ST. TRIZAH CHILDRENS` HOME SCHOOL. QUATATION FOR A CLASSROOM IN THE NEW SITE. QUANTITY NUMBER PRICE @ TOTALS 1. Posts 30pcs @ 300 9,000.00 2. Round poles 60 pcs @250 15,000.00 3. 4 by 2 200feets @50 10,000.00 4. Nails 8kg ”4” 12kg @120 1,440.00 5. Roofing nails 20kg @250 5,000.00 6.nails 3kg “3” @120 1,440.00 7.roofing sheets 3m 60pcs @850 51,000.00 8. wall sheets 2.5 m 40pcs @ 750 30,000.00 9. windows 6 pcs @ 550 33,000.00 10. Doors 1pc @ 8500 8,500.00 11. sand 2lorries @10,000 20,000.00

MOKUA 2(1)

Embed Size (px)

DESCRIPTION

QUOTE

Citation preview

Page 1: MOKUA 2(1)

ST. TRIZAH CHILDRENS` HOME SCHOOL.

QUATATION FOR A CLASSROOM IN THE NEW SITE.

QUANTITY NUMBER PRICE @ TOTALS

1. Posts 30pcs @ 300 9,000.00

2. Round poles 60 pcs @250 15,000.00

3. 4 by 2 200feets @50 10,000.00

4. Nails 8kg ”4” 12kg @120 1,440.00

5. Roofing nails 20kg @250 5,000.00

6.nails 3kg “3” @120 1,440.00

7.roofing sheets 3m 60pcs @850 51,000.00

8. wall sheets 2.5 m 40pcs @ 750 30,000.00

9. windows 6 pcs @ 550 33,000.00

10. Doors 1pc @ 8500 8,500.00

11. sand 2lorries @10,000 20,000.00

12. ballast 2 lorries @ 10,000 20,000.00

13. hardcore 3 lorries @ 10,000 30,000.00

14. cement 50 bags @ 750 37,500.00

15. binding wire 2 rolls @ 1500 3,000.00

16. transportation 10,800 10,800

17. stones 2 lorries @ 15,000.00 30,000.00

18. labour 4000 4000.00

TOTAL COSTS FOR ONE CLASSROOM 355,680 × 2 = 711,360