50
-~29399O8.xis, MHI Guide Section Statement, Requirement Design of US-APWR Note RG 1.9 C 1 Design Considerations RG 1.9 C 1.1 Clause 1.1.1, "Inclusions," of IEEE Std 387-1995 To be considered in design The GTG controls (manual and should be supplemented to include deisel generator automatic) as well as generator auto controls, manual controls, and diesel generator output breaker will be included in output breaker. the scope of the equipment. The breaker, however, is often provided by others as part of the plant switchgear. RG 1.9 C 1.2 When the characteristics of the required emergency To be considered in design This is a design consideration for diesel generator loads are not accurately known, such MHI in the selection of the 4500 kW as during an early stage of design, each emergency GTG in the US-APWR application. diesel generator selected for an onsite power supply system should have a continuous load rating (as defined in Section 3.2 of IEEE Std 387-1995) equal to the sum of the conservatively estimated connected loads (nameplate rating) that the diesel generator would power at any one time, plus a 10- to 15-percent margin. In the absence of fully substantiated performance characteristics for mechanical equipment such as pumps, the electric motor drive ratings should be calculated using conservative estimates of these characteristics (e.g., pump runout conditions and motor efficiencies of 90 percent or less, and power factors of 85 percent or less). RG 1.9 C 1.3 During the operating license or combined license To be considered in design This is a design consideration for stages of review, the maximum design-basis loads MHI in the selection of the 4500 kW should be within the continuous rating (as defined in GTG in the US-APWR application. Section 3.2 of IEEE Std 387-1995) of the diesel generator with sufficient margin (i.e., not less than 5 percent). 9/28/2009, 10:59-AM

Mitsubishi Heavy Industries, Ltd. Matrix Incorporating RG 1.9 and IEEE 387 … · 2012. 12. 2. · RG 1.9 C 1.1 Clause 1.1.1, "Inclusions," of IEEE Std 387-1995 To be considered in

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • -~29399O8.xis, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 1 Design ConsiderationsRG 1.9 C 1.1 Clause 1.1.1, "Inclusions," of IEEE Std 387-1995 To be considered in design The GTG controls (manual and

    should be supplemented to include deisel generator automatic) as well as generatorauto controls, manual controls, and diesel generator output breaker will be included inoutput breaker. the scope of the equipment. The

    breaker, however, is often providedby others as part of the plantswitchgear.

    RG 1.9 C 1.2 When the characteristics of the required emergency To be considered in design This is a design consideration fordiesel generator loads are not accurately known, such MHI in the selection of the 4500 kWas during an early stage of design, each emergency GTG in the US-APWR application.diesel generator selected for an onsite power supplysystem should have a continuous load rating (asdefined in Section 3.2 of IEEE Std 387-1995) equal tothe sum of the conservatively estimated connectedloads (nameplate rating) that the diesel generatorwould power at any one time, plus a 10- to 15-percentmargin.In the absence of fully substantiated performancecharacteristics for mechanical equipment such aspumps, the electric motor drive ratings should becalculated using conservative estimates of thesecharacteristics (e.g., pump runout conditions andmotor efficiencies of 90 percent or less, and powerfactors of 85 percent or less).

    RG 1.9 C 1.3 During the operating license or combined license To be considered in design This is a design consideration forstages of review, the maximum design-basis loads MHI in the selection of the 4500 kWshould be within the continuous rating (as defined in GTG in the US-APWR application.Section 3.2 of IEEE Std 387-1995) of the dieselgenerator with sufficient margin (i.e., not less than 5percent).

    9/28/2009, 10:59-AM

  • -2939908.xls, MHI

    Guide I Section[ Statement, Requirement I Design of US-APWR ] NoteRG 1.9 C 1.4 Clause 4.1.2 of IEEE Std 387-1995 pertains, in part,

    to the starting and load-accepting capabilities of thediesel generator. In conformance with Clause 4.1.2,each diesel generator should be capable of startingand accelerating to rated speed, in the requiredsequence, all the needed engineered safety featuresand emergency shutdown loads. The diesel generatorshould be designed such that the frequency will notdecrease, at any time during the loading sequence, tcless than 95 percent of nominal and the voltage willnot decrease to less than 75 percent of nominal. (Alarger decrease in voltage and frequency may bejustified for a diesel generator that carries only onelarge connected load.) Frequency should be restoredto within 2 percent of nominal in less than 60 percentof each load-sequence interval for a steploadincrease, and less than 80 percent of each load-sequence interval for disconnection of the singlelargest load.

    MHI will perform this functional testin qualification program

    This design consideration will beconfirmed with the completion of th(Initial Type Test. Specifically thisincludes the unit Start and LoadAcceptance Test in conjunction withthe Margin Test. The margin testin(will confirm that the specifiedmaximum voltage and frequencyexcursions will not be exceeded.

    The actual loads will be sequencedto the unit during completion of theLOOP tests as part of the Pre-Operational Site Testing.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 Voltage should be restored to within 10 percent of MHI will perform this functional test This design consideration will be

    nominal within 60 percent of each load-sequence in qualification program confirmed with the completion of thEinterval. The acceptance value of the frequency and Initial Type Test. Specifically thisvoltage should be based on plant-specific analysis includes the unit Load Capability(where conservative values of voltage and frequency Tests in conjunction with the Marginare measured) to prevent load interruption. (A greater Tests. The margin testing willpercentage of the load-sequence interval may be confirm that the specified maximumused if it can be justified by analysis. However, the voltage and frequency excursionsload-sequence interval should include sufficient will not be exceeded.margin for the accuracy and repeatability of the load-sequence timer.) During recovery-from transients The actual loads will be sequencedcaused by disconnection of the largest single load, to the unit during completion of thethe speed of the diesel generator should not exceed LOOP tests as part of the Pre-the nominal speed plus 75 percent of the difference Operational Site Testing.between nominal speed and the overspeed trip setpoint, or 115 percent of nominal (whichever is lower).Furthermore, the transient following a complete lossof load should not cause the diesel generator speedto reach the overspeed trip set point.

    RG 1.9 C 1.5 Emergency diesel generators should be designed so To be considered in design The GTG will be designed for* that they can be tested as described in Regulatory testing as described in Position 2Position 2. The design should allow testing of the (See Section C2 below).diesel generators to simulate the parameters ofoperation (e.g., manual start, automatic start, loadsequencing, load shedding, operation time), normalstandby conditions, and environments (e.g.,temperature, humidity) that would be expected ifactual demand were placed on the system. Ifprelubrication systems or prewarming systemsdesigned to maintain lube oil and jacket water coolingat certain temperatures (or both) are normally inoperation, this would constitute normal standbyconditions for the given plant.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 1.6 Design provisions should include the capability to test To be considered in design The GTG will be designed for

    each emergency diesel generator independently of testing independently of redundantthe redundant units. Test equipment should not causE units.a loss of independence between redundant dieselgenerators or between diesel generator load groups.Testability should be considered in selecting andlocating instrumentation sensors and criticalcomponents (e.g., governor, starting systemcomponents). Instrumentation sensors should bereadily accessible and designed so that theirinspection and calibration can be verified in place.The overall design should include status indicationand alarm features.

    RG 1.9 C 1.7 Clause 4.5.3.1 of IEEE Std 387-1995 pertains tostatus indication of diesel generator unit conditions.The following paragraphs should supplement theguidance in this clause:

    RG 1.9 C 1.7.1 A surveillance system should be provided with a To be considered in design This is a design consideration forremote indication in the control room to display MHI in the coordination of controlsemergency diesel generator status (i.e., under test, and remote indication.ready-standby, lockout).A means of communication should also be providedbetween diesel generator testing locations and themain control room to ensure that the operators knowthe status of the diesel generator under test.

