Financial Year Project Name Project Activity (scope and target area)
Completion Date
Project Cost Status (Indicate whether Complete, Ongoing or Intending to tender
Remarks
2013/2014 Cheberen
Secondary
Construction of a new
classroom
Mar-14 600,000 Complete Funds fully utilized and it
is in use.
2013/2014 Tian Dispensary Completion of the
dispensary and 3
roofed staff
Jun-14 400,000 Complete Funds fully utilized and it
is in use.
2013/2014 Ngemba Moi Ecd Construction of a
classroom
Aug-13 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kamalanget
primary school
completion of a
classroom
Apr-14 450,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kapcheluguny
Primary
Completion of a
classroom
Apr-14 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Oterit Sec school Construction of a
classroom
Apr-14 700,000 Complete Funds fully utilized and it
is in use.
2013/2014 Emining Sec.
School
Construction of a
classroom
Mar-14 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Emining
Empowerment
center
Completion of the
center- fencing
Jun-14 150,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kures community
Borehole
Servicing of the
borehole, installation
of tank and solar
system
Nov-14 1,500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Emining Chiefs
Office
Completion of the
chiefs office-painting
,window glasses,
ceiling board, furniture
Aug-14 150,000 Complete Funds fully utilized and it
is in use.
PROJECT IMPLEMENTATION STATUS AS AT MAY 2016
MOGOTIO NG_CDF
2013/2014 Asenwe ECD completion of a
classroom
Apr-14 400,000 Complete Funds fully utilized and it
is in use.
2013/2014 Sitet Primary Construction of a
classroom
Aug-14 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kamar Chiefs
Office
Completion of the
chiefs office-painting
,window glasses,
ceiling board
Jul-14 200,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kibotany Primary Construction of a new
classroom
Aug-14 600,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kipkitur Primary Ceiling and wiring of
adminstration block
doors
Aug-14 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Koibarak
Secondary
Completion of main
laboratory
Jul-14 600,000 Complete Funds fully utilized and it
is in use.
2013/2014 Muguyuni Primary Completion of a
classrooms .
Jul-14 400,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kamasai Pry.
School
Completion of a
classroom
Aug-14 250,000 Complete The facility is in use
2013/2014 Kapnosgei Primary Construction of a new
classroom
Aug-14 700,000 Complete The facility is in use
2013/2014 kapsiloi pry School Completion of a
classroom
Aug-14 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Embogong Primary Completion of a
classroom
Sep-14 300,000 Complete The facility is in use
2013/2014 Biikwen Gobat
Primary
Construction of a
classroom
Nov-14 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 kimose Dispensary Completion of the
dispensary-roofing,
painting and glazing
Jul-14 500,000 Complete The facility is in use
2013/2014 chemereng Dam Cleaning of the dam by
removing soil
Sep-14 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kimngorom Girls
High School
Completion of
dormitory and teacher
house
Aug-14 1,000,000 Complete The facility is in use
2013/2014 Kapleel Water
Project
Distribution of water to
kimngorom,pipe
connection
Jul-14 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kapterit Kiptuno
Water project
Distribution of water to
kimngorom,pipe
connection
Sep-14 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kisanana
Secondary
Completion of a
classroom
Sep-14 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 kisanana Health
Centre
Completion of
paedriatic ward,
painting, glazing,
flooring and ceiling
Sep-14 400,000 Complete Funds fully utilized and it
is in use.
2013/2014 AIC Majimoto
Sec. School
Construction of ICT
laboratory
May-14 1,600,000 Complete The facility is in use
2013/2014 Maji moto youth
polytechnic
Fencing the school
compound.
Aug-14 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Koibos Chiefs
Office
Completion of the
chiefs office- painting,
ceiling board
Sep-14 200,000 Complete The facility is in use
2013/2014 Koibos Chiefs
Office
Completion of the
chiefs office.
Sep-14 100,000 Complete The facility is in use
2013/2014 Letoi primary
school
Completion of a
classroom
Aug-14 500,000 Complete The facility is in use
2013/2014 Cheptolil dam
water project
Construction of the
dam
Sep-13 645,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kaplelwo
Secondary
Completion of
classrooms
Aug-14 500,000 Complete The facility is in use
2013/2014 Radad Water
Borehole
Purchase of motor and
wiring
Oct-13 150,000 Complete Funds fully utilized and it
is in use.
2013/2014 Sarakwa Cattle
Dip
Completion of the dip,
walling and roofing
Jul-14 436,628 Complete The facility is in use
2013/2014 Aram Primary
School
Construction of a
classroom
Aug-14 500,000 Complete The facility is in use
2013/2014 Chepkokon ECD Construction of two
new classrooms
Aug-14 700,000 Complete Funds fully utilized and it
is in use.
2013/2014 Koitebes chiefs
office
Completion of the
chiefs office- painting,
ceiling board
Aug-15 200,000 Complete The facility is in use
2013/2014 Lolbugo pri.
School
Construction of a
classroom
Sep-14 600,000 Complete The facility is in use
2013/2014 Kiptoim
Dispensary
Completion of the
dispensary-furniture
and painting
Nov-13 200,000 Complete Funds fully utilized and it
is in use.
2013/2014 Sagasagik Sec.
School
Completion of
Administration block
Mar-14 500,000 Complete The facility is in use
2013/2014 Mogotio
Community
primary school
Construction of a new
classrooms
Sep-13 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kaplegich ECD Completion of a
classroom
Aug-14 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kelelwa hill
Primary
Completion of land
payment and
construction of a
classroom
Apr-14 1,000,000 Complete The facility is in use
2013/2014 Reuben Cheruiyot
Sec. School
Completion of
laboratory.
Aug-14 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kipsogon Sec.
School
Completion of
administration block
block
Sep-14 400,000 Complete The facility is in use
2013/2014 Bulioke ECD Completion of a
classroom
Sep-13 300,000 Complete Funds fully utilized and it
is in use.
2013/2014 Molo Sirwe
Primary
Completion of a
classroom
Apr-14 400,000 Complete The facility is in use
2013/2014 Molo Sirwe Sec.
School
Completion of a
dormitory
Aug-13 800,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kipnyung'Uny
Primary
Construction of a
permanent classroom
Jun-14 700,000 Complete The facility is in use
2013/2014 Pombo Pry. School Construction of a
permanent Classroom
Sep-14 700,000 Complete The facility is in use
2013/2014 Ngubereti pry.
School
Completion of staff
house
Aug-14 300,000 Complete The facility is in use
2013/2014 Kaplengnoi Cattle
Dip
Completion of the
cattle dip walling and
roofing
Jul-14 440,000 Complete The facility is in use
2013/2014 Chemalengnet foot
bridge
Construction of the
foot bridge
Mar-15 800,000.00 Complete The facility is in use
2013/2014 Chomiek Primary Completion of two
classrooms
Sep-13 600,000 Complete Funds fully utilized and it
is in use.
2013/2014 Oldebes Secondary Completion of a
laboratory
Sep-13 997,400 Complete Funds fully utilized and it
is in use.
2013/2014 Olkiram Water
supply
Water distribution Aug-13 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kabergei Primary Completion of two
classrooms
Aug-13 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Olkokwe borehole Replacement of worn
out pipes
Sep-13 150,000 Complete Funds fully utilized and it
is in use.
2013/2014 Olkokwe chiefs
office
Completion of the
chiefs office- painting,
ceiling board, furniture
Sep-13 200,000 Complete Funds fully utilized and it
is in use.
2013/2014 Olkokwe Sec.
School
Completion of
classroom.
Aug-13 700,000 Complete Funds fully utilized and it
is in use.
2013/2014 Proposed Ebenezer
primary
Construction of a new
classroom
Aug-13 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Rosoga Chiefs
Office
Completion of the
chiefs office- painting,
ceiling board
Aug-13 180,000 Complete Funds fully utilized and it
is in use.
2013/2014 St. Maximilian
Kolbes Primary
Construction of a
classroom
Aug-13 700,000 Complete Funds fully utilized and it
is in use.
2013/2014 Mugurin Sec.
School
Completion of four
classroom & fencing
Aug-13 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Waseges Pry.
School
Construction of a
permanent classroom
Aug-13 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Nyalilbuch
borehole
Purchase of a water
pump
Sep-13 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Sinende chiefs
office
Completion of the
chiefs office- painting,
ceiling board
Oct-13 300,000 Complete The facility is in use
2013/2014 Waseges
Dispensary
Completion of the
dispensary, doors
fixing,ceiling,plasterin
g and laying of floor
Aug-14 150,000 Complete Funds fully utilized and it
is in use.
2013/2014 Sore Secondary Construction of a
classroom
Aug-14 600,000 Complete Funds fully utilized and it
is in use.
2013/2014 Kaburgei resource
center
Leveling of the field,
construction of hostels
and Library
Aug-14 974,793 95% of the works has
been done so
far.Continuos exercise.
Funds fully utilized
2013/2014 Kapsok Primary Fencing of the school
compound
Aug-14 300,000 Complete Funds fully utilized
2013/2014 Kipkigei Primary Completion of a
classroom and
construction of a
classroom- painting
Aug-13 350,000 Complete Funds fully utilized and it
is in use.
2013/2014 Sirwa Secondary Completion of girls
dormitory
Aug-14 700,000 Complete Funds fully utilized
2013/2014 Sigowo water
project
Survey, Establishment
of water intake and
laying of pipes.
Sep-13 250,000 Complete Funds fully utilized
2013/2014 Kapkole dam Cleaning of the dam by
removing soil
Feb-14 500,000 Complete Funds fully utilized
2013/2014 Kapnosgei water
project
Purchase of sub-
mersible pump and
motor
Mar-14 500,000 Complete Funds fully utilized
2013/2014 Kabuswo - Kiribot
Foot bridge
Completion of the
bridge bridge- 1 beam,
reck support,siderails
Mar-14 1,500,000.00 Complete Funds fully utilized and it
is in use.
2013/2014 Kabuswo Chiefs
Office
Construction of the
chiefs office
Sep-14 500,000 Complete Funds fully utilized and it
is in use.
2013/2014 Office
Administration
To meet office
Administration
expenses.
May-14 2,726,030.00 Complete Funds fully utilized
2013/2014 Monitoring &
Evaluation
Monitoring projects in
the constituency
May-14 863,015.00 Complete Funds fully utilized
2013/2014 Bursary Bursary for needy
students
Aug-13 4,500,000.00 Complete Funds fully utilized
2013/2014 Bursary Bursary for needy
students
Aug-13 11,848,335.00 Complete Funds fully utilized
2013/2014 Emergency To meet contingencies
arising from
uncertainties and
emergencies within the
constituency
May-14 Nil Complete Funds fully utilized
2013/2014 RECCURRENT Recurrent expenses May-14 1,579,778.00 Complete Funds fully utilized
2013/2014 SPORTS Leveling of the field,
construction of hostels
and Library
Sep-14 974,793.31 Complete in levelling Works In Progress 60% of
works has been done.
2013/2014 SPORTS Kaburgei Resource
Centre. Planting of
trees to prevent soil
erosion.
Sep-14 800,000.00 Complete Funds fully utilized
2013/2014 Kamar Primary completion of a
classroom
Aug-14 400,000 Complete Funds fully utilized and it
is in use.
TOTAL 64,515,774
2014/2015 Kapngemui
Primary
Completion of 3
classrooms, plastering
and glazing
Nov-15 450,000 Complete Funds fully utilized and it
is in use.
2014/2015 Tian Pry. School Construction of a new
classroom-600,000
Aug-15 600,000 Complete Funds fully utilized and it
is in use.
2014/2015 Tian Pry. School Completion of a
classroom-plastering
and roofing-200,000
Sep-15 200,000 Complete Funds fully utilized and it
is in use.
2014/2015 Emining Chiefs
Office
Completion of the
chief's office-ceiling
Feb-15 222,350 Complete Funds fully utilized and it
is in use.
2014/2015 Kamalanget
Primary school
construction of a new
classroom.
Sep-16 400,000 50% of the works has
been done so
far.Continuos exercise.
Works In Progress 50% of
works has been done.
2014/2015 Kabogor Primary Construction of a new
classroom
Sep-16 500,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress 60% of
works has been done.
2014/2015 Kabuswo Primary Construction of new
classroom.
Sep-16 400,000 65% of the works has
been done so
far.Continuos exercise.
Works In Progress 65% of
works has been done.
2014/2015 Kiribot Primary Construction of a new
classroom
Sep-16 800,000 80% of the works has
been done so
far.Continuos exercise.
Works In Progress 80% of
works has been done.
2014/2015 Molos Primary Construction of a new
classroom
Sep-16 600,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress 60% of
works has been done.
2014/2015 Lengnane Dam Completion of the dam Jul-14 500,000 Complete Funds fully utilized and it
is in use.
2014/2015 Tingtinyon
Primary
Construction of anew
classroom
Sep-16 600,000 50% of the works has
been done so
far.Continuos exercise.
Works In Progress 50% of
works has been done.
2014/2015 Kibotany Primary Completion of a
classroom-plastering
Sep-15 700,000 Complete Funds fully utilized and it
is in use.
2014/2015 Koibarak
Secondary
Completion of a lab
roofing, plastering
Oct-14 700,000 Complete Funds fully utilized and it
is in use.
2014/2015 Muguyuni Primary Construction of a new
classroom
Sep-16 700,000 80% of the works has
been done so
far.Continuos exercise.
Works In Progress 80% of
works has been done.
2014/2015 Koibarak primary
school
Construction of two
semi-permanent
classrooms.
Aug-14 107,565 Complete Funds fully utilized and it
is in use.
2014/2015 Kipkitur
Dispensary
Shelves, wiring,
electricity connection
and construction of the
gate.
Sep-16 300,000 80% of the works has
been done so
far.Continuos exercise.
Works In Progress 80% of
works has been done.
2014/2015 Kamasai Pry.
School
Construction of a
classroom
Sep-16 600,000 65% of the works has
been done so
far.Continuos exercise.
Works In Progress 65% of
works has been done.
2014/2015 Kapnosgei Primary Construction of a
classroom
Sep-16 600,000 75% of the works has
been done so
far.Continuos exercise.
Works In Progress 75% of
works has been done.
2014/2015 Cheplabot Ecd Transfer of land
ownership from private
owner to the school
Apr-14 100,000 Complete Funds fully utilized
2014/2015 Sosion Pry. School Construction of a
classroom
Sep-16 600,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress 60% of
works has been done.
2014/2015 Chemoinoi
Primary
Construction of a
classroom
Sep-16 700,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress 60% of
works has been done.
2014/2015 Chemoinoi
Dispensary
Completion of health
centre staff houses-
plastering and glazing
Sep-16 200,000 80% of the works has
been done so
far.Continuos exercise.
Works In Progress 80% of
works has been done.
2014/2015 Kimose health
center
Completion of the
health center
Jul-14 100,000 Complete Funds fully utilized and it
is in use.
2014/2015 Kapterit Primary Construction of one
classroom
Aug-15 800,000 Complete Funds fully utilized and it
is in use.
2014/2015 Kimngorom Girls
High School
Purchase of the School
Bus.
Nov-15 5,000,000 Complete Funds fully utilized and
the Bus is in use.
2014/2015 Kisanana
Secondary
Construction of
administration block
Sep-16 500,000 50% of the works has
been done so
far.Continuos exercise.
Works In Progress 50% of
works has been done.
2014/2015 Koisaram Water
Borehole
Drilling of a bore hole N/A 1,000,000 Ongoing Works In Progress 80% of
works has been done.
2014/2015 Koisaram Primary Completion of a
classroom
Aug-14 400,000 Complete Funds fully utilized and it
is in use.
2014/2015 Emsos Primary Completion of the
classroom-plastering
Jul-15 600,000 Complete Funds fully utilized and it
is in use.
2014/2015 Emsos Primary Completion of the
classroom-plastering
Jul-15 140,000 Complete Funds fully utilized and it
is in use.
2014/2015 Majimoto Health
Center
Fencing the facility
with wooden poles and
wire mesh
Sep-14 90,000 Complete Funds well utilized
2014/2015 Siewa Dam Fencing the dam Aug-14 110,000 Complete Funds well utilized
2014/2015 AIC Majimoto
Sec. School
Purchase of School
Bus.
Nov-15 5,000,000 Complete Funds fully utilized and
the Bus is in use.
2014/2015 Chemutung health
center
Construction of health
center
N/A 600,000 70% of the works has
been done so
far.Continuos exercise.
Works In Progress 70% of
works has been done.
2014/2015 Majimoto primary
school
Renovation of two
school dormitories
Aug-14 400,000 Complete Funds well utilized
2014/2015 Majimoto primary
school
Power connection Aug-15 150,000 Complete Funds fully utilized
2014/2015 Emsos dispensary Construction of shelves
and internal fixings
Oct-14 120,000 Complete Funds fully utilized and
Facility is in use.
2014/2015 Mutaran primary
school
Completion of a
classroom-plastering
Apr-15 600,000 Complete Funds fully utilized and it
is in use.
2014/2015 Radad Primary
School
Completion of 2
classroom windows,
glazing and plastering
Aug-14 300,000 Complete Funds fully utilized and
Facility is in use.
2014/2015 Radat primary
school
Completion of three
door toilets
Aug-14 325,000 Complete Funds fully utilized and
Facility is in use.
2014/2015 Kwirindoche
primary school
Construction of a
classroom.
Sep-16 600,000 65% of the works has
been done so
far.Continuos exercise.
Works In Progress 65% of
works has been done.
2014/2015 Kiskis primary
school
Construction of a
classroom.
Sep-16 600,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress 60% of
works has been done.
2014/2015 Radad Secondary
School
Construction of three
door toilet.
Sep-16 300,000 80% of the works has
been done so
far.Continuos exercise.
Works In Progress 80% of
works has been done.
2014/2015 Kaplelwo
Secondary
Completion of a new
classroom
Aug-15 300,000 Complete Funds fully utilized and it
is in use.
2014/2015 Koitebes chiefs
office
Plastering,glazing,wind
ows,ceilling
Jul-15 300,000 Complete Funds fully utilized and it
is in use.
2014/2015 Matebei Primary Completion of a
classroom.
Augt 2015 300,000 50% of the works has
been done so
far.Continuos exercise.
Works In Progress 50% of
works has been done.
2014/2015 Koitebes Sec.
School
Plastering,glazing,wind
ows
Aug-14 400,000 Complete Funds fully utilized and it
is in use.
2014/2015 Equator Suswo Soi
Water Project
Drilling of the borehole Sep-15 900,000 Complete Funds fully utilized and it
is in use.
2014/2015 Sagasagik Pry.
School
Construction of a
classroom
Augt 2014 600,000 70% of the works has
been done so
far.Continuos exercise.
Works In Progress 70% of
works has been done.
2014/2015 Sagasagik Pry.
School
Renovation of
classrooms
Nov-15 400,000 85% of the works has
been done so
far.Continuos exercise.
Works In Progress 85% of
works has been done.
2014/2015 Lombogishu Sec.
School
Completion of two
classrooms
Sep-15 600,000 Complete Funds fully utilized and it
is in use.
2014/2015 Lombogishu
Primary School
Renovation of
classrooms-plastering,
painting and dooring.
Aug-14 337,932 Complete Funds fully utilized and it
is in use.
2014/2015 Kelelwa Primary Construction of a toilet Jul-15 300,000 Complete Funds fully utilized and it
is in use.
2014/2015 Logiri Primary Construction of a new
classroom
Aug-15 500,000 65% of the works has
been done so
far.Continuos exercise.
Works In Progress needs
more funds to complete
2014/2015 Lomanira Primary Completion of a
classroom
May-15 300,000 Complete Funds fully utilized and it
is in use.
2014/2015 Ngusero Primary Construction of a new
classroom and semi-
permanent
Administration block.
Aug-15 300,000 50% of the works has
been done so
far.Continuos exercise.
Works In Progress needs
more funds to complete
2014/2015 Mogotio Girls
High
Construction of a new
dormitory
Sep-15 800,000 20% of the works has
been done so
far.Continuos exercise.
Works In Progress needs
more funds to complete
2014/2015 Noiwet Day And
Boarding Primary
Renovation of 6
classrooms-plastering
Aug-15 650,000 Complete Funds fully utilized and it
is in use.
2014/2015 Reuben Cheruiyot
Sec. School
Construction of
staffroom/administratio
n block.
Sep-15 500,000 Complete Funds fully utilized and it
is in use.
2014/2015 Mogotio Youth
Polytechnic
Completion of
dormitory
Nov-15 500,000 Complete Funds fully utilized and it
is in use.
2014/2015 Olduka Cattle dip Construction of a new
Cattle Dip
Sep-14 700,000 65% of the works has
been done so
far.Continuos exercise.
Works In Progress needs
more funds
2014/2015 Molo Sirwe
Primary
Construction of new
toilet
Apr-15 100,000 Complete Funds fully utilized and it
is in use.
2014/2015 Molo Sirwe Sec.
School
Construction of new
girls dormitory
Aug-15 2,000,000 50% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Chebarer cattle dip Construction of a new
cattle dip
Jun-15 760,000 Complete Funds fully utilized and it
is in use.
2014/2015 Chebarer primary
school
Purchase of land and
construction of
classroom
May-15 700,000 Complete Funds fully utilized and it
is in use.
2014/2015 Kipnyung'Uny
Primary
Completion of a
classroom-plastering
Aug-15 400,000 Complete Funds fully utilized and it
is in use.
2014/2015 Kitecho primary Construction of a new
classroom
Nov-15 600,000 Complete Funds fully utilized and it
is in use.
2014/2015 Ng'endalel
borehole
Water distribution Sep-15 600,000 Complete Funds fully utilized and it
is in use.
2014/2015 Ng'endalel
borehole
Installation of solar
panel system to assist
in pumping water
Oct-15 2,000,000 75% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Ngubereti Day
Secondary
Completion of a
laboratory
Aug-15 300,000 Complete Funds fully utilized and it
is in use.
2014/2015 Ngubereti Water
Project
Purchase of land 1/4
acre
Jun-15 150,000 Complete Funds fully utilized and it
is in use.
2014/2015 Ngubereti Water
Project
Construction of a water
tank.
Jun-15 850,000 Complete Funds fully utilized and it
is in use.
2014/2015 Oldebes Water
Project
Purchase of pipes for
water
Sep-15 400,000 85% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Chomiek Water
project
Construction of 50m3
water tank.
Sep-15 500,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Oldebes Primary Completion of seven
classrooms-plastering
Aug-15 600,000 Complete Funds fully utilized and it
is in use.
2014/2015 Kabergei Primary Completion of
classroom-plastering
Aug-15 250,000 Complete Funds fully utilized and it
is in use.
2014/2015 Olkokwe Sec.
School
Construction of a
classroom
Oct-15 700,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Olkokwe Sec.
School
Wiring & Electricity
connection
Aug-15 150,000 Complete Funds fully utilized and it
is in use.
2014/2015 Rosoga Chiefs
Office
Completion of the
chiefs office- Window
glazing.
May-15 300,000 Complete Funds fully utilized and it
is in use.
2014/2015 Kures Primary Construction of new
classroom.
Oct-15 500,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Rosoga secondary Construction of dining
hall
Nov-15 500,000 40% of the works has
been done so
far.Continuos exercise.
Works In Progress needs
more funds to complete
2014/2015 Kapkundul
Primary
Construction of a new
classroom
Jul-15 800,000 Complete Funds fully utilized and it
is in use.
2014/2015 Kibulwe primary
school
Purchase of land. Feb-15 500,000 Complete Funds fully utilized.
2014/2015 Kibulwe primary
school
Construction of a
permanent classroom
Oct-15 500,000 50% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Nyalilbuch
Primary
Construction of a
permanent classroom
Oct-15 700,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Sinende Secondary Construction of a new
classroom
Oct-15 700,000 70% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Sore Secondary Completion of three
classrooms plastering
Oct-15 900,000 80% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Kapkein Primary Completion of a
classroom-plastering,
glazing.
Oct-15 300,000 75% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 sigowo water
project
Purchase and laying
down pipes along the
water lines
Sep-15 250,000 Complete Funds fully utilized and it
is in use.
2014/2015 Beche bono water
project
Establishment and
extension of weir
Mar-15 150,000 Complete Funds fully utilized and it
is in use.
2014/2015 Sirwa Secondary Construction of two
classrooms &
staffroom
May-16 2,000,000 60% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Sirwa Health
Center
Construction of
medical laboratory
Sep-15 500,000 80% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 Molos Dispensary Completion
plastering,windows,ceil
ling,doors
Jun-15 500,000 Complete Funds fully utilized and it
is in use.
2014/2015 CDF Office Completion of CDF
office-79000 fencing
Sep-14 229,000 Complete Funds fully utilized and it
is in use.
2014/2015 CDF Motor
Vehicle-Land
cruiser/Land Rover
Purchase of CDF
motor Vehicle
Sep-15 6,000,000.00 Complete Funds fully utilized and
Vehicle is in use.
2014/2015 Office
Administration
Payment of staff
salaries(shs.1,000,000)
Jun-15 1,236,000.00 Complete Funds fully utilized.
2014/2015 Office
Administration
Purchase of
photocopiers, staplers
Continuos
exercise
200,000.00 Ongoing Works In Progress
2014/2015 Office
Administration
Purchase of CDF 2
computers
Continuos
exercise
300,000.00 Ongoing Works In Progress
2014/2015 Office
Administration
Purchase of fuel,
repairs and
maintenance,printing,st
ationery,telephone,trav
el and subsistence
Jun-15 1,500,000.00 Complete Funds fully utilized.
2014/2015 Office
Administration
Payment of NSSF
Deductions
Jun-15 50,000.00 Complete Funds fully utilized.
2014/2015 Office
Administration
Payment of committee
sitting
allowances,transport,co
nferences
Jun-15 1,907,493.78 Complete Funds fully utilized.
2014/2015 Monitoring &
Evaluation
Purchase of fuel,
repairs and
maintenance,printing,st
ationery,Airtime,
Jun-15 500,000.00 Complete Funds fully utilized.
2014/2015 Monitoring &
Evaluation
Payment of committee
sitting
allowance,transport,co
nferences
Jun-15 1,735,788.28 Complete Funds fully utilized.
2014/2015 Monitoring &
Evaluation
Undertake Training of
the PMCs/CDFCs on
CDF Related issues
Jun-15 607,958.61 Complete Funds fully utilized.
2014/2015 Constituency Audit Constituency Audit Continuos
exercise
500,000.00 awaiting CDF Board
guideline
undisbursed funds
2014/2015 Bursary Tertiary
Schools
Payment of Bursary to
needy students
Jan-15 8,284,817.53 Complete Funds fully utilized.
2014/2015 Bursary Tertiary
Schools
Payment of Bursary to
needy students
Jan-15 4,000,000.00 Complete Funds fully utilized.
2014/2015 Mocks/CATs Printing and
distributions
Jan-15 1,000,000.00 Complete Funds fully utilized.
2014/2015 Emergency To cater for any
unforeseen occurrences
in the constituency
Continuos
exercise
2,529,819.00 Ongoing undisbursed funds
2014/2015 EMERGENCY Kimngorom girls
secondary construction
of girls dormitory
May-16 1,000,000.00 Ongoing Funded by emergency funds
2014/2015 EMERGENCY Rosoga secondary
school construction of
dining hall
Apr-16 500,000.00 Ongoing Funded by emergency funds
2014/2015 EMERGENCY Rosoga primary school
renovation of
classroom
Jun-15 350,000.00 Complete Funds fully utilized and it
is in use.
2014/2015 EMERGENCY Kabarbaya dam
embankment/gabions
Sep-15 200,000.00 Complete Funds fully utilized and it
is in use.
2014/2015 EMERGENCY Tian primary school
construction of toilets
Sep-15 167,000.00 Complete Funds fully utilized and it
is in use.
2014/2015 EMERGENCY Kabergei primary
school roofing of
classroom blown by
wind.
Jul-15 125,000.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Aram primary school
construction of toilets
Aug-15 200,000.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Chemorgong primary
school construction of
toilets
Aug-15 200,000.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Sirwa secondary school
construction of girls
toilets and bathrooms
Aug-15 400,000.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Tung tung-chepnes
foot bridge
construction
Jun-16 800,000.00 50% of the works has
been done so
far.Continuos exercise.
Works In Progress
2014/2015 EMERGENCY Sagasagik pry.
School(Roofing of
classrooms blown-off
by wind.)
Aug-15 141,200.00 Complete Funds fully utilized and it
is in use.
2014/2015 EMERGENCY Kimose pry.
School(Roofing of
classrooms blown-off
by wind.)
Jul-15 120,020.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Kaplelwo pry.
School(One
classroom.)
Jul-15 423,600.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Kapyemit pry.
School(Roofing of
classrooms blown -off
by wind.)
Jul-15 123,550.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Kenet ECD(Land
buying-to be funded by
emergency).
May-15 200,000.00 Complete Funds fully utilized.
2014/2015 EMERGENCY Kaburgei pry.
School(Construction of
teachers latrines.)
Aug-14 63,540.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Kisanana girls
Sec.School(Buying of
land.)
Sep-14 70,600.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Mogotio constituency
Boda Boda Sheds-
Mogotio
Centre(Construction of
Boda Boda Shed.)
Oct-15 35,300.00 Complete Funded by emergency funds
and it is in use
2014/2015 SPORTS Mogotio constituency
Boda Boda Sheds-
Mogotio Centre and
Noiwet
Centre(Construction of
Boda Boda Shed.)
Nov-15 100,000.00 Ongoing Works In Progress
2014/2015 EMERGENCY Mogotio Health
Centre(Ambulance
Servicing.)
Jun-14 21,180.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Mogotio Constituency
Boda Boda Sheds-
Noiwet
Centre(Construction of
Boda Boda Shed.)
Jun-16 21,180.00 Ongoing Works In Progress-requires
additional funding
2014/2015 EMERGENCY Chebarer Pry.
School(Fencing of the
compound.)
Sep-15 127,080.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Ngubereti
Borehole(Renovation
and Rehabilitation of
the Borehole.)
Oct-14 70,600.00 Complete Funded by emergency funds
and it is in use
2014/2015 EMERGENCY Koisaram Pry.
School(Renovation and
Completion
Augt 2014 10,590.00 Complete Funded by emergency funds
and it is in use
2014/2015 Constituency
Sports
Tournament.
Carry out Constituency
Sports tournament and
the winning
teams/schools to be
awarded with trophies,
balls and games kits-
Kaburgei resource
centre-
shs.300,000:sports
development.
Continuos
exercise
1,138,690.60 Ongoing Works In Progress
2014/2015 SPORTS To support activities in
the
constituency(tourname
nts and music).
Continuos
exercise
200,000.00 Ongoing Works In Progress
2014/2015 MOGOTIO
CONSTITUENCY
.
Planting of trees to
prevent soil erosion in
the constituency.
Mar-14 338,698.00 Complete Funds fully utilized.
TOTAL 94,891,553.00
2015/2016 EMERGENCY
(5%)
To Cater for emergencies
that may occur within the
constituency during the
year
Continuos
exercise
2,407,647.00 Ongoing undisbursed emergency
funds
2015/2016 Motomisie water pan dam excavation Mar-16 500,000.00 Ongoing Funded by emergency funds
2015/2016 Emining sec school construction of one
classroomMar-16 300,000.00 Ongoing Funded by emergency funds
2015/2016 Kiptoim sec school 2 classrooms Mar-16 300,000.00 Ongoing Funded by emergency funds
2015/2016 Kaplelwo sec school one classroom Mar-16 300,000.00 Ongoing Funded by emergency funds
2015/2016 Kiptulwe water pan purchase 3 acre land Mar-16 300,000.00 Ongoing Funded by emergency funds
2015/2016 Maranbei water pan purchase 5 acre land Mar-16 1,500,000.00 Ongoing Funded by emergency funds
2015/2016 Mogotio sub-county
water and expansion
project
water piping Mar-16 60,000.00 Ongoing Funded by emergency funds
2015/2016 Mogotio constituecy
bodaboda sheds-
noiwett
construction of bodaboda
shedMar-16 100,000.00 Ongoing Funded by emergency funds
2015/2016 Employees
Salaries
Payment of staff
salaries and gratuity
Continuos
exercise
1,632,300.00 Ongoing Works In Progress
2015/2016 Goods and Services Purchase of fuel, repairs
and maintenance,
printing, stationery,
telephone, travel and
subsistence, office tea,
etc.
Continuos
exercise
1,232,000.00 Ongoing Works In Progress
2015/2016 Purchase of
Computers
Purchase of CDF
computers,Printers and
shredders
Continuos
exercise
673,004.00 Ongoing Works In Progress
2015/2016 Purchase of
Furniture/equipment
s
Purchase of
photocopiers, staplers
,office tables,chairs
Continuos
exercise
704,630.00 Ongoing Works In Progress
2015/2016 NSSF Payment of NSSF
DeductionsContinuos
exercise
50,000.00 Ongoing Works In Progress
2015/2016 NHIF Payment of NHIF
DeductionsContinuos
exercise
67,200.00 Ongoing Works In Progress
2015/2016 Committee Expenses Payment of Committee
sitting allowances,
transport, conferences
Continuos
exercise
1,668,000.00 Ongoing Works In Progress
2015/2016 SPORTS
ACTIVITIES (2%)
Carryout constituency
sports tournaments Continuos
exercise
1,500,000.00 Ongoing Works In Progress
2015/2016 Goods and Services Purchase of fuel, repairs
and maintenance,
printing, stationery,
Airtime, travel and
subsistence, e.t.c
Continuos
exercise
300,000.00 Ongoing Works In Progress
2015/2016 Committee Expenses Payment of Committee
sitting allowances,
transport, conferences
Continuos
exercise
1,213,017.00 Ongoing Works In Progress
2015/2016 CDFC/PMC
Capacity Building
Undertake Training of
the PMCs/CDFCs on
CDF Related issues
Continuos
exercise
1,500,550.00 Ongoing Works In Progress
2015/2016 ENVIRONMENTA
L ACTIVITIES
(2%)
Planting of trees to
prevent soil erosionContinuos
exercise
500,000 Ongoing Works In Progress
2015/2016 Bursary Secondary
Schools
Payment of bursary to
needy student
Continuos
exercise
10,543,887.00 Ongoing Works In Progress
2015/2016 Bursary Tertiary
Schools
Payment of bursary to
needy student
Continuos
exercise
5,000,000.00 Ongoing Works In Progress
2015/2016 Mocks/CATs Printing and
distribution of Mocks
and CATs
Continuos
exercise
1,000,000.00 Ongoing Works In Progress
2015/2016 Kures primary
school
completion of two
classrooms-Plastering
and finishings
Sep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Ebenezar primary
school
completion of classroom
& toilet constructionApr-16 400,000.00 Ongoing Works In Progress
2015/2016 Lombala primary
school
Construction of new 4-
door latrine blockSep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Rosoga primary
school
construction of girls
latrinesSep-16 150,000.00 NEW Yet to receive the funds
2015/2016 Kipsogon primary
school
construction of one new
classroomApr-16 500,000.00 Ongoing Works In Progress
2015/2016 kelelwa hill primary
school
completion of
2classrooms-plastering
and flooring
Apr-16 500,000.00 Ongoing Works In Progress
2015/2016 Ngusero primary
school
completion of
3classrooms-
plastering,flooring and
paintworks
Apr-16 500,000.00 Ongoing Works In Progress
2015/2016 Kiskis Primary
School
construction of a new
latrine blockSep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Kaplelwo Primary
School
completion of 4
classrooms-
plastering,flooring and
roofing
Apr-16 600,000.00 Ongoing Works In Progress
2015/2016 Molok Primary
School
Completion of girls
dormitory-
plastering,paintworks
and partitioning
Sep-16 400,000.00 NEW Yet to receive the funds
2015/2016 Letoi Primary
School
completion of 4
classrooms-
plastering,painting and
flooring
Apr-16 400,000.00 Ongoing Works In Progress
2015/2016 Radad Primary
School
construction of two new
latrine blocks for both
boys & girls
Sep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Matebei Primary
School
construction of one new
classroom(kshs.400,000/
and renovation of
classrooms-
kshs.100,000/
Sep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Chepkokon Primary
School
completion of two
classrooms-
plastering,roofing,floorin
g and fencing
Apr-16 700,000.00 Ongoing Works In Progress
2015/2016 Aram Primary
School
completion of
2classrooms-
plastering,flooring and
roofing
Sep-16 400,000.00 NEW Yet to receive the funds
2015/2016 Koitebes Primary
School
completion of the
administration block-
plastering and finishings
Sep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Kapterit Primary
School
Construction of a new
classroom Sep-16 600,000.00 NEW Yet to receive the funds
2015/2016 Kimngorom day &
boarding Primary
School
Construction of a new
classroom Sep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Sore Primary School Completion of
2classrooms-plastering
and paintworks
May-16 400,000.00 Ongoing Works In Progress
2015/2016 Kipkigei Primary
School
completion of two
classrooms-
plastering,flooring,paint
works and finishing
Sep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Kaplaimoi Primary
School
Construction of 1
classroom (ICT)Sep-16 700,000.00 NEW Yet to receive the funds
2015/2016 Kapsok Primary
School
Construction of one new
classroom Sep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Chemorgong
Primary School
Completion of
2classrooms-plastering
and finishings
Sep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Kaburgei Primary
School
Construction of
staffroom (prefabricated
)
May-16 200,000.00 Ongoing Works In Progress
2015/2016 Sirwa Primary
School
construction of ICT
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Sagasagik Primary
School
Construction of one new
latrine blockSep-16 150,000.00 NEW Yet to receive the funds
2015/2016 Lolbugo primary
school
construction of one new
classroomApr-16 500,000.00 Ongoing Works In Progress
2015/2016 Esageri school for
the deaf
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Kiptoim primary
school
Completion and
Renovation of
classrooms-
plastering,flooring and
roofing
Sep-16 200,000.00 NEW Yet to receive the funds
2015/2016 A.I.C Esageri day
boarding primary
school
Construction of dining
hallSep-16 600,000.00 NEW Yet to receive the funds
2015/2016 Ainopsos Primary
School
completion of one
classroom-plastering and
paintworks
Sep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Kaplogos Primary
School
completion of two
classrooms-
plastering,flooriong and
paintworks
Sep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Ngentui Primary
School
construction of
administration blockSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Kapngemui Primary
School
construction of one new
classroomSep-16 600,000.00 NEW Yet to receive the funds
2015/2016 Oterit Primary
School
Completion of of
administration block and
3 classrooms-plastering
and paintworks
Awaiting for
funds
300,000.00 NEW Yet to receive the funds
2015/2016 Nato Primary School completion of two
classrooms-
plastering,flooring and
painting
Sep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Kamalanget Primary
School
completion of two
classrooms-
plastering,flooring and
painting
Sep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Kapcheluguny
Primary School
completion of two
classrooms-
flooring,painting,fixing
doors and windows
Sep-16 400,000.00 NEW Yet to receive the funds
2015/2016 Emining Primary
School
completion of two
classrooms-
plastering,flooring and
painting
Sep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Sorti Primary School Construction of one new
classroomsSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Emining Divisional
Education Office
Renovation of office
verandah and roofingSep-16 100,000.00 NEW Yet to receive the funds
2015/2016 Kimose Primary
School
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Sosion Primary
School
completion of the 2
classrooms-
plastering,flooring and
painting
Apr-16 300,000.00 Ongoing Works In Progress
2015/2016 Maji Motto Primary
School
fencing the school
compoundSep-16 100,000.00 NEW Yet to receive the funds
2015/2016 Kapyemit Primary
School
Construction of one new
classroom Sep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Kaplegich Primary
School
Construction of one new
classroom Sep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Sitet Primary School Completion of one
classroom -flooring and
plastering
Sep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Chebarer Primary
School
Construction of one new
classroom Sep-16 600,000.00 NEW Yet to receive the funds
2015/2016 Chepyuan Primary
School
construction of one new
classroomsSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Magoi Primary
School
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Molo-Sirwe Primary
School
construction of 2 new
classroomsSep-16 850,000.00 NEW Yet to receive the funds
2015/2016 Kapkundul Primary
School
construction of one new
a classroom Sep-16 700,000.00 NEW Yet to receive the funds
2015/2016 Ngendalel Primary
School
completion of one
classroom-flooring and
plastering
Sep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Kabergei Primary
School
completion of 2
classrooms-flooring and
plastering
Sep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Kabuswo primary
school
construction of boys
dormitorySep-16 800,000.00 NEW Yet to receive the funds
2015/2016 Kamasai primary
school
construction of one new
classroomSep-16 600,000.00 NEW Yet to receive the funds
2015/2016 Kamasai primary
school
construction of teachers
house-prefabricatedSep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Chebirebei primary
school
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Waseges primary
school
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Kamar primary
school
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Molos primary
school
Completion of one new
classroomsSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Kisanana primary
school
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Koisaram primary
school
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Chomiek Primary
School
purchase of 6 acres land
for expansionApr-16 650,000.00 Ongoing Works In Progress
2015/2016 Oldebes Primary
School
construction of boys
toiletsSep-16 100,000.00 NEW Yet to receive the funds
2015/2016 Pombo primary
school
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Kipnyuguny primary
school
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 kipkitur primary
school
construction of one new
classroomSep-16 600,000.00 NEW Yet to receive the funds
2015/2016 Koibarak primary
school
construction of one new
classroomSep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Chomiek primary
school
Construction of teachers
latrine block-
kshs.100,000/ and
completion of
2classrooms-plastering
and flooring-
kshs.200,000/
Sep-16 300,000.00 NEW Yet to receive the funds
2015/2016 Rosoga Secondary
School
construction of
laboratory-plastering and
flooring
Apr-16 800,000.00 Ongoing Works In Progress
2015/2016 Kipsogon Secondary
School
completion of
4classrooms-
plastering,flooring and
oaintworks
Sep-16 200,000.00 NEW Yet to receive the funds
2015/2016 Mogotio Girls
Secondary School
Completion of girls
dormitory-walling and
roofing
Sep-16 500,000.00 NEW Yet to receive the funds
2015/2016 Proposed Mogotio
Day Secondary
School
Proposed 4 classroom Sep-16 1,200,000.00 New (NOT
APPROVED)
conditional approval
2015/2016 Kaplelwo Secondary
School
replacement of roofs
blown by windSep-16 50,000.00 New Yet to receive the funds
2015/2016 Radad Secondary
School
construction of
laboratory Sep-16 600,000.00 New Yet to receive the funds
2015/2016 Ngubereti Day
Secondary School
construction of one new
classroomSep-16 500,000.00 New Yet to receive the funds
2015/2016 Kimngorom Girls
Secondary School
completion of dormitory-
walling and roofingApr-16 800,000.00 ongoing Works In Progress
2015/2016 Kimngorom Girls
Secondary School
Construction of
laboratory-Sep-16 1,500,000.00 New Yet to receive the funds
2015/2016 Sirwa Secondary
School
construction of
laboratory-kshs.750,000/
& staff house-
kshs.800,000
May-16 1,550,000.00 ongoing Works In Progress
2015/2016 Sore Secondary
School
construction of science
laboratorySep-16 800,000.00 New Yet to receive the funds
2015/2016 Kiptoim Secondary
School
purchase of school bus May-16 5,000,000.00 ongoing Works In Progress
2015/2016 Sagasagik
Secondary School
completion of
classrooms-flooring and
plastering-kshs.350,000/
and construction of a
laboratory.-kshs.500,000/
May-16 850,000.00 Ongoing Works In Progress
2015/2016 Lombogishu
Secondary School
construction of new
laboratory-kshs.800,000/
and completion of
classrooms-plastering
and flooring-
kshs.200,000/
Apr-16 1,000,000.00 Ongoing Works In Progress
2015/2016 Cheberen Secondary
School
completion of one
classroomSep-16 200,000.00 New Yet to receive the funds
2015/2016 Cheberen Secondary
School
construction of one new
classroomSep-16 500,000.00 New Yet to receive the funds
2015/2016 Oterit Secondary
School
construction of 3 new
classroomsMay-16 2,000,000.00 Ongoing Works In Progress
2015/2016 Kimose Secondary
School
Equipping girls
dormitory with bedsMay-16 500,000.00 Ongoing Works In Progress
2015/2016 A.I.C Maji-Motto
Secondary School
construction of one new
classroom May-16 500,000.00 ongoing Works In Progress
2015/2016 A.I.C Maji-Motto
Secondary School
completion of 3
classrooms-
plastering,flooring and
paintworks
May-16 600,000.00 Ongoing Works In Progress
2015/2016 Molo-Sirwe
Secondary School
Completion of dormitory-
plastering,flooring and
finishings
May-16 500,000.00 ongoing Works In Progress
2015/2016 Molo-Sirwe
Secondary School
construction of one new
classroomSep-16 500,000.00 New Yet to receive the funds
2015/2016 Mugurin Secondary
School
construction of
laboratorySep-16 800,000.00 New Yet to receive the funds
2015/2016 Olkokwe Secondary
School
construction of one new
classroomSep-16 500,000.00 New Yet to receive the funds
2015/2016 Sinende Secondary
School
construction of one new
classroomsSep-16 600,000.00 New Yet to receive the funds
2015/2016 kisanana secondary
school
purchase of school bus May-16 5,000,000.00 ongoing Works In Progress
2015/2016 A.I.C kisanana
Totona girls
secondary school
purchase of land May-16 800,000.00 ongoing Works In Progress
2015/2016 Oldebes Secondary
School
completion of laboratory-
flooring and plasteringSep-16 800,000.00 New Yet to receive the funds
2015/2016 Koibarak Secondary
School
Construction of girls
dormitorySep-16 700,000.00 New Yet to receive the funds
2015/2016 Rosoga Chiefs
Office
construction of latrines Sep-16 200,000.00 New Yet to receive the funds
2015/2016 Mogotio Chiefs
Office (ACC)
Renovation of the office-
flooring,plastering and
paintworks
Sep-16 200,000.00 New Yet to receive the funds
2015/2016 Koibos Soi Chiefs
Office
construction of chiefs
officeSep-16 500,000.00 New Yet to receive the funds
2015/2016 Ngubereti Chiefs
Office
construction of the office Sep-16 500,000.00 New Yet to receive the funds
2015/2016 Koitebes Chiefs
Office
completion of the office-
plastering and
paintworks and fencing
Sep-16 200,000.00 New Yet to receive the funds
2015/2016 Kimngorom Chiefs
Office
completion of the office-
plastering, flooring and
painting
Sep-16 200,000.00 New Yet to receive the funds
2015/2016 Cheberen Chiefs
Office
construction of chiefs
office-Sep-16 500,000.00 New Yet to receive the funds
2015/2016 Emining Chiefs
Office
fencing and wiring the
officeSep-16 200,000.00 New Yet to receive the funds
2015/2016 Koibos Chiefs
Office
Completion of the office
block flooring and
plastering
Sep-16 250,000.00 New Yet to receive the funds
2015/2016 Molo-Sirwe Chiefs
Office
construction of chiefs
officeSep-16 500,000.00 New Yet to receive the funds
2015/2016 Simotwe Chiefs
Office
construction of chiefs
officeSep-16 500,000.00 New Yet to receive the funds
2015/2016 Olkokwe Police
Post
construction of police
post officeSep-16 500,000.00 New Yet to receive the funds
2015/2016 Kabuswo Chiefs
Office
completion of chiefs
office -flooring and
plastering
Sep-16 200,000.00 New Yet to receive the funds
2015/2016 Kapnosgei Chiefs
Office
construction of a latrine
blockSep-16 100,000.00 New Yet to receive the funds
2015/2016 Sinende Chiefs
Office
completion of the office-
flooring and plasteringSep-16 400,000.00 New Yet to receive the funds
2015/2016 Chebirebei Assistant
Chiefs Office
construction of the
Ass.chiefs office-
prefabricated
Sep-16 200,000.00 New Yet to receive the funds
2015/2016 Molos Assistant
Chiefs Office
construction of the office-
prefabricatedSep-16 200,000.00 New Yet to receive the funds
2015/2016 Ngendalel Chiefs
Office
completion of the office -
flooring and plasteringSep-16 200,000.00 New Yet to receive the funds
2015/2016 Mugurin Dispensary electrification Sep-16 300,000.00 New Yet to receive the funds
2015/2016 Olkokwe Health
Centre
installation of electricity Sep-16 100,000.00 New Yet to receive the funds
2015/2016 Proposed Oterit
Dispensary
Purchase of land-4 acres Sep-16 400,000.00 New Yet to receive the funds
2015/2016 Chepngerechi Water
dam
Purchase of 2acres land Sep-16 300,000.00 New Yet to receive the funds
2015/2016 Kapnosgei Borehole purchase of submersible
pump for pumping waterSep-16 350,000.00 New Yet to receive the funds
2015/2016 Ainopkor Bridge Completion of the
bridge -Slab laying
Sep-16 400,000.00 New Yet to receive the funds
2015/2016 Kaplengnoi Cattle
Dip
Fencing , construction
of toilets & store
Sep-16 100,000.00 New Yet to receive the funds
2015/2016 Legetetwe Cattle
Dip
Renovation ,
construction of store &
latrines
Sep-16 200,000.00 New Yet to receive the funds
2015/2016 Kabuswo cattle dip purchase of land-2
acres
Sep-16 150,000.00 New Yet to receive the funds
TOTAL 100,452,235.00