123
MIT Rocket Team USLI 2011 Critical Design Review January 23, 2011 Project Valhalla

MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

MIT Rocket Team

USLI 2011

Critical Design Review

January 23, 2011

Project Valhalla

Page 2: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

2

REPORT AUTHORS

Christian Valledor Project Manager

Andrew Wimmer Team Safety Officer Tripoli Rocket Association Level 3

Ben Corbin EHS Representative

Ryan McLinco Launch Vehicle Lead

Jonathan Allen Payload Lead

Eric Peters Recovery Lead

Ben Couchman Avionics Lead

Anna Ho Outreach Coordinator

Jake Bograd-Denton

Michelle Burroughs

Jason Elizalde

Jedediah Storey

Leo Tampkins

Page 3: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

3

NAMING CONVENTIONS

NASA and the space industry have typically been very creative with their acronyms for

spacecraft and space instruments. From LEM to SRB, NASA has come up with the

most recognized TLAs the -world has ever known, approaching even greater rhetorical

strength with C.O.L.B.E.R.T.. We in the MIT Rocket Team also share such an affinity for

acronyms, so we decided to put some extra thought into the naming of our rocket

project. We also honor NASA‟s tradition of naming conventions based off mythological

gods from ancient civilizations. However, where NASA chooses its naming inspiration,

we wholeheartedly disagree; the Greek and Roman gods are too overused for us to

name our rocket parts after. Instead, we turned to the Norse gods, whose deeds are so

epic and intense that modern comic book heroes are based off of them.

While most people are familiar with the god Odin, few are familiar with the one-handed

god if single combat, victory, and heroic glory, for which the third day of our modern

week is named after. Scandinavians would have called this god in his human form a

yager, which is German for "hunter" or someone who tracks animals. This is appropriate

considering the goal of the UAV payload is to track targets on the ground and

autonomously report their location. For these reasons, we are naming the entirety of our

rocket the Tactical Yager Rocket – TYR

One of the most famous Norse gods is the Norse god of fire. A brother to Odin and

father of a wolf, this god has inspired many names including a company that produces

rocket engines. We at the MIT Rocket Team couldn't pass up the opportunity to use his

name for a piece of our rocket. This is why we have named the structural section of the

rocket that houses the motor and spits fire the Ludicrously Overpowered Kinetic

Impulser – LOKI

Vikings were inspired to be brave in their fights because only the righteous and brave

who die in battle would enter the gates of Valhalla to sit with Odin and fight by his side

in the end of times. One son of Loki, an eight-legged horse that travels across land, sea,

and air, is responsible for delivering fallen warriors to their glorious fate. This god carries

those valiant warriors who die in battle over land and sea across the Rainbow Bridge

through the gates of Vahalla. For this reason, we have named our motor the Single-

Loaded Electrically-Ignited Propulsively Numerous Integrated Rocket – SLEIPNIR

From the basis of these Norse naming inspirations, there was only one logical choice for

building a machine that would reach the heavens, named after the home of Odin himself

– Project Valhalla

However, not even the Norse gods were powerful enough by modern standards when it

came to naming the crown jewel of our rocket: the UAV payload we are ejecting from

the rocket to perform a search mission. The one series of magnificent beings that exists

today from which we can draw truly incredible names from is none other than the

Transformers series. While casual fans of the series may often bicker about who their

Page 4: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

4

favorite Transformer is, often arguing between Optimus Prime and Megatron, there is

only one Transformer that truly and unequivocably incites emotions of grandeur, terror,

destruction, power, and might, and it first appeared in the 1986 Transformers theatrical

release as the Transformer that was so powerful it literally ate planets. For this reason,

we have given our unmanned aerial vehicle the name UNmanned Integrated Craft for

Rescue with Onboard Navigation – UNICRON

Page 5: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

5

CONTENTS

Report Authors ................................................................................................................ 2 Naming Conventions ....................................................................................................... 3 1 Summary of CDR ................................................................................................... 10

1.1 Team Summary ................................................................................................ 10 1.2 Launch Vehicle Summary ................................................................................ 10

1.3 Payload Summary ............................................................................................ 10

2 Changes Since PDR .............................................................................................. 11 2.1 Launch Vehicle Changes ................................................................................. 11 2.2 Payload Changes ............................................................................................. 11

