MONTHLY PROJECT UPDATE September 21, 2020

MONTHLY PROJECT UPDATE

  • Upload
    others

  • View
    2

  • Download
    1

Embed Size (px)

Citation preview

Page 1: MONTHLY PROJECT UPDATE

MONTHLY PROJECT UPDATESeptember 21, 2020

Page 2: MONTHLY PROJECT UPDATE

Notable Activities occurred this Period:

▪ Construction:

o Knapp Elementary School

▪ Contaminated soils removed from site

▪ Classroom Addition footings and piers installed 90%

▪ Underground piping installed at new office area

▪ Temporary partitions installed for areas started early Phase 1B and Phase 2

▪ ACM abatement started Phase 2

▪ Storm water piping from basin to street installed

▪ Concrete block units being installed at windows and foundation walls

▪ Anchor bolts and leveling plates for steel installed

▪ Storm water inlets on site completed

▪ Lansdale Borough has indicated they will not replace storm water from Knoll Dr.

▪ Accelerated plan discussed with SGA, School Principal and Mr. Schneider currently implemented

▪ Land Development completed

o Crawford Stadium

▪ Sanitary manholes #6, 7, and 2 installed

▪ Footings and foundation walls completed and grouted both buildings▪ Underground plumbing and electric being installed at both buildings

▪ Track perimeter drain at 80%

▪ Electrical exterior wall rough-in ongoing at both buildings

▪ Continued installation of field netting imbedded sports items along sidelines

Page 3: MONTHLY PROJECT UPDATE

Activities Planned for Next Period:

▪ Planning & Design:

o Knapp Elementary School

▪ Continue submittal review and approval

▪ Flashing school zone sign final design approval

anticipated

▪ Inspection procedure with Lansdale Borough

for each Phase defined and coordinated.

▪ Accelerated phasing changes require submittal

for long lead items also accelerated.

▪ Construction:

o Knapp Elementary School

▪ Complete foundations at classroom addition

▪ ACM abatement completed Phase 1B & 2

▪ Installation of foundations and piers at rear

addition and mechanical wall

▪ Install and grout bearing plates for steel rear

▪ Wall framing at new office to begin

▪ Steel installation to begin

▪ Masonry walls install ongoing

▪ Slab to grade and underground MEP rough

in completed

▪ Electric rough-in/network IDF relocation

▪ HVAC main piping install and branch tie-in

▪ Playground safety surface installation at

relocated play area

▪ Finalize bus parking area stone and curbing

▪ Install water service to building

▪ Base paving scheduled for October

Page 4: MONTHLY PROJECT UPDATE

Activities Planned for Next Period:

▪ Planning & Design:

o Crawford Stadium

▪ Continue submittal reviews and approval

▪ Continue subcontractor Township permit

requirements

▪ Building permits issued and Land

Development finalized.

▪ Construction:

o Crawford Stadium

▪ Continued installation of field draining system

▪ Complete perimeter channel drain installation

▪ Bring field to final grade

▪ Continue building masonry walls

▪ Complete installation of underground utilities at

buildings

▪ Pour building floor slabs end of month

▪ Communications duct bank installation started

▪ Electrical duct bank installation completed to

buildings

▪ Complete sanitary line

▪ Water line installation to buildings

▪ Continue imbedded materials installation, net

sleeves, pole vault box, triple jump, etc.

▪ Re-stabilize stockpiles as needed

Page 5: MONTHLY PROJECT UPDATE

▪ Schedule Status:

o Knapp Elementary School – 2 lost work-days due to weather Sept.

▪ Late items – Non-Critical Path

‐ Admin Office slab – 15 day late start

‐ Kitchen Addition Foundations – 5 day late start

▪ Late Items – Critical Path

‐ Steel Erection Admin – 10 days late

▪ Accelerated Items

‐ Piers – 10 days early start

‐ Storm Piping – 3 days early finish

‐ MC Underground – 2 day early finish

‐ Phase 1B & 2 ACM Removal – 60 day early start

o Crawford Stadium – 2 lost work-days due to weather Sept.

▪ Late items – Non-Critical Path

‐ Sanitary Sewer – 1 day late finish

‐ Bleacher Footings – 10 days late start

‐ Plumbing Rough – 2 days late finish

‐ Communication installation inside – 30 days late start

▪ Late Items – Critical Path

‐ No Items

▪ Accelerated Items

‐ Turf Anchor – 60 days early start

‐ Foundation walls – 8 days early start

‐ Foundation Insulation – 5 days early start

Page 6: MONTHLY PROJECT UPDATE

▪ Newly-Identified Critical Issues:

o Knapp Elementary School

▪ Unsuitable soils removal at new bus roadway – Unit cost & allowance

▪ Underground gas line in incorrect location – Lowering of gas line to install

storm water piping, raise elevation of storm at multiple locations.

▪ Existing to remain storm inlet had no bottom, replaced as allowance cost

▪ Additional storm inlet added to avoid gas line conflict, added per allowance

cost

▪ MCCD required changes to Erosion and Sediment Control Drawings COR

GC 001 - $14,405.63

▪ Newly-Identified Critical Issues:

o Crawford Stadium

▪ Unidentified concrete curbing around the perimeter of the existing track

needs to be removed and disposed of from the site.

▪ Underground transite sanitary piping removal currently under way. Should

be completed this week.

▪ Unsuitable soils at various areas surrounding track and in field. Heavily

pumping soils were discovered at new track location identified. Removal

under way.

▪ Discrepancies in scale on the drawings supplied to the Architect, resulted in

inaccurate survey dimensions for Communications work during the bidding

process. Quantities confirmed and reviewed. Change order request

submitted COR EC 001 - $30,146.83

▪ RFI#30 Additional Shock (water hammer) Arrestors COR PC 001 - $1,443.92

▪ ASI-001 Additional Roof Drain COR PC 002- $6,274.85

▪ Towamencin Township required manhole painting COR GC 001 - $1,892.98

Page 7: MONTHLY PROJECT UPDATE

▪ Safety Warning Status:

o Knapp Elementary School

▪ 1 - Warnings for mask protection

▪ 1 - Warning for hard hat violation

▪ 1- Scaffolding violation for access and assembly, corrected

same day

o Crawford Stadium

▪ 2 - Warnings for mask protection

▪ 1 – Warnings for hard hat violation

▪ 1 - Warning for safety barrier not in place correctly

▪ Accident Report Issues:

o Knapp Elementary School

▪ No accidents to report

o Crawford Stadium

▪ No accidents to report

Page 8: MONTHLY PROJECT UPDATE

Track Channel Drain Install Amenities Building CMU

Crawford Stadium

Page 9: MONTHLY PROJECT UPDATE

Below Field Drainage Athletics Building Foundation

Page 10: MONTHLY PROJECT UPDATE

Endzone Play Clock Post & Foundation Concession & Men’s Bathroom

Plumbing Underground

Page 11: MONTHLY PROJECT UPDATE

Stadium looking South Stadium looking West Stadium looking North Stadium looking East

Page 12: MONTHLY PROJECT UPDATE

New Addition Footings & Piers

Knapp Elementary School

Parent Drop Off & Hard Play Area Removal

Page 13: MONTHLY PROJECT UPDATE

New Window Infills Admin Classroom Addition Foundations New Door frames Admin Area

Page 14: MONTHLY PROJECT UPDATE

Mason Tower & Foundation CMU Underground Piping Nurses Area

Page 15: MONTHLY PROJECT UPDATE

Basin #2 Topsoil on Berm Classroom Addition Pier Ready Classroom Addition Pier Pour

Page 16: MONTHLY PROJECT UPDATE

Topsoil Application Basin #2 Demolition of Courtyard For New Office