Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Modelling and Real-Time Simulation of a Modular Bidirectional
Solid-State Transformer for Ultra-Fast Charging of Electric Vehicles
by
Yousef Al-Shawesh
A thesis submitted to the
School of Graduate and Postdoctoral Studies
in partial fulfilment of the requirements for the degree of
Master of Applied Science in Electrical and Computer Engineering
Department of Electrical, Computer, and Software Engineering
Faculty of Engineering and Applied Science
University of Ontario Institute of Technology (Ontario Tech University)
Oshawa, Ontario, Canada
August 2021
© Yousef Al-Shawesh, 2021
ii
THESIS EXAMINATION INFORMATION
Submitted by: Yousef Mohammed Lutf Al-Shawesh
Master of Applied Science in Electrical and Computer Engineering
Thesis title: “Modelling and Real-Time Simulation of
a Modular Bidirectional Solid-State Transformer for Ultra-Fast
Charging of Electric Vehicles”
An oral defence of this thesis took place on August 9, 2021, in front of the following
examining committee:
Examining Committee:
Chair of Examining Committee
Asst. Prof. Dr. Khalid Elgazzar
Research Supervisor
Prof. Dr. Hossam Gaber
Supervisory Committee Member
Assoc. Prof. Dr. Mohamed Youssef
Thesis Examiner
Prof. Dr. Sheldon Williamson (Ontario Tech University)
The above committee determined that the thesis is acceptable in form and content and that
a satisfactory knowledge of the field covered by the thesis was demonstrated by the
candidate during an oral examination. A signed copy of the Certificate of Approval is
available from the School of Graduate and Postdoctoral Studies.
iii
ABSTRACT
This thesis proposes a modular Solid-State Transformer (SST) system architecture to be
directly interfacing with a three-phase MV utility network enabling high-power and ultra-
fast charging capabilities for electric vehicles, with the capacity to incorporate energy
storage systems at the MVDC-link. This topological configuration allows bi-directional
power flow for Vehicle-to-Grid and for scalability to higher voltage and power levels. A
detailed model-based design of a multi-module SST is presented with 3.3 kV SiC
MOSFETs for highly efficient charging rated at 1.5 MW, supplied by a 27.6 kV distribution
feeder. The SST switching model is based on a high-frequency two-stage power conversion
solution with a Cascaded H-Bridge (CHB) rectification stage followed by a Dual Active
Bridge (DAB) conversion stage. Control strategies and modulation schemes are
implemented to achieve voltage balance and unity power factor, and to mitigate current
harmonics and voltage ripples in compliance with IEEE standards, validated by Model-in-
the-Loop real-time simulation.
Keywords: Ultra-Fast Charging of Electric Vehicles; High-Power Multilevel Converters;
CHB Rectifier; DAB; SiC MOSFET
iv
AUTHOR’S DECLARATION
I hereby declare that this thesis consists of original work of which I have authored
alone. And ideas and inventions attributed to others have been properly referenced. This
dissertation is the result of my own work and includes nothing which is the outcome of
work done in collaboration. My central contribution was on the review of literature,
formulating the problem statement, defining the thesis objectives, collection of data,
procuring the real-time simulator equipment from the market, design, modelling and
simulation of the SST-based ultra-fast charging solution, as well as the analysis of the
results obtained. The fundamental concepts of control strategies and modulation schemes
utilised in this thesis were developed by others and are acknowledged in the main content.
This is a true copy of the thesis, including any required final revisions, as accepted by
my examiners.
I authorise the University of Ontario Institute of Technology (Ontario Tech
University) to lend this thesis to other institutions or individuals for the purpose of scholarly
research. I further authorise the University of Ontario Institute of Technology (Ontario
Tech University) to reproduce this thesis by photocopying or by other means, in total or in
part, at the request of other institutions or individuals for the purpose of scholarly research.
I understand that my thesis will be made electronically available to the public.
Yousef Al-Shawesh
v
STATEMENT OF CONTRIBUTIONS
An article summarising the design and simulation results of the ultra-fast charging
system architecture proposed in this thesis, showing the different models derived will be
submitted for publication in a peer-reviewed journal as:
Yousef Al-Shawesh and Hossam Gaber, “Modular Bidirectional Ultra-Fast Charger based
on a Two-Stage High-Frequency Solid-State Transformer with 3.3 kV SiC MOSFETs”,
Energies, 2021 [To be submitted on 30 August 2021].
A book chapter is also considered for publication from Chapters 2 and 3 of this
thesis as:
Yousef Al-Shawesh and Hossam Gaber, “A Comprehensive Review of State-of-the-Art
Ultra-Fast Charging Standards, Topologies and Configurations”, Springer, 2021.
The work described in Sections 3.6 and 4.4 was implemented in practice at the Vehicle-
to-Grid (V2G) laboratory, the Canadian Centre for Housing Technology (CCHT), the
National Research Council of Canada (NRC) in Ottawa. Through a 33-weeks-long service
contract, I led the development efforts of modelling, control, and simulation of the V2G-
enabled EV fast-charging system. I also contributed to engineering design, commissioning
and technical support of hardware and software systems including various communication
protocols for the CCHT-V2G testing facility. I also took part in developing an algorithm
for multiple EVs, and co-authored an article published in a peer-reviewed journal.
I hereby certify that I am the sole author of this thesis and that no part of this thesis has
been published or submitted for publication. I have used standard referencing practices to
acknowledge ideas, research techniques, or other materials that belong to
others. Furthermore, I hereby certify that I am the sole source of the creative works and/or
inventive knowledge described in this thesis.
vi
DEDICATION
I dedicate this MASc thesis and all my scholastic awards and university degrees
that I had undertaken around the world to:
my angel, my mother,
my life mentor, my father,
my uncle, Abdulwahab,
my beloved family, my lifetime friends,
and
Arabia Felix, Yemen, my fatherland.
vii
ACKNOWLEDGEMENTS
First and foremost, all praise is due to Allah the Almighty for everything I have
been blessed with in all my educational and career endeavours across four continents.
I would like to express my sincerest thanks to Prof. Dr. Hossam Gaber, for giving
me the opportunity to conduct my MASc research course at his leading research lab group,
and for inspiring me to contribute to research projects that address real-world engineering
problems throughout my Master’s studies. It has been a great honour to be his student. I
sincerely appreciate his supportive supervision and constructive guidance on my MASc
thesis. I highly appreciate the valuable guidance and support I received during my MASc
from the Dean Prof. Dr. Langis Roy. I also would like to thank Dr. Mohamed Youssef, Dr.
Khalid Elgazzar, and Dr. Sheldon Williamson for their constructive feedback on this thesis.
Special thanks to the staff of the School of Graduate and Postdoctoral Studies
(SGPS) and the Office of Student Life at Ontario Tech University for facilitating excellent
professional training programmes and workshops which have enriched my graduate studies
experience. Moreover, I would like to thank my colleagues at the Smart Energy Systems
Lab (SESL), Ontario Tech University Academic Council (AC), and the Graduate Students’
Council (GSC), as well as my friends and the many amiable people whom I had the pleasure
of working and commuting with in Toronto, Oshawa, Ottawa, and Montreal, and who made
this two-year-long academic and professional venture in Canada more interesting.
The work described in this thesis was carried out in the context of the project titled
“Analysis and Design of Fast Charging Stations for Electric Buses” which was partially
funded in the first eight months of my MASc studies by Mitacs and Canadian Urban Transit
Research & Innovation Consortium (CUTRIC) through the Mitacs Accelerate Fellowship.
I gratefully acknowledge both Mitacs and CUTRIC for the financial grant: IT15756.
Part of this applied research was conducted in the second year at the National
Research Council of Canada (NRC) in Ottawa. I would like to tremendously thank Mr
Yeong Yoo for his great mentorship and constructive feedback on the work undertaken at
the Canadian Centre for Housing Technology (CCHT), and for the numerous intellectually
stimulating and enlightening discussions we have had on various scientific and technical
topics. My sincere appreciation to the NRC for hosting me and enabling my access to their
cutting-edge R&D facilities, in spite of the lockdown restrictions due to the pandemic of
CoViD-19 which had initially hindered our lab work activities’ progress for several weeks.
The independent research I undertook at the graduate school, while also working
off-campus simultaneously to self-fund this degree, over the past two years has been
intensely challenging, but I have tried my very best to make it worthwhile. During my
international graduate student life, I had spent much effort and time on many projects and
ideas that ended up unexpectedly drifting through the wind. Having read over a thousand
of published journal articles, I have learnt that asking the right questions is as important as
viii
answering them. It took me a while to learn new lessons from failures within the reality of
working on research problems that have no discernible solution, that is when unrealistic
expectations were quickly shattered. Not only my research interests that pushed me to
conquer the unknown due to the nature of my research, because I realised that full
autonomy, in-depth analytical thinking and dealing with uncertainty which I had developed
over the years were highly important. This thesis is merely a fraction of what I have worked
on throughout the MASc programme. More questions than answers emerged out of many
simulations I had derived, some approaches had outright failed in their own right, but each
and every single one gave me new insights into each research problem. The competence to
find that insight is a vital skill I have honed. Success in such a research environment cannot
be achieved in solitary, and it requires full funding and focus on a clearly specified topic at
a time. Uplifting leadership with insightful inputs is essential for the success of any
complex project. Having learnt these lessons along with the student volunteer leadership
opportunities I held at Ontario Tech, I am so grateful for this daring but fruitful adventure.
With so much love and honour, my profound gratitude to the dearest persons of my
entire life: the queen of kindness, my mother, my life mentor, my father, and my angel,
Abdulwahab, who always believed in my aspirations, and who have earnestly helped me
with everything they had and beyond to acquire the best education at every stage of my
schooling journey and longed for this achievement to come true. I cannot imagine myself
without their continued devotion and self-sacrificing support even while them being under
the war and myself thousands of kilometres far away for over seven years to this day. I am
truly the luckiest person in life to ever have such a genuinely supportive and fervently
encouraging family. To my late beloved grandfather, Lutf, and great-uncle, Abdulrahman,
I will always cherish the beautiful moments you have shown me the principles of
conscientiousness, magnanimity, and generosity. To my dear grandmother, Amatalrazaq,
who passed away while I was writing this thesis, I will always remember our last phone
conversation with tears when you were lovingly praying for me to have a bright future.
May Allah grant them the highest level of paradise. Also, I am forever thankful for the love
and prayers of my grandparents, Lutf and Amatullah, may Allah bless them with great
health and long life. Perseverance, persistence, and prudence are a few of the many core
values they have instilled in me, and which have been indispensable to this success.
Moreover, I am so grateful for the love and compliments of my three charming siblings:
Salma, Isra and Ilyas. I miss each and every one of you immensely and I hope to always
see your consistent academic excellence in your medical, engineering and computer
specialisations. Your ambition and optimism, despite all the circumstances, have been a
great inspiration for me to overcome countless obstacles I have encountered overseas.
Lastly, I am thankful to Canada for granting me this unique opportunity to pursue
my MASc studies, despite the two unsolicited PhD admission offers that I received from
Sydney, Australia in 2019 and the job that I enjoyed in Circular Quay, in pursuit of a more
challenging career in North America. The Great White North will always be my second
home, and I love to see it always prospering. Yousef Al-Shawesh, August 2021.
ix
TABLE OF CONTENTS
ABSTRACT ……………………………………………………………………………iii
AUTHOR’S DECLARATION ....................................................................................... iv
STATEMENT OF CONTRIBUTIONS .......................................................................... v
DEDICATION .................................................................................................................. vi
ACKNOWLEDGEMENTS ........................................................................................... vii
TABLE OF CONTENTS ................................................................................................ ix
LIST OF TABLES ........................................................................................................... xi
LIST OF FIGURES ........................................................................................................ xii
GLOSSARY OF ACRONYMS & ABBREVIATIONS ............................................. xvii
LIST OF MAIN SYMBOLS & NOMENCLATURE ................................................. xxi
Chapter 1. Introduction .................................................................................................... 1
1.1 Background and Motivation .......................................................................... 1
1.2 Current Challenges ........................................................................................ 6
1.3 Problem Statement………….....………………………..…………………11
1.4 Research Objectives .................................................................................... 15
1.5 Thesis Outline ............................................................................................. 16
Chapter 2. State of the Art Review.................................................................................17
2.1 EV Charging Classifications, Standards and Protocols, and Latest
Technologies ……………..……………………………………………….17
2.2 Grid Connections & Common Architectures of State-of-the-Art
DC Fast Charging Systems………….……………..…………..……..…..22
2.3 State-of-the-Art SST-based Ultra-Fast Charging Structures and
Converter Topologies………………………..…………………………….26
2.4 Viable Multi-level Converters for the MV ISOP DPSS SST…..............….41
2.4.1 Multi-level Converters for the AC-DC Conversion Stage.......................42
2.4.2 Isolated Converters for the DC-DC Conversion Stage……..……….….43
2.5 Control Strategies and Modulation Techniques for Multi-level
Converters…………………….………………...…………………………48
2.6 Modelling Approaches and Simulation Software Tools for SSTs.………..54
2.7 Summary……………………………….……………………….……..…..55
Chapter 3. Power Circuit Design ………….…......………………………………....... 56
x
3.1 System Requirements, Specifications and Assumptions ........................... 56
3.2 Proposed SST System Architecture with Modular Configuration ............. 61
3.3 MVAC Grid Distribution Feeder Voltage Level and Filter Selections. ..... 64
3.4 Cascaded H-Bridge MVAC-MVDC Rectifier ........................................... 70
3.5 Dual Active Bridge MVDC-LVDC Converter ........................................... 83
3.6 EV Battery Model ....................................................................................... 93
3.7 Overall Power Circuit of the SST System Model ....................................... 96
3.8 Summary ..................................................................................................... 98
Chapter 4. Control System Design and Modulation Scheme Implementation......... 99
4.1 Monitoring System for the Grid based on a Three-Phase PLL……….....100
4.2 Control and Modulation for the MVAC-MVDC Conversion Stage ........102
4.3 Control and Modulation for the MVDC-LVDC Conversion Stage……..117
4.4 EV Battery Controller ……………………………………………….….126
4.5 Summary…...………………………………………………….…..…….128
Chapter 5. Results and Analysis………….…………….....…...…………………..... 130
5.1 Design Parameters of the SST System and Cost Estimations…………....130
5.2 Performance Evaluation of the UFCSEV under Various Scenarios…..…137
5.3 Efficiency Analysis …………………….……………..….…….…..…... 152
Chapter 6. Conclusions and Recommendations…...……………………...…….….. 156
6.1 Summary of Results …...……………….……………..….…….……... 156
6.2 Contributions ……..…………………….……………..….…….……... 158
6.3 Limitations ……….…………………….……………..….…….……... 158
6.4 Future Works and Recommendations ………………..….…….…….... 159
References ………………………………………………………….………………....160
Appendices ………………………………………………………………………....... 183
Appendix A: Framework of the Research Study ….....………...…………....... 183
Appendix B: Flowchart of the Systematic Design Procedure of the CHB..........184
Appendix C: Optimisation Flowchart for the Selection of fCHB and LCHB........185
Appendix D: Flowchart of the Systematic Design Procedure of the DAB…......186
Appendix E: Flowchart of the Control System Design Process for the SST.......187
Appendix F: Flowchart of the CCCV Charging Method.....................................188
xi
LIST OF TABLES
CHAPTER 1
Table 1.1 Comparison of ESS Technologies for EV Charging Applications [29–30] ..........6
CHAPTER 2
Table 2.1: Comparison of IEC and SAE Standards and Ratings for EV Charging [69]…...19
Table 2.2: Comparison of the SST Topological Configurations for EV Fast
Charging [107]………………………………………………………….……30
Table 2.3: Comparison of State-of-the-Art SSTs for EV Ultra-Fast Charging-Part (a)....39
Table 2.4: Comparison of State-of-the-Art SSTs for EV Ultra-Fast Charging-Part (b)....40
Table 2.5: Comparison of Modular Multi-level AC-DC Converter
Topologies [159–167]………………………………………………………...45
Table 2.6: Comparison of Isolated Bidirectional DC-DC Converter Topologies [169]....47
Table 2.7: Comparison of High-Frequency Modulation Techniques
for Multi-level Converters………..……….....…….…………………………53
Table 2.8: Review of Simulation Models for Two-Stage SSTs..……………………...…54
CHAPTER 3
Table 3.1: MVAC Feeder Overhead Line Parameters...…………………………………64
Table 3.2: IEEE Standards for Current Distortion Limits for odd Harmonics in
per cent of IL [236]…..……………………….……...……...………………..66
Table 3.3: Design Parameters of the EV Battery………………………………………...96
CHAPTER 4
Table 4.1: Comparison of Modulation Techniques for the DAB Converter [306-308]..125
CHAPTER 5
Table 5.1: UFCSEV System Specifications………………………………………..…...130
Table 5.2: Switching Devices’ Ratings, Number of CHB Cells and MVDC-Voltages..131
Table 5.3: CHB Parameters and Values………………………………….………..…...133
Table 5.4: DAB Parameters and Values………………………………….………..…...134
Table 5.5: DC-Link Voltages and Turns-Ratios of HFT...………………...…..…..…...135
Table 5.6: Cost Estimates of Power Circuit Devices and Components………..…..…...136
xii
LIST OF FIGURES
CHAPTER 1
Figure 1.1: Conventional EV Fast Charging employing an MV-LV LFT [57]…………...12
CHAPTER 2
Figure 2.1: Types of EV Charging Mechanisms: (a) DC Conductive Charging with
Overhead Indoor/at Depot Pantograph, b) DC Conductive Charging with
On-route Pantograph, (c) DC Charging with Off-board Charger, (d) AC
Conductive Charging with On-board Charger, e) Inductive Wireless
Charging [64, 74] …………………………………………………………...22
Figure 2.2: EV Charging System with AC Coupling…………………………………….24
Figure 2.3: EV Charging System with DC Coupling…………………………………….24
Figure 2.4: Classifications of SST [106]………...………………………………………..26
Figure 2.5: SST Type-I: Single-Stage SPSS Configuration with no DC-link……..….....29
Figure 2.6: SST Type-II: Two-Stages SPDS Configuration with an LVDC-link…...…..29
Figure 2.7: SST Type-III: Two-Stages DPDS Configuration with an MVDC-link…..…29
Figure 2.8: SST Type-IV: Three-Stages DPDS with MVDC and LVDC-links…………29
Figure 2.9: Control Strategies for Multi-level Converters……………………………….51
Figure 2.10: Classification of Multi-level Modulation Techniques for
Multi-level Converters……………………………………………………..51
CHAPTER 3
Figure 3.1: Power Triangle Diagram………………………………………...…………..59
Figure 3.2: Four-Quadrant Operating Area of the SST-based High-Power
Conversion System………………………………………………………….60
Figure 3.3: Architecture of the Proposed SST-based High Power Conversion System…61
Figure 3.4: Configurational Topology of the Proposed DPSS SST-based Charging
System………………………………………………………………….……62
Figure 3.5: Configuration of the Proposed Modular ISOP SST-based High-Power
Charging System…………………………………………………..………...63
Figure 3.6: Fundamental Structure of a Single Converter Cell of the Proposed SST...…63
Figure 3.7: Single-line Diagram of the MVAC Distribution Feeder…………………….65
xiii
Figure 3.8: Three Phase Star Connection from the MVAC Feeder to the UFCSEV…….65
Figure 3.9: Schematic Diagrams Filters: (a) L-filter (b) LC-filter (c) LCL-filter………..67
Figure 3.10: The SST Converter Topology with the DC-Links’ Capacitors…...…….….68
Figure 3.11: Three-Phase Representation of Cascaded Rectifier Topology
within the Proposed SST System Configuration………………………..…71
Figure 3.12: Single-Phase Representation of Cascaded H-Bridge MVAC-MVDC
Rectifier Topology……...…………..……………………………………...72
Figure 3.13: Simple Circuit Diagram of Single-Phase Connection from MVAC
Grid to the CHB……………………………………………………….……72
Figure 3.14: Representation of the Relationship between the required Rectified
Output Voltage Amplitude of the CHB and the Phase Angle between
the MVAC Grid Voltage and Current [259]..………...……………………73
Figure 3.15: Vector Representation of the Relationship between the Voltages
and Current at Unity PF (a) Arbitrary Current (b) Power flow from
CHB to MVAC Grid (c) Power flow from MVAC Grid to CHB…………74
Figure 3.16: Factors for Trade-offs of Selecting the Optimum Number of CHB
Rectifier Cells [259]………………...………..………………………….…77
Figure 3.17: Representation of MVDC-Link Voltage Limitations………………………78
Figure 3.18: Multiple Module Topology of DAB MVDC-LVDC Converter.…………..85
Figure 3.19: Equivalent Circuit Schematic of the HFT………………………………….86
Figure 3.20: Simplified Circuit Schematic of HFT…………………..………………….86
Figure 3.21: Phase Shift Waveform Representation of the Input and Output
Voltages of the HFT………………….…………………………………..89
Figure 3.22: DAB Output Power versus Duty Cycle [263]..…………………………….90
Figure 3.23: DC Conversion-Ratio versus Output Current of the DAB [263]…..………91
Figure 3.24: Model of the Li-ion EV Battery [277-279] ……..…………………………93
Figure 3.25: Characteristics of the Charge and Discharge of the Li-ion Battery
Cell [276]…………………………………………………..……………....95
Figure 3.26: Topological Configuration of the Modular Structure of the Proposed
SST System…………………………………………...……………………97
Figure 3.27: System-Level Simulink Model of the Overall Power Circuit of the SST….98
xiv
CHAPTER 4
Figure 4.1: Three-Phase Phase-Locked Loop Structure for Grid Monitoring..………...101
Figure 4.2: Current-Mode Closed-Loop Feedback Controller for the CHB Rectifier….102
Figure 4.3: Decoupled Current Control Scheme for Three-Phase Single Cell of
the CHB Rectifier ……………………………………………….………...105
Figure 4.4: ABC and dq0 Frames with A-axis and the d-axis initially aligned………...106
Figure 4.5: Voltage Balancing Control Scheme for the Multi-level CHB Rectifier……107
Figure 4.6: Carrier Signals of the CHB Cells for Phase-A based on Phase Shift
Sinusoidal Pulse Width Modulation (PS-SPWM) ………………………...109
Figure 4.7: Averaged Model of a Single H-Bridge Cell of the CHB Rectifier in
Single-Phase…………………………………………………………….….111
Figure 4.8: Averaged Model of the Three-Phase Circuit of the CHB Rectifier
with NCHB Cells………………………………………………………….....112
Figure 4.9: Simplified Averaged Model of the Three-Phase CHB Rectifier with
NCHB Cells………………………………………………………………….113
Figure 4.10: Current-Mode Closed-Loop Feedback Controller for the DAB Converter.118
Figure 4.11: Dynamic Averaged Model of a Single Module of the DAB Converter......119
Figure 4.12: Voltage Waveforms of the DAB HFT with the Operation States of
MOSFETs ..................................................................................................120
Figure 4.13: Equivalent Circuit of the Dynamic Averaged Model of the DAB
Module for period t0 ..................................................................................120
Figure 4.14: Equivalent Circuit of the Dynamic Averaged Model of the DAB
Module for period t1 ...................................................................................121
Figure 4.15: Simplified Circuit Diagram of Figure 4.13.................................................121
Figure 4.16: Simplified Circuit Diagram of Figure 4.14.................................................121
Figure 4.17: Waveforms of DAB Operation with the Rectangular Phase Shift
Modulation Technique................................................................................126
Figure 4.18: Waveforms of the Charging Profiles using CCCV Method for the
EV Battery..................................................................................................127
xv
CHAPTER 5
Figure 5.1: Voltage and Current Waveforms of the three-phase MVAC Grid at rated
Charging Power and Ideal Grid Condition..................................................137
Figure 5.2: SST Input Active and Reactive Power Waveforms at rated Charging
Power and Ideal Grid Condition...................................................................138
Figure 5.3: Harmonics Distortion of Input Current to the SST.......................................139
Figure 5.4: Harmonics Distortion of Input Voltage to the SST ………………………..140
Figure 5.5: MVDC-Link Voltage (Top) Output Current (Bottom) and of each CHB
Cell at the rated Charging Power………………..………………………….141
Figure 5.6: Output Current and Voltage of the DAB Converter to the EV Battery
at the rated Charging Power………………………………………………..142
Figure 5.7: Waveforms of HFT Primary and Secondary Voltage in Ideal Grid
Condition at the rated Charging Power…..……......................................…143
Figure 5.8: Waveforms of the Input Voltage and Current from the MVAC to the SST
with disturbances conditions at the grid between 0.2 and 0.5 s…….…...…143
Figure 5.9: Comparison of the Grid Frequency Measurements using the proposed
PPL versus the built-in MATLAB PLL………..……….……………...….144
Figure 5.10: The dq components of the MVAC grid affecting the CHB
controller during the disturbances between 0.2 and 0.5 s………....……...145
Figure 5.11: The MVAC Grid Voltage LL RMS measurement from the proposed
PLL showing the affected disturbances between 0.2 and 0.5 s ….…….146
Figure 5.12: The MVAC Grid Voltage LL RMS measurement from the
proposed PLL during ideal grid conditions…………………………...….146
Figure 5.13: Phase angles’ measurements of the MVAC grid voltages during
ideal grid condition using the proposed PLL.……..……...……………....147
Figure 5.14: Simulation Results of the MVAC– 3Phase with LLLG Fault a) Voltages
b) Currents c) Grid Frequency using the built-in MATLAB PLL………...148
Figure 5.15: Overall Simulation Model of the SST-based UFCSEV ……………...…..149
Figure 5.16: Pulsing signals for CHB MOSFETs: Top: Switches 1&4
Bottom: Switches 2&3 ……………………….. ……………………...….149
Figure 5.17: Pulsing signals for DAB MOSFETs using Phase-Shift Modulation:
a) Switches 1&4 b) Switches 2&3 c) Switches 5&8
d) Switches 6&7……………………………………………………...…...150
xvi
Figure 5.18: Li-ion Battery Characteristics for the EV Battery Model used on
MATLAB/Simulink ………………………………..……………………150
Figure 5.19: EV’s Charging Profile with SoC limits………………………………...…151
Figure 5.20: Forward Characteristic Approximation of a MOSFET (or Diode)
by Vsw,0 and r………………………………...........................................…152
xvii
GLOSSARY OF ACRONYMS & ABBREVIATIONS
ABP Adaptive Balancing Power
AC Alternating Current
AFE Active Front-End
BESS Battery Energy Storage System
BEV Battery Electric Vehicle
BMS Battery Management System
BPSM Bidirectional Phase Shift Modulation
CAES Compressed Air Energy Storage
CAN Control Area Network
CHB Cascaded H-Bridge
CHAdeMO Charge de Move
CCCV Constant Current Constant Voltage
CCS Combined Charging System
DAB Dual Active Bridge
DAM Dynamic Average Model
DBC Dead Beat Control
DHB Dual Half-Bridge
DER Distributed Energy Resource
DES Distributed Energy System
DC Direct Current
DPSS Dual Primary Single Secondary
DPDS Dual Primary Dual Secondary
DSP Digital Signal Processor
DSM Detailed Switching Model
EB Electric Bus
EMI Electromagnetic Interference
EMS Energy Management System
xviii
EMT Electromagnetic Transient
ESS Energy Storage System
EV Electric Vehicle
EVSE Electric Vehicle Supply Equipment
FC Flying Capacitor
FCS Finite Control Set
FESS Flywheel Energy Storage System
FPGA Field Programmable Gate Array
FCV Fuel-Cell Vehicle
G2V Grid-to-Vehicle
GHG Green-House Gas
GB/T Guobiao
HE High Energy
HESS Hybrid Energy Storage System
HFT High-Frequency Transformer
HIL Hardware-in-the-Loop
HP High Power
HV High Voltage
IEC International Electrotechnical Commission
IBC Interleaved Boost Converter
ICE Internal Combustion Engine
IGBT Insulated-Gate Bipolar Transistor
IPT Inductive Power Transfer
ISOP Input-Series, Output-Parallel
ITCM Integrated Triangular Current Mode
JBS Junction Barrier Schottky
KPB Kinetic Power Booster
LF Low Frequency
xix
LFP Lithium-Iron Phosphate
LFT Line Frequency Transformer
Li-ion Lithium-Ion
LMO Lithium Manganese Oxide
LPF Low-Pass Filter
LV Low Voltage
LVDC Low Voltage Direct Current
NPC Neutral-Point-Clamped
NPP Neutral Point Piloted
MFT Medium-Frequency Transformer
MIL Model-in-the-Loop
MIMO Multiple Input Multiple Output
MMC Modular Multi-level Converter
MPC Model Predictive Control
MV Medium Voltage
MVAC Medium Voltage Alternating Current
MOSFET Metal–Oxide Semiconductor Field-Effect Transistor
PCC Point of Common Coupling
PET Power Electronic Transformer
PEV Plug-in Electric Vehicle
PHEV Plug-in Hybrid Vehicle
PF Power Factor
PFC Power Factor Correction
PID Proportional–Integral–Derivative
PR Proportional Resonant
PSFB Phase-Shift Full-Bridge
PLC Power Line Communication
PLL Phase-Locked Loop
xx
PV Photovoltaic
PWM Pulse Width Modulation
RES Renewable Energy Source
RFB Redox Flow Battery
RMS Root Mean Square
SAE Society of Automotive Engineers
SHB Sample-and-Hold Block
SISO Single Input Single Output
SoC State of Charge
SoH State of Health
SPDS Single Primary Dual Secondary
SPM Single-Phase Module
SPTS Single Primary Triple Secondary
SRF Synchronous Reference Frame
SST Solid-State Transformer
SVM Space Vector Modulation
TCC Transistor-Clamped Converter
THD Total Harmonic Distortion
TLB Three-Level Boost
TPSS Triple Primary Single Secondary
TPS Triple Phase Shift
UFCSEV Ultra-Fast Charging System for Electric Vehicles
V2G Vehicle-to-Grid
V4G Vehicle-for-Grid
VSC Voltage-Source Converter
WBGSs Wide-bandgap Semiconductors
ZCS Zero-Current Switching
ZVS Zero-Voltage Switching
xxi
LIST OF MAIN SYMBOLS & NOMENCLATURE
g Phase angle of the grid supply
ϕ Phase
𝜑 Impedance phase angle between the active and apparent power vectors
fg Nominal grid frequency
h Harmonic order
ISC Maximum short-circuit current at PCC
IL Maximum demand load current (at fundamental frequency) at PCC
VMVAC-ph Phase-to-neutral voltage of the MVAC grid
VMVAC_LL Nominal voltage (RMS line-to-line) of the MVAC grid
IMVAC-ph Phase current of the MVAC grid flowing through the grid filter
LCHB Inductor of the grid filter
fCHB Switching frequency of the CHB rectifier
MCHB Nominal modulation index of the CHB
NCHB Number of H-Bridge cells of the CHB rectifier
Smax Maximum apparent power flowing through the SST
VCHB1 Fundamental AC input voltage to the CHB
VMVDC Voltage across the MVDC-link
VMOSFET_rated Rated blocking voltage value of the MOSFET semiconductor switch
fDAB Switching frequency of the DAB converter
dDAB Phase shift or duty cycle of the DAB converter
CO2 Carbon Dioxide
GaN Gallium Nitride
NiCd Nickel–Cadmium
NiMH Nickel–Metal Hydride
Si Silicon
SiC Silicon Carbide
1
Chapter 1. Introduction
This chapter introduces the motivation of this study followed by the challenges
pertaining to the predilection of conventional charging of electric vehicles in favour of
ultra-fast charging. The scope, problem and objectives of the thesis are defined, and the
framework and methodology of which this research has been carried are briefly introduced.
The thesis layout with a brief overview of each chapter finalises this introductory chapter.
1.1 Background and Motivation
1.1.1 Electrification of Transportation
In the light of the continued increasing demand for efficient, reliable and convenient
transportation means, there is perhaps no apter symbol of the 21st century than the
automobile and mass transit; the dominant means of mobility aspired and one of the levers
of socio-economic progress throughout the globe [1–3].
In today’s world, the energy for personal and public transportation emanates largely
from petroleum in the form of gasoline, diesel, and gas to power traditional vehicles by
ICEs. These modes of transport are in crisis due to their heavy dependency on fossil fuels.
However, the environmental impacts and energy security problems are rapidly making
automobile transportation and mass transit unsustainable for our society [2]. This is
because transportation is one of the largest contributors to GHG emissions in the world
with 15% of the total emissions [3–4]. Canada is the 7th biggest GHG emitter in the world;
which is the highest amongst all G20 members; with its transportation that accounts for
28% of the total CO2 emissions as the 2nd largest contributor of emission in the country [5].
Over the past few decades cultivated, the evolution of the transportation sector was
increasingly being questioned for its impact on climate change and public health. A
considerable amount of research has been dedicated to rationalising energy consumption
and finding alternative solutions which aim to curb and mitigate the environmental issues
stemming from transportation sources without penalizing personal, commercial or mass
mobility. In order to preserve the climate and natural resources of planet Earth, the
transition from ICE vehicles to BEVs will play a vital role in ensuring sustainability as this
technology presents an enormous opportunity to decrease CO2 emissions and air pollution.
2
Electrification of transport is regarded as a promising trend as it is more environmentally
friendly and has higher efficiency. In the mobility industry, compared with conventional
ICE, an electric driven engine is able to increase the efficiency by 30-40% [6–9]. This has
become the major objective for the automotive industry worldwide and has led to the
invention and development of new propulsion technologies focused on vehicle
electrification which is the most viable option by spurring a different mix of vehicles. The
ICEs in conventional cars have been replaced by motors with rechargeable battery packs
as in PEV that can be recharged from any external electricity sources such as wall sockets.
PEV technology is a subcategory of alternative-fuel vehicles that includes BEVs, PHEVs,
and FCVs [7–9]. Most state-of-the-art EVs mainly operate using electrical energy being
stored in their batteries [7]. The electricity stored in the batteries either drives or contributes
to driving the EV wheels. The fact that these batteries have limited energy capacity for
storage and use in long-distance travel, recharging EVs from time to time is essential to
overcome drive range anxiety. However, there is still challenging evidence when
considering the capacity of the existing electricity distribution networks to supply the
necessary power sufficient to recharge these EVs [7–8]. Currently, due to the limited
number of charging stations and the relatively high price of the battery, PHEV is more
welcomed by the global market. However, with further penetration of EV charging systems
and advancement of battery technologies, PEV has a much more potential to be dominant
in the future from viewpoints of environment, efficiency, and cost [7–11].
Transportation electrification is revolutionising the mobility industry and
transforming the future of how automobiles, public transits, watercraft, and even aircraft
and spacecraft are powered to support the larger goal of sustainable development with zero
tail-pipe modes of transport. Regardless of technology development, higher cost, limited
range, and long recharging time represent critical drawbacks that still limit the adoption
and availability of all EVs in both personal and mass transportation sectors. Thus, the role
of automobile and mass transit in the present needs to become part of a much bigger energy
network, wherein energy storage, power conversion, information and communication play
a principal role. Therefore, research is moving rapidly towards vehicle electrification that
assists in enhancing both the mobility and the power industries. Therefore, the only
potential energy source for transportation is electricity as it tackles the simultaneous
3
demands for energy supply security, fuel diversity, reductions in GHG emissions, and it is
widely obtainable and can be produced domestically, in both urban and rural areas.
1.1.2 Charging and V2G Concepts for Electric Vehicles
Transitioning to an electric transportation model requires energy storage capable of
supplying the energy and power demands of such EV. The availability and effectiveness
of charging equipment for EVs play a vital role in their development, grid integration and
fostered adoption by users worldwide. As the number of EVs increases, there is an urgent
and intensifying need for sustainable, efficient, cost-effective, reliable, and fast responsive
EV charging solutions. One practical way to achieving an all-electric cruising range of EVs
is to design and implement well distributed charging infrastructures. Thus, battery chargers
play a critical role in the development of EVs [9]. A charging station generally includes a
charging stand, power outlet, charge cord, attachment plug, vehicle connector, and
protection equipment. Charging system configurations can vary from country to country
depending on the standards adopted and the type of electrical grid connection as well as
the charging power level, voltage level and nominal grid frequency. In all cases, the
charging time and lifetime of an EV’s battery are greatly influenced by the characteristics
of the charger that must guarantee a suitable charge of the battery. Significant research has
been focused on developing efficient and reliable charging with high power density, low
cost and low weight and volume. The power level is the main charging parameter, which
is proportional to the charging time, cost, equipment size and impacts on the grid.
International standards are referred to this parameter for the EV charging equipment
classifications [12].
The EV charging system can be categorised into two types: off-board and on-board
chargers with unidirectional or bidirectional power flow capability. On-board chargers
usually have limited power levels due to their weight, space need and costs. This charger
is installed inside the EV which allows owners to charge their EVs anywhere from a
suitable electricity source. Off-board charger is usually designed for high power charging
rates and is less constrained by size and weight. Unidirectional charging simplifies the
interconnection issues and limits hardware requirements whereas bidirectional charging
supports battery energy injection back to the grid; this technology is known as V2G [12].
4
EV batteries can be utilised as effective storage devices in micro-grids when they are
plugged in for charging. Most vehicles usually represent an idle asset as an average vehicle
sit parked for about 22 hours each day. Charging millions of EVs from the electricity power
grid could nevertheless be significant, in the form of increased loading of power supply
capacity, transmission, distribution and economics. Hence, the interaction between
vehicles and the utility grid effect should be considered in an intelligent and coordinated
method by controlling and scheduling the charging via communication-based distributed,
dispatch, and decentralised control systems for improved energy infrastructure. EVs could
potentially support energy management by storing energy when there is a surplus (G2V)
as DES and feeding this energy back to the grid in times of high demands on the grid or
shortages via V2G. V2G capabilities applied to the utility power grids still face some
challenges such as control complexities and regulatory policies [13–14].
1.1.3 Energy Storage Technology Options for EV Charging Applications
The expansion of electric mobility is a key component of strides towards
decarbonisation. Apart from EVs development, there has been an emerging interest in
employing electric ESSs in transportation electrification. Currently, the short-range of EB
and the lack of infrastructure for high-power charging terminals is a limiting factor for
rapid growth in electric public long-haul transport. ESS plays a key role in enabling the
roll-out of EV charging stations, especially in locations with a weak power distribution
grid. The ESS to be selected should have high efficiency and be able to afford to operate
in a lot of frequent charge/discharge cycles before its end-of-life point is reached, due to
the frequent connection and disconnection of EV fleets. ESS should also have high power
density and moderate energy density to enable delivering a large amount of power quickly.
The most commonly used ESS is the BESS technology, which includes Li-ion, Lead-
acid, NiCd/NiMH and other types of batteries. Lead-acid is a cheap BESS option, but it
has low efficiency and low power density. The health of a Lead-acid battery is significantly
reduced due to its chemical materials when overcharged or discharged. NiCd BESS has
been widely used since the late 1990s, its power density is much higher compared to Lead-
acid, but its life cycles are short, and it suffers from memory effects. NiMH BESS has an
improved power and energy density, while its capacity is still reduced critically in
overcharge conditions. On the other hand, Li-ion BESS is commonly used nowadays in
5
transportation electrification applications due to its high performance and cost-
effectiveness. Li-ion battery is the most widely employed technology in EVs as it has
advanced significantly over the past decades, making EVs more cost-effective and
practical. The cost of batteries has fallen considerably to less than $120/kWh [14–16].
Though it can operate in higher current conditions, Li-ion degradation issues still exist in
the condition of deep charge and discharge in peak rate [17–21]. There is theoretically up
to the five-fold potential to go from the current Li-ion energy density of 200 Wh/kg to up
to 1000 Wh/kg possible with Li-air batteries. There is a huge potential for research into the
material, stability, safety, cycle life, power and energy density and manufacturability of
such emerging technologies such as Li-air, Li-sulphur and Mg-ion [64].
Employing a chemical Li-ion-based BESS in the charging system is feasible, but
multiple charging cycles shorten the battery life span. This, unfortunately, leads to more
frequent system replacements, making this option costly and dismally polluting as they
pose recycling complications to the environment. Looking for sustainable alternatives
comes into the picture. Flywheel: for instance, employs a rotating steel or composite mass
to achieve energy storage as it is driven by an electric machine, including an induction
machine, permanent magnetic machine, and brushless DC machine. The biggest feature of
the flywheel is that it purely operates mechanically, and it utilises recyclable materials.
FESS technology has a huge advantage compared to any other ESSs; that its capacity can
reach up to several hundred kW at 100 % cycle stability and also has over 20 years of
service life and scalability to individual applications [22–23]. Chakratec [24] developed a
unique kinetic battery, based on a flywheel concept, which can withstand practically a very
high number of charging cycles. Utilising its proprietary KPB technology, Chakratec
facilitates the deployment of fast and ultra-fast EV charging stations in any location with a
weak grid. This applies especially to EBs as they run for long-haul or all-day shuttle
operation, but they have a battery capacity limitation. Opportunity charging at scheduled
stops extends their range to better fit normal bus schedules. ABP’s FESS enables
opportunity charging without the need for extensive upgrades to the utility grid [25].
In addition to offering a sustainable alternative of ESS with high efficiency and long-
life cycle, FESS has high power density as it is capable of delivering high-power bursts
which enable fast charging in low-voltage power grids allowing extended ranges for
6
electric transportation without hauling bigger batteries and without requiring significant
grid expansion at every bus stop. The advantage of flywheels on opportunity charging
station is frequented several times a day by EBs. Less frequent use increases effective cost
both of infrastructure and per unit energy. The latter is due to ratcheted demand charges on
peak loads. BESSs are not suitable in this application as cycling them multiple times per
day would severely shorten their life. On the other hand, FESSs match this application
quite well as they are designed for more than 100,000 cycles under the same conditions.
FESS, with a flexible grid interface for nearly any point of coupling, is freely scalable and
can be designed for individual applications [24] – [28]. There are also other ESS solutions
that can be employed in EV charging, such as ultra-capacitors and redox flow batteries.
Table-1 illustrates the energetic characteristics of various ESS technologies for EV
charging applications. Choosing an appropriate ESS technology depends on economic
considerations and technical specifications of the respective technology.
Table 1.1: Comparison of ESS Technologies for EV Charging Applications [29–30]
ESS
Technology
Energy
Density
Power
Density
For 200 EVs
per day L
ifet
ime
[cycl
es]
Inves
tmen
t
Cost
[$/k
W·h
]
Cost
Per
cycl
e
[$/k
W·h
]
[W.h
/kg
]
[W.h
/l]
[W/k
g]
[W/l
]
Mas
s [t
]
Vo
lum
e
[m3]
Lead-acid 30 74 100 250 76 31 ~ 103 300 0.5
Li-ion HE 200 630 220 650 11 4 ~ 104 800 0.5
Li-ion HP 80 140 750 1400 29 16 ~ 104 2000 0.5
RFB 23 30 60 80 99 76 ~ 104 500 0.1
Supercapacitor 6 7.6 5900 7400 380 300 ~ 105 7000 0.08
Flywheel 11 18 800 1300 207 127 ~ 106 4000 0.08
CAES 23 24 23 24 99 95 ~ 106 50 0.02
1.2 Current Challenges
Despite the recent advancements of technologies for EV charging solutions, there
are still many challenges that are encountered by the electric power and mobility industries.
Some of the most significant challenges that are being considered in research and
development nowadays are focused on the followings:
7
1.2.1 Prolonged Charging and Driver Range Anxiety
The driving range of EVs on one single charge is still shorter than the range of the
ICE gasoline vehicles due to the orders of magnitude larger (12,000 Wh/kg) energy density
of petroleum [31–32]. Despite the falling cost and major improvements in performance,
Li-ion battery degradation at rest and during cycling, as well as the charging rate limitations
due to the electrochemical processes and its limited energy density (compared to
petroleum) still pose major challenges to further EV adoption [33–36]. Range anxiety is a
serious issue and has led to the urgent need to re-think refuelling similar to gasoline
stations. To provide a better performance in terms of the mileage range of the EV, there
are two feasible solutions. The first is increasing the battery capacity resulting in an
increase in the cost, size, and weight of the EV [36]. The second solution would be to
enhance the fast-charging infrastructure; thus, enabling drivers to recharge their EVs more
frequently. Out of the two solutions, the latter proves to be more beneficial technically and
economically [37–38].