2.3 Activity Plan Changes ...................................................................................... 12

3 Design and Verification of Launch Vehicle ............................................................. 12 3.1 Mission Statement, Requirements, and Mission Success Criteria ................... 12

3.2 Major Vehicle Milestone schedule .................................................................... 13

3.3 System Level Review ....................................................................................... 13 3.3.1 Rocket Design and Subsystems ................................................................ 14

3.3.2 Subsystem Requirements and Descriptions .............................................. 14 3.3.3 Demonstrate design meets system level requirements ............................. 39

3.3.4 Workmanship and relation to success ....................................................... 39 3.3.5 Planned Component, functional, and static testing .................................... 40

3.3.6 Status and plan for remaining Manufacture and Assembly........................ 41

3.3.7 Integrity of design ...................................................................................... 42

3.4 Recovery System ............................................................................................. 43

3.4.1 Parachute choice and testing .................................................................... 43

3.5 Safety and Failure analysis .............................................................................. 44

3.6 Mission Performance Predictions ..................................................................... 46

3.6.1 Mission Performance Criteria .................................................................... 46

3.6.2 Flight Profile Simulation ............................................................................. 46

3.6.3 Scale Model Test ....................................................................................... 50 3.6.4 Stability ...................................................................................................... 51

3.7 Payload Integration Plan .................................................................................. 51

3.7.1 Installation and removal, dimensions, precision fit ..................................... 51

3.7.2 Tasking & Integration Schedule ................................................................. 55 3.7.3 Compatibility of elements ........................................................................... 55

3.7.4 Simplicity of integration procedure ............................................................. 56 3.8 Launch Operation Procedures ......................................................................... 56

3.8.1 Recovery Preparation ................................................................................ 64

3.8.2 Motor Preparation ...................................................................................... 67

3.8.3 Igniter Installation ...................................................................................... 67

3.8.4 Setup on Launcher .................................................................................... 68 3.8.5 Troubleshooting ......................................................................................... 68

3.8.6 Post Flight Inspection ................................................................................ 68 3.9 Vehicle Safety .................................................................................................. 69

3.9.1 Identification of Safety Officers .................................................................. 69

Page 6: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

6

3.9.2 Analysis of Failure modes and Mitigations................................................. 69

3.9.3 Potential Hazards ...................................................................................... 71

3.9.4 Environmental Concerns ........................................................................... 76

4 Payload Criteria ...................................................................................................... 76 4.1 Testing and Design of Payload Experiment ..................................................... 76

4.1.1 System Level Review ................................................................................ 76 4.1.2 Demonstrate design meets system level requirements ............................. 97

4.1.3 Workmanship and relation to success ....................................................... 98 4.1.4 Planned Component, functional, and static testing .................................... 99 4.1.5 Status and plan for remaining Manufacture and Assembly...................... 100

4.1.6 Describe Integration Plan ........................................................................ 103 4.1.7 Instrumentation precision and repeatability ............................................. 104

4.2 Payload Concept Features and Definition ...................................................... 105

4.2.1 Creativity & Originality of Payload ........................................................... 105

4.3 Science Value ................................................................................................ 106 4.3.1 Payload Science Objectives .................................................................... 106 4.3.2 Payload Success Criteria ......................................................................... 106

4.3.3 Experimental Logic, Approach, Verification ............................................. 106 4.3.4 Describe test and measurement, variables and controls ......................... 107

4.3.5 Relevance of Expected Data ................................................................... 109 4.3.6 Accuracy and Error Analysis .................................................................... 109

4.3.7 Experiment Process Procedures ............................................................. 109 4.4 Payload Safety ............................................................................................... 110

4.4.1 Identification of Safety Officer .................................................................. 110

4.4.2 Failure Modes .......................................................................................... 110

4.4.3 Potential Hazards .................................................................................... 116

4.4.4 Environmental Concerns ......................................................................... 117

5 Activity Plan ......................................................................................................... 118 5.1 Budget Plan.................................................................................................... 118

5.2 Timeline ......................................................................................................... 119 5.3 Educational Engagement ............................................................................... 119

6 Conclusion ........................................................................................................... 122

Page 7: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

7

Table of Figures Figure 3-1: Overall Rocket ............................................................................................ 14

Figure 3-2: Tube Coupler Segment ............................................................................... 16

Figure 3-3: Nose Cone .................................................................................................. 16

Figure 3-4: Nose Cone Coupler .................................................................................... 17

Figure 3-5: Motor Centering and Retention ................................................................... 18

