67
Ministry of Public Works and Housing Affair World Bank Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI) www.jufmp.com 1 Korea Engineering Consultant Corp of Korea, in association with PT. Puser Bumi Mekon PT. Tetira International Consultants PT. Duta Cipta Mandiri Engineering Consultants 1 Prepared by

Monthly Report April 2015 - JUFMP/JEDI

Embed Size (px)

DESCRIPTION

Prepared by Construction Supervision Consultant for JUFMP/JEDI. Main works of the project are to dredge

Citation preview

  • Ministry of Public Works and Housing Affair World Bank

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/

    Jakarta Emergency Dredging Initiative (JEDI)

    www.jufmp.com 1

    Korea Engineering Consultant Corp of Korea,

    in association with

    PT. Puser Bumi Mekon

    PT. Tetira International Consultants

    PT. Duta Cipta Mandiri Engineering Consultants 1

    Prepared by

  • 1. JUFMP/JEDI Information

    2. Consultant Services

    3. Executive Summary

    4. Issues

    5. Ongoing Construction Packages

    Package 1

    Package 2A

    Package 2B

    Package 3

    Package 5

    6. Photo Gallery

    2

    Table of Contents

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Project Information

    Project Name : JUFMP/JEDI

    Loan Agreement : 8121 ID

    Date of Loan Sign : February 17, 2012

    Effective Date : August 8, 2012

    Closing Date : March 31, 2017

    Loan Amount : USD 139,640,000

    Executing Agency : 1. Directorate General Water Resources, MoPW

    2. Directorate General Cipta Karya, MoPWHA

    3. Provincial Government of DKI Jaya

    3

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 1. Reduce the frequency and extend of flooding in Jakarta through

    dredging, and rehabilitation and construction of embankment of key

    waterways and flood retention basins;

    2. Establishing institutional coordination between, and strengthening

    their capacity of the three responsible agencies, to improve the

    operations, maintenance and management of Jakartas flood management system.

    The project is intended to reduce the economic and social cost of

    flooding by partially restoring the capacity of the citys flood control system to its original design level.

    Project Development Objective (PDO)

    4

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 1. Dredging and rehabilitation of selected key floodways, canals

    and retention basins.: This component support the dredging and

    rehabilitation of 11 floodways/canals and 4 retention basins which

    have been identified as a priority sections of Jakarta flood

    management system in the need of urgent rehabilitation and

    improvement in flow capacities (USD 176.1 million)

    2. Technical assistance for project management, social

    safeguards, and capacity building: The component will support

    contracts managemnt, engineering design review, construction

    supervision engineers for dredging and rehabilitation works and

    technical assistance for implementation of the project, including

    Resettlement Policy Framework, Resettlement Plan and Grievance

    Redress System (USD 13.4 million)

    Project Components

    5

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Project Organization

    6

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Project Location

    7

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Subprojects and PIU

    8

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Construction Supervision Consultant (CSC) for JUFMP/JEDI

    Project Name : Construction Supervision Consultant for JUFMP/JEDI

    Source of Fund : World Bank

    Addendum No.1 : 1,784,300 USD + 38,494,770,000 IDR

    Contract Amount : 2,072,400 USD + 38,153,170,999 IDR

    Engineer : Directorate of River and Coastal, Directorate General Water Resources, Ministry of Public Work and Housing

    Contractor : Korea Engineering Consultants Corporation with PT. Puser Bumi Mekon joint venture and sub consultancy PT. Tetira International Consultant and PT. Duta Cipta Mandiri Engineering Consultant

    Contract No. : 06/KTR/PPK-Ad-Satker/X/2013 September 11, 2013

    Notice to Proceed : HI.0102-Ad/496 October 18, 2013

    Time Period : 40.5 months Adendum No.1, originally 60 months

    9

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • The main services of the Consultant for JUFMP/JEDI are:

    Supervision of Dredging Work and Construction/Rehabilitation of Embankment

    Quality Assurances and Quality Control Assist in Implementation of Environmental Management (RKL/RPL) Assist in Implementation of Resettlement Plans (RPs) Implementation of Grievance Redress System (GRS) and Complaint

