Monthly Progress Report of

February 2017

Page 2: Monthly Progress Report of February 2017 - Haqbaz

Executive SummaryProject Details and Building Progress report

Completed• 20th to pool deck floor toilet floor tile work• False ceiling work in toilet 20th floor and pool deck floor• False ceiling work in stair lobby & fire hose box covering 20th floor• Electrical work1st & 2nd fix G.F to roof floor• Waterproofing work for Jacuzzi and steam room• Lift work – Ground floor to lift machine room• Lift lobby floor tile 1stto 3rd floor• Final coat painting in kitchen portion 4th to 19th floor

In Progress• Floor tile – 20th floor to pool deck floor• Ground floor to Pool deck floor paint Primer & filler work • AC first fix• AC second fix• AC final fix• False ceiling works -4th to pool deck floor• Firefighting work G.F to Pool deck floor• Electrical work 3rd fix G.F to roof floor• Plumbing work 1st fix 4th to Pool deck floor• Plumbing work final fix 4th to 19th floor• Thermal insulation work ground floor to 20th floor• Aluminum doors and windows work 4th to 19th floor• Aluminum doors and windows work 20th floor• Aluminum cladding frame work front elevation• Aluminum cladding work front elevation• Balcony handrail fixing in roof, left, front and right side elevation• Vanity work – 4th to 19th floor• Internal wall 1st coat painting in 5th, 7th to roof deck floor• External wall 1st coat painting in left and right side elevation• External wall final coat painting in rear side elevation• Wooden doors fixing Ground floor to Pool deck floor• Waterproofing in roof area• Gypsum ceiling in lift lobby• Marble fixing in lift lobby wall• Epoxy painting in staircase, pump room and lift machine room• Epoxy painting in parking floor• Wall and floor tile – guard room• False ceiling works - ground floor• Final coat painting in gypsum ceiling 4th to 20th floor• Swimming pool work

Page 3: Monthly Progress Report of February 2017 - Haqbaz

3 - Jana Tower, Juffair — a project by Haqbaz Development

Activity Floor Status

Toilet floor tile work 20Th to pool deck floor COMPLETED

False ceiling work in toilet 20Th floor and pool deck floor COMPLETED

False ceiling work in stair lobby & fire hose box covering

20Th floor COMPLETED

Electrical work1st & 2nd fix G.F to roof floor COMPLETED

Waterproofing work Jacuzzi and steam room COMPLETED

Lift work Ground floor to lift machine room COMPLETED

Lift lobby floor tile 1St to 3rd floor COMPLETED

Final coat painting in kitchen portion 4Th to 19th floor COMPLETED

Floor tile 20Th floor to pool deck floor COMPLETED

Paint primer & filler work Ground floor to pool deck floor COMPLETED

Ac first fix COMPLETED

Ac second fix COMPLETED

Ac final fix COMPLETED

False ceiling work 4Th to pool deck floor COMPLETED

Firefighting work G.F to pool deck floor IN PROGRESS

Electrical work 3Rd fix g.F to roof floor IN PROGRESS

Plumbing work 1St fix 4th to pool deck floor IN PROGRESS

Plumbing work final fix 4Th to 19th floor IN PROGRESS

Thermal insulation work Ground floor to 20th floor IN PROGRESS

Aluminum doors and windows work 4Th to 19th floor IN PROGRESS

Aluminum doors and windows work 20Th floor IN PROGRESS

Aluminum cladding frame work Front elevation IN PROGRESS

Balcony handrail fixing in roof Left, front and right side elevation IN PROGRESS

Vanity work 4Th to 19th floor IN PROGRESS

Internal wall 1st coat painting 5Th, 7th to roof deck floor IN PROGRESS

External wall 1st coat painting Left and right side elevation IN PROGRESS

External wall final coat painting Rear side elevation IN PROGRESS

Wooden doors fixing Ground floor to pool deck floor IN PROGRESS

Waterproofing Roof area IN PROGRESS

Progress ReviewThe following is the list of work activities executed until 28th February 2017, as per the progress on site.

Page 4: Monthly Progress Report of February 2017 - Haqbaz

4 - Jana Tower, Juffair — a project by Haqbaz Development

Progress ReviewThe following is the list of work activities executed until 28th February 2017, as per the progress on site.

