STHAPATI ARCHITECTS, INTERIOR DESIGNERS ENGINEERS, PROJECT MANAGERS FOLLOW UP OF MOM Project Review Meeting for Construction of KLR Factory, Plot #34, Sector 33, Gurgaon The following is the status of issues brought forth in meeting of 27.12.2013: 1. ELECTRICAL (TRINITRON): Location of various installations was discussed and clarified, based on the discussion; Trinitron will provide shop drawings by 30 th Dec 2013. DECISION: Trinitron will provide the same on priority. Await drawing 2. DATA / VOICE CABLES: Issue discussed, client to arrange meeting with vendor (HP). DECISION: shall discuss in next week. Await meeting 3. SECURITY: Issue discussed, client to arrange meeting with vendor (HP). Await meeting 4. FIRE: Issue discussed, client desires provision of fire detection as per norms, smoke detectors to be provided. Sthapati to do the needful along with the vendor. DECISION: OK Client to identify vendor 5. PIPELINES (SOPAN): Location of various installations was discussed and clarified, based on the discussion; the route of the pipelines was decided, however whether the pipelines are to be provided above false ceiling or below is yet to be confirmed by the client. Sthapati to coordinate and facilitate fixing of saddles for the pipes. OFFICE: 15 ABUL FAZAL ROAD, BENGALI MARKET, NEW DELHI – 110 001 TEL : 43105233, 2335 8400 email : [email protected]

MOM -Follow Up

Embed Size (px)

DESCRIPTION

Minutes of Meeting

Citation preview

Page 1: MOM -Follow Up

STHAPATI ARCHITECTS, INTERIOR DESIGNERS

ENGINEERS, PROJECT MANAGERS

FOLLOW UP OF MOMProject Review Meeting for Construction of KLR Factory, Plot #34, Sector 33, Gurgaon

The following is the status of issues brought forth in meeting of 27.12.2013:1. ELECTRICAL (TRINITRON): Location of various installations was discussed and clarified,

based on the discussion; Trinitron will provide shop drawings by 30th Dec 2013. DECISION: Trinitron will provide the same on priority.Await drawing

2. DATA / VOICE CABLES: Issue discussed, client to arrange meeting with vendor (HP).DECISION: shall discuss in next week.Await meeting

3. SECURITY: Issue discussed, client to arrange meeting with vendor (HP). Await meeting

4. FIRE: Issue discussed, client desires provision of fire detection as per norms, smoke detectors to be provided. Sthapati to do the needful along with the vendor.DECISION: OKClient to identify vendor

5. PIPELINES (SOPAN): Location of various installations was discussed and clarified, based on the discussion; the route of the pipelines was decided, however whether the pipelines are to be provided above false ceiling or below is yet to be confirmed by the client. Sthapati to coordinate and facilitate fixing of saddles for the pipes.DECISION: Below false ceiling is OK for PIPELINES but it should be covered with GYPSUM which looks like a beam & points for opening can be considered.

6. FALSE CEILING: Samples of gypsum false ceiling were shown and handed over; the pros and cons were discussed. Client to decide.DECISION: Gypsum is ok with GI structure on top, having good strength on top.

7. PARTITIONS: Samples of gypsum partition were shown and handed over, the pros and cons vis-à-vis aluminum partition were discussed. The glass in partitions could be toughened. Client to decide.DECISION: Gypsum is OK with GI structure (washable painted) having good strength on which the doors can be operated without hassle & life-long endurance. Instead of toughened glass we can prefer ordinary glass having 8mm thickness—you may also suggest us according for the best.

8. AIR CONDITION: Client was informed about the availability of 3.0 TR split AC machines. Which could be:

OFFICE: 15 ABUL FAZAL ROAD, BENGALI MARKET, NEW DELHI – 110 001 TEL : 43105233, 2335 8400email : [email protected]

Page 2: MOM -Follow Up

STHAPATI ARCHITECTS, INTERIOR DESIGNERS

ENGINEERS, PROJECT MANAGERS

a. Cassette units, approx price 1.10 lacs; b. High wall mounted units, approx. price 0.75 lacs, these are three phase industrial

units with a higher airflow.Both are available by Carrier, Panasonic, and Blue Star. Client to decide.DECISION: 3.0 TR high wall-mounted `Industrial ACs’ to be used. Proposed locations are shown in the drawing.