+800
b) Concrete Work
CCSP capping = 2,292.1 m3, backpile capping = 150.30 m3, walling = 86 m3
c) Pilling Work
Furnishing of CCSP W-325 and W-450, total = 8,057 units L 12 m = 5,269 units, L 14 m = 2,948 units, L 15 m = 55 units, L 18 m = 237 units
Furnishing of square pile 40x40 cm, total = 2,064 units L 10 m = 1,656 units, L 12 m = 408 units
Driving of CCSP W-450, total = 8,426 units L 12 m = 5,268 units, L 14 m = 2,870 units, L 15 m = 55 units, L 18 m = 233 units
Driving of square pile total = 1,842 units L 10 m = 1,513 units, L 12 m = 329 units
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
36
Package 2A: Progress of Dredging Works (thousand m3)
May 2014 Apr 2015
13.7 29.4 67.1
92.8
123.4
134.7
182.5
246.7
377.4
457.5 530.1
605.5
711.7
806.7
0
80
160
240
320
400
480
560
640
720
800
880
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
37
Package 2A. Schedule and Progress of Construction Work (%)
May 2014 Apr 2015
1 3 3
8
17 19
32 38
41 46
49
53
60 62
65 66 70
11
23 27
29 34 37
40
46 47
54 57
65 66 69
73 78
82
0
10
20
30
40
50
60
70
80
90
Schedule Progress
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
38
Package 2A. Financial Progress (billion IDR)
Apr 2015
148.6 57%
52.9 20%
58.5 23%
Disbursed Undisbursed Remaining
Contract Value = 260.0
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
39
PACKAGE 2B - LOWER SUNTER FLOODWAY
Contractor:
PT. Hutama Karya (Persero)
BBWS CILCIS World Bank
General Information
40
P I U : BBWS Ciliwung-Cisadane, DGWR
Contractor : PT. Hutama Karya
No Objection Letter : No. JUFMP/1
Letter of Acceptance : No.14705/-7.793.2
Contract No. : HK.02.03/PPK SP-SNVT CC/XI/315.4
Contract Amount : IDR 65,258,477,570
Amendment I No. : HK.02.03/AMD/PPK SP-SNVT/PJSA CC/II/38.5
Amendment I Amount : IDR 74,965,463,260
Signed Date : Nov 11, 2013
Notice to Proceed : Nov 11, 2013
Completion Day : 730 Calendar days
Elapsed Days : 535 days (73.3%)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Location and Scope of Works
41
Concrete wall
1,000 m
Concrete Wall
400 m
Concrete Wall
400 m
Lower Sunter Floodway
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Lower Sunter Drain
a) Dredging Work: total = 533,689 m3, progress = 376,624 m3 (70.6%)
STA 0+025 - STA 7+350
b) Concrete Work
Type-A (K-225), total = 1,998 m3
Formwork type A2 = 4,083 m2
Reinforcement bar, deformed = 87,305 kg Lean concrete, t = 10 cm, total = 149 m3
Graded sand fill, t = 10 cm, total = 149 m3
Stone masonry, total = 278 m3
c) Pilling Work
Furnishing of concrete pile 20x20x400, total = 3,600 units Driving of concrete pile 20x20x400, total = 2,961 units
42
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
43
Package 2B. Progress of Dredging Works (thousand m3)
May 2014 Apr 2015
3.0 16.8
47.6
57.3
81.3
126.8
185.0
243.6
282.7 306.5
314.2
334.2
376.6
0
50
100
150
200
250
300
350
400
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
44
Package 2B. Schedule and Progress of Construction Work (%)
Dec 2014 Apr 2015
0 2 5
9 13
17
23
29
37 37
44
51
58
64
68
74 79
13 13 14 18
24 27
31 37
42 44
47
56 59
65 68
73
79
0
10
20
30
40
50
60
70
80
90
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
45
Package 2B. Financial Progress (billion IDR)
Apr 2015
33.9 45%
21.0 28%
20.0 27%
Disbursed Undisbursed Remaining
Contract Amount = 75.0
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
46
PACKAGE 3 CIDENG THAMRIN DRAIN
Contractor:
PT. Dutaraya Dinametro
DG Cipta Karya World Bank
General Information
47
P I U : Directorate of Environmental Sanitation Development, Directorate General Human Settlement, Ministry of Public Work and Housing
Contractor : PT. Dutaraya Dinametro
No Objection Letter : No. JUFMP-3
Contract No. : HK.02.03/JUFMP-FSK/XI/1
Contract Amount : IDR 62,324,785,000 (Addendum 2)
IDR 48,747,011,000 (Original Contract)
Signed Date : Nov 15, 2013
Notice to Proceed : Nov 15, 2013
Completion Day : 730 Calendar days
Elapsed Days : 531 days (72.7%)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Location and Scope of Works
48
Reinforced Concrete Block
EXISTING
SHEETPILES
NEW
SHEETPILES
