Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
1
Modeling of Ontario Special Protection Systems
in Contingency Analysis
Yinhua Guo, Vivian Cheuk
Ontario Grid Control Centre
Hydro One Networks • Transmission Company in Ontario
– 98% of Ontario transmission system, 30,000km HV circuits
– Interconnect with New York, Michigan, Minnesota, Manitoba, and Quebec (asynchronous)
• Largest Distribution Utility in Ontario
– 123,000km low voltage distribution lines
– Serving 1.4 million suburban/rural customers
– Extensive distributed generation (wind & solar)
2
SPS Deployment in Ontario
• Over 50 SPS Systems in Operation
– Defend system stability, thermal & voltage limits
• Over 540 SPS Modules
– Over 720 contingency signals & over 3000 logic evaluations
• Over 470 Remedial Control Actions
• Secure Arming Logic
– Multi-level blocking switches & selection switches
4
SPS Simulation- Contingency Detection
• Signal Types
– Status based
– Protective relay trip signals
– Analog value based (e.g., load shedding)
• Contingency Condition Derivations
– Over 720 SPS contingencies
– Over 3000 logic evaluations
7
SPS Simulation- Control Actions
• Generation Rejection
• Load Rejection
• Generation/HVDC Runback
• Capacitor/Reactor Switching
• Breaker Trip/Close
• Group (generation, load, CB) Rejection
8
SPS Simulation- Arming Logic • Selection & Blocking Switches
– Detailed logic for conditional arming status
• Staged Tripping
– Time staged control actions
– Violation level staged control actions
• Trip Supervision/Interlocking (analog, status)
– Local switch/relay to block GR if generation < threshold
– Load rejection: if Vpresent < V < Vthreshold
9
Other Protections Modeled as SPS
• Over Load Protection
– Transformer 2pu protection
• Under Voltage Load Shedding
– Lower voltage threshold & voltage presence check
• Under/Over Voltage Capacitor/Reactor Switching
• Line-end Open
11
Transformer 2pu Protection
– Staged tripping of loads in 4.5”, 7.5”, 9.5”
12
– Over current based: I > 2*I_rated
RTNET & RTCA Sequence • RTNET every 30 sec
– State estimator
– Thermal limit calculation
– SPS base update
• RTCA every 3 min
– About 4400 contingency cases
– CA redefinitions
– Screening/full processing
13
SPS & CA Redefinition
• Dynamically Expand CA Outages at CB Level
• Simulate Protective Relay Actions
– Interlock bypass switches considered
• Transfer Trip for LEO Protection
• SPS Remedial Actions Incorporated
• Cascading Outages: iterative simulation of interactions among SPS, LEO, overload, 59/27 voltage relays
14
SPS Results in CA
• For each SPS Module
– Total generation rejection selected
– Total load rejection selected
• For each Contingency Case
– SPS modules activated
– SPS control action equipment outages
– SPS control action CB tripped
16
CA/SPS Results Validation
• Verification of SPS Simulation
– Simulated vs. expected results
– Simulated results against real events
• Verification of CA Solutions
– SE solution against SCADA measured values
– CA solution against SE/power flow solution
– Pre-outage CA solution against post-outage system state (real time or DTS Replay)
18
Challenges & Experience
• Interactions of Different Control Actions
– Load rejection vs capacitor auto-switching
– Granularity of time stages
• CA Convergence vs SPS Actions
– Powerflow may diverge before load rejection, but analog based overload/undervoltage LR needs solved solution
• SPS Simulation Performance
– Code optimization
19