Figure 3-6: Recovery System Bulkhead ........................................................................ 19

Figure 3-7: Sabot Overview ........................................................................................... 20

Figure 3-8: Payload Integration Stacking ...................................................................... 20

Figure 3-9: Recovery Configuration .............................................................................. 21

Figure 3-10: Sabot Hard Point ....................................................................................... 22

Figure 3-11: MAWD Flight Computer ............................................................................ 24

Figure 3-12: ARTS2 Flight Computer ............................................................................ 25

Figure 3-13: ARTS2 Telemetry Transmitter .................................................................. 25

Figure 3-14: ARTS2 Telemetry Receiver ...................................................................... 26

Figure 3-15: ARTS GUI ................................................................................................. 27

Figure 3-16: ARTS Data Analyzer ................................................................................. 27

Figure 3-17: Power Switch ............................................................................................ 28

Figure 3-18: Avionics Package ...................................................................................... 29

Figure 3-19: Axial Case BCs ......................................................................................... 33

Figure 3-20: Lateral Case BCs ...................................................................................... 33

Figure 3-21: Axial Case Results .................................................................................... 34

Figure 3-22: Lateral Case REsults ................................................................................ 35

Figure 3-23: Motor Retention BCs ................................................................................. 37

Figure 3-24: Motor Retention Displacement .................................................................. 37

Figure 3-25: Motor Retention Stress ............................................................................. 38

Figure 3-26: Predicted CM and CP Locations ............................................................... 46

Figure 3-27: Predicted Acceleration and Velocity Profiles ............................................. 48

Figure 3-28: Simulated Altitude Profile .......................................................................... 49

Figure 3-29: Scaled Launch Simulated Results ............................................................ 50

Figure 3-30: Scale Model Rocket .................................................................................. 50

Figure 3-31: Tube-Tube interface .................................................................................. 53

Figure 3-32: Main parachute/shock cord attached to eye bolt and recovery system

bulkhead ........................................................................................................................ 54

Figure 3-33: Nose cone/upper body tube interface ....................................................... 55

Figure 3-34: Integrated avionics assembly, main parachute, sabot and UAV assembly 55

Figure 4-1: Airfoil Comparison ....................................................................................... 82

Figure 4-2: NACA 4412 Polar ........................................................................................ 83

Figure 4-3: Tail .............................................................................................................. 84

Figure 4-4: Wing Rotator Mechanism ............................................................................ 86

Figure 4-5: UAV In Stowed Configuration ..................................................................... 87

Figure 4-6: Stowed tail .................................................................................................. 87

Figure 4-7: Wing Boundary Conditions.......................................................................... 90

Page 8: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

8

Figure 4-8: Effective Strain ............................................................................................ 91

Figure 4-9: Wing Deflection ........................................................................................... 92

Figure 4-10: New Wing Boundary Conditions ............................................................... 93

Figure 4-11: New Effective Strain .................................................................................. 94

Figure 4-12: New Wing Deformation ............................................................................. 94

Figure 4-13: Wing Rotator Boundary Conditions ........................................................... 95

Figure 4-14: Stress Distribution ..................................................................................... 96

Figure 4-15: Deformation .............................................................................................. 96

Figure 4-16: Ground Station User Interface ................................................................ 102

Table of Tables

Table 3-1: Rocket Budget Summary ............................................................................. 14

Table 3-2: Hardware Specifications............................................................................... 26

Table 3-3: Launch Loading ............................................................................................ 30

Table 3-4: Recovery Shock Calculations ....................................................................... 31

Table 3-5: Carbon Fiber Properties ............................................................................... 31

Table 3-6: Axial Stress Calculations .............................................................................. 32

Table 3-7: Buckling Calculations ................................................................................... 32

Table 3-8: Bending Calculations ................................................................................... 32

Table 3-9: Payload Bulkhead Bolt Shear Calculations .................................................. 35

Table 3-10: Threaded Rod Sizing ................................................................................. 35

Table 3-11: Motor Retention Sizing ............................................................................... 36

Table 3-12: Stringer Sizing ............................................................................................ 38

Table 3-13: Parachute Descent Rates .......................................................................... 43

Table 3-14: Potential Rocket Failure Modes ................................................................. 44

Table 3-15: Scale Model Dimensions ............................................................................ 50

Table 3-16: Tasking and Integration Schedule .............................................................. 55

Table 3-17: Possible Launch Failure Modes ................................................................. 68

Table 3-18: Potential Failure Modes ............................................................................. 69

Table 3-19: Tool Use Injury Potentials and Mitigations ................................................. 73

Table 4-1: UAV Characteristics ..................................................................................... 77

Table 4-2: Stability Analysis .......................................................................................... 78

Table 4-3: Flight Case Analysis ..................................................................................... 79

Table 4-4: Deployment Loading .................................................................................... 88

Table 4-5: Foam Material Properties ............................................................................. 88

Table 4-6: Fiberglass material Properties ...................................................................... 89

Table 4-7: Fiberglass Layup Properties ......................................................................... 89

Table 4-8: Wing Deflection Calculations ........................................................................ 90

Table 4-9: Carbon Fiber Layup Properties .................................................................... 92

Table 4-10: Carbon Fiber Deflection Calculations ......................................................... 92

Table 4-11: Avionics testing ........................................................................................ 101

Table 4-12: Precision of Transmitted Data .................................................................. 104

Table 4-13: Sensor Precision ...................................................................................... 104

Page 9: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

9

Table 4-14: Potential UAV Failure Modes ................................................................... 110

Table 4-15: Potential Avionics and ground Station Failure Modes .............................. 114

Table 5-1: Budget ........................................................................................................ 118

Table 5-2: Total Budget ............................................................................................... 118

Page 10: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

10

1 SUMMARY OF CDR

1.1 TEAM SUMMARY

MIT Rocket Team,

Massachusetts Institute of Technology

Cambridge, MA

Dr. Paulo Lozano

Faculty Advisor

[email protected]

Andrew Wimmer

Safety Officer, Rocket Owner, TRA # 9725 Level 3

[email protected]

John Kane

Local NAR Contact

[email protected]

1.2 LAUNCH VEHICLE SUMMARY

The purpose of the launch vehicle is to reach an apogee of 1 mile and deploy the UAV

payload after descending to an altitude of 2500 feet. Diagrams of the vehicle are

provided below in the rocket section.

The carbon fiber and fiberglass airframe will be 132 inches long, the inner diameter of

the rocket tube is designed to be 6 inches, and the outer diameter of the fins is 16.25

inches. Furthermore, the mass of the rocket is projected to be 44.5 lbs (not including a

payload mass of 7 pounds) and ballasted (in the nose cone) as necessary in order to

reach an apogee of 5280 feet using a single commercial Cesaroni L1115 motor.

Payload deployment will be performed at 2500 feet using two sabot halves that will be

pulled out of the tube by the drogue parachute and separated using the deployable UAV

wings.

1.3 PAYLOAD SUMMARY

The rocket payload will consist of a 3.75 ft long, 7.5 pound UAV that will be launched

from the rocket at an altitude of 2500 ft. It will fit inside the rocket by means of folding

wings, tail, and propeller. The UAV will have a TR 35-30A 1700kv Brushless Outrunner

motor onboard but will function as a glider for the majority of its flight.

The UAV will fly to GPS coordinates supplied by a human operator. The UAV will not

require advanced airplane or flight knowledge, which will make it useful for search and

rescue type missions as well as for scientific research. The UAV will carry GPS tracking,

airspeed sensors, atmospheric sensors, an accelerometer, a video capture device, and

an onboard computer.

Page 11: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

11

2 CHANGES SINCE PDR

2.1 LAUNCH VEHICLE CHANGES

A number of changes have been made to the rocket design since PDR in order to solve

problems and improve the design. The changes revolve primarily around review of the

design to simplify fabrication and integration.

Airframe

The length of the rocket was increased to 132 in to allow for an internal coupler

between the two airframe segments

Fin slots in the motor centering rings will extend to the motor tube to improve

strength

Rocket diameter decreased from 6.5” to 6”

Inter-segment coupler changed from external doublers to internal phenolic

coupler

Integration access door added to upper part of intersegment coupler so permit

integration with the new coupler design

Material type changed to Soller Composites braided carbon fiber

Recovery

The recovery simulation was updated to reflect the parachutes being X-form

rather than hemispherical

Drogue and main parachute diameters increased to 4ft and 13ft, respectively, to

account for decreased drag of X-form profile.

Deployment

Standard (non-expanding) foam will be used for the sabot

Propulsion

The sub-scale test motor will be an Aerotech G80

The full-scale test flight motor has been changed to a Cesaroni K1085

Avionics

Two plates are used for mounting avionics components within the avionics

assembly to allow the threaded rod to pass through the middle

2.2 PAYLOAD CHANGES

Avionics

Page 12: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

12

Replaced uBlox GPS module with MediaTek to reduce cost

Removed external SCP1000 sensor from flight computer to use pressure sensor

internal to flight computer

Replaced SD Card board with FAT16/32 support to one without to reduce cost.

2.3 ACTIVITY PLAN CHANGES

Since the completion of the preliminary design review, the team has moved into the final

stages of planning for educational outreach events at both the Boston Museum of

Science and the MIT Museum. The event at the Museum of Science will be held on

Saturday February 5th, with two 15-20 minute talks. One discussion will focus on rocket

technology and history, and another will be a discussion of the space industry. Two

hands-on workshops will be conducted before, during, and after the presentations: one

will allow participants will build their own Alka-Seltzer, and another where participants

will build their own parachutes. We are currently working on securing space to set off

the rockets and drop the parachutes. We have set a date for our outreach event at the

MIT Museum will follow a similar format. The MIT Museum event will take place on

Sunday, May 1, from 10am to 1pm.

3 DESIGN AND VERIFICATION OF LAUNCH VEHICLE

3.1 MISSION STATEMENT, REQUIREMENTS, AND MISSION SUCCESS

CRITERIA

Mission Statement

Use a rocket to rapidly deploy a UAV capable of completing search and rescue type

missions with the use of a ground based system requiring little to no UAV flight training.

Constraints

Follow all rules of NASA USLI 2011, including but not limited to:

Rocket apogee shall be closest to but not exceeding 5280ft.

At no time may a vehicle exceed 5600ft

Minimum science payload deployment of 2500ft

Must carry one PerfectFlight MAWD for official altitude recording

Dual deployment recovery must be used

Dual altimeters must be used for all electronic flight systems

Each altimeter must have its own battery and externally located arming switch

Recovery and payload electronics must be independent from each other

At all times the system must remain subsonic

Shear pins must be used in the deployment of both the drogue and main parachute

Page 13: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

13

All components of the system must land within 2500ft of the launch site in a wind

speed of 10 mi/hr

Scientific method must be used in the collection, analysis and reporting of all data.

Electronic tracking devices must be used to transmit the location of all components

after landing

Only Commercially available, NAR/TRA certified motors may be used

Full-scale flight model must be flown prior to FRR

Students must do 100% of all work for USLI competition related projects

$5000 maximum value of rocket and science payload as it sits on the launch pad

Requirements

Launch UAV with Rocket

Meet the needs of NASA Science Mission Directorate including:

o Gather atmospheric measurements of: Pressure, Temperature, relative

humidity, solar irradiance, and ultraviolet radiation at a frequency no less than

once every 5 seconds upon decent, and no less than once every minute after

landing.

o Take at least two still photographs during decent, and at least 3 after landing.

All pictures must be in an orientation such that the sky is at the top of the

frame.

o All data must be transmitted to ground station after completion of surface

operations.

o Science payload must carry GPS tracking unit.

Successfully perform model search and rescue/reconnaissance mission

3.2 MAJOR VEHICLE MILESTONE SCHEDULE

The full schedule for rocket development may be found in Appendix 2. Key dates are

presented below for reference:

9/10: Project initiation

11/19: PDR materials due

12/30: Scaled test launch

1/24: CDR materials due

2/15: Balloon deployment test

2/30: Full-scale test launch

3/21: FRR materials due

4/14: Competition launch

3.3 SYSTEM LEVEL REVIEW

Page 14: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

14

3.3.1 ROCKET DESIGN AND SUBSYSTEMS

As described in the summary section, the purpose of the rocket is to reach 1 mile and deploy the UAV at an altitude of 2500 feet. This will be accomplished with a Cesaroni L1115 motor and a 132 inch long, 6 inch diameter airframe. The UAV will be contained within a sabot, which will be located just aft of the nosecone. The drogue parachute will be above the sabot, the main parachute below the sabot, and the avionics below the recovery system. The overall rocket can be seen in Figure 3-1.

FIGURE 3-1: OVERALL ROCKET

Furthermore, the rocket budget summary (for mass and cost) can be seen in Table 3-1.

TABLE 3-1: ROCKET BUDGET SUMMARY

System

Mass (kg) Cost (USD)

Rocket

Propulsion 5.46 552.00

Airframe-Body 3.62 455.09

Airframe-Fairing 1.01 27.00

Avionics/Comm 0.99 947.38

Payload Support Equipment 1.82 152.24

Recovery 2.19 434.60

SUBTOTAL 15.09 2568.31

The subsystems, which will be described in greater detail below, are:

Airframe

Recovery

Deployment

Propulsion

Avionics/Communications

3.3.2 SUBSYSTEM REQUIREMENTS AND DESCRIPTIONS

Page 15: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

15

Airframe

The airframe is comprised of the following components:

Body Tube

Nose Cone

Fins

Motor Retention System

Recovery System Bulkhead

Each of these will be described in detail below.

The body tube is a carbon fiber laminate tube of inner diameter 6”. The laminate is a 2-

ply layup of Soller Composites 14.5 oz/sqyd biaxial sleeve carbon fiber fabric and

Aeropoxy 2032/3665 matrix. Carbon fiber was chosen as the material for the primary

structure due to its high strength-to-weight ratio, toughness, and ease of manufacture to

customized shapes and dimensions. The biaxial sleeve was chosen due to difficulties in

fabricating wrinkle-free tubes. All layups for the rocket are done in-house using a

custom oven and vacuum bagging equipment in the rocket team lab. For fabrication and

transportation reasons, it would be difficult to make the entire tube in one segment. As a

result, the body tube is split into 2 segments, with a “seam” just below the base of the

sabot, as seen in Figure 3-2. The two segment lengths are 56” for the upper segment

and 48” for the lower segment. The seam between the tubes is accomplished by adding

use of a phenolic coupler that is epoxied to the upper segment. The use of an internal

coupler was accomplished by lengthening the upper segment.

Page 16: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

16

FIGURE 3-2: TUBE COUPLER SEGMENT

Additionally, the tube will have 2 pressure relief holes (of 0.25” diameter, unless

otherwise specified) in each of the following locations:

Just above the fins in the propulsion section

Avionics bay: the hole for the switches will double as a pressure relief hole

In the middle of the section between the avionics bay and the sabot

In the nose cone

The nose cone is a 2-ply carbon laminate, just like the body tube. The shape is a

tangent ogive for manufacturing simplicity, and the length was chosen to fit the drogue

parachute and maintain stability of the rocket. The length is 27 in and shape is shown in

Figure 3-3.

FIGURE 3-3: NOSE CONE

The nose cone is mounted to the body tube using 4 nylon 2-56 bolts (MMC 97263A077)

fastened to the inside using Helicoils (MMC 91732A203), which will act as shear pins.

Shear area is provided using doublers on both the top of the tube and the inner portion

of the nose cone, as shown in Figure 3-4. Similarly, the doublers are on the outside of

the tube to allow the sabot to cleanly exit the body tube. Bolts are used because they

can be easily threaded into the inner doubler during integration and will fail at low

loading since they are plastic.

Page 17: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

17

FIGURE 3-4: NOSE CONE COUPLER

Four fins were chosen with the dimensions as shown in Appendix 3 for rocket stability

reasons (see Section Error! Reference source not found. and Modeling XX). The fins

are a carbon fiber, 3/16” plywood, carbon fiber sandwich laminate to maximize stiffness

with minimum mass. The fins are located in position and angle relative to the rocket

using slots that are laser-cut into the motor centering rings. Oversized slits added to the

body tube to allow the fins to pass through, but provide no DOF restrictions. Fabrication

of the fins is as follows:

Sand the laser-cut plywood core edges (not tabs) to a taper

Laminate the plywood core with a ply of carbon fiber on each face using standard

plate lamination techniques (see manufacturing plan section)

Obtain body tube with motor tube and centering rings installed

Affix fins to the centering rings/motor tube assembly using 5 minute epoxy and let

cure

Apply another layer of carbon fiber across and between the fins, i.e. “Tip-to-Tip”

The motor mount will consist of a commercial 75mm motor tube and laser-cut, plywood

centering rings. There will be four centering rings in total, one located at each end of the

motor tube and two in the middle. The farthest forward will be made from 1/2” plywood.

The farthest aft centering ring will be made from two rings of 3/16” plywood sandwiched

together; the OD of the forward ring will be the ID of the body tube, and the OD of the

aft ring will be the OD of the body tube. This will transfer some of the thrust load through

compression of the aft centering ring, rather than through shear in the epoxy joints

holding the motor mount in the body tube. The middle centering rings will be made from

½” plywood, with four slots to accept the fin tabs. The fin tabs will also be slotted at the

centering ring locations to allow the fins to contact the motor tube for additional support.

One will be located near the forward edge of the fin tabs and the other near the aft edge

of the fin tabs, close to the aft-most centering ring. Plywood is chosen because it is

relatively cheap, strong, light, and able to withstand the high temperatures of the motor

casing without deforming.

Motor retention will be accomplished as follows. Two 8-32 T-nuts will be mounted to the

aft-most centering ring, 180° apart at a radius of roughly 2.375”. 1.5” 8-32 screws will go

through two small clearance holes in the motor retention plate and screw into the T-nuts

to hold the plate in place. The motor retention plate will be a piece of 1/32” steel sheet

that has a hole cut in it; this hole will be made large enough for the motor‟s nozzle to fit

through, but small enough to keep the motor casing from falling out of the motor tube.

There is a thrust ring on our 75mm hardware that prevents the motor casing from

moving forward during burn.

The mounting and retention system can be seen in Figure 3-5.

Page 18: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

18

FIGURE 3-5: MOTOR CENTERING AND RETENTION

The recovery system bulkhead serves as a reaction point for lateral forces from the

payload, which come from two sources: inertial force of payload during boost, and

drogue drag force between drogue parachute deployment and main parachute

deployment. Axial forces will be reacted through a threaded rod to the motor casing, for

reaction via the motor mount assembly. The bulkhead must also be removable to

enable removal of the avionics bay, which sits between the motor retention bulkhead

and the recovery system bulkhead. The threaded rod will be used to affix the payload

support bulkhead to the airframe. No hardware will be used to affix the payload support

bulkhead to the lower body segment directly. The body tube will have a doubler

concentric with the recovery system bulkhead to allow for transfer of shear loads. The

bulkhead will need to attach to both the charge released locking mechanism and the

quick link to the main parachute shock cord. As a result, the bulkhead needs to have an

eye bolt that is capable of transferring the loads to the bulkhead, which will be done

through via an eyenut (MMC 3274T41) and threaded rod (MMC 95412A652). The

design of the bulkhead is shown in Figure 3-6. Furthermore, the bulkhead will be

manufactured from polycarbonate for its relative cheap price (compared to other plastic

rod stock).

Page 19: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

19

FIGURE 3-6: RECOVERY SYSTEM BULKHEAD

Recovery

A detailed description of the recovery process can be found in the Section 3.2.

Deployment

Deployment of the UAV and parachutes is as follows.

Initially, the stacking of the rocket above the recovery system bulkhead is as follows (as

seen in Figure 3-7 and Figure 3-8):

Payload Bulkhead attachment quick links

Charge released locking mechanism

Main parachute

Sabot base hardpoint

Sabot halves (cradling UAV)

Sabot top hardpoint

Drogue parachute quick link

Drogue parachute

Page 20: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

20

Nose cone ejection charge

Note: There is a redundant igniter in the charge in the nose cone and a redundant

igniter in the charge released locking mechanism.

FIGURE 3-7: SABOT OVERVIEW

FIGURE 3-8: PAYLOAD INTEGRATION STACKING

The deployment then occurs as follows:

Just after apogee, nose cone ejection charge fires

Nose cone separates, but remains attached to the drogue parachute

Drogue parachute deploys

Rocket descends to 2500 feet

At 2500 feet, the charge released locking mechanism fires. Mechanism to be

used is the “FruityChutes L2 Tender Descender”

The drogue parachute pulls the sabot out of the rocket tube

As the sabot leaves the tube, the spring-loaded UAV wings push the sabot

halves apart

The sabot pulls the main parachute bag out behind it

Main parachute deploys and remains attached to the main body tube

After deployment, the rocket will fall to the ground in two sections, as shown in Figure

3-9:

Page 21: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

21

Sabot and nose cone, which are attached to the drogue parachute via the upper

hardpoint and a shock cord

Main body tube, which is attached to the main parachute via the recovery system

bulkhead and a shock cord

FIGURE 3-9: RECOVERY CONFIGURATION

Deployment into two pieces (rather than one) is performed in order to minimize the

chance of contact between the sabot/UAV and the body tube after separation. This will

enable the drogue parachute to pull the UAV/sabot away from the rocket to allow clean

separation and minimize the chances of entanglement.