Cideng Thamrin Drain
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Cideng-Thamrin Drain
49
a) Dredging Work: total = 49,224 m3, progress = 3,598 m3 (7.3%)
STA 0CT-4 - STA CT-31
b) Concrete Work
Type-A (K-225), total = 998.8 m3
c) Pilling Work
Furnishing of CCSP W-325 L = 14 m, total = 602 units
Furnishing of CCSP W-350 L = 16 m, total = 1,538 units
Driving of CCSP W-325 L = 14 m, total = 602 units
Driving of CCSP W-350 L = 16 m, total = 1,524 units
Driving of 6 Pipe L = 10 m under Bridges
target = 18,960 m, progress = 12,110 m (63.9%)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
50
Package 3. Schedule and Progress of Construction Work (%)
Dec 2014 Apr 2015
5 5 3 6 10
13 16
20 25
33
41
47
62 62
71
82 87
0 0 5
11 15
21 26
34
41
48
63 62 64 64
72
79 83
0
10
20
30
40
50
60
70
80
90
100
Schedule Progress
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
51
Package 3. Financial Progress (billion IDR)
Apr 2015
19.8 29%
34.2 50%
14.5 21%
Disbursed Undisbursed Remaining
Contract Amount = 68.5
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
52
PACKAGE 5
TANJUNGAN DRAIN AND LOWER ANGKE DRAIN
Contractor:
PT. SAC Nusantara and PT. Penata Karya Utama (JO)
DG Cipta Karya World Bank
General Information
53
P I U : Directorate of Environmental Sanitation Development, DGHS, MoPW
Contractor : PT. SAC Nusantara and PT. Penata Karya Keluarga Utama (JO)
No Objection Letter : -
Letter of Acceptance : No.KU.03.01/JUFMP/02/VIII/2014
Contract No. : HK.02.03/JUFMP-FSK/IX/2
Contract Amount : IDR 139,700,045,000 (incl. Tax)
Signed Date : Sep 3, 2014
Notice to Proceed : -
Completion Day : 730 Calendar days
Elapsed Days : 239 days (32.7%)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Location and Scope of Works
54
LENGTH
OF DREDGING
600 m SHEET PILE
1,092 m
Dredging : 11,210 m3
Embankment Repair: 1,092 m
TANJUNGAN
DRAIN
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Location and Scope of Works
55
SHEET PILE
248 m
LENGTH
OF DREDGING
4,050 m
RETAINING WALL
573 m
Dredging : 241,800 m3
Embankment Repair : 821 m
LOWER ANGKE
DRAIN
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Tanjungan Drain
56
a) Dredging Works: total = 11,500 m3, progress = 4,468 m3 (38.9%)
b) Concrete Work
Total concrete = 228.3 m3
Formwork type-A2 = 182.6 m2
c) Pilling Works
Furnishing of CCSP W-500, total = 1,000 units 14 m = 600 units, L 16 m = 400 units
Furnishing of square pile 0.3x0.3x10 m, total = 50 units
Driving of CCSP W-500, total = 935 units
14 m = 559 units, L 16 m = 376 units
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
57
Package 5. Schedule and Progress of Construction Work (%)
Oct 2014 Apr 2015
0.6
2.3
3.5
5.5
9.3
13.0
16.9
0.4
3.1
9.0
10.1
13.0 13.6 14.1
0
5
10
15
20
Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15
Schedule Progress
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
58
Package 5. Financial Progress (billion IDR)
Apr 2015
22.2 16%
10.7 8%
106.8 76%
Disbursed Undisbursed Remaining
Contract Value = 139.7
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Check list reinforcement bar STA 3 + 200
Ciliwung Gunung Sahari Drain Result of Concrete Work STA 3 + 350
Ciliwung Gunung Sahari Drain
Package 1
59
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Activities of Dredging pump STA 0 + 850 at
Ciliwung Gunung Sahari Drain Excavation for foundation of pump station at
Waduk Melati
Package 1
60
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Concrete Work for the foundation of pump
station at Waduk Melati Dredging Work at STA 0+050 Waduk Melati
Package 1
61
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Package 2A
62
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Package 2A
63
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Package 2B
64
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Package 3
65
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Package 3
66
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
MoPW&HA World Bank
Mr. President, Ministry of PWHA and
Governor of DKI visited Tanjungan Drain Dredging work at Tanjungan Drain