Upload
others
View
2
Download
1
Embed Size (px)
Citation preview
MONTHLY PROJECT UPDATESeptember 21, 2020
Notable Activities occurred this Period:
▪ Construction:
o Knapp Elementary School
▪ Contaminated soils removed from site
▪ Classroom Addition footings and piers installed 90%
▪ Underground piping installed at new office area
▪ Temporary partitions installed for areas started early Phase 1B and Phase 2
▪ ACM abatement started Phase 2
▪ Storm water piping from basin to street installed
▪ Concrete block units being installed at windows and foundation walls
▪ Anchor bolts and leveling plates for steel installed
▪ Storm water inlets on site completed
▪ Lansdale Borough has indicated they will not replace storm water from Knoll Dr.
▪ Accelerated plan discussed with SGA, School Principal and Mr. Schneider currently implemented
▪ Land Development completed
o Crawford Stadium
▪ Sanitary manholes #6, 7, and 2 installed
▪ Footings and foundation walls completed and grouted both buildings▪ Underground plumbing and electric being installed at both buildings
▪ Track perimeter drain at 80%
▪ Electrical exterior wall rough-in ongoing at both buildings
▪ Continued installation of field netting imbedded sports items along sidelines
Activities Planned for Next Period:
▪ Planning & Design:
o Knapp Elementary School
▪ Continue submittal review and approval
▪ Flashing school zone sign final design approval
anticipated
▪ Inspection procedure with Lansdale Borough
for each Phase defined and coordinated.
▪ Accelerated phasing changes require submittal
for long lead items also accelerated.
▪ Construction:
o Knapp Elementary School
▪ Complete foundations at classroom addition
▪ ACM abatement completed Phase 1B & 2
▪ Installation of foundations and piers at rear
addition and mechanical wall
▪ Install and grout bearing plates for steel rear
▪ Wall framing at new office to begin
▪ Steel installation to begin
▪ Masonry walls install ongoing
▪ Slab to grade and underground MEP rough
in completed
▪ Electric rough-in/network IDF relocation
▪ HVAC main piping install and branch tie-in
▪ Playground safety surface installation at
relocated play area
▪ Finalize bus parking area stone and curbing
▪ Install water service to building
▪ Base paving scheduled for October
Activities Planned for Next Period:
▪ Planning & Design:
o Crawford Stadium
▪ Continue submittal reviews and approval
▪ Continue subcontractor Township permit
requirements
▪ Building permits issued and Land
Development finalized.
▪ Construction:
o Crawford Stadium
▪ Continued installation of field draining system
▪ Complete perimeter channel drain installation
▪ Bring field to final grade
▪ Continue building masonry walls
▪ Complete installation of underground utilities at
buildings
▪ Pour building floor slabs end of month
▪ Communications duct bank installation started
▪ Electrical duct bank installation completed to
buildings
▪ Complete sanitary line
▪ Water line installation to buildings
▪ Continue imbedded materials installation, net
sleeves, pole vault box, triple jump, etc.
▪ Re-stabilize stockpiles as needed
▪ Schedule Status:
o Knapp Elementary School – 2 lost work-days due to weather Sept.
▪ Late items – Non-Critical Path
‐ Admin Office slab – 15 day late start
‐ Kitchen Addition Foundations – 5 day late start
▪ Late Items – Critical Path
‐ Steel Erection Admin – 10 days late
▪ Accelerated Items
‐ Piers – 10 days early start
‐ Storm Piping – 3 days early finish
‐ MC Underground – 2 day early finish
‐ Phase 1B & 2 ACM Removal – 60 day early start
o Crawford Stadium – 2 lost work-days due to weather Sept.
▪ Late items – Non-Critical Path
‐ Sanitary Sewer – 1 day late finish
‐ Bleacher Footings – 10 days late start
‐ Plumbing Rough – 2 days late finish
‐ Communication installation inside – 30 days late start
▪ Late Items – Critical Path
‐ No Items
▪ Accelerated Items
‐ Turf Anchor – 60 days early start
‐ Foundation walls – 8 days early start
‐ Foundation Insulation – 5 days early start
▪ Newly-Identified Critical Issues:
o Knapp Elementary School
▪ Unsuitable soils removal at new bus roadway – Unit cost & allowance
▪ Underground gas line in incorrect location – Lowering of gas line to install
storm water piping, raise elevation of storm at multiple locations.
▪ Existing to remain storm inlet had no bottom, replaced as allowance cost
▪ Additional storm inlet added to avoid gas line conflict, added per allowance
cost
▪ MCCD required changes to Erosion and Sediment Control Drawings COR
GC 001 - $14,405.63
▪ Newly-Identified Critical Issues:
o Crawford Stadium
▪ Unidentified concrete curbing around the perimeter of the existing track
needs to be removed and disposed of from the site.
▪ Underground transite sanitary piping removal currently under way. Should
be completed this week.
▪ Unsuitable soils at various areas surrounding track and in field. Heavily
pumping soils were discovered at new track location identified. Removal
under way.
▪ Discrepancies in scale on the drawings supplied to the Architect, resulted in
inaccurate survey dimensions for Communications work during the bidding
process. Quantities confirmed and reviewed. Change order request
submitted COR EC 001 - $30,146.83
▪ RFI#30 Additional Shock (water hammer) Arrestors COR PC 001 - $1,443.92
▪ ASI-001 Additional Roof Drain COR PC 002- $6,274.85
▪ Towamencin Township required manhole painting COR GC 001 - $1,892.98
▪ Safety Warning Status:
o Knapp Elementary School
▪ 1 - Warnings for mask protection
▪ 1 - Warning for hard hat violation
▪ 1- Scaffolding violation for access and assembly, corrected
same day
o Crawford Stadium
▪ 2 - Warnings for mask protection
▪ 1 – Warnings for hard hat violation
▪ 1 - Warning for safety barrier not in place correctly
▪ Accident Report Issues:
o Knapp Elementary School
▪ No accidents to report
o Crawford Stadium
▪ No accidents to report
Track Channel Drain Install Amenities Building CMU
Crawford Stadium
Below Field Drainage Athletics Building Foundation
Endzone Play Clock Post & Foundation Concession & Men’s Bathroom
Plumbing Underground
Stadium looking South Stadium looking West Stadium looking North Stadium looking East
New Addition Footings & Piers
Knapp Elementary School
Parent Drop Off & Hard Play Area Removal
New Window Infills Admin Classroom Addition Foundations New Door frames Admin Area
Mason Tower & Foundation CMU Underground Piping Nurses Area
Basin #2 Topsoil on Berm Classroom Addition Pier Ready Classroom Addition Pier Pour
Topsoil Application Basin #2 Demolition of Courtyard For New Office