Standard Time System Tank Container
2009 MODE 10 Page 1 Revision A Tank Container of 20 Revised : 2009-nov
TABLE OF CONTENTS
TABLE OF CONTENTS ............................................................................................................................................ 1
TABLE OF REVISIONS ............................................................................................................................................ 3
CONFIRMATION OF RECEIPT.............................................................................................................................3
GENERAL REMARKS .............................................................................................................................................. 4
0.0 MISCELLANEOUS .............................................................................................................................................. 5
0.1 PREPARATION TIME.............................................................................................................................5 0.2 CLEANING .............................................................................................................................................5 0.3 DECALS AND ISO-MARKING...............................................................................................................6 0.4 MISCELLANEOUS. ................................................................................................................................6 0.5 CHECKING ISO DIMENSION. ...............................................................................................................7
1.0 TOP........................................................................................................................................................................ 8
1.1 TOP CROSSMEMBER -- REPLACEMENT.............................................................................................8 1.2 TOP CROSSMEMBER – SECTIONING. .................................................................................................8 1.3 SUPPORT RAIL -- REPLACEMENT / STRAIGHTENING ......................................................................8 1.4 MANHOLE -- REPLACEMENT ..............................................................................................................9 1.5 GANGWAY – REPLACEMENT / STRAIGHTENING.............................................................................9
2.0 ENDS ................................................................................................................................................................... 10
2.1 END TOP RAIL -- REPLACEMENT......................................................................................................10 2.2 END TOP RAIL – INSERT / STRAIGHTENING....................................................................................10 2.3 END TOP RAIL -- SECTIONING...........................................................................................................10 2.4 END BOTTOM RAIL -- REPLACEMENT. ............................................................................................11 2.5 END BOTTOM RAIL – INSERT / STRAIGHTENING. ..........................................................................11 2.6 END BOTTOM RAIL -- SECTIONING..................................................................................................11 2.7 CORNER POST - REPLACEMENT. ......................................................................................................12 2.8 CORNER POST – INSERT / STRAIGHTENING....................................................................................12 2.9 CORNER CASTING -- REPLACEMENT...............................................................................................12 2.10 SUPPORT RIB PLATE -- REPLACEMENT .........................................................................................13
3.0 SIDES................................................................................................................................................................... 14
3.1 SIDE TOP RAIL -- REPLACEMENT. ....................................................................................................14 3.2 SIDE TOP RAIL – INSERT / STRAIGHTENING. ..................................................................................14 3.3 SIDE TOP RAIL -- SECTIONING. .........................................................................................................14 3.4 SIDE BOTTOM RAIL -- REPLACEMENT. ...........................................................................................15 3.5 SIDE BOTTOM RAIL – INSERT / STRAIGHTENING. .........................................................................15 3.6 SIDE BOTTOM RAIL -- SECTIONING. ................................................................................................15 3.7 SIDE POST -- REPLACEMENT.............................................................................................................16 3.8 SIDE POST -- SECTIONING .................................................................................................................16 3.9 BEARER -- REPLACEMENT ................................................................................................................16 3.10 DIAGONAL BRACE -- REPLACEMENT............................................................................................16
