MINUTES OF MEETING - NO 4Project: Site Development Works for Proposed 110kV Substation at Technocity.Venue: Park Centre, Technopark Project Office.Date : 21.05.2014IN PRESENCE OF
CLIENT M/s TECHNOPARK (TP)Mr. Mahesh Manager ProjectsMr.Sreekesh Asst Manager ProjectsCONSULTANT M/s C R NARAYANA RAO (CRN)Mr.N.Raman Project Manager
The following points were discussed in the meeting are as follows,
SI NO. POINTS DISCUSSED ACTION BY TARGET
DATEREMARKS
1 CRN informed TP all the MOM dated on 24-04-14,07-05-14 and 14-05-14 will be send very soon. CRN 24-05-14
2 CRN informed TP Mr.Sanal chandran- Project engineer will be deputed at site by june1st week. TP asked CRN to submit the credentials of official con-cerned with this project at the earliest.
CRN For Information
Only
3 TP informed CRN that draft MOM should be prepared and forwarded by CRN to Technopark at least within two days after a meeting is held. The MoM has to be signed by representatives of each concern.
CRN For Information
Only
4 TP informed CRN that the MoM of Kick Off meeting has not been finalized. TP further informed that MoM was already prepared by TP and forwarded to CRN a month back.
TP For Information
Only
5 TP informed that all the coconut trees (246nos) and rubber trees (42nos) to be uprooted at Sub Station Site has to be stack properly at various areas.
CRN/Thoppil For Information
Only
6 CRN informed that the filling soil sample to be tested by approved laboratory. Based on the satisfactory of soil report the filling work shall be permitted.
Thoppil For Information
Only
7 TP informed CRN to be meet electrical consultant (TP) viz. Feedback Ventures
CRN For Information
CRN Technopark
- 1 -
TECHNOCITY(WRM: CRN)
to finalize the Level of Substation yard. TP directed CRN to propose on the date when meeting could be held so that TP can get the concurrence for meeting from Feedback Ventures.
Only
8 TP informed CRN that apart from the live/tendered works the following new works proposed at Technocity campus has to be taken up by CRN:
1) 20 Lakh Litre capacity UG sump to constructed without pumping facility
2) One main gate entrance structure to be constructed for Technocity
3) Design inputs to Technopark for one sub way to be constructed across the NH.
CRN For Information
Only
9. TP has gave the provisional approval to CRN to use the existing shed to be used for TC site office.
Thoppil For Information
Only10 TP informed CRN that for quantity
variation refer the clause no 9.7 page no 41 of work order copy.
CRN/Thoppil For Information