As described above, the UAV is encased within the two sabot halves, which are made

of foam and laminated in a ply of fiberglass so as to maintain shape. Force will be

transferred between the hardpoints using a 4x 10-24 nylon threaded rods (MMC

94435A355), which will mount to the upper and lower hardpoints using clearance holes

and nuts. Finally, plastic hardpoints are glued to the upper and lower ends of the sabot

halves. These hardpoints enable recovery and deployment system fixtures to be

attached to the sabot. One of these hardpoint sets is shown in Figure 3-10. As can be

seen below, the hardpoint halves overlap to ensure force transfer between halves when

in tension. Adhesive is applied as shown in the figure. An eye bolt is threaded into the

lower hardpoint half, which serves as the attachment points for:

Lower hardpoint: the charge released locking mechanism

Page 22: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

22

Upper hardpoint: the drogue parachute and upper shock cord (attaches to nose

cone)

It should be noted that the upper hardpoint will require eye bolts in both hard point

halves due to ensure both sabot halves remain attached to the drogue parachute.

FIGURE 3-10: SABOT HARD POINT

Propulsion

The rocket will be powered by a Cesaroni L1115 solid rocket motor. This motor was

chosen because it is commercially available and does not require any modifications in

order to reach the flight altitude requirement of 5280 feet based off the mass estimates

available this early in the design process. The motor is actually more powerful than

required given the current mass estimates, but this will ensure that even with mass

creep over multiple design iterations, the rocket mass can be optimized with ballast

weight to come as close to 5280 feet as the models can predict.

The Cesaroni L1115 is also reloadable and relatively inexpensive compared to its

Aerotech counterparts. It does not require extensive ground support equipment

compared to hybrid motors, which were originally considered for propulsion. The L1115

is 75mm in diameter, 24.5 inches in length, and has a total impulse of 4908 Newton-

seconds over a 4.49 second burn time.

For the full-scale test, the Cesaroni K1085 solid rocket motor will be used. The K1085

has enough power to launch the full system up to an altitude of 2000 feet and still has

the same diameter as the L1115, so minimal changes will have to be made to the motor

housing section for the full scale test launch. The K1085 is 75mm in diameter, 13.8

inches long, and provides 2486 Newton-seconds of thrust over a 4.84 second burn time

Avionics/Communications

The purpose of the rocket avionics is to control parachute deployment while collecting

rocket flight data and relaying it to the ground station.

Page 23: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

23

The rocket avionics system is comprised of two flight computers (miniAlt/WD and

ARTS2) and an ARTS2 transmitter. The miniAlt/WD flight computer serves as a backup

altimeter that measures the rockets altitude during launch and stores in on the computer

board and will fire a redundant igniter for the recovery charge after the ARTS is

programmed to. This data can be retrieved after rocket recovery where the miniAlt/WD

flight computer is connected to the ground station computer via a miniAlt/WD to PC

Connect Data Transfer Kit. The ARTS2 flight computer handles primary parachute

deployment as well as determining the rocket state variables and flight states. The

ARTS2 Transmitter transmits the data from the ARTS2 to the ground station receiver.

Rocket Flight data includes:

State Variables:

o Altitude

o Maximum Altitude

o Velocity

o Acceleration

Flight State:

o On Pad

o Thrust

o Coast

o Apogee

o Descent

o Drogue parachute Deployment

o Main parachute Deployment

Power Supply

Three 9 volt batteries will provide power for the flight computers and transmitters. One

of the batteries will be dedicated towards powering the miniAlt/WD while the other two

will power the ARTS2 flight computer and telemetry system to create a power source

redundancy in case one was to fail. On the ARTS2 board one battery powers the two

systems while the other powers the igniters. They will be located inside the removable

rocket avionics section of the rocket, alongside the rest of the avionics system.

Hardware Description

MiniAlt/WD Logging Dual Event Altimeter (PerfectFlite)

This flight computer measures the rocket‟s altitude by sampling the surrounding air

pressure relative to the ground level pressure. The altitude above the launch platform is

calculated every 50 milliseconds. After launch, the device continuously collects data

until landing. Altitude readings are stored in nonvolatile memory and can be

downloaded to a computer through a serial data I/O connector. The miniAlt/WD has two

Page 24: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

24

channels for parachute deployment; one for the main parachute