Standard Time System Tank Container
2009 MODE 10 Page 2 Revision A Tank Container of 20 Revised : 2009-nov
4.0 VALVES .............................................................................................................................................................. 17
4.1 BOTTOM VALVE. ................................................................................................................................17 4.2 FOOT VALVE. ......................................................................................................................................17 4.3 REMOTE ASSEMBLY ..........................................................................................................................17 4.4 PRESSURE RELIEF VALVE.................................................................................................................17 4.5 AIR LINE VALVE .................................................................................................................................18 4.6 VALVE BOX .........................................................................................................................................18
5.0 UNDERSTRUCTURE......................................................................................................................................... 19
5.1 BOTTOM CROSSMEMBER -- REPLACEMENT..................................................................................19 5.2 BOTTOM CROSSMEMBER -- SECTIONING.......................................................................................19 5.3 SUPPORT RAIL—REPLACEMENT / STRAIGHTENING ....................................................................19
REQUEST OF CHANGE / NEW STS CODE. ........................................................................................................ 20
Standard Time System Tank Container
December 2001 MODE 10 Page 3 Revision A Tank Container of 20 Revised : 2002-01-23
TABLE OF REVISIONS
Chapter No. Revision No Revision Date Sign. May 2000
TABLE OF CONTENTS A pse TABLE OF REVISION A pse GENERAL REMARKS A pse 0.0 MISCELLANEOUS A pse 1.0 ROOF A pse 2.0 FRONT A pse 3.0 SIDES A pse 4.0 REAR A pse 5.0 DOORS A pse 6.0 FLOOR A pse 7.0 UNDERSTRUCTURE A pse
Confirmation of receipt
As confirmation of receipt of STS mode 10 this page must be returned to CENEQUEMR,TEC with e-mail to [email protected]. Please fill out below and return: Date______________________________ Location __________________________ Department________________________ Confirm hereby receipt of STS, mode 10, December 2001, chapter: All Signed by ________________________(user ID) In case you distribute to other locations/departments please add these locations below: Cc___________________________ Cc___________________________ Cc___________________________ Cc___________________________ Final, if you have any comments, request for codes, request to changes etc., please do not hesitate to apply same on attached sheet, page 31 and forward to CENEMR,TEC on above adress.
Standard Time System Tank Container
December 2001 MODE 10 Page 4 Revision A Tank Container of 20 Revised : 2002-01-23
GENERAL REMARKS All estimations of man-hours are based on high cube containers and include: • MIG welding when joining steel parts. • 3 coat paint system Estimation of repairs which includes use of spare parts such as corner casting – corner post – crossmember – header – sill and top/bottom rail, asume spare parts delivered in correct size and shape. Time for manufacturing of spare parts shall bee included in the price for spare parts. Glossary of terms Replace : Remove damaged part and install new part. Reinstallation : Remove sound part and install same part in previous position. Doubler plate : Plate or angle which add thickness to a part of a structure such as header/sill Reinforcement/ gusset plate : Same as doubler plate Stiffener : Plate which add strength to the formed part of a structure such as header/sill Section : A piece of a structure such as: top/bottom rail – floor – locking rod. Splice : A section which is connected to the structure with plates (e.g. ALU-container) Insert : A part worked in a structure such as: top/bottom rail – corner post – header/sill etc.
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
2009 MODE 10 Page 5 Revision A Tank Container of 20 Revised : 2009-nov
0.0 MISCELLANEOUS
0.1 PREPARATION TIME
0A Job with a process time of less than or equal to 2 hours.
1 0.1 0003
0A Job with a process time of more than 2 hours but less than or equal to 8 hours.
1 0.3 0005
0A Job with a process time of more than 8 hours but less than or equal to 24 hours.
1 0.6 0008
0A Job with a process time of more than 24 hours but less than or equal to 40 hours.
1 0.9 0011
0A Job with a process time of more than 40 hours 1 1.2 0014
*** Total labor cost and hours 9997
*** Total repair shop material 9998
*** Total owner supplied parts 9999
0.2 CLEANING
*** Remove cargo label. per piece 9 0.1 0986
All other cleaning please see chapter “General instruction” in Policy Manual.