The duration required to charge such batteries can be significantly minimised, which
implies the use of the grid and additional sources of energy that must be managed
efficiently and intelligently. A waiting period is also required to recharge the ESS installed
in charging stations once the EV departs. Such a period should also be minimised in order
to reduce the time that the driver needs to wait at the station before charging the EV battery
and to accelerate the EV battery swapping process at some charging stations if applicable.
Recharging the battery of parked EVs at the parking lots of workplaces, residential
buildings, or in public charging stations could be one of the prominent solutions. However,
users are bound to charge their EVs via residential AC mains with low power capability
due to the lack of fast charging infrastructures. These charging points are referred to as
level-1 (120 V) and level-2 (240 V) AC chargers as per SAEJ1772 standards [39]. In such
cases, EVs are equipped with dedicated on-board chargers that are capable of drawing
power of 1.92 kW (level-1) and 19.2 kW (level-2) from the utility grid [40]. Typically,
these chargers take more than 8 hours for a single charge to add about 200 miles of driving
range on the EV. This is; however, undesirable for highway driving and long trips. Thus,
there is a huge demand to enhance the power capability of on-board battery chargers to
8
quickly replenish the charge in an EV battery. However, it is difficult to develop high
power density on-board chargers due to the size, cost, weight and safety constraints of the
EVs. Thus, establishing fast and ultra-fast charging infrastructures to meet the increasing
power demand while facilitating acceptable and safe charging of EV batteries is a feasible
solution that is currently undertaken by extensive research and development [41–42].
1.2.2 Limited Capacity of EVs’ Batteries
EV batteries have limited storage capacity used for a limited average range while
travelling long distances, which is defined by the EV battery performance. Substantial
development in the area of on-board batteries is expected in order to lengthen the total
driving range. Nowadays, commercially available fast-charging solutions allow recharging
of an EV within 20 minutes as a minimum [43–44]. High energy density lithium batteries,
based mostly on the LMO spinel or LFP electro chemistries are widely utilised by
manufactures worldwide in order to reach the highest autonomy possible while having
prolonged charging disadvantage of durations in the scale of 6-8 hours for charging power
between 3-4 kW. High power density batteries; however, require less time to recharge. Li-
ion batteries are popular energy storage solutions for peak loads and demand charges, but
they suffer from a few inherent deficiencies such as insufficient power density to meet
peak-power demand, uncontrolled thermal management (cooling the battery and warming
it up during colder weather conditions), and limited lifetime/driving range (only 249 km is
achievable at best from a 90 kWh all-electric bus battery pack on a single charge [45–46].
1.2.3 Complex Installation and Inefficiency of Existing MVAC-LVAC LFTs
The entire system of modern EV fast charger stations with AC and DC coupling
system connects to the MVAC utility supply via a three-phase step-down service LFT that
delivers power at LVAC (up to 480 V or 600 V line to line) to all of its subsystems, which
is usually not readily available in public installations. The subsystems are connected to the
transformer via switchgear cabinets that contain circuit breakers and disconnects. The
system may include ESSs and generation capabilities to help mitigate demand charges that
are incurred during peak power consumption requirements at the charging station. An
9
example of an AC-coupled system is a supercharger station in Mountain View, California,
which includes six superchargers and 200 kW (400 kWh) of BESS [53–57].
Existing ultra-fast charging solutions employ MV-LV LFTs to step down the AC
voltage as in DC distribution configurations, where the charging station connects to the
MVAC distribution system via an MV-LV transformer and an LV rectifier. The three-
phase LFT delivers power at LV to a single AC-DC rectifier stage, which then distributes
the DC power to individual station subsystems. The dedicated service transformer is used
to reduce the distribution system MV and provide a three-phase supply to a single DC fast
charger or to a DC fast-charging station comprising of multiple chargers. The conventional
iron-and-copper LFT in this application adds power losses and costs to the charger system
and generally complicates installations. Moreover, distributing high power to a charger or
a charging station at LV implies the need for conductors and LV distribution and
switchgear equipment that are large and bulky in size and weight [47–48]. The existing
transformer and the charger system total efficiency is around 93%. Besides its relatively
high losses at the average load level, the LFT cannot convert single-phase service to three-
phase for certain equipment [49–51]. These make LFTs an undesirable choice for ultra-fast
charging applications for EVs.
1.2.4 Limited Capability of Power Grids for High-Power Ultra-Fast Charging
The existing distribution utility grid has limitations in power capability. For
instance, European power is rated up to 3.6 kW and 11 kW for single-phase systems and
three-phase connections, respectively [29]. Charging a 100 kWh battery for Tesla Model S
EV from a standard 240 V, 30 A outlet takes approximately 11 hours to reach 80% SoC,
after which the car is able to cover up to 647 km of travel distance [52]. Since 38 km only
is the average daily travelling distance for a typical car as estimated by [53], charging EVs
using level-1 and level-2 would satisfy the demands of some EV drivers. However, for the
long-stretch highway travel segments, faster-charging options must be guaranteed in order
to overcome the “range anxiety”. If a fuel tanking for a conventional ICE vehicle with the
flow rate of 35 l/min, it would require an equivalent power of 22 MW which is utterly
absurd if compared with the charging of EVs. Even for lower charging rates between 5 to
10 minutes, it is necessary to connect to a strong grid with a higher capability if the EV
10
battery’s ability to accept a high charging power rate is taken into account. The worst-case
scenario is when several EVs are being charged simultaneously. This demands a huge
upgrade and change in the existing public infrastructures. In this case, the charging station
must have an ESS as a buffer to supply energy when needed and alleviate the high effects
of power demand on the grid system [53–55]. The scale of the charging power at the EV
input and the transferred energy required is of absolute importance regarding the electricity
power grid. A high-power charging solution requires the deployment of an extra buffering
ESS in order to mitigate the adverse impacts on the distribution grid. Existing industry
charging stations employ one type of ESS technology to directly charge EVs, otherwise,
EVs are charged directly from the electricity grid if it has sufficient capacity without
impacting other loads; like blackouts in neighbourhoods. However, when a fast-charging
station is not operational at full power rate, the ESS unit can still benefit from drawing
energy from the grid as widely spread by chargers based on CHAdeMO standard [56].
1.2.5 System Integration and V2G Impacts on Grids and EVs’ Batteries
Since electricity is distributed with AC, whereas, batteries use DC, power electronic
devices are required to convert AC into DC for charging batteries. In the EV application
framework, this could be achieved by deploying off-board or on-board chargers. As many
EVs require high-power and compact chargers, high-power chargers are often implemented
off-board due to the size constraints inside EV. However, low power chargers are regularly
embarked into the EVs. In some cases, a combination of off-board and on-board chargers
are often implemented in order to achieve the appropriate compatibility regarding the
power, voltage, and current ratings between the utility grid AC mains and the EV batteries.
One important concern of the effects of fast charging on the EV battery pack is that
its usage over time results in degradation of the battery’s SoH. The situation is even worse
for V2G as it has a huge direct impact on the battery lifetime due to the electro-chemical
reactions taking place in the battery. The rate at which chemical reactions take place for
each of the battery chemistry is well defined since the battery is subjected to such high
voltage and current levels during fast charging. With comparatively higher temperatures
generated, the EV battery experiences greater thermal degradation as a result [36].
11
There are significant discrepancies and variations of charging specifications based
on the manufacturers in many countries due to the wide range of EV models, batteries and
charging technologies that exist in the market. For instance, the EV manufacturers prefer
to sell their products in a set with a Level-1 single-phase on-board charger, which could be
connected to a standard household 16 A socket, the charging power is even more limited,
reaching a maximum of 1.92 kW. Therefore, a small-sized EV with a 20 kWh battery would
require at least 9 hours to be recharged up to 90% SoC. However, level-3 which requires
off-board chargers has been implemented nowadays by the CHAdeMO consortium [56],
where the charging current is limited up to 120 A by the connector used. This enables
charging a commercial EV within 30 minutes depending on the EV battery capacity. Off-
board DC fast chargers have limited flexibility for charging availability and locations. Such
a fast charger requires high input power which may affect the electricity grid as the loading
of this charger needs to be regulated. Still, EV manufacturers have not yet reached an
agreement on the standard connectors and power levels required for fast charging, the
increased charging especially where bidirectional power flow is used via the V2G
technology constitutes many challenges. Standardized charging protocols and charger inlet
connectors must be well-established in order to ensure charging compatibility and safety.
Thus, it is important to look at some aspects of the impacts caused by such charging stations
on the grid power quality and reliability such as harmonics by analysing the THD, power
factor, phase unbalance, ground fault and electricity sources.
1.3 Problem Statement
The development of ultra-fast charging technology has recently increased the
autonomy and the flexibility of EV drivers by mitigating the range limitations given
through the prolonged charging times (as in most cases taking several hours for a single
charge by conventional charging). Commercially available ultra-fast charger solutions
employ 3-phase LVAC input units that can be supplied by 208/480 V AC. For instance,
ABB [57] and Siemens [58]’s state-of-the-art high-power charging systems for electric
12
buses with a charging power of up to 450 kW are to be connected to the LV side of the
distribution step-down LFT with multi-windings and varying turns ratio. These conductive
DC ultra-fast chargers incorporate conventional service three-phase LFTs that convert
MVAC to the required LVAC with three power conversion stages, as shown in Figure 1.1:
(1) AC-AC conversion stage via LFT (MVAC-LVAC step-down transformer).
(2) AC-DC conversion stage via power electronics (LVAC-LVDC rectifier), with
an output that provides a shared DC distribution link for the loads tied to the
LV system. However, this front-end rectifier unit has disadvantages especially
in MW range high-power charging operations, such as producing unwanted
harmonic effects. With more stringent requirements by the grid code, in terms
of THD, which puts constraints on restricting the switching frequency of the
power electronic devices. Since there is no zero crossing of the voltage in the
DC-link system, this stage also requires more complicated protection devices
and control strategies [59].
(3) DC-DC conversion stage via power electronics (LVDC-LVDC converter to
convert the DC-link voltage to the voltage required to charge the EV battery.
No galvanic isolation is required in this stage as it is provided by the LFT of the
first stage.
Figure 1.1: Conventional EV DC Fast Charging employing an MV-LV LFT [57]
At low voltage levels, the input current to the conventional charging system is
typically large rated at 90A for 480V AC or 200 A at 208 V AC. This yields in increased
power losses and lower efficiency. Most DC fast chargers have an overall efficiency in the
range of 90-92%. Combining this with the efficiency of the MVAC-LVAC three-phase
13
LFT (~99%), results in 89-91% of overall system efficiency (excluding power losses on
the low voltage runs). If the LFT secondary drops (runs) are included, the overall system
efficiency can be expected to decrease further [47]. This service LFT also adds complexity
in installation as well as costs to the EV charging system. Furthermore, distributing high
power to an EV charging station at LV implies the need for large size conductors and bulky
LV distribution and switchgear equipment, which severely limit the number of EVs that it
can support. Besides, LFTs are unable to mitigate voltage flicker and unable to provide
perfect voltage regulation, especially at the distribution level as there is an inversely
proportional relationship between the transformer rating and its capability to perform
voltage regulation. Additionally, the saturation of the iron-and-copper LFT’s core results
in harmonics that usually yields high inrush currents. LFT also has limited performance
under DC-offset load unbalances. Other drawbacks of such LFT include its inability to
convert single-phase service to three-phase for powering certain types of equipment and
some environmental concerns, particularly when its mineral oil leaks [49–51]. Most of the
commercially available DC fast chargers have a total efficiency of around 93% if the LFT
has a 98.5% efficiency. The power losses and costs can be halved if this conventional LFT
is replaced with an SST or PET technology [48]. This approach enables direct connection
to the MVAC grid with the elimination of the LFT. The SST technology essentially covers
all functionalities of the LFT and AC/DC conversion stage. It also offers additional
functionalities such as galvanic isolation, bi-directional power flow, fault isolation and
fault current limitation. Simpler charging architecture adopting a common DC bus
configuration can be achieved as it offers the flexibility to also integrate large-scale DESs
such as RESs and ESSs with reduced conversion stages and higher efficiency by direct
connection to the MV utility grid at a comparable high voltage level [60–61]. Multilevel
converter systems are advantageous over bulky LFT for providing voltage adaptation as
required. Especially, SST modular multilevel converters have great benefits such as
reduced filtering effort, lower harmonics as well as robust operation and reduced switching
losses [62]. As SST is an emerging technology, previous publications focused primarily on
G2V on their SST system architectures without considering bidirectional power flow
capability for important applications such as V2G and V4G which can provide significant
technical benefits to the utilities such as frequency regulation and peak shaving. Moreover,
14
most of the previously published research employed Si IGBTs as the main switching
devices for their proposed SSTs. In addition to lacking the design steps and justifications
on the selection of converter topologies and their parameters, most previously proposed
SST configurations consider few aspects in regard to IEEE standards requirements and lack
a comprehensive analysis considering THD, PFC, power balance, voltage ripple,
efficiency, and costs while employing a highly efficient and commercially available SiC
MOSFETs for practical implementation. To investigate the SST performance while
considering prototyping costs, there is a lack of a detailed model-based design of two-stage
high-frequency SST combining the key features of CHB and DAB for ultra-fast charging
applications without a third stage. Different modelling methodologies of multilevel power
converters have been presented in various publications where some techniques such as
averaged modelling, and semi-analytical modelling were applied. However, there is still
no much research focusing on modelling of modular converters for ultra-fast charging at a
large scale incorporating a MVDC bus system that guarantees flexibility and optimum
efficiency in a wide range of operations. Also, for high fidelity of SST performance
analysis, there has not been any real-time simulation conducted with the implementation
of MIL in the literature. This research study became possible by choosing OPAL-RT real-
time simulator [63] with MATLAB/Simulink as an integrated testing and validation
platform using the MIL real-time simulation approach. This is because of the OPAL-RT’s
key features that include its fastest computing level for real-time simulation that achieves
more accurate results on FPGA for power electronics applications. Since most of the
research found in publications focuses on small-scale experimental setups in a few kW to
validate their theoretical design of various power conversion systems, an experimentally
verified method without the need to build a whole physical test bench is undertaken in this
study using OPAL-RT’s RT-LAB. RT-LAB is an integrated hardware and software system
with multi-core processors used for external validation and verification of power systems
and power electronics simulation models with full integration with MATLAB/Simulink.
Using the MIL real-time simulation technique saves time, manpower and cost for
industrial-based high-power applications such as EV charging. Verification of the proposed
model-based design approach is based on the MIL concept, for the first time in EV charging
applications, to validate transient response and dynamic behaviour of the proposed
15
switching simulation model in real-time. The MIL technique is advantageous compared to
any other method of modelling and simulation due to its ultra-high fidelity and very small
step time appropriate in capturing such transient behaviour owing to its unique simulator
based on FPGA. A detailed framework of the methodology undertaken for this research
study is outlined in the flowchart shown in Appendix A.
1.4 Research Objectives
The main purpose of this thesis is to develop, analyse and evaluate the realisation of a
two-stage multi-level SST system model with an MVDC-link utilising MVAC-MVDC and
MVDC-LVDC high-power converters directly interfacing with a three-phase utility-scale
MVAC power distribution feeder for EV ultra-fast charging applications. This is achieved
by developing a modular model-based design of an SST based on multi-modules with 3.3
kV SiC MOSFETs and an HFT, targeted for ultra-fast charging operation rated at 1.5 MW
of power and a maximum DC charging voltage of 1000 V. The specific objectives are:
1) Develop a realistic time-domain system-level simulation model of a 27.6 kV AC
grid-connected multi-module DPSS ISOP SST based on MVAC-MVDC CHB and
galvanically isolated MVDC-LVDC DAB converters, and an EV battery for the
UFCSEV system on MATLAB/Simulink to be integrated with OPAL-RT-LAB.
2) Implement appropriate control strategies and structures, and modulation schemes
to incorporate necessary functionalities: voltage balance, THD mitigation and PFC.
3) Optimise the design and sizing parameters of each component of the SST high-
power conversion system model to achieve full modularity as well as maintaining
low voltage ripples across the DC-links in compliance with IEEE standards.
4) Evaluate the developed system-level model performance, validate the UFCSEV
design by MIL real-time simulation, and analyse the efficiency of the SST system.
16
1.5 Thesis Outline
The present thesis consists of six chapters, which are organised as follows:
Chapter 1 serves as a generic introduction, beginning with a motivation for the topic
of transportation electrification and briefly describes the concepts of charging and V2G
with ESSs. The challenges of the charging infrastructures available today are outlined, and
the specific research problem addressed in this thesis is also defined. State-of-the-art
research approaches and the objectives of this thesis are also summarised.
Chapter 2 reviews the literature on latest ultra-fast charging technologies and
industry standards. It also provides an overview of SST structures and compares the various
SST converter topologies for ultra-fast charging applications, modelling types, and relevant
control strategies and modulation schemes presented in most recent publications.
Chapter 3 presents the proposed UFCEV architecture and describes in detail the
selected power converter topologies for the two-stage DPSS SST, and the first order design
parameters’ calculations. It also depicts the overall system-level model of the power circuit
of the modular SST system based on time-domain detailed switching modelling technique.
Chapter 4 demonstrates the selection of the control strategies, modulation schemes,
and modelling techniques implemented for the proposed SST charging system. It also
provides the detailed derivations of the transfer functions of the open loop and closed-loop
of the PI-controllers using averaged dynamic models, and small-signal models with state-
space averaging. It also shows the control technique implemented for the EV battery model.
Chapter 5 illustrates the design and simulation results of the developed SST model.
Various operating scenarios are also detailed for analysis and discussion of the transient
and dynamic performance of the system model validated by MIL real-time simulation.
Chapter 6 concludes this thesis by summarising the previous chapters, highlighting
the contributions, and presenting possible future works for extending such research studies.
17
Chapter 2. State-of-the-Art Review
This chapter provides a brief description and evaluation of presently available EV
fast-charging mechanisms, standards and protocols. A comparative study of the present
status and future implementation plans for ultra-fast charging infrastructures is outlined.
This chapter also reviews the latest publications which propose SST configurations and
topologies for EV ultra-fast charging applications. Different DC-link structures, control
schemes and modulation techniques of the relevant power converters are also compared.
2.1 EV Charging Classifications, Standards and Protocols, and Latest Technologies
Re-charging of EVs’ batteries can be performed using three developed approaches
namely, inductive, AC conductive and DC conductive.
Wireless charging can be enabled by the IPT mechanism. This technology already
exists in the industry but still has not been standardised yet. The IPT method is facilitated
by transferring the energy via an airgap from the power supply underneath the EV to the
EV battery through the magnetic induction capability based on the principle of
electromagnetic induction at high frequency. The main components of inductive charging
are two coils; the primary coil, which is placed on the road interface (charging pad) in the
building construction linked to the socket (power network), and the secondary coil which
is placed on the EV battery pack plate. This charging strategy is not fully mature yet due
to its high infrastructure cost, inefficiency, and low-power-transfer capability [65–67].
In contrast, the AC charging system transfers energy from the mains supply to the
EV battery through the EV’s on-board charger. This is the most common charging
technique as it provides much more flexibility in choosing where to charge whether at
home, workplace, or at a public charging station due to its lower-cost construction and
installation requirements. The AC conductive method is also known as Level-1 or Level-2
as defined by the SAE J1772, which refers to 120 V and 240 V charging, respectively. This
can be implemented almost anywhere provided that a standard electrical outlet with AC
power is available and also depending on the level of current that the supporting circuitry
can sustain. However, this conductive charging has two disadvantages namely, power
18
output limitation due to the size and weight restriction on the on-board charger, as well as
relatively long charging period. Additionally, the AC power of the utility grid outlet has to
be converted to DC power using an on-board inverter coupled with a DC-DC converter in
order to charge the EV battery via its DC positive and negative terminals [68, 69].
DC conductive charging, also known as Level-3; on the other hand, is suitable for
high-power and rapid charging applications, which usually take less than 1 hour for a single
charge. The power output of the DC chargers is limited only by the ability of the EV battery
to accept the charge. The biggest advantage of such a DC charger is that it can be designed
with either high or low charging rates and it is not limited to its weight and size. DC
charging solutions use off-board chargers which are located outside the EV, and this setup
provides flexibility because it does not take up space within the EV and also the charger
can be shared by several EVs. The higher the power charger delivers, the faster the charging
gets. Nevertheless, with higher power operation, the AC/DC converter, the DC/DC
converter, and the power control circuits become larger and more expensive. That is why
DC charging requires high investment for installation compared to AC charging and could
be availably accessed at public charging stations only. Although DC fast charging is quite
attractive as it delivers high power to the EV battery which results in very short recharging
times, DC charging has a number of limitations as the power cannot be increased infinitely
due to two technical limitations. First, the high charging current leads to high overall losses
in charger and battery (I2R). Suppose the internal resistance of the EV battery is R, and the
power losses in the battery can be expressed simply by I2R, where I is the charging current,
then the losses would increase by a factor of 4 times whenever the current is doubled. For
any EV charger, it is important that the cable is flexible lightweight so that the user can
carry the cable and connect to the EV. With higher charging powers, thicker and thicker
cables are needed to allow more charging current. Else, it will heat up due to the losses.
Today’s DC fast chargers can transmit charging currents up to 250A without cooling.
However, in the future with currents above 250 A, the charging cables would become too
heavy and less flexible for usage. This applies to CHAdeMO 3.0 that is 350-400 kW
charging enabled, charging with up to 600 A and 1.5 kV. The solution would then be to
use thinner cables for the given current with cooling systems built-in and thermal
19
management to ensure that the cable does not heat up which is more complex and costly to
implement compared to using a cable without cooling [68].
With the continuously growing number of EVs during the past decade, various
standards have been introduced globally by several industry governing bodies, including
the SAE and the IEC that stipulates specific standards of charger voltage, power range, and
configurations for manufacturers to enable EV charging based on established standardised
protocols in order to ensure charging compatibility and safety. The comparison of the
classifications defined by SAE and IEC is summarised in Table-2.1 where IEC defines four
unique modes, whereas SAE has six different modes for EV charging [69].
Table 2.1 Comparison of IEC and SAE Standards and Ratings for EV Charging [69]
Standard Category Ratings (Voltage, Current, Power) Applications
IEC
61851
Mode-1 1×250V, 3×480V
16A/ϕ, 13.3 kW/ϕ
Household outlet charging
On-board charging
Mode-2
1×250V, 3×480V
32A/ϕ, 26.6 kW/ϕ
Household outlet with on-board
charger or dedicated EVSE
Mode-3 3×400V, ≤ 80A/ϕ, 66.5 kW/ϕ On-board charging w/ dedicated
EVSE Slow or Fast charging
Mode-4 ≤ 1000V(DC), 300A, 300 kW DC fast charging
Off-board charger or dedicated EVSE
SA
E J
1772
AC
Level-1 1×120V, 12 A/16 A, ≤ 1.9kW Residential parking lots
On-board chargers Level-2 1×240V, ≤ 80 A, ≤ 19.2kW
Level-3 3-ϕ or 1-ϕ, ≥ 20kW Not implemented yet
DC
Level-1 200-400 V, ≤ 80 A, ≤ 36 kW DC fast charging
Off-board chargers Level-2 200-400 V, ≤ 200 A, ≤ 90 kW
Level-3 200-600 V, 400 A, ≤ 240 kW DC fast charging, Off-board chargers
There are various communication protocols, inlet connectors, and plugs that EV
manufacturers and other service providers have developed to ensure enhanced safety and
proper charging operation of the DC fast-charging system. These standards vary by
manufacturers and by geographical areas of countries. CHAdeMO, CCS, GB/T, and Tesla
are the four distinct standards for DC conductive charging coupler types that are used in
EVs today. The CHAdeMO standard was proposed by Japanese companies, such as Nissan
20
and Mitsubishi. CHAdeMO serves the largest number of fast-chargeable plug-ins around
the world. CHAdeMO 2.0 allows for up to 400 kW (1,000 V/400 A) high-voltage DC fast
charging [70]. The CCS Type-1, also known as the Combo-1, and Type-2, known as the
Combo 2 system, that uses the SAE J1172 standards are promoted predominately in North
America and Europe, respectively. A CCS connector has AC plugs along with two
additional DC pins for fast charging. CCS v1.0 supports power up to 80 kW at 500 V and
200 A, whereas the newest CCS standard, CCS v2.0, can support DC fast-charging up to
350 kW at the supply line voltages of up to 1,000 V, with the maximum output current of
500 A. Furthermore, Tesla Inc. has developed its own proprietary charging system
standards and plugs exclusively for Tesla EVs. Tesla’s 1st and 2nd generation versions of
superchargers have the capability of delivering up to 120 kW and 135 kW respectively.
These superchargers have a charging voltage ranging from 50 V to 410 V and a maximum
current of 210 A to serve power to either single EV charging or multi-EV charging split
power when multiple EVs are being charged simultaneously. Multi-vehicle charging can
be realised by paralleling the EVs. However, the 3rd generation of Tesla’s superchargers,
with better efficiency (96%), can support up to 250 kW of DC charging without power-
sharing between adjacent EVs plugged into the same stall of a supercharger [71]. Another
example of a CCS and CHAdeMO compatible DC fast-charger is Delta Ultra-Fast Charger
which can be supplied by a 3-phase, 400 V AC to provide up to 150 kW at 170-1000 V DC
and 300A with 94% peak efficiency [72, 73]. One of the most popular DC fast-chargers in
North America and Europe is the ABB Terra HP which complies with SAE Combo 1 and
CHAdeMO, which can be connected to a 3-phase 480 V AC to deliver a maximum output
power of 350 kW at 150-920 V DC and 375 A or 500 A, with peak efficiency at a full load
of almost just over 95% [74, 75]. Of the highest efficiency available in the market today
reaching 98% peak efficiency is the Tritium Veefil-PK in compliance with CCS Type 1
and 2 CHAdeMO, which can be supplied by a 3-phase, 480 V AC to provide DC fast
charging power of 350 kW at 950 V DC, 500 A (CCS) or 200 A (CHAdeMO) [76, 77].
These DC fast chargers are suitable for many EVs including heavy-duty types.
Configuration BB, known as GB/T, is only used in China which mandates the use of a new
standard (GB/T 20234.3-2015) for all new EVs even foreign EVs sold in China to follow
21
the GB/T standard. The current GB/T standard is for up to 237.5 kW at 950 V and 250 A,
whereas the new GB/T standard offers 900 kW charging at 1,500 V and 600 A [78].
For the operation of public transit busses that require charging as fast as filling up
a gasoline tank, ultra-fast charging technologies specified for EBs have been developed
over the past decade. Canada is home to four EBs’ manufacturers namely, Green Power
Motor Company [79], The Lion Electric Company [80], New Flyer Industries [81], and
Nova Bus [82]. Amongst the largest on-board battery capacity of these EBs is the Nova
Bus LFSe+ battery which has powerful modular options capable of storing up to 564 kWh
of energy [83]. For such public transit EBs, there are some world-leading electrification
technology developers including BTC Power [84], BAE Systems [85], Proterra [86],
SIEMES [87] and ABB [88]. The EB charging technologies can be categorised into two
types permitting flexibility on EB allocation and route planning:
1) Flash Charging through Overhead Rails for High-Power Charging
Operating for a charging system compatible with SAE J3105 standards, the
maximum charging power of this type that is available in the market today is 1500 kW with
a DC voltage ranging from 150-1000 V with a continuous 1000 A [89]. The charging
interface via roof-mounted fixed conductors and a structural mast inversely mounted
pantograph at 4–5 m height where the moving parts are on the stationary side of the
charging system, where the EB is charged within a few seconds or minutes depending on
the EB battery’s SoC. The most popular of this system is VersiCharge Go/MaxxHP built
by SIEMENS US with dedicated configurations for overhead and depot charger rated at
150-600 kW. SIEMENS SICHARGE is currently being developed for overhead and depot
chargers rated at 50-600 kW, with flexible dispenser configurations and semi-parallel
charging [87].
2) Plug-in at Depot via Inlet Ports and Connectors for Low-Power Charging
For a standardised charger of CCS type 1, J1772, the charging power is rated at 150
kW maximum. The most popular of this charging system is VersiCharge Ultra 50/175
developed by SIEMENS US, rated at 50 and 175 kW, taking only 30 minutes to fully
charge the EB battery [87].
22
Figure 2.1: Types of EV Charging Mechanisms: (a) DC Conductive Charging with Overhead
Indoor/at Depot Pantograph, b) DC Conductive Charging with On-route Pantograph,
I DC Charging with Off-board Charger, (d) AC Conductive Charging with On-board
Charger, I Inductive Wireless Charging [64, 74]
2.2 Grid Connections & Common Architectures of State-of-the-Art DC Fast
Charging Systems
The current state-of-the-art DC fast chargers available on the market today, capable of
delivering more than 50 kW typically have two main distribution link architectures for
connecting the DC fast charging systems to the MVAC grid. These are the AC common
link architecture and DC common link architecture as depicted in Figure 2.2 and Figure 2.3
respectively. Both systems require a three-phase step-down LFT that provides LV power
supply as well as galvanic isolation which separates the EVs from the grid [69].
The AC-link architecture utilises the secondary windings of the LFT as the main AC
distribution bus, where various loads or DESs can connect by independent AC–DC and
DC-DC conversion units. On the other hand, the DC-Link architecture provides a shared
DC distribution bus by using a single dedicated AC–DC conversion unit from the LFT.
The concept of the AC-Link multiport system is to have several interleaved AC-DC
rectifiers connecting the loads or DESs independently to the MVAC grid. This architecture
improves the reliability, redundancy, and overall system stability because each AC-DC
conversion stage is independent of the other systems connected to the LFT. Nevertheless,
one drawback of this architecture is the high unwanted harmonic effects of the several
independent AC-DC rectifiers on the utility grid, especially in high-power charging
operations [90]. When more dynamic loads and DESs such as ESSs, solar PV systems are
connected to the AC-link, the number of independent rectifier units in the system increases,
thus leading to more complex control, larger size, and higher cost [69].
23
The alternative approach is using the DC-link architecture, via a single front-end, high-
power AC–DC rectifier unit along with PFC that connects the MVAC grid via the MVAC-
LVAC LFT to a regulated DC voltage standalone substation. The shared DC distribution
bus is a simpler system that requires fewer power conversion stages compared to the AC-
link architecture; thereby, enhancing the overall system efficiency. Furthermore, the
common DC-link system provides a more flexible structure, which can be easily integrated
with DESs such as RESs and ESSs. In addition, the DC-link is less susceptible to power
conditioning issues compared to the AC-link system in terms of PFC and synchronisation.
Therefore, the DC-link architecture concept allows EV charging systems to act as
intelligent systems, reducing the adverse impacts of a higher EV penetration in the existing
electricity network and load diversification. The absence of reactive power in such a DC
system simplifies the control [93]. However, the reliability of the DC-link architecture
depends primarily on the front-end AC-DC conversion stage, which must be rated at higher
voltage and power levels than that of the AC-link system to directly interface to the
MVAC-LVAC LFT while allowing power transfer to the system loads. This yields more
stringent limits in terms of THD as required by the utility grid code. These constraints can
restrict the switching frequency of the semiconductor switching devices and the overall
system efficiency, particularly in high power of MW range applications. A recent
comparative analysis in [91] examined the impact in terms of harmonic generation of the
common DC and AC bus architectures specifically for EV fast-charging stations by using
a VSC connected with the grid found that the DC-bus architecture has a much better
performance than that of the common AC-bus architecture. This is due to the lower THD
in the current and voltage which yields a better power quality obtained in the case of DC-
bus configuration. Additionally, the EV charging rate is faster in the case of DC-bus
architecture as compared to the AC-bus. The system efficiency of the DC-link
configuration is higher because of the better power quality and power factor. Furthermore,
the DC-bus system in the dynamic state is more stable as compared to the AC-bus system.
Moreover, this architecture requires more complicated control strategies and DC protection
schemes than the common AC-link system due to the absence of voltage zero crossing in
the DC-link system [92]. The lack of established standards for protection coordination in
DC-connected systems makes this configuration less desirable [93]. However, employing
24
bi-directional AC-DC active front-end AC-DC rectifiers can enable smart networks, with
the capability to transfer energy from the EV battery to the grid as a V2G technology.
Figure 2.2: EV Charging System with AC Coupling
Figure 2.3: EV Charging System with DC Coupling
To the best knowledge of the author, the implementation technique of most
manufacturers’ charging architectures commonly uses one form of the AC-link architecture
due to the well-established standards and practices for the AC power distribution systems
[93]. Figure 1.1 illustrates a simplified block diagram of a typical DC fast-charging system
fed from a MVAC distribution grid via the MVAC-LVAC LFT, which provides an AC
distribution bus to the LV electrical systems, including EV chargers. The typical EV
charger contains two distinct conversion stages: an AC-DC rectification stage, where the
conversion of three-phase or single-phase AC input voltage to an intermediate DC voltage
25
happens, followed by a DC-DC power conversion stage, which interfaces the EV battery.
An isolated DC-DC converter can also be implemented by transforming the intermediate
DC voltage to a regulated DC voltage level of the EV battery through an HFT. This fulfils
the galvanic isolation requirements of IEC standards for safety purposes [94, 95].
From economical perspectives, the costs of the charging infrastructure hardware
include the EV charger and its pedestal. Based on several studies for DC fast chargers, the
average hardware cost for 50 kW DC fast charger is in the range between $20,000 and
$35,800, for 150 kW DC fast charger, the cost starts from $75,600 to $100,000 while for
350 kW DC fast charger, the cost ranges between $128,000 and $150,000 [96]. Advanced
ultra-fast DC chargers for EVs are properly configured to directly connect with a three-
phase power supply, having 480 V line-to-line AC voltage. Since this voltage level is
typically in-accessible in public installations, a dedicated MVAC-LVAC LFT is used to
supply three-phase power to the charging system. Besides adding complexity to the
installation and the requirement for confined concrete foundation, this bulky LFT increases
the size and cost. Moreover, for high-power applications, the LFT requires large conductors
and bulky switchgear protection equipment. As a result, this increases the overall cost of
the charging system. The control of existing utility grid requires a fast response from all
entities connected to it, which may not be possible with traditional LFTs. Moreover, other
drawbacks relating to LFT include limited performance in voltage regulation, additional
heating losses and reactive power control issues [97, 98].
Therefore, the existing ultra-fast-charging station architecture can severely limit the
number of EVs and charging power. With the recent research advancement to further
accelerate EV charging technologies, an innovative solution has been proposed in
publications by which the charging system can be directly interfaced with the MVAC grid
distribution feeder, without the need to install such a heavy and bulky LFT on which the
current architecture widely depends. Indeed, with the reach and technological
advancements in power electronics and materials technologies, especially with the
introduction of SST and WBG-based semiconductor devices, such development of
modular, high-power density, compact and efficient design withstanding high-voltages,
new ultra-fast charging systems appear to be forthcoming and promising in the next years.
26
2.3 State-of-the-Art SST-based Ultra-Fast Charging Structures and Converter
Topologies
In addition to providing power conversion and galvanic isolation with its lighter
weight and size, the SST has other unique features compared to the traditional LFT, such
as higher efficiency, better controllability, current limiting capabilities [99]. Most of the
SSTs proposed in publications aim at converting the grid line-frequency MVAC input to
an LVAC output via three conversion stages. The first stage has an active front-end rectifier
that converts the MVAC input into a DC voltage. An isolated DC-DC converter in the
second stage, which provides a galvanic isolation, then converts the DC voltage to establish
a DC-link at a desired DC voltage level. The third conversion stage inverts the DC voltage
into a final line-frequency LVAC output. Other designs with fewer conversion stages such
as the single-stage SST proposed in [100] can also be implemented. However, the three-
stage SST design explicitly creates a common DC-link which enables integrating DESs,
ESSs, EVs, and other DC loads [101, 102]. Comparative studies of the SST configurations,
topologies, and their applications have been summarised in [103–107]. Figure 2.4 below
classifies SSTs in different aspects and highlights in blue the selected category for the work
proposed in this thesis.
Figure 2.4: Classifications of SST [106]
With the several SST implementations proposed in the literature, this section
focuses on SST systems that are specifically designed for ultra-fast EV charging
applications. The main function of the SST is to convert the MVAC into LVDC while
27
providing galvanic isolation by employing an HFT inside the SST. Since the operating
frequency of the HFT is much higher than the LFT (tens of kHz versus 60 Hz), the size of
the HFT is much smaller than that of the LFT. Instead of the conventional LFT and rectifier,
an ultra-fast charging system's overall efficiency can be significantly improved by using
an SST, which also saves spacings compared to the state-of-the-art approach. This is
because a higher efficiency yields power savings for the owner of the EV charging station,
and a reduced system footprint leads to better utilisation of the charging infrastructure site
[93].
For successful adoption of the SST technology, it is important to point out that
connecting power electronics directly to the MVAC grid line introduces several issues in
terms of safety, protection, and power quality that need careful mitigation while also
complying with the current standards relevant for MV equipment and EV chargers such as
those developed by IEEE, IEC, CHAdeMo and SAE [123–131]. Although the installation
cost of the SST-based ultra-fast charging solution is significantly lower than that of the
LFT, the material cost of the SST is still five times higher than the LFT [132, 133].
However, the relatively smaller size of the MV SST results in lower power losses by half
of the LFT system. The SST weight and volume can even be reduced to nearly one-third
[132]. The overall system efficiency of the SST at 1 MW power is higher than that of the
LFT by 7% (from 91.5% to 98.5%) reducing the power losses from 85 to 15 kW as shown
in [96]. This increase in efficiency yields a reduction in electricity costs.
With a primary focus on the SST conversion stages, Figures 2.5-2.8 below show
four possible topological configurations [103]. Figure 2.5 shows a single-stage SST
topology that involves AC-AC conversion with an isolated HFT link, and a DC-DC
converter interfaced at the EV battery to obtain the desired DC voltage level. An example
of this topology is proposed in [134, 135]. Since there is no dedicated DC-bus on the input
side, this topology may not offer PFC, reactive power compensation, and bidirectional
power flow for V2G applications. This limits the functionality of SST in addition to the
low voltage conversion ratio and switching frequency of this topology despite the simple
control required [136]. Another SST topological configuration that uses a two-stage
conversion with an isolated DC-DC converter and provides an LVDC link is shown in
28
Figure 2.6 [137–139]. With the presence of this DC-link, this SST topology allows for
integrating RESs and ESSs while also performing reactive power compensation [140].
However, types I and II of the SST topological configurations are inappropriate for MV
applications because multi-level modules with complex control cannot be applied at the
high voltage side easily and it is difficult to achieve ZVS. In addition to these major
challenges, high switching losses also lead to lower efficiency in these two topologies.
Type-III SST topology, as shown in Figure 2.7 has a two-stage conversion with a dedicated
PWM rectifier with PFC and an MVDC-link [140–143]. With the use of a resonant
converter, it is possible to achieve ZVS and soft switching [136]. However, due to the
unavailability of an LVDC-link in this topology, the integration of RESs and ESSs at the
LVDC is not possible. For high-power ultra-fast charging interfacing an MVAC directly,
the SST topologies of types I, II, and III are not suitable for this application due to high
switching losses when operating at a high switching frequency, which results in low
efficiency. On the contrary, type IV topology which consists of a three-stage conversion
including both MVDC and LVDC links at the primary and secondary side of the HFT
respectively is illustrated in Figure 2.8 [144, 145]. The first stage consists of a front-end
active rectifier which shapes the input current and provides reactive power compensation
and harmonic elimination while also allowing bidirectional power flow [146–152]. The
second stage consists of HFT and a DAB DC-DC converter to regulate the active power
flow. The third stage includes a DC-DC converter to further stepped-down the voltage is
transferred to the LVDC-link to interface the EV battery for charging at the desired voltage
level. Table-2 below summarises the comparison of the four SST topological
configurations in terms of voltage regulation, modularity implementation size, and cost.
29
Figure 2.5: SST Type-I: Single-Stage SPSS Configuration with no DC-link
Figure 2.6: SST Type-II: Two-Stages SPDS Configuration with an LVDC-link
Figure 2.7: SST Type-III: Two-Stages DPDS Configuration with an MVDC-link
Figure 2.8: SST Type-IV: Three-Stages DPDS with MVDC- and LVDC-Link
30
Table 2.2: Comparison of the SST Topological Configurations for EV Fast Charging [107]
Top
olo
gic
al
Con
figu
rati
on
DC-Link
Regulation
Ad
van
tages
Dis
ad
van
tages
Size Cost
MVDC
-Link LVDC-
Link
Ty
pe-
1
(Fig
ure
2.5
)
Ex
ample
s in
[13
4,
135
]
N/A N/A Simple control
and
simple
modularity
implementation
No PFC
and poor
compensati
on in
reactive
power
Small
because
of the
absence
of a DC-
link
Low as a
result of
the
reduced
size and
filter
Type-
1I
(Fig
ure
2.6
)
Exam
ple
s in
[137
–139
]
N/A Good PFC and
capability to
integrate RESs
and ESSs at the
LVDC-link
High
switching
losses
resulting in
lower
efficiency
Medium
because
of more
power
devices
and
LVDC-
link
required
Moderate
because
of more
power
devices
required
Type-
1II
(Fig
ure
2.7
)
Exam
ple
s in
[140
–142
]
Good N/A
PFC and low
THD
Integration
of RESs
and ESSs
cannot be
implemente
d because
there is no
LVDC-link
Medium
because
of more
power
devices
and
MVDC-
link
required
Medium
as a
result of
more
power
devices
required
Ty
pe-
1V
(Fig
ure
2.8
)
Ex
ample
s in
[14
4, 1
45
]
Very
good
Very
good
Reactive power
compensation,
harmonic
elimination,
and simple
modularity
implementation
Complex
control and
bulky
capacitors
Large
because
of
presence
of
MVDC-
and
LVDC-
links and
more
required
power
devices
High
because
of high
bulky
DC-links
required
with a
large
number
of power
devices
31
Most of the SST-based MVAC grid-connected DC fast chargers proposed in
publications are implemented as single-phase single-port power conversion units that
directly interface to EVs. Nevertheless, these converters can also serve as the central front-
end rectifiers in a DC-connected fast charging configuration with proper modifications.
Moreover, by connecting three identical single-phase power converters in delta or wye
form with a phase-shift of 120 degrees between each phase, three-phase implementations
can be realised. To interface to the MVAC grid directly, the SSTs normally consist of
identical modules as building blocks all linked in cascade at the input to increase the
capability of voltage blocking in order to reach the desired voltage and power levels. The
outputs of these modules are then connected in parallel to provide a large output current at
the desired LVDC suitable for EV charging. Electric Power Research Institute (EPRI) and
Virginia Tech [108, 109] developed an MV fast charger topology consisting of three
modules that are connected in series at the MVAC grid side (2.4 kV) and in parallel at the
EV battery side. Each module of the AC-DC conversion stage is realised by a unidirectional
NPC front-end rectifier with PFC. The internal DC-link of each module operates at 1250
V DC where either Si IGBTs or SiC MOSFETs be used off the shelf. Following the
unidirectional rectification stage, two ISOP PSFBs convert the internal DC-link voltage to
the desired LVDC at the output. Since this topology uses a large number of active
semiconductor switches, the drawbacks of this SST implementation include limited
achievable efficiency and compactness as well as an increase in the overall system cost.
Additionally, the output of the PSFB DC-DC converter is fixed at 450 V DC, therefore, a
subsequent DC-DC stage is necessary to be included to accommodate the EV battery
charging profile. To integrate the EV battery in the design, a six-phase IBC (from the
battery point of view) is implemented in the system, which has an overall efficiency of
almost 96% at 38 kW.
In [110], a multi-level converter is proposed for direct connection to the MVAC
grid based on a three-level NPC topology suitable for a direct connection to a 3.3 or 4.16
kV MVAC grid. This SST topology offers better performance and higher flexibility due to
the presence of a bipolar DC-bus [110]. On the contrary, this topology requires a DC-bus
voltage balancing control, which leads to higher complexity and additional circuitry.
