Monroe County Justice Center Sparta, WI AGENDA
THE Louis Berger Group, INC.
4
Monroe County Justice Center Sparta, WI LEGAL/FINANCIAL
A/E Services Contract
THE Louis Berger Group, INC.
5
Design-Bid-Build Delivery Method
Preferred direction
Construction Management CM as Advisor or as GC
Add additional management layer
Design-Build Delivery Method
State Law prohibits
Design-Build Delivery with a Development Group
County doesn't own facility
Monroe County Justice Center Sparta, WI LEGAL/FINANCIAL
Project Delivery Method
THE Louis Berger Group, INC.
6
Monroe County Justice Center Sparta, WI LEGAL/FINANCIAL
Project Delivery Method
LBG MC Contractor
Owners Rep
Requirements
Land
Site
Financing
Project Architect
Design
Engineering
Material/Systems
Superintendent
Materials/Systems
Cost
Construction
Design - Bid - Build Project Delivery Method
Project Goal; organize /consolidate team as quickly as possible to leverage expertise
while competitively bidding project
THE Louis Berger Group, INC.
7
Monroe County Justice Center Sparta, WI LEGAL/FINANCIAL
MCJC Project Representative - Roles/Responsibilities
Skills Knowledge of MC community/players
Understanding of MCJC project
Organize administrative files, coordinate meetings
Ability to communicate/provide status reports
Understanding of project phases
Previous building project experience
The Monroe County Justice Center Liaison Manager acts as Monroe County’s active representative during the design and construction
phase of the project. As such, he/she will act as the Architect’s and General Contractor’s primary point of contact, and Monroe County’s
project oversight manager, ensuring that the interests of Monroe County, the MC Board and MC Building Committee are being met.
Participate in team coordination calls/meetings
Report/attend monthly MC BC meetings
Prepare monthly status report
Maintain project r records/files
Monitor project budget
Act as coordinator for project communications
Coordinate internal team monthly status calls/meetings
On-Going Duties
THE Louis Berger Group, INC.
8
Monroe County Justice Center Sparta, WI LEGAL/FINANCIAL
MCJC Project Representative -Roles/Responsibilities (by phase)
Program Validation/Schematic Design : (2 .5 Months) Full Time Set up administrative filing system
Attend design kick-off meeting
Coordinate Justice Center facility tours
Coordinate user groups program validation meetings
Attend user group program validation meetings
Prepare user group meeting minutes
Document/report user group issues
Coordinate/attend SD review meeting
Consolidate SD review meeting comments
Monitor site survey/geotec report
Coordinate meetings with utilities, etc.
Design Development: (2.5 Months) Half Time Coordinate/attend room data sheet review meetings
Coordinate meetings with MCJC facility staff
Coordinate/attend 50% review meeting
Consolidate 50% review meeting comments
Coordinate meetings with utilities, etc.
Coordinate with agencies
Construction Documentation: (4.5 Months) Half Time Coordinate/attend 75% review meeting
Consolidate 75% review meeting comments
Coordinate division 1 and bidding requirements spec.
Coordinate 100% review, document comments
MCJC Project Rep. Involvement = 24 months +
Bidding/ Negotiations: (2 Months) Half Time Distribute bid documents
Coordinate pre- bid meeting
Prepare/distribute minutes from pre-bid meeting
Coordinate/consolidate questions from bidders
Verify bidder qualifications
Participate in bid opening
Participate in GC selection
Participate in contract negotiations
Construction / Const. Administration : (24 Months) .75 Time Attend progress meetings
Daily site observation
Monthly pay request review
Coordinate/consolidate RFI’s
Coordinate/consolidate submittals/shop drawings
Develop building punch lists
Monitor project close out
Coordinate move-in
THE Louis Berger Group, INC.
9
Monroe County Justice Center Sparta, WI LEGAL/FINANCIAL
Cash Flow Projection
2013
2014
2015
THE Louis Berger Group, INC.
10
Monroe County Justice Center Sparta, WI LEGAL/FINANCIAL
Project Budget Target?
Org.
$ 25M Red. Board Approved
THE Louis Berger Group, INC.
12
LOGISTICS Monroe County Justice Center Sparta, WI
Project Schedule
MILESTONES: MC Board meeting dates, Bldg. Comm. meeting dates, special events, etc.
THE Louis Berger Group, INC.
14
Monroe County Justice Center Sparta, WI
LBG Sub-Consultants Process?
LOGISTICS
Structural
Courtroom layout/technology
Security
THE Louis Berger Group, INC.
16
Monroe County Justice Center Sparta, WI
Updates
PROJECT INFORMATION
911 Dispatch committee
Site Information Development
- Chosen Valley Testing
- Braun Intertec
City of Sparta Action Items
- Street Closing
Participants Involvement - LBG Meetings
- Century Link
- Sparta City Planning
- Xcel Energy
- Fire Department
- Police Department
- Hospital
- Historic Society
- State DOC
- District Courts
Property Acquisitions
THE Louis Berger Group, INC.
18
Program/Budget Validation
Description
The purpose of the program/budget validation phase is to
meet with the four primary building component leaders to
review staff and space forecasts and confirm all of the
key workflow patterns.
Activities
Confirm facility program
Confirm staffing requirements
Confirm critical workflow patterns
Monroe County Justice Center Sparta, WI
“Confirming the direction”
DESIGN ACTIVITY/NEXT STEPS
DD
DESIGN/PRODUCTION
CD B/N Prog. Validation Construction/CA
OCCUPANCY PLANNING
Project Planning Needs Assess. Master Planning Concept SD
DESIGN/PRODUCTION
1 month
THE Louis Berger Group, INC.
19
Schematic Design (SD)
Description
The purpose of the schematic design phase is to develop
a plan of action regarding how a building will look based
on the client's budget and specific design requests. The
architect prepares rough plans, or schematics, that show
a general model of where rooms will be located, the
placement of doors and windows and how the building
will be structured overall.
Schematic design is perhaps the most important time we
spend interacting with clients. At this stage, we have
frequent meetings in order to keep clients abreast of our
work and direction. During these meetings, we present
drawings that describe design ideas with respect to
budget."
Once the owner approves the schematic design the
project moves on to the next phase, design development
Activities
Refine floor plans
Develop room data sheets
Select exterior material palette
Refine exterior design
Update cost estimate
Monroe County Justice Center Sparta, WI
“Bringing the idea into focus”
DESIGN ACTIVITY/NEXT STEPS
DD
DESIGN/PRODUCTION
CD B/N Prog. Validation Construction/CA
OCCUPANCY PLANNING
Project Planning Needs Assess. Master Planning Concept SD
2 months
THE Louis Berger Group, INC.
20
Design Development (DD)
Description
During the design development phase, the
architect expands the schematic designs by
making them more detailed. Floor plans show
rooms in the correct size and shape. A listing of
major materials, room finishes and special
equipment is developed. The architect verifies that
the design complies with building codes and
works with engineers to design the structure,
mechanical and electrical systems.
Once the design is developed thoroughly and
approved by the owner, the next phase begins.
Activities
Finalize all engineering issues such as structural system,
heating and cooling systems, lighting system, etc..
Coordinate with other design consultants, such as
mechanical engineer, acoustical engineer, structural
engineer, landscape architect, etc., on final systems and
design.
Finalize construction techniques and materials.
Finalize equipment requirements, sizes, furniture layout.
Finalize all design issues that affect the look of the building
and the feel of the rooms.
Choose all materials.
Finalize code issues.
Complete outline specifications, a written list of criteria for
materials and building methods.
Revise cost estimate, considering probable labor and
material requirements.
Monroe County Justice Center Sparta, WI
“Detailing the project”
DESIGN ACTIVITY/NEXT STEPS
DD
DESIGN/PRODUCTION
CD B/N Prog. Validation Construction/CA
OCCUPANCY PLANNING
Project Planning Needs Assess. Master Planning Concept SD
2.5 months
THE Louis Berger Group, INC.
