Monthly Progress Report of
February 2017
Executive SummaryProject Details and Building Progress report
Completed• 20th to pool deck floor toilet floor tile work• False ceiling work in toilet 20th floor and pool deck floor• False ceiling work in stair lobby & fire hose box covering 20th floor• Electrical work1st & 2nd fix G.F to roof floor• Waterproofing work for Jacuzzi and steam room• Lift work – Ground floor to lift machine room• Lift lobby floor tile 1stto 3rd floor• Final coat painting in kitchen portion 4th to 19th floor
In Progress• Floor tile – 20th floor to pool deck floor• Ground floor to Pool deck floor paint Primer & filler work • AC first fix• AC second fix• AC final fix• False ceiling works -4th to pool deck floor• Firefighting work G.F to Pool deck floor• Electrical work 3rd fix G.F to roof floor• Plumbing work 1st fix 4th to Pool deck floor• Plumbing work final fix 4th to 19th floor• Thermal insulation work ground floor to 20th floor• Aluminum doors and windows work 4th to 19th floor• Aluminum doors and windows work 20th floor• Aluminum cladding frame work front elevation• Aluminum cladding work front elevation• Balcony handrail fixing in roof, left, front and right side elevation• Vanity work – 4th to 19th floor• Internal wall 1st coat painting in 5th, 7th to roof deck floor• External wall 1st coat painting in left and right side elevation• External wall final coat painting in rear side elevation• Wooden doors fixing Ground floor to Pool deck floor• Waterproofing in roof area• Gypsum ceiling in lift lobby• Marble fixing in lift lobby wall• Epoxy painting in staircase, pump room and lift machine room• Epoxy painting in parking floor• Wall and floor tile – guard room• False ceiling works - ground floor• Final coat painting in gypsum ceiling 4th to 20th floor• Swimming pool work
3 - Jana Tower, Juffair — a project by Haqbaz Development
Activity Floor Status
Toilet floor tile work 20Th to pool deck floor COMPLETED
False ceiling work in toilet 20Th floor and pool deck floor COMPLETED
False ceiling work in stair lobby & fire hose box covering
20Th floor COMPLETED
Electrical work1st & 2nd fix G.F to roof floor COMPLETED
Waterproofing work Jacuzzi and steam room COMPLETED
Lift work Ground floor to lift machine room COMPLETED
Lift lobby floor tile 1St to 3rd floor COMPLETED
Final coat painting in kitchen portion 4Th to 19th floor COMPLETED
Floor tile 20Th floor to pool deck floor COMPLETED
Paint primer & filler work Ground floor to pool deck floor COMPLETED
Ac first fix COMPLETED
Ac second fix COMPLETED
Ac final fix COMPLETED
False ceiling work 4Th to pool deck floor COMPLETED
Firefighting work G.F to pool deck floor IN PROGRESS
Electrical work 3Rd fix g.F to roof floor IN PROGRESS
Plumbing work 1St fix 4th to pool deck floor IN PROGRESS
Plumbing work final fix 4Th to 19th floor IN PROGRESS
Thermal insulation work Ground floor to 20th floor IN PROGRESS
Aluminum doors and windows work 4Th to 19th floor IN PROGRESS
Aluminum doors and windows work 20Th floor IN PROGRESS
Aluminum cladding frame work Front elevation IN PROGRESS
Balcony handrail fixing in roof Left, front and right side elevation IN PROGRESS
Vanity work 4Th to 19th floor IN PROGRESS
Internal wall 1st coat painting 5Th, 7th to roof deck floor IN PROGRESS
External wall 1st coat painting Left and right side elevation IN PROGRESS
External wall final coat painting Rear side elevation IN PROGRESS
Wooden doors fixing Ground floor to pool deck floor IN PROGRESS
Waterproofing Roof area IN PROGRESS
Progress ReviewThe following is the list of work activities executed until 28th February 2017, as per the progress on site.
4 - Jana Tower, Juffair — a project by Haqbaz Development
Progress ReviewThe following is the list of work activities executed until 28th February 2017, as per the progress on site.
Activity Floor Status
Gypsum ceiling Lift lobby IN PROGRESS
Marble fixing Lift lobby wall IN PROGRESS
Epoxy painting Staircase, pump room and lift machine room IN PROGRESS
Epoxy painting Parking floor IN PROGRESS
Wall and floor tile Guard room IN PROGRESS
False ceiling works Ground floor IN PROGRESS
Final coat painting in gypsum ceiling 4Th to 20th floor IN PROGRESS
Swimming pool work Pool deck floor IN PROGRESS
5 - Jana Tower, Juffair — a project by Haqbaz Development
Steel work for jacuzzi in 20th floor
Piping work for jacuzzi in 20th floor
Floor tile fixing in roof deck floor
Steel work for jacuzzi in 20th floor
Piping work for jacuzzi in 20th floor
Floor tile fixing in roof deck floor
Site Snapshot
6 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Floor tile in 20th floor toilet
Gypsum ceiling painting in 20th floor
Final coat ceiling painting in roof deck floor
Floor tile in pool deck floor toilet
Gypsum ceiling painting in 20th floor
Final coat wall painting in roof deck floor
7 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
1Stcoat wall painting in 18th floor
Final coat wall painting in rear side elevation
Floortile fixing in 20th floor
1Stcoat wall painting in 19th floor
Final coat wall painting in rear side elevation
Floortile fixing in pool deck floor: (lift lobby)
8 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Wall tile works in 20th floor toilet
Wall tile works in ground floor toilet
Floor plaster in 20th floor steam room
Wall tile works in pool deck floor toilet
Floortile works in ground floor guard room
Floor plaster in 20th floor jacuzzi room
9 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Waterproofing in 20th floor steam room
Gypsum ceiling in 20th floor stair lobby
Stair lobby gypsum ceiling painting in 20th floor
Waterproofing in 20th floor jacuzzi room
Gypsum ceiling in pool deck floor stair lobby
Stair lobby gypsum ceiling painting in pool deck floor
10 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Thermal insulation work in ground floor
Toilet tile ceiling in 20th floor
Toilet gypsum ceiling painting in 20th floor
Gypsum ceiling painting in ground floor
Toilet gypsum ceiling in 20th floor
Toilet gypsum ceiling painting in pool deck floor
11 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Gypsum ceiling final coat in 19thfloor
Kitchen gypsum ceiling final coat in 19th floor
Aluminum windows glass fixing in left side elevation
Gypsum ceiling final coat in 18thfloor
Kitchen gypsum ceiling final coat in 18th floor
Aluminum windows glass fixing in right side elevation
12 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Aluminum louver fixing in parking floor
Bedroom door fixing in 13th floor
Lift lobby marble fixing in 17thfloor
Toilet door fixing in 14th floor
Entrance door fixing in 14thfloor
Lift lobby marble fixing in 14thfloor
13 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Bitumen paint primer apply in roof: (waterproofing)
Granular membrane in roof: (waterproofing)
Waterproofing in pool deck floor
Bituflame membrane in roof: (waterproofing)
Screed concrete poring in 20th floor: (gym room)
Primer work in pump room / water tank room
14 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Primer work in staircase
Wooden work in suana room
Epoxy painting work in pump room / water tank room
15 - Jana Tower, Juffair — a project by Haqbaz Development
Front elevation
Site Snapshot
16 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Left side elevation
17 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Right side elevation
18 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Rear elevation