*** Partial blasting/repainting (only after CPH’s approval)
2 2.0 0918
*** Mechanical cleaning (scrap off paint/glue) (Only after CPH’s approval)
2 2.0 0919
*** Sales tax (Only after CPH’s approval) 1 0976
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
2009 MODE 10 Page 6 Revision A Tank Container of 20 Revised : 2009-nov
0.3 DECALS AND ISO-MARKING.
8B Replace decal of type 4 letters e.g. MAEU 7 0.2 0951
8B Replace decal of digit type (per 3 digits) 9 0.2 0952
8B Replace ckeck decal 7 0.1 0953
8B Replace U.I.C. decal 2 0.1 0954
8C Replace Star Door Logo 2 0.1 0955
*** Replace Miscellaneous markings 4 0.2 0959
8A Paint marking of Side Star Logo 2 0,7 0961
8A Paint marking of Side Letter 9 0.2 0962
8A Painting repair of part of letter 9 0.1 0963
10.03 Re-install data plate. (per piece) 2 0.2 0985
0.4 MISCELLANEOUS.
Emergency repair. 3 0.5 0802
*** Handling and trucking charge. 2 0.0 0917
10.02 Replace document box 9 0.2 6721
*** Replace temperature gauge 1 0,1 6722
10.05 Weld and paint cuts or cracks. = < 500 9 0.2 7891
> 500 9 0.3 7892
*** Tank presure test 1 M 8100
*** Replace gusset plate. (leased boxes only) 4 0.5 7920
*** Straighten gusset plate. (leased boxes only) 4 0.1 7981
*** Straighten/re-weld gusset plate. (leased boxes only)
4 0.2 7982
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
2009 MODE 10 Page 7 Revision A Tank Container of 20 Revised : 2009-nov
0.5 CHECKING ISO DIMENSION.
5B Checking ISO dimension 4 0.3 9200
(3 measurements - Roof, front and side)
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 8 Revision A Tank Container of 20 Revised : 2002-01-23
1.0 TOP
1.1 TOP CROSSMEMBER -- REPLACEMENT.
4.01 Replace top crossmember 4 0.6 1121
(Remove damaged crossmember --- install new crossmember - masking and painting)
1.2 TOP CROSSMEMBER – SECTIONING.
4.01 Replace top crossmember section. 600 4 0.4 1151
(including masking and painting)
1200 4 0.5 1152
1.3 SUPPORT RAIL -- REPLACEMENT / STRAIGHTENING Support between end top rail and side top rail
4.02 Replace support rail 4 0.4 1221
(Remove damaged support rail --- install new support rail - masking and painting)
*** Straighten support rail 4 0.1 1281
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 9 Revision A Tank Container of 20 Revised : 2002-01-23
1.4 MANHOLE – REPLACEMENT (including masking and painting if necessary)
4.05 Replace Manhole Lid 1 0.3 1321
4.05 Replace Gasket for manhole lid 1 0.3 1322
4.05 Replace Hinge Pin for manhole lid 2 0.2 1323
4.05 Replace Bracket for hinge pin 2 0.1 1324
4.05 Replace Lock for manhole lid 1 0.1 1325
4.05 Replace Bracket for lock 2 0.1 1326
4.07 Replace Manhole Box 1 1.7 1621
4.07 Replace Lid for manhole box 1 0.2 1622
4.07 Straighten Manhole Box 1 0.1 1681
4.07 Straighten Lid for manhole box 1 0.1 1682
1.5 GANGWAY – REPLACEMENT / STRAIGHTENING (including masking and painting if necessary)
4.06 Replace Gangway < 600 4 0.2 1521
600 to 1200 2 0.3 1522
> 1200 2 0.4 1523
4.06 Straighten Gangway 4 0.1 1581
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 10 Revision A Tank Container of 20 Revised : 2002-01-23
2.0 ENDS
2.1 END TOP RAIL -- REPLACEMENT.
5.04 Replace End Top Rail 2 1.8 2421 (Remove damaged end top rail --- install new end
top rail - masking and painting )
2.2 END TOP RAIL – INSERT / STRAIGHTENING.
5.00 Manufacture and install insert (material thickness 5 mm)
150 2 0.9 2441
(including masking and painting)
300 2 1.0 2442
450 2 1.0 2443
600 2 1.1 2444
900 1 1.3 2445
1200 1 1.5 2446
1500 1 1.7 2447
*** Straighten Top End Rail 2 0.1 2481
2.3 END TOP RAIL -- SECTIONING.
5.04 Replace End Top Rail section 1200 1 0.8 2451 (including masking and painting)
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 11 Revision A Tank Container of 20 Revised : 2002-01-23