    RG 1.9 C 1.7.2 To facilitate the diagnosis of failure or malfunction, the To be considered in design Each GTG unit will havesurveillance system should indicate which of the annunciator with appropriate first ouemergency diesel generator protective trips has been logic.activated first.

    9/28/2009, 10:59 AM

  • '-2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 1.8 The following should supplement Clause 4.5.4 of To be considered in design A minimum of two (2) differential

    IEEE Std 387-1995, which pertains to bypassing relays and two (2) turbine speedemergency diesel generator protective trips during sensors must be provided foremergency conditions: shutdown operation in emergencyThe emergency diesel generator should be tripped mode. This also applies to anyautomatically on engine overspeed and generator- other shutdown that remains activedifferential overcurrent. A trip should be implemented during emergency run operationwith two or more measurements for each trip (example high turbine exhaust gasparameter with coincident logic provisions for trip temperature).actuation.The design of the coincident logic trip circuitry should The GTG control panel will beinclude the capability to indicate individual sensor designed with appropriate bypasstrips. The design of the bypass circuitry should circuitry including test, status andinclude the capability to (1) test the status and manual reset.operability of the bypass circuits, (2) trigger alarms inthe control room for abnormal values of all bypassparameters (common trouble alarms may be used),and (3) manually reset the trip bypass function. Thecapability to automatically reset the bypass function isnot acceptable.

    RG 1.9 Clause 4.5.4(b) of IEEE Std 387-1995, which pertains To be considered in designto retaining all protective devices during emergencydiesel generator testing, does not apply to periodictests [safety injection actuation system (SIAS),combined with SIAS and LOOP, and protective tripbypass] that demonstrate diesel generator systemresponse under simulated design-basis events.

    RG 1.9 C 1.9 Clause 4.5.2.2 of IEEE Std 387-1995 should be To be considered in design MHI to note that isochronous modemodified to read as follows: of operation us required forUpon receipt of an emergency start-diesel signal, the emergency operation.automatic control system shall provide automaticstartup and automatic adjustment of speed andvoltage to a ready-to-load condition in the emergency(isochronous) mode.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 2 Diesel Generator Testing

    Clauses 3, 5, 6, and 7 of IEEE Std 387-1995 shouldbe supplemented as discussed below.

    RG 1.9 C 2.1 DefinitionsFigure 1 illustrates those components and systemsthat should be considered to be within the emergencydiesel generator boundary when evaluating failures.Systems that support the emergency diesel generatoiand perform other plant functions are depicted asbeing outside this boundary.IEEE Std 387-1995 provides similar definitions ofcomponents and system boundaries and may also beused as guidance; however, generator breakersshould be considered as part of the diesel generatorboundary.The following definitions apply to the regulatorypositions that address testing, recordkeeping, andreporting of emergency diesel generator performanceStart demands: All valid and inadvertent startdemands, including all start-only demands and allstart demands that are followed by load-run demandswhether by automatic or manual initiation, are startdemands. In a start-only demand, the emergencydiesel generator is started, but no attempt is made toload the emergency diesel generator (see theexceptions below).

    To be considered in design

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Sectionl Statement, Requirement Design of US-APWR NoteRG 1.9 Start failures: Any failure within the emergency diesel

    generator system that prevents the generator fromachieving a specified frequency (or speed) andvoltage within specified time allowance is classified a,,a valid start failure. (For monthly surveillance tests,the emergency diesel generator can be brought torated speed and voltage in the time recommended bythe manufacturer to minimize stress and wear.) Anycondition identified during maintenance inspections(with the emergency diesel generator in the standbymode) that would definitely have resulted in a startfailure if a demand had occurred should count as avalid start demand and failure.Load-run demands: To be valid, the load-run attemptshould follow a successful start and meet one of thefollowing criteria (see the exceptions below):- a load-run of any duration that results from a real(i.e., not a test) automatic or manual signal- a load-run test to satisfy the plant's load andduration test specifications- other operations (e.g., special tests) in which theemergency diesel generator is planned to run for at le

    To be considered in design

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide SectionT Statement, Requirement Design of US-APWR NoteRG 1.9 Load-run failures: A load-run failure should be

    counted when the emergency diesel generator startsbut does not pick up the load and run successfully.Any failure during a valid load-run demand shouldcount (see the exceptions below). (For monthlysurveillance tests, the emergency diesel generatorcan be loaded at the rate recommended by themanufacturer to minimize stress and wear.) Anycondition identified during maintenance inspections(with the emergency diesel generator in the standbymode) that definitely would have resulted in a load-ruifailure if a demand had occurred should count as avalid load-run demand and failure.

    To be considered in design

    L _______________________________

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide I Section! Statement, Requirement I Design of US-APWR NoteRG 1.9 Exceptions: Unsuccessful attempts to start or load-

    run should not count as valid demands or failureswhen they can definitely be attributed to any of thefollowing:- any operation of a trip that would be bypassed in thEemergency operation mode (e.g., high cooling-watertemperature trip). malfunction of equipment that is not required tooperate during the emergency operating mode (e.g.,synchronizing circuitry)- intentional termination of the test because ofalarmed or observed abnormal conditions (e.g., smallwater or oil leaks) that would not have ultimatelyresulted in significant damage or failure of theemergency generator* component malfunctions or operating errors that didnot prevent the emergency diesel generator frombeing restarted and brought to load within 5 minutes(i.e., without corrective maintenance or significantproblem diagnosis)- a failure to start because a portion of the startingsystem was disabled for test purposes, if followed bya successful start with the starting system in itsEach diesel generator valid failure that results indeclaration of the emergency diesel generator asbeing inoperable should count as one demand andone failure. Exploratory tests during corrective orpreventive maintenance should not count asdemands or failures. However, the successful testthat is performed to declare the emergency dieselcqenerator operable should count as a demand.

    To be considered in design

    RG 1.94 J.

    To be considered in design

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 2.2 Test Descriptions

    The table on site testing from the standard isrepeated in this guide as Table 1 to addresssupplementary guidance when required. The followin(test descriptions should be used in conjunction withthe preoperational and surveillance testing describedin the table. The licensee should have detailedprocedures for each test described herein. Theprocedures should identify special arrangements orchanges in normal system configuration that must bemade to put the emergency diesel generator. undertest. Jumpers and other nonstandard configurationsor arrangements should not be used after initialequipment startup testing.

    RG 1.9 C 2.2.1 Starting Test MHI will perform this functional test Starting test is part of siteClause 7.2.1.1 of IEEE Std 387-1995 should be in GTG Site Testing Program acceptance test program required asupplemented as follows: installation of unit.The acceptance criteria for frequency and voltage This test is performed in plantshould be equal to or higher than the minimum periodically after installation.required voltage and frequency within specified timeallowance for the safety-related -loads.

    RG 1.9 C 2.2.2 Slow-Start Test This test is performed in plant This is a standard test for provingClause 7.5.1 of IEEE Std 387-1995 should be periodically after installation, periodic start of the GTG duringsupplemented as follows: surveillance testing by site.This test involves demonstrating proper startup fromstandby conditions, and verify that the required desigrvoltage and frequency are attained. For this test, theemergency diesel generator can be slow-started andreach rated speed on a prescribed schedule tominimize stress and wear.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 2.2.3 Load Run (Load Acceptance) Test This test is performed in plant This is a standard test for proving

    Clause 7.5.2 of IEEE Std 387-1995 should be periodically after installation, periodic start and load carryingsupplemented as follows: capability of the GTG duringThis test involves demonstrating 90-100 percent of surveillance testing by site.the continuous rating of the emergency dieselgenerator, for an interval of not less than 1 hour anduntil attainment of temperature equilibrium.This test may be accomplished by synchronizing thegenerator with offsite power. The loading andunloading of an emergency diesel generator duringthis test should be gradual and based on a prescribedschedule that is selected to minimize stress and wearon the diesel generator.

    RG 1.9 C 2.2.4 Rated Load Test MHI will perform this functional test Rated load test is part of siteClause 7.2.1.3 (a) of IEEE Std 387-1995 should be in GTG Site Testing Program acceptance test program required asupplemented as follows: installation of unit.If the design-basis event loads are higher than thecontinuous rating of the emergency diesel generator,the test should be conducted at the worst case desigr -basis event loads.

    RG 1.9 C 2.2.5 LOOP Test MHI will perform this functional testClause 7.5.4 of IEEE Std 387-1995 should be in GTG Site Testing Programsupplemented as follows:This test involves simulating a LOOP to demonstratethat (1) the emergency buses are deenergized andthe loads are shed from the emergency buses, and(2) the emergency diesel generator starts on theautostart signal from its standby conditions; attainsthe required voltage and frequency, and energizespermanently connected loads within acceptable limitsand time; energizes all autoconnected shutdownloads through the load sequencer; and operates forgreater than or equal to 5 minutes. If the requiredsafety loads are not available, one or more equivalentload(s) may be used.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 2.2.6 Combined SIAS and LOOP Test MHI will perform this functional test

    Clause 7.5.6 of IEEE Std 387-1995 should be in GTG Site Testing Programmodified to read as follows:This test involves demonstrating that emergency This test is performed in plantdiesel generator can satisfactorily respond to a LOOP periodically after installation.in conjunction with SIAS in whatever sequence theymight occur [e.g., loss-of-coolant accident (LOCA)followed by delayed LOOP or LOOP followed byLOCA]. A simultaneous LOOP/LOCA event would bedemonstrated by verifying that the diesel generatorunit starts on the auto-start signal from its standbyconditions, attains the frequency and voltage withinacceptable limits and time, energizes the auto-connected shutdown loads through the loadsequencer within the acceptable limits of pump starttime, and operates for a minimum of 5 minutes.

    RG 1.9 C 2.2.7 Largest Load Rejection Test MHI will perform this functional testClause 7.5.7 of IEEE Std-1995 should be in GTG Site Testing Programsupplemented as follows:This test involves demonstrating the emergency This test is performed in plantdiesel generator's capability to reject a load equal to periodically after installation.loss of the largest single load while operating at itsdesign load power factor and verify that the frequencyand voltage requirements are met and the unit will nottrip on overspeed.

    RG 1.9 C 2.2.8 Design-Load Rejection Test MHI will perform this functional testClause 7.5.8 of IEEE Std-1 995 should be in GTG Site Testing Programsupplemented as follows:This test involves demonstrating the emergency This test is performed in plantdiesel generator's capability to reject a load equal to periodically after installation.90-100 percent of the continuous rating whileoperating at its design load power factor and verifythat the voltage requirements are met and that theunit will not trip on overspeed.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 2.2.9 Endurance and Load Margin Test MHI will perform this functional test

    Clause 7.5.9 of IEEE Std 387-1995 should be in GTG Site Testing Programsupplemented as follows:This test involves demonstrating the capability of the This test is performed in plantemergency diesel generator at continuous rating and periodically after installation.worst case power factor for an interval of not lessthan 24 hours. Of this period, 2 hours are at a loadequal to 105-110 percent of the diesel generator'scontinuous rating, and 22 hours are at a load equal to90-100 percent of the generator's continuous rating.The test process should verify that frequency andvoltage requirements are maintained.

    RG 1.9 C 2.2.10 Hot Restart Test MHI will perform this functional testClause 7.5.10 of IEEE Std 387-1995 should be in GTG Site Testing Programsupplemented as follows:This test involves demonstrating the hot restart This test is performed in plantfunctional capability at full load-temperature periodically after installation.conditions (after the emergency diesel generator hasoperated for 2 hours at continuous rating) by verifyingthat the emergency diesel generator starts on amanual or auto-start signal, attains the requiredfrequency and voltage within acceptable limits andtime, and operates for longer than 5 minutes. Thistest may be performed following the endurance andmargin test described above.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 2.2.11 Periodic-Trip Bypass Test MHI will perform this functional test

    Clause 7.5.12 of IEEE Std 387-1995 should be in GTG Site Testing Programsupplemented as follows:This test involves demonstrating that automatic diese This test is performed in plantgenerator unit trips are automatically bypassed as periodically after installation.designed. Typically, engine overspend, generatordifferential current trip and those trips retained withcoincident logic are not bypassed. This test shouldalso verify that the critical protective trips that are notautomatically bypassed perform their intendedfunction.

    RG 1.9 C 2.3 Preoperational and Surveillance Testing MHI will perform Site AcceptanceTable 1 relates preoperational and surveillance tests tests and Preoperational teststo the anticipated schedule for performance (e.g., following GTG installation at site.preoperational, monthly surveillance, 6-month testing,scheduled refueling period, and 10-year testing).A prelube period should precede all planned testsdescribed in this regulatory guide. The tests should bEin general accordance with the manufacturer'srecommendations for reducing engine wear, includingcooldown operation at reduced power followed bypostoperation lubrication.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 2.3.1 Preoperational Testing MHI will perform Site Acceptance

    A preoperational test program should be implementec tests and Preoperational testsfor all emergency diesel generator systems following following GTG installation at site.assembly and installation at the site. This programshould include the tests identified in Table 1.In addition, through a minimum of 25 valid start andload demands without failure on each installedemergency diesel generator, this test shoulddemonstrate that the new emergency diesel generatohas attained a level of reliability acceptable forentering into an operational category.

    RG 1.9 C 2.3.2 Surveillance Testing These tests are performed in plantAfter plants are licensed (after fuel load), periodic periodically after installation.surveillance testing of each emergency dieselgenerator should demonstrate the continuedcapability and reliability of the diesel generator unit toperform its intended function. When the emergencydiesel generator is declared operational inaccordance with the plant's technical specifications,the following periodic test program should beimplemented.

    RG 1.9 C 2.3.2.1 Monthly Testing These tests are performed in plantAfter completion of the reliability demonstration durinn periodically after installation.preoperational testing, the emergency dieselgenerators should be periodically tested duringnormal plant operation.Each diesel generator should be started as describedin Regulatory Position 2.2.2 and loaded as describedin Regulatory Position 2.2.3 at least once every 31days (with the maximum allowable extension not toexceed 25 percent of the surveillance interval).

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR- NoteRG 1.9 C 2.3.2.2 Six-Month (or 184-Day) Testing These tests are performed in plant

    This test may substitute for a monthly test. To periodically after installation.demonstrate the capability of the emergency dieselgenerator to start from standby conditions and providEthe necessary power to mitigate a LOCA coincidentwith a LOOP, each diesel generator should be startedfrom standby conditions once every 6 months asdescribed in Clause 7.5.3 of IEEE Std 387-1995. Thiswill verify that the diesel generator reaches therequired voltage and frequency within acceptablelimits and time as specified in the plant technicalspecifications. Following this test, the emergencydiesel generator should be loaded as described inClause 7.5.2 of IEEE Std 387-1995 (see also Table1).

    RG 1.9 C 2.3.2. Refueling Outage Testing These tests are performed in plantThe capability of the overall emergency diesel periodically after installation.generator design should be demonstrated duringevery refueling outage (or at a frequency of not morethan every 24 months) by performing the testsidentified in Table 1. Certain tests may be conductedduring the operating mode with NRC approval if thetests can be safely performed without increasing theprobability of plant trip, loss of power to the safetybuses, or LOOP.

    RG 1.9 C 2.3.2.4 Ten-Year Testing These tests are performed in plantThis testing involves demonstrating that the trains of periodically after installation.standby electric power are independent at afrequency of once every 10 years (during a plantshutdown) or after any modifications that could affectemergency diesel generator independence(whichever is shorter) by starting all redundant unitssimultaneously to identify certain common-failuremodes undetected in single diesel generator unit test,(see also Table 1).

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteRG 1.9 C 3 Reporting Criteria

    Licensees must conform to the reportingrequirements of 10 CFR Part 21, "Reporting ofDefects and Noncompliance" (Ref. 2); 10 CFR 50.72,"Immediate Notification Requirements for OperatingNuclear Power Reactors"; and 10 CFR 50.73,"License Event Reporting System."

    IEEE 387 4. Principal design criteriaIEEE 387 4.1 CapabilityIEEE 387 4.1.1 General To be considered in design

    When in service, each diesel-generator unit shallhave the capability of performing as a redundant unitof a standby power supply, in accordance with the

    requirements stated in IEEE Std 308-1991 .

    6 lnformation on references can be found in clause 2.

    IEEE 387 4.1.2 Mechanical and electrical capabilitiesThe diesel-generator unit shall also have each of thefollowing specific capabilities to meet the design,application, and qualification requirements of thisstandard:

    To be considered in design

    9/28/2009, 10:59 AM

  • '-2939908.xls, MHI

    GuideIEEE 387

    IEEE 387

    Section Statement, Requirement Design of US-APWR Notea) Design conditions. The unit shall be capable ofoperating during and after any design basis eventwithout support from the preferred power supply. Thefollowing design conditions, including appropriatemargins as required by subclause 6.3.1.5 of IEEE Stc323-1983, shall be specified by those individualsresponsible for the system application and, as aminimum, shall include

    1) Operational cycles (4000 starts7 over a period of 4(years, unless otherwise specified)

    2) Operating hours (6000 h8 over a period of 40years, unless otherwise specified)3) Temperature at equipment locations (minimum an(maximum with durations and average annualambient)4) Seismic response spectra5) Radiation (1 ' 104 rd of gamma integrated doseover a period of 40 years, unless otherwise specified)6) Humidity (minimum and maximum with durations)7) Load profile, including allowable voltage andfrequency variations (see 3.7 and annex A)8) Absolute barometric pressure (altitude and tornadcdepressurization, duration, and magnitude)9) Combustion air contaminants (salt, sand, etc.)10) Fuel tvye and aualitv

    To be considered in design

    b) Starting and loading. The unit shall be capable of To be considered in designstarting, accelerating, and being loaded with thedesign load within the time required by the equipmentspecification1) From the normal standby condition.2) With cooling not available, for a time equivalent tothat required to bring the cooling equipment intoservice with energy from the diesel-generator unit.3) On a restart with an initial engine temperatureequal to the continuous rating full-load enginetemperature.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 c) Light-load or no-load operation. The unit shall be To be considered in design KHI must define light load limitation

    capable of accepting design load following operation applicable to GTat light load or no load for the time required by theequipment specification.d) Design load. The unit shall be capable of carryingthe design load for the time required by the equipmenspecification.e) Quality of power. The unit shall be capable ofmaintaining voltage and frequency at the generatorterminals within limits that will not degrade theperformance of any of the loads comprising thedesign load below their minimum requirements,including the duration of transients caused by loadapplication or load removal.

    IEEE 387 4.2 RatingsIEEE 387 4.2.1 Application To be considered in design

    The diesel-generator unit shall have continuous andshort-time ratings that reflect the output capabilities o!the diesel-generator unit in accordance with therequirements of 4.1 and the following:a) Inspections and scheduled maintenance shall beperformed periodically using the manufacturer'srecommendations and procedures.b) Unscheduled maintenance shall be performed inaccordance with the need as indicated by the periodicinspections and operating experience.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 4.2.2 Operation To be considered in design

    The diesel-generator units may be utilized to the limitof their power capabilities, as defined by thecontinuous and short-time ratings. Unless time andload parameters for light-load and no-load operationare established by tests and documentation, thefollowing precautions shall be taken:a) When 4 h operation at 30% or less of thecontinuous rating have been accumulated (without atleast 0.5 h operation above 50% of the continuousrating), the unit shall be operated at a load of at least50% of the continuous rating for a minimum of 0.5 h.b) Operating at 30% or greater of the continuousrating shall be restricted to the manufacturer'srecommendations.

    IEEE 387 4.3 Interactions To be considered in designIndependence between units shall not becompromised. Mechanical and electric systeminteractions between a particular diesel-generator uniand other units of the standby power supply, thenuclear plant, the conventional plant, and the Class1 E electric system shall be coordinated in such a waythat the diesel generator unit's design function, andcapability requirements of 4.1, may be realized for an)design basis event, except failure of that diesel-generator unit.

    IEEE 387 4.4 Design and application considerations To be considered in designDesign and application considerations shall include,but not necessarily be limited to, the considerationslisted in table 1.

    IEEE 387 4.5 Design featuresIEEE 387 4.5.1 Mechanical and electrical design features

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 4.5.1.1 Vibration To be considered in design

    Vibration amplitudes shall be limited to be within thedesign capabilities of the diesel-generator unit andauxiliary components. Solenoids, relays, and otherdevices shall be mounted in such a way to minimizevibration effects.

    IEEE 387 4.5.1.2 Torsional vibration To be considered in design KHI to perform torsional analysis ofHarmful torsional vibration stresses shall not occur rotating drivelinewithin a range from 10% above to 10% below ratedidle speed and from 5% above to 5% below ratedsynchronous speed.

    IEEE 387 4.5.1.3 Overspeed To be considered in designMoving parts shall be designed to withstand that levelof overspeed that results from a short-time rating loadrejection. Margin shall be provided to allow theoverspeed device to be set sufficiently high toguarantee thatthe unit will not trip on short-time rating load rejection.As a minimum, the generator rotor, exciter rotor (ifused), and flywheel shall be designed to withstand anoverspeed of 25% without damage.

    IEEE 387 4.5.1.4 Governor operation To be considered in designIf the diesel engine is equipped to operate in both theisochronous and the droop mode, provisions shall beincluded to automatically place the engine governor inthe proper mode of operation when thedieselgenerator unit is required to operateautomatically (see 4.5.2.2).

    IEEE 387 4.5.1.5 Voltage regulator operation To be considered in designIf the voltage regulator is equipped to operate in theparalleled and nonparalleled mode, provisions shallbe included to automatically place the voltageregulator in the proper mode of operation when thedieselgenerator unit is required to operateautomatically (see 4.5.2.2).

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 4.5.2 ControlIEEE 387 4.5.2.1 Control modes To be considered in design

    The diesel-generator unit shall be provided withcontrol systems, permitting automatic and manualcontrol.

    IEEE 387 4.5.2.2 Automatic control To be considered in designUpon receipt of an emergency start-diesel signal, theautomatic control system shall provide automaticstartup and automatic adjustment of speed andvoltage to a ready-to-load condition.a) A start-diesel signal shall override all otheroperating modes and return control of thedieselgenerator unit to the automatic control system.b) An emergency start-diesel signal shall not overrideany manual non-operating modes such as those forrepair and maintenance.

    IEEE 387 4.5.2.3 Control points To be considered in designProvisions shall be made for control both from thecontrol room and external to the control room.

    IEEE 387 4.5.3 SurveillanceIEEE 387 4.5.3.1 Surveillance systems To be considered in design

    The diesel-generator unit shall be provided withsurveillance systems permitting remote and localalarms and indicating the occurrence of abnormal, pretrip, or trip conditions.

    IEEE 387 4.5.3.2 Modes surveyed To be considered in design See RG1.9 Design ConsiderationAs a minimum, the following conditions shall be section C1.7.1surveyed:a) Unit not runningb) Unit running, not loadedc) Unit running, loadedd) Unit out of service

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 4.5.3.3 Surveillance instrumentation To be considered in design See RG1.9 Design Consideration

    The following systems shall have sufficient section C1.7.2mechanical and electric instrumentation to survey thevariables required for successful operation and togenerate the abnormal, pre-trip, and trip signalsrequired for alarm of such conditions:a) Starting systemb) Lubricating systemc) Fuel systemd) Primary cooling systeme) Secondary cooling systemf) Combustion air systemg) Exhaust systemh) Generatori) Excitation systemj) Voltage regulation systemk) Governor system

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 4.5.4 Protection To be considered in design See RG1.9 Design Consideration

    The diesel-generator unit shall be automatically section C1.8tripped on an engine overspeed or generatordifferential overcurrent, or both. Protective features,other than engine overspeed and generatordifferential current, shall bea) Blocked from automatically tripping the diesel-generator unit during an accident condition and shallbe annunciated in the plant control room, orb) If protective features other than engine overspeedand generator differential current are retained duringaccident conditions, two or more independentmeasurements of each of these parameters withcoincident trip logic shall be provided. The design ofthe coincident trip logic circuitry shall provide alarmfor each individual sensor initiation. All protectivedevices shall remain effective during the diesel-generator unit testing, and during operation in non-accident conditions.

    IEEE 387 5 5. Factory production testingIEEE 387 5.1 5.1 GeneralIEEE 387 5.1.1 Implementation To be considered in design

    Testing shall be performed in accordance with awritten test plan.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 5.1.2 Documentation To be considered in design and test

    Test documentation shall include the following: plana) Equipment performance specificationsb) Identification of the specific feature or features tobe demonstrated by the testc) Test pland) Report of test results. The report shall include thefollowing:1) Objective2) Equipment tested3) Description of test facility (test setup),instrumentation used including calibration recordsreference, and test environment4) Test procedures, including acceptance/rejectioncriteria5) Test data and accuracy (results)6) Test abnormalities and failures, including theirdisposition and effect on test results7) Summary, conclusions, and recommendations8) Supporting data9) Approval signature and date

    IEEE 387 5.1.3 Analyses To be considered in design and test It is anticipated that testing will beAlthough testing is preferred, analyses may plan used exclusively, the use ofsupplement test or be substituted for test, where analytical techniques may betesting is not practical, to demonstrate conformance required.to the criteria stated in clause 4. Analysis shall includEthe basis of assumptions used.

    9/28/2009,10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 5.1.4 Substitutions To be considered in design and test

    When tests are performed at the manufacturer's or planassembler's facilities, and not at the site, the exhaustmuffler, intake air filter-silencer, and radiator (ifapplicable) normally used for shop tests may besubstituted in place of the equipment to be providedfor a specific site, since it is not practical to utilize theequipment and piping that will exist at the site orfuture sites for which the diesel-generator unit is bein(qualified.Results of tests shall be corrected to the condition ofthe service environment and design characteristics,including site exhaust muffler and intake air filter-silencer systems.

    IEEE 387 5.2 Factory production testsThe following tests are minimum requirements forfactory production tests.

    IEEE 387 5.2.1 Engine testsEach engine shall be tested, utilizing either a waterbrake dynamometer or a generator to provideaccurate means to control power absorption. Thefollowing tests shall be performed:a). Break-in test. Each manufacturer shall developtheir own break-in schedule to best suit the engine.b) Performance test.

    MHI will perform these tests inqualification program

    Engine testing is to be by KHI.Engines may be tested individuallyprior to installaing on speedreducing gearbox.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 1) Test runs. After the engine has satisfactorily MHI will perform these tests in Additional/Substitute test data will

    completed the break-in test, the following minimum qualification program be developed and recorded specifictests shall be run to establish the operating to gas turbine.characteristics. These tests may be conducted in anyorder desired.2) Data logging. Test logs of all of the above testsshall become a part of the records for a particularengine. The test logs shall include at least thefollowing data:i) Speed (r/min)ii) Brake (hp or kW)iii) Brake specific fuel consumptioniv) Intake manifold pressurev) Intake manifold temperaturevi) Individual cylinder exhaust temperaturevii) Turbocharger exhaust temperatureviii) Jacket water temperature (engine inlet and outletix) Jacket water pressure (engine inlet)x) Lube oil temperature (engine inlet and outlet)xi) Lube oil header pressure (engine inlet)xii) Type of fuel and fuel heat contentxiii) Barometric pressurexiv) Intake air temperature3) Controls-alarm and shutdown. All engine-mountedalarms and shutdowns, where applicable, shall be setand checked. The points of activation shall be on thetest logs.

    4) Inspection. At any point after the break-in test or uCIEEE 387 5.2.2 Generator tests MHI will perform these tests in

    Generator testing shall be in accordance with NEMA qualification programMG 1-1993.

    IEEE 387 5.2.3 Excitation, control, and other accessories/auxiliaries MHI will perform these tests inAll such devices and assemblies shall be tested in qualification programaccordance with the manufacturer's standardpractices.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 6 Qualification requirementsIEEE 387 6.1 General To be considered in design and test GTG will be installed in Mild

    The diesel-generator units applied as part of the plan Environment as defined in IEEE 322standby power supply shall be qualified in accordancE 1983. An analysis will be performedwith the requirements of this clause.9 This addressing aging of components asqualification will provide verification that the unit will required prior to functional ormeet the requirements of clause 4 under all expected seismic testing.environmental conditions. Qualification shall beaccomplished by performance of type tests onunaged equipment or by analysis, or by a combinatiorof both as required in 6.2 and by functional testing asrequired in 6.4 following any aging or seismic testing.All qualification shall be performed in accordance witha written plan that defines analysis and tests to beperformed, parameters to be monitored during tests,test instrumentation, and acceptance criteria forequipment.

    9The requirements for qualification in this clause arebased on IEEE Std 323-1983 and IEEE Std 627-1980as applicable to dieselgenerator units to ensure thatthe equipment can perform within its specificationrequirements.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 6.2 Initial type tests MHI will perform these tests in Initial type test will be performed at

    Diesel-generators not previously type tested as qualification program ESI.standby power sources for nuclear power generatingstations shall be subject to a type testing programconsisting of load capability, start and loadacceptance, and margin tests. It is preferred thatthese tests be performed at the enginemanufacturer's or assembler's factory;however, they may be conducted at the site if certifiedcalibration instrumentation is provided to measureand record the same functions and characteristicsnormally measured under factory testing conditions.Type tests may be performed on one or more units,and qualification of one unit will qualify like units ofthat type for equal or less severe service. If start andload acceptance tests (see 6.2.2) are performedusing more than one identical unit, then each of theseunits must be tested for load capability (see 6,2.1)and margin (see 6.2.3).

    IEEE 387 Type tests shall be performed following successfulcompletion of the factory production tests. Followingthe successful completion of these type tests, theequipment shall be inspected in accordance with themanufacturer's standard procedure, and inspectionresults shall be documented.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 6.2.1 Load capability tests MHI will perform these tests in Load capability testing will be

    These tests demonstrate the capability of the diesel- qualification program performed at ESI. KHI must definegenerator unit to carry the following rated loads at light load limitations applicable torated power factor for the period of time indicated, GT.and to successfully reject load in accordance with7.2.1.4. One successful completion of the testsequence shall satisfy this particular requirement.a) Load equal to the continuous rating shall beapplied for the time required to reach enginetemperature equilibrium.b) Immediately following step a), the short-time ratedload shall be applied for a period of 2 h and thecontinuous rated load shall be applied for a period of22 h.c) The short-time rating load rejection test shall beperformed. The load rejection test will be acceptablethe increase in speed of the diesel engine does notexceed 75% of the difference between nominal speecand the overspeed trip set point, or 15% abovenominal, whichever is lower.d) Light-load or no-load capability as described in4.1.2 step c) shall be demonstrated by test. Lightloador no-load operation shall be followed by a loadapplication 3 50% of the continuous kilowatt rating for

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide I Sectionl Statement, Requirement Design of US-APWR NoteIEEE 387 6.2.2 Start and load acceptance tests

    A series of tests shall be conducted to establish thecapability of the diesel-generator unit to start andaccept load within the period of time necessary tosatisfy the plant design requirement. An acceptablestart and load acceptance test is defined as follows;however, other methods with proper justification maybe found equivalent for the level of reliability to be

    demonstrated. 10

    1°While the reliability testing is not a specificrequirement of IEEE Std 323-1983 or IEEE Std 627-1980, it is a required type test for this equipment.

    MHI will perform these tests inqualification program

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide SectionT Statement, Requirement Design of US-APWR NoteIEEE 387 A total of 100 valid start and load tests shall be

    performed with no failures allowed. Failure of the unitto successfully complete this series of tests, asprescribed, will require a review of the system designadequacy,the cause of the failures to be corrected, and the testEcontinued until 100 valid tests are achieved withoutany failure. The start and load tests shall beconducted as follows:a) Engine cranking shall begin upon receipt of thestart-diesel signal, and the diesel-generator unit shallaccelerate to specified frequency and voltage withinthe required time interval.b) Immediately following step a), the diesel-generatorunit shall accept a single-step load 3 50% of thecontinuous kilowatt rating. Load may be totallyresistive or a combination of resistive and inductiveloads.c) At least 90 of these tests shall be performed withthe diesel-generator unit initially at warm standby,based on jacket water and lube oil temperatures at orbelow values recommended by the enginemanufacturer.After load is applied, the diesel-generator unit shall

    MHI will perform these tests inqualification program

    Start and Load acceptance testingwill be performed at ESI. Number ostarts to be 150 with no failuresrather than 100. This is to satisfyearlier comments regardingreliability of gas turbine.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 1) Unsuccessful start attempts that can definitely be To be considered in design and test

    attributed to operator error, including setting of planalignment control switches, rheostats, orpotentiometers, or other adjustments that may havebeen changed inadvertently prior to that particularstart test.2) Tests performed for verification of a scheduledmaintenance procedure required during this series oftests. This maintenance procedure shall be definedprior to conducting the start and load acceptancetests and will then become a part of the normalmaintenance schedule after installation.3) Tests performed in the process of troubleshooting.Each start attempt performed in the troubleshootingprocess shall be defined as such before a startattempt is made.4) Successful start attempts that were terminatedintentionally without loading.5) Failure of any of the temporary service systemssuch as dc power source, output circuit breaker, load,interconnecting piping and wiring, and any othertemporary setup that will not be a part of thepermanent installation.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide I Section] Statement, Requirement Design of US-APWR I NoteIEEE 387

    IEEE 387

    6.2.3 Margin testsTests shall be conducted to demonstrate the diesel-generator unit capability to start and carry loads thatare greater than the magnitude of the most severestep load within the plant design load profile, includincstep changes above base load. The limiting case sterchange over base load as defined by the design loadprofile shall be demonstrated. This is not necessarilythe largest step change, but may be a smaller stepchange as the full-load capability of the diesel-generator unit is approached. These tests may becombined with the load capability or start and loadacceptance tests. At least two margin tests shall beperformed using either the same or different loadarrangement. A margin test load at least 10% greaterthan the magnitude of the most severe single-stepload within the load profile is considered sufficient forthe margin test.The frequency and voltage excursions recorded mayexceed those values specified for the plant designload. The criteria for margin tests are as follows:

    MHI will perform these tests inqualification program

    Margin tests will be performed atESI.

    a) Demonstrate the ability of the generator andexcitation system to accept the margin test load(usually the low power factor, high inrush, and highstarting current of a pump motor) withoutexperiencing instability resulting in generator voltagecollapse, or significant evidence of the inability of thevoltage to recover.b) Demonstrate that there is sufficient engine torqueavailable to prevent engine stall, and to permit theengine speed to recover, when experiencing themargin test load.

    MHI will perform these tests inqualification program

    Typically the margin test load is acombination of large inductionmotors in conjunction with resistive& reactive load banks at test facility.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 6.3 Aging To be considered in design and GTG will be installed in Mild

    Aging methods are described in this clause for the qualification test plan Environment as defined in IEEE 323applicable conditions listed in 4.1.2 step a), which are 1983. An analysis will be performeddetermined to be significant. addressing aging of components as

    required prior to functional orseismic testing.

    IEEE 387 6.3.1 Safety classification To be considered in design andComponents and assemblies within the scope of this qualification test planstandard (see figure 1) shall be classified into one ofthe two following categories:a) Components and assemblies required to enablethe diesel-generator unit to meet its capabilities in 4.1(hereinafter called the safety-related function). Thesecomponents and assemblies require consideration ofaging as a potential cause for common mode failuresExamples may include the governor, generator, cableexcitation system, engine, starting air solenoid valvesand those gaskets and seals that are applied toprevent leakage that degrades unit performance.b) Components and assemblies not required toperform a safety-related function. Each of thesenonsafety-related components or assemblies require,verification that it will not degrade the safetyrelatedfunction. This may be accomplished by testing oranalysis. Examples may include generator resistancetemperature detectors (RTDs), neutral groundingequipment, space heaters, starting air compressorsand drives, keep-warm heaters and pumps, and those

    IEEE 387 6.3.2 Aging classificationFurther classification of the safety-relatedcomponents identified in 6.3.1 step a) is required toaddress the potential for age-related failures. Thecategories in table 2 illustrate this classification.

    To be considered in design andqualification test plan

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 Components without significant age-related failure To be considered in design and

    mechanisms may be excluded. For example, it is qualification test planrecognized that cast iron used in the basic engineblock will not represent a potential age-related failuremechanism over normal nuclear service life.Following classification, those components withpotential age-related failures shall be qualified bytesting (the preferred method), analysis, or acombination of test and analysis. Components with aresultant identified qualified life less than the overallqualified life objective shall have amaintenance/replacement interval defined. If aging bytest is used, it shall be followed by seismicqualification to meet IEEE Std 344- 1987. In all casesthe documentation requirements in clause 6 of IEEEStd 323-1983 shall be satisfied. An example of thisprocess is given in annex B.

    IEEE 387 6.4 Seismic qualification requirements To be considered in design and Seismic qualification in accordanceSeismic qualification in accordance with IEEE Std 344. qualification test plan with IEEE 344 will be performed on1987 is required for all safety-related components. all safety-related components. ThisNonsafety-related components require analysis or tes will be accomplished by ato show that they will not degrade the safety-related combination of testing and analysis.function of the unit during a seismic event. Seismictesting shall be followed by functional testing to verifythe applicable capabilities in clause 4.

    IEEE 387 6.5 Ongoing surveillance To be considered in design andOngoing surveillance, including the periodic tests qualification test plandescribed in 7.4, may be used as a basis for theidentification of equipment degradation and validationof the results of the aging and aged equipment testindescribed in 6.3. 1

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide I Section] Statement, Requirement Design of US-APWR NoteIEEE 387

    IEEE 387

    6.5.1 Preventive maintenance, inspection, and testingA separate preventive maintenance, inspection, andtesting program (see also 6.5.2) shall be establishedfor the diesel-generator unit and all supportingsystems based on the manufacturer'srecommendations, including time intervals for partsreplacement of those components with a qualified lifeless than the unit qualified life objective. Theserecommendations may be based on operating hoursor fixed time intervals, or both. Procedures shallinclude, as a minimum, specific programs for eachportion of the unit as follows:a) The engine, including the governor, overspeed tripdevice, internal components to the maximum extentpractical, turbocharger, lube oil components, fuel oilcomponents, jacket water components, startingcomponents, cleaning, adequate lubrication, andwater chemistryb) The generator and rotating exciter (if used),including insulation condition, bearings, coolingsystem, lubricating system, and space heaters (ifapplicable)c) Electrical auxiliary equipment, including localengine and generator control, exciter and voltageregulator, and protection and surveillancecomponentsd) Subsystems, including1) Starting energy, typically consisting of air receivertanks, compressors, piping, valves, and associatedinstrument and control devices2) Fuel oil, typically consisting of pumps, filters,strainers, piping, valves, and associated instrumentand control devices3) Lube oil, typically consisting of pumps, filters,strainers, keep-warm heaters and pumps, coolers,sump tanks, piping, valves, and associated

    To be considered in design

    To be considered in design

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 6.5.2 Records and analysis To be considered in design

    Records shall be maintained for each diesel-generator unit to provide a basis for an analysis of theunit's overall performance. These records alsoprovide a basis for verifying any assumptions madeconcerning agerelated failure mechanisms. Thedocumentation may also be used to shorten or extencthe replacement intervals.

    IEEE 387 6.6 Modifications To be considered in designModifications to a previously qualified diesel-generator unit, such as governor, generator, overallsystem flywheel effect, excitation systemcharacteristics, cooling media, or otheraccessories/auxiliaries that may change the capabilitýor performance of a previously qualified diesel-generator unit, shall be analyzed to determine if thedegree of change is major or minor.a) Major changes to a qualified engine, such aschanges in stroke or bore, brake mean effectivepressure, speed, or diesel-generator arrangement inunique or different configuration shall be requalified inaccordance with this clause.b) Minor changes to a previously qualified diesel-generator unit, such as component parts substitution,shall be qualified by analysis or testing, or both.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 6.7 Documentation To be considered in design

    Qualification documentation shall be in accordancewith IEEE Std 323-1983, and shall include thefollowing:a) Service and environment [see 4.1.2 item a)]b) Classification table of all components as safety-related or nonsafety-relatedc) Analysis/justification for nonsafety-relatedcomponentsd) Classification table of safety-related componentswith or without age-related failure mechanismse) Justification of aging methods for variouscomponentsf) Test data for control panels, exciter/regulator(including seismic)g) Test data for insulation systems testingh) Test data for seismic testing of smaller mechanicalcomponentsi) Analytical data for seismic analysis of generator,engine, and major mechanical componentsj) Historical data/justification for items requiringperiodic replacementk) Correlation of qualification program to instructionbook information for periodic replacement, etc.

    IEEE 387 7 Site testingIEEE 387 7.1 Testing MHI will perform testing in GTG Site

    Site testing shall consist of site acceptance testing, Testing Programpre-operational testing, and periodic testing. Individuatests shall be as shown in table 3.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.2 Site acceptance testing MHI will perform testing in GTG Site

    After final assembly and preliminary start-up testing, Testing Programeach diesel-generator unit shall be tested at the siteto demonstrate the capability of the unit to perform itsintended function.

    IEEE 387 7.2.1 Tests MHI will perform testing in GTG SiteThe tests to be given to the diesel-generator unit are Testing Programshown in table 3 and shall be as follows.

    IEEE 387 7.2.1.1 Starting test MHI will perform testing in GTG SiteStarting tests shall demonstrate the capability to attair Testing Programand stabilize frequency and voltage within the limitsand time defined in the equipment specification.

    IEEE 387 7.2.1.2 Load acceptance test MHI will perform testing in GTG SiteLoad acceptance tests shall demonstrate the Testing Programcapability to accept the individual loads that make upthe design load, as described in 3.4, in the desiredsequence and time duration and to maintain thevoltage and frequency within the acceptable limits.NOTE-If the diesel-generator unit has a light-load orno-load operation capability, the load acceptance testsequence shall include consideration of the potentialeffects on load acceptance following such operation(see also 4.2.2).

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.2.1.3 Rated load test MHI will perform testing in GTG Site

    Rated load tests shall demonstrate the capability of Testing Programcarrying the following loads for the indicated timeswithout exceeding the manufacturer's design limits:a) A load equal to the continuous rating for the timerequired to reach engine temperature equilibrium pluslhb) Immediately following the load in item a), the ratedshort-time load shall be applied for a period of 2 h

    IEEE 387 7.2.1.4 Load rejection test MHI will perform testing in GTG SiteLoad rejection tests shall demonstrate the capability Testing Programof rejecting short-time rated load without exceedingspeeds or voltages that will cause tripping orcomponent damage.

    IEEE 387 7.2.1.5 Electrical test MHI will perform testing in GTG SiteElectrical tests shall demonstrate that the electrical Testing Programproperties of the generator, excitation system, voltageregulation system, engine governor system, and thecontrol and surveillance systems are acceptable forthe intended application.

    IEEE 387 7.2.1.6 Subsystem test MHI will perform testing in GTG SiteTests shall demonstrate the capability of the control, Testing Programprotection, and surveillance systems to function inaccordance with the requirements of the intendedapplication.

    IEEE 387 7.2.2 Test loads To be considered in designLoads to be applied, carried, and rejected during sitetesting shall be the design load auxiliaries located atthe station. Equivalent loads may be used if theseauxiliaries cannot be operated for testing.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.3 Pre-operational testing MHI will perform testing in GTG Site Note additional 25 start and load

    Following completion of the site acceptance testing, Testing Program tests to be performed afterpre-operational tests shall be performed to installation at site.demonstrate starting and operational adequacy of thediesel-generators and the system.The individual pre-operational tests shall be asindicated in table 3 and as described in 7.5.Reliability tests shall demonstrate that an acceptablelevel of reliability has been achieved to place the newdiesel-generators into operation. This shall beachieved by a minimum of 25 valid start and loadtests without failure on each installed diesel-generator.

    IEEE 387 7.4 Periodic testingIEEE 387 7.4.1 General

    After being placed in service, the diesel-generator uniishall be tested periodically to demonstrate that thecontinued capability and availability of the unit toperform its intended function is acceptable.Records and analysis described in 7.6 shall bemaintained for all periodic tests. It is recognized thatsome of these tests may be combined and notnecessarily performed individually.It is not necessary to begin these tests from standbyconditions unless otherwise specified.

    These tests are performed in plantperiodically after installation.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide SectionT Statement, Requirement Design of US-APWR NoteIEEE 387 a) Test equipment shall not cause a loss of

    independence between redundant diesel-generatorunits or between diesel-generator load groups.b) Periodic testing of a diesel-generator unit shall notimpair the capability of the unit to supply emergencypower in the required time in response to start-dieselsignals.c) All diesel-generator unit protective trips and alarmsshould be operative during applicable periodic testingd) Written procedures for testing shall be preparedand utilized. The procedures shall include themanufacturer's applicable test recommendations andshall identify all special arrangements or changes inthe normal system configuration required to performthe test. The procedures shall ensure that the systemis restored to its normal configuration after completiorof the tests. All tests shall be in general accordancewith the manufacturer's recommendations forreducing engine wear, including cool-down operationat reduced power followed by post-operationlubrication.Test procedures that involve starting and stopping thediesel-generator unit shall include the following steps1) Observe and record all pre-start data listed in table2) Initiate the start-diesel signal and measure and rec,3) Confirm that the generator voltage and frequency a4) Record all parameters listed in table 4 at the beginr5) Observe and record all post-test data listed in table

    These tests are performed in plantperiodically after installation.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 e) Communication shall be established between the These tests are performed in plant

    diesel-generator unit testing location and the main periodically after installation.control room so that operators are cognizant of thestatus of the diesel-generator unit undergoing the testf) During system operational tests, problems mayarise with individual components that do not detractfrom the overall test purpose. These componentsshall be repaired and their interface with the systemshall be retested; however, the total test need not berepeated unless necessary due to the critical functionof the component involved.Abnormal conditions discovered during any test shallbe evaluated to determine if1) The condition would prevent the diesel-generatorunit from performing its intended function.2) The test is a valid test.

    IEEE 387 7.4.2 Periodic tests These tests are performed in plantPeriodic tests shall consist of availability, system periodically after installation.operation, and independence verification tests.

    IEEE 387 7.4.2.1 Availability tests These tests are performed in plantThese tests demonstrate the continued capability of periodically after installation.the diesel-generators to start and accept load.Each diesel-generator unit shall be started and loadedat least once in 31 days (slow-start and load-run test)In lieu of the above test, once every six months a faststart and load-run test shall be performed.

    IEEE 387 7.4.2.2 System operation tests These tests are performed in plantThis series of tests demonstrates the ability. of the periodically after installation.diesel-generator unit to perform its intended functionunder simulated accident conditions.These tests shall be performed at shutdown/refuelingoutages once every two years.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.4.2.3 Independence verification test These tests are performed in plant

    Subsequent to any modifications where diesel- periodically after installation.generator unit independence may have been affectedor every 10 years during a plant shutdown or refuelingoutage, whichever is the shorter, an independentverification test shall be conducted.

    IEEE 387 7.5 Test descriptionsThe following descriptions apply to the tests listed intable 3. These tests should be preceded by a pre-lubEperiod and should be in general accordance with themanufacturer's recommendations for reducing enginewear, including cool-down operation at reduced powefollowed by post-operation lubrication. Unlessotherwise noted, these tests should be performed atpower factor as close as practical to the design loadpower factor as plant voltage conditions permit.

    IEEE 387 7.5.1 Slow-start test MHI will perform testing in GTG SiteDemonstrate proper start-up from standby conditions Testing Programand verify that the required design voltage andfrequency are attained. The unit should reach ratedspeed on a prescribed schedule selected to minimizestress and wear on the diesel-generator unit.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.5.2 Load-run test MHI will perform testing in GTG Site

    Demonstrate load-carrying capability, with load Testing Programequivalent to 90-100% of the continuous rating of thediesel-generator unit, for an interval of not less than 1h and until temperature equilibrium has been attainedThis test may be accomplished by synchronizing thegenerator with offsite power. Testing may beperformed at unity power factor or at a lagging powerfactor within the diesel-generator unit capability.The loading and unloading of a diesel-generator unitduring this test should be gradual and based on aprescribed schedule selected to minimize stress andwear on the diesel-generator unit.

    IEEE 387 7.5.3 Fast-start test MHI will perform testing in GTG SiteDemonstrate that each diesel-generator unit starts Testing Programfrom standby conditions (if a plant has normallyoperating pre-warm systems, this would constitute itsstandby conditions) and verify that the diesel-generator unit reaches required voltage andfrequency within acceptable limits and time, asdefined in the plant technical specifications.

    IEEE 387 7.5.4 Loss-of-offsite power (LOOP) test MHI will perform testing in GTG SiteDemonstrate by simulating a loss of offsite power that Testing Programa) The emergency buses are de-energized and theloads are shed from the emergency buses.b) The diesel-generator unit starts on the auto-startsignal from its standby conditions, attains the requiredvoltage and frequency within acceptable limits andtime, energizes the auto-connected shutdown loadsthrough the load sequencer, and operates for aminimum of 5 min.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.5.5 Safety injection actuation signal (SIAS) test MHI will perform testing in GTG Site

    Demonstrate that on a SIAS, the diesel-generator unil Testing Programstarts on the auto-start signal from its standbyconditions, attains the required voltage and frequencywithin acceptable limits and time, and operates onstandby for a minimum of 5 min.

    IEEE 387 7.5.6 Combined SIAS and LOOP test MHI will perform testing in GTG SiteDemonstrate by simulating a loss of offsite power in Testing Programconjunction with SIAS thata) The emergency buses are de-energized and theloads are shed from the emergency buses.b) The diesel-generator unit starts on the auto-startsignal from its standby conditions, attains the requirecvoltage and frequency within acceptable limits andtime, energizes the auto-connected shutdown loadsthrough the load sequencer, and operates for aminimum of 5 min.

    IEEE 387 7.5.7 Largest-load rejection test MHI will perform testing in GTG SiteDemonstrate the emergency diesel-generator unit's Testing Programcapability to reject a loss of the largest single load,and verify that the voltage and frequencyrequirements are met and that the unit will not trip onoverspeed.

    IEEE 387 7.5.8 Design-load rejection test MHI will perform testing in GTG SiteDemonstrate the diesel-generator unit's capability to Testing Programreject a load equal to 90-100% of the design loads,and verify that the unit will not trip on overspeed.

    9/28/2009, 10:59 AM

  • -2939908.xis, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.5.9 Endurance and load test MHI will perform testing in GTG Site

    Demonstrate load-carrying capability for an interval of Testing Programnot less than 8 h, of which 2 h should be at a loadequivalent to the short-time rating of the diesel-generator unit and 6 h at a load equivalent to90-100% of the continuous rating. (For the pre-operational test, use 2 h and 22 h.) Verify that voltageand frequency requirements are maintained.

    IEEE 387 7.5.10 Hot restart test MHI will perform testing in GTG SiteDemonstrate hot restart functional capability at full- Testing Programload temperature conditions by verifying that thedieselgenerator unit starts on a manual or auto-startsignal, attains the required voltage and frequencywithin acceptable limits and time, and operates for aminimum of 5 mrin.

    IEEE 387 7.5.11 Synchronizing test MHI will perform testing in GTG SiteDemonstrate the ability to Testing Programa) Synchronize the diesel-generator unit with offsitepower while the unit is connected to the emergencyload.b) Transfer this load to the offsite power.c) Isolate the diesel-generator unit.d) Restore the diesel-generator unit to standby status

    IEEE 387 7.5.12 Protective-trip bypass test MHI will perform testing in GTG SiteDemonstrate that specified automatic diesel- Testing Programgenerator unit trips are automatically bypassed asdesigned.Typically, engine overspeed and generator differentiacurrent trip are not bypassed.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.5.13 Test mode override test MHI will perform testing in GTG Site

    Demonstrate that with the diesel-generator unit Testing Programoperating in the automatic test mode while connectedto its bus, a simulated safety injection signal override,the test mode bya) Returning the diesel-generator unit to standbyoperations.b) Automatically energizing the emergency loads frorroffsite power.

    IEEE 387 7.5.14 Independence test MHI will perform testing in GTG SiteDemonstrate that, by starting and running (unloaded) Testing Programredundant units simultaneously, potential commonfailure modes that may be undetected in single dieselgenerator unit tests do not occur.

    9/28/2009, 10:59 AM

  • -2939908.xls, MHI

    Guide Section Statement, Requirement Design of US-APWR NoteIEEE 387 7.6 Records MHI will document all testing in GTQ

    Records shall be maintained for each diesel- Site Testing Program.generator unit to provide a basis for an analysis of theunit's overall performance. The records shall be Following completion of installationretrievable and shall provide a basis for verifying any the continuation of record keepingassumptions made. The documentation may also be will be by owner.used to shorten or extend the replacement intervalsor to extend equipment or station life. The recordsshall include, as a minimum, the following features:a) All start attempts, including those from bona fidesignals; maintenance, repair, and out-of-service timehistories, as well as cumulative maintenance andoperating data; cumulative statistical analysis ofdiesel-generator unit test results, together with resultsof operation of the diesel-generator unit whenrequired by actual demandb) Critical failure mechanisms, human errors, andcommon mode failures, including cause andcorrective actionc) Test parameter data indicated in table 4 that mayhave application for reliability and data trending

    9/28/2009, 10:59 AM