Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Mitigating the Threats of Invasive Alien Species in the Insular Caribbean: Full Size Project (FSP)
End Stage Report – Stage: KS2, KS3 and K4 up to June 2011)Project Executive: Lindsey Norgrove
Project Manager: Bob Ramnanan
Date:28 July, 2011
Project Finance Code: VM10076A
ESR Version: October 2009
Progress to this Stage: KS2
Stage: KS2 Stakeholder consultations & data collection (Q4, Y2)
Project To Date
-Planned
Project To Date
- Actual
Data collection for National
Invasive Species Strategies
(NISS)
•Collate national and regional information
on status of IAS and existing policies
and plans.
•Risk assessment
•National stakeholder consultation
•Produce draft NISS
• All countries capacity enhanced in use
of legal tools to manage IAS. .
•Draft NISS ahead of schedule and
within budget
Regional consultations on
marine, terrestrial & fresh
water IAS
•Host Terrestrial, Fresh Water and
Marine IAS consultation
•Establish working groups
•Prepare draft Regional IAS strategy
•Third regional consultations held in
Bahamas in March 2011
• Final Draft RISS circulated
•National and regional working groups
functional and serving as a coordinating
mechanism.
Critical Situation Analysis
(CSA) for each country
produced & disseminated
• Prepare CSA for each country
•Distribute CSAs (Y2Q1)
• St. Lucia's circulated. Others to be
circulated by end of 2011.
Project website functional &
linked to existing databases
• Establish Website (Y2Q4) •CIASNET.ORG launched and was
adopted as official site for CPHDF and
CISWIG
Initial levels of public
awareness of IAS assessed at
pilot sites
•Baseline surveys completed
•Distribute reports (Y2Q1)
• St. Lucia’s report circulated
•Reports for Bahamas and Jamaica
being finalized
• DR and TT completing surveys.
Progress to this Stage: KS3
Stage: KS3 Implementation of pilot projects
Project To Date
-Planned
Project To Date
- Actual
Maria Island, St Lucia: continuous monitoring plan in place.
•Recruit and train staff
•Map boundaries of project area
•Detail activity plan
•Implement continuous monitoring plan (Y2Q4)
•Maria island marine reserve mapped.
•Reef check conducted.
• Lionfish taskforce and emergency plan in place
•Offshore islands kept IAS free through baiting and surveillance operations.
Prevention of Frosty Pod Rot, •Baseline survey to • Trained staff engaged in surveillance. Prevention of Frosty Pod Rot,
Trinidad & Tobago: Continuous
monitoring in place; emergency
action plan developed.
•Baseline survey to determine if present
•Field and lab identification training
•Establish hotline
•Develop emergency plan
• Trained staff engaged in surveillance.
•National stakeholders sensitized to risk
•Pathways analysis 60% completed.
•PA for FPR initiated
Caulerpa in Trinidad & Tobago:
eradication programme completed. •Pilot replaced with pilot to promote Public Awareness of Aquatic IAS
•PA plan completed. Poster and flier on Lionfish distributed
Alto Velo & Cabritos, Dominican
Republic: eradication of invasive
vertebrates and 1 plant
completed.
•Complete baseline survey
•Devise best eradication strategies•Eradicate target species (Y2, Q1)
•Neem eradication started.
•Plan for invasive mammals being finalized.
•Feasibility study completed with IC.
Progress to this Stage: KS3
Stage: KS3 implementation of pilot
projects
Project To Date
-Planned
Project To Date
- Actual
Endemic Iguanas Jamaica: eradication of predators implemented
•Pre-eradication baseline survey of
goat island
•Removal of target species
•Train rangers and other stakeholders
•Prepare adaptive management plan
•Baseline survey completed and report
is being finalized.
•Predator trapping has lead to the most
significant increase in nests since 1991.
Invasive alien iguanas St. Lucia: Eradicated.
•Train field staff
•Train dogs and dog handlers
•Demonstrated feasibility of Canines to
locate nests and live invasive iguanas. Lucia: Eradicated. •Train dogs and dog handlers
•Develop detail eradication plan
•Implement line trapping grid.
locate nests and live invasive iguanas.
•Plans being put in place to establish a
local canine team. .
Lionfish control, Bahamas: research into reproductive biology and invasion ecology conducted
•Conduct research into reproductive
biology and invasive ecology
•Population control experiment
initiated
•Policy and regulatory reform to aid
management
•Experiments started on 12 sites.
•Fish surveys and quarterly removals
ongoing
•Stakeholders trained al level 4 Reef
fish identification.
Lionfish Control
Jamaica: management
programme instituted
•Conduct baseline survey
•Institute surveillance and monitoring
plan
•Prepare regulatory impact
assessment
•Research commenced on 5 pilot sites
around the island.
•Database now has 371 detailed
datasets. Gut content done for 358
specimens giving data on prey
preference.
Progress to this Stage KS3 Cont’d
Stage KS3
Implementation of pilot projects
Project To Date
- Planned
Project To Date
- Actual
Green mussel control,
Trinidad & Tobago:
environmental and
economic impact
assessment
•Baseline survey of Perna virdis
distribution
•Ecological assessment of Perna
virdis
•Economic impact assessment
•Ecological assessment of Pernaviridis has shown drastic declines in populations compared to initial invasion..
•Taxonomic identification of specimens collected during the extensive survey ongoing. •Training in management extensive survey ongoing.
Lower Black River
Morass, Jamaica: IAS
mapping & removal of
target species
•Ecosystem evaluation
•IAS Mapping
•Determine effective IAS control
strategies
•Adaptive Management plan
•Equipment (ATVs) purchased and there is agreement among all parties to begin research on the control strategies.
Nariva Swamp, Trinidad &
Tobago: development of
eradication/control
methods for Red Palm
Mite and Coconut Moth on
native plant species
•Baseline survey of invasive palm
pests and indicator palm species
•Surveillance and monitoring of
invasive palm pests
•Determine most effective control
strategies for invasive palm pests
•Baseline survey shows high degree of susceptibility by native Moriche palm that is main source of food for the endangered blue and gold macaw.
•Greenhouse studies initiated.
• Economic impact inititated.
Progress to this Stage KS4
Key Stage 4: Dissemination of findings & recommendations (Y4, Q4)
Project To Date
- Planned
Project To Date
- Actual
NISS for Dominican Republic, Jamaica, St Lucia & Trinidad & Tobago
•Disseminate draft National Invasive Species Strategies in year 3 Q4
•Draft disseminated for St. Lucia via the
CIASNET.ORG ahead of schedule.
CRISIS documents for marine, terrestrial & aquatic IAS
•Disseminate CRISIS document in Y4 Q4
•Final regional IAS strategy and action
plan for Fresh Water; Marine and
Terrestrial ecosystems circulated.
Best Practice Guidelines (based on Critical Situation Analyses)
•Disseminate Best Practices Guidelines
•25 papers submitted for inclusion in first
Best Practices guideline magazine. To be
circulated in September
Roll out use of CABI IAS Compendium
•Ensure project data is included in Compendium
•Roll out Compendium in participating countries
•Carded for years three and four
Dissemination of pilot project findings & recommendations
•Disseminate via website
•Final Conference
•Carded for years three and four
Post-intervention levels of public awareness of IAS assessed at pilot sites
•Conduct post implementation survey
•Carded for year four
Progress to this Stage- Financials
(£)
Report Stage
- Planned
Report Stage
- Actual
Original Full Project
- Planned
Project To Date
- Planned
Project To Date
- Actual
Full Project – Current Projection
Costs Billed to Project Donor
Gross Revenue:397,007 268,293 2,092,432 1,205,822 582,7402,092,432
Collaborator Costs:342,593 239,937 1,857,206 1,088,685 494,9331,882,951
Collaborator Costs:342,593 239,937 1,857,206 1,088,685 494,9331,882,951
Net Revenue:54,414 28,356 235,226 117,137 87,807209,481
CABI Implementation Costs
CABI Staff Costs: 35,892 26,093 126,063 73,014 76,876 126,063
Direct Costs:(other direct costs, for example
travel etc)
18,521 2,263 63,612 44,123 10,931 63,612
Net Profit/Loss:(‘Project Contribution’)
0 0 45,551 0 0 19,806
Net Project Contribution (%):
0 0 19% 0 0 9%
Dissemination of Results to Date
Dissemination and
Measures of Results
– Planned
Dissemination and
Measures of Results -
Actual
Effectiveness Key
Success?
(tick)
National Public
Awareness campaigns
(print and electronic) for
all the IAS in the five
participating countries.
•Participating countries have had good press coverage in national press. In particular Bahamas, Jamaica, and Saint Lucia.
Increasing press coverage is leading to a greater awareness of the issue which should encourage policy makers to take it more seriously.
�
more seriously.
Posting Reports and
other outputs on the
Website CIASNET.ORG
•Some newspaper articles on the site.
•All publications produced by the project will be posted to the site
Paper on the site accepted for publication in the 47th
proceedings of the CFCS meeting. .
Dissemination of Special
Publications and Project
Reports
•National Critical Situation Analyses
•Baseline reports
•Feasibility studies for IAS eradication
•PA publication “Invasion of the Aliens”
CSA and NISS for Saint Lucia disseminated via website. Others to be circulated by years end.
Feasibility study circulated via website
Best practices manual to be distributed in September
�
Impact of Project to Date
Planned Impact Actual Impact Comments Key
Success?
(tick)
Scientific/Technical:
•Increased national capacity to address potential risks posed to biodiversity of global significance from IAS
•Participating countries participated in regional workshop on “Legal tools for combating IAS in the Caribbean”
•Five post graduate students of UWI conducting research on
•44 Participants (including legal experts) benefitted from the regional training in collaboration with the Environmental Law Institute.
•The results would contribute to fill an indentified gap in IAS
�
�UWI conducting research on economic impact of IAS in the Caribbean.
to fill an indentified gap in IAS knowledge in the Caribbean.
�
•Increased prevention of new IAS introductions impacting global biodiversity
The project is building capacity and providing guidance in strengthening regulatory framework for managing IAS
Training workshops and pilot implementation is building capacity at all levels.
�
Impact of Project to Date cont’d
Planned Impact Actual Impact Comments Key
Success?
(tick)
Commercial:
•Access to data and best practice established, and public awareness of IAS strengthened
•Established baseline data for IAS in pilot sites
•Updated critical situation analysis by five countries
•Public and Private domain CIASNET.ORG established.
•Completed reports on the CIASNET.ORG site
•Printed Best Practices manual to be circulated by September 2011 and via the web
•Adopted by CISWIG and �
CIASNET.ORG established. •Adopted by CISWIG and CPHDF as their official website
Social:
•Increased regional
cooperation to reduce risk
posed to biodiversity of global
significance
•New regional and international organizations providing in kind funding and support.
•Countries actively cooperating to develop regional strategy through the three regional working groups: Fresh Water; Marine and Terrestrial Working Groups.
•International Conservation (IC); Caribbean Regional Agriculture Policy Network (CaRAPAN); ICRI and NOAA providing support on Lionfish
•Project invited to collaborate on training on IAS in Plant Quarantine course organized by UWI and USDA/APHIS
�
Impact of Project to Date cont’d
Planned Impact Actual Impact Comments Key
Success?
(tick)
Environmental
•Increased capacity to eradicate, and improve control and management of IAS impacting global biodiversity
•To date Saint Lucia has prevented the invasive iguana from affecting the endemic one and is actively pursuing a surveillance of new marine IAS in the Maria island nature reserve.
•Tracker dogs demonstrated effectiveness in detecting invasive iguana.
�
reserve.
•Dominican Republic completed feasibility study with assistance of IC for IAS on Alto Velo and Cabrito Islands and with assistance from TNC Catalina Island
•Jamaica and Bahamas actively researching means of reducing the impact of Lionfish. Project participating with ICRI and other stakeholders to develop a regional Lionfish strategy.
•Eradication to begin in November to avoid nesting of endemic iguana. Keen interest from surrounding communities has cause a rethink of methodologies for eradication.
•The project work on Lionfish in the Bahamas and Jamaica is contributing to the understanding of management of this marine invasive. international partners NOOA, ICRI and REEF are partnering in these efforts.
�
�
Additional Project Outcomes
● Key Successes (other than those identified as Impact on Project or Dissemination of
Results)
● The implementation of the project by the five countries to date and exposure gained via national and regionally press and attendance at regional and international meetings has consolidated CABI CLA’s leadership position on IAS issues in the wider Caribbean. This is reflected by the offers of collaboration from organisations such as International Conservation (IC); Caribbean Agricultural Policy Network (CaRAPN) among others that were not among the original project collaborators. SPAW.
● Benefits Achieved● Benefits Achieved● The project continues to leverage additional funds both in cash and in kind.
● The work done in this project and the recognition of CABI by organisations and countries in the region will make introducing programmes like plant wise easier for CABI. .
Has there been increased Scope for CABI than originally
planned? (If so, provide comments)
● Greater project management demands are being made of CABI but we are getting less in terms of anticipated consultancies and income.
Lessons Learned
What … Comments
went Well: 1. Adaptive
management employed
to make the project more
sound.
2. Leveraging of funds
3. Proactive approach of
1. The project only envisaged measuring impact of Perna
virdis this was expanded following the workshop held in
June 2010. With a team of students doing economic
impact assessments of IAS.
2.Attendance at international and regional meetings and
CABI’s leadership has assisted in the leveraging of funds. 3. Proactive approach of
UNEP’s Task Manager
(TM)
CABI’s leadership has assisted in the leveraging of funds.
3.The TM has been proactive in managing risks on the
project especially those of a political nature.
went Badly: Lack of
capacity and high level of
bureaucracy and new
personnel contributed to
slow start of project.
This is reflected in lengthy delays in revising work plans
and budget and getting required approvals prior to
implementation. Poor understanding by NEAs and
Collaborators on CABI’s role of oversight in technical
matters.
was Lacking: Involvement
of Arne Witt in the review
of pilot projects prior to
submission of the project.
Arne Witt who is providing technical backstopping to the
project has a problem with in all the pilot projects. As the
methodologies and budgeted amounts are inadequate to
generate the expected results.
Lessons Learned cont’d
What … Comments
would you do
Differently Next
Time: 1. Wider
Consultation with
CABI’s technical
experts.
2. Choose pilot
1. Arne Witt who had the experience in managing a similar
project was not consulted prior to the submission of the FSP
to GEF his prior involvement could have helped improve
technical soundness and speedier implementation of pilots.
2. It was known prior to submission of the project that the
eradication of Caulerpa taxifolia pilot in Trinidad and Tobago
was no longer feasible. This pilot was supposed to have 2. Choose pilot
projects carefully
3. Document Roles
and Responsibilities
clearer.
4. Adopt best
practices for IAS
management into
account in project
development
was no longer feasible. This pilot was supposed to have
been funded up to 2/3 by co-financing. It is difficult for the
replacement to co-finance to the same value since a large
amount of the co-finance was in kind.
3. Although the PCAs that we signed spoke to roles and
responsibilities in project implementation this should have
been communicated clearer during the preparation phase.
4. Doing a feasibility study prior to eradication of any IAS is
considered a best practice. This was not incorporated in the
project design.
Any Other
Comments
No.
Commentary on Variations from Plan● Outputs: Outputs for components 1 (national strategies); 2
(Regional Strategies) and 3 (Information) are ahead of target Components 4&5 (pilot projects) are behind target.
● Schedule: components 1; 2 and 3 are ahead of schedule. Components 4&5 are more than 6 months behind schedule in some instances.
● Financials: The total project only expended 26% of its total ● Financials: The total project only expended 26% of its total budget to date or 48% of its planned expenditure to date.
● Events Affecting Performance: Late singing of PCA in TT; General bureaucracy and low capacity at the national level. Weather affected implementation in St. Lucia and Trinidad.
● Input / Effect of Donor, Partners, End-Users etc: UNEP and all NEAs are proactive in managing risks.
● Current Assessment of Business Case: measures being adopted to minimize variance in time and budget.
Key Risks – Project( ) = Previous Rating
Risk Owner Likelihood
(L)
(1=Low;
3=High)
Impact
(I)
(1=Low;
3=High)
Total
(L x I)
(1=Low; 9=High)
Management Strategy
(Choose from Prevention,
Reduction, Contingency,
Transference, Acceptance,
and give brief description)
Update
One or more partners fails to meet UNEP/GEF’s acceptance criteria
Project Manager
M H H Reduction: Take all possible steps to support & assist partners
Transference: Ensure that CABI is not
Low.
All have been
accepted by
UNEP/GEF. This was
overstated in the PID.
UNEP has assured criteria that CABI is not
contractually liable for shortcomings by partners
UNEP has assured
that CABI will not be
held accountable for
partner shortcoming.
Governments commitment to regional collaboration is reduced due to changes in the
political environment
Project Manager
L M L Reduction: The existence of the CISWG provides the basis for regional collaboration and the FSP should be able to feed into this working group. The PSC will also have members from each country’s NEA, allowing greater regional collaboration.
Low.
Participating Countries
have given
undertaking at the last
IPSC meeting to
advancing the regional
IAS agenda at the
appropriate regional
fora such as CISWIG
and COTED.
Key Risks – Project( ) = Previous Rating
Risk Owner Likelihood
(L)
(1=Low;
3=High)
Impact
(I)
(1=Low;
3=High)
Total
(L x I)
(1=Low; 9=High)
Management Strategy
(Choose from Prevention,
Reduction, Contingency,
Transference, Acceptance,
and give brief description)
Update
Lack of cross-sectoral
communication and
coordination
Project Manager
M H H Reduction: The establishment of an inclusive, multi-sectoral NSC in each country will provide a forum for
Medium.
The management
strategy has been
effective as there is a
wide cross section of
public and NGOs on
the NSC. Private between agencies
forum for communication between agencies and different sectors.
the NSC. Private
sector involvement
has been limited.
Key stakeholders do not agree to national strategies or participate in these strategies
Project Manager
L M L Reduction: Stakeholder workshops, liaison and networking will be undertaken to ensure they are fully engaged and able to contribute to the development of the national strategies.
Low.
No need for change in
proposed strategy at
this time.
Key Risks – Project( ) = Previous Rating
Risk Owner Likelihood
(L)
(1=Low;
3=High)
Impact
(I)
(1=Low;
3=High)
Total
(L x I)
(1=Low; 9=High)
Management Strategy
(Choose from Prevention,
Reduction, Contingency,
Transference, Acceptance,
and give brief description)
Update
Public not receptive to environmental information and
display no interest in IAS
Team Leaders
L L L Reduction: A multi-media public awareness campaign will be implemented, including a focus on the potential benefits
Low.
With apparent climate
change and other
natural disasters
public interest in the
environment is
increasing. interest in IAS control.
the potential benefits of IAS control and the use of school groups,
which may present a more receptive audience.
increasing.
Enforcement of regulations may
be difficult due to a lack of awareness of IAS issues at both the institutional and public level.
Project Manager
M M M Reduction: The public awareness campaign should enable stronger enforcement of regulations to be undertaken, as the public will become aware of the regulations, as well as general IAS issues.
High.
This is higher due to
the capacity/HR
issues at the national
levels. Requested
assistance of the
Project Directors and
NSCs. Also getting
high profile champions
will be pursued in each
country.
Key Risks – Project
Risk Owner Likelihood
(L)
(1=Low;
3=High)
Impact
(I)
(1=Low;
3=High)
Total
(L x I)
(1=Low; 9=High)
Management Strategy
(Choose from Prevention,
Reduction, Contingency,
Transference, Acceptance, and
give brief description)
Update
Key personnel lost from key institutions and stakeholder groups
Project Manager
M M M Reduction: A full time national co-ordinator, funded by the project, will be appointed in each country. Robust, well-documented
Low.
Full involvement
of NSCs and
Project Directors
is helping to
reduce this risk. documented management systems will be established which are not dependant on individuals
Biodiversity is threatened by other pressures on the habitat and ecosystems
Team Leaders
H L M Acceptance: All five countries have a NBSAP describing threats to biodiversity and strategies to reduce these threats. All five countries also have designated protected areas, and two of the pilot sites (Jamaica and St. Lucia) are in protected areas.
Medium
Project will benefit
from other
initiatives such as
those be pursued
by UNEP-CEP
and the SPAW
Protocol under the
CATAHENA
Convention.
Key Risks – Project
Risk Owner Likelihood
(L)
(1=Low;
3=High)
Impact
(I)
(1=Low;
3=High)
Total
(L x I)
(1=Low; 9=High)
Management Strategy
(Choose from Prevention, Reduction,
Contingency, Transference,
Acceptance, and give brief
description)
Update
Changes in IAS status affected by climatic variability, changing the impact of
Project Manager
M M M Reduction: Best practice guidelines for “Climate Change & Invasives; and Early Warning Systems”, from the ‘Toolkit for Best Prevention and Management Practices of
Medium.
Task manager is
looking into
getting support
from US experts
to do training
workshop. impact of project interventions
Management Practices of Invasive Alien Species’ will be integrated into IAS management strategies and methodologies for pilot activities.
Unforeseen financial pressure
due to current economic climate
Executive
M H H Acceptance: All financing has been agreed and committed with all partners providing a detailed breakdown of their project contributions. However the value of local co-financing relative to GEF funding will be unavoidably affected by exchange rate fluctuations.
Medium
Some
International
Collaborators
such as
USDA/APHIS and
IICA have
contributed more
than plan. Also
leveraging new
sources.
Commentary on Projection of Project
● Events Affecting Future Performance: Hurricane Thomas could delay implementation of pilot activities in Saint Lucia.
● Risks
● Previous Risk Total: 38
● Current Risk Total: 31
● Comments: Proactive nature of UNEP;CLA RD and NSC is assisting in managing the risks.
● Overall – Likely Impact on Next Stage: Time variance of approximately six months
● Overall - Likely Impact on Project: Could lead to delay of more three to six months. Increase activities in the area of PA should utilize unspent funds once approved by UNEP.