2.4 END BOTTOM RAIL -- REPLACEMENT.
5.04 Replace End Bottom Rail 2 1.8 2521 (Remove damaged end bottom rail--- install new
end bottom rail- masking and painting
2.5 END BOTTOM RAIL – INSERT / STRAIGHTENING.
5.00 Manufacture and install insert (material thickness 5 mm)
150 2 0.9 2541
(including masking and painting)
300 2 1.0 2542
450 2 1.0 2543
600 2 1.1 2544
900 1 1.3 2545
1200 1 1.5 2546
1500 1 1.7 2547
*** Straighten Bottom End Rail 2 0.1 2581
2.6 END BOTTOM RAIL -- SECTIONING.
5.04 Replace End Bottom Rail section 1200 1 0.8 2551 (including masking and painting)
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 12 Revision A Tank Container of 20 Revised : 2002-01-23
2.7 CORNER POST - REPLACEMENT.
5.03 Replace Corner Post --- exclucive castings 2 2.2 2521
(Remove damaged corner post--- install new corner post - masking and painting)
2.8 CORNER POST – INSERT / STRAIGHTENING.
5.00 Manufacture and install insert (material thickness 6 mm)
150 2 1.0 2641
(including masking and painting)
300 2 1.1 2642
450 2 1.2 2643
600 2 1.4 2644
900 1 1.6 2645
1200 1 1.9 2646
1500 1 2.1 2647
5.03 Straighten Corner Post 2 0.5 2681
2.9 CORNER CASTING -- REPLACEMENT.
5.03 Replace Corner Casting 2 1.3 2721 (Remove damaged corner casting --- install new
corner casting - masking and painting)
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 13 Revision A Tank Container of 20 Revised : 2002-01-23
2.10 SUPPORT RIB PLATE -- REPLACEMENT
Support between corner post and end rails
5.01 Replace Support Rib Plate 2 0.5 2221 (Remove damaged rib plate --- install new rib plate -
masking and painting)
*** Straighten Support Rib Plate 2 0.1 2281
*** Alignment of frame to ISO standard 1 0.5 2381
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 14 Revision A Tank Container of 20 Revised : 2002-01-23
3.0 SIDES
3.1 SIDE TOP RAIL -- REPLACEMENT.
7.01 Replace Side Top Rail 2 1.8 3421 (Remove damaged side top rail --- install new side
top rail - masking and painting )
3.2 SIDE TOP RAIL – INSERT / STRAIGHTENING.
5.00 Manufacture and install insert (material thickness 5 mm)
150 2 0.9 3441
(including masking and painting)
300 2 1.0 3442
450 2 1.0 3443
600 2 1.1 3444
900 1 1.3 3445
1200 1 1.5 3446
1500 1 1.7 3447
*** Straighten Side Top Rail 2 0.1 3481
3.3 SIDE TOP RAIL -- SECTIONING.
7.01 Replace Side Top Rail section 600 2 1.1 3451
(including masking and painting)
900 2 1.1 3452
1200 1 1.2 3453
1800 1 1.7 3454
2400 1 2.1 3455
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 15 Revision A Tank Container of 20 Revised : 2002-01-23
3.4 SIDE BOTTOM RAIL -- REPLACEMENT.
7.02 Replace Side Bottom Rail 2 2.0 3521 (Remove damaged side bottom rail --- install new
enside bottom rail - masking and painting )
3.5 SIDE BOTTOM RAIL – INSERT / STRAIGHTENING.
5.00 Manufacture and install insert (material thickness 6 mm)
150 2 1.0 3541
(including masking and painting)