    Handling Mechanism

    Monitoring, Reporting and Recording Assist CPMU, CPIU and PIUs in Project Management

    Outline of Consultant Services

    10

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Executive Summary

    11

    103.5 58%

    53.0 30% 22.3

    12%

    Total Budget 178.7

    Prov Gov of DKI (37%) + IBRD (67%)

    DG Water Resources (20%) + IBRD (80%)

    DG Cipta Karya (20%) + IBRD (80%)

    Figure 1. Budget Allocation for Component 1of JUFMP (in million USD)

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Executive Summary

    12

    Executing Agencies/ Packages Budget (Loan +

    APBN/D) Loan Allocation APBD/N Sharing

    USD USD USD

    DKI Jakarta 103,492,537 69,340,000 34,152,537

    Package 1 36,716,418 24,600,000 12,116,418

    Package 4 47,014,925 31,500,000 15,514,925

    Package 7 19,761,194 13,240,000 6,521,194

    DGWR 53,000,000 42,400,000 10,600,000

    Package 2A 31,000,000 24,800,000 6,200,000

    Package 2B 8,125,000 6,500,000 1,625,000

    Package 6 13,875,000 11,100,000 2,775,000

    DGCK 22,250,000 17,800,000 4,450,000

    Package 3 6,717,421 5,373,937 1,343,484

    Package 5 15,532,579 12,426,063 3,106,516

    TOTAL 178,742,537 129,540,000 49,202,537

    Table 1. Budget Allocation for Component 1

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Executive Summary

    13

    Items Total Loan IBRD

    APBD/N Sharing

    Bilateral Grant

    USD USD USD USD

    Supervision Consultant 10,100,000 10,100,000 - - Flood Management Information System

    500,000 - - 500,000

    Panel of Experts 500,000 - 500,000 - Resetlement Cost (DKI Jaya) 2,800,000 - 2,800,000 -

    Total Component 2 13,900,000 10,100,000 3,300,000 500,000 Total Project Cost (Comp 1+2) 192,642,537 139,640,000 52,502,537 500,000

    Table 2. Budget Allocation for Component 2

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Executive Summary

    14

    Table 3. Contract Amount by Packages (IDR)

    Executing Agencies/ Packages

    Contract Amount Loan APBN/D Sharing

    DKI Jakarta 284,180,000,000 190,400,600,000 93,779,400,000

    Package 1 284,180,000,000 190,400,600,000 93,779,400,000

    Package 4 - - -

    Package 7 - - -

    DGWR 334,965,463,260 267,972,370,608 66,993,092,652

    Package 2A 260,000,000,000 208,000,000,000 52,000,000,000

    Package 2B 74,965,463,260 59,972,370,608 14,993,092,652

    Package 6 - - -

    DGCK 208,214,431,000 166,571,544,800 41,642,886,200

    Package 3 68,514,386,000 54,811,508,800 13,702,877,200

    Package 5 139,700,045,000 111,760,036,000 27,940,009,000

    TOTAL 827,359,894,260 624,944,515,408 202,415,378,852

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Executive Summary

    15

    Figure 4. Financial Progress (in billion IDR)

    -

    50

    100

    150

    200

    250

    300

    Package 1 Package 2A Package 2B Package 3 Package 5

    163.6 148.6

    33.9 19.8 22.2

    208.7 201.5

    54.9 54.0

    32.9

    284.2

    260.0

    75.0 68.5

    139.7

    Disbursed Disbursement + Un-disbursement Contract Amount

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Executive Summary

    16

    Table 4. Volume of Dredge Material of On-going Packages

    Package Sign Date Notice to Proceed

    Period

    Volume (thousand m3)

    Weight Garbage Sludge

    Garbage + Sludge

    (days) (m3) (m3) (m3) (%)

    Package 1 Nov 26,2013 Dec 02,2013 730 2.8 165.6 168.4 8.3

    Ciliwung-Gn. Sahari 1.5 85.1 86.6 4.2

    Waduk Melati 1.4 80.5 81.9 4.0

    Package 2A Nov 11,2013 Nov 11,2013 730 18.8 1,007.3 1,026.1 50.4

    Package 2B Nov 11,2013 Nov 11,2013 730 20.0 513.7 533.7 26.2

    Package 3 Nov 15,2013 Nov 15,2013 730 0.8 48.4 49.2 2.4

    Package 5 Sep 3,2014 Sep 3,2014 730 6.2 253.0 259.2 12.7

    Tanjungan Drain 0.0 11.2 11.2 0.6

    Lower Angke Drain 6.2 241.8 248.0 12.2

    T O T A L 48.7 1,988.0 2,036.7 100.0

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Executive Summary

    17

    Table 5. Progress of Dredging Works (On-going Packages)

    Package Trip of Truck

    Volume (thousand m3)

    Garbage Sludge Garbage + Sludge

    Package 1 8,765 - 160.5 160.5 95.3%

    Ciliwung-Gn.Sahari 4,644 - 84.3 84.3 97.4%

    Waduk Melati 4,121 - 76.2 76.2 93.0%

    Package 2A 48,407 - 806.7 806.7 78.6%

    Package 2B 21,968 - 376.6 376.6 70.6%

    Package 3 209 - 3.6 3.6 7.3%

    Package 5 144 - 2.4 2.4 0.9%

    Tanjungan Drain 144 - 2.4 2.4 21.7%

    Lower Angke Drain - - - - -

    T O T A L 79,493 - 1,349.8 1,349.8 66.3%

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Executive Summary

    18

    Figure 5. Schedule and Progress of Construction Works (%)

    0 10 20 30 40 50 60 70 80 90

    Package 5

    Package 3

    Package 2B

    Package 2A

    Package 1

    16.9

    86.5

    78.5

    69.6

    75.8

    14.1

    82.7

    78.7

    82.3

    74.2

    Progress Schedule

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 1. Package 1 Ciliwung-Gunung Sahari and Waduk Melati

    a) Waduk Melati: (i) construction schedule for Waduk Melati

    pump station needs to be precisely managed to complete

    within the contract period, and (ii) guard rail as an

    additional work will be installed around the Waduk (fencing

    in original contract was changed to guard rail in MC 0).

    b) Gunung Sahari drain: remaining works such as gaps

    between embankment edge and bridges, U-ditch along the

    right bank and side walk along Jl. Gunung Sahari drain

    should be completed as scheduled. DKI requested to

    heighten the side walk.

    Issues

    19

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 2. Package 2A Cengkareng Floodway

    a) Contractor proposed embankment work at both sides of the

    floodway between bridges at STA 2+250 - STA 2+500 to use

    stone masonry rather than piles for the reason of working space

    limitation.

    b) STA 3+400 - STA 5+050: several missing portion (gaps) on the

    presence of road crossings and culverts.

    c) Remedial works have not been started.

    3. Package 2B Lower Sunter Floodway a) Temporary disposal of dredge material at some places not

    applied.

    4. Package 3 Cideng-Thamrin Drain

    Issues

    20

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 5. Package 4 Sentiong Sunter, Waduk Sunter Utara, Waduk Sunter Selatan and Waduk Sunter Timur III

    a) Bid opened on March 24, 2015. PT. Adhi Karya has the lowest

    bidding price of 296.9 billion IDR

    6. Package 5 Lower Angke and Tanjungan Drain

    a) Not sufficient storage space available for CCSPs and heavy

    equipment (such as crane) at Lower Angke Drain.

    7. Package 6 Banjir Kanal Barat (BKB)and Upper Sunter

    a) Dredge from Karet to river mouth proposed to add to Package 6.

    b) Bidding is delayed due to LARAP.

    Issues

    21

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 8. Package 7 Grogol Seketaris, Pakin, Kali Besar, Jelakeng and Krukut.

    a) Bid opened March 10, 2015. PT. Waskita Karya has the lowest

    bidding price of 226.8 billion IDR.

    9. LARAP

    a) Houses and buildings along Upper Sunter Floodway (Package 6) in Kayu Putih village of Pulo Gadung sub-district have been

    demolished by DKI Jaya Government. PAPs of JUFMP/JEDI

    located on Jatinegara Kaum were not affected by the demolition.

    b) Due to problem at Lower Angke Muara, Dinas Tata Air DKI,

    embankment work at Kel. Kapuk Muara modified to stone

    masonry instead of concrete piles.

    Issues

    22

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • c) LARAP reports for Sentiong Sunter, Waduk Sunter Utara and

    Waduk Sunter Selatan were prepared and second socialization

    is planned.

    10. Construction Supervision Consultant

    a) Staff of site offices have faced difficulties due to shortage of

    transportation (mainly motor cycles).

    b) Overtime payment for enumerators, surveyors and drivers not

    yet settled.

    Issues

    23

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    24

    PACKAGE 1

    CILIWUNG-GUNUNG SAHARI DRAIN AND WADUK MELATI

    PT. Brantas Abipraya (Persero)

    Contractor:

    City Gov of DKI World Bank

  • General Information

    25

    P I U : DPU - DKI

    Contractor : PT. Brantas Abipraya

    No Objection Letter : No. JUFMP 1

    Letter of Acceptance : No. 14705/-7.793.2

    Contract No. : 15380/-1.793.2 dated Nov 26, 2013

    Contract Amount : IDR 284,180,000,000 (incl. PPN)

    Signed Date : Nov 26, 2013

    Notice to Proceed : 15452/-1.793.2 dated Nov 26, 2013

    Completion Day : 730 Calendar days

    Elapsed Days : 514 days (70.4%)

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • General Information

    26

    ISTIQLAL MOSQUE

    SHEET PILE

    4,832 m

    Dredging Volume: 86,557 m3

    Progress : 78,185 m3 or 90.3%

    Embankment Repair : 4.600 m

    LENGTH

    OF DREDGING

    5,100 m

    Ciliwung Gunung Sahari Drain

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/

    Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 27

    Ciliwung Gunung Sahari Drain

    a) Dredging Work: total = 86,557 m3, progress = 84,279 m3 (97.4%)

    STA 0+500 - STA 5+100 (Martadinata Bridge - Istiqlal - Pasar Baru)

    b) Concrete Work

    volume = 2,681 m3 , length = 4,300 m reinforcement bar, deformed = 91.04 ton

    c) Pilling Work

    Furnishing of CCSP W-450, total = 5,178 units L 12 m = 2,442 units, L 14 m = 1,582 units, L 17 m = 1,154 units

    Furnishing of square pile 40x40 cm, total = 392 units Driving of CCSP W-450, total = 5,178 units

    d) Miscellaneous Works

    Demolishing and disposal of existing concrete, total = 12.8 m3 Demolishing and disposal stone masonry, total = 2,088 m3

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 28

    Waduk Melati

    a) Dredging Works: total = 81,878 m3, progress = 76,167 m3 (93.0%)

    b) Concrete Work

    Total concrete = 570.25 m3, length = 1,229 m Reinforcement bar, deformed = 30.95 ton

    c) Pilling Works

    Furnishing of CCSP W-450, total =1,208 units 10 m = 959 units, L 12 m = 249 units

    Driving of CCSP W-450, total = 1,208 units

    d) Miscellaneous Work

    Demolishing and disposal of stone masonry, total = 1,021 m3

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 29

    Package 1: Progress of Dredging Works (thousand m3)

    May 2014 Apr 2015

    0.1 0.1 0.1

    2.3

    27.3

    55.8

    81.3

    97.6 116.6

    132.3 149.2

    160.4

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 30

    Package 1: Schedule and Progress of Construction Work (%) May 2014 Apr 2015

    0 2

    6 10

    14

    19 23

    29

    36

    44

    51

    58

    65

    72

    77

    72 76

    3 4 6 9

    15

    20

    30

    37

    43

    53

    58

    62 67

    69 71

    73 74

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    Schedule Progress

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 31

    Package 1: Financial Progress (billion IDR)

    Apr 2015

    163.6 58%

    45.1 16%

    75.5 26%

    Disbursed Undisbursed Remaining

    Contract Value = 284.2

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    32

    PACKAGE 2A - CENGKARENG FLOODWAY

    Contractor:

    Adhi Karya-Hutama Karya-Jaya Konstruksi JV

    BBWS CILCIS World Bank

  • General Information

    33

    P I U : BBWS Ciliwung-Cisadane, DGWR

    Contractor : Adhi Karya-Hutama Karya-Jaya Konstruksi (JV)

    No Objection Letter : No. JUFMP/107 dated Sep 7, 2013

    Letter of Acceptance : No.KU.03.01/PPK SP-SNVT PJSA CC/XI/310.1 dated Nov 6, 2013

    Contract No. : HK.02.03/PPK SP-SNVT PJSA CC/XI/315.4 dated Nov 11, 2013

    Amendment IV : IDR 260,000,000,000 incl. 10% tax

    Amendment II : IDR 234,627,368,750 incl. 10% tax

    Original Contract : IDR 209,808,000,000 incl. 10% tax

    Signed Date : Nov 11, 2013

    Completion Day : 730 Calendar days

    Elapsed Days : 535 days (73.3%)

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Location and Scope of Works

    34

    Sta 7+800

    Sta 6+750

    Sta 5+000

    Sta 3+750

    Replacement

    of Water Gates Sta 4+500

    Sta 5+875

    W : 325 ; B : 1000 L : 14 meter

    KAPUK

    PULO

    BRIDGE

    KEMBANGAN

    BRIDGE

    KAPUK

    RAYA

    DREDGING WORK

    Target

    Length = 8,380 m

    Volume=1,026,125 m3

    Finished

    Length = 4+700 m

    Volume= 711,684 m3

    PILLING WORK

    Target

    Length = 5,700 m

    CCSP W-325 = 5,700 units

    Pile 30x30 = 1,425 units

    Finished

    Length = ... m CCSP W-325 = 5,703 units

    Pile 30x30 = 1,203 units

    PILLING WORK

    Length = 4,600 m

    CCSP W-325 = 110,699 units

    Pile 30x30 = 390,000 units

    PILLING WORK

    Target

    Length = 2,100 m

    CCSP W-325 = 2,100 units

    Pile 30x30 = 525 units

    Finished

    Length = 1,000 m

    CCSP W-325 = 1,071 units

    Pile 30x30 = 175 units

    Cengkareng Floodway

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 35

    Cengkareng Floodway

    a) Dredging Work: total = 1,026,125 m3, progress = 806,700 m3 (78.6%)

    STA 0+500 - STA 7+800

    b) Concrete Work

    CCSP capping = 2,292.1 m3, backpile capping = 150.30 m3, walling = 86 m3

    c) Pilling Work

    Furnishing of CCSP W-325 and W-450, total = 8,057 units L 12 m = 5,269 units, L 14 m = 2,948 units, L 15 m = 55 units, L 18 m = 237 units

    Furnishing of square pile 40x40 cm, total = 2,064 units L 10 m = 1,656 units, L 12 m = 408 units

    Driving of CCSP W-450, total = 8,426 units L 12 m = 5,268 units, L 14 m = 2,870 units, L 15 m = 55 units, L 18 m = 233 units

    Driving of square pile total = 1,842 units L 10 m = 1,513 units, L 12 m = 329 units

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 36

    Package 2A: Progress of Dredging Works (thousand m3)

    May 2014 Apr 2015

    13.7 29.4 67.1

    92.8

    123.4

    134.7

    182.5

    246.7

    377.4

    457.5 530.1

    605.5

    711.7

    806.7

    0

    80

    160

    240

    320

    400

    480

    560

    640

    720

    800

    880

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 37

    Package 2A. Schedule and Progress of Construction Work (%)

    May 2014 Apr 2015

    1 3 3

    8

    17 19

    32 38

    41 46

    49

    53

    60 62

    65 66 70

    11

    23 27

    29 34 37

    40

    46 47

    54 57

    65 66 69

    73 78

    82

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    Schedule Progress

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 38

    Package 2A. Financial Progress (billion IDR)

    Apr 2015

    148.6 57%

    52.9 20%

    58.5 23%

    Disbursed Undisbursed Remaining

    Contract Value = 260.0

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    39

    PACKAGE 2B - LOWER SUNTER FLOODWAY

    Contractor:

    PT. Hutama Karya (Persero)

    BBWS CILCIS World Bank

  • General Information

    40

    P I U : BBWS Ciliwung-Cisadane, DGWR

    Contractor : PT. Hutama Karya

    No Objection Letter : No. JUFMP/1

    Letter of Acceptance : No.14705/-7.793.2

    Contract No. : HK.02.03/PPK SP-SNVT CC/XI/315.4

    Contract Amount : IDR 65,258,477,570

    Amendment I No. : HK.02.03/AMD/PPK SP-SNVT/PJSA CC/II/38.5

    Amendment I Amount : IDR 74,965,463,260

    Signed Date : Nov 11, 2013

    Notice to Proceed : Nov 11, 2013

    Completion Day : 730 Calendar days

    Elapsed Days : 535 days (73.3%)

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Location and Scope of Works

    41

    Concrete wall

    1,000 m

    Concrete Wall

    400 m

    Concrete Wall

    400 m

    Lower Sunter Floodway

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Lower Sunter Drain

    a) Dredging Work: total = 533,689 m3, progress = 376,624 m3 (70.6%)

    STA 0+025 - STA 7+350

    b) Concrete Work

    Type-A (K-225), total = 1,998 m3

    Formwork type A2 = 4,083 m2

    Reinforcement bar, deformed = 87,305 kg Lean concrete, t = 10 cm, total = 149 m3

    Graded sand fill, t = 10 cm, total = 149 m3

    Stone masonry, total = 278 m3

    c) Pilling Work

    Furnishing of concrete pile 20x20x400, total = 3,600 units Driving of concrete pile 20x20x400, total = 2,961 units

    42

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 43

    Package 2B. Progress of Dredging Works (thousand m3)

    May 2014 Apr 2015

    3.0 16.8

    47.6

    57.3

    81.3

    126.8

    185.0

    243.6

    282.7 306.5

    314.2

    334.2

    376.6

    0

    50

    100

    150

    200

    250

    300

    350

    400

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 44

    Package 2B. Schedule and Progress of Construction Work (%)

    Dec 2014 Apr 2015

    0 2 5

    9 13

    17

    23

    29

    37 37

    44

    51

    58

    64

    68

    74 79

    13 13 14 18

    24 27

    31 37

    42 44

    47

    56 59

    65 68

    73

    79

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 45

    Package 2B. Financial Progress (billion IDR)

    Apr 2015

    33.9 45%

    21.0 28%

    20.0 27%

    Disbursed Undisbursed Remaining

    Contract Amount = 75.0

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    46

    PACKAGE 3 CIDENG THAMRIN DRAIN

    Contractor:

    PT. Dutaraya Dinametro

    DG Cipta Karya World Bank

  • General Information

    47

    P I U : Directorate of Environmental Sanitation Development, Directorate General Human Settlement, Ministry of Public Work and Housing

    Contractor : PT. Dutaraya Dinametro

    No Objection Letter : No. JUFMP-3

    Contract No. : HK.02.03/JUFMP-FSK/XI/1

    Contract Amount : IDR 62,324,785,000 (Addendum 2)

    IDR 48,747,011,000 (Original Contract)

    Signed Date : Nov 15, 2013

    Notice to Proceed : Nov 15, 2013

    Completion Day : 730 Calendar days

    Elapsed Days : 531 days (72.7%)

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Location and Scope of Works

    48

    Reinforced Concrete Block

    EXISTING

    SHEETPILES

    NEW

    SHEETPILES

    Cideng Thamrin Drain

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Cideng-Thamrin Drain

    49

    a) Dredging Work: total = 49,224 m3, progress = 3,598 m3 (7.3%)

    STA 0CT-4 - STA CT-31

    b) Concrete Work

    Type-A (K-225), total = 998.8 m3

    c) Pilling Work

    Furnishing of CCSP W-325 L = 14 m, total = 602 units

    Furnishing of CCSP W-350 L = 16 m, total = 1,538 units

    Driving of CCSP W-325 L = 14 m, total = 602 units

    Driving of CCSP W-350 L = 16 m, total = 1,524 units

    Driving of 6 Pipe L = 10 m under Bridges

    target = 18,960 m, progress = 12,110 m (63.9%)

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 50

    Package 3. Schedule and Progress of Construction Work (%)

    Dec 2014 Apr 2015

    5 5 3 6 10

    13 16

    20 25

    33

    41

    47

    62 62

    71

    82 87

    0 0 5

    11 15

    21 26

    34

    41

    48

    63 62 64 64

    72

    79 83

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    Schedule Progress

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 51

    Package 3. Financial Progress (billion IDR)

    Apr 2015

    19.8 29%

    34.2 50%

    14.5 21%

    Disbursed Undisbursed Remaining

    Contract Amount = 68.5

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    52

    PACKAGE 5

    TANJUNGAN DRAIN AND LOWER ANGKE DRAIN

    Contractor:

    PT. SAC Nusantara and PT. Penata Karya Utama (JO)

    DG Cipta Karya World Bank

  • General Information

    53

    P I U : Directorate of Environmental Sanitation Development, DGHS, MoPW

    Contractor : PT. SAC Nusantara and PT. Penata Karya Keluarga Utama (JO)

    No Objection Letter : -

    Letter of Acceptance : No.KU.03.01/JUFMP/02/VIII/2014

    Contract No. : HK.02.03/JUFMP-FSK/IX/2

    Contract Amount : IDR 139,700,045,000 (incl. Tax)

    Signed Date : Sep 3, 2014

    Notice to Proceed : -

    Completion Day : 730 Calendar days

    Elapsed Days : 239 days (32.7%)

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Location and Scope of Works

    54

    LENGTH

    OF DREDGING

    600 m SHEET PILE

    1,092 m

    Dredging : 11,210 m3

    Embankment Repair: 1,092 m

    TANJUNGAN

    DRAIN

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Location and Scope of Works

    55

    SHEET PILE

    248 m

    LENGTH

    OF DREDGING

    4,050 m

    RETAINING WALL

    573 m

    Dredging : 241,800 m3

    Embankment Repair : 821 m

    LOWER ANGKE

    DRAIN

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Tanjungan Drain

    56

    a) Dredging Works: total = 11,500 m3, progress = 4,468 m3 (38.9%)

    b) Concrete Work

    Total concrete = 228.3 m3

    Formwork type-A2 = 182.6 m2

    c) Pilling Works

    Furnishing of CCSP W-500, total = 1,000 units 14 m = 600 units, L 16 m = 400 units

    Furnishing of square pile 0.3x0.3x10 m, total = 50 units

    Driving of CCSP W-500, total = 935 units

    14 m = 559 units, L 16 m = 376 units

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 57

    Package 5. Schedule and Progress of Construction Work (%)

    Oct 2014 Apr 2015

    0.6

    2.3

    3.5

    5.5

    9.3

    13.0

    16.9

    0.4

    3.1

    9.0

    10.1

    13.0 13.6 14.1

    0

    5

    10

    15

    20

    Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15

    Schedule Progress

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • 58

    Package 5. Financial Progress (billion IDR)

    Apr 2015

    22.2 16%

    10.7 8%

    106.8 76%

    Disbursed Undisbursed Remaining

    Contract Value = 139.7

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Check list reinforcement bar STA 3 + 200

    Ciliwung Gunung Sahari Drain Result of Concrete Work STA 3 + 350

    Ciliwung Gunung Sahari Drain

    Package 1

    59

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Activities of Dredging pump STA 0 + 850 at

    Ciliwung Gunung Sahari Drain Excavation for foundation of pump station at

    Waduk Melati

    Package 1

    60

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Concrete Work for the foundation of pump

    station at Waduk Melati Dredging Work at STA 0+050 Waduk Melati

    Package 1

    61

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Package 2A

    62

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Package 2A

    63

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Package 2B

    64

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Package 3

    65

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Package 3

    66

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank

  • Mr. President, Ministry of PWHA and

    Governor of DKI visited Tanjungan Drain Dredging work at Tanjungan Drain

    Package 5

    67

    Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

    MoPW&HA World Bank