21
Construction Documentation (CD)
Description
Once the owner has approved the design development
phase, the architect prepares detailed working drawings
(formerly known as blueprints) and specifications, which
the contractor will use to establish actual construction
costs and build the project.
Activities
Prepare specific and detailed Construction Drawings
required to bid, apply for approval from building and
planning departments, and complete construction. These
may include dimensioned floor plans, elevations, sections,
details, engineering plans such as electrical, mechanical,
structural, and/or civil engineering plans, landscape plans,
final interior design plans, energy report, and written
Specifications that cover all materials, methods of
construction, and construction contract requirements.
Specifications are closely coordinated with construction
drawings.
Continue coordination with consultants. Coordination of
consultants’ Drawings and written Specifications is
essential to avoid conflicts between the various trades
during construction.
Resolve any outstanding building or planning code issues
.
Apply for permit if required.
Monroe County Justice Center Sparta, WI
“ Engineering and detailing the project for construction”
DESIGN ACTIVITY/NEXT STEPS
DD
DESIGN/PRODUCTION
CD B/N Prog. Validation Construction/CA
OCCUPANCY PLANNING
Project Planning Needs Assess. Master Planning Concept SD
4.5 months
THE Louis Berger Group, INC.
22
Bidding / Negotiations
Description
Activities
Monroe County Justice Center Sparta, WI
In this phase, the Construction Documents are sent
out to multiple contractors to obtain a bid, or cost of
the project. This phase is sometimes handled by the
Architect and sometimes by the Owner. Either way,
the drawings are distributed, questions about the
drawings are fielded, the bids are collected and a
contractor is awarded the project.
Review owner's bidding requirements
Contact prospective bidders
Select potential bidders
Distribute bid documents
Conduct pre-bid conference
Conduct pre-bid walk-throughs
Answer questions during bidding
Issue addenda
Conduct bid opening
Analyze bids
Negotiate construction contract
Award contract
DESIGN ACTIVITY/NEXT STEPS
DD
DESIGN/PRODUCTION
CD B/N Prog. Validation Construction/CA
OCCUPANCY PLANNING
Project Planning Needs Assess. Master Planning Concept SD
2 months
THE Louis Berger Group, INC.
23
Construction / Construction Administration (CA)/Commissioning
Description
On-site observation and conscientious
administration of paperwork throughout
construction is necessary to assure that
communication flows smoothly, that high
standards are maintained, and that the client
gets their construction money’s
worth.
Activities
Make periodic site visits while project is under construction,
observing construction for compliance of design intent.
Conduct on-site meetings with contractors, suppliers, client, etc.
Clarify drawings as required.
Answer contractor’s questions.
Complete additional drawings as required.
Process numerous documents and paperwork for contractor’s
payment, changes, submittals from the contractor, etc.
Administrate changes with client and contractor.
Participate in resolution should any disputes arise during
construction.
Review construction and punch list
Close out
Monroe County Justice Center Sparta, WI DESIGN ACTIVITY/NEXT STEPS
DD
DESIGN/PRODUCTION
CD B/N Prog. Validation Construction/CA
OCCUPANCY PLANNING
Project Planning Needs Assess. Master Planning Concept SD
24 months
THE Louis Berger Group, INC.
24
Next Steps: Program/Budget Validation (Feb.)
Monroe County Justice Center Sparta, WI DESIGN ACTIVITY/NEXT STEPS
DD
DESIGN/PRODUCTION
CD B/N Prog. Validation Construction/CA
OCCUPANCY PLANNING
Project Planning Needs Assess. Master Planning Concept SD
DESIGN KICK-OFF
Conduct design kick-off meeting
PROGRAM/BUDGET VALIDATION PREP
Prepare/submit departmental spread sheets for review
Collect/document final site opportunities/constraints plan
Prepare for on-site program validation workshop
Design team travels to MC for on-site departmental workshops
ON-SITE PROGRAM/BUDGET VALIDATION WORKSHOP
Set up design workshop room
Conduct departmental workshops
Refine/ document departmental staff/space requirements
Refine/document floor plans
Submit departmental staff/space requirements for final review
Conduct final program/space plan validation meeting
1 month Feb. 2013