Activity Floor Status

Gypsum ceiling Lift lobby IN PROGRESS

Marble fixing Lift lobby wall IN PROGRESS

Epoxy painting Staircase, pump room and lift machine room IN PROGRESS

Epoxy painting Parking floor IN PROGRESS

Wall and floor tile Guard room IN PROGRESS

False ceiling works Ground floor IN PROGRESS

Final coat painting in gypsum ceiling 4Th to 20th floor IN PROGRESS

Swimming pool work Pool deck floor IN PROGRESS

Page 5: Monthly Progress Report of February 2017 - Haqbaz

5 - Jana Tower, Juffair — a project by Haqbaz Development

Steel work for jacuzzi in 20th floor

Piping work for jacuzzi in 20th floor

Floor tile fixing in roof deck floor

Steel work for jacuzzi in 20th floor

Piping work for jacuzzi in 20th floor

Floor tile fixing in roof deck floor

Site Snapshot

Page 6: Monthly Progress Report of February 2017 - Haqbaz

6 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Floor tile in 20th floor toilet

Gypsum ceiling painting in 20th floor

Final coat ceiling painting in roof deck floor

Floor tile in pool deck floor toilet

Gypsum ceiling painting in 20th floor

Final coat wall painting in roof deck floor

Page 7: Monthly Progress Report of February 2017 - Haqbaz

7 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

1Stcoat wall painting in 18th floor

Final coat wall painting in rear side elevation

Floortile fixing in 20th floor

1Stcoat wall painting in 19th floor

Final coat wall painting in rear side elevation

Floortile fixing in pool deck floor: (lift lobby)

Page 8: Monthly Progress Report of February 2017 - Haqbaz

8 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Wall tile works in 20th floor toilet

Wall tile works in ground floor toilet

Floor plaster in 20th floor steam room

Wall tile works in pool deck floor toilet

Floortile works in ground floor guard room

Floor plaster in 20th floor jacuzzi room

Page 9: Monthly Progress Report of February 2017 - Haqbaz

9 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Waterproofing in 20th floor steam room

Gypsum ceiling in 20th floor stair lobby

Stair lobby gypsum ceiling painting in 20th floor

Waterproofing in 20th floor jacuzzi room

Gypsum ceiling in pool deck floor stair lobby

Stair lobby gypsum ceiling painting in pool deck floor

Page 10: Monthly Progress Report of February 2017 - Haqbaz

10 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Thermal insulation work in ground floor

Toilet tile ceiling in 20th floor

Toilet gypsum ceiling painting in 20th floor

Gypsum ceiling painting in ground floor

Toilet gypsum ceiling in 20th floor

Toilet gypsum ceiling painting in pool deck floor

Page 11: Monthly Progress Report of February 2017 - Haqbaz

11 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Gypsum ceiling final coat in 19thfloor

Kitchen gypsum ceiling final coat in 19th floor

Aluminum windows glass fixing in left side elevation

Gypsum ceiling final coat in 18thfloor

Kitchen gypsum ceiling final coat in 18th floor

Aluminum windows glass fixing in right side elevation

Page 12: Monthly Progress Report of February 2017 - Haqbaz

12 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Aluminum louver fixing in parking floor

Bedroom door fixing in 13th floor

Lift lobby marble fixing in 17thfloor

Toilet door fixing in 14th floor

Entrance door fixing in 14thfloor

Lift lobby marble fixing in 14thfloor

Page 13: Monthly Progress Report of February 2017 - Haqbaz

13 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Bitumen paint primer apply in roof: (waterproofing)

Granular membrane in roof: (waterproofing)

Waterproofing in pool deck floor

Bituflame membrane in roof: (waterproofing)

Screed concrete poring in 20th floor: (gym room)

Primer work in pump room / water tank room

Page 14: Monthly Progress Report of February 2017 - Haqbaz

14 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Primer work in staircase

Wooden work in suana room

Epoxy painting work in pump room / water tank room

Page 15: Monthly Progress Report of February 2017 - Haqbaz

15 - Jana Tower, Juffair — a project by Haqbaz Development

Front elevation

Site Snapshot

Page 16: Monthly Progress Report of February 2017 - Haqbaz

16 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Left side elevation

Page 17: Monthly Progress Report of February 2017 - Haqbaz

17 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Right side elevation

Page 18: Monthly Progress Report of February 2017 - Haqbaz

18 - Jana Tower, Juffair — a project by Haqbaz Development

Site Snapshot

Rear elevation

Page 19: Monthly Progress Report of February 2017 - Haqbaz