32
Another modular SST topology proposed in [111] included ten modules connected
in series at the MVAC grid side to share an 8 kV MVAC voltage. The first stage of this
topology is a multi-module of front-end rectifiers, where each module has an uncontrolled
diode rectifier bridge accompanied by two unidirectional three-level boost converter phase
legs in parallel, to create an internal MVDC-link rated at 1.4 kV. A DSP controller is used
to regulate the rectifier for PFC with multiple control to ensure low THD and voltage
regulation. The second stage consists of two ISOP half-bridge LLC converters that enable
soft switching. The DC-bus voltage is regulated via a traditional PI controller. To achieve
high efficiency in this design, the control strategy should operate the LLC converters in an
open loop with a 100% duty cycle while the output voltage is regulated by the front-end
rectifier which adjusts the DC-link voltage. However, this controller leads to a narrow
output voltage range that may not be able to accommodate the required EV charging
profile. For this reason, an additional DC-DC converter is required to follow the EV battery
voltage. The system efficiency of this topology is close to 97.5% at a rated load of 25 kW.
A 50 kW MV fast-charging system is developed based on the topology proposed in
[112–115], where three modules are connected in series at the MVAC grid side to share a
2.4 kV voltage. Each module has a single diode bridge to rectify the MVAC input. This
approach improves the system efficiency because it reduces the forward voltage drop on
diodes. PFC is achieved via the three-level boost converter within each module. The
following conversion stage consists of a half-bridge NPC DC-DC converter, an HFT, and
a diode bridge rectifier. In this SST, the half-bridge NPC DC-DC converter further reduces
the size of the HFT. Three loops with PI controllers are the control configuration for this
topology. The main loop regulates the DC bus voltage whereas the voltage balancing loop
maintains the capacitor voltage. The NPC loop controls the LVDC output voltage. This
control technique aims at mitigating input current harmonics by limiting the current THD
below 2%. For this SST system, the efficiency can exceed 97.5% at 50 kW. A similar
modular SST configuration with a similar per phase control scheme of three loops proposed
in [155] was adopted to interface a 12.47 kV MVAC grid for an ultra-fast charging
application rated at 350 kW. This high-power density (1.6 kW/L) solution has a system
efficiency of just over 98%.
33
Another SST design for EV charging is proposed in [116], where a front-end full-
bridge rectifier and a DHB converter are used in the AC-DC and DC-DC conversion stages
respectively. Integrating ESSs into the charging station is realised by a non-isolated DC-
DC boost converter, which is added between the rectification end and the DC-DC
conversion stages. This converter is capable of bidirectional power flow; however, it
utilises more active switches, which yields in low efficiency and poor switch utilisation.
Moreover, compared to unidirectional converters, the control is more complex. This design
was validated with a 140 V AC input voltage using a down-scaled prototype. Another
single-phase IGBT-based SST implementation to interface a 2 kV utility grid using an AFE
full-bridge rectifier with unified voltage balance and an isolated DC-DC current-fed DAB
converter with decentralised control is proposed in [117]. However, the experiment of this
design was verified at a reduced LVAC input voltage rated at 440 V. A similar single-phase
SST design of three ISOP modules was proposed in [118] with an active front-end full-
bridge rectifier and an isolated DAB DC-DC converter in two conversion stages
respectively was constructed with Si IGBTs and validated by an experimental setup with a
3.6-kV input voltage. However, the system efficiency of this converter was reported to be
less than 92%.
Another three-phase SST-based ultra-fast charging system rated at 400 kW with the
interface to a 4.8 or 13.2 kV MVAC grid was implemented by Delta Electronics [119].
Each module of the proposed multi-level topology is rated at 15 kW with 1-kV AC input
voltage considering line-to-neutral voltage. This topology consists of three ISOP modules
for 4.8 kV and nine ISOP modules for a 13.2-kV grid connection. The two conversion
stages included a front-end full-bridge NPC converter and an isolated LLC DC-DC
converter respectively. To the HFT primary side of the LLC converter is a three-level
converter, in order to reduce the stress on the resonant components., whereas the secondary
side is an active full-bridge rectifier to operate in synchronism in order to reduce the losses.
Because of the limitation of the LLC converter to only produce a constant 1 kV DC, this
design requires a subsequent non-isolated DC-DC converter to be connected to the EV
battery. Although this SST utilises 15 kV SiC MOSFETs to increase the system efficiency,
this results in expensive design costs. Another drawback is the complexity in control
required to allow for bidirectional operation due to the limitation of the LLC converter.
34
Each module of this design has an efficiency of 97.3% measured at 15 kW and 1 kV AC
input.
Another modular multi-module SST configuration for EV ultra-fast charging
proposed in [154] utilises a front-end three-level boost (TLB) rectifier circuit digital control
system and a half-bridge LLC DC-DC converter with 1.2 kV SiC devices. The entire
structure of the control system consists of four parts that include a PLL, PWM generators,
feedback control, and an ideal feed-forward loop. The main function of the ideal duty-ratio
feed-forward loop is to improve the input current THD at the zero-crossing. At the 3.8 kV
MVAC side, four modules are serially connected. The LLC transformers are used to
achieve voltage balancing. At 16 kW, the system efficiency is just over 98%.
Another MVAC-connected three-phase SST architecture for an ultra-fast charging
station to simultaneously charge multiple EVs is proposed in [156]. This configuration
utilises a two-level VSC to regulate the MVDC cascaded with an MVDC-LVDC DAB that
regulates the LVDC-link voltage. Each DAB module employs an MFT. Unlike
conventional DC fast charging station structure based on full rated dedicated charging
converters, partial power processing is implemented for independent charging control over
each EV using partial power rated DC-DC converters for charging individual EVs. This
approach eliminates redundant power conversion while processing only a fraction of the
total EV battery charging power. Compared to other Si-based EV fast-charging solutions
reported in the literature, this method reduces the circuit complexity and simplifies the
control strategy. A downscaled laboratory testbed with two charging ports rated at 117 kW.
The maximum power assumed for the charging unit to simultaneously charge 6 EVs is
rated at 702 kW with an efficiency of 95 and energy loss of 2.62 kWh. The control system
implemented in this prototype is a traditional SRF-PLL for synchronization with the three-
phase grid. A rotating dq0 reference frame is used for the grid current control The VSC’s
dedicated controller is employed to exchange active or reactive power with the grid. A
phase-shift modulation scheme is used for the DAB in addition to a dead beat predictive
current control to minimize any transient DC currents in the HF AC-link. To inject a desired
current into the EV battery, a full bridge resonant boost converter is used as the partial
power charger with the input current of the partial rated series element is controlled. To
35
ensure the operation of ZCS of all the active switches, a variable frequency control must
be implemented.
Another three-phase ISOP modular and scalable power conversion configuration
rated at 1.1 MVA is proposed in [156] with 6 SPMs, each consisting of an NPC full-bridge
AFE stage and an isolated DC-DC DAB stage. A three-level NPC full-bridge and a full H-
bridge are used on the 2.15 kV MVDC and 750 V LVDC sides of the DAB converter,
respectively. Compared to other SST-based solutions where a centralised controller is used
to ensure module-level voltage and power balancing, a fully decentralised control is
implemented for the DC-DC stage as a DC transformer based on only local sensor feedback
and the AFE stages based on encoded gate pulses received via optical fibres are controlled
using feedback of only the LVDC output with no communication required with other
modules. Unlike other SSTs where large capacitors are used to suppress double-line
frequency voltage variations on the MVDC-link originating from AC power pulsations
through the SPMs, this configuration requires reduced capacitance size on the MVDC-link.
A grid-side breaker and a pre-charge circuit is used for soft start-up of the system, which
also has a central controller responsible for regulating the LVDC output by dynamically
controlling the grid current. The inherent voltage and power balancing capability is
demonstrated through detailed switching model simulation on PLECS. The efficiency of
the DAB stage is reported to be > 99%.
Another three-phase ISOP SST-based power electronic architecture for ultra-fast
charging three types of EVs with batteries of vastly different voltage and power ratings is
proposed in [157]. This structure comprises of MV delta-connected CHBs as an active
front-end rectifier and QABs utilised an isolated DC-DC conversion stage due to its low
cost and high efficiency. The QAB has four FBs interlinked through the windings of MFTs.
Three sub-modules of the CHB and one QAB form a cell in each phase, where three cells
form a cluster. Three charging ports are derived from the cells of three phases where the
output of the QABs of the cells in each phase are paralleled to form one charging port. The
three-phase QABs’ output voltages are controlled according to the specified EV battery
voltage and the EV model type. Devices for the CHB with a lesser current rating can be
utilised since the total current decreases as a result of the magnitude of zero sequence
36
current. To reduce the reactive current in the MFTs, the turns ratio of the MFTs in the three-
phase clusters are adjusted to match the output voltage of the QAB where all sub-modules’
capacitor voltages of the three phases are equal. The charging power drawn from each port
depends on the number of EVs being charged; thus, the power ratings of the three charging
ports can also be different. This creates an imbalance in the system where cluster power
causes the sub-module DC-link capacitor voltages to deviate from their desired value. This
also leads to drawing unbalanced currents from the grid. In this case, the power needs to
be circulated among the SST clusters by utilising zero sequence current in order to balance
the power among the clusters. A balancing winding is added to each of the MFTs of the
QAB this architecture and is utilised to reduce the unbalance in the delta-connected clusters
by a parallel connection such that a circulating current flows among the transformers of the
three phases. This also reduces the magnitude of the zero-sequence current required to
balance the cluster powers. A 4 kVA scaled-down prototype is presented to verify the
effectiveness of this SST system by interfacing it to 220 V. The simulation model presented
includes a 3.3 kV grid, three sub-modules in each cluster, and three charging ports rated at
500 kW, 300 kW, and 200 kW for Port-1, Port-2, and Port-3 respectively.
A variety of multi-level AC-DC converter topologies, such as the MMC, are
suitable for very high powers (several MWs) and are therefore only applicable to EV ultra-
fast high-power charging stations with multiple charging spots. For conventional LFT-
based charging stations, modularity is not possible as an extension of voltage and power
capabilities requires the replacement of the LFT. The modular design with ISOP
configuration is preferable as it can achieve a better inherent redundancy by adding
additional modules even with using Si LV MOSFETs or IGBTs. With V2G capability, a
bidirectional power flow can also allow the integration of RESs and ESSs to the grid.
Moreover, the size of the passive filters at the MVAC grid side can be reduced by the multi-
level waveform generated by the modular front-end rectifiers. Nevertheless, a large number
of components of switches and associated gate drivers in this modular design can increase
the system size and cost, offsetting the feature brought by smaller passive filters. The
control complexity increases in order to maintain a balanced voltage sharing between the
modules with the input series connection to the MVAC grid. System reliability may get
reduced as a result of the large number of components required [93].
37
With the recent development of SiC MOSFETs with blocking medium voltages of
10–15 kV, a single-module SST converter can now be realised to be directly interfacing
MVAC grid. The most significant advantages of this system implementation are reduced
control complexity and the potential of achieving higher reliability and efficiency of the
system. A 10-kW single-module SST proposed in [120] was designed to interface a 3.6 kV
MVAC input using 13 kV SiC MOSFETs and JBS diodes with an internal MVDC-link
voltage of 6 kV. A similar design with an LCL filter is depicted in [153]. A unipolar
modulation with one leg operating as an unfolding bridge with LF is implemented to reduce
the switching losses of the front-end rectification stage. To further reduce the losses, the
switching frequency of the PWM leg of the H-bridge rectifier is limited to 6 kHz only. A
DHB converter with 13 kV SiC MOSFETs is chosen in this design as the isolated DC-DC
conversion stage with a phase-shift closed-loop control of the DHB involving two control
loops, an inner current loop, and an outer voltage control loop to regulate the output voltage
of 400 VDC. To mitigate the steady-state offsets, the PI controller is used for voltage
harmonics compensation. However, higher-order current harmonics are not included in this
control strategy as they lay beyond the cut-off frequency of the LC filter. The conversion
of sensor output into pulses functions as the main protection system against disturbances
[144]. Soft switching is also realised by turn-on ZVS achieved for all the MOSFETs. The
HFT turns ratio of N = 15 was implemented to convert the MVAC on the primary side into
LVAC at the secondary side. The overall system efficiency measured at 10 kW was 94%.
Another single-module SST with a larger power rating proposed in [121, 122] is
designed to interface a 3.8-kV MVAC input based on 10 kV SiC MOSFETs. A full-bridge
rectifier with a 7 kV internal MVDC-link is used for the front-end conversion stage. Similar
to [120], a unipolar modulation with the triangular current mode is adopted for the rectifier
to reduce the switching losses. However, the switching frequency can be varied from 35 to
75 kHz for the PWM leg. Unlike the limitation of [120], an LC-branch between the
terminals of the two-phase legs is inserted, to achieve a high switching frequency at MV
with soft-switching over the whole line period while also limiting the current harmonics.
The isolated DC-DC conversion stage is implemented using an LLC series resonant
converter with 10 kV SiC MOSFETs half-bridge on the primary side of the HFT. ZVS is
achieved for all MOSFETs of the LLC converter which operates at a fixed frequency to
38
output a regulated voltage of 400 VDC by adjusting the internal DC-link voltage of 7 kV
DC through the rectifier. The system efficiency measured at 25 kW is 99.1%.
Tables 2.3 and 2.4 summarise a comparison of a number of SST-based topologies
and their control techniques discussed in this section for EV ultra-fast charging systems.
Different parameters that are considered in this table include voltage and current
harmonics, overloads, voltage drop under varying loading conditions, DC offset load
unbalances, and protection against disturbances. It can be concluded that most of the
research in the literature focuses primarily on the THD mitigation of input current in order
to meet the IEEE power quality standards, whereas other parameters such as voltage drops
under varying loading conditions are not thoroughly investigated.
39
Table 2.3: Comparison of State-of-the-Art SSTs for EV Ultra-Fast Charging – Part (a)
SS
T T
op
olo
gy
Nu
mb
er o
f P
ha
ses
MVAC
Voltage (L-L
RMS), SST
Rated
Power,
Number of
Cells per
Phase
Converter
Topologies Number of
Components per
Module
Control Strategy
Sim
ula
tio
n
Mo
del
Ex
perim
en
tal
Pro
toty
pe AC-DC
Stage
DC-DC
Stage
Sw
itch
es
Dio
des
Tra
nsf
orm
ers
[11
2] 1 2.4 kV, 50
kW, 3
TLB NPC 12 16 2 Three loops PI
Controller
[15
8]
3
3.3
kV
, 1
MW
, 3
22
0 V
, 4
kV
A, 1
Delta-
connected
CHB
QAB 28 28 3 PLL, PR and PI
Controllers
[1
44]
1 3.6 kV, 10
kW, 1
CHB DHB 8 8 1 PWM
[15
4] 1 3.8 kV, 16
kW, 4
TLB Half-Bridge
LLC Converter
6 16 2 PLL
[12
1, 1
22
] 1 3.8 kV, 25
kW, 1
ITCM LLC Series
Resonant
Converter
10 0 1 Phase Shift
Modulation
[15
6]
3 4.16 kV, 2.1
MW, 6
charging
ports
VSC DAB and a
Current-fed
Resonant Full-
Bridge Boost
Converter
22 8 1 SRF-PLL
[11
1] 1 8 kV, 25 kW 3-level
AFE
LLC
Converter
8 12 2 DSP Controller
[15
5] 3 12.47 kV,
350 kW
3-Level
Boost
Converter
DAB 12 14 1 TPS Controller
[15
7]
3 13.2 kV, 1
MW, 6
NPC DAB 16 4 1 Decentralised for
DAB with BPSM
[11
9]
3
4.8 kV or 13.2
kV, 400 kW
3-level
Dual
NPC
LCL
Resonant
Converter
16 4 1 Complex Control
for LLC Converter
40
Table 2.4: Comparison of State-of-the-Art SSTs for EV Ultra-Fast Charging– Part (b)
SS
T T
op
olo
gy Capabilities and Advantages Limitations and
Disadvantages
Pro
toty
pe
Sy
stem
Eff
icie
ncy
[11
2]
Unidirectional power flow, low current THD
below 2%, PFC, high power quality, and
high efficiency with double pulse test
No protection against s overloads
or disturbances in system
96.6%
[15
8]
PFC and Power balancing using zero
sequence current and balancing winding
Requires increasing the window to
accommodate the additional
winding
97.7%
[1
44]
Bidirectional power flow, low voltage THD
~ 3%, AC systems decoupling, steady state
and voltage drop analysis and has protection
via conversion of sensor output into pulses
No control for steady state DC off-
set load unbalances 95.2%
[15
4]
PFC, low THD at zero current crossing, and
Voltage regulation, input current regulation,
voltage balancing
Not reported 98.4%
[12
1, 1
22
]
Bidirectional power flow, PFC, and current
THD according to the IEEE 519 Standard,
Calorimeter loss distribution and efficiency
measurement
No protection against system
disruptions and overloads, and no
control for DC off-set load
unbalances
99.1%
[15
6]
Low losses, ZVS or ZCS operation Mo modularity. suited only for
applications with a low input
voltage and high output voltage
95 %
[11
1]
PFC, low THD for both current and voltage,
and voltage regulation against both load and
source
No control for DC off-set load
unbalances due to mismatching of
LLC transformers
97.5%
[15
5]
High efficiency, PFC, low current THD,
modular design, voltage regulation, and
double pulse test
High cost due to many expensive
SiC MOSFETs required
98.1%
[15
7]
Balancing of module level voltage and
power flow utilizing complete decentralized
control, has protection using a grid-side
breaker and a pre-charge circuit soft start-up
No analysis available for THD,
PFC and ZCS/ZVC
Not
reported
[11
9]
Modular design with bidirectional power
flow, low THD and PFC.
Fixed output voltage and power,
high cost, complex control, poor
switch utilisation
96.5%
41
2.4 Viable Multi-level Converters for the MV ISOP DPSS SST
High-power electronic converters can operate at various voltage levels; HV, MV,
and LV. The classic IGBT-based 2-level converter configuration can be used for LV
applications. For MV and HV applications, there are two possible options, either using:
• 2-level converters or few cells using MV Si semiconductor switches, or WBG
(GaN or SiC) devices with high blocking voltage capability, connected in series.
• Multi-level converters or a large number of cells with LV SiC or Si devices.
Each multi-level converter consists of multiple power semiconductor switching
devices and capacitive voltage sources, which are utilised to generate a voltage waveform
of multi-steps. This stepped voltage waveform is produced by switching the power
semiconductor devices in such a way that the capacitive voltage sources are added to the
desired voltage. A multi-level converter has a defined number of levels which is equal to
the number of constant voltage values that can be produced between the output terminal
and the neutral. With at least three different voltage levels, the converter can be classified
as multi-level. For instance, if each phase of the converter generates three different voltage
levels, then it is called a three-level converter. With the current advancement of MV SiC
devices which many types already exist in the market, multi-level converters represent an
attractive solution for high-power applications including ultra-fast charging for EVs due to
their advantages in terms of output power quality and filtering requirements. In addition to
their high-power ratings and increased efficiency, they have reduced harmonic content,
lower common-mode voltages, and possible fault-tolerant operation. A number of
topologies for multilevel converters have been mentioned in publications, with some
configurations boasting bidirectional power flow operation. Four main modular multi-level
topologies of the most widely MV grid-tied converters used in industry, considered for
each conversion stage of the DPSS SST system proposed in this thesis, are introduced, and
categorised as follows:
42
2.4.1 Multi-level Converters for the AC-DC Conversion Stage:
1) Flying Capacitor Converter
The FC converter consists of several conventional two-level VSCs, but with some
modifications, where each level is connected one over the other with flying capacitors
that are utilised to clamp the voltage across the devices to a fraction of the total DC
voltage, but where the load cannot be directly connected to the neutral. In order to obtain
zero voltage level in this topology, the load is connected to the positive or negative bar,
through the flying capacitor with opposite polarity with respect to the DC-link. Besides
its modular structure which can easily be extended to achieve higher voltage levels and
power rates, the FC has other advantages and disadvantages as summarised in Table 2.5.
2) Transistor-Clamped Converter
The TCC, also known as the NPP has the same structure as the FC, but bidirectional
switches are utilised instead of the flying capacitors. This topology allows for a
controllable path for the currents and better control of the power loss distribution [159].
3) Modular Multi-level Converter
The MMC, also known as M2C, was introduced in the early 2000s and has been
implemented in several industrial applications. Formed by connecting several identical
modules, the MMC topology consisting of an AC/DC converter and a floating capacitor,
in series to obtain a single or three-phase output voltage [159]. The module switches are
utilised to connect or bypass their respective capacitor to the total array of capacitors in
the converter leg in order to produce the multilevel waveform.
4) Cascaded H-Bridge Converter
The CHB rectifier consists of a series connection of several single-phase full-bridge
(HB) converters. Each HB cell consists of four switches to enable independent DC
voltage at the load and represents two voltage source phase legs; whose line-to-line
voltage equals that HB’s output. A single HB cell can generate three different output
voltages as a result. The output voltages of the individual HB cells can be combined to
43
form different output voltage levels, this increases the total converter output voltage and
power rating.
As the emphasis has been placed on the modularity of these converter topologies,
a modular system is a system comprising of identical building blocks of similar sub-
systems for the aim to the scalability of service and effectively reduce manufacturing
costs while also providing optional degrees of redundancy, by implementing a control
that can bypass defective modules [168].
2.4.2 Isolated Bidirectional Converters for the DC-DC Conversion Stage:
With the wide range of available isolated topologies such as the flyback, Cúk and
forward converters that feature simple circuit design and a low number of switches, these
classic converters suffer from the poor transformer and switch utilisation. In particular, the
Cúk converter has drawbacks such as suffering from hard switching and requiring two
inductors and two blocking capacitors with large current handling capacity. It also has
unevenly distributed switch stresses. These limitations make the isolated flyback, forward
and Cúk topologies not suitable for the isolated DC-DC conversion stage of the MV DPSS
SST. Four possible topology candidates for the bidirectional DC-DC converter are:
1) Single-Phase Dual Active Bridge
This DAB consists of two full bridges; one on the primary side and another one on
the secondary side, with an HFT in between. Leakage inductance is added to the HFT
primary side as energy storage and to adjust the shape of the flowing current waveform.
2) Three-Phase Dual Active Bridge
The three-phase DAB has three half-bridges on both the primary and secondary
sides of the HFT. Three inductors are added to the primary side of the HFT to be used for
energy storage. Either three single-phase HFTs or one three-phase HFT can be used in the
circuit.
44
3) Bidirectional Isolated Push-Pull Converter
The Bidirectional Isolated Push-Pull has a centre-tapped transformer with two
windings on the secondary side and one output inductor. The output inductor operates at
double the switching frequency of the semiconductor switching devices. The transformer
is poorly utilised and requires a higher power rating because each winding conducts only
during half of the switching period.
4) LLC Resonant Converter
This resonant converter generates nearly sinusoidal transformer currents resulting
in low switching losses. This allows for operating at higher switching frequencies and
higher power densities. This converter topology has a capacitor in series with the
transformer leakage inductance. This capacitor blocks the DC current and prevents
saturation of the HFT, whose primary and secondary sides are both connected to a full-
bridge circuit.
Table 2.6 compares these four topologies and describes their key features and major
drawbacks.
45
Table 2.5: Comparison of Modular Multi-level AC-DC Converter Topologies [159–167]
To
po
log
y
Nu
mb
er o
f S
wit
ch
es
per
Mo
du
le
Vo
lta
ge
Ba
lan
ce
Co
ntr
ol
Major Advantages Major Disadvantages
FC
8
Com
ple
x
• The several capacitors allow the
converter to ride through deep voltage
sags and short power outages.
• Can control both the real and reactive
power.
• Provides switch combination
redundancy for balancing different
voltage levels.
• Higher output levels require a large
number of capacitors making the
converter more bulky, expensive, and
difficult to package.
• Requires high switching frequencies to
keep the capacitors balanced.
• Requires a complex start-up control
for pre-charging the capacitors to the
same voltage level.
• Poor switch utilisation and efficiency.
TC
C
12
Com
ple
x
• Requires only half the number of
switches to handle half the voltage
compared to the FC allowing double the
switching frequency and a better output
waveform for the same current.
• Simple control of the power switches’
gates since only one transistor is
switched at once: proportional relation
between the transistor turn-on state and
the output voltage.
• Requires a voltage balancing strategy.
• Requires a large number of transistors.
46
MM
C
8
Co
mp
lex
• Highly scalable for MV and HV
levels.
• Low harmonic content.
• Low filter requirements.
• Does not require additional capacitors
for the HVDC-link as each module has
its own capacitor.
• Increasing the converter levels yields
in a decrease in the module switching
frequency without compromising the
power quality.
• Requires a complex control to pre-
charge the capacitors and balance the
average value of the voltage across each
sub-module capacitor. C
HB
4
Sim
ple
• Can generate more output voltage
levels than the FC. This allows the
CHB to have lower switching
frequencies for the same output voltage
waveform.
• Can operate at lower switching
frequencies allowing for air cooling and
higher fundamental output frequency
without derating and without the use of
an output filter.
• Allows for fully modularised layout
to easily reach MV by adding more
cells to each phase.
• Easy packaging as each level of the
converter has the same structure.
• Does not require additional clamping
diodes or voltage balancing capacitors.
This results in smaller size and lower
cost.
• Allows for soft switching, thus, does
not require bulky and lossy snubber
circuits.
• Simple balance control of the DC
capacitor voltages since the average
charge of each capacitor over one line
cycle equals zero.
• The maximum voltage of each H-
bridge DC-link is limited by the voltage
rating of its power switching devices.
This limits the CHB from generating a
higher voltage at the DC-link.
47
Table 2.6: Comparison of Isolated Bidirectional DC-DC Converter Topologies [169]
To
po
log
y
Nu
mb
er o
f
Sw
itch
es p
er
Mo
du
le
Major Advantages Major Disadvantages
Sin
gle
-Ph
ase
DA
B
8 • Has the fewest passive components.
• Comparatively very good
efficiency.
• Operates with evenly shared
currents in the power switches.
• Has soft switching properties.
• Possibility for large RMS DC
capacitor currents to occur
especially on the secondary side of
the HFT.
Th
ree-P
ha
se D
AB
12 • Smaller RMS DC current compared
to the single-phase DAB.
• Can employ components (switches,
inductors, and HFT) with lower
ratings compared to the single-phase
DAB.
• Does not require extra inductors.
• Achieves good overall efficiency.
• Requires a large number of
switches and inductors which leads
to higher losses.
• Operating within wide power and
voltage ranges leads to high
conduction and switching losses,
and thus low efficiency.
Bid
irect
ion
al
Pu
sh-P
ull
Co
nv
erte
r
6 • Can handle high current with
reduced inductor requirements.
• Fewer switches required.
• Requires a complex HFT design
but with ineffective utilisation.
LL
C R
eso
na
nt
Co
nv
erte
r
8 • Can operate at higher switching
frequencies and higher power
densities.
• Has good efficiency.
• Requires large sizes of inductor
and capacitor.
• As the actual switching frequency
varies significantly with the
supplied voltage and the load, in the
case of no load, it is impossible to
control this converter since this
situation requires infinite switching.
48
2.5 Control Strategies and Modulation Techniques for Multi-level Converters
2.5.1 Control Strategies for Multi-level Converters
There are different novel control strategies and techniques which have been applied
to various power electronic converter topologies, with the aim to improve the power
converter steady-state and transient performances, fault ride-through capabilities,
reliability, and efficiency. With the advancements of DSP and microcontroller
technologies, more sophisticated control techniques in comparison with the classical linear
control methods have been implemented [170, 171]. Figure 2.9 provides an overview of
the control classifications and methods applicable to multi-level converters.
Linear control is the most popular control technique for multi-level converters
because it is well established in the literature. It can be implemented in natural, stationary,
or synchronous reference frames [171]. In the natural reference frame, three PI error
compensators can be utilised in the linear control to derive the required voltage which the
power converter aims to generate in order to obtain the desired output current. Additional
feed-forward corrections or PLL algorithms can be utilised to compensate for the current
amplitude and phase errors, especially for cases with utility voltage disturbances [171].
Alternative linear control options can be used to convert the phase currents into a rotating
synchronous reference frame (direct and quadrature components (d-q) to obtain two DC
equivalent currents which allow currents to be controlled using two PI compensators to
ultimately reduce the error on the fundamental components to zero. In a stationary
reference frame (α-β), the implementation of linear control is possible using variable-
frequency generators to produce the reference voltages. The key advantage that linear
controllers based on PI compensators offer is that they can produce good reference tracking
performances. However, they may have a limitation in their dynamic response, especially
when compared with more sophisticated control methods, which can provide faster
transient response [171–173]. To overcome the limitation of PI controllers in terms of
reference tracking error and harmonic rejection, linear control with PR compensators has
also been implemented for multi-level converters in natural [174] and stationary [175]
reference frames without using feed-forward compensations [176].
49
To control the phase currents to the desired references, a feedback control loop as
a hysteresis control is typically utilised with 2-level hysteresis comparators [171]. In
addition to its good dynamic performance, hysteresis control has been successfully applied
to multi-level converters [177–181] due to its simplicity and robustness to maintain the
switching frequency constant by varying the tolerance band of the hysteresis control
comparator although the switching frequency relies primarily on the AC voltage and the
load parameters [171].
More advanced control approaches have also been proposed in publications as
potential methods to overcome the limitations of traditional control techniques. For
instance, neural network [182], Fuzzy logic [183, 184], sliding mode [185] and MPC and
DBC predictive control techniques [186–190] have attracted significant research interest
for power converter applications. DBC has been applied to current control in rectifiers
[191] and DC-DC converters [192]. DBC control provides a faster dynamic than is possible
using a discrete-time control as it employs the discretised system model to calculate the
optimal voltage reference value that the converter must apply to track the desired current
reference with zero error at the next sampling instant. However, DBC is very sensitive to
model parameter errors and delays in the measured variables, and it is also difficult to
include non-linearity and other constraints. Similarly, MPC uses a discretised system
model to predict the system behaviour for every possible converter state. MPC requires a
suitable modulation technique may if considering a continuous control set [170].
Nevertheless, considering the finite number of output states of the power converter, FCS-
MPC [193–195] is usually considered because of its robustness and simple implementation
due to the absence of a modulator. A different approach has been applied for the output
current control in power control in active front-end rectifiers [196, 197]. However, the lack
of a modulator is the main drawback of FCS-MPC since the controller can select only from
a limited number of output voltages vectors of the converter. Besides, the cost function
minimisation algorithm requires high computational effort [170, 186, 187]. FCS-MPC has
been applied to several converter topologies and applications [188, 196, 198, 199] and more
advanced schemes which include modulation techniques inside the FCS-MPC algorithm
have been proposed [200–202]. In all these publications, the duty cycles are calculated by
solving an optimisation problem to determines the optimal control action in order to track
50
the desired reference with minimal error. For multidimensional optimisation problems,
multi-objective control can become rather complex since a solution to a must be
determined.
2.5.2 Modulation Techniques for Multi-level Converters
Several modulation strategies and techniques have been developed for multi-level
converter topologies, which can be classified depending on the switching frequency they
produce for operating the semiconductor switching devices as can be seen from Figure-
2.10 below [203]. With the aim to improve the converter modularity, reliability, efficiency,
and waveforms quality, implementing such modulation techniques take advantage of the
increased degrees of freedom provided by the higher number of possible switching states
provided by the multi-level converter topologies [204].
Multilevel modulation methods are required because of the inherent complexities of
multi-level converters due to a large number of power semiconductor switching devices.
Modulation techniques can be categorised based on the domain in which they operate into
two types: voltage level-based algorithms and space vector-based algorithms.
Of the most highly adopted voltage level-based algorithms are the PWM modulation
techniques, which operate in the time domain, due to their simplicity, high performance,
fixed switching frequency, and easy implementation in both digital and analogue hardware
[205]. Carrier phase-shifted PWM (CPS-PWM) is a multi-carrier-based sinusoidal PWM
that can be implemented for multi-level converters such as the CHB, where each CHB cell
is assigned with two carrier signals which are modulated independently using the same
reference signal. In order to generate the stepped multi-level waveform, a phase shift across
all the carriers is introduced [206]. The switching frequency of each cell in an n-level
converter is n times lower than the converter output frequency.
Level-shifted PWM (LS-PWM) is another multicarrier-based sinusoidal PWM that can
be obtained by arranging the carriers in shifts. In this modulation technique, each carrier
represents a possible output voltage level of the converter [159].
51
Figure 2.9: Control Strategies for Multi-level Converters
Figure 2.10: Classification of Multi-level Modulation Techniques for Multi-level Converter
52
The LS-PWM can be classified depending on the consecutive arrangement of
carrier signals as follows [49]:
• Phase Disposition PWM (PD-PWM), where all carrier signals are arranged
in vertical shifts with respect to each other.
• Phase Opposition Disposition PWM (POD-PWM), where the positive
carrier signals are arranged in phase with each other, but in opposite phase
with the negative carrier signals.
• Alternate Phase Opposition Disposition PWM (APOD-PWM), where each
consecutive carrier signal is in the opposite phase with its predecessor.
On the other hand, space vector-based algorithms are modulation techniques where
the reference voltage is represented by a reference vector to compute the switching
times and states instead of using a phase reference in the time domain. Since they have
redundant vectors, space vector algorithms can generate the same phase-to-neutral
voltage, which can be utilised to enhance the multi-level converter properties. Such
properties include minimizing the switching frequency, controlling the DC-link voltage
when floating cells are in use, enhancing the voltage spectrum, and reducing the
common-mode DC output voltage and the effect of over-modulation of output currents.
Space vector modulation techniques are not widely used in the industry because they
require more hardware than PWM carrier-based techniques. Space vector modulation
requires at least three stages: a stage to select the vectors for modulation, a stage to
compute the duty cycle, and a stage where the sequence for the vectors is produced
[206]. SVM can be classified into two categories: 2D and 3D.
The 2D-SVM works by transferring the three-phase voltages of the multi-level
converter to the α-β plane while determining the nearest vector to the reference vector
to produce the switching sequence and their duty cycles. On the other hand, the 3D-
SVM is used for unbalanced systems or if a zero sequence or triple harmonics are
present in the system. In this case, the state vectors are no longer located in the α-β
plane; however, the α-β plane is extended into the third dimension with a γ axis in order
to calculate the state vectors under these conditions, The 3D-SVM modulation
technique is applicable for all applications that provide a 3D vector control.
53
The single-phase modulation (1DM) is another SVM that utilises a simple
algorithm to determine the switching sequence and corresponding times by generating
the reference phase voltage as an average of the nearest phase-voltage levels. The 1DM
requires post-processing to select one stage between the possible redundant states,
therefore, this technique is independent of the chosen topology [206].
Table 2.7 summarises the high switching frequency modulation techniques which
can be used to select the most suitable technique for the AC-DC conversion stage of
the DPSS SST system.
Table 2.7: Comparison of High-Frequency Modulation Techniques for Multi-level Converters
Mo
du
lati
on
Tec
hn
iqu
e
Alg
ori
thm
Ha
rdw
are
Req
uir
emen
ts Remarks
PS
-PW
M
Sim
ple
Minimal • Each converter cell is assigned with a pair of carrier signals for easy
control to distribute the power evenly among the cells across the
entire modulation index. • The devices can operate at a lower
switching frequency resulting in lower losses.
• This technique allows a reduction in the input current THD.
LS
-PW
M
Sim
ple
Minimal • Better than the PS-PWM in terms of harmonic cancellation
properties.
• Suffers from uneven power distribution among the cells resulting
in distortion in the input current of the multi-level converter circuits.
2D
-SV
M
Co
mp
lex
Extensive • Uses simple calculations.
• Only applicable for balanced three-phase balanced systems.
3D
-SV
M
Co
mp
lex
Extensive • Can be used for balanced and unbalanced three-phase systems
with or without neutral or triple harmonics and for balancing DC-
link capacitor voltages.
• Useful for compensating the zero sequence in active power filters.
1D
M
Sim
ple
Extensive • Its computational costs are low.
• Independent of topology and the number of phases and levels.
• Equivalent performance to that of the 2D-SVM and 3D-SVM.
54
2.6 Modelling Approaches and Simulation Software Tools for SSTs
Besides the complexity of the actual designs of the SST, analysing its performance as
a component of an actual power system raise huge difficulties. That is why computer-based
simulation is considered a reasonable alternative. Several types of SST have been
modelled, simulated, and tested to be analysed. There are basically three main model types:
detailed switching models, average models, and steady-state models. Table 2.8 reviews a
selection of two-stage SST models demonstrated in publications.
Table 2.8: Review of Simulation Models for Two-Stage SSTs
SST Configuration Modelling
Approach
Simulation Software
Platform/Tool
References
Three-phase, two-stage, multilevel, bidirectional
Single-phase, two-stage, two-level, bidirectional
Single-phase, two-stage, multilevel, bidirectional
Single-phase, two-stage, two-level, bidirectional
Single-phase, two-stage, multilevel, bidirectional
Single-phase, two-stage, two-level, bidirectional
Single-phase, two-stage, two-level
Single-phase, two-stage, multilevel, bidirectional
Single-phase, two-stage, multilevel, bidirectional
Average model
Switching model
Switching model
Average model
Average model
Switching model
Switching model
Switching model
Switching model
MATLAB/Simulink
MATLAB/Simulink
MATLAB/Simulink
MATLAB/Simulink
MATLAB/PLECS
MATLAB/PLECS
SPICE
PSIM
PSIM
[207]
[208]
[209]
[210]
[211]
[212]
[213, 214]
[215]
[216]
There are currently very few steady-state models for power flow calculations of
SSTs. OpenDSS has been implemented for SST modelling in [217]. This simulation model
can be used to analyse the impact of the SST on distribution system performance. However,
DSMs are widely available because they generally require using very small time-step sizes
(< 1 μs). This implies that longer simulation times limit the size of the system model to be
practically analysed. MATLAB/Simulink is the most popular simulation tool for this type
of model due to its powerful EMT solvers. DAM can be used as an alternative to mitigate
the small time-step limitation of the DSM. DAM approximates the behaviour of the power
converter by applying the moving average operator at the switching frequency to the DSM
where the switching effects are eliminated from the model, but the dynamic performance
55
is preserved for simulation. DAMs can reproduce the transient behaviour of the DSM with
high accuracy but using a larger time step size. This enables the implementation of transient
models in real-time simulation platforms like OPAL-RT-LAB.
An average model of the SST presented in [218] was validated by comparing results
from those with the detailed switching model [219, 220]. PSCAD/EMTDC has been
utilised in [221] to simulate a three-phase SST system model including substation and
loads. Stability analysis of a modular SST has been modelled using dynamic phasor as
presented in [222]. The phasor modelling technique significantly reduces the simulation
time compared to EMT and DAM modelling. A detailed implementation of a three-phase
SST model using DigSilent Power Factory, based on the DAM technique is demonstrated
in [223]. Several case studies under different operating conditions of a bidirectional
MV/LV SST are presented in [224] where the model was developed using
MATLAB/Simulink. Real-time simulation of SST models using RTDS is proposed in
[225]. This DAM was tested and validated by comparing its performance to that of DSM
and a cycle-by-cycle average model built-in MATLAB and PLECS [226]. An intelligent
control platform for real-time simulation of the multi-level converter with energy
management schemes has been demonstrated with both hardware design and software
structure at FREEDM [227]. A new protection technique for SST has been verified by HIL
testing in [228]. Another performance testing for SST based on the Xilinx Zynq-7000 with
FPGA technology is proposed in [229]. There are also other simulation implementations
of the SST, in Simplorer, Multisim/Labview, EMTP/ATP SPICE and SABER software
platforms for applications other than fast charging for EVs.
2.7 Summary
This chapter introduced the classifications of charging mechanisms and industry
standards and provided a comprehensive review of the SST configurations and topologies
for ultra-fast charging applications with state-of-the-art technologies. For the chosen two-
stage DPSS SST structure, this chapter compared possible multi-level rectifiers and DC-
DC converters with advantages and drawbacks. Several control strategies and modulation
techniques applicable for multi-level power converters were investigated. Different
modelling approaches with several examples applied for SSTs were also briefly reviewed.
56
Chapter 3. Power Circuit Design
This chapter presents the proposed UFCSEV architecture and the associated MVAC
host system. The selection of the modular multi-level SST converter topologies and the
design of the circuit parameters are also described in detail.
To examine how the SST-based high-power conversion system behaves under certain
conditions for the UFCSEV application specified, a realistic system-level simulation model
needs to be derived first. Constructing the system model requires determining specific
values of several parameters, such as the MVAC line voltage, the switching frequencies,
and the ratings of passive components of the converters in both conversion stages. This
objective is typically accomplished through a detailed step-by-step design process. Because
this research study is focused on the dynamic performance of the SST-based conversion
system, a first-order design that offers an approximate estimation of the parameters’ values
is presented in this chapter. Other factors such as losses and design optimisation methods
are also considered. This chapter aims to present how the essential parameter values
required for the design of the SST-based conversion system are determined.
The first section of this chapter provides an overview of the requirements,
specifications, and assumptions made for the first-order design. The second section gives
a brief description of MVAC grid selection, and the filters required to minimise waveform
distortions. The third and fourth sections describe the analysis for the parameter selection
of the CHB and the DAB converter topologies selected. The design process, the equations
and optimisation of parameters’ selection of the converters are also delineated. The last
section presents the overall power circuit of the SST-based high power conversion system
with further discussions on its modularity.
3.1 System Requirements, Specifications and Assumptions
The calculations for the preliminary design of the SST-based high power
conversion system are based on the requirements and specifications set initially for this
thesis in accordance with the nominal and standard values. Other system parameters that
57
are not specified or cannot be computed directly, from stipulated values of the first-order
design, will be selected based on the requirements and assumptions outlined below.
3.1.1 Requirements
The fundamental requirement is that the SST-based high power conversion system
should operate at an MVAC level on the input side and at an LVDC level on the output
side. Moreover, the SST-based high power conversion system should be capable of
supplying an output active power of 1.5 MW for the UFCSEV. This research study also
attempts to address other requirements including the followings:
1) Fast response of the transient and dynamic effects for analysis based on
Electromagnetic Transient (EMT) simulation.
2) Four-quadrants power transfer operation modes to manage the output voltage
and current in all of the four-quadrant areas.
3) Total harmonic distortion content is compliant with IEEE standards.
3) The calculated parameters should allow for practical implementation of the SST-
based high power conversion system for future system scalability and
customisation.
3.1.2 Specifications
The essential parameters that need to be initially specified for the SST-based high
power conversion system developed in this thesis are as follows:
• MVAC Grid Voltage Level (Line-to-Line, RMS), VMVAC (LL) = 27.6 kV
• Nominal Grid Frequency, fg = 60 Hz
• Rated Output Active Power, Pcharging-rated = 1.5 MW
• Maximum LVDC Output Voltage Level, VDC_charging-max = 1000 VDC
58
While a higher power rating is better to achieve much faster charging, the selection
of 1.5 MW as the rating of the charging power in this SST design is based on the highest
power rating available in commercially available chargers to illustrate the model with a
realistic MW range. As of today, Proterra’s EB charger rated at 1.5 MW is the highest
power rating available in the market [89]. A higher charging voltage will minimise the
charging cable size to carry heavy currents for this 1.5 MW charging, the DC voltage
charging which is the rated output voltage of the proposed SST is selected in compliance
with the highest voltage rating of both IEC 61851 and SAE J1772 standards in accordance
with Mode-4 and Level-3 charging voltage, respectively. To reduce the cable size and
cooling requirements as well as the power losses over the conductor, I2R, a low current
rating is usually desired in the design which also requires increasing the charging voltage
to reach the rated power.
It is also of high importance to determine the voltage rating of the high-power
electronic semiconductor switches available for the selected converter topologies. This will
allow for specifying the restrictions for voltage levels and will also aid in specifying the
required number of H-Bridges in the CHB AC-DC rectifier as well as the number of
modules of the DAB conversion stage.
3.1.3 Assumptions
Due to the limitation of available equations in the literature to easily obtain certain
design parameters, assumptions will allow for simple calculation and approximation of
values for such parameters. For this research study, the following assumptions were
realised for simulation purposes, unless specified otherwise:
• The system components are presumably lossless.
• The semiconductor power switches turn on and off instantaneously.
• The passive components of the power circuit operate within the linear region only;
therefore, phenomenon such as saturation is avoided.
59
For maximum power transfer, it is assumed that the SST-based high power
conversion system required should be capable of power transfer in all four quadrants: for
both active and reactive power flow. As only the rated active power is given in the
specifications for the SST-based high power conversion system, the assumption made in
this research is that at unity power factor operation, the rated active power equals the
maximum apparent power. This assumption can be described in the following equation:
𝑆𝑚𝑎𝑥 = Pcharging-rated ; for PF = 𝑐𝑜𝑠 (𝜑) = 1 (3.1)
Rewriting Equation (3.1) yields:
|𝑆| = √𝑃2 + 𝑄2 ≤ | Pcharging-rated | (3.2)
Figure 3.1: Power Triangle Diagram
The desired area to operate the SST-based high power conversion system in all four
quadrants is shown in the highlighted (shaded) areas below:
60
Figure 3.2: Four-Quadrant Operating Area of the SST-based High Power Conversion System
The optimal solution for the SST charger is to enable transmitting the active and
reactive powers bidirectionally between the power grid and the EV battery. G2V operates
when the energy is provided from the power grid to the EV battery whereas V2G operates
when the EB transfers energy to the power grid, especially for ancillary services such as
peak shaving and frequency regulation [232]. To support the power grid with reactive
power, the mode of V4G is utilised and accompanied simultaneously with G2V or V2G
operation modes, while the EV battery functions as static var compensators [233, 281]. The
EV battery can be charged and discharged according to the transmission direction of the
active power. The coordination of operation mode scenarios for this bidirectional system
with the full control region as shown in the x-y axes of the PQ plane of Figure 3.2, can be
divided into eight operation modes according to the direction of P and Q power transfer,
are as follows:
(I) G2V operation mode.
(II) V2G operation mode.
(III) Inductive V4G operation mode.
61
(IV) Capacitive V4G operation mode.
(V) G2V combined with the inductive V4G operation mode; where the main
power grid provides the positive active/reactive power to the EV battery.
(VI) V2G combined with the inductive V4G operation mode; where the EV
battery delivers the active power to the power grid.
(VII) V2G along with the capacitive V4G operation mode; where the EV battery
operates as a static var generator to compensate the reactive power.
(VIII) G2V along with the capacitive V4G operation mode; where the EV battery
operates as a static var generator to compensate the reactive power.
The positive directions of P and Q represent the power being delivered from the
main power grid to the EV battery.
The inductive/capacitive operation refers to positive/negative Q power during the
power transfer. The inductive operation modes occur when the grid current lags behind the
same-phase voltage by 90° in. On the contrary, the grid current leads its voltage by 90° in
the capacitive operation modes.
3.2 Proposed SST System Architecture with Modular Configuration
The proposed system architecture of an SST-based high-power system with two-
conversion stages is presented in Figure 3.3 below.
Figure 3.3: Architecture of the Proposed SST-based High Power Conversion System
62
The best advantage of this system architecture is that it has no issues with the
asymmetrical operation due to the connection of each module of the DC-DC stage
conversion stage to each module of the AC-DC rectification stage that is connected to a
three-phase MVAC grid. The proposed SST-based EV charging system configuration with
the selected converter topologies is shown below in Figure 3.4.
Figure 3.4: Configurational Topology of the Proposed DPSS SST-based Charging System
For a modular design with multiple modules, the grid connection to the MVAC line
is implemented by connecting the inputs of all CHB modules in series while the output end
of the SST system is connected in parallel to the EV battery side as ISOP modular multi-
module SST. The proposed SST-based high-power ultra-fast charging system
configuration is illustrated in Figure 3.5 below. Employing ISOP in this configuration
results in a multi-cell SST system which consists of multi-level CHB rectifier modules
connected in series to interface the MVAC grid with a grid filter. The CHB rectification
stage converts the MVAC to MVDC constructing an MVDC-link where ESSs or RESs can
be linked. The second conversion stage consists of single-phase DAB converter modules
with independent galvanic isolation HFTs. This isolated conversion stage converts the
MVDC voltage from the MVDC-link to an LVDC level. The output terminals of all DAB
modules are then connected in parallel to interface the EV battery. This parallel connection
allows for high levels of DC current to flow and a constant output voltage to meet the
desired EV battery specifications for ultra-fast charging. The grid filter is placed before the
proposed SST configurational topology with the aim to alleviate the harmonic distortions
of the input current and voltage waveforms generated by the SST-based conversion system.
63
Figure 3.5: Configuration of the Proposed Modular ISOP SST-based High-Power Charging System
The internal structure of a single converter cell from Figure 3.5 is presented in
Figure 3.6 below.
Figure 3.6: Fundamental Structure of a Single Converter Cell of the Proposed SST
64
3.3 MVAC Grid Distribution Feeder Voltage Level and Filter Selections
Since the standard voltage level for Toronto Hydro for customer-owned distribution
substation with feeders that typically feeds a conventional transformer which steps the
MVAC down to an LVAC is rated at 27.6 kV (line-to-line, RMS) with a nominal frequency
of 60 Hz, the proposed UFCSEV system is to be fed directly from a three-phase 27.6 kV
distribution substation feeder, available as a lateral overhead line, by replacing the isolation
low-frequency service transformer [234]. This 27.6 kV is configured as a grounded star
(wye) configuration to be the input voltage of the MVAC-MVDC stage of the SST-based
high power conversion system of the UFCSEV as shown in Figure 3.7 and Figure 3.8.
The UFCSEV is to be connected to bus B1 on the feeder as indicated in Figure 3.7 above
where Bx: Bus x, Lx: Line x, Mx: Load x, and Tx: Transformer x. The MVAC distribution
feeder chosen is 10 km long and its overhead line (selecting line type 336 AL427 from
Table 3.1 below [235]) has: R1=1.696 , X1=3.809 , R0=4.689 , and X0=12.808 .
This is simply because this line type has the minimum impedance value in comparison to
the other four types tabulated in Table 3.1. This is important for efficiency improvement
as a low impedance (especially resistance) results in a low voltage drop and thus low power
losses, I2R, over the line.
Table 3.1: MVAC Feeder Overhead Line Parameters
Line Type R1
[ohms/km]
X1
[ohms/km]
B1
[uS/km]
R0
[ohms/km]
X0
[ohms/km]
B0
[uS/km]
Summer
Rating
[A]
Winter
Rating
[A]
10ASR427 0.5523 0.4852 3.6 0.9644 1.461 1.92 321 321
40ASR427 0.2697 0.4637 4.12 0.6071 1.4052 1.86 452 452
30ASR427 0.348 0.468 3.76 0.702 1.322 0 100 100
4 ASR-48 1.3515 0.5106 3.55 1.7778 1.7066 1.72 172 172
336 AL427 0.1696 0.3809 4.33 0.4689 1.2808 1.9 655 655
65
Figure 3.7: Single-line Diagram of the MVAC Distribution Feeder
Figure 3.8: Three Phase Star Connection from the MVAC Feeder to the UFCSEV
The high-frequency switching effects of the power electronic switches in the SST-
based high power conversion system cause its voltage and current waveforms to be
accompanied by distortions. This distortion yields an efficiency reduction in the conversion
66
system due to power losses, oscillations in the rotating machines, line cables, and
capacitors, and heating in the power equipment [236].
The Total Harmonic Distortion (THD) is the total distortion caused by a waveform
and is defined as the ratio between the RMS value of all the harmonics to the RMS value
of the fundamental harmonic [236]. The Total Demand Distortion (TDD) is another term
used in harmonics analysis and its calculation is the same as the THD. However, the value
of TDD is calculated under full load conditions only, whereas the THD can be determined
under any condition. As the current varies depending on the load, the TDD can be utilised
to provide a clear definition of the current distortion in the power conversion system. The
IEEE standards, as in the IEEE 519-1992 [236], provide recommendations for distortion
levels for improved power quality. Thus, the distortion levels for which the SST-based high
power conversion system are designed according to this standard definition. Table 3.2
below specifies the recommended limits for the voltages and currents. The ratio of the
short-circuit current to the load current is assumed to be smaller than 20 because the short
circuit current at the PCC is unknown. This assumption ensures compatibility of the SST-
based high power conversion system with any value of short-circuit current. In order to
allow the SST-based high power conversion system to operate at a safe level even below
the IEEE recommended limits, the distortion limit for the design of the SST system will be
set to 80% of the IEEE recommended values. It can be seen from Table 3.2 that even
harmonics are limited to 25% of the odd harmonic limit.
Table 3.2: IEEE Standards for Current Distortion Limits for odd Harmonics in percent of IL [236]
ISC / IL h < 11 11 ≤ h < 17 17 ≤ h < 23 17 ≤ h < 23 35 ≤ h TDD
< 20 4 2 1 0.6 0.3 5
20 < 50 7 3.5 2.5 1 0.5 8
50 < 100 10 4.5 4 1.5 0.7 12
100 < 1000 12 5.5 5 2 1 15
> 1000 15 7 6 2.5 1.4 20
67
The SST-based high power conversion system is to be connected to the MVAC grid
through a filter for the two following functions [238]:
1) Allowing control of the active and reactive power between the MVAC grid and
the SST-based high power conversion system.
2) Reducing the harmonic distortion generated by the SST-based high power
conversion system.
There are three types of filters, which are the most commonly used in power
electronics [49, 238]:
a) L-filter is the most basic filter, which has an inductor that provides damping of
‒20 dB over the whole range. To sufficiently attenuate the harmonic distortion
content, this filter must be used for power converters operating at high
switching frequencies.
b) LC-filter utilises a shunt capacitor to obtain an attenuation of ‒40 dB. This
filter is typically suited for configurations where the load impedance across the
capacitor is relatively high and above the switching frequency.
c) LCL-filter provides an attenuation of ‒60 dB for frequencies higher than the
filter’s resonance frequency (fr). This filter achieves low harmonic distortion
levels with smaller passive elements at lower switching frequencies. Due to
resonance; however, this filter is susceptible to causing distortions to the
dynamic and steady-state current waveforms.
Figure 3.9 below shows the schematic diagrams of the three filter types.
Figure 3.9: Schematic Diagrams of Filters: (a) L-filter (b) LC-filter (c) LCL-filter
68
The SST-based high power conversion system requires one filter to couple the
MVAC-MVDC CHB rectifier to the MVAC grid. A simple L-filter is selected for coupling
the CHB to the MVAC grid due to two main reasons [239]:
1. The converter circuit structure of the CHB with a large number of H-Bridges and
its modulation scheme requires a high switching frequency. The increased
number of H-Bridges can effectively result in a more sinusoidal waveform for
voltage and current. With these two properties, the harmonic distortion content
gets reduced and thus requires smaller filters. Proper filtering operation is
ensured by selecting an appropriate high effective switching frequency.
Selecting a small size of the L-filter ensures a low voltage drop on the inductor.
2. Since high-voltage capacitors are expensive, a filter with a capacitor is avoided
for a more economical design, and thus not included in the CHB filter.
The SST-based high power conversion system contains an MVDC-link,
between the CHB rectifier and the isolated DAB converter consisting of two
parallel capacitors. The DAB modules also have capacitors to the LVDC end to
smoothen the output voltage fed to the terminals of the EV battery as shown below.
Figure 3.10: The SST Converter Topology with the DC Links’ Capacitors
69
Since the rectified voltage from the MVAC-MVDC CHB to the MVDC-LVDC
DAB across the MVDC-bus is not normally constant, capacitor-based filters are therefore
utilised in order to obtain a smooth DC voltage at the MVDC-link as well as at the output
of each module of the DAB converter. A capacitor of an infinite value would yield a
constant voltage at the DC-link [240]. In practice; however, only a finite value of the
capacitance is possible for the filter design allowing a small voltage ripple. The peak-to-
peak voltage ripple in the DC-link is limited up to 10% in practice [241]. The minimum
capacitance for DC smoothing filter for the rectified sinusoidal waveforms from the CHB
rectifier to the DAB converter can be determined using the following equation [240]:
𝐶𝐴𝐶/𝐷𝐶_𝑚𝑖𝑛 =𝑃
2𝜋𝑓𝑔∗ 𝑉𝐷𝐶 ∗ ΔV (3.3)
where CAC/DC_min is the minimum capacitance value for the rectifier’s DC voltage with
sinusoidal ripple, P is the power that flows through the DC-link, fg is the grid sinusoidal
frequency, VDC is the DC-link voltage of the rectifier, ΔV is the peak-to-peak voltage ripple
of the MVDC-link.
To smoothen the voltage waveforms produced as a result of the switching actions
of the DAB converter, additional capacitors are required on both of its sides. The minimum
capacitance for the DAB DC-DC converter capacitors can be calculated according to [242]
as follows:
𝐶𝐷𝐶/𝐷𝐶_𝑚𝑖𝑛 =50∗𝑃
𝑉𝐷𝐶2 ∗ 𝑓𝑠𝑤
(3.4)
where CDC/DC_min is the minimum capacitance value for the DC-DC converter, P is the
power that flows through the DC-link, fsw is the switching frequency of the DC-DC
converter, VDC is the DC-link voltage.
70
3.4 Cascaded H-Bridge MVAC-MVDC Rectifier
The AC-DC stage, also known as the rectification stage of the SST system, consists
of an input L-filter and multiple AC-DC converter cells with an output filter capacitance to
each H-Bridge cell. This section outlines the selection of the converter topology and
components’ parameters.
To directly interface a 27.6 kV MV grid feeder, either series connections of power
semiconductor switches or multi-level converters have to be implemented [50]. To avoid
issues with voltage sharing among individual power switches, employing multi-level
converters can generate multi-level output voltage waveforms with improved harmonic
performance. Cascading of the rectifier cells is therefore a feasible approach to interface
the SST to the MV grid. This approach also results in reduced filtering requirements
compared to a conventional two-level approach [160].
3.4.1 Power Converter Circuit Topology and Components
The CHB rectifier is responsible for converting MVAC to a rectified MVDC
voltage and is often required to operate at unity power factor.
After reviewing the most relevant high-power converter topologies that are widely
used in the industry, multilevel modular-based converters topologies are the most popular
topologies in MV applications because of their benefits to directly interface with MVAC
grids. Among the high potential benefits of the available topologies, that still have not been
fully applied for ultra-fast charging solutions is to employ the CHB rectifier as it is a very
economically viable option compared to other choices owing to its industry ubiquity. Due
to its simple voltage balance control and modular structure which are its main advantages
compared to other potential AC-DC multi-level converters as analysed in Table 2.5, the
CHB is obviously the most suited topology for the AC-DC conversion stage of the SST
system. With proper control strategies and modulation techniques, the SST-based EV
charging system configuration with this CHB topology makes the three phases of the power
conversion system deliver the same power at all times without any asymmetrical issues.
71
Another main feature of employing the CHB in the SST-based high power
conversion system is its modularity; it can easily reach MV by adding more power cells to
each phase of the three-phase MVAC grid. This particular power converter topology can
cope with any grid voltage by increasing the number of cascaded cells and can be scaled to
higher voltage levels easily. Off-the-shelf CHB converter is commercially available in the
market for different MVAC grid voltage levels: 3.3 kV (three cells per phase), 6.6 kV (six
cells per phase), and 11 kV (eleven cells per phase) [243].
The CHB rectifier is composed of a series of connections of several single-phase
full-bridge converters (HBs) referred to as cells. Each one of these cells, realised by
MOSFETs, enables an independent DC voltage, as shown in Figure 3.12. An output
capacitance-based filter is connected to each H-Bridge cell. In order to achieve the desired
DC voltage waveform at the DC-link, a control circuit is connected to each H-Bridge cell
by switching its semiconductor devices on and off.
Figure 3.11: Three-Phase Representation of Cascaded Rectifier Topology within the Proposed SST
System Configuration
72
Figure 3.12: Single-Phase Representation of Cascaded H-Bridge MVAC-MVDC Rectifier Topology
Figure 3.13: Simple Circuit Diagram of Single-Phase Connection from MVAC Grid to the CHB
where Sx is the semiconductor switch consisting of a SiC MOSFET and an anti-parallel
diode, and CCHB is the CHB capacitor at the MVDC-link.
73
Considering the fundamental frequency equivalent circuit of the phase stack shown
in Figure 3.13 with constant phase current amplitude, the required voltage amplitude of
VCHB1 varies with the power factor which depends on the phase angle between the phase
voltage and the phase current, due to the voltage drop across the L-filter inductance, LCHB.
As can be seen in Figure 3.14, the worst-case operating point at the highest VCHB1 voltage
amplitude requirement occurs in the capacitive case (φ = 90°) which limits the maximum
feasible filter inductance, LCHB1, for a given total voltage at the MVDC-link.
The required output voltage, Vi, of the CHB rectifier and can be calculated from:
Vi = M · ∑VMVDC (3.5)
where ∑VMVDC is the total voltage at the MVDC-link.
The power transfer between the MVAC grid and the CHB can be analysed by
considering the fundamental harmonics using the single-phase representation shown in
Figure 3.12 above. This representation replaces the CHB rectifier circuit with the VCHB1 as
a single AC-voltage source. The vector relationship of the power circuit parameters is
illustrated in Figure 3.14 and Figure 3.15.
Figure 3.14: Representation of the Relationship between the required Rectified Output Voltage
Amplitude of the CHB and the Phase Angle between the MVAC Grid Voltage and Current [259]
74
Figure 3.15: Vector Representation of the Relationship between the Voltages and Current at Unity
PF (a) Arbitrary Current (b) Power flow from CHB to MVAC Grid (c) Power flow from MVAC
Grid to CHB
Using the vector analysis, the equations of the power flow between the MVAC grid
and the CHB can be derived as follows:
𝑃 = 3 ∗ 𝑉MVAC−ph ∗ 𝐼MVAC−ph ∗ cos(φ)
= 3 ∗ 𝑉MVAC−ph ∗𝑉CHB1∗sin(δ)
2𝜋𝑓𝑔𝑟𝑖𝑑∗ 𝐿𝐶𝐻𝐵 (3.6)
𝑄 = 3 ∗ 𝑉MVAC−ph ∗ 𝐼MVAC−ph ∗ sin( φ)
= 3 ∗ 𝑉MVAC−ph ∗𝑉MVAC−ph− 𝑉CHB1∗ cos (δ)
2𝜋𝑓𝑔𝑟𝑖𝑑∗ 𝐿𝐶𝐻𝐵 (3.7)
75
where P and Q are the active and reactive power flowing between the MVAC grid and the
CHB respectively, φ is the impedance angle between the voltage and current of the MVAC
grid, and δ is the angle between the MVAC grid voltage and the AC input voltage to the
CHB rectifier.
The amplitude of the phase current flowing through the L-filter can be determined
from the following formula:
I𝑴𝑽𝑨𝑪−𝒑𝒉 =√2 ∗ 𝑃ph
𝑉𝑴𝑽𝑨𝑪_𝑳𝑳/√3 (3.8)
From Equation (3.8), the RMS value and the rectified average value of the phase
current can be calculated from:
I𝑀𝑉𝐴𝐶−𝑝ℎ−𝑅𝑀𝑆 =I𝑴𝑽𝑨𝑪−𝒑𝒉
√2 and I𝑀𝑉𝐴𝐶−𝑝ℎ−𝑎𝑣𝑒 =
2∗ I𝑴𝑽𝑨𝑪−𝒑𝒉
𝜋 (3.9)
where Pph is the active power at each phase which equals 500 kW. The values of parameters
VMVAC-ph and fg are fixed by the host MVAC grid system as selected in Section 3.3.
However, the value of IMVAC-ph is determined by the SST charging system load. To adjust
the amount of active and reactive power flowing through the SST conversion system, the
angle φ needs to be adjusted accordingly by adjusting the voltage VCHB1 or angle δ. Also,
adjusting the active and reactive power flow between the MVAC grid and the CHB can be
achieved by adjusting the modulation index given in the two following equations:
MCHB =√2 ∗ 𝑉CHB1
𝑁𝐶𝐻𝐵∗ 𝑉MVDC (3.10)
MCHB =√2 ∗ 𝑉MVAC_LL
√3∗ ∑ 𝑉MVDC (3.11)
Since each CHB cell generates the same VMVDC value, the total MVDC-link voltage is split
among the cascaded rectifier cells. Without loss of generality, this calculation assumes
unity power factor operation and a power flow from the MVAC grid to the EV battery.
76
The parameters that are required to construct the simulation model of the CHB
rectifier are:
• Number of H-Bridges, NCHB
• MVDC-Link Voltage, VMVDC
• C-Filter Capacitance at the MVDC-link, CCHB
• Switching Frequency, fCHB
• L-Filter Inductance for the MVAC Grid, LCHB
3.4.2 Number of H-Bridges and MVDC-Link Voltage
Since the CHB rectifier is comprised of several H-Bridges connected in cascade,
an increase of H-Bridges’ number leads to a better waveform [239]. Nevertheless, adding
one H-Bridge cell requires an additional DAB converter module with its HFT. This yields
in increasing the overall conversion system size and volume, control complexity, and total
cost. Therefore, the number of H-Bridge cells of the CHB is to be kept to a minimum.
Considering the recent advances in SiC power semiconductor technology which
have resulted in 4H-SiC IGBTs with MV blocking voltage ratings [244, 245], conventional
single-cell two-level or three-level converter topologies based on 10 kV [246] or 15 kV
[247] power switching devices could be alternatively considered for the SST system.
However, single-cell SST based on HV semiconductor devices suffers from the high dv/dt
and di/dt values required to limit switching losses.
Significant efficiency and power density gains can be achieved by replacing using
SiC devices instead of LV Si IGBTs in the multi-cell SST system. Only LV SiC power
modules are limited to blocking voltages up to 3300 V are currently available in the market
as discrete products [248–250]. Hence, SiC MOSFET power modules will prevail in the
foreseeable future. Moreover, in order to limit the susceptibility to cosmic-ray-induced
failures, only about 50 % to 60 % of the power semiconductor switching devices’ rated
77
blocking voltage can be used in an application [251, 252]. Therefore, the cascaded CHB
rectifier cells system can be realised using few cells employing 3.3 kV MOSFETs, but also
using a large number of CHB cells based on LV Si IGBTs such as 1200 V IGBT. The trade-
offs considering efficiency, power density, and reliability aspects which have to be
considered for the selection of the optimum number of cascaded cells for the 27.6 kV grid
voltage with the optimum power MOSFET blocking voltage [253, 254], where switching
losses and conduction losses are also considered.
As can be seen from Figure 3.16 below, if the number of cascaded cells is high, the
required blocking voltage of the power semiconductor device is low. Since the phase
current passes through more bipolar power semiconductors connected in series as in the
cascaded topology, the conduction losses increase, and the total voltage drop across the
switches increases. Moreover, since the switching energies of the power switch with
blocking voltage increase, high switching losses are generated, especially when using high
switching frequencies. Thus, if the design considers using power semiconductor devices
with higher blocking voltages, the switching losses are significant. On the other hand, the
design is dominated by conduction losses if it is based on lower blocking voltages.
Figure 3.16: Factors for Trade-offs of Selecting the Optimum Number of CHB Rectifier Cells [259]
78
The output voltage of the CHB rectifier at the MVDC-link is bounded by two values:
1. The lower limit of voltage across the MVDC-link is set by the ripples.
The voltage ripple across the MVDC-link is set to be limited to 10% only. If the
voltage drop over the L-filter inductor is assumed to be zero, the peak AC voltage
amplitude over each H-Bridge cell should be a maximum of 95% of the MVDC-
link voltage. In order to avoid any overlap of the MVDC voltage ripple and the AC
voltage, the AC voltage supplied to each H-Bridge cell is to be kept below 95%.
2. The upper limit of voltage across the MVDC-link is set by the blocking
voltage rating of the switching device.
The value of the MVDC-link voltage cannot be larger than the rated blocking
voltage value of the available SiC MOSFET switching device. In practice, the upper
value of the MVDC-link voltage is limited to 80% of the rated SiC MOSFET
blocking voltage, considering a safety margin of 20%.
These limitations can be represented in the drawings of Figure 3.17 below.
Figure 3.17: Representation of MVDC-Link Voltage Limitations: (a) Lower Limit (b) Upper Limit
79
where VMVAC-ph_peak is the peak voltage of VMVAC-ph, VMOSFET_peak is the peak voltage
across the MOSFET switch, and Margin VMVDC is the margin between the maximum and
minimum MVDC-link voltage.
As can be seen from Figure 3.17, there is a margin between VMVDC_max and
VMVDC_min. This margin can be utilised to select the MVDC-link voltage level such that an
optimal value of the HFT winding ratio of the DAB converter is achieved.
Since the maximum MVDC-link voltage value is limited by the rated MOSFET
blocking voltage value, which can be calculated as follows:
VMVDC_max = 80%
105% ∗ VMOSFET_rated (3.12)
The minimum MVDC-link voltage is limited by the peak phase voltage of the
MVAC grid and the number of H-Bridge cells. Equation (3.13) below can be used to
calculate this voltage:
𝑉MVDC_min = 100%
95% ∗
√2 𝑉MVAC_ph
𝑁CHB (3.13)
The number of H-Bridge cells can be calculated using the following equation:
𝑁CHB = 𝑖𝑛𝑡 (100%
95%∗
√2 𝑉MVACph
𝑉MVDC_max ) (3.14)
where int is the function that rounds the value between the brackets upwards to the next
highest integer. This equation illustrates the equivalence of determining the optimum
number of cascaded converter cells considering the optimum switch blocking voltage.
3.4.3 C-Filter for the CHB Rectifier Cells
The capacitance value of the C-filter, required to obtain a smooth voltage at the
MVDC-link, can be determined using Equation (3.3) above. Assuming that the power
flowing from the MVAC grid to the CHB rectifier is evenly distributed among the three
80
phases and many H-Bridge cells, the rectified power per phase, per one H-Bridge cell can
be determined as follows:
PCHB1-ph = 1
3
𝑃𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔_𝑟𝑎𝑡𝑒𝑑
𝑁𝐶𝐻𝐵 (3.15)
The required capacitance value for a given voltage ripple criterion depends mainly
on the capacitor current of a specific cell, which can be calculated from the phase current,
the modulation index function, and the constant DC current. For this SST design, identical
cells with the same blocking voltage and filter capacitance are assumed.
The capacitances of the CHB cells are selected such as to result in a peak-to-peak
voltage ripple of 10 %, which is mainly a ripple at twice the grid frequency This is to buffer
the difference between the AC-side power that is proportional to sin2 (2π fg t) and the DC-
side power, which is constant. Setting the MVDC-link voltage ripple to 10% maximum,
Equation (3.12) can be substituted into Equation (3.3), which yields Equation (3.16) below
which can be used for the capacitor selection for CHB cells:
𝐶𝐶𝐻𝐵_𝑚𝑖𝑛 =
13
𝑃𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔_𝑟𝑎𝑡𝑒𝑑
𝑁𝐶𝐻𝐵
2𝜋𝑓𝑔𝑟𝑖𝑑 ∗ (0.1 ∗ 𝑉𝑀𝑉𝐷𝐶) ∗ 𝑉𝑀𝑉𝐷𝐶
=𝑃𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔_𝑟𝑎𝑡𝑒𝑑
0.6 𝜋 𝑓𝑔 ∗ 𝑁𝐶𝐻𝐵 ∗ 𝑉𝑀𝑉𝐷𝐶2 (3.16)
For designs based on different blocking voltages of the switching devices, the total
energy buffering capability of a phase stack at twice the grid frequency does not primarily
rely upon the number of CHB cells as additional current components at the respective
switching frequency lead to slight differences in the capacitance requirements.
By averaging the values of polypropylene foil capacitors of various capacitance and
voltage ratings provided in the datasheets from different manufacturers, the capacitor
volume can be estimated from the capacitance value and the DC voltage of each CHB cell
by assuming a constant volume per stored energy of 6.3 cm3 /J which corresponds to an
energy density of 0.16 J/cm3 as reported in [258].
81
3.4.4 L-filter and Switching Frequency for the CHB Rectifier
Considering the variable number of cascaded CHB cells that can generate an output
voltage waveform with multiple levels, an L-filter inductor, LCHB is required to limit the
current harmonics injected into the power grid. Based on the THD caused by the CHB
rectifier, the values of the carrier or switching frequency fCHB and the inductor of the L-
filter LCHB can be determined. The higher the switching frequency is, the lower is the
harmonic distortion. However, increasing the switching frequency has a drawback as the
switching losses increases as a result. Selecting a higher inductance value for the LCHB
reduces the THD; however, this increases the inductor voltage drop as well as its size and
cost.
The required switching frequency for each cell mainly depends on the number of
CHB cells. The reference impedance and inductance can be determined from:
𝑍B = 𝑉𝑀𝑉𝐴𝐶_𝐿𝐿
2
P𝒄𝒉𝒂𝒓𝒈𝒊𝒏𝒈_𝒓𝒂𝒕𝒆𝒅 and 𝐿B =
𝑍B
2𝜋𝑓g (3.17)
If the allowable maximum relative peak-to-peak ripple of the phase-current is given
by δIpp = ∆Ipp
IMVAC−ph , then for a single two-level H-bridge rectifier modulated with unipolar
PWM, where the output frequency of the H-bridge is twice the MOSFET switching
frequency, due to interleaved operation of the two bridge legs, the maximum current ripple
during a half period of the grid current occurs when the modulation index is MCHB = ½
[259]. Therefore, the required switching frequency for a given maximum peak-to-peak
current ripple can be calculated from:
𝑓sw_2L = ∑ 𝑉𝑀𝑉𝐷𝐶
8∗ 𝐿f 𝐿B ∆Ipp (3.18)
For multiple H-Bridge cells connected in a cascade where CPS-PWM is employed,
the magnitude of the steps in the output voltage is reduced to (∑VMVDC)/NCHB. To
determine when the highest switching distortion happens, the control structure, scheme and
modulation techniques of the CHB rectifier should considered.
In this design, the CHB rectifier is modulated using the PWM with phase-shifted
carriers, known as the PS-PWM modulation scheme where each H-Bridge cell of the CHB
82
is assigned two carrier signals with a frequency of fCHB. As a result of the CPS-PWM
modulation scheme, the effective switching frequency of the CHB rectifier can be
calculated as follows [255, 256]:
𝑓𝐶𝐻𝐵−𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 = 2 ∗ 𝑁CHB ∗ 𝑓𝐶𝐻𝐵 (3.19)
where fCHB-effective is the effective switching frequency of the CHB rectifier, and fCHB is the
frequency of the carrier signal to the MOSFET switches of the CHB rectifier.
∆Ipp = ∑ 𝑉𝑀𝑉𝐷𝐶
8∗ 𝐿f ∗ 𝑓sw_2L =
(∑𝑉𝑀𝑉𝐷𝐶)/𝑁𝐶𝐻𝐵
8∗ 𝐿f ∗ 𝑁𝐶𝐻𝐵∗ 𝑓CHB (3.18)
where fCHB is the switching frequency per H-Bridge leg required to achieve the same
current ripple in the same L-filter inductor, which can be reduced based on the following:
𝑓CHB = 𝑓sw_2L
𝑁𝐶𝐻𝐵2
(3.19)
The switching frequency decreases with the number of CHB cells squared, which
corresponds with the findings published in [260].
Considering the trade-offs shown in Figure 3.16, by using CPS-PWM and many
cascaded rectifier cells, the number of voltage levels and the effective switching frequency
seen by the LCHB inductor are increased, and hence the required switching frequency per
cell and the filtering LCHB inductor value can be reduced. To address the reliability concerns
that might arise when the number of cells is high, using a fewer number of cascaded cells
with power switches of higher blocking voltages could reduce the number of available
voltage levels of the CHB. In this case, either a larger filter, LCHB and/or higher switching
frequencies are required to keep the harmonic content of the grid current within limits [255,
256]. Since the VCHB1 voltage shown in Figure 3.14 above is limited by the total MVDC-
link voltage; ∑VMVDC, there is an upper limit for the filter inductance, LCHB. If the
capacitive operating point should be reachable at nominal current and MCHB_max = 1, the L-
filter inductance is constrained by:
𝐿CHB ≤ 𝐿CHB,𝑚𝑎𝑥 = ∑VMVDC − √2/3 𝑉MVAC_LL
2𝜋𝑓g ∗ I𝑴𝑽𝑨𝑪−𝒑𝒉 (3.20)
where MCHB_max is the maximum modulation index value.
83
Due to the stringent requirements set by IEEE [236], the harmonic distortion levels
are imposed for frequencies above the 35th harmonic, which is at 2100 Hz for a grid
frequency of 60 Hz. From Equation (3.17), a switching frequency of 1050 Hz will produce
distortions above the 35th harmonic. For analysis, the harmonics above the 35th will be
determined first because the suggested distortion level for every harmonic above the 35th
is the same. When both the fCHB and LCHB values are found to reduce the distortion for
harmonics above the 35th to the desired levels, the next step is to determine if this
combination of values also reduces the individual distortion levels below the 35th harmonic.
When the THD is below the desired levels, that combination of fCHB and LCHB values is
suited for the design of the CHB rectifier. Appendix C demonstrates a flowchart of this
optimisation process [49].
It should be noted that several combinations of fCHB and LCHB values could result
in distortion levels compliant with the IEEE standards. In such practical cases, the most
suitable selection for the CHB rectifier design is to select a combination of values that are
suitable based on other factors such as the switching losses as well as the size and weight,
and voltage drop of the LCHB inductor.
3.5 Dual Active Bridge MVDC-LVDC Converter
A single-phase DAB full-bridge DC-DC converter is selected for this conversion
stage due to its overall high efficiency and the fewest passive components it contains
compared to other viable bidirectional isolated DC-DC converter as can be seen from Table
2.6, which makes it a perfect candidate for soft switching properties as well as achieving
evenly shared currents in the switching devices. Soft switching in power electronics means
that the switching devices turn on and off at either zero voltage or at zero current. This
yields to neglectable switching losses, increased efficiency at high switching frequencies,
and smaller dimension size of the HFT [263].
84
3.5.1 Power Converter Circuit Topology and Components
The number of DAB DC-DC converter modules is equal to the number of H-Bridge
cells of the CHB rectifier where each DAB module is connected to a single H-Bridge cell
from the CHB, that is: NDAB = NCHB
For simplicity, this conversion stage can be divided in three parts in order:
• A DC-AC converter
• An HFT in between the DC-AC converter and the AC-DC converter
• An AC-DC converter
The purpose of the HFT in this topology is to meet the galvanic isolation
requirement. It also allows large conversion ratios of voltage and current between the input
and the output of the DAB converter. Size reduction is obtained using the HFT in
comparison with the LFT. Additionally, the HFT assists in ensuring a sinusoidal AC
current shape with low harmonic distortion as well as PFC and achieving soft-switching
conditions over the whole AC module voltage. It also helps in keeping the AC-side voltage
within the limits of the blocking voltage capability of the power MOSFET switching
devices. Previous studies show that for non-isolated EV chargers, a person gets electrically
shocked especially during direct coupling between the EV charger to the EV battery, while
for isolated EV chargers with no connection from the neutral to the ground, this is not the
case. The output side of the UFCSEV has to be designed as an unearthed DC power supply
(IT system) with insulation monitoring [272, 273]. Earthing of such station could be
designed using grounding standards and methods reported in [230, 231]. IEC 61851-23
[129] standard recommends the isolation requirements between the AC distribution grid
and the EV battery, this safety requirement can be met by the galvanic isolation provided
by the HFT meets the requirement for UFCSEV between the MVAC distribution grid and
the EV battery.
The DAB DC-DC power circuit schematic is shown in Figure 3.18. The outputs of the
DAB modules are all connected in parallel for a fixed voltage and increased current at the
output to the EV battery.
85
The parameters required to construct the DAB converter model are:
• HFT Turns-Ratio, nHFT
• Leakage Inductance, LDAB
• C-Filter Capacitances: CDAB1 at the MVDC-Link and CDAB2 at the LVDC-Link
• Switching Frequency, fDAB
Figure 3.18: Multiple Module Topology of the DAB MVDC-LVDC Converter
3.5.2 HFT
In this design, the phase shift modulation technique is utilised to control the power flow
between the high-voltage side and the low-voltage side of the HFT. Figure 3.19 below
shows the equivalent circuit diagram of the HFT to be used for analytical purposes [261].
86
Figure 3.19: Equivalent Circuit Schematic of the HFT
Figure 3.20: Simplified Circuit Schematic of HFT
The small series resistances and large parallel branches can be neglected which
results in a simplified circuit as depicted in Figure 3.20. This allows for summation of both
leakage inductances as in the following equation [262]:
𝐿𝐷𝐴𝐵 = 𝐿𝐷𝐴𝐵1 + 𝐿𝐷𝐴𝐵2 ∗ 𝑛HFT2 (3.21)
where VDAB1_AC is the primary side voltage of the HFT, VDAB2_AC is the secondary side
voltage of the HFT, RDAB1 is the resistance of the HFT primary winding, RDAB2 is the
resistance of the HFT secondary winding, LM is the magnetizing inductance of the HFT,
LDAB1 is the leakage inductance of the HFT primary winding, LDAB2 is the leakage
inductance of the HFT secondary winding, RM is the magnetic core resistance of the HFT,
LDAB is the referred primary leakage inductance of the HFT, IL-DAB is the current flowing
through the inductor LDAB [263].
87
Besides providing the required galvanic isolation, the HFT provides voltage
matching between the high-voltage side and the low-voltage side of the DAB converter.
The leakage inductance, 𝐿𝐷𝐴𝐵 of the HFT is used as an instantaneous energy storage device
[265]. The relationship between the high-voltage side and low-voltage side defines the
turns-ratio of the HFT, which can be calculated from:
𝑛HFT = 𝑉𝑀𝑉𝐷𝐶
𝑉𝐿𝑉𝐷𝐶 (3.22)
The value of 𝑛HFT depends primarily on the ratio of the DC-links’ values which are
determined by the requirements of the CHB rectifier and the EV battery respectively. For
standardised design, it is preferable to have 𝑛HFT with a small numerator and denominator
[265]. For instance, it is more preferred to have a turns-ratio value of 2/3 than that of
315/994. To simplify the turns-ratio design, the following equations can be used:
G = 𝑉𝑀𝑉𝐷𝐶
GCD (𝑉𝑀𝑉𝐷𝐶 , 𝑉𝐿𝑉𝐷𝐶) 𝑥
𝑉𝐿𝑉𝐷𝐶
GCD (𝑉𝑀𝑉𝐷𝐶 , 𝑉𝐿𝑉𝐷𝐶) =
𝑉𝑀𝑉𝐷𝐶 ∗ 𝑉𝐿𝑉𝐷𝐶
(GCD (𝑉𝑀𝑉𝐷𝐶 , 𝑉𝐿𝑉𝐷𝐶))2 (3.23)
for VMVDC_min ≤ VMVDC ≤ VMVDC_max and VLVDC_min ≤ VLVDC ≤ VLVDC_max
where G is the optimum value of the turns-ratio 𝑛HFT, GCD is the greatest common divisor,
VMVDC_min and VLVDC_min are the minimal values of the VMVDC and VLVDC respectively, and
VMVDC_max and VLVDC_max are the maximum values of the VMVDC and VLVDC, respectively.
The optimal turns-ratio of the HFT occurs at the minimal value of G, where Equation (3.22)
becomes:
𝑛HFT = 𝑉𝑀𝑉𝐷𝐶 @G−min
𝑉𝐿𝑉𝐷𝐶 @G−min (3.24)
where VMVDC@G-min is the voltage VMVDC at the minimum value of G, and similarly
VLVDC@G-min is the voltage VLVDC at the minimum value of G.
88
3.5.3 Leakage Inductance and Switching Frequency for the DAB Converter
Since the phase shift modulation scheme is applied for the DAB converter, the
phase shift is adjusted between the voltage VDAB1_AC and VDAB2_AC as can be seen from
Figure 3.21. If power losses are neglected, the active power transferred through the MVDC-
LVDC DAB converter can be calculated as follows [265]:
𝑃DAB_rated =n𝐻𝐹𝑇 ∗ 𝑉𝑀𝑉𝐷𝐶 ∗ 𝑉𝐿𝑉𝐷𝐶
2 ∗ 𝑓𝐷𝐴𝐵 ∗ 𝐿𝐷𝐴𝐵 ∗ d𝐷𝐴𝐵 (1 – d𝐷𝐴𝐵) (3.25)
and the duty cycle is based on half the switching period as:
d𝐷𝐴𝐵 = (𝑡𝑜𝑛−𝐷𝐴𝐵) / (𝑇𝑠−𝐷𝐴B/2)
= 2 * 𝑡𝑜𝑛−𝐷𝐴𝐵 * fDAB (3.26)
and the rated power per DAB module can be simply determined assuming that the power
is evenly distributed among the multiple DAB modules as follows:
𝑃DAB_module = 𝑃𝐷𝐴𝐵_𝑟𝑎𝑡𝑒𝑑
3 ∗ 𝑁𝐷𝐴𝐵 (3.27)
where PDAB_rated is the rated power transferred through the DAB converter, VMVDC is the
input voltage of the DAB on the CHB side, VLVDC is the output voltage of the DAB on the
EV battery side, PDAB-module is the rated power of each DAB module, NDAB is the number of
modules of DAB, ton-DAB is the time-delay before the low-voltage of the DAB H-Bridge is
switched on, Ts-DAB is the switching period of the DAB.
Selecting an effective switching frequency for the DAB converter requires a
detailed design. Depending on the HFT characteristics, power-switching devices
(MOSFETs), and the desired efficiency, an optimal switching frequency can be
determined. Due to the complexity of detailed design and optimisation to determine the
switching frequency, the scope of this research study is to employ previous research results.
Since most publications reported in [266-271] use a switching frequency of 20 kHz for the
DAB converter for high-power ratings from 1 kW to 1 MW, this frequency will be utilised
as the switching frequency of the DAB converter of the SST system. Since this is applicable
for a large range of power ratings, a frequency of 20 kHz is high enough to prevent the
HFT and external inductors from generating acoustic noise [270].
89
Figure 3.21: Phase Shift Waveform Representation of the Input and Output Voltages of the HFT
The leakage inductance of each DAB module can be determined using this formula:
LDAB =nHFT ∗ V𝑀𝑉𝐷𝐶 ∗ 𝑉𝐿𝑉𝐷𝐶
2 ∗ 𝑓𝐷𝐴𝐵 ∗ 𝑃𝐷𝐴𝐵−𝑚𝑜𝑑𝑢𝑙𝑒 ∗ d𝐷𝐴𝐵 (1 – d𝐷𝐴𝐵) (3.28)
The maximum power the DAB can transfer happens when the duty cycle dDAB = 0.5. This
yields to:
LDAB =nHFT ∗ V𝑀𝑉𝐷𝐶 ∗ 𝑉𝐿𝑉𝐷𝐶
8 ∗ 𝑓𝐷𝐴𝐵 ∗ 𝑃𝐷𝐴𝐵_𝑚𝑜𝑑𝑢𝑙𝑒 (3.29)
However, the value of LDAB is restricted to a maximum of 80% of the maximum value of
LDAB for sufficient bandwidth of the duty cycle dDAB, thus, Equation (2.29) yields to:
LDAB_max =nHFT ∗ V𝑀𝑉𝐷𝐶 ∗ 𝑉𝐿𝑉𝐷𝐶
10 ∗ 𝑓𝐷𝐴𝐵 ∗ 𝑃𝐷𝐴𝐵_𝑚𝑜𝑑𝑢𝑙𝑒 (3.30)
where LDAB-max is the maximum leakage inductance of the HFT required to operate the
DAB converter, PDAB-rated is the rated power flowing through the DAB converter module.
As can be seen from Equation (3.23), LDAB_max is inversely proportional to the maximum
transferable power through the DAB converter module, when other parameters are fixed.
90
3.5.4 DAB Operation with Soft Switching
The DAB topology was selected among all isolated bidirectional DC-DC converter
topologies for its soft-switching capabilities where the MOSFET switches turn on and off
at either zero voltage or at zero current. The operating range of the DAB has to be in a
certain region in order to take advantage of the soft-switching properties [274, 275]. DC
conversion ratio is a parameter introduced in [263] in order to identify that region. This
ratio is also known as the normalised output voltage which can be calculated from the
following equation:
DC conversion-ratio =n𝐻𝐹𝑇 ∗ 𝑉𝐿𝑉𝐷𝐶
𝑉𝑀𝑉𝐷𝐶 (3.31)
The variation of dDAB can cause the DAB converter to shift from the soft switching
region to the hard switching region, as can be seen from Figure 3.22 and Figure 3.23. Since
the hard switching region does not occur at zero voltage or zero current, which introduces
unwanted switching losses, therefore, this region is to be avoided [49].