300 2 1.1 3542
450 2 1.2 3543
600 2 1.4 3544
900 1 1.6 3545
1200 1 1.9 3546
1500 1 2.1 3547
*** Straighten Side Bottom Rail 2 0.1 3581
3.6 SIDE BOTTOM RAIL -- SECTIONING.
7.01 Replace Side Bottom Rail section 600 2 1.4 3551
(including masking and painting)
900 2 1.4 3552
1200 1 1.5 3553
1800 1 2.0 3554
2400 1 2.5 3555
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 16 Revision A Tank Container of 20 Revised : 2002-01-23
3.7 SIDE POST -- REPLACEMENT
7.03 Replace Side Post 2 0.4 3121 (Remove damaged side post --- install new side
post - masking and painting )
3.8 SIDE POST -- SECTIONING
7.03 Replace Side Bottom Rail section < 1200 1 0.6 3151
(including masking and painting)
> 1200 1 0.7 3152
3.9 BEARER -- REPLACEMENT
7.05 Replace Bearer 2 1.5 3321
(Remove damaged besrer --- install new besrer - masking and painting )
*** Straighten Bearer 2 0.1 3381
3.10 DIAGONAL BRACE -- REPLACEMENT
7.04 Replace Diagonal Brace 2 0.5 3221
(Remove damaged brace --- install new brace - masking and painting )
*** Straighten Diagolan Brace 2 0.1 3281
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 17 Revision A Tank Container of 20 Revised : 2002-01-23
4.0 VALVES
4.1 BOTTOM VALVE.
8.01 Replace Bottom Valve 1 0.2 6121
8.01 Replace ‘‘O’’ ring and main seal in Bottom Valve 1 0.1 6122
8.01. Replace two ‘‘O’’ rings at spindle for Bottom Valve 1 0.2 6123
8.01 Replace connecting flange with blind flange 1 0.2 6124
4.2 FOOT VALVE.
8.01 Replace Foot Valve 1 0.2 6221
8.01 Replace ‘‘O’’ ring in Foot Valve 1 0.2 6222
4.3 REMOTE ASSEMBLY (including painting if necessary)
8.01 Replace Wire for remote assembly 1 0.2 6821
*** Replace bracket for Wire 4 0.1 6822
8.01 Replace Bearing Bracket for remote assembly 2 0.2 6823
8.01 Replace Handle for remote assembly 1 0.2 6824
4.4 PRESSURE RELIEF VALVE
8.02 Replace Pressure Relief Valve and envelope seal 2 0.1 6321
8.02 Replace ‘‘O’’ ring/spring/presure plate/vacuum poppet for pressure relief valve
2 0.2 6322
(Dismounting of valve - replace damaged items e.g ‘‘O’’ rings, springs - remounting of valve)
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 18 Revision A Tank Container of 20 Revised : 2002-01-23
4.5 AIR LINE VALVE
8.03 Replace Air Line Valve 1 0.2 6421
4.6 VALVE BOX
4.07 Replace Valve Box 1 1.7 6621 (including masking and painting)
4.07 Replace Lid for valve box 1 0.2 6622
4.07 Straighten Valve Box 1 0.1 6681
4.07 Straighten Lid for valve box 1 0.1 6682
Standard Time System Tank
CPH Refe-rence
Description
Size L x W (in mm)
Max. Pieces
Man-hours
per piece
STS Code
December 2001 MODE 10 Page 19 Revision A Tank Container of 20 Revised : 2002-01-23
5.0 UNDERSTRUCTURE
5.1 BOTTOM CROSSMEMBER -- REPLACEMENT
4.01 Replace bottom crossmember 4 0.7 7121
(Remove damaged crossmember --- install new crossmember - masking and painting )
5.2 BOTTOM CROSSMEMBER -- SECTIONING
4.01 Replace bottom crossmember section 600 4 7151
(including masking and painting
1200 7152
5.3 SUPPORT RAIL—REPLACEMENT / STRAIGHTENING
Support between end bottom rail and side bottom rail
4.02 Replace support rail 4 0.4 7221
(Remove damaged support rail --- install new support rail - masking and painting )
*** Straighten support rail 4 0.1 7281
Standard Time System Tank
2009 MODE 10 Page 20 Revision A Tank Container of 20 Revised : 2009-nov
Request of change / new STS code.
This page must be forwarded to CENEMRTEC case you request changes in codes or request new STS code.
Requesting office:Telex address:Name and initials:
New STS code yes no Revised STS code (code number)
Code requested for modes:00 01 02 03 04 05 06
Description of work:
Size (in mm): Pieces: Suggested Man-hours: Page:
For CENEQUEMR,TEC use only
Suggested STS Manual Description
Suggested RKRP Description
Suggested WMNR Description
CENEMR comments: