MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Embed Size (px)

Citation preview

Page 1: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

MONDAYMONDAY

1717

MARCH 2003MARCH 2003

Page 2: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Haivan Pass Tunnel Construction ProjectHaivan Pass Tunnel Construction Project

CONSTRUCTION PROGRESS

February 2003

Page 3: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Construction ProgressConstruction ProgressEnd of February 2003

Package Progress (physical)

1A 65%

1B 75%

2A 30%

2B 50%

3 0

4 0

5 55%

6 0

7 100%

Page 4: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Progress of Haivan TunnelProgress of Haivan Tunnel

Tunnel monitoring – End of February 2003

1907.7m (79.12)

1796.6m (75.5%)

2117.6m (54.9%)

2161.7m (56.1%)

1856.3m (97.9%)

Page 5: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Progress of Haivan TunnelProgress of Haivan Tunnel

Package IA – North Tunnel Section

Main tunnel: 3857.0 m, 2 lanes, 89 m2

Evacuation tunnel: 3875.0m, 15.5 m2

Ventilation Adit: 1895.5 m, 36.2 m2

Page 6: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

Main tunnel: 3857.0 mMain tunnel: 3857.0 mEvacuation tunnel: 3857.0 mEvacuation tunnel: 3857.0 mVentilation Adit: 1896.5 mVentilation Adit: 1896.5 m

February 2003

2161.7m (56.1%)

2117.6m (54.9%)

1856.3m (97.9%)

Page 7: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

North Portal area

Page 8: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

Ventilation Adit Portal area

Page 9: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

Explosive charging at main tunnel

Page 10: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

Installation of waterproofing membrane at Main tunnel

Page 11: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

Installation of waterproofing membrane at Main tunnel

Page 12: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

Completed lining concrete at layby No.3 and Vehicular cross passage connection

Page 13: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

Tunnel face drilling at Evacuation tunnel

Page 14: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

Explosive charging at Ventilation tunnel

Page 15: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IA – North Tunnel Section

February 2003

Shotcrete spraying at Electrostatic precipitator

Page 16: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Progress of Haivan TunnelProgress of Haivan Tunnel

Package IB – South Tunnel Section

Main tunnel: 3857.0 m, 2 làn xe, 89 m2

Evacuation tunnel: 3875.0m, 15.5 m2

Page 17: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

Main tunnel: 2380.0 mMain tunnel: 2380.0 mEvacuation tunnel: 2411.0 mEvacuation tunnel: 2411.0 m

February 2003

1796.6m (75.5%)

1907.7m (79.12)

Page 18: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

February 2003

South portal area

Page 19: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

February 2003

Shotcrete for finishing between concrete lining

Page 20: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

February 2003

Installation of water proofing membrane

Page 21: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

February 2003

Concrete lining form No. 2

Page 22: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

February 2003

Placcement of Concrete lining form No. 1

Page 23: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

February 2003

Drilling of Evacuation tunnel

Page 24: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

February 2003

Electrostatic precipitator No. 3

Page 25: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IB - South Tunnel Section

February 2003

North abutment of Bridge No. 1

Page 26: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Progress of Haivan TunnelProgress of Haivan Tunnel

Tunnel monitoring – End of February 2003

1907.7m (79.12)

1796.6m (75.5%)

2117.6m (54.9%)

2161.7m (56.1%)

1856.3m (97.9%)

Page 27: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Package IIA – Lang Co Bridge Section

Lang Co Bridge, 876.390 m total length

Two lane roadway, 782.61m total length

A northern toll plaza

Construction of 187m2 area enclosed car port

Page 28: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

Overall Progress: 30%

• North approach: Road and surcharge fill completed 100%

• Lang Co Bridge: 28%

• Total 182 nos of bored piling completed, remaining 64 nos

• Total 10 girders launched

• South approach: embankment finished up to 1000 m3

Page 29: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

General view of Lang Co view

Page 30: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

Launching girder span No. 25

Page 31: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

Launching girder span No. 26

Page 32: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

Construction of P10

Page 33: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

Construction of P19

Page 34: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

Sight view of P21, P22, P23…

Page 35: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

Completed P24, P25, A2 abutment on site

Page 36: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIA – Lang Co Bridge Section

February 2003

Installation of floating system

Page 37: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Overall Progress: 50%

Bridge No. 2 : 334m, 46%

Bridge No. 3 : 33 m, 50%

Bridge No. 4 : 175 m, 97%

Bridge No. 5 : 133 m, 48%

Bridge No. 6 : 150 m, 47%

Bridge No. 7 : 133 m, 48%

Package IIB – Southern Highway Section

February 2003

Page 38: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIB – Southern Highway Section

February 2003

Bridge No.2: launching spans (A1-P3)

Page 39: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIB – Southern Highway Section

February 2003

Bridge No. 2: Pier P4 - P8

Page 40: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIB – Southern Highway Section

February 2003

Bridge No.4: Completed deck slab view from A1

Page 41: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIB – Southern Highway Section

February 2003

Bridge No.5: Girder casting yard

Page 42: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIB – Southern Highway Section

February 2003

Bridge No.6: Girder casting yard

Page 43: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package IIB – Southern Highway Section

February 2003

Bridge No.7: Abutment A1 under structural backfilling

Page 44: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

Overall progress: 55%

•110/22kV Substation

• Brick work was 90% completed

•110 GIS was delivered on site

• 110kV Transmission Line: 110kV Transmission Line Tower foundation excavation started

Page 45: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

South Portal Area

Package V: 110/22kV Substation and 110kV Transmission Line

Page 46: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110/22kV Substation operation and control center building

Page 47: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110kV GIS delivery on site

Page 48: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

Earthing register measurement for access

Page 49: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110kV Overhead Transmission Line Tower Foundation Excavation

Page 50: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003

ConclusionConclusion

Progress of Project is updated monthly at project’s homepage

http://haivan.cup.com

Consultant Team’s email: [email protected]

Page 51: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003