Figure 3.22: DAB Output Power versus Duty Cycle [263]
91
Figure 3.23: DC Conversion-Ratio versus Output Current of the DAB [263]
From Figure 3.22 and Figure 3.23, the per unit output current of the DAB can be calculated
using:
I𝐿𝑉𝐷𝐶(p. u. ) = 𝐼𝐿𝑉𝐷𝐶
2π 𝑓𝐷𝐴𝐵∗ 𝑉𝑀𝑉𝐷𝐶∗n𝐻𝐹𝑇 ∗ 𝐿𝐷𝐴𝐵 (3.32)
𝑅 = 𝐷𝐶−𝑟𝑎𝑡𝑖𝑜 (p.u.)
𝐼𝐿𝑉𝐷𝐶 (p.u.) (3.33)
The DC conversion-ratio, DC-ratio, should ideally be equal to one, in order to avoid
the hard switching region as can be seen from Figure 3.23 and Figure 3.24. Keeping the
voltage values on both sides of the DAB as constant as possible provides a full range of
soft-switching operations [49].
92
3.5.5 C-Filters for the DAB Modules
The DAB converter is to also employ two capacitance-based filters, one at the side
of the CHB rectifier (to further smooth out the voltage ripple across the MVDC-link) and
the other one on the EV battery side. The capacitance value of the capacitor on the CHB
rectifier side can be calculated from:
𝐶𝐷𝐴𝐵1 =50 ∗ 𝑃𝐷𝐴𝐵_𝑚𝑜𝑑𝑢𝑙𝑒
𝑓𝐷𝐴𝐵 ∗ 𝑉𝑀𝑉𝐷𝐶2 (3.34)
Similarly, the capacitance value of the C-filter on the EV battery side can be determined
using the following equation:
𝐶𝐷𝐴𝐵2 = 𝐶𝐿𝑉𝐷𝐶 =50 ∗ 𝑃𝐷𝐴𝐵_𝑚𝑜𝑑𝑢𝑙𝑒
𝑓𝐷𝐴𝐵 ∗ 𝑉𝐿𝑉𝐷𝐶2 (3.35)
where 𝐶𝐷𝐴𝐵1 is the C-filter capacitance at the input of the DAB and 𝐶𝐷𝐴𝐵2 is the C-filter
capacitance at the output of the DAB.
CDAB1 is to be connected in parallel at the MVDC-link with the capacitor C-filter capacitor
of the CHB, CCHB. Since CCHB is employed to smooth out the voltage ripples caused by the
switching actions of the CHB, the CDAB1 is also utilised to further reduce the voltage ripples
caused by the switching actions of the DAB converter. Since the voltage ripple over CCHB
operates at a much lower frequency than that over CDAB1, a low-frequency capacitance is
utilised in practical cases for the CCHB while a high-frequency capacitance is implemented
for the CDAB1.
To simplify the analysis in this design, CCHB and CDAB1 are added together to obtain
a total capacitance at the MVDC-link between each H-bridge cell and DAB module as:
𝐶MVDC-Link = 𝐶𝐶𝐻𝐵 + 𝐶𝐷𝐴𝐵1 (3.36)
93
3.6 EV Battery Model
A Li-ion electrochemical BESS is utilised for this research study for the EV battery
for the proposed UFCSEV by selecting a very popular Li-ion battery available in the market
which has the highest nominal cell capacity of 3450 mAh and a nominal cell voltage of
3.60 V as given in the datasheet [276]. For simulation purposes, an electrical-based model
is constructed by implementing the dynamic model proposed in [277-279]. This battery
model is comprised of a controlled-voltage source, which is connected in series with
internal resistors RC and RD for charge and discharge cycles, respectively. In this model,
the controlled-voltage source is dependent on the battery SoC. The charge and discharge
characteristics of the selected battery are independently represented in this model.
However, this model does not take into consideration the effect of temperature and self-
discharge of the selected Li-ion battery, which is also assumed to have no memory effect.
Figure 3.24: Model of the Li-ion EV Battery [277-279]
where Q is the capacity of the EV battery in Ah, IEV is the current flowing through the EV
battery in A, VEV is the voltage across the EV battery in V, RC is the internal resistor in the
charge cycle, RD is the internal resistor in the discharge cycle, 𝐸𝑜 is the constant voltage of
94
the EV battery in V; K is the polarization constant in (V/Ah), C is the polarisation voltage
slope in (V/Ah), 𝑖 is the battery current in A, 𝑖∗ is the filtered battery current in A, t is the
charge or discharge time, 𝑖𝑡 = ∫𝑖 𝑑𝑡 is the battery charge in Ah, 𝐴𝑏 is the exponential zone
amplitude, B is the exponential zone time constant inverse calculated as (𝐴ℎ −1 ), 𝑃𝑜𝑙𝑟𝑒𝑠 is
the polarisation resistance, and u(t) is the charge or discharge mode. For the charge mode,
𝑢(𝑡) = 1, whereas for the discharge mode, 𝑢(𝑡) = 0.
Using the model shown in Figure 3.24, the EV battery SoC during the charging and
discharging processes can be estimated by the following formula [280]:
𝑆𝑜𝐶 = 𝑄𝑜−∫ η 𝐼𝐸𝑉 dt
𝑄 (3.37)
where 𝑄𝑜 is the initial stored charge at the battery in Ah and 𝜂 is the battery efficiency. The
efficiency of the EV battery depends primarily on the charging current and the battery
voltage. The charging efficiency (𝜂𝑐ℎ) and discharging efficiency (𝜂𝑑𝑖𝑠) of the EV battery
can be calculated from the two following equations [3.7]:
η𝑐ℎ = 𝑉𝑂𝐶
𝑉𝑂𝐶 – 𝑅𝐶 𝐼𝐸𝑉 (3.38)
η𝑑𝑖𝑠 = 𝑉𝑂𝐶 − 𝑅𝐷 𝐼𝐸𝑉
𝑉𝑂𝐶 (3.39)
where 𝑉𝑜𝑐 is the open-circuit voltage of the EV battery.
The parameters required to construct the EV battery model are determined from the
charge and discharge curves of the Li-ion battery available in the datasheet [3.43] based on
the procedures reported in [277-278]. The EV battery has a low-pass filter for the current
which is utilised to account for the dynamics of the battery. The polarisation resistance is
different for the charge mode when (𝑢(𝑡) = 1) and the discharge mode when (𝑢(𝑡) = 0),
which can be calculated from [278]:
Pol𝑟𝑒𝑠 = 𝐾 𝑄
𝑄 – 𝑖𝑡 (1 − 𝑢(𝑡)) + 𝐾
𝑄
𝑖𝑡 – 0.1𝑄 (𝑢(𝑡)) (3.40)
The polarisation voltage slope C can be determined from the discharge curve slope
in the linear region, which represents the effect of SoC on the open-circuit voltage of the
EV battery. As can be seen from the discharge curves depicted in Figure 3.26, the initial
95
voltage of the cell terminal of the EV battery varies according to the discharge rate. Due to
the presence of the internal resistance in the EV battery, the initial voltage, at zero discharge
capacity, decreases as the discharge rate increases, which is in accordance with Figure 3.25:
ε = V + I . R (3.41)
where 𝜀 is the terminal voltage in V, V is the open-circuit voltage in V, I is the current
flowing through the battery cell in A, and R is the internal resistance of the battery cell in
Ω. The internal resistance of the battery cell for the discharge and charge cycles are
determined from Figure 3.26 and Equation (3.41) to be 0.085 Ω and 0.114 Ω, respectively.
Figure 3.25: Characteristics of the Charge and Discharge of the Li-ion Battery Cell [276]
The cells of the EV battery need to be stacked together in series and parallel to build
the required battery capacity of 564 kWh for the selected EV: Nova Bus LFSe+ [83]. Table
3.3 below shows the required number of battery cells to be stacked together with the
equivalent resistance for the series and parallel connections for the internal resistance.
96
Table 3.3: Design Parameters of the EV Battery
EV
Battery
Capacity
Number of Battery
Cells (Series x
Parallel)
Nominal
Voltage
Current at 1 C
Charge/Discharge
Rate
Internal Resistances
RC RD
564 kWh 278 x 162 1000 V 580 A 0.085 Ω 0.0114 Ω
3.7 Overall Power Circuit Model of the Modular SST System
Based on the design results shown in Table 5.2, the CHB rectifier requires 10 H-
Bridge cells per phase, totalling 30 CHB cells for the three-phase cascaded connection to
the 27.6 kV distribution feeder. Moreover, one DAB converter module is connected at the
MVDC-link on the side of each H-Bridge cell. A total of 30 DAB modules are constructed
in the whole structure of the SST system model. All DAB modules are connected in parallel
at the LVDC which leads to a fixed voltage at the EV battery side and an increase in power
results in an increase in current flows. The total number of MOSFET switching devices is
360. Figure 3.26 shows the modular structure of the SST topology proposed for the 1.5
MW UFCSEV. Since there are 30 CHB-DAB couples, the proposed topological
configuration is expandable for any voltage level on the CHB rectifier side. A higher or
lower MVAC grid voltage simply requires an increase or decrease in the number of CHB
cells and DAB modules, respectively. Besides its voltage scalability, the SST’s rated power
is also scalable. Since the power on the MVAC grid side is equally distributed among the
CHB-DAB modules, an increase of the SST modules or simply increasing their power
density and handling capabilities provides an overall higher power capability to withdraw
from the MVAC grid to charge the EV battery.
97
Figure 3.26: Topological Configuration of the Modular Structure of the Proposed SST System
The overall system-level model constructed on Simulink is shown in Figure 3.27.
This simulation was first constructed on MATLAB/Simulink and is based on a
time-domain detailed switching model using EMT discrete with a step size simulation of
200 ns to study the transient and dynamic performances of the SST system using
measurement blocks to monitor the simulation results of each converter module at the two
stages and observing the charging output electrical quantities at the load being the EV
battery model.
98
Figure 3.27: System-Level Simulink Model of the Overall Power Circuit of the SST
3.8 Summary
In this chapter, the detailed procedures, and equations for the first-order design of the
SST system were presented while taking into account practical implications such as the
safety margins, harmonic distortions, ripple, and soft switching. To make the design
procedure applicable at any specified power, voltage, or current level, the design formulae
are expressed in a general form. The overall SST power circuit illustrates the modularity
of the selected converter topologies, which allows for further scalability and customisation
to any voltage level and any power rating.
99
Chapter 4. Control System Design and Modulation Scheme
Implementation
This chapter presents the control strategies, schemes, structures, and modulations
techniques utilised in order to keep the proposed SST system operating at the desired
setpoint, especially for the main purpose of the UFCSEV.
For the simulation intended to be carried out in this thesis, the mode in which the SST
system operates is the first quadrant operation (I) mode, where the SST needs to be
controlled properly to provide active power mainly for EV charging. Each conversion stage
of the SST system has specific tasks to keep the MVAC current, the MVAC voltage, the
MVDC voltage, or the LVDC voltage at a constant level. The main objectives of
controlling the power converters at the two-stage SST system during operation are:
For the CHB rectifier: control the MVDC-link between the CHB and DAB constant
(at 2500 V DC) while also maintaining a voltage balance across all cells of the three-phases.
For the DAB converter: control the LVDC side voltage and current at the desired EV
battery specifications constant (i.e. at 1000 V DC maximum charging voltage and 1500
A of charging current at rated charging power).
The overall control scheme for the CHB and DAB converters is based on feedback
controllers used to improve the dynamic behaviour of the SST with high accuracy by
actively monitoring the controlled parameter being measured so as to adjust the duty cycle
in order to obtain the desired steady-state value corresponding to the pre-defined reference
value. In this linear control scheme, the feedback controllers implemented utilise the PI
compensators due to their simplicity for implementation in simulation as well as in practice
[283]. Besides these PI controllers, an extra controller is required for proper operation of
the SST system as well as for grid monitoring in order to derive certain characteristics
about the power grid under both normal and abnormal conditions [284]. This controller is
based on the PLL algorithms to determine the MVAC grid frequency, its angular
frequency, and the RMS value of the supply voltage to the main control loops.
100
4.1 Monitoring System for the Grid based on a Three-Phase PLL
There are several techniques to detect the grid phase by deriving this information based
on the supply voltage zero-crossing detection, arctangent calculation, or PLL algorithms
[284]. Since the PI compensators introduce a steady-state error when operating in the abc-
frame to control the MVAC grid waveforms, those waveforms must be transformed to the
dq0-frame [285, 286]. Transforming the abc-frame to the dq0-frame requires information
about the MVAC grid voltage, in particular the value of the phase angle θg.
For detecting the grid voltage phase angle, the PLL is one of the most widely used
approaches to extracting the phase angle as it demonstrates a robust technique compared
to the other methods because it has better disturbance and noise rejection [284]. For grid-
connected applications, several PLL structures have been presented in the literature [287–
289]. The control system designed in this thesis is based on the classic PLL algorithms by
employing a rotating reference frame, to distinguish between single-phase and three-phase
structures.
The control scheme of the three-phase PLL used for grid monitoring is shown in the
block diagram of Figure 4.1, which includes three blocks namely, the coordinate
transformation from a natural to a rotating reference frame, the PLL algorithm, and the
RMS and frequency measurement systems [290, 291]. The MVAC grid voltage is first
transformed from its natural abc-frame to the stationary αβ-frame using the Clarke
transformation block. The grid voltage is then transformed from the αβ-frame to the dq0-
frame by using an initial estimate of the angular frequency ωo, which is set to 2π times the
nominal grid frequency, which is equal to 120π for 60 Hz, which can be integrated to derive
the grid voltage phase angle, θg. This PLL scheme is also able to extract the grid frequency
fg, from ωg, when appropriately scaled and filtered using an LPF to eliminate the high order
harmonics. The dq0 transformation generates the quadrature component (Vq), which is
compared with the pre-defined reference value for the error signal. The error signal is then
regulated to zero using the PI control compensators in order to synchronise the d-axis of
the synchronous reference frame to the MVAC voltage vector. Until the PLL produces a
phase angle equal to that of the input, then the error signal becomes zero. The values of the
grid frequency and the amplitude of the grid voltage can also be extracted by the PLL.
101
The RMS voltage can also be obtained by the PLL which calculates the absolute value
of the voltage vector in a stationary reference frame which is then divided by √2 to give
the RMS value of the grid voltage. This measurement is performed under non-distorted
grid conditions. In the case where high order harmonics are present on the grid voltage
measurement, an LPF is required for harmonics rejection. However, in the case of an
unbalanced grid voltage, the negative sequence generated on the three-phase grid voltage
system cannot be filtered; therefore, improvements to the PLL algorithm to extract the
positive sequence angle are needed [292].
The built-in PLL block available on MATLAB/Simulink library cannot be used in the
SST control system because its tests have shown unsatisfactory simulation results found in
Section 5.1. This traditional block contains an averaging block used to remove the voltage
ripples using a buffer that stores, for a specified period of time, the value of the voltage
waveform. However, this buffer has technical issues under transient behaviour which result
in unacceptably long computational times. This is because the simulation step size gets
reduced but MATLAB/Simulink has to adjust the size of the buffer dynamically. Thus, the
PLL shown in Figure 4.1 is utilised instead of the built-in block on MATLAB/Simulink.
Figure 4.1: Three-Phase Phase-Locked Loop Structure for Grid Monitoring
where ωg = 2πfg and fg is the grid frequency which is equal to 60 Hz, θg is the grid voltage
phase angle, Kp and Ki are the PI compensator gains of the PI controller.
102
4.2 Control and Modulation for the MVAC-MVDC Conversion Stage
When the power flows from the MVAC grid to the CHB rectifier, the CHB has to
provide a constant output voltage at the MVDC-link. The voltage-mode control (also
known as duty cycle control) consists of a single control loop to adjust the duty cycle
directly as a response to the changes in the voltage output of the CHB. The key advantage
of the voltage-mode control is that it has low requirements in hardware design and reacts
quickly to output voltage disturbances. However, when disturbances happen in the input
voltage, a feed-forward loop is required because the voltage-mode controller reacts rather
slowly in this case since these disturbances have to propagate from the input side to the
output voltage side before they can be measured and adjusted by the controller. On the
other hand, the current-mode control (also known as the current-programmed mode or
current-injected mode) with feed-back methods of two loops: an inner current loop and an
outer voltage loop, is used to generate a constant voltage at the MVDC-link are
implemented for the proposed SST system [293-298]. As can be seen from the control
structure shown in Figure 4.2, the MVDC-link voltage is indirectly controlled by the
current loop, whereas the current is controlled directly. The output voltage of the CHB is
measured and compared to the desired value defined for the reference MVDC. An error
signal is generated as a result of the difference between these two values to produce a
reference current value, which is then compared to the actual current value to finally
generate a duty cycle. This requires a complex control system due to the very robust wide-
bandwidth output voltage control. The current-mode control is utilised in this study because
of its robustness to adjust the MVDC-link voltage properly.
Figure 4.2: Current-Mode Closed-Loop Feedback Controller for the CHB Rectifier
103
The values of the PI controllers can be found by using the mathematical expression
of transfer functions in control theory. In this control system, the open-loop transfer
function comprises of a small-signal transfer function, Gss, and the sampling delay, Tsm.
This sampling delay is caused by the limitation of sampling actions of the DSPs and
microcontrollers, which are to be utilised in order to implement the control scheme. The
closed-loop transfer function can be derived by combining the PI compensator transfer
function, HPI together with the open-loop transfer function, and is expressed as:
𝑇𝑐losed-loop = 𝐻𝑃𝐼 ∗ 𝑇𝑠𝑚 ∗ 𝐺s𝑠 (4.1)
Since the DSP and microcontroller devices have constraints on not permitting the
sampling frequency to be too high. For practical cases, sampling is typically allowed to be
twice per the modulation period. The sampling delay considered in deriving the closed-
loop transfer function of this controller can be roughly estimated using the switching
frequency fsw, by the following equation [294]:
T𝑠𝑚 = 𝑒− 𝑠
1
2𝑓𝑠𝑤 (4.2)
To ensure the control system is stable, the closed-loop transfer function requires
positive values for both the phase margin and the gain margin [301]. The gain margin is
defined as the magnitude at which the phase crosses -180o, whereas the phase margin is
determined at the cut-off frequency 𝑓𝑐𝑢𝑡, from the formula below [293]:
ph𝑎𝑠𝑒 𝑚𝑎𝑟𝑔𝑖𝑛 = 180° + ∠𝑇𝑐𝑙osed-loop (𝑗2𝜋𝑓𝑐𝑢𝑡) (4.3)
The cut-off frequency is the frequency where the magnitude of the loop gain crosses
0dB, so the magnitude is unity or 0 dB:
|𝑇 (𝑗2𝜋𝑓𝑐𝑢𝑡)| = 0 dB = 1 (4.4)
where T is the transfer function of the open-loop or the closed-loop.
The controller bandwidth depends primarily on the maximum cut-off frequency;
which equals half the switching frequency because of the sampling delay. The PI
compensator can be generally described in terms of the lag frequency, flag which should
104
have a value that is much lower than the cut-off frequency, 𝑓𝑐𝑢𝑡. The interference of the
integrator at the cut-off frequency can be avoided as follows:
H𝑃𝐼(𝑠) = H∞ ∗ (1 +2𝜋𝑓𝑙𝑎𝑔
𝑠) (4.5)
where H∞ is the gain at s ⸻> ∞.
The PI control compensator is commonly expressed in terms of the proportional
gain Kp and the integral gain Ki as follows:
H𝑃𝐼(𝑠) = H∞ (𝐾𝑝 +𝐾𝑖
𝑠) (4.6)
The magnitude value of the PI compensator can be calculated using equations (4.1)
and (4.4) from the following:
|H∞| = |1
𝑇𝑠𝑚(j2π𝑓𝑐𝑢𝑡)∗𝐺𝑠𝑠(j2π𝑓𝑐𝑢𝑡)∗(1+2𝜋𝑓𝑙𝑎𝑔
𝑠) | (4.7)
Then the PI-compensators of the controller can be constructed as:
H𝑃𝐼 = −sign∠T(j2π𝑓𝑐𝑢𝑡) ∗ H∞ ∗ (1 +2𝜋𝑓𝑙𝑎𝑔
𝑠) (4.8)
The negative sign of the transfer function of the open-loop is utilised as a correction
factor for the absolute values determined from Equation (4.7).
For voltage balance across all three phases, the MVDC-voltages are summed together and
then averaged to be compared to the desired reference value of the MVDC, VMVDC* which
is set to 2500 V DC. Voltage balancing is required to handle any imbalances that may occur
in the system due to device losses or negative sequence voltages. The PI controller
compensates for the error generated, and then the output value is fed to the inner current-
loop as a decoupled current control scheme shown in Figure 4.3, which includes interphase
balancing control to balance the average MVDC link voltages between the three phases.
Besides regulating the overall MVDC-link voltage, the power factor can be corrected.
Moreover, the PLL algorithm shown in Figure 4.1 is implemented to synchronise the
control signals with the grid phase angle, θg.
105
Figure 4.3: Decoupled Current Control Scheme for Three-Phase Single Cell of the CHB Rectifier
As can be seen from Figure 4.3, the Park transformation block converts the three-
phase signals into the d-q rotating reference frame as given by the following matrix:
[𝑑𝑞] =
2
3 [
𝑐𝑜𝑠(𝜃𝑔) 𝑐𝑜𝑠 (𝜃𝑔 −2𝜋
3) 𝑐𝑜𝑠(𝜃𝑔 +
2𝜋
3)
−𝑠𝑖𝑛(𝜃𝑔) −𝑠𝑖𝑛 (𝜃𝑔 −2𝜋
3) −𝑠𝑖𝑛(𝜃𝑔 +
2𝜋
3)] [
𝐴𝐵𝐶] (4.9)
where θg is the angle between the A and d axes for the q-axis alignment or the angle between
the A and d axes for the d-axis alignment, ω is the rotational speed of the d-q reference
frame, and t is the time, in s, from the initial alignment.
Figure 4.4 shows the alignment of the A-phase vector to the d-axis for a balanced ABC and
dq0 system where A, B, and C are the components of the three-phase system in the ABC
reference frame, d and q are the components of the two-axis system in the rotating reference
frame, and 0 is the zero component of the two-axis system in the stationary reference frame.
106
Figure 4.4: ABC and dq0 Frames with A-axis and the d-axis initially aligned
The PI controllers can easily control the signals within the d-q reference frame,
using the θg obtained from the PLL block, where the MVAC grid side voltage and current
measurements are transformed to the d-q reference frame. In the d-q reference frame, the
d component is utilised to control the active power flow, whereas and the q component
pertains to the reactive power flow. Combined with the sinusoidal phase-shifted PWM
carries as the selected modulation technique for this controller, setting the dq components’
parameters of the controller can also provide control for PFC aiming at a unity power
factor, which prevents any possible penalties incurred from the local grid utility for low
power factor. For G2V applications with unidirectional power flow, the q-axis current
command, Iq_MVAC*, is set zero. This corresponds to a unity power factor which also avoids
any related power loss. The decoupling factor, ωLCHB takes into consideration the MVAC
grid side L-filter inductance between the MVAC grid connection and the CHB rectifier
input. The d-axis voltage and q-axis voltage commands are generated to be transformed
back to the ABC reference frame by an inverse Park transformation block for the final
three-phase voltage commands.
107
To balance the average voltage across the 10 MVDC-link capacitors in each phase,
two levels of balancing control are implemented in this control. First, the three-phase
voltages are controlled by the interphase balancing control where an average MVDC
voltage between phases is obtained as already shown in Figure 4.3. Another balancing
control is the intraphase balancing, which is implemented to balance the voltages of each
H-bridge cell of the CHB rectifier within one phase. In order to achieve the desired control
objectives, voltage measurements of the 10 MVDC-link capacitor, MVAC grid side phase
voltages, and MVAC grid side phase currents are taken as feedback signals. Figure 4.5
provides the block diagram of the voltage balance scheme for the multi-level CHB in which
the voltage equalising among all CHB cells is realised. A voltage command is set to the
desired overall MVDC-link voltage, VMVDC* = 2500 V, which is to be compared with the
sum of all ten MVDC-link capacitors. The balancing control is selected to be a single PI
stage utilised as a voltage regulator. This control avoids any steady-state errors as compared
to the cascaded proportional controllers implemented in [302, 303] that use the average
MVDC-link voltage and active current, Id_MVAC, as integral action, which has been found
in this study susceptible to errors.
Figure 4.5: Voltage Balancing Control Scheme for the Multi-level CHB Rectifier
108
To achieve balance on the individual level of each CHB cell, active current is
distributed within each phase by adjusting the amount of time each H-bridge is active:
V𝑀𝑉𝐷𝐶_𝑖𝑛 =1
𝑛(𝑉𝑀𝑉𝐷𝐶_𝑖𝑛 + 𝑉𝑀𝑉𝐷𝐶_𝑖𝑛 + ⋯+ 𝑉𝑀𝑉𝐷𝐶_𝑖𝑛) 𝑓𝑜𝑟 𝑛 = 1… N𝐶𝐻𝐵 (4.10)
The average voltage at the MVDC-link of each phase is calculated by averaging the
MVDC-link voltages of the three phases:
V𝑀𝑉𝐷𝐶_𝑎𝑣𝑒𝑟𝑎𝑔𝑒 =1
3(𝑉𝑀𝑉𝐷𝐶_𝐴 + 𝑉𝑀𝑉𝐷𝐶_𝐵 + 𝑉𝑀𝑉𝐷𝐶_𝐶) (4.11)
where I is either phase A, B or C
To avoid conflicting controls, the intraphase balancing controller is purposely
under-tuned compared to the controller of the interphase balance. In this case, intraphase
is seen as the outer voltage loop, whereas the interphase balance is seen as the inner current
loop. For the interphase balancing control, the error signal is then fed to the PI controller
with a balancing signal that is multiplied by cos(θ), with θ being the phase obtained from
the PLL block. This is to align the individual PS-PWM modulation signals in phase or 180
out of phase with the summed voltage commands of the previous levels of control.
The PS-PWM carries-based modulation technique is implemented in the MVAC-
MVDC CHB rectification stage, to generate the gate signals for the CHB rectifier’s
MOSFETs as it is the most appropriate modulation scheme for cascaded multi-level
converters given the key advantages described in Table 2.7. The PS-SPWM method carries
are based on sine-triangle PWM which considers the number of CHB cells within a single
phase as can be seen from the modulation waveforms example of a single-phase CHB cells
shown in Figure 4.6 below. Each triangular carrier waveform is assigned for one CHB cell.
The PWM carrier waveforms operate at the selected CHB switching frequency but are
staggered in phase by 2π/NCHB. This interleaving of the PWM carrier waveforms generates
the “effective” switching frequency of 2NCHBfsw. To generate the gate signals for each
phase in unipolar modulation, the sinusoidal PWM signals are adjusted to be equal and
opposite signal to be superimposed on the PWM carrier waveforms. In the case of a voltage
imbalance within a phase, each CHB cell has its own modulation signal that varies in
109
magnitude. The resulting PWM modulation signal redirects the active current to or from
their respective capacitor at the MVDC-link. To handle any voltage imbalances, this same
procedure is then applied for the remaining two phases with the sinusoidal PWM
modulation signal being phase shifted by ±2π/3 and varied in magnitude [304, 305].
Figure 4.6: Carrier Signals of the CHB Cells for Phase-A based on Phase Shift Sinusoidal
Pulse Width Modulation (PS-SPWM)
The MVAC phase current can be adjusted by increasing or decreasing the
magnitude of the PS-PWM modulation signal without imposing any phase shift. This
approach is then applied for each of the other two phases B and C, by substituting θ with θ
– 2π/3 and θ + 2π/3, respectively. Since each phase acts as a single-phase CHB cell
operating under unipolar modulation technique, there is a significant second harmonic at
120 Hz, which can make the MVDC feedback signal appear sinusoidal, degrading the CHB
rectifier performance. The performance of the PI controller in a practical design can be
improved by applying a low-pass or notching filter to the feedback signals of each phase
[304, 305].
The transfer function for the outer voltage-loop of the CHB rectifier control can be
derived by developing a dynamic averaged model in order to approximate the original
110
system by averaging the effect of the fast-switching circuit while preserving the low-
frequency behaviour of the converter [293, 294]. The averaged model has to be linearised
around a quiescent operation point, in which the harmonics of the modulation or excitation
frequency are neglected. A small-signal model is then derived using the average model to
obtain the required transfer functions, which are then utilised to adjust the gains of the PI
controllers to obtain stability. This section deals with obtaining the small-signal model of
the CHB and its closed-loop current control using the three-phase dq transformation to
control the voltage at the MVDC-link of the SST system.
To construct an averaged switch model of the CHB rectifier, the switch network is
to be replaced with its averaged switch network in order to obtain a complete averaged
circuit of the converter. The switch network is comprised of one switch or more and diode
pairs, while its averaged switch model contains a controlled voltage and current source.
The average model removes the high-frequency components of the switching leaving only
the fundamental frequency. The switching function is averaged over one period and then
replaced with an averaged switch model with an operator, which can be expressed as [293,
297, 298]:
𝑑 = 1
𝑇𝑠∫ 𝑆(𝜏) 𝑑𝜏
𝑡+𝑇𝑠
𝑡 (4.12)
where d is the average switching function or the duty cycle, Ts is the fundamental period,
and S(τ) is the switching function.
The averaged model of a single H-Bridge cell in a single-phase circuit is shown in
Figure 4.4 where the H-Bridge switching devices are replaced with a controlled voltage
source on the MVAC grid side and a controlled current source on the MVDC-link side,
whereas the other power circuit components remain unchanged.
Using the averaging operator of Equation (4.12), the controlled voltage source and
controlled current source of the DAM, shown in Figure 4.7, are expressed by:
𝐕 𝑀𝑉𝐷𝐶 = (
1
𝑇𝑠∫ 𝑆(𝜏) 𝑑𝜏
𝑡+𝑇𝑠
𝑡) ∗ V𝑀𝑉𝐷𝐶 = 𝑑𝑉𝑀𝑉𝐷𝐶 (4.13)
𝐈 𝑀𝑉𝐷𝐶−𝐶𝐻𝐵 = (1
𝑇𝑠∫ 𝑆(𝜏) 𝑑𝜏
𝑡+𝑇𝑠
𝑡) ∗ I𝑀𝑉𝐴𝐶 = 𝑑𝐼𝑀𝑉𝐴𝐶 (4.14)
111
Figure 4.7: Averaged Model of a Single H-Bridge Cell of the CHB Rectifier in Single-Phase
The same approach can be applied for the CHB rectifier with multiple cells of NCHB,
where the averaging operator is applied for the voltage and current equations below for the
three-phase circuit of the CHB rectifier shown in Figure 4.8. The average voltage and
current equations are expressed as follows:
𝐕 𝐶𝐻𝐵−𝑖 = ∑ (d𝑖𝑛−𝐶𝐻𝐵
N𝐶𝐻𝐵
𝑛=1∗ V𝑖𝑛_𝑀𝑉𝐷𝐶
) (4.15)
𝐈 𝑖𝑛_𝑀𝑉𝐷𝐶−𝐶𝐻𝐵 = d𝑖𝑛−𝐶𝐻𝐵 ∗ I𝑀𝑉𝐴𝐶𝑖 𝑓𝑜𝑟 𝑛 = 1… N𝐶𝐻𝐵 (4.16)
where I is either phase A, B or C, 𝐕𝐶𝐻𝐵−𝑖 is the MVAC generated by phase I across the
CHB, V𝑖𝑛𝑀𝑉𝐷𝐶 is the voltage on the MVDC-link side of the nth H-bridge cell, din is the
average switching function for the nth H-bridge cell in phase I, and 𝐈𝑀𝑉𝐴𝐶𝑖 is the MVAC
current flowing from phase i.
112
Figure 4.8: Averaged Model of the Three-Phase Circuit of the CHB Rectifier with NCHB Cells
As can be seen from Figure 4.8, this model is still too complicated to derive the
controller transfer functions. In this case, the following assumptions are considered for
further simplifications:
1) The voltages of the MVDC-links of all CHB cells are the same:
𝐕𝑀𝑉𝐷𝐶 = V𝐴𝑛_𝑀𝑉𝐷𝐶 = V𝐵𝑛_𝑀𝑉𝐷𝐶 = V𝐶𝑛_𝑀𝑉𝐷𝐶 𝑓𝑜𝑟 𝑛 = 1… N𝐶𝐻𝐵 (4.17)
where VMVDC is the average voltage on the MVDC-link side of each cell of the CHB.
2) The load of each CHB cell is the same, thus the MVAC currents flowing
from all three phases are the same.
𝐑𝐿 = R𝐿−𝐴𝑛 = R𝐿−𝐵𝑛 = R𝐿−𝐶𝑛 𝑓𝑜𝑟 𝑛 = 1… N𝐶𝐻𝐵 (4.18)
|𝐈𝑀𝑉𝐴𝐶| = |𝐈𝑀𝑉𝐴𝐶_𝐴| = |𝐈𝑀𝑉𝐴𝐶_𝐵| = |𝐈𝑀𝑉𝐴𝐶_𝐶| 𝑓𝑜𝑟 𝑛 = 1… N𝐶𝐻𝐵 (4.19)
113
where RL is the load of each CHB cell, and |IMVAC| is the amplitude of the MVAC phase
current.
3) Since each voltage across the MVDC-link is assumed to be equal, the duty
cycles in the same phase are assumed to be all equal.
These assumptions allow the controlled voltage sources can be replaced with only
one controlled voltage source that is NCHB times the value of a single controlled voltage
source; therefore, the simplified averaged model is shown in Figure 4.9 below.
Figure 4.9: Simplified Averaged Model of the Three-Phase CHB Rectifier with NCHB Cells
To derive the transfer functions that are required to tune the CHB PI control system
compensator gains from the simplified averaged model shown in Figure 4.9, the small-
signal model is utilised by formulating the equations for the MVAC and MVDC side of the
CHB rectifier using Kirchhoff’s Voltage Law as follows:
114
N𝐶𝐻𝐵 ∗ 𝐕𝑀𝑉𝐷𝐶 ∗ [
𝐝𝐴−𝐶𝐻𝐵
𝐝𝐵−𝐶𝐻𝐵
𝐝𝐶−𝐶𝐻𝐵
] + 𝐋𝐶𝐻𝐵𝑑
𝑑𝑡 [
𝐈𝑀𝑉𝐴𝐶𝐴
𝐈𝑀𝑉𝐴𝐶𝐵
𝐈𝑀𝑉𝐴𝐶𝐶
] + 𝐑𝐶𝐻𝐵 [
𝐈𝑀𝑉𝐴𝐶𝐴
𝐈𝑀𝑉𝐴𝐶𝐵
𝐈𝑀𝑉𝐴𝐶𝐶
] + [
𝐕𝑀𝑉𝐴𝐶−𝑝ℎ𝐴
𝐕𝑀𝑉𝐴𝐶−𝑝ℎ𝐵
𝐕𝑀𝑉𝐴𝐶−𝑝ℎ𝐶
] = 0 (4.20)
[𝐝𝐴𝑛−𝐶𝐻𝐵 𝐝𝐵𝑛−𝐶𝐻𝐵 𝐝𝐶𝑛−𝐶𝐻𝐵] [
𝐈𝑀𝑉𝐴𝐶𝐴
𝐈𝑀𝑉𝐴𝐶𝐵
𝐈𝑀𝑉𝐴𝐶𝐶
] − 𝟑𝐂𝑀𝑉𝐷𝐶𝑑
𝑑𝑡 𝐕𝑀𝑉𝐷𝐶 −
3
𝐑𝐿 𝐕𝑀𝑉𝐷𝐶 = 0 𝑓𝑜𝑟 𝑛 = 1…𝐍𝐶𝐻𝐵 (4.21)
Since the controller is based on PI compensators, Equations (4.20) and (4.21) are
to be rewritten in the dq-domain using the Park transformation [299] as follows:
N𝐶𝐻𝐵 ∗ 𝐕𝑀𝑉𝐷𝐶 ∗ [𝐝𝑑−𝐶𝐻𝐵
𝐝𝑞−𝐶𝐻𝐵] + 𝐋𝐶𝐻𝐵
𝑑
𝑑𝑡 [𝐈𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞
] − [0 𝐋𝐶𝐻𝐵ω𝑔
−𝐋𝐶𝐻𝐵ω𝑔 0] [
𝐈𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞
] + 𝐑𝐶𝐻𝐵 [𝐈𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞
] − (𝐕𝑀𝑉𝐴𝐶−𝑝ℎ_𝑑
𝐕𝑀𝑉𝐴𝐶−𝑝ℎ_𝑑) (4.22)
[𝐝𝑑𝑛−𝐶𝐻𝐵 𝐝𝑞𝑛−𝐶𝐻𝐵] [𝐈𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞
] − 𝟑𝐂𝑀𝑉𝐷𝐶𝑑
𝑑𝑡 𝐕𝑀𝑉𝐷𝐶 −
3
𝐑𝐿 𝐕𝑀𝑉𝐷𝐶 = 0 𝑓𝑜𝑟 𝑛 = 1…𝐍𝐶𝐻𝐵 (4.23)
In order to construct the small-signal model, the time-varying signals of Equations
(4.22) and (4.23) are to be linearised around a quiescent operating point. This can be
achieved by giving the time-varying variable x a quiescent value X added with a
superimposed small perturbation ; that is 𝑥 = 𝑋 + , as to be applied to Equations (4.22)
and (4.23) as follows [293]:
N𝐶𝐻𝐵 ∗ (𝐕𝑀𝑉𝐷𝐶 + 𝑣𝑀𝑉𝐷𝐶) ∗ [𝐃𝑑−𝐶𝐻𝐵 + d𝑑−𝐶𝐻𝐵
𝐃𝑞−𝐶𝐻𝐵 + d𝑞−𝐶𝐻𝐵
] + 𝐋𝐶𝐻𝐵𝑑
𝑑𝑡 [𝐈𝑀𝑉𝐴𝐶𝑑
+ 𝑖𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞+ 𝑖𝑀𝑉𝐴𝐶𝑞
] − [0 𝐋𝐶𝐻𝐵ω𝑔
−𝐋𝐶𝐻𝐵ω𝑔 0] [
𝐈𝑀𝑉𝐴𝐶𝑑+ 𝑖𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞+ 𝑖𝑀𝑉𝐴𝐶𝑞
] +
𝐑𝐶𝐻𝐵 [𝐈𝑀𝑉𝐴𝐶𝑑
+ 𝑖𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞+ 𝑖𝑀𝑉𝐴𝐶𝑞
] − [𝐕𝑀𝑉𝐴𝐶−𝑝ℎ𝑑
+ 𝑣𝑀𝑉𝐴𝐶−𝑝ℎ𝑑
𝐕𝑀𝑉𝐴𝐶−𝑝ℎ𝑑 + 𝑣𝑀𝑉𝐴𝐶−𝑝ℎ𝑑 ] = 0 (4.24)
[𝐃𝑑−𝐶𝐻𝐵 + d𝑑−𝐶𝐻𝐵 𝐃𝑞−𝐶𝐻𝐵 + d𝑞−𝐶𝐻𝐵] [𝐈𝑀𝑉𝐴𝐶𝑑
+ 𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞+ 𝑀𝑉𝐴𝐶𝑞
] − 𝟑𝐂𝑀𝑉𝐷𝐶𝑑
𝑑𝑡 (𝐕𝑀𝑉𝐷𝐶 + 𝑀𝑉𝐷𝐶) −
3
𝐑𝐿(𝐕𝑀𝑉𝐷𝐶 + 𝑀𝑉𝐷𝐶) = 0
(4.25)
The quiescent value of the duty cycle for a given current can be found by
considering only the DC terms of Equation (4.24). This yields to the equation below, which
will be utilised for the decoupling between the dq0-frame:
[𝐃𝑑−𝐶𝐻𝐵
𝐃𝑞−𝐶𝐻𝐵] = −
𝐑𝐶𝐻𝐵−[0 𝐋𝐶𝐻𝐵ω𝑔
−𝐋𝐶𝐻𝐵ω𝑔 0][
𝐈𝑀𝑉𝐴𝐶𝑑
𝐈𝑀𝑉𝐴𝐶𝑞]+ [
𝐕𝑀𝑉𝐴𝐶−𝑝ℎ𝑑
𝐕𝑀𝑉𝐴𝐶−𝑝ℎ𝑑
]
𝐍𝐶𝐻𝐵 ∗ 𝐕𝑀𝑉𝐷𝐶
(4.26)
115
The small-signal model can be formed by using the first-order AC terms of
Equations (4.24) and (4.25) and neglecting the second-order terms. Using Laplace
transform domain with the operator s Equations (4.24) and (4.25) are expressed as below:
N𝐶𝐻𝐵(𝐕𝑀𝑉𝐷𝐶 ∗ d𝑑−𝐶𝐻𝐵) + N𝐶𝐻𝐵(𝑀𝑉𝐷𝐶 ∗ 𝐃𝑑−𝐶𝐻𝐵) + (𝐬𝐋𝐶𝐻𝐵 + 𝐑𝐶𝐻𝐵) ∗ 𝑀𝑉𝐴𝐶_𝑑 – (𝐋𝐶𝐻𝐵ω𝑔 ∗ 𝑀𝑉𝐴𝐶𝑞) − 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑑 = 0 (4.27)
N𝐶𝐻𝐵(𝐕𝑀𝑉𝐷𝐶 ∗ d𝑞−𝐶𝐻𝐵) + N𝐶𝐻𝐵(𝑀𝑉𝐷𝐶 ∗ 𝐃𝑞−𝐶𝐻𝐵) + (𝐬𝐋𝐶𝐻𝐵 + 𝐑𝐶𝐻𝐵) ∗ 𝑀𝑉𝐴𝐶_𝑞 – (𝐋𝐶𝐻𝐵ω𝑔 ∗ 𝑀𝑉𝐴𝐶𝑑) − 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑞 = 0 (4.28)
(𝐃𝑑−𝐶𝐻𝐵 ∗ 𝑀𝑉𝐴𝐶𝑑) + (d𝑑−𝐶𝐻𝐵 ∗ 𝐈𝑀𝑉𝐴𝐶_𝑑) + (𝐃𝑞−𝐶𝐻𝐵 ∗ 𝑀𝑉𝐴𝐶𝑞
) + ( d𝑞−𝐶𝐻𝐵 ∗ 𝐈𝑀𝑉𝐴𝐶𝑞 ) − (𝟑𝐂𝑀𝑉𝐷𝐶 +
3
𝐑𝐿)𝑀𝑉𝐷𝐶 = 0
(4.29)
The control-to-output current transfer function for the d-frame of the current
decoupled controller can be derived from Equations (4.27–4.29) by keeping only the
variables that are of interest and setting all other AC variations to zero as follows:
G𝐼𝑑𝑑−𝐶𝐻𝐵 =𝑀𝑉𝐴𝐶_𝑑
d𝑑−𝐶𝐻𝐵 (4.30)
by applying these conditions: d𝑞−𝐶𝐻𝐵 = 𝑀𝑉𝐷𝐶 = 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑑 = 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑞 = 0 , Equation (4.27)
becomes:
N𝐶𝐻𝐵(𝐕𝑀𝑉𝐷𝐶 ∗ d𝑑−𝐶𝐻𝐵) + (𝐬𝐋𝐶𝐻𝐵 + 𝐑𝐶𝐻𝐵) ∗ 𝑀𝑉𝐴𝐶_𝑑 – (𝐋𝐶𝐻𝐵ω𝑔 ∗ 𝑀𝑉𝐴𝐶𝑞) = 0 (4.31)
The transfer function of the control-to-output-current for the d-frame is then
expressed by using Equations (4.29–4.31) as follows:
G𝐼𝑑𝑑−𝐶𝐻𝐵 =𝑀𝑉𝐴𝐶_𝑑
d𝑑−𝐶𝐻𝐵= −
(N𝐶𝐻𝐵∗𝐕𝑀𝑉𝐷𝐶)∗(𝐬𝐋𝐶𝐻𝐵+𝐑𝐶𝐻𝐵)
(𝐬𝐋𝐶𝐻𝐵+𝐑𝐶𝐻𝐵)2+ (ω𝑔2∗L𝐶𝐻𝐵
2) (4.32)
The transfer function for the control-to-output-current in the q-frame is the same of
that in the d-frame and has the same final equation shown below:
G𝐼𝑑𝑞−𝐶𝐻𝐵 =𝑀𝑉𝐴𝐶_𝑞
d𝑞−𝐶𝐻𝐵= −
(N𝐶𝐻𝐵∗𝐕𝑀𝑉𝐷𝐶)∗(𝐬𝐋𝐶𝐻𝐵+𝐑𝐶𝐻𝐵)
(𝐬𝐋𝐶𝐻𝐵+𝐑𝐶𝐻𝐵)2+ (ω𝑔2∗L𝐶𝐻𝐵
2) (4.33)
where d𝑑−𝐶𝐻𝐵 = 𝑀𝑉𝐷𝐶 = 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑑 = 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑞 = 0
The transfer function for the output-current-to-voltage of the MVDC-link can be
derived from (4.29) by setting the AC variation of the duty cycle and MVAC grid voltage
in the dq-frame to zero as well as removing the load RL:
116
G𝑉𝐼𝑑−𝐶𝐻𝐵 =𝑀𝑉𝐷𝐶
𝑀𝑉𝐴𝐶_𝑑 (4.34)
by applying these conditions: d𝑑−𝐶𝐻𝐵 = d𝑞−𝐶𝐻𝐵 = 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑑 = 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑞 = 0, Equation (4.29)
becomes:
(𝐃𝑑−𝐶𝐻𝐵 ∗ 𝑀𝑉𝐴𝐶_𝑑) + (𝐃𝑞−𝐶𝐻𝐵 ∗ 𝑀𝑉𝐴𝐶_𝑞 ) − (𝟑𝐬𝐂𝑀𝑉𝐷𝐶 ∗ 𝑀𝑉𝐷𝐶) = 0 (4.35)
Also, by applying these conditions: d𝑑−𝐶𝐻𝐵 = d𝑞−𝐶𝐻𝐵 = 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑑 = 𝑀𝑉𝐴𝐶−𝑝ℎ−𝑞 = 0, to Equation
(4.27) to find the value of 𝑀𝑉𝐴𝐶_𝑞:
𝑖𝑀𝑉𝐴𝐶_𝑞 = −L𝐶𝐻𝐵 ∗ ω𝑔
𝐬𝐋𝐶𝐻𝐵+𝐑𝐶𝐻𝐵∗ (𝑖𝑀𝑉𝐴𝐶𝑑
) − 𝐍𝐶𝐻𝐵∗ 𝐃𝑞−𝐶𝐻𝐵
𝐬𝐋𝐶𝐻𝐵+𝐑𝐶𝐻𝐵∗ (𝑀𝑉𝐷𝐶) (4.36)
The final transfer function for the output-current-to-voltage of the MVDC-link controller
can be expressed by using Equations (4.30–4.31) as follows:
G𝑉𝐼𝑑−𝐶𝐻𝐵 =𝑀𝑉𝐷𝐶
𝑀𝑉𝐴𝐶_𝑑 =
(𝐃𝑑−𝐶𝐻𝐵
) ∗(𝐬𝐋𝐶𝐻𝐵+𝐑𝐶𝐻𝐵) – (𝐃𝑞−𝐶𝐻𝐵
∗ L𝐶𝐻𝐵∗ ω𝑔)
𝐍𝐶𝐻𝐵 ∗ ((𝐃𝑞−𝐶𝐻𝐵
))2+ 3𝐬𝐂𝑀𝑉𝐷𝐶 (𝐬𝐋𝐶𝐻𝐵+𝐑𝐶𝐻𝐵)
(4.37)
When controlling the current flowing from the MVAC grid to the desired value by
the CHB rectifier cells, the voltage at the MVDC-link VDAB1 is controlled by the DAB
converter modules and therefore is assumed to be constant. The three-phase MVAC grid
current flowing through the L-filter inductor LCHB of each phase is measured and
transformed to the dq-frame using the Park transform block which converts the time-
domain current components of ABC reference frame to direct, quadrature, and zero (dq0)
components in a rotating reference frame. This modelling block can also preserve the active
and reactive powers with the SST powers in the abc reference frame by implementing an
invariant version of the Park transform. For a balanced system, the zero component is equal
to zero. The dq0 current values are then compared with the desired dq0-value which are
predefined in this model and are shown with an asterisk. The error signal is fed to the PI
controller, which has compensators that are properly selected using the transfer functions
derived from the averaged models described above. The desired current value can be
generated at ideally zero error, or a very small error is sufficient for that [293, 295].
The closed-loop transfer functions for the single-level CHB currents by taking into
account the sampling delay can be found from:
117
T𝑠𝑚−𝐶𝐻𝐵−1𝑛 = 𝑒− 𝑠
1
2𝑓𝐶𝐻𝐵 (4.38)
𝑇Idd-CHB-1n = 𝐻 Idd-CHB-1n ∗ 𝑇𝑠𝑚-CHB-1n ∗ 𝐺 Idd-CHB (4.39)
𝑇Idq-CHB-1n = 𝐻 Idq-CHB-1n ∗ 𝑇𝑠𝑚-CHB-1n ∗ 𝐺 Idq-CHB (4.40)
For each H-Bridge cell, the theoretical cut-off frequency fcut is at half the switching
frequency fCHB; but the achievable fcut is much lower due to the sampling delay.
The current-loop, shown in Figure 4.2, serves as an intermediate step between the
voltage-loop and the duty cycle, and therefore its closed-loop transfer function from
equation (4.39) has to be added to that of the voltage-loop, to Equation (4.41) below. To
avoid any interference between the inner-current-loop as a result of the operation of the
outer-voltage-loop, the fcut for the PI compensator of the outer-voltage-loop is selected to
be nearly 1/10th of the fcut of the inner-current-loop.
T𝑉𝐼𝑑−𝐶𝐻𝐵−1𝑁 = H𝑉𝐼𝑑−𝐶𝐻𝐵−1𝑁 ∗ G𝑉𝐼𝑑−𝐶𝐻𝐵 ∗ T𝐼𝑑𝑑−𝐶𝐻𝐵−1𝑛
T𝐼𝑑𝑑−𝐶𝐻𝐵−1𝑛+1 (4.41)
4.3 Control and Modulation for the MVAC-LVDC Conversion Stage
Since the DAB modules are connected between the CHB cells in series and the EV
battery in parallel, voltage control is required to maintain the VMVDC and VLVDC as constant
to their rated value as possible. The voltage which is controlled by the DAB is determined
by the mode it is operating in. Depending on the SST operation, the DAB is responsible
for keeping the VLVDC at a constant value when operating in G2V charging, or the DAB
would be responsible for keeping the VMVDC constant when the SST operates in V2G. The
focus of this section would be on the G2V operation where the DAB controller should be
primarily controlling the VLVDC.
The closed-loop current-mode control scheme with an inner current-loop and an
outer-voltage-loop implemented for the DAB converter is shown in Figure 4.10 below.
118
Figure 4.10: Current-Mode Closed-Loop Feedback Controller for the DAB Converter
Using the same approach utilised to derive the DAM of the CHB rectifier in Section
4.2, the dynamic averaged model of a single module of the DAB converter is shown in
Figure 4.11 below. However, since the DAB is to be operated in high frequency, using this
model results in increased computational time for a long period of simulating multi-kHz
waveforms. For system-level dynamic simulations, the currents and voltages of the HFT
are of less importance to be considered compared to other SST system waveforms. In this
case, only the input and output voltages of the DAB converter are considered in deriving a
mathematical averaged model in order to speed up the simulations. Assuming the DAB
converter is lossless, the relationship between the primary and secondary powers as the
input and output parameters can be determined by the power balance as follows:
𝑃DAB1 = 𝑃DAB2 ⇔ VMVDC I𝐷𝐴𝐵1 = VLVDC I𝐷𝐴𝐵2 (4.42)
Where PDAB1 is the input power to the DAB supplied from the CHB side through
the MVDC-link, which can be calculated using [300]:
𝑃DAB1 =n𝐻𝐹𝑇 ∗ 𝑉𝑀𝑉𝐷𝐶 ∗ 𝑉𝐿𝑉𝐷𝐶
2 ∗ 𝑓𝐷𝐴𝐵 ∗ 𝐿𝐷𝐴𝐵 ∗ d𝐷𝐴𝐵 (1 – d𝐷𝐴𝐵) (4.43)
where dDAB is the duty cycle of the DAB, and PDAB2 is the output power of the DAB
to be transferred to the EV battery side through the LVDC-link.
The input and output currents of the DAB can be found from Equation (4.42) and
(4.43) as follows:
IDAB1 =n𝐻𝐹𝑇 ∗ 𝑉𝐿𝑉𝐷𝐶
2 ∗ 𝑓𝐷𝐴𝐵 ∗ 𝐿𝐷𝐴𝐵 ∗ d𝐷𝐴𝐵 (1 – d𝐷𝐴𝐵) (4.44)
119
IDAB2 =n𝐻𝐹𝑇 ∗ 𝑉𝑀𝑉𝐷𝐶
2 ∗ 𝑓𝐷𝐴𝐵 ∗ 𝐿𝐷𝐴𝐵 ∗ d𝐷𝐴𝐵 (1 – d𝐷𝐴𝐵) (4.45)
Since the values of the input current flowing to the DAB and the output current
flowing out of the DAB are linked to the opposite side of the HFT by means of the voltage
value, an averaged model using these two equations is shown in Figure 4.11.
As can be seen from Figure 4.11, this model does not contain enough parameters
to construct a small-signal model to derive the transfer functions. The state-space averaging
is an alternative approach to deriving the small-signal model of the DAB converter, which
can be derived as linear combination independent inputs. In this state-space, the physical
state of the DAB energy storage elements, such as capacitor voltages and inductor currents
are described. The description of state-space is the first step to construct the state-space
averaged model such that each switching interval is derived and multiplied with the duty
cycle for that interval [293].
When the SST system operates in G2V for charging the EV battery, the DAB
behaves as a buck converter where the power flows from the MVDC side to the LVDC
side. Figure 4.12 shows the HFT voltage waveforms of the HFT of the DAB module.
Figure 4.11: Dynamic Averaged Model of a Single Module of the DAB Converter
120
Figure 4.12: Voltage Waveforms of the DAB HFT with the Operation States of MOSFETs
Figure 4.13 below shows the equivalent circuit of the DAB model shown in Figure
4.11 during t0 with the parameters transferred to the secondary side of the HFT. For period
t1, the equivalent circuit diagram of the DAB model is shown in Figure 4.14.
Figure 4.13: Equivalent Circuit of the Dynamic Averaged Model of the DAB Module for period t0
121
Figure 4.14: Equivalent Circuit of the Dynamic Averaged Model of the DAB Module for period t1
where LDAB’’ = LDAB/ ηHFT 2 and RDAB’’ = RDAB/ ηHFT 2
For analysis, further simplifications of Figures 4.13 and 4.14 by reducing the
circuits to simplified circuits as shown in Figure 4.15 and Figure 4.16 below. Since the
voltage waveforms in the transformer are symmetrical, only one-half of the waveform is
considered for the analysis.
Figure 4.15: Simplified Circuit Diagram of Figure 4.13
Figure 4.16: Simplified Circuit Diagram of Figure 4.14
122
where LDAB is the HFT leakage inductance, and CLVDC is the capacitor placed at the
LVDC-link, both elements act as energy storage.
From Figure 4.15 and Figure 4.16, Kirchhoff’s voltage and current laws are applied
to derive the mathematical equations of each circuit parameters as follows:
−𝑉𝐷𝐴𝐵1_𝐴𝐶
n𝐻𝐹𝑇 + 𝐿𝐷𝐴𝐵
′′ 𝑑
𝑑𝑡 (𝐼𝐷𝐴𝐵2) + 𝑅𝐷𝐴𝐵
′′ 𝐼𝐷𝐴𝐵2 − 𝑉𝐿𝑉𝐷𝐶 = 0 (4.46)
𝐶𝐿𝑉𝐷𝐶𝑑
𝑑𝑡(𝑉𝐿𝑉𝐷𝐶) +
𝑉𝐿𝑉𝐷𝐶
R𝐿2 + 𝐼𝐷𝐴𝐵2 = 0 (4.47)
−𝑉𝐷𝐴𝐵1_𝐴𝐶
n𝐻𝐹𝑇 + 𝐿𝐷𝐴𝐵
′′ 𝑑
𝑑𝑡 (𝐼𝐷𝐴𝐵2) + 𝑅𝐷𝐴𝐵
′′ 𝐼𝐷𝐴𝐵2 + 𝑉𝐿𝑉𝐷𝐶 = 0 (4.48)
𝐶𝐿𝑉𝐷𝐶𝑑
𝑑𝑡(𝑉𝐿𝑉𝐷𝐶) +
𝑉𝐿𝑉𝐷𝐶
R𝐿2 − 𝐼𝐷𝐴𝐵2 = 0 (4.49)
The state-space variables for the current IDAB2 flowing through the inductance LDAB
and the capacitor voltage VLVDC over CLVDC are expressed as:
𝑑
𝑑𝑡𝑥 = 𝐀1𝑥 + 𝐁1𝑢 ⇔ d
dt [𝐼𝐿𝑉𝐷𝐶𝑉𝐿𝑉𝐷𝐶
] =
[
−𝑅𝐷𝐴𝐵
′′
𝐿𝐷𝐴𝐵′′
1
𝐿𝐷𝐴𝐵′′
−1
𝐶𝐿𝑉𝐷𝐶 −
1𝑅𝐿2𝐶𝐿𝑉𝐷𝐶]
[𝐼𝐿𝑉𝐷𝐶𝑉𝐿𝑉𝐷𝐶
] + [
1
n𝐻𝐹𝑇𝐿𝐷𝐴𝐵′′
0]𝑉𝐷𝐴𝐵1_𝐴𝐶
(4.50)
𝑑
𝑑𝑡𝑥 = 𝐀2𝑥 + 𝐁2𝑢 ⇔ d
dt [𝐼𝐿𝑉𝐷𝐶𝑉𝐿𝑉𝐷𝐶
] =
[ −
𝑅𝐷𝐴𝐵′′
𝐿𝐷𝐴𝐵′′
− 1
𝐿𝐷𝐴𝐵′′
1𝐶𝐿𝑉𝐷𝐶
−1
𝑅𝐿2𝐶𝐿𝑉𝐷𝐶]
[𝐼𝐿𝑉𝐷𝐶𝑉𝐿𝑉𝐷𝐶
] + [
1
n𝐻𝐹𝑇𝐿𝐷𝐴𝐵′′
0]𝑉𝐷𝐴𝐵1_𝐴𝐶
(4.51)
Equations (4.50) and (4.51) are the state-space equation for Figures 4.15 and 4.16,
respectively. The small-signal model for the DAB converter can be derived by substituting
these two equations in the general formula given by [293] as:
𝑠 = 𝐴 + 𝐵 + (𝐴1 – 𝐴2) 𝑋 + (𝐵1 – 𝐵2 )𝑈 (4.52)
where is the small AC variation of the state-space variables, is the small AC
variation of the independent variables, X is the quiescent value of the state-space variables,
U is the quiescent value of the independent variables, 𝑑 is the small AC variation of the
duty cycle. Also, by simplifying Equations (4.50) and (4.51), a matrix is utilised to
formulate A1, A2, B1, and B2 to be substituted in Equation (4.52) as follows [293]:
123
𝐴 = D𝐷𝐴𝐵A1 + (1 − D𝐷𝐴𝐵) A2 ⇔ 𝐴 =
[
−𝑅𝐷𝐴𝐵
′′
𝐿𝐷𝐴𝐵′′
2𝐷𝐷𝐴𝐵−1
𝐿𝐷𝐴𝐵′′
−2𝐷𝐷𝐴𝐵+1
𝐶𝐿𝑉𝐷𝐶 −
1𝑅𝐿2𝐶𝐿𝑉𝐷𝐶]
(4.53)
𝐵 = D𝐷𝐴𝐵B1 + (1 − D𝐷𝐴𝐵) B2 ⇔ 𝐵 = [
1
n𝐻𝐹𝑇𝐿𝐷𝐴𝐵′′
0] (4.54)
where DDAB is the quiescent value of the duty cycle. The small-signal model for the
DAB operating as a buck converter can be derived from Equations (4.50-4.54) which
results in:
𝑆 [𝑖𝐿𝑉𝐷𝐶
𝐿𝑉𝐷𝐶] =
[
−𝑅𝐷𝐴𝐵
′′
𝐿𝐷𝐴𝐵′′
2𝐷𝐷𝐴𝐵−1
𝐿𝐷𝐴𝐵′′
−2𝐷𝐷𝐴𝐵+1
𝐶𝐿𝑉𝐷𝐶 −
1𝑅𝐿2𝐶𝐿𝑉𝐷𝐶]
[𝑖𝐿𝑉𝐷𝐶
𝐿𝑉𝐷𝐶] + [
1
n𝐻𝐹𝑇𝐿𝐷𝐴𝐵′′
0] 𝐷𝐴𝐵1_𝐴𝐶 +
[ 2V𝐿𝑉𝐷𝐶
𝐿𝐷𝐴𝐵′′
−2I𝐿𝑉𝐷𝐶𝐶𝐿𝑉𝐷𝐶 ]
𝑑𝐷𝐴𝐵 (4.55)
For deriving the transfer functions, Equation (4.55) expressed by line-by-line
equations yields:
𝑆𝑖𝐿𝑉𝐷𝐶 = −𝑅𝐷𝐴𝐵
′′
𝐿𝐷𝐴𝐵′′
𝑖𝐿𝑉𝐷𝐶 + 2𝐷𝐷𝐴𝐵−1
𝐿𝐷𝐴𝐵′′
𝐿𝑉𝐷𝐶 + 1
n𝐻𝐹𝑇𝐿𝐷𝐴𝐵′′
𝐷𝐴𝐵1_𝐴𝐶 + 2V𝐿𝑉𝐷𝐶
𝐿𝐷𝐴𝐵′′
𝑑𝐷𝐴𝐵 (4.56)
𝑆𝐿𝑉𝐷𝐶 = −2𝐷𝐷𝐴𝐵+1
𝐶𝐿𝑉𝐷𝐶 𝑖𝐿𝑉𝐷𝐶 −
1𝑅𝐿2𝐶𝐿𝑉𝐷𝐶
𝐿𝑉𝐷𝐶 − 2I𝐿𝑉𝐷𝐶𝐶𝐿𝑉𝐷𝐶
𝑑𝐷𝐴𝐵 (4.57)
Using Equations (4.59) and (4.57), the two transfer functions required to tune the
PI compensators of the DAB controller are as follows:
G𝐼𝑑−𝐷𝐴𝐵 = 𝐿𝑉𝐷𝐶
𝐷𝐴𝐵=
2V𝐿𝑉𝐷𝐶
(s𝐿𝐷𝐴𝐵′′ +𝑅𝐷𝐴𝐵
′′ )=
2V𝐿𝑉𝐷𝐶
n𝐻𝐹𝑇−2 (sL𝐷𝐴𝐵+R𝐷𝐴𝐵)
(4.57)
G𝑉𝐼−𝐷𝐴𝐵 = 𝐿𝑉𝐷𝐶
𝑖𝐿𝑉𝐷𝐶=
R𝐿2(−2𝐷𝐷𝐴𝐵+1)
(sR𝐿2∗C𝐿𝑉𝐷𝐶)+1 (4.57)
where G𝐼𝑑−𝐷𝐴𝐵 is the transfer functions of the control-to-output-current, with the
condition: 𝐿𝑉𝐷𝐶= 𝐷𝐴𝐵1_𝐴𝐶 = 0
and G𝑉𝐼−𝐷𝐴𝐵 is the transfer function of the output-current-to-LVDC-link-voltage,
with the condition: 𝑑𝐷𝐴𝐵=𝐷𝐴𝐵1_𝐴𝐶 = 0
124
There are different modulation techniques for the DAB presented in the literature,
where each of these techniques has a certain operating range of input voltage, output
voltage, and load in which the DAB converter results in the lowest losses. As the DAB
MVDC-LVDC conversion stage expects to receive a constant input voltage from the
MVAC-LVDC CHB rectification stage via the MVDC-link, each of the DAB modules is
expected to deliver a constant output voltage at the LVDC-link. This results in the DAB
operating at a constant input-output voltage ratio. The load of the DAB, which is in this
research study the EV battery, is the only operating parameter that changes depending on
the specifications of charging voltage and the C-rate at which the EV battery is being
charged. The three main modulation techniques applicable for the DAB converter
mentioned in [306-308] are the followings:
• Phase Shift (Rectangular) Modulation:
This modulation technique works by switching the primary and the secondary side
at a fixed duty cycle of 50%. Then, the angle between the primary and secondary switching
waveforms is adjusted to control the power transfer between both sides.
• Trapezoidal Modulation:
This technique includes a blanking time added to the primary switching voltage to
reduce the turn-off switching losses. This approach causes half the number of switches
(four switches) to switch off under zero-voltage conditions. Nevertheless, a higher RMS
current is required for adding this blanking time in order to transfer the same amount of
power, which leads to reduced efficiency in the DAB, due to higher conduction losses
across the switches [306-308].
• Triangular Modulation:
This technique is a special case of trapezoidal modulation, which utilises the phase
shift or blanking time to cause one edge of the switching voltage at the primary to overlap
with the secondary switching voltage. This results in a triangular current, with two switches
only turning off under non-zero-voltage conditions. While this technique allows for further
reduction of the turn-off losses, the larger current peak increases the conduction losses
[306-308].
125
Table 4.1 briefly compares the main advantages and disadvantages of these
modulation techniques. As can be seen from Table 4.1, the advantages of the phase shift
rectangular modulation technique outweigh the higher turn-off losses encountered by this
technique. Besides the simple implementation and lower RMS currents result in lower
component ratings, the phase shift rectangular modulation technique is selected for the
DAB converter control to achieve the highest power possible while sharing the losses
symmetrically on all switches of the DAB.
Table 4.1: Comparison of Modulation Techniques for the DAB Converter [306-308]
Modulation
Technique
Advantages Drawbacks
Phase Shift
(Rectangular)
• Simple algorithm
• Has the highest power transfer
possible compared to the other
two modulation techniques due to
the RMS circuit current which are
the lowest.
• Symmetrical share of the losses
on all switches
• ZVS during turn-on of the
switches
• Requires eight commutations.
• Negative current on the DC side reduces
power transfer, this results in lower
efficiency.
• High losses at low power levels are
caused by reactive power when no active
power is transferred.
• Turning off the switches occurs under
non-zero-voltage conditions, which yields
in switching losses.
Trapezoidal • Higher voltage range
• Lower switching losses
• Complicated algorithm.
• Higher conduction losses
• Unable to operate under no-load
conditions.
• Unsymmetrical losses if the primary
voltage differs from the secondary
voltage.
Triangular • Lowest switching losses
compared to the other two
techniques.
• Suitable when the primary and
secondary voltage ratios are
different from the HFT turns-ratio
• Complicated algorithm
• Switching losses occur in the same two
switches.
• Inefficient utilisation of the period for
power transfer.
• Highest RMS current compared to the
other two techniques.
126
Figure 4.17: Waveforms of DAB Operation with the Rectangular Phase Shift Modulation Technique
4.4 EV Battery Controller
Since the DAB converter interfaces directly with the EV battery to provide charging
voltage and current as predefined by the EV’s BMS, there are three control techniques that
this DAB can deliver charging power to the EV battery, namely: Constant Current (CC),
Constant Voltage (CV), and Constant Current Constant Voltage (CCCV). Since the CC
and CV techniques require the charger to supply a current/voltage level as specified by the
BMS throughout the charging process with protection against overvoltage or overcurrent
for the EV battery, the most viable solution for this application is to implement the CCCV
approach. Besides allowing for overvoltage and overcurrent protection, the CCCV process
is achieved by employing CC charging during the initial charging phase to protect against
overcurrent, especially in typical ultra-fast charging cases where a large amount of
charging current is required. Until the EV battery’s SoC reaches a predefined level,
normally 80% or 90% maximum, it switches to CV charging to protect the EV battery
against overvoltage. This process also allows the charging current to decrease
exponentially [309]. Figure 4.18 shows the typical current and voltage profiles for the
charging process with the CCCV control.
127
Figure 4.18: Waveforms of the Charging Profiles using CCCV Method for the EV Battery
Another ultra-fast charging technique proposed by [310] used to increase the charge
acceptance and provide a more accurate SOC estimation, the EV battery can also be
charged with current pulses that can be negative discharging and/or with variable frequency
However, since this research area is still not confirmed whether this pulse charging is
actually beneficial for EV batteries, thus, it is not adopted in this thesis.
The CCCV technique is implemented in the controller of the DAB which aims to
provide a constant output current and provide a constant output voltage as requested by the
BMS of the EV battery, while also allowing a seamless transition between CC mode and
CV mode as requested by the BMS of the EV battery. This controller is assumed to be
insensitive to other variables of the EV battery which is satisfied by assuming the LVDC
voltage as the output voltage for the DAB is relatively constant at all times during operation
under normal grid conditions. This controller utilises a cascaded control structure where
the inner-current-loop and outer-voltage-loop for controlling the charging current and
charging voltage, respectively. This structure is explained in detail in section 4.3.
In practice, the purpose of the voltage control in the CCCV charging process is to
hold the output voltage constant immediately before the mode transition; therefore, it is not
necessary to move to another voltage set-point. In MATLAB/Simulink, this can be simply
128
achieved by adding an SHBs to each of the controllers of the DAB modules, which is also
initiated by the mode switching signal. It should be noted that employing a feed-forward
technique could improve the performance of CCCV controller hardware, by alleviating the
stress on the voltage controller. In addition, the feed-forward component term is a constant
input DC bias, need not be considered in the design process because it does not affect the
performance of the PI compensators of the controller and, which is another big advantage
of this mechanism.
4.5 Summary
This chapter described in detail the control strategies and modulation techniques
that were implemented for the proposed SST for the UFCSEV system. For both the CHB
rectification stage and DAB conversion stage, closed-loop feedback controllers are
employed based on the current-mode scheme which has an inner-current-loop and an outer-
voltage-loop.
Voltage balancing schemes for the CHB rectifier were implemented in order to
balance the voltages across the capacitors of each CHB cell in the MVDC-link side. This
scheme prevents any uneven DC voltages in the CHB in this controller. Most importantly
voltage balances for the three phases of the multi-cell CHB are implemented by taking into
account the phase angle difference between phases A, B, and C using the phase angle signal
data from PLL block, which is utilised for grid monitoring. This balancing scheme is of
most importance to ensure an evenly distributed power among all the CHB cells while
preventing any possible damage to the power circuit components caused by voltage
unbalance. Phase shift PWM based on sinusoidal, and triangle carrier signals are selected
for switching the power MOSFETs while also considering the number of CHB cells within
a single phase.
For the DAB MVDC-LVDC conversion stage, each DAB module is controlled by
adjusting the duty cycle calculated from the predefined reference values of the output
129
voltage and current at the LVDC-link, which can be monitored by the BMS of the EV
battery to specify the required charging voltage level and current rate. The CCCV charging
protocol is employed in this control scheme by assuming the MVDC-link voltages as the
input of the DAB constant during the whole operation and the turns-ratio of the HFT is also
assumed constant. The rectangular phase shift modulation technique was implemented for
the DAB converter in order to ensure ZVC during the turn-on period of the power
MOSFETs.
Dynamic averaged modelling with small-signal and state-space averaging were
derived in order to derive the open-loop and closed-loop transfer functions. This approach
is implemented to determine the PI compensator gains of the controllers of the MVAC-
MVDC CHB cells as well as the MVDC-LVDC DAB modules.
130
Chapter.5 Results and Analysis
This chapter presents the parameters’ values of the power circuits components of
the SST system. Further analysis on the parameters’ selections based on standardised sizes
as well as rough cost estimations of the power components is also delineated based on off-
the-shelf power components.
Simulation results of the voltages, currents, and powers of the UFCSEV system in
an ideal grid condition are also presented. Various disturbances in the MVAC grid side are
implemented to investigate the SST behaviour as well using MIL real-time simulation.
5.1 Design Parameters of the SST System and Cost Estimations
5.1.1 UFCSEV System Specifications
As specified in the first section of Chapter 3, the specifications of the ultra-fast
charging system for the design of the SST-based high power conversion system are
summarised in Table 5.1 below.
Table 5.1: UFCSEV System Specifications
Parameter Name Symbol Value
Rated Charging Power Pcharging_rated 1.5 MW
MVAC Grid Voltage (Line-Line_RMS) VMVAC_LL 27.6 kV
Nominal Grid Frequency fg 60 Hz
Maximum DC Charging Voltage VDC_charging-max 1000 V
131
5.1.2 CHB Parameters
The power switching devices available in the market as discrete components have
blocking voltage ratings of 600, 750, 1200, 1700, and 3300 V based on IGBT and MOSFET
switching devices with anti-parallel diodes. Since selecting a large number of H-Bridge
cells increases the control complexity and total cost of the CHB rectifier, a low number of
cells is desired. The chosen values of the number of H-Bridge cells and the voltage range
of the MVDC-link are highlighted in Table 5.5 below.
Table 5.2: Switching Devices’ Ratings, Number of CHB Cells, and MVDC Voltages
Rated
Voltage
(Vswitch-rated)
Number of
CHB Cells per
Phase (NCHB)
Minimum Voltage at
the MVDC-Link
(VMVDC-min)
Maximum Voltage
at the MVDC-Link
(VMVDC-max)
600 V 52 456.18 V 457.14 V
750 V 42 564.79 V 571.43 V
1200 V 26 912.36 V 914.29 V
1700 V 19 1248.49 V 1295.24 V
3300 V 10 2372.14 V 2514.29 V
Since 3300 V of blocking voltage results in the lowest number of CHB cells to
interface with the 27.6 kV MVAC grid, the type of switching device selected is SiC-based
MOSFET with the capability to handle an MV voltage level of up to 3300 V. Several
manufacturers of semiconductor power devices, such as GeneSiC, Wolfspeed, Mitsubishi
and Hitachi, ROHM, which have demonstrated their capability to fabricate, and package
SiC power MOSFETs for targeted application in the MV voltage range. However,
challenges still complicate their commercialisation, due to the factors regarding technology
maturity level, device and packaging availability, and potential issues such as EMI. At the
132
time of writing this thesis, the 3300V SiC MOSFET device availability and procurement
of the devices are limited to engineering samples. While still many of the 3300 V and
higher blocking voltage levels of SiC MOSFET under development, for this research study,
3300 V SiC-based MOSFETs (G2R120MT33J for the CHB cells and G2R50MT33-CAL
for the DAB modules) which have been very recently commercialised in the market as a
discrete component are selected for the main switches of the proposed SST system. Based
on the datasheets given in [311, 312], this MOSFET can be implemented for applications
such as MV-grid-connected EV ultra-fast chargers, which also justifies this selection.
Moreover, the final value of the MVDC-link voltage is selected from Table 5.4
below. The final values of the CHB converter’s power circuit parameters are calculated
using Equations (3.6 – 3.20) are presented below in Table 5.2. The values of the L-filter
inductor and switching frequency are determined using the optimisation process described
in the flowchart in Appendix C. The selection of the switching frequency, fCHB, is based on
the findings reported in [282] from the figure of efficiency versus power density for the
two-stage converter module with an AC-DC H-bridge module connected to a DC-DC DAB
converter for various switching frequencies. Since a lower switching frequency
corresponds to a higher efficiency, 10 kHz is selected in this case study as the switching
frequency for the CHB for improved efficiency. Moreover, this selection is also justified
based on the proportional relationship between the switching losses and switching
frequency. In addition to higher efficiency consideration, such that the switching losses are
minimised by selecting a lower value of switching frequency, THD mitigation is also taken
into consideration, and thus the final selection of the filter inductance value, LCHB, is based
on the lowest attainable THD from simulation and FFT analysis.
133
Table 5.3: CHB Parameters and Values
Parameter Name Symbol Value
Number of CHB Cells per
Phase
NCHB 10
Voltage at MVDC-Link VMVDC-link 2500 V
L-Filter Inductance LCHB 1.27 mH
C-Filter Capacitance ** CCHB 212.2 μF
Switching Frequency fCHB 10 kHz
** minimum value
For the C-filter capacitor of the CHB from the calculation shown in Table 5.3, the
nearest standard value is 220 μF is selected.
5.1.3 DAB Parameters
The calculated values of the DAB converter parameters are presented below in
Table 5.4. Assuming that the power is distributed equally amongst all the DAB modules,
the rated power of each module is calculated using Equation (3.25). The turns ratio of the
HFT is selected by choosing the minimum values of both the nominator and denominator
of Equation (3.24). The maximum leakage inductance of the HFT is computed according
to Equation (3.28). The required capacitances of the C-filters of the DAB are calculated
using Equation (3.34) and Equation (3.36). The calculated value of the 𝐶𝐷𝐴𝐵1 is 20 μF.
𝐶MVDC-Link = 𝐶𝐶𝐻𝐵 + 𝐶𝐷𝐴𝐵1 = 220 +20 = 240 μF, however, the standardised off-the-shelf
capacitor value selected is 3300 μF following the optimisation process of this capacitor
value as shown in Appendix B ensuing the ripple of the MVDC-link voltage is below 5%
based on the simulation. The same approach applied for the capacitor across the LVDC-
134
link, which is selected as off-the-shelf standard value of 2200 μF following the optimisation
process to ensure less than 5% ripple as demonstrated in Appendix D. These capacitor’s
values have been optimised to obtain smooth voltage waveforms with low ripples.
The selection of the leakage inductance is based on the simulation of the current
flowing through the HFT while ensuring ZCS. Moreover, the selection of the switching
frequency of the DAB is based on the findings reported in [69] which compared three
different values of 20 kHz, 50 kHz and 100 kHz and the estimated the efficiency of the
DAB is 98.52%, 97.93% and 96.12% respectively. As there is a proportional relationship
between the switching losses and switching frequency, the lowest possible value of 20 kHz
is selected aiming for higher efficiency.
Table 5.4: DAB Parameters and Values
Parameter Name Symbol Value
Number of Modules NDAB 10
Rated Power of each DAB module PDAB-module 50 kW
HFT turns-ratio nHFT 5:2
Voltage at DC-Link VMVDC 2500 V
Output Voltage VLVDC 1000 V
Leakage Inductance * LDAB 625 μH
C-Filter Capacitance on the MVDC-link
side**
CMVDC 240 μF
C-Filter Capacitance on the LVDC-Link
side **
CLVDC 125 μF
Switching Frequency fDAB 20 kHz
* maximum value
** minimum value
135
According to Equation (3.42) and the ranges of MVDC-link voltages (VMVDC-min
and VMVDC-max) calculated in Table 5.2, Table 5.5 shows the minimum value of G for the
given range of VMVDC while setting VLVDC constant as it is the maximum DC-charging
voltage for the EV battery. The value of 2500 V puts VMVDC in the middle of its extremes.
The associated value of 2:5 for the nHFT with VLVDC = 1000 V is selected.
Table 5.5: DC-Link Voltages and Turns-Ratios of HFT
VMVDC VLVDC G nHFT
2380 1000 23800 238/100
2400 1000 60 12/5
2420 1000 6050 121/50
2440 1000 1525 61/25
2460 1000 6150 123/50
2480 1000 1550 62/25
2500 1000 10 5/2
136
5.1.4 Cost Estimation of Power Circuit Devices and Components of the SST
System
Table 5.6 below shows an estimation of the costs of the SST power circuit
components and devices, taking into account as of today’s maximum cost
approximation as well as availability to purchase from suppliers in Canada for to
be bought online from widely known e-commerce websites for power electronics.
With the current research and development advancements, the MV SiC
MOSFETs and MV capacitors would reduce in the next couple of years.
Table 5.6: Cost Estimates of Power Circuit Devices and Components
Device or
Component
Required
Quantity
Cost per One
Item in USD
Subtotal References
3300 V SiC MOSFET 360 $100 $36,000 [311 - 313]
HFT 30 $15 $450 [314]
3300 μF Capacitors 30 $300 $9,000 [315]
2200 μF Capacitors 30 $200 $6,000 [315]
5.6 μH Inductors 30 $20 $600 [316]
1.27 mH Inductors 3 $40 $120 [316]
Total Cost $52,170.00
Compared to the conventional fast charging systems that include a traditional LFT
which costs approximately $60,000 alone, along with the off-board or pantograph DC-fast
charger’s power circuit component that could cost at least $128,000 for 350 kW of power
only as reported in [96], it is believed that the proposed SST system could reduce the capital
cost of the UFCSEV power circuit components by at least 60%. By also considering the
efficiency, modularity, control capability as well as high power density for an MW range
of charging power, the SST is comparatively very cost-effective.
137
5.2 Performance Evaluation of the UFCSEV under Various Scenarios
Figure 5.1: Voltage and Current Waveforms of the three-phase MVAC Grid at rated Charging
Power and Ideal Grid Condition
Figure 5.1 above represents the three-phase voltage and current waveforms of the
MVAC grid as the input voltage and current to the SST system at the rated charging power
of 1.5 MW, where the phase voltages VA, VB, and VC and their phase voltage amplitude
equals: VA = 𝑉𝑚 cos(𝜔0𝑡), VB = 𝑉𝑚𝑐𝑜𝑠 [𝜔0𝑡 − 2𝜋/3 ] and VC = 𝑉𝑚 𝑐𝑜𝑠 [𝜔0𝑡 − 4𝜋/3 ],
where 𝑉m = 𝑉MVAC-LL x √2 / √3 where 𝑉MVAC-LL is the nominal line-to-line phase voltage
root-mean-square (RMS) value which equals to 27.6 kV and 𝑉𝑚 is the phase-to-neutral
voltage amplitude which equals to 22.5353 kV. The waveforms of the active and reactive
power that is delivered from the MVAC grid to the SST at rated charging power are shown
in Figure 5.2 below. After running the simulation at 0 second, the input active power of the
grid reached the required 1.5 MW rated value following the command of the controller in
about 0.016 second as the transient response to the steady-state value. This is accomplished
by adjusting the values of the predefined references of the Vd*, Id*, Vq* and Iq* of the abc-
138
dq0 transformation in the PLL control system. While the reactive power is set to 0 in this
case study, the simulation shows very small variations in a fraction of less than 10-11. Since
this is very small, it is neglected and thus assumed as 0 VAR.
Figure 5.2: SST Input Active and Reactive Power Waveforms at Rated Charging Power and Ideal
Grid Condition
The THD is analysed using the Fast Fourier Transform function on
MATLAB/Simulink. The waveforms and their respective THD of the input MVAC grid
current as well as the VCHB are shown in Figures 5.3 and 5.4 below. The analysis shows a
THD of 2.45% for the input current considering the high switching frequency of 10 kHz
selected for the CHB rectifier cells. This is within the recommended IEEE standards for
harmonics above 35th order. The THD for the VCHB is 5.95%. This is comparatively higher
than aimed for due to voltage sparks in the first positive cycle of the waveform period
which occurs due to the grid filter since the inductor resists the change by producing a
voltage between its leads in opposing polarity to the change. If considering the other cycles
after the first half, the THD is below 1%.
139
As can be seen from the sinusoidal waveforms, the input voltage and current
waveforms to the SST are in phase, which corresponds to a unity power factor as only
active power is being drawn from the MVAC grid to the UFCSEV.
Figure 5.3: Harmonics Distortion of Input Current to the SST
140
Figure 5.4: Harmonics Distortion of Input Voltage to the SST
141
The output voltage and current of each CHB cell are shown in Figure 5.5 below.
As can be seen, the controller for the CHB rectifier successfully regulated the MVDC-
link at 2500 V with a ripple of less than 5% as set in the first-order design.
The output current corresponds to the voltage of the CHB for an output power of
50 kW per cell totalling an output power delivered to the DAB converter of 1.5 MW.
Figure 5.5: MVDC-Link Voltage (Top) and Output Current (Bottom) of each CHB Cell at the rated
Charging Power
142
The output voltage and current of the DAB converter to the EV battery are shown
in Figure 5.6 below. As can be seen, the controller for the DAB converter successfully
regulated the LVDC-link at 1000 V of smooth charging voltage with a ripple of less than
10% as set in the first order design.
The total output current of the DAB modules connected in parallel amounts to 1.5
kA for a total charging power of 1.5 MW being delivered to the EV battery.
Figure 5.6: Output Current and Voltage of the DAB Converter to the EV Battery at the rated
Charging Power
The primary and secondary voltage waveforms of the HFT are shown in Figure
5.7.
To further investigate the dynamic performance of the proposed SST, disturbances
conditions at the grid between 0.2 and 0.5s are applied and the resultant waveforms are
shown in Figures 5.8 – 5.11.
143
Figure 5.7: Waveforms of HFT Primary and Secondary Voltage in Ideal Grid Condition at the rated
Charging Power
Figure 5.8: Waveforms of the Input Voltage and Current from the MVAC to the SST with
disturbances conditions at the grid between 0.2 and 0.5 s
144
Figure 5.9: Comparison of the Grid Frequency Measurements using the proposed PPL versus the
built-in MATLAB PLL
145
Figure 5.10: The dq components of the MVAC grid affecting the CHB controller during the
disturbances between 0.2 and 0.5 s
146
Figure 5.11: The MVAC Grid Voltage LL RMS measurement from the proposed PLL showing the
affected disturbances between 0.2 and 0.5 s
To further validate the proposed PLL compared to the built-in PLL on
MATLAB/Simulink, the following simulation waveforms (shown in Figures 5.12 – 14)
imply the accuracy of the proposed PLL and is therefore utilised for the proposed SST.
Figure 5.12: The MVAC Grid Voltage LL RMS measurement from the proposed PLL during ideal
grid conditions
147
Figure 5.13: Phase angles’ measurements of the MVAC grid voltages during ideal grid condition
using the proposed PLL
148
Figure 5.14: Simulation Results of the MVAC – 3 Phase with LLLG Fault Analysis
a) Voltages b) Currents c) Grid Frequency using the built-in MATLAB PLL
149
Figure 5.15 below shows the developed model of the proposed SST-based
UFCSEV including the power circuits and control systems as well as the EV battery.
Figure 5.15: Overall Simulation Model of the SST-based UFCSEV
The pulsing signals applied to the gates of each MOSFET device of both the CHB
cells and DAB modules from the duty cycle generated by the controllers are shown in
Figure 5.16-5.17 below. The characteristics of the battery model is shown in Figure 5.18.
Figure 5.16: Pulsing signals for the CHB MOSFETs:
Top: Switches 1&4 Bottom: Switches 2&3
150
Figure 5.17: Pulsing signals for DAB MOSFETS using Phase-Shift Modulation:
a) Switches 1&4 b) Switches 2&3
c) Switches 5&8 d) Switches 6&7
Figure 5.18: Li-ion Battery Characteristics for the EV Battery Model used on MATLAB/Simulink
151
Using the Powerful 564 kWh of on-board LFSe+ EB [83] with modular battery
capacity value for the EV battery model to simulate the UFCSEV proposed in this thesis,
the following figures show the EV battery’s SoC and energy by applying the rated charging
power 1.5 MW of SST. In this scenario, the minimum SoC and maximum SoC values are
controlled within 20% and 90% respectively, in order to prevent degradation of the EV
battery while being charged. As can be seen from Figure 5.18, charging at the SST’s rated
charging power of 1.5 MW, takes approximately 13 minutes and 32 seconds to go from
30% SoC to 90% SoC of the 564 kWh EB capacity. This is considered much faster charging
rate compared to a conventional DC-fast charging station, due to a much higher power.
Figure 5.19: EV’s Charging Profile with SoC limits
The time-domain dynamic analysis using the phasor modelling technique derived and
implemented in this case was adopted from [232] which is able to simulate the UFCEV
system on MATLAB/Simulink/ RT-LAB much faster for a timescale of several minutes.
152
5.3 Efficiency Analysis
Since the system-level simulation-based model designed in this thesis assumed that
the power circuit devices, i.e. SiC MOSFETs are lossless, the efficiency of the SST
depends primarily on the efficiency of the semiconductor switching devices selected.
To analyse the efficiency of the MOSFET selected, both conduction losses and
switching losses are taken into account and their calculations are illustrated below.
5.3.1 Conduction Losses
In general, the characteristic of VDS versus IDS (or, for the anti-parallel diodes, VF
versus IF) of bipolar power semiconductors can be approximated by the linear model shown
in Figure 5.20 below as:
VDS (IDS) = VDS,0 + r · IDS where Vsw,0 = VDS,0 (5.1)
Figure 5.20: Forward Characteristic Approximation of a MOSFET (or Diode)
by Vsw,0 and r
153
The total forward voltage drop at rated current flowing through the semiconductor
switch, VDS (Irated); therefore, consists of the two partsVDS,0 and VDS,r = r · Irated.
Employing the fundamental concepts of semiconductor physics in [293], the total
forward voltage drops at rated current, the VDS,0 and VDS,r scale with the blocking voltage
(VMosfet-rated) can be estimated roughly by: VDS (IDS-rated) = VDS,0 + r · IDS-rated
Since the current flowing into one of the H-Bridges equals the phase current flows
through two MOSFETs per cell at any instant in time. The first step to calculate the
conduction loss is to assume here that the characteristics of MOSFETs and diodes are the
same. For each phase stack-based on the MOSFET with a blocking voltage of 3300 V, the
total conduction losses at the rated current, Irated, can be calculated as follows [259]:
Pconduction_loss = 2 · (VDS,0 · I𝑀𝑉𝐴𝐶−𝑝ℎ−𝑎𝑣𝑒 + r · I2MVAC-ph-RMS) (5.2)
By substituting the values from Equations (3.8) and (3.9), Pph = 500 kW,
I𝑀𝑉𝐴𝐶−𝑝ℎ = 14.7916 𝐴 , I𝑀𝑉𝐴𝐶−𝑝ℎ−𝑅𝑀𝑆 = 10.45924 A and I𝑀𝑉𝐴𝐶−𝑝ℎ−𝑎𝑣𝑒 =
9.416625 A , and from the datasheets [5.1, 5.2]: VDS,0 =3.5 V and r = 120 m Ω at an
operating temperature of T = 25°C, into Equation (5.2), the conduction loss for per H-
Bridge per phase = 92.17134 W.
Since there is one H-Bridge per CHB cell and two H-Bridges per DAB module, the
total conduction losses for the three-phase with 10 cells and 10 modules system = 3 x 10 x
3 x 92.17134 W = 8,295.42 W.
Since the number of cells is inversely proportional with the rated blocking voltage
of the MOSFET, the reduction of the forward voltage drop with the blocking voltage is not
very significant; therefore, high conduction losses must be expected for designs based on
lower blocking voltages.
154
5.3.2 Switching Losses
The switching losses depend on the blocking voltage with low complexity and can
be expressed by the switching energies of the MOSFET/diode which are approximated by
considering the blocking voltage utilisation, u = VMVDC/ VMosfet-rated to scale linearly with
the switched current and with the applied DC voltage. Then, using a normalised switching
energy, Ksw = Esw / Irated for u which is typically specified in the datasheet, and with [Ksw]
= mJ/A, the switching losses of a specific MOSFET can be expressed by considering the
switching energy of a certain transition which can be determined from Ksw as
Esw = Ksw · Isw · u / 0.5 with [Esw] = mJ (5.3)
Since each bridge leg in a CHB cell is operated at a fixed switching frequency, fCHB
of 10 kHz, where the ratio between switching frequency and the fundamental frequency is
quite high for normal PWM operation, and since there is a linear dependency between
switched current and resulting switching energies is assumed from Equation (5.3), the turn-
off losses during half a grid period can be estimated based on the bridge leg’s average
current, I𝑀𝑉𝐴𝐶−𝑝ℎ−𝑎𝑣𝑒 , as [259]:
Poff,leg = Koff · 1
1000000I𝑀𝑉𝐴𝐶−𝑝ℎ−𝑎𝑣𝑒 (
𝑢
0.5) · fCHB (5.4)
where the factor 1/1000000 is required to compensate for the μJ/A unit of Koff. Each
of the three switching energies is dissipated once per H-bridge leg during one switching
cycle (although not in the same device). The overall switching losses of an H-bridge cell
of the CHB based on MOSFETs with a blocking voltage 3300 V, can therefore be
calculated from:
Psw_CHB = 2 x Ksw · 1
1000000I𝑀𝑉𝐴𝐶−𝑝ℎ−𝑎𝑣𝑒 (
𝑢
0.5) · fCHB (5.5)
where Ksw = Koff + Kon and from the datasheet: Esw_CHB = Eoff + Eon = (501 +168)
μJ , the switching losses of an H-bridge cell of the CHB = 20.2727 W and for all CHB cells
in the three-phases: the total CHB switching losses = 3 x 10 x 190.9 = 608.1818 W
155
Similarly, using Esw_DAB = Eoff + Eon = (687+304) μJ, the switching losses of an H-bridge
module of the DAB can be calculated from:
Psw_DAB = 2 x Ksw · 1
1000000I𝑀𝑉𝐷𝐶−𝑎𝑣𝑒 (
𝑢
0.5) · fDAB (5.5)
For the DC-AC H-bridge of the DAB, the switching losses = 60.0606 W.
For the DC-AC H-bridge of the DAB, the switching losses = 24.0242 W.
The total switching losses of the DAB = 3 x 10 (84.08484) = 2522.54527 W.
It can be noted that the switching frequency is inversely proportional with V3Mosfet-
rated, which indicates that the high switching losses occur for designs utilising
semiconductor switching devices with high blocking voltage ratings.
5.3.3 Overall Efficiency of the SST
The overall efficiency of the SST can be determined by the following equation:
𝜂 = P𝑜𝑢𝑡𝑝𝑢𝑡
P𝑖𝑛𝑝𝑢𝑡 % =
P𝑖𝑛𝑝𝑢𝑡 − P𝑡𝑜𝑡𝑎𝑙_𝑙𝑜𝑠𝑠𝑒𝑠
P𝑖𝑛𝑝𝑢𝑡 % (5.6)
The total losses of the SST considering the losses of the semiconductor switches only is:
P𝑡𝑜𝑡𝑎𝑙_𝑙𝑜𝑠𝑠𝑒𝑠 = P𝑐𝑜𝑛𝑑𝑢𝑐𝑡𝑖𝑜𝑛_𝑙𝑜𝑠𝑠𝑒𝑠 + P𝑠𝑤𝑖𝑡𝑐ℎ𝑖𝑛𝑔_𝑙𝑜𝑠𝑠𝑒𝑠 = 8,295.42 + (608.1818 +
2522.54527) = 11,426.147 W.
Since the input power into the SST system is the rated active charging power of 1.5 MW,
using Equation (5.6), the overall efficiency of the SST system is:
𝜂 = P𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔_𝑟𝑎𝑡𝑒𝑑 − P𝑡𝑜𝑡𝑎𝑙_𝑙𝑜𝑠𝑠𝑒𝑠
P𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔_𝑟𝑎𝑡𝑒𝑑% =
1500 𝑘𝑊 − 11.426147 𝑘𝑊
1500 𝑘𝑊 % = 99.2383 %
The overall system efficiency of the SST at 1.5 MW charging power is higher than
that of the LFT-based system by 7.738% (from 91.5% to 99.2383%) reducing the power
losses from 85 kW as reported in [96] to 11.426 kW in this SST System. As a result of this
efficiency yields a significant reduction in electricity costs and energy savings.
156
Chapter 6. Conclusions and Recommendations
6.1 Summary of Results
This research study aimed to design a realistic simulation-based model of an SST-
based high-power conversion for ultra-fast charging rated at 1.5 MW as a dedicated charger
for one connected EV with a large battery capacity, such as an EB or heavy-duty vehicle
without partial processing for multiple EVs. A two-stage DPSS ISOP configurational
topology is proposed with an MVAC-MVDC rectification stage using CHB cells followed
by an MVDC-LVDC conversion stage using DAB modules. A total of ten CHB cells in
each phase of the three-phase system is directly connected to a dedicated 27.6 kV
distribution feeder. The power circuit for the case study contained a total of 360 MOSFETs.
Based on the review analysis performed in this thesis, it is believed that the selected
converter topologies outperform all other topologies available today for multi-level
modular converter structure with a high level of modularity. The selected architecture,
converter topologies, and modulation schemes offer high flexibility and control
capabilities. The multi-level CHB rectifier is modulated using phase-shift PWM
modulation. Besides its modular structure, the CHB can handle higher voltages and it is
easy to implement voltage balancing control, reactive power compensation and THD
reduction. The DAB is modulated using the rectangular phase-shift modulation technique
with high efficiency during the EV charging operation. This topology operates smoothly at
a fixed voltage level at the MVDC- and LVDC-links with the phase shift modulation.
Mathematical models based on dynamic averaged modelling and state-space as well as
small-signal models are derived in order to construct the controllers of the SST system.
This technique is also utilised in order to reduce the computational time of simulations.
This thesis is divided into several chapters to concentrate on a certain part of the
research to meet the thesis objectives. A comprehensive review of literature on SST-based
ultra-fast charging and other related topics revealed the SST offers much better
performance with control capabilities than the conventional LFT. The SSTs are expected
to be widely implemented in various applications at MV and HV levels and power in the
MW ranges. Due to the recent advances in the integration of RESs and ESSs to the utility
157
networks, V2G will be a key role in a smart grid in the near future. This will liberate the
electricity market which would be more complex as a result. The SST has the potential to
play a key role in providing new ways for controlling electricity routing and also in adding
functionalities to the distribution systems such as smart protection against faults and
enhanced power quality through the injection of currents with very low harmonic contents.
To efficiently and rapidly manage the changing dynamic loads of ultra-fast
charging, the SST offers the most viable solution available today to dynamically adjust the
charging power and energy distribution in the power grid. The resulting power circuit
shows that the proposed SST system based on the CHB-DAB couple topology is extremely
modular. To interface with an increased voltage level on the MVAC grid side of the SST,
the number of CHB cells has to be simply increased by connecting new cells in series.
Both of the CHB and DAB converters are independently controlled based on the
current-mode control scheme with feedback signals such that the controllers keep the
converter parameter at the desired value constant. The voltage balancing scheme ensures
an equal voltage of the MVDC-link among all the CHB cells. The SST performance is
validated using real-time simulation results.
The SST model focused on time-domain detailed switching simulations for
voltages, currents, and power flowing within the UFCSEV and is successfully validated
using MIL real-time simulation on MATLAB/Simulink/RT-LAB. A secondary
study is performed to analyse the efficiency of the SST system based on the conduction
and switching losses at the MOSFET semiconductor switches selected in this study using
real data from the datasheets of the power MOSFETs.
The overall conclusion of this study can be summarised by confirming that the
proposed SST topological configuration with its controllers that are presented in this thesis
are capable of solving the challenges encountered in delivering high-power charging. Thus,
it is appealing for future implementation especially for EVs with large battery capacities
such as heavy-duty vehicles, where the focus is laid on system compactness due to the lack
of excessive filtering and LFTs, utilising the proposed ISOP CHB-DAB high-frequency
SST with integrated ESSs between at the MVDC-link without the need of additional high-
power chargers for partial processing that may result in an unbalanced system.
158
6.2 Contributions
The novelty of the proposed versatile topological configuration is the combination of
CHB and DAB without a third conversion stage which has not been utilised in three-phase
two-stage high-frequency DPSS SST architectures to the best knowledge of the author,
especially for ultra-fast charging applications with SiC MOSFETs. This modular design
features key advantages such as redundancy, easy scalability to higher voltage and power
levels, a very low charging current ripple, current and voltage control capability, soft
switching over a wide range of input and output voltage variations, bidirectional power
flow for ultra-fast charging of EVs with V2G and V4G capabilities. These features imply
evident offered advantages compared to the conventional power conversion concepts. A
framework of the UFCSEV model-based design with detailed steps for MIL real-time
simulation is also presented with step-by-step systematic approaches for the design
processes of both the CHB and DAB circuits and their controllers. Suitable controllers for
this SST are implemented to properly regulate the currents, voltages, and power flow from
the SST to the EV battery while taking into account the THD, PFC, power balance across
all modules and voltage ripple in accordance with IEEE standards considering high power
quality. Off-the-shelf components sizes as realistic values for the parameters utilising
datasheets of commercially available SiC MOSFETs and standard values of passive
components were selected in order to make the hardware design of the system proposed in
this study feasible and quick in implementation in practice. Approximate cost estimation
of the SST power circuit components is also shown. Efficiency analysis considering the
conduction and switching losses of the semiconductor MOSFET devices is also outlined.
6.3 Limitations
While this thesis proposed an SST topology and implemented the most appropriate
control schemes and modulations methods validated by real-time simulations, there are
certain aspects of the SST system which have not been covered in this research study due
to time restraints. The simulation results presented are for G2V charging application only.
Constructed on MATLAB/Simulink and integrated with RT-LAB, the developed model is
limited to the capabilities of these software tools. Furthermore, the efficiency analysis did
not cover the power losses in HFTs due to the varying values of the core hysteresis, core
eddy current, and winding losses of various products from various manufacturers.
159
6.4 Future Works and Recommendations
Even after the end of a thesis work, several new challenges, questions and
stimulating ideas arise. Indeed, several future research directions can be proposed. Towards
real-scale implementation, additional control schemes to achieve V2G and V4G for power
transfer in other quadrants should be developed. In order to achieve better performance of
this SST system, more advanced control such as MPC and Neural Network algorithms and
techniques with feed-forward loops should be developed. Proper protections schemes and
devices such as switchgear, circuit breakers and disconnects, or other smart protection
devices should be investigated, especially in ultra-fast charging applications. This is
because the controllers implemented for this SST system are not perfectly strong enough
to sustain short-circuit conditions or asymmetric grid conditions by maintaining the desired
voltages and currents. Such disturbances’ conditions would lead to permanent damage of
the SST components as well as other connected systems. A possible solution could be
implementing an intelligent algorithm in order to ensure a reliable operation by restoring
the grid currents to their safe operation point. Also a comparison between star- and delta-
connected SST should be investigated. A laboratory hardware prototype of the SST should
be constructed and operated under nominal conditions for practical analysis. EMI and
oscillating behaviour issues should also be taken into consideration. The developed SST
model should then be refined until it perfectly predicts the behaviour of the nominal
laboratory prototype. The model should be further developed to predict the SST behaviour
under worst-case conditions; fault-ride short circuit conditions using Hardware-in-the-
Loop (HIL) testing. The SST design should be improved until worst-case behaviour meets
the specifications until reliability and production yield are acceptable. Another research
area to investigate is implementing a start-up charging procedure of the SST capacitors.
This is because the capacitors at the MVDC- and LVDC- links in this research study were
assumed to be charged initially at a voltage level equal to their rated values. Moreover,
inrush currents were not considered in this study. Therefore, protection measures should
be considered for future studies in order to avoid large inrush currents when starting the
SST. Finally, given the large number of hardware elements, studies on the failure rates and
reliability of such SST structures with integrated ESSs are of great importance, in
association with fault diagnosis techniques and implementations of redundancy schemes.
160
REFERENCES
[1] Aber, J. “Electric Bus Analysis for New York City Transit.”, Accessed: September
2019. [Online]. Available: http://www.columbia.edu/~ja3041/Electric Bus Analysis for
NYC Transit by J Aber Columbia University - May 2016.pdf
[2] Alexander, M. “Environmental Assessment of a Full Electric Transportation Portfolio.
NRDC & Electric Power Research Institute, 1, 1–18. 2015. [Online]. Available:
http://doi.org/10.1017/CBO9781107415324.004
[3] Centre for Climate Change and Energy Solutions, “Global Carbon Dioxide Emissions,
1850–2030”. [Online]. Available: https://www.c2es.org/content/international-emissions
[4] United States Environmental Protection Agency “Sources of Greenhouse Gas
Emissions”, October 2019. [Online]. Available:
https://www.epa.gov/ghgemissions/sources-greenhouse-gas-emissions
[5] Prairie Climate Centre, "Where Do Canada's Greenhouse Gas Emissions Come
From?", Accessed: October 2019. [Online]. Available:
http://prairieclimatecentre.ca/2018/03/where-do-canadas-greenhouse-gas-emissions-
come-from
[6] D. Aggeler, F. Canales, H. Zelaya-De La Parra, A. Coccia, N. Butcher, and O.
Apeldoorn, “Ultra-fast dc-charge infrastructures for EV-mobility and future smart grids,”
in Proc. IEEE Power and Energy Society Innovative Smart Grid Technology Conf. Europe,
Gothenburg, Sweden, Oct. 2010, pp. 1-8.
[7] A. Emadi, S. S. Williamson, and A. Khaligh, “Power electronics intensive solutions for
advanced electric, hybrid electric, and fuel cell vehicular power systems,” IEEE Trans. on
Power Electronics vol. 21, no. 3, pp. 567-577, May 2006.
[8] Y. Lee, A. Khaligh, and A. Emadi, “Advanced integrated bi-directional AC/DC and
DC/DC converter for plug-in hybrid electric vehicles,” IEEE Trans. on Vehicular
Technology, vol. 58, no. 3, pp. 3970-3980, Oct. 2009.
[9] D. S. Gautam, F. Musavi, M. Edington, W. Eberle, and W. G. Dunford, “An automotive
onboard 3.3-kW battery charger for PHEV application,” IEEE Trans. on Vehicular
Technology, vol. 61, no. 8, pp. 3466 -3474, Oct. 2012.
[10] S. Li, J. Deng, and C. C. Mi, “Single-stage resonant battery charger with inherent
power factor correction for electric vehicles,” IEEE Trans. on Vehicular Technology, vol.
62, no. 9, pp. 4336-4344, Nov. 2013.
[11] Y. Du, S. Lukic, B. Jacobson, and A. Huang, “Review of high power isolated bi-
directional dc-dc converters for PHEV/EV DC charging infrastructure,” in Proc. IEEE
Energy Conversion Congress and Expo., San Jose, CA, Sept. 2011, pp. 553-560.
[12] M. C., Falvo, D. Sbordone, I. S. Bayram; M. Devetsikiotis, “EV charging stations and
modes: International standards”, International Symposium on Power Electronics, Electrical
Drives, Automation and Motion, 2014.
161
[13] F. M., Shakeel, Om P. Malik, “Vehicle-To-Grid Technology in a Micro-grid Using
DA Fast Charging Architecture”, IEEE Canadian Conference of Electrical and Computer
Engineering (CCECE), 2019.
[14] B. Nykvist and M. Nilsson, “Rapidly falling costs of battery packs for electric
vehicles,” Nature Climate Change, vol. 5, no. 4, p. 329, 2015.
[15] Z. P. Cano et al., “Batteries and fuel cells for emerging electric vehicle markets,”
Nature Energy, vol. 3, no. 4, p. 279, 2018.
[16] IEA. Global EV Outlook 2019. Accessed: December 2019. [Online]. Available:
https://www.iea.org/publications/reports/ globalevoutlook2019/
[17] Y. Lee, A. Khaligh, and A. Emadi, “Advanced integrated bi-directional AC/DC and
DC/DC converter for plug-in hybrid electric vehicles,” IEEE Trans. Veh. Technol., vol.
58, no. 3, pp. 3970– 3980, Oct. 2009.
[18] Y. Du, S. Lukic, B. Jacobson, and A. Huang, “Review of high power isolated bi-
directional DC-DC converters for PHEV/EV DC charging infrastructure,” in Proc. IEEE
Energy Conversion Congr. Expo., Sep. 2011, pp. 553–560.
[19] P. Sapkota and H. Kim, “Zinc–air fuel cell, a potential candidate for alternative
energy,” J. Ind. Eng. Chem., vol. 15, no. 4, pp. 445–450, Jul. 2009.
[20] P. F. Ribeiro, B. K. Johnson, M. L. Crow, A. Arsoy, and Y. Liu, “Energy storage
systems for advanced power applications,” Proc. IEEE, vol. 89, no. 12, pp. 1744–1756,
Dec. 2001.vol. 55, no. 6, pp. 2258–2267, Jun. 2008.
[21] S. Vazquez, SM. Lukic, E. Galvan, L.G. Franquelo, J. M. Carrasco, “Energy Storage
Systems for Transport and Grid Applications” IEEE Trans. Ind. Electron, vol. 57, no. 12
pp. Dec. 2010
[22] R. G. Lawrence, K. L. Craven, and G. D. Nichols, “Flywheel UPS,” IEEE Ind. Appl.
Mag., vol. 9, no. 3, pp. 44–50, May/Jun. 2003.
[23] M. M. Flynn, P. Mcmullen, and O. Solis, “Saving energy using flywheels,” IEEE Ind.
Appl. Mag., vol. 14, no. 6, pp. 69–76, Nov./Dec. 2008.
[24] Chakratec Flywheel Technology for E-Mobility, Accessed: November 2019. [Online].
Available: https://chakratec.com/technology/
[25] Adaptive Balancing Power Flywheel Technology for Charging, Accessed: November
2019. [Online]. Available: https://www.adaptive-balancing.com/
[26] H. Akagi and H. Sato, “Control and performance of a doubly-fed induction machine
intended for a flywheel energy storage system,” IEEE Trans. Power Electron., vol. 17, no.
1, pp. 109–116, Jan. 2002.
[27] S. Samineni, B. K. Johnson, H. L. Hess, and J. D. Law, “Modeling and analysis of a
flywheel energy storage system for voltage sag correction,” IEEE Trans. Ind. Appl., vol.
42, no. 1, pp. 42–52, Jan./Feb. 2006.
162
[28] G. O. Cimuca, C. Saudemont, B. Robyns, and M. M. Radulescu, “Control and
performance evaluation of a flywheel energy storage system associated to a variable-speed
wind generator,” IEEE Trans. Ind. Electron., vol. 53, no. 4, pp. 1074–1085, Jun. 2006.
[29] H. Hõimoja, M. Vasiladiotis, S. Grioni, M. Capezzali, A. Rufer, and H. B. Püttgen,
“Toward Ultrafast Charging of Electric Vehicles,” in 2012 CIGRE Session, Paris, France,
August 26-31, 2012.
[30] Martel Tsirinomeny, “Contribution to the Ultra-Fast Charging of Electric Vehicles:
The Configurable Modular Multilevel Converter (CMMC)”, Ph.D. Thesis, EPFL, 2016.
[31] Z. P. Cano et al., “Batteries and fuel cells for emerging electric vehicle markets,”
Nature Energy, vol. 3, no. 4, p. 279, 2018.
[32] IEA. Global EV Outlook 2019. Accessed: Dec. 29, 2019. Available Online:
https://www.iea.org/publications/reports/ globalevoutlook2019/
[33] S. Manzetti and F. Mariasiu, “Electric vehicle battery technologies: From present state
to future systems,” Renew. Sustain. Energy Rev., vol. 51, pp. 1004–1012, Nov. 2015.
[34] S. Ahmed et al., “Enabling fast charging—A battery technology gap assessment,” J.
Power Sources, vol. 367, pp. 250–262, Nov. 2017.
[35] M. Keyser et al., “Enabling fast-charging–battery thermal considerations,” J. Power
Sources, vol. 367, pp. 228–236, Nov. 2017.
[36] Hannan, M.A.; Hoque, M.M.; Hussain, A.; Yusof, Y.; Ker, P.J. State-of-the-Art and
Energy Management System of Lithium-Ion Batteries in Electric Vehicle Applications:
Issues and Recommendations. IEEE Access 2018, 6, 19362–19378.
[37] Gao, Y.; Zhang, X.; Cheng, Q.; Guo, B.; Yang, J. Classification and Review of the
Charging Strategies for Commercial Lithium-Ion Batteries. IEEE Access 2019, 7, 43511–
43524.
[38]. Ahmed, S.; Bloom, I.; Jansen, A.N.; Tanim, T.; Dufek, E.J.; Pesaran, A.; Zhang, J.
Enabling fast charging—A battery technology gap assessment. J. Power Sour. 2017, 367,
250–262.
[39] Collin, R.; Miao, Y.; Yokochi, A.; Enjeti, P.; Jouanne, A. “Advanced Electric Vehicle
Fast-Charging Technologies”, Energies 2019, 12, 1839.
[40] Khaligh, A.; Dusmez, S. Comprehensive Topological Analysis of Conductive and
Inductive Charging Solutions for Plug-In Electric Vehicles. IEEE Trans. Veh. Technol.
2012, 61, 3475–3489.
[41] Vehicle On-Board Charger. Accessed: November 2019. [Online]. Available:
https://www.tesla.com/support/home-charging- \installation-redirect
[42] Yilmaz, M.; Krein, P.T. Review of Battery Charger Topologies, Charging Power
Levels, and Infrastructure for Plug-In Electric and Hybrid Vehicles. IEEE Trans. Power
Electron. 2013, 28, 2151–2169.
163
[43] Vehicle Enterprise. Accessed: November 2019. [Online]. Available:
http://www.observatoire-vehicule-entreprise.com/.
[44] M. Kamachi, H. Miyamoto, and Y. Sano, “Development of power management system
for electric vehicle ‘i-MiEV,’” 2010 Int. Power Electron. Conf. - ECCE ASIA -, pp. 2949–
2955, 2010.
[45] G. Dinger, Andreas; Martin, Ripley; Mosquet, Xavier; Rabl, Maximilian; Rizoulis,
Dimitrios; Russo, Massimo, Sticher, “Focus Batteries for Electric Cars,” p. 18, 2010.
[46] Altairnano. Accessed: December 2019. [Online]. Available:
http://www.altairnano.com/.
[47] Don Kintner, “Medium-Voltage Intelligent Universal Transformer™ Based DC Fast
Charging Development and Demonstration”, EPRI. Available Online: www.epri.com
[48] Srdjan Srdic and Srdjan Lukic,“Toward Extreme Fast Charging Challenges and
opportunities in directly connecting to a medium-voltage line.”, IEEE Electrification
Magazine, March 2019.
[49] A. Shiri, “A solid state transformer for interconnection between the medium and the
low voltage grid design” Delft University of Technology, October 2013.
[50] L. Heinemann and G. Mauthe, “The universal power electronics based distribution
transformer, an unified approach,” in Proc. 32nd Annu. IEEE Power Electron. Specialists
Conf. (PESC), Vancouver, Canada, August 2001, pp. 504–509. DOI:
10.1109/PESC.2001.954164
[51] M. Firouzjaee, “Advanced modeling of solid state transformer”, Ph.D. Thesis, UPC,
Barcelona, January 2018.
[52] Tesla Model S, Available Online: www.tesla.com
[53] Deepak Ronanki, Apoorva Kelkar, Sheldon S. Williamson “Extreme Fast Charging
Technology—Prospects to Enhance Sustainable Electric Transportation”, Energies 2019,
12, 3721; doi:10.3390/en12193721.
[54] M. Tsirinomeny, H. Hõimoja, A. Rufer, G. Dziechciaruk, A. Vezzini, M. Tsirinomeny,
A. Vezzini, H. Himoja, and A. Rufer, “Optimizing EV driving-recharge time ratio under
limited grid connection,” 7th IET Int. Conf. Power Electron. Mach. Drives (PEMD 2014),
pp. 1–6, 2014.
[55] K. Yunus, H. Z. D. La Parra, and M. Reza, “Distribution grid impact of Plug-In
Electric Vehicles charging at fast-charging stations using stochastic charging model,” Proc.
2011 14th Eur. Conf. Power Electron. Appl., pp. 1–11, 2011.
[56] CHAdeMO Association.” Available Online: http://www.chademo.com/
[57] ABB Electric Vehicle Infrastructure. Available Online: www.abb.com/evcharging.
[58] Siemens AG, “eBus - High Power Charging Solutions from Siemens,” Technical
Presentation, 2015.
164
[59] P. J. Rodríguez and P. C. Estay, Predictive control of power converters and electrical
drives. A John Wiley & Sons, Ltd., Publication, 2012.
[60] Ahmed, A.-S.; Jad, B.; Ahmed, F.A. Solid state transformers topologies, controllers,
and applications: State-of-the-art literature review. Electronics 2018, 7, 298.
[61] Huber, J.E.; Kolar, J.W. Applicability of Solid-State Transformers in Today’s and
Future Distribution Grids. IEEE Trans. Smart Grid 2019, 10, 317–326.
[62] D. Christen, F. Jauch, J. Biela, Ultra-Fast Charging Station for Electric Vehicles with
integrated split Grid Storage, 17th European Conference on Power Electronics and
Applications, Geneva, Switzerland, September 8-10, 2015.
[63] OP4510 V2 Real-time Simulator, Accessed: October 2019. [Online]. Available:
https://wiki.opal-rt.com/display/HDGD/OP4510+V2
[64] Electric Cars: Technology, Accessed: March 2020. [Online]. Available:
https://ocw.tudelft.nl/courses/electric-cars-technology
[65] R. Bosshard, U. Badstübner, J. W. Kolar, and I. Stevanović, “Comparative evaluation
of control methods for inductive power transfer,” in 2012 International Conference on
Renewable Energy Research and Applications (ICRERA), Nov 2012, pp. 1–6.
[66] J. Dai and D. C. Ludois, “A survey of wireless power transfer and a critical comparison
of inductive and capacitive coupling for small gap applications,” IEEE Transactions on
Power Electronics, vol. 30, no. 11, pp. 6017–6029, Nov 2015.
[67] S. Rajakaruna, F. Shahnia, and A. Ghosh, Plug-in electric vehicles in smart grids.
Springer, 2016.
[68] Chandra Mouli GR. Charging electric vehicles from solar energy: Power converter,
charging algorithm and system design. 2018. 224 p. Available Online:
https://doi.org/10.4233/uuid:dec62be4-d7cb-4345-a8ae-65152c78b80f
[69] Lee Gill, “Evaluation and Development of Medium-Voltage Converters Using 3.3 kV
SiC MOSFETs for EV Charging Application”, MSc Thesis, Virginia Polytechnic Institute
and State University, 2019.
[70] (2018) Chademo releases the latest version of the protocol enabling up to 400kw.
Online. [Online]. Available: https://www.chademo.com/ chademo-releases-the-latest-
version-of-the-protocol-enabling-up-to-400kw/
[71] T. T. Team. (2019) Introducing v3 supercharging. Online. [Online]. Available:
https://www.tesla.com/blog/introducing-v3-supercharging
[72] ‘Delta’, https://www.deltaww.com/en-US/products/EV-Charging/ 4865.
[73] ‘Delta’, Accessed: November 2019. [Online]. Available: https://3814f048-6c69-488c-
9f3ee8df0a79bfd4.filesusr.com/ugd/1667b4_ed598c2eeea34ffd9d792ba156c78710.pdf
[74] ABB High Power Charging, Accessed: November 2019. [Online]. Available:
https://new.abb.com/ev-charging/ products/car-charging/high-power charging
165
[75] ABB, Accessed: December 2019. [Online]. Available:
https://search.abb.com/library/Download.aspx?DocumentID=9AKK107680A7994&Lang
uageCode=en&DocumentPartId=&Action =Launch.
[76] Tritium VEEFIL-RT 50KW DC FAST CHARGER. Tritium Pty Ltd, Accessed:
January 2020. [Online]. Available: https://www.tritium.com.au/product/productitem?url=
veefil-rt-50kwdc-fast-charger
[77] Tritium LAUNCHING SOON- VEEFIL-PK DC ULTRA-FAST CHARGER 175 kW-
475 kW. Tritium Pty Ltd, Accessed: January 2019. [Online]. Available: https://www.
tritium.com.au/veefillpk
[78] M. KANE. (2018) China is developing new gb/t fast charging standard at 900 kw,
Accessed: February 2020. [Online]. Available: https://insideevs.com/news/338620/ china-
is-developing-new-gb-t-fast-charging-standard-at-900-kw/
[79] Green Power Motor Company, Accessed: January 2020. [Online]. Available:
www.greenpowerbus.com.
[80] The Lion Electric Company, Accessed: January. [Online]. Available:
www.thelionelectric.com.
[81] New Flyer Industries, Accessed: January 2020. [Online]. Available:
www.newflyer.com.
[82] Nova Bus, Accessed: November 2019. [Online]. Available: www.novabus.com.
[83] LFSe+ Electric Bus, Nova Bus, Accessed: February 2020. [Online]. Available:
https://novabus.com/wp-content/uploads/2017/09/LFSe_brochure_march2021_EN.pdf
[84] BTC Power, Accessed: November 2019. [Online]. Available: www.btcpower.com.
[85] BAE Systems, Accessed: November 2019. [Online]. Available:
https://www.baesystems.com.
[86] Proterra, Accessed: October 2019. [Online]. Available:
https://www.proterra.com/energy-services/charging-infrastructure/.
[87] SIEMENS, Accessed: October 2019. [Online]. Available: www.siemens.com.
[88] ABB, Accessed: November 2019. [Online]. Available: https://global.abb/group.
[89] Proterra, Accessed: September 2020. [Online]. Available:
https://www.proterra.com/wp-content/uploads/2020/10/SPEC_CHG-
SYS_1.5M_V8_10.26.20.pdf
[90] C. C. Chan and K. T. Chau, “An overview of power electronics in electric vehicles,”
IEEE Transactions on Industrial Electronics, vol. 44, no. 1, pp. 3–13, Feb 1997.
[91] G. Sharma, V.K. Sood, M.S. Alam, S.M. Shariff, "Comparison of common DC and
AC bus architectures for EV fast-charging stations and impact on power quality"
eTransportation, 2020. https://doi.org/10.1016/j.etran.2020.100066
166
[92] P. J. Rodríguez and P. C. Estay, Predictive control of power converters and electrical
drives. A John Wiley & Sons, Ltd., Publication, 2012.
[93] H. Tu, H. Feng, S. Srdic and S. Lukic, "Extreme Fast Charging of Electric Vehicles:
A Technology Overview," in IEEE Transactions on Transportation Electrification, vol. 5,
no. 4, pp. 861-878, Dec. 2019, doi: 10.1109/TTE.2019.2958709.
[94] J. J. Justo, F. Mwasilu, J. Lee, and J.-W. Jung, “Ac-microgrids versus dc-microgrids
with distributed energy resources: A review,” Renewable and Sustainable Energy Reviews,
vol. 24, pp. 387 – 405, 2013. [Online]. Available:
http://www.sciencedirect.com/science/article/pii/S1364032113002268
[95] J. Francfort, T. Garetson, D. Karner, S. D. Salisbury, and J. G. Smart, “Considerations
for corridor and community dc fast charging complex system design,” 2017
[96] Y. Tahir, et.al “A state-of-the-art review on topologies and control techniques of solid-
state transformers for electric vehicle extreme fast charging”, IET Power Electronics, April
2021.
[97] Srdic, S., Lukic, S.: Toward extreme fast charging: challenges and opportunities in
directly connecting to medium-voltage line. IEEE Electrif. Mag. 7(1), 22–31 (2019)
[98] EN 61851-23:2014 - Electric vehicle conductive charging system - Part 23: DC
electric vehicle charging station. https://standards.iteh. ai/catalog/standards/clc/114bd98a-
e033-4c5d-9bdc-4f8de579cc34/ en-61851-23-2014 (2020). Accessed July 2020.
[99] J. W. Kolar and J. E. Huber, “Solid-state transformers-key design challenges,
applicability, and future concepts,” in Conference Guide. IEEE, 2016, pp. 26–26
[100] Q. Zhu, L. Wang, A. Q. Huang, K. Booth, and L. Zhang, “7.2-kv single-stage solid-
state transformer based on the current-fed series resonant converter and 15-kv sic mosfets,”
IEEE Transactions on Power Electronics, vol. 34, no. 2, pp. 1099–1112, Feb 2019.
[101] X. She, A. Q. Huang, S. Lukic, and M. E. Baran, “On integration of solid-state
transformer with zonal dc microgrid,” IEEE Transactions on Smart Grid, vol. 3, no. 2, pp.
975–985, June 2012.
[102] X. Yu, X. She, X. Zhou, and A. Q. Huang, “Power management for dc microgrid
enabled by solid-state transformer,” IEEE Transactions on Smart Grid, vol. 5, no. 2, pp.
954–965, March 2014.
[103] X. She, A. Q. Huang, and R. Burgos, “Review of solid-state transformer technologies
and their application in power distribution systems,” IEEE Journal of Emerging and
Selected Topics in Power Electronics, vol. 1, no. 3, pp. 186–198, Sep. 2013.
[104] A. Q. Huang, “Medium-voltage solid-state transformer: Technology for a smarter
and resilient grid,” IEEE Industrial Electronics Magazine, vol. 10, no. 3, pp. 29–42, Sep.
2016.
[105] H. Silva, D. Jayamaha and N. Lidula, “Review on design and control of solid state
transformer based microgrids”, AIMS Energy, 7(6): 901–923, Dec 2019.
167
[106] M. A. Shamshuddin, F. Rojas, R. Cardenas, J. Pereda, M. Diaz, and R. Kennel, “Solid
State Transformers: Concepts, Classification, and Control,” Energies, vol. 13, no. 9, p.
2319, May 2020.
[107] Hannan, M.A. et al.: State of the art of solid-state transformers: Advanced topologies,
implementation issues, recent progress and improvements. IEEE Access 8, 19113–19132
(2020).
[108] EPRI, “Utility direct medium voltage dc fast charger update: Dc fast charger
characterization,” December 2012.
[109] A. Maitra, S. Rajagopalan, J.-S. Lai, M. DuVall, and M. McGranaghan, “Medium
voltage stand alone dc fast charger,” May 30 2013, uS Patent App. 13/479,389.
[110] Tan, L.; Wu, B., and Rivera, S. ‘A bipolar-DC-bus EV fast charging station
withintrinsic DC-bus voltages equalization and minimized voltage ripples’. In:IECON2015
- 41st Annual Conference of the IEEE Industrial Electronics Society. Nov. 2015,pp.
002190–002195.
[111] J.-S. Lai, W.-H. Lai, S.-R. Moon, L. Zhang, and A. Maitra, “A 15-kV class intelligent
universal transformer for utility applications,” in Proc. IEEE Appl. Power Electron. Conf.
Expo. (APEC), Mar. 2016, pp. 1974–1981.
[112] S. Srdic, C. Zhang, X. Liang, W. Yu, and S. Lukic, “A SiC-based power converter
module for medium-voltage fast charger for plug-in electric vehicles” in Proc. IEEE Appl.
Power Electron. Conf. Expo. (APEC), Mar. 2016, pp. 2714–2719.
[113] S. Srdic, X. Liang, C. Zhang, W. Yu, and S. Lukic, “A SiC-based high-performance
medium-voltage fast charger for plug-in electric vehicles,” in Proc. IEEE Energy Convers.
Congr. Expo. (ECCE), Sep. 2016, pp. 1–6.
[114] X. Liang, C. Zhang, S. Srdic, and S. M. Lukic, “Predictive control of a series-
interleaved multicell three-level boost power-factorcorrection converter,” IEEE Trans.
Power Electron., vol. 33, no. 10, pp. 8948–8960, Oct. 2018.
[115] D. Rothmund, G. Ortiz, and J. W. Kolar, “SiC-based unidirectional solid-state
transformer concepts for directly interfacing 400 V DC to medium-voltage AC distribution
systems,” in Proc. IEEE 36th Int. Telecommun. Energy Conf. (INTELEC), Sep./Oct. 2014,
pp. 1–9.
[116] M. Vasiladiotis and A. Rufer, “A modular multiport power electronic transformer
with integrated split battery energy storage for versatile ultrafast EV charging stations,”
IEEE Trans. Ind. Electron., vol. 62, no. 5, pp. 3213–3222, May 2015.
[117] D. Sha, G. Xu, and Y. Xu, “Utility direct interfaced charger/discharger employing
unified voltage balance control for cascaded H-bridge units and decentralized control for
CF-DAB modules,” IEEE Trans. Ind. Electron., vol. 64, no. 10, pp. 7831–7841, Oct. 2017.
[118] X. She, X. Yu, F. Wang, and A. Q. Huang, “Design and demonstration of a 3.6-kV-
120-V/10-kVA solid-state transformer for smart grid application,” IEEE Trans. Power
Electron., vol. 29, no. 8, pp. 3982–3996, Aug. 2014.
168
[119] C. Zhu. High-Efficiency, Medium-Voltage-Input, Solid-State Transformer-Based
400-kW/1000-V/400-A Extreme Fast Charger for Electric Vehicles. [Online]. Available:
https://www.energy.gov/sites/
prod/files/2019/06/f64/elt241_zhu_2019_o_4.24_9.31pm_jl.pdf
[120] F. Wang, G. Wang, A. Huang, W. Yu, and X. Ni, “Design and operation of a 3.6 kV
high performance solid state transformer based on 13 kV SiC MOSFET and JBS diode,”
in Proc. IEEE Energy Convers. Congr. Expo. (ECCE), Sep. 2014, pp. 4553–4560.
[121] D. Rothmund, T. Guillod, D. Bortis, and J. W. Kolar, “99.1% efficient 10 kV SiC-
based medium-voltage ZVS bidirectional single-phase PFC AC/DC stage,” IEEE J. Emerg.
Sel. Topics Power Electron., vol. 7, no. 2, pp. 779–797, Jun. 2019.
[122] D. Rothmund, T. Guillod, D. Bortis, and J. W. Kolar, “99% efficient 10 kV SiC-
based 7 kV/400 V DC transformer for future data centers” IEEE J. Emerg. Sel. Topics
Power Electron., vol. 7, no. 2, pp. 753–767, Jun. 2019.
[123] IEEE Recommended Practice and Requirements for Harmonic Control in Electric
Power Systems, IEEE Standard 519-2014, Jun. 2014, pp. 1–29.
[124] IEEE Standard for General Requirements for Dry-Type Distribution and Power
Transformers, IEEE Standard C57.12.01-2015, Feb. 2015, pp. 1–52.
[125] Electromagnetic Compatibility (EMC)—Part 2–12: Environment— Compatibility
Levels for Low-Frequency Conducted Disturbances and Signalling in Public Medium-
Voltage Power Supply Systems, Standard IEC 61000-2-12:2003, Apr. 2003, pp. 1–55.
[126] Electromagnetic Compatibility (EMC)—Part 3–6: Limits—Assessment of Emission
Limits for the Connection of Distorting Installations to MV, HV and EHV Power Systems,
Standard IEC TR 61000-3-6:2008, Feb. 2008, pp. 1–58.
[127] Plugs, Socket-Outlets, Vehicle Connectors and Vehicle Inlets— Conductive
Charging of Electric Vehicles—Part 3: Dimensional Compatibility and Interchangeability
Requirements for D.C. and A.C./D.C. Pin and Contact-Tube Vehicle Couplers, Standard
IEC 62196-3:2014, Jun. 2014, p. 1.
[128] Requirements, Standard IEC 61851-1:2017, Feb. 2017, pp. 1–287.
[129] Electric Vehicle Conductive Charging System—Part 23: DC Electric Vehicle
Charging Station, Standard IEC 61851-23:2014, Mar. 2014, pp. 1–159.
[130] Electric Vehicle Conductive Charging System—Part 24: Digital Communication
Between A D.C. EV Charging Station and an Electric Vehicle for Control of D.C.
Charging, Standard IEC 61851-24:2014, Mar. 2014, pp. 1–63.
[131] SAE Electric Vehicle and Plug in Hybrid Electric Vehicle Conductive Charge
Coupler, Standard SAE J1772, Oct. 2017, p. 1.
[132] . Avdeev, B., Vyngra, A., Chernyi, S.: Improving the electricity quality by means of
a single-phase solid-state transformer. Designs 4(3), 35 (2020) 55.
169
[133] Huber, J.E., Kolar, J.W.: Volume/weight/cost comparison of a 1MVA 10 kV/400 V
solid-state against a conventional low-frequency distribution transformer. In: 2014 IEEE
Energy Conversion Congress and Exposition, ECCE 2014. Pittsburgh, PA, pp. 4545–4552
(2014).
[134] Qin, H., Kimball, J.W.: Ac-Ac dual active bridge converter for solid state
transformer. In: 2009 IEEE Energy Conversion Congress and Exposition, ECCE 2009. San
Jose, CA, pp. 3039–3044 (2009) 65.
[135] Chen, H., Prasai, A., Divan, D.: Dyna-C: A minimal topology for bidirectional solid-
state transformers. IEEE Trans. Power Electron. 32(2), 995– 1005 (2017).
[136] Abu-Siada, A., Budiri, J., Abdou, A.: Solid state transformers topologies, controllers,
and applications: State-of-the-art literature review. Electronics 7(11), 298 (2018).
[137] Carpita, M., et al.: Multi-level converter for traction applications: Small scale
prototype tests results. IEEE Trans. Ind. Electron. 55(5), 2203–2212 (2008).
[138] Drábek, P., et al.: New configuration of traction converter with medium frequency
transformer using matrix converters. IEEE Trans. Ind. Electron. 58, 5041–5048 (2011).
[139] Hugo, N., et al.: Power electronics traction transformer. In: 2007 European
Conference on Power Electronics and Applications, EPE. Barcelona, Spain (2007).
[140] She, X., et al.: Review of solid state transformer in the distribution system: From
components to field application. In: 2012 IEEE Energy Conversion Congress and
Exposition, ECCE 2012. Raleigh, NC, pp. 4077–4084 (2012).
[141] Banaei, M.R., Salary, E.: Power quality improvement based on novel power
electronic transformer. In: 2011 2nd Power Electronics, Drive Systems and Technologies
Conference, PEDSTC 2011. Tehran, Iran, pp. 286–291 (2011)
[142] Sabahi, M., et al.: Zero-voltage switching bi-directional power electronic
transformer. IET Power Electron. 3(5), 818–828 (2010).
[143] Singh, B., et al.: A review of three-phase improved power quality ac-dc converters.
IEEE Trans. Ind. Electron. 51(3), 641–660 (2004).
[144] Wang, F., et al.: Design and operation of A 3.6kV high performance solid state
transformer based on 13kV SiC MOSFET and JBS diode. In: 2014 IEEE Energy
Conversion Congress and Exposition, ECCE 2014. Pittsburgh, PA, pp. 4553–4560 (2014).
[145] Fan, H., Li, H.: High-frequency transformer isolated bidirectional DCDC converter
modules with high efficiency over wide load range for 20 kVA solid-state transformer.
IEEE Trans. Power Electron. 26(12), 3599– 3608 (2011).
[146] Kimura, N., et al.: Solid state transformer investigation for HVDC transmission from
offshore windfarm. In: 2017 IEEE 6th International Conference on Renewable Energy
Research and Applications (ICRERA). San Diego, CA, pp. 574–579 (2017).
170
[147] Madhusoodhanan, S., et al.: Solid-state transformer and MV grid tie applications
enabled by 15 kV SiC IGBTs and 10 kV SiC MOSFETs based multilevel converters. IEEE
Trans. Ind. Appl. 51(4), 3343–3360 (2015).
[148] Parseh, N., Mohammadi, M.: Solid state transformer (SST) interfaced doubly fed
induction generator (DFIG) wind turbine. In: 2017 25th Iranian Conference on Electrical
Engineering, ICEE 2017. Tehran, Iran, pp. 1084–1089 (2017).
[149] Zhang, Z., et al.: Voltage and power balance control strategy for three phase modular
cascaded solid stated transformer. In: Conference Proceedings - IEEE Applied Power
Electronics Conference and Exposition – APEC. Long Beach, CA, pp. 1475–1480 (2016).
[150] Chetri, C., et al.: Study of various design for SST implementation. Int. J. Sci. Res.
Eng. Dev. no date, 3. 3(1), 1–8 (2020).
[151] Mostafa, M.A., et al.: SBO-based selective harmonic elimination for nine levels
asymmetrical cascaded H-bridge multi-level inverter. Aust. J. Electr. Electron. Eng. 15(3),
131–143 (2018).
[152] Mostafa, M.A., Abdou, A.F., El-Gawad, A.F.A., El-Kholy, E.E.: Comparison of
multi-carrier and SHE-PWM for a nine levels cascaded H-bridge inverter. In: 2017 19th
International Middle-East Power Systems Conference, MEPCON 2017 – Proceedings.
Cairo, Egypt, pp. 1483–1491 (2018)
[153] Andersson, D., Carlsson, D.: Measurement of ABB s prototype fast charging station
for electric vehicles. M.S. Thesis. Chalmers University of Technology, Sweden (2012).
[154] Lee, M., et al.: Modeling and control of three-level boost rectifier based medium-
voltage solid-state transformer for DC fast charger application. IEEE Trans. Transp.
Electrif. 5(4), 890–902 (2019).
[155] Liang, X., et al.: A 12.47 kV Medium Voltage Input 350 kW EV Fast Charger using
10 kV SiC MOSFET. In: 2019 IEEE Applied Power Electronics Conference and
Exposition (APEC). Anaheim, CA, pp. 581–587 (2019)
[156] V. M. Iyer, S. Gulur, G. Gohil and S. Bhattacharya, "Extreme fast charging station
architecture for electric vehicles with partial power processing," 2018 IEEE Applied Power
Electronics Conference and Exposition (APEC), 2018, pp. 659-665, doi:
10.1109/APEC.2018.8341082.
[157] M A Awal, et.al., “Modular Medium Voltage AC to Low Voltage DC Converter for
Extreme Fast Charging Applications”, Accessed: November 2020. [Online]. Available:
arXiv:2007.04369, 8 Jul 2020.
[158] A. C. Nair and B. G. Fernandes, "A Solid State Transformer based Fast Charging
Station for Various Categories of Electric Vehicles with Batteries of Vastly Different
Ratings," in IEEE Transactions on Industrial Electronics, doi: 10.1109/TIE.2020.3038091.
[159] S. Kouro, M. Malinowski, K. Gopakumar, J. Pou, L. G. Franquelo, J. Rodriguez, M.
A. Perez, and J. I. Leon, “Recent Advances and Industrial Applications of Multilevel
Converters,” IEEE Trans. Ind. Electron., vol. 57, no. 8, pp. 2553–2580, Aug. 2010.
171
[160] J. Rodriguez, S. Bernet, B. Wu, J. O. Pontt, and S. Kouro, “Multilevel Voltage-
Source Converter Topologies for Industrial Medium-Voltage Drives,” IEEE Trans. Ind.
Electron., vol. 54, no. 6, pp. 2930–2945, Dec. 2007.
[161] S. Khomfoi and L. M. Tolbert, “Multilevel power converters,” in in Power
Electronics Handbook, Third Edit., Elsevier Inc., 2007, pp. 455–486.
[162] J.-S. Lai and F. Zheng Peng, “Multilevel converters-a new breed of power
converters,” IEEE Trans. Ind. Appl., vol. 32, no. 3, pp. 509–517, 1996.
[163] J. Dixon and L. Moran, “High-level multistep inverter optimization using a minimum
number of power transistors,” IEEE Trans. Power Electron., vol. 21, no. 2, pp. 330–337,
Mar. 2006.
[164] V. Guennegues, B. Gollentz, F. Meibody-Tabar, S. Rael, and L. Leclere, “A
converter topology for high speed motor drive applications,” Power Electronics and
Applications, 2009. EPE ’09. 13th European Conference on. pp. 1–8, 2009.
[165] M. Malinowski, K. Gopakumar, J. Rodriguez, and M. A. Perez, “A Survey on
Cascaded Multilevel Inverters,” IEEE Trans. Ind. Electron., vol. 57, no. 7, pp. 2197–2206,
Jul. 2010.
[166] M. Hiller, D. Krug, R. Sommer, and S. Rohner, “A new highly modular medium
voltage converter topology for industrial drive applications,” Power Electronics and
Applications, 2009. EPE ’09. 13th European Conference on. pp. 1–10, 2009.
[167] Y. Liu, “A review of module multi-level converters,” in 2011 Seventh International
Conference on Natural Computation, 2011, pp. 1934–1940
[168] B. Wu, “Current status of multi-megawatt AC drives,” in 2004 IEEE International
Conference on Industrial Technology, 2004. IEEE ICIT ’04., 2004, vol. 1, pp. 438–443.
[169] F. Krismer, “Modeling and Optimization of Bidirectional Dual Active Bridge DC –
DC Converter Topologies,” 2010.
[170] P. Cortés, M. P. Kazmierkowski, R. M. Kennel, D. E. Quevedo, and J. Rodríguez,
“Predictive Control in Power Electronics and Drives,” IEEE Trans. Ind. Electron., vol. 55,
no. 12, pp. 4312–4324, 2008.
[171] M. P. Kazmierkowski and L. Malesani, “Current control techniques for three-phase
voltage-source PWM converters: a survey,” IEEE Trans. Ind. Electron., vol. 45, no. 5, pp.
691–703, 1998.
[172] H. Kim and H. Akagi, “The instantaneous power theory on the rotating pqr reference
frames,” Int. Conf. Power Electron. Drives Syst., no. July, pp. 422–427, 1999.
[173] H. Akagi, S. Ogasawara, and H. Kim, “The theory of instantaneous power in three-
phase four-wire systems: a comprehensive approach,” IEEE Conf. Rec. Ind. Appl. Conf.,
1999.
172
[174] M. Ciobotaru, P. Zanchetta, Y. De Novaes, and F. Blaabjerg, “Study and analysis of
a natural reference frame current controller for a multi-level H-bridge power converter,”
IEEE Power Electron. Spec. Conf., pp. 2914–2920, 2008.
[175] M. Ciobotaru, P. Zanchetta, Y. De Novaes, and J. C. Clare, “A stationary reference
frame current control for a multi-level H-bridge power converter for universal and flexible
power management in future electricity network,” IEEE Power Electron. Spec. Conf., pp.
3943–3949, 2008.
[176] M. Ciobotaru, F. Iov, S. Bifaretti, and P. Zanchetta, “Short-circuit analysis of the
UNIFLEX-PM using stationary and natural reference frame control,” EPE J. Eur. Power
Electron. Drives, vol. 19, no. December, pp. 42–50, 2009.
[177] P. C. Loh, G. H. Bode, and P. Tan, “Modular hysteresis current control of hybrid
multilevel inverters,” IEE Proc. Electr. Power Appl., pp. 1–8, 2005.
[178] A. Shukla, A. Ghosh, and A. Joshi, “Hysteresis Current Control Operation of
Flying Capacitor Multilevel Inverter and Its Application in Shunt Compensation of
Distribution Systems,” IEEE Trans. Power Del., vol. 22, no. 1, pp. 396–405, 2007.
[179] A. Shukla, A. Ghosh, and A. Joshi, “Improved Multilevel Hysteresis Current
Regulation and Capacitor Voltage Balancing Schemes for Flying Capacitor Multilevel
Inverter,” IEEE Trans. Power Electron., vol. 23, no. 2, pp. 518–529, 2008.
[180] R. Gupta, A. Ghosh, and A. Joshi, “Multiband Hysteresis Modulation and
Switching Characterization for Sliding-Mode-Controlled Cascaded Multilevel Inverter,”
IEEE Trans. Ind. Electron., vol. 57, no. 7, pp. 2344–2353, 2010.
[181] A. Dey, P. P. Rajeevan, R. Ramchand, K. Mathew, and K. Gopakumar, “A Space
Vector-Based Hysteresis Current Controller for a General n -Level Inverter-Fed Drive
With Nearly Constant Switching Frequency Control,” IEEE Trans. Ind. Electron., vol. 60,
no. 5, pp. 1989–1998, 2013.
[182] B. K. Bose, “Neural Network Applications in Power Electronics and Motor Drives
— An Introduction and Perspective,” IEEE Trans. Ind. Electron., vol. 54, no. 1, pp. 14–
33, 2007.
[183] C. Cecati, F. Ciancetta, and P. Siano, “A Multilevel Inverter for Photovoltaic
Systems With Fuzzy Logic Control,” IEEE Trans. Ind. Electron., vol. 57, no. 12, pp.
4115–4125, 2010.
[184] C. Xu and Y. C. Shin, “A Multilevel Fuzzy Control Design for a Class of Multi-
input Single-Output Systems,” IEEE Trans. Ind. Electron., vol. 59, no. 8, pp. 3113–3123,
Aug. 2012.
[185] D. Casini, M. Marchesoni, and L. Puglisi, “Sliding Mode Multilevel Control for
Improved Performances in Power Conditioning Systems,” IEEE Trans. Power Electron.,
vol. 10, no. 4, pp. 453–463, 1995.
[186] S. Kouro, P. Cortes, R. Vargas, U. Ammann, and J. Rodríguez, “Model predictive
control—A simple and powerful method to control power converters,” IEEE Trans. Ind.
Electron., vol. 56, no. 6, pp. 1826–1838, 2009.
173
[187] J. Rodríguez and M. P. Kazmierkowski, “State of the Art of Finite Control Set Model
Predictive Control in Power Electronics,” IEEE Trans. Ind. Informat., vol. 9, no. 2, pp.
1003–1016, 2013.
[188] J. Barros, F. Silva, and E. Jesus, “Fast predictive optimal control of NPC multilevel
converters,” IEEE Trans. Ind. Electron., vol. 60, no. 2, pp. 619–627, 2013.
[189] F. Villarroel, J. R. Espinoza, C. A. Rojas, J. Rodríguez, M. Rivera, and D. Sbárbaro,
“Multi-objective Switching State Selector for Finite-States Model Predictive Control
Based on Fuzzy Decision Making in a Matrix Converter,” IEEE Trans. Ind. Electron., vol.
60, no. 2, pp. 589–599, 2013.
[190] S. Bifaretti, P. Zanchetta, A. J. Watson, L. Tarisciotti, and J. C. Clare, “Advanced
power electronic conversion and control system for universal and flexible power
management,” IEEE Trans. Smart Grid, vol. 2, no. 2, pp. 231–243, 2011.
[191] L. Malesani, P. Mattavelli, and S. Buso, “Robust dead-beat current control for PWM
rectifiers and active filters,” IEEE Trans. Ind. Appl., vol. 35, no. 3, pp. 613–620, 1998.
[192] S. Saggini, W. Stefanutti, E. Tedeschi, and P. Mattavelli, “Digital Deadbeat Control
Tuning for dc-dc Converters Using Error Correlation,” IEEE Trans. Power Electron., vol.
22, no. 4, pp. 1566–1570, Jul. 2007.
[193] M. A. Perez, J. Rodríguez, E. J. Fuentes, and F. Kammerer, “Predictive Control of
AC– AC Modular Multilevel Converters,” IEEE Trans. Ind. Electron., vol. 59, no. 7, pp.
2832–2839, Jul. 2012.
[194] J. M. Espi, J. Castelló, R. García-Gil, G. Garcera, and E. Figueres, “An adaptive
robust predictive current control for three-phase grid-connected inverters,” IEEE Trans.
Ind. Electron., vol. 58, no. 8, pp. 3537–3546, 2011.
[195] P. Cortés, A. Wilson, S. Kouro, J. Rodríguez, and H. Abu-Rub, “Model predictive
control of multilevel cascaded H-bridge inverters,” IEEE Trans. Ind. Electron., vol. 57, no.
8, pp. 2691–2699, 2010.
[196] P. Cortés, J. Rodríguez, P. Antoniewicz, and M. P. Kazmierkowski, “Direct Power
Control of an AFE Using Predictive Control,” IEEE Trans. Power Electron., vol. 23, no. 5,
pp. 2516–2523, 2008.
[197] P. Zanchetta and D. Gerry, “Predictive current control for multilevel active rectifiers
with reduced switching frequency,” IEEE Trans. Ind. Electron., vol. 55, no. 1, pp. 163–
172, 2008.
[198] P. Cortes and J. Rodríguez, “Predictive current control strategy with imposed load
current spectrum,” IEEE Trans. Power Electron., vol. 23, no. 2, pp. 612–618, 2008.
[199] K. H. Ahmed, A. M. Massoud, S. J. Finney, and B. W. Williams, “A Modified
Stationary Reference Frame-Based Predictive Current Control With Zero Steady-State
Error for LCL Coupled Inverter-Based Distributed Generation Systems,” IEEE Trans. Ind.
Electron., vol. 58, no. 4, pp. 1359–1370, Apr. 2011.
174
[200] G. Abad, M. Á. Rodríguez, and J. Poza, “Two-Level VSC Based Predictive Direct
Torque Control of the Doubly Fed Induction Machine With Reduced Torque and Flux
Ripples at Low Constant Switching Frequency,” IEEE Trans. Power Electron., vol. 23, no.
3, pp. 1050–1061, 2008.
[201] Y. Zhang, W. Xie, Z. Li, and Y. Zhang, “Model Predictive Direct Power Control of
a PWM Rectifier With Duty Cycle Optimization,” IEEE Trans. Power Electron., vol. 28,
no. 11, pp. 5343–5351, 2013.
[202] P. Antoniewicz and M. P. Kazmierkowski, “Virtual-Flux-Based Predictive Direct
Power Control of AC/DC Converters With Online Inductance Estimation,” IEEE Trans.
Ind. Electron., vol. 55, no. 12, pp. 4381–4390, Dec. 2008.
[203] J. Rodríguez, J. S. Lai, and F. Z. Peng, “Multilevel inverters: a survey of topologies,
controls, and applications,” IEEE Trans. Ind. Electron., vol. 49, no. 4, pp. 724–738, 2002.
[204] L. G. Franquelo and J. Rodríguez, “The age of multilevel converters arrives,” IEEE
Trans. Ind. Electron., no. June, pp. 28–39, 2008.
[205] M. Kazmierkowski, L. Franquelo, J. Rodriguez, M. Perez, and J. Leon, “High
Performance Motor Drives,” IEEE Ind. Electron. Mag., vol. 5, no. 3, pp. 6–26, Sep. 2
[206] S. Mekhilef and M. N. Abdul Kadir, “Novel Vector Control Method for Three-Stage
Hybrid Cascaded Multilevel Inverter,” IEEE Trans. Ind. Electron., vol. 58, no. 4, pp. 1339–
1349, Apr. 2011.
[207] Liu Y, Escobar-Mejia A, Farnell C, et al. (2014) Modular multilevel converter with
high-frequency transformers for interfacing hybrid DC and AC microgrid systems. 5th
IEEE International Symposium on Power Electronics for Distributed Generation Systems
(PEDG). IEEE, 1–6.
[208] Ponraj T, George A (2014) A solid state transformer integrating distributed
generation and storage. Int J Innov Res Comput Commun Eng 2: 4029–4035.
[209] Sun Y, Liu J, Li Y, et al. (2016) Research on voltage and switching balance control
for cascaded power electronic transformer under hybrid PWM modulation. 8th IEEE
International Power Electronics and Motion Control Conference (IPEMC-ECCE Asia).
IEEE, 2033–2038.
[210] .Liu B, Zha Y, Zhang T, et al. (2016) Solid state transformer application to grid
connected photovoltaic inverters. International Conference on Smart Grid and Clean
Energy Technologies (ICSGCE ). IEEE, 248–251.
[211] Wang F, Huang A, Wang G, et al. (2012) Feed-forward control of solid-state
transformer. 27th Annual IEEE Applied Power Electronics Conference and Exposition
(APEC). IEEE, 1153–1158.
[212] Malan WL, Vilathgamuwa DM, Walker GR, et al. (2016) A three port resonant solid
state transformer with minimized circulating reactive currents in the high frequency link.
IEEE Annual Southern Power Electronics Conference (SPEC). IEEE, 1–6.
175
[213] Saghaleini M, Farhangi S (2007) Distributed power supply with power factor
correction: A solution to feed all modules in power electronic transformers. 7th
International Conference on Power Electronics (ICPE). IEEE, 1225–1229.
[214] Saghaleini M, Hekmati A, Farhangi S (2007) An advanced distributed power supply
for power electronic transformers. 33rd Annual Conference of the IEEE Industrial
Electronics Society (IECON). IEEE, 2038–2043.
[215] Yun HJ, Kim HS, Ryu MH, et al. (2015) A simple and practical voltage balance
method for a solid-state transformer using cascaded H-bridge converters. 9th International
Conference on Power Electronics (ICPE). IEEE, 2415–2420.
[216] Zengin S, Boztepe M (2015) Trapezoid current modulated DCM AC/DC DAB
converter for two-stage solid state transformer. 9th International Conference on Electrical
and Electronics Engineering (ELECO). IEEE, 634–638.
[217] Guerra G, Martinez-Velasco JA (2017) A solid state transformer model for power
flow calculations. Int J Electr Power Energy Syst 89: 40–51.
[218] Zhao T, Zeng J, Bhattacharya S, et al. (2009) An average model of solid state
transformer for dynamic system simulation. IEEE Power and Energy Society General
Meeting. IEEE, 1–8.
[219] Gonzalez-Agudelo D, Escobar-Mejia A, Ramirez-Murrillo H (2016) Dynamic model
of a dual active bridge suitable for solid state transformers. 13th International Conference
on Power Electronics (CIEP). IEEE, 350–355.
[220] Busada C, Chiacchiarini H, Jorge SG, et al. (2017) Modeling and control of a medium
voltage three-phase solid-state transformer. 11th IEEE International Conference on
Compatibility, Power Electronics and Power Engineering (CPE-POWERENG). IEEE,
556–561.
[221] Ramachandran V, Kuvar A, Singh U, et al. (2014) A system level study employing
improved solid state transformer average models with renewable energy integration. IEEE
Power and Energy Society General Meeting. IEEE, 1–5.
[222] Parimi M, Monika M, Rane M, et al. (2016) Dynamic phasor-based small-signal
stability analysis and control of solid state transformer. 6th IEEE International Conference
on Power Systems (ICPS). IEEE, 1–6.
[223] Hunziker NS (2016) Solid-state transformer modeling for analyzing its application
in distribution grids. PCIM Europe; International Exhibition and Conference for Power
Electronics, Intelligent Motion, Renewable Energy and Energy Management. IEEE, 2167–
2174.
[224] Adabi ME, Martinez-Velasco JA, Alepuz S (2017) Modeling and simulation of a
MMC-based solid-state transformer. Electr Eng, 1–13.
[225] Jiang Y, Breazeale L, Ayyanar R, et al. (2012) Simplified solid state transformer
modeling for real time digital simulator (RTDS). IEEE Energy Conversion Congress and
Exposition (ECCE). IEEE, 1447–1452.
176
[226] Mo R, Mao C, Lu J, et al. (2012) Three-stage solid state transformer modeling
through real time digital simulation with controller hardware-in-the-loop. 7th International
Power Electronics and Motion Control Conference (IPEMC). IEEE, 1116–1119.
[227] Wang F, Lu X, Wang W, et al. (2012) Development of distributed grid intelligence
platform for solid state transformer. 3rd IEEE International Conference on Smart Grid
Communications (SmartGridComm). IEEE, 481–485.
[228] Tatcho P, Li H, Jiang Y, et al. (2013) A novel hierarchical section protection based
on the solid state transformer for the future renewable electric energy delivery and
management (FREEDM) system. IEEE T Smart Grid 4: 1096–1104.
[229] Nila-Olmedo N, Mendoza-Mondragon F, Espinosa-Calderon A, et al. (2016) ARM
+ FPGA platform to manage solid-state-smart transformer in smart grid application.
International Conference on ReConFigurable Computing and FPGAs. IEEE, 1–6.
[230] Y. Al-Shawesh, S.C.Lim, M. Nujaim, “Analysis of the Design Calculations for
Electrical Earthing Systems”, International Review of Electrical Engineering, Apr. 2021.
https://doi.org/10.15866/iree.v16i2.16839
[231] S.C. Lim, Y. Al-Shawesh, “A Systematic Method for the Design of Earthing
System for Low-voltage Installations”, Journal of Recent Technology and Engineering
(IJRTE), vol.8, October 2019, pp. 12 – 15. ISSN: 2277-3878.
https://doi.org/10.35940/ijrte.c1003.1083s19
[232] Yeong Yoo, Yousef Al-Shawesh, and Alain Tchagang, “Coordinated Control
Strategy and Validation of Vehicle-to-Grid for Frequency Control,” Energies, vol. 14, no.
9, p. 2530, Apr. 2021.
https://doi.org/10.3390/en14092530
[233] T. He, D. D.-C. Lu, M. Wu, Q. Yang, T. Li, and Q. Liu, “Four-Quadrant Operations
of Bidirectional Chargers for Electric Vehicles in Smart Car Parks: G2V, V2G, and V4G,”
Energies, vol. 14, no. 1, p. 181, Dec. 2020.
[234] Toronto Hydro, Accessed: September 2020. [Online]. Available:
https://www.torontohydro.com/documents/20143/5652827/condition-of-service-
customer-owned-substation-requirements-revision-11.pdf/4a0bd77e-7a72-dae6-c3e4-
f68f93c73da5?t=1577737859217
[235] Tarek Abdul-Galil, et. al., “Protection Coordination Planning with Distributed
Generation”, Natural Resources Canada (NRCan), June 2007, Available Online:
https://www.nrcan.gc.ca/sites/www.nrcan.gc.ca/files/canmetenergy/files/pubs/2007-
149e.pdf
[236] IEEE Standards, IEEE Recommended Practices and Requirements for Harmonic
Control in Electrical Power Systems IEEE Recommended Practices, 1992.
[237] R. Teodorescu, M. Liserre, and P. Rodríguez, Grid Converters for Photovoltaic and
Wind Power Systems, vol. 5, no. 2. Chichester, UK: John Wiley & Sons, Ltd, 2011, pp.
289 – 312.
177
[238] Khaled h. Ahmed, S. J. Finney, and Barry w. Williams, “Passive Filter Design for
Three Phase Inverter Interfacing in Distributed Generation,” vol. 8, no. 2, pp. 49–58, 2007.
[239] J. Rodriguez, L. G. Franquelo, S. Kouro, J. I. Leon, R. C. Portillo, M. A. M. Prats,
and M. A. Perez, “Multilevel Converters: An Enabling Technology for High-Power
Applications,” Proc. IEEE, vol. 97, no. 11, pp. 1786–1817, Nov. 2009.
[240] P. T. Krein, R. S. Balog, and M. Mirjafari, “Minimum Energy and Capacitance
Requirements for Single-Phase Inverters and Rectifiers Using a Ripple Port,” IEEE Trans.
Power Electron., vol. 27, no. 11, pp. 4690–4698, Nov. 2012.
[241] S. Sirisukprasert, “The Modeling and Control of a Cascaded-Multilevel Converter
Based STATCOM The Modeling and Control of a Cascaded-Multilevel Converter-Based
STATCOM,” 2004.
[242] N. SCHlBLl, “Symmetrical multilevel converters with two quadrant DC-DC
feeding,” ECOLE POLYTECHNIQUE FEDERALE DE LAUSANNE, 2000.
[243] Iunnissi, Sebastian Andre Rivera, “Architecture and control of an electric vehicle
charging station using a bipolar DC bus”, PhD Thesis, Ryerson University, 2016.
[244] X. Wang and J. A. Cooper, “High-voltage n-channel IGBTs on freestanding 4H-SiC
epilayers,” IEEE Trans. Electron Devices, vol. 57, no. 2, pp. 511–515, February 2010. DOI:
10.1109/TED.2009.2037379
[245] S. H. Ryu, C. Capell, L. Cheng, C. Jonas, A. Gupta, M. Donofrio, J. Clayton, M.
O’Loughlin, A. Burk, D. Grider, A. Agarwal, J. Palmour, A. Hefner, and S. Bhattacharya,
“High performance, ultra high voltage 4H-SiC IGBTs,” in Proc. IEEE Energy Conversion
Congr. and Expo (ECCE USA), Raleigh, NC, USA, September 2012, pp. 3603–3608. DOI:
10.1109/ECCE.2012.6342311
[246] T. Zhao, L. Yang, J. Wang, and A. Q. Huang, “270 kVA solid state transformer based
on 10 kV SiC power devices,” in Proc. IEEE Electric Ship Technologies Symp., Arlington,
VA, USA, May 2007, pp. 145–149. DOI: 10.1109/ESTS.2007.372077
[247] K. Hatua, S. Dutta, A. Tripathi, S. Baek, G. Karimi, and S. Bhattacharya,
“Transformer less intelligent power substation design with 15kV SiC IGBT for grid
interconnection,” in Proc. IEEE Energy Conversion Congr. and Expo. (ECCE USA),
Phoenix, AZ, USA, September 2011, pp. 4225–4232. DOI: 10.1109/ECCE.2011.6064346
[248] D. Grider, “Recent advances in sic mosfet technology,” Jun 2016.
[249] GeneSic Semiconductors, Accessed: October 2020. [Online]. Available:
https://www.genesicsemi.com/sic-mosfet/G2R50MT33K/G2R50MT33K.pdf
[250] C. Ionita, M. Nawaz, K. Ilves, and F. Iannuzzo, “Comparative assessment of
3.3kv/400a sic mosfet and si igbt power modules,” in 2017 IEEE Energy Conversion
Congress and Exposition (ECCE), Oct 2017, pp. 1343–1349.
[251] J. Dodge, “Reduce circuit zapping from cosmic radiation,” Power Electronics
Technology, pp. 20–26, September 2007.
178
[252] N. Kaminski and A. Kopta, “Failure rates of HiPak modules due to cosmic rays (ABB
application note 5SYA 2042-04),” 2011.
[253] S. Dieckerhoff, S. Bernet, and D. Krug, “Power loss-oriented evaluation of high
voltage IGBTs and multilevel converters in transformerless traction applications,” IEEE
Trans. Power Electron., vol. 20, no. 6, pp. 1328–1336, November 2005. DOI:
10.1109/TPEL.2005.857534
[254] S. Thomas, M. Stieneker, and R. W. De Doncker, “Development of a modular high-
power converter system for battery energy storage systems,” in Proc. 14th Europ. Power
Electron. and Appl. Conf. (EPE), Birmingham, UK, August 2011.
[255] B. Mwinyiwiwa, Z. Wolanski, and B.-T. Ooi, “Microprocessor implemented SPWM
for multiconverters with phase-shifted triangle carriers” IEEE Trans. Ind. Appl., vol. 34,
no. 3, pp. 487–494, May 1998. DOI: 10.1109/28.673718
[256] J. Rodriguez, J.-S. Lai, and F. Z. Peng, “Multilevel inverters: A survey of topologies,
controls, and applications,” IEEE Trans. Ind. Electron., vol. 49, no. 4, pp. 724–738, August
2002. DOI: 10.1109/TIE.2002.801052
[257] M. März, A. Schletz, B. Eckardt, S. Egelkraut, and H. Rauh, “Power electronics
system integration for electric and hybrid vehicles,” in Proc. 6th Int. Integrated Power
Electron. Systems Conf. (CIPS), Nuremberg, Germany, March 2010.
[259] J. E. Huber and J. W. Kolar, "Optimum Number of Cascaded Cells for High-Power
Medium-Voltage AC–DC Converters," in IEEE Journal of Emerging and Selected Topics
in Power Electronics, vol. 5, no. 1, pp. 213-232, March 2017, doi:
10.1109/JESTPE.2016.2605702.
[260] H. Ertl, J. W. Kolar, and F. C. Zach, “Analysis of a multilevel multicell switch-mode
power amplifier employing the “flying-battery” concept,” IEEE Trans. Ind. Electron., vol.
49, no. 4, pp. 816–823, August 2002. DOI: 10.1109/TIE.2002.801056
[261] P. C. Sen, “Principles of Electric Machines and Power Electronics,” 2nd ed., John
Wiley & Sons, Ltd, 1997.
[262] B. Zhao, Q. Yu, and W. Sun, “Extended-Phase-Shift Control of Isolated Bidirectional
DC–DC Converter for Power Distribution in Microgrid,” IEEE Trans. Power Electron.,
vol. 27, no. 11, pp. 4667–4680, Nov. 2012.
[263] M. N. Kheraluwala, R. W. Gascoigne, D. M. Divan, and E. D. Baumann,
“Performance characterization of a high-power dual active bridge DC-to-DC converter,”
IEEE Trans. Ind. Appl., vol. 28, no. 6, pp. 1294–1301, 1992.
[264] C. M. H. Bai and C. W. S. Gargies, “Operation , design and control of dual H-bridge-
based isolated bidirectional DC – DC converter,” vol. 1, no. 4, pp. 507–517, 2008.
[265] S. Inoue and H. Akagi, “A Bidirectional DC–DC Converter for an Energy Storage
System With Galvanic Isolation,” IEEE Trans. Power Electron., vol. 22, no. 6, pp. 2299–
2306, Nov. 2007.
179
[266] R. T. Naayagi, A. J. Forsyth, and R. Shuttleworth, “High-Power Bidirectional DC–
DC Converter for Aerospace Applications,” IEEE Trans. Power Electron., vol. 27, no. 11,
pp. 4366–4379, Nov. 2012.
[267] G. Ortiz, J. Biela, D. Bortis, and J. W. Kolar, “1 Megawatt, 20 kHz, isolated,
bidirectional 12kV to 1.2kV DC-DC converter for renewable energy applications,” in The
2010 International Power Electronics Conference - ECCE ASIA -, 2010, pp. 3212–3219.
[268] G. G. Oggier, G. O. GarcÍa, and A. R. Oliva, “Switching Control Strategy to
Minimize Dual Active Bridge Converter Losses,” IEEE Trans. Power Electron., vol. 24,
no. 7, pp. 1826– 1838, Jul. 2009.
[269] R. L. Steigerwald, R. W. De Doncker, and H. Kheraluwala, “A comparison of high-
power DC-DC soft-switched converter topologies,” IEEE Trans. Ind. Appl., vol. 32, no. 5,
pp. 1139– 1145, 1996.
[270] H. Akagi and R. Kitada, “Control and Design of a Modular Multilevel Cascade BTB
System Using Bidirectional Isolated DC/DC Converters,” IEEE Trans. Power Electron.,
vol. 26, no. 9, pp. 2457–2464, Sep. 2011.
[271] S. Inoue and H. Akagi, “A Bidirectional Isolated DC–DC Converter as a Core Circuit
of the Next-Generation Medium-Voltage Power Conversion System,” IEEE Trans. Power
Electron., vol. 22, no. 2, pp. 535–542, Mar. 2007.
[272] The Automotive Research Association of India, “AUTOMOTIVE INDUSTRY
STANDARD for Electric Vehicle Conductive DC Charging System”, January 2018.
Available Online:
morth.gov.in/sites/default/files/ASI/320201825106PMAIS_138_Part_2_F.pdf
[273] Bender GmbH & Co. KG, “Electrical safety for e-mobility,” Technical Brochure,
2014, Accessed: September 2020. [Online]. Available:
https://www.benderinc.com/fileadmin/content/Products/b/e/Emobility/EV%20Brochure_
10.16.19.pdf
[274] R. W. A. A. De Doncker, D. M. Divan, and M. H. Kheraluwala, “A three-phase soft-
switched high-power-density DC/DC converter for high-power applications,” IEEE Trans.
Ind. Appl., vol. 27, no. 1, pp. 63–73, 1991.
[275] S. Inoue and H. Akagi, “A Bidirectional Isolated DC–DC Converter as a Core Circuit
of the Next-Generation Medium-Voltage Power Conversion System,” IEEE Trans. Power
Electron., vol. 22, no. 2, pp. 535–542, Mar. 2007.
[276] Datasheet of NCR18650GA Lithium-ion Battery, Available at:
https://industrial.panasonic.com/ww/products/pt/lithium-ion/models. Accessed, Oct 2020.
[277] O. Tremblay, and L. Dessaint. “Experimental validation of a battery dynamic model
for EV applications.” World Electric Vehicle Journal 3, no. 2, pp. 289-298, 2009.
[278] S. N. Motapon, A. Lupien-Bedard, L.-A. Dessaint, H. Fortin-Blanchette, and K. Al-
Haddad, “A Generic Electrothermal Li-ion Battery Model for Rapid Evaluation of Cell
Temperature Temporal Evolution,” IEEE Transactions on Industrial Electronics, vol. 64,
no. 2, pp. 998–1008, 2017.
180
[279] O. Tremblay and L. Dessaint, “A Generic Battery Model for the Dynamic Simulation
of Hybrid Electric Vehicles”, Vehicle Power and Propulsion Conference 2007, IEEE 2008.
[280] Youssef, H. “A Control Strategy for a Microgrid Integrated with Multiple Solar-PV
Units and a Large-Scale Battery Energy Storage System”, University of Toronto, 2018.
[281] V. Monteiro, J. G. Pinto and J. L. Afonso, "Operation Modes for the Electric
Vehicle in Smart Grids and Smart Homes: Present and Proposed Modes," in IEEE
Transactions on Vehicular Technology, vol. 65, no. 3, pp. 1007-1020, March 2016, doi:
10.1109/TVT.2015.2481005.
[282] Felix Thomas Jauch, “Medium Voltage AC-DC Converter Systems for Ultra-Fast
Charging Stations for Electric Vehicles”, PhD Thesis, ETH Zurich, 2016.
[283] S. Yang, Q. Lei, F. Z. Peng, and Z. Qian, “A Robust Control Scheme for Grid-
Connected Voltage-Source Inverters,” IEEE Transactions on Industrial Electronics, vol.
58, no. 1, pp. 202–212, Jan. 2011.
[284] Uniflex-PM Project, “D5.1 Report on Control Strategies,” Accessed: November
2020. [Online]. Available: http://www.eee.nott.ac.uk/uniflex/Deliverables.htm, vol.
019794, pp. 1–162, 2006.
[285] D. N. Zmood, S. Member, D. G. Holmes, and G. H. Bode, “Frequency-Domain
Analysis of Three-Phase Linear Current Regulators,” vol. 37, no. 2, pp. 601–610, 2001.
[286] R. Teodorescu, F. Blaabjerg, M. Liserre, and P. C. Loh, “Proportional-resonant
controllers and filters for grid-connected voltage-source converters,” IEE Proceedings -
Electric Power Applications, vol. 153, no. 5, p. 750, 2006.
[286] S. Golestan, M. Monfared, F. D. Freijedo, and J. M. Guerrero, “Dynamics
Assessment of Advanced Single-Phase PLL Structures,” IEEE Trans. Ind. Electron., vol.
60, no. 6, pp. 2167–2177, 2013.
[287] C. Henrique, R. R. Pereira, L. Eduardo, G. Lambert-Torres, B. K. Bose, and S. U.
Ahn, “A Digital PLL Scheme for Three-Phase System Using Modified Synchronous
Reference Frame,” IEEE Trans. Ind. Electron., vol. 57, no. 11, pp. 3814–3821, 2010.
[288] F. D. Freijedo, A. G. Yepes, Ó. López, A. Vidal, and J. Doval-Gandoy, “Three-Phase
PLLs With Fast Postfault Retracking and Steady-State Rejection of Voltage Unbalance and
Harmonics by Means of Lead Compensation,” IEEE Trans. Power Electron., vol. 26, no.
1, pp. 85–97, Jan. 2011.
[289] F. Liccardo, P. Marino, and G. Raimondo, “Robust and Fast Three-Phase PLL
Tracking System,” IEEE Trans. Ind. Electron., vol. 58, no. 1, pp. 221–231, Jan. 2011.
[290] H. Kim and H. Akagi, “The instantaneous power theory on the rotating pqr reference
frames,” Int. Conf. Power Electron. Drives Syst., no. July, pp. 422–427, 1999.
[291] H. Akagi, S. Ogasawara, and H. Kim, “The theory of instantaneous power in three-
phase four-wire systems: a comprehensive approach,” IEEE Conf. Rec. Ind. Appl. Conf.,
1999.
181
[292] Rodriguez and J. Pou, “Decoupled double synchronous reference frame PLL for
power converters control,” IEEE Trans. Power Electron., vol. 22, no. 2, pp. 584–592, 2007.
[293] R. W. Erickson and D. Maksimovic, Fundamentals of Power Electronics. Springer,
2001, pp. 189, 190, 198, 213–221.
[294] S. Buso and P. Mattavelli, Digital Control in Power Electronics, vol. 1, no. 1. 2006,
pp. 38– 49.
[295] D. Czarkowski, “DC/DC converter,” in Power Electronics Handbook (Third
Edition), 2011, pp. 249–263.
[296] P. C. Sen, “A general unified large signal model for current programmed DC-to-DC
converters,” IEEE Trans. Power Electron., vol. 9, no. 4, pp. 414–424, Jul. 1994.
[297] S. Sirisukprasert, A. Q. Huang, and J.-S. Lai, “Modeling, analysis and control of
cascaded-multilevel converter-based STATCOM,” in 2003 IEEE Power Engineering
Society General Meeting (IEEE Cat. No.03CH37491), pp. 2561–2568
[298] S. Sirisukprasert, “The Modeling and Control of a Cascaded-Multilevel Converter-
Based STATCOM The Modeling and Control of a Cascaded-Multilevel Converter-Based
STATCOM,” 2004.
[299] P. C. Krause, Analysis of electric machinery. McGraw-Hill, 1986, p. 111.
[300] M. H. Bai and C. W. S. Gargies, “Operation, design and control of dual H-bridge
based isolated bidirectional DC – DC converter,” vol. 1, no. 4, pp. 507–517, 2008.
[301] J. J. D’Azzo and C. H. Houpis, Linear control system analysis and design:
conventional and modern. 2007, p. Chapter 8.
[302] Y. Hu, J. Cheng, Y. Zhou, and G. Chen, “Control strategy of cascaded multilevel
converter based on dual active bridge for wind energy conversion system,” in IECON
2017-43rd Annual Conference of the IEEE Industrial Electronics Society, IEEE, 2017, pp.
2419–2424.
[303] L. Maharjan, S. Inoue, and H. Akagi, “A transformerless energy storage system based
on a cascade multilevel pwm converter with star configuration,” IEEE Transactions on
Industry Applications, vol. 44, no. 5, pp. 1621–1630, 2008.
[304] Li, Y. Wang, and B. Q. Li, “Generalized theory of phase-shifted carrier PWM for
cascaded h-bridge converters and modular multilevel converters,” IEEE Journal of
Emerging and Selected Topics in Power Electronics, vol. 4, no. 2, pp. 589–605, 2015.
[305] H. Akagi, “Classification, terminology, and application of the modular multilevel
cascade converter (mmcc),” IEEE Transactions on power electronics, vol. 26, no. 11, pp.
3119–3130, 2011.
[306] Y. Wang, S. W. H. de Haan, and J. a. Ferreira, “Optimal operating ranges of three
modulation methods in dual active bridge converters,” in 2009 IEEE 6th International
Power Electronics and Motion Control Conference, 2009, vol. 3, pp. 1397–1401.
182
[307] N. Schibli, “Symmetrical multilevel converters with two quadrant DC-DC feeding,”
EPFL, 2000.
[308] R. W. A. A. De Doncker, D. M. Divan, and M. H. Kheraluwala, “A three-phase
soft-switched high-power-density DC/DC converter for high-power applications,” IEEE
Trans. Ind. Appl., vol. 27, no. 1, pp. 63–73, 1991.
[309] O. Veneri, “Technologies and Applications for Smart Charging of Electric and Plug-
in Hybrid Vehicles.” Springer Nature, 2016.
[310] S. Dusmez, A. Cook, and A. Khaligh, “Comprehensive analysis of high-quality
power converters for level 3 off-board chargers,” in Vehicle Power and Propulsion
Conference (VPPC), 2011 IEEE, pp. 1–10, IEEE, 2011.
[311] GeneSiC MOSFET Data Sheet, Accessed: April 2021. [Online]. Available:
https://www.genesicsemi.com/sic-mosfet/G2R120MT33J/G2R120MT33J.pdf
[312] GeneSiC MOSFET Data Sheet, Accessed: April 2021. [Online]. Available:
https://www.genesicsemi.com/sic-mosfet/bare-chip/G2R50MT33-CAL/G2R50MT33-
CAL.pdf
[313] 3300 V SiC MOSEFT, Accessed: April 2021. [Online]. Available:
https://www.newark.com/genesic-semiconductor/g2r120mt33j/3300v-120m-to-263-7-
g2r-sic-mosfet/dp/89AH0975
[314] Semiconductors, Alibaba e-Commerce, Accessed: April 2021. [Online]. Available:
https://www.alibaba.com/
[315] Passive Components, Newark e-Commerce, Accessed: April 2021. [Online].
Available: https://www.newark.com/w/c/passive-components/capacitors
[316] Passive Components, Mouser e-Commerce, Accessed: April 2021. [Online].
Available: https://www.mouser.com/Passive-Components
183
APPENDICES
Appendix A: Framework of the Research Study
184
Appendix B: Flowchart of the Systematic Design Procedure of the CHB
185
Appendix C: Optimisation Flowchart for the Selection of fCHB and LCHB
186
Appendix D: Flowchart of the Systematic Design Procedure of the DAB
187
Appendix E: Design Process of the Control System for the SST
188
Appendix F: Flowchart of the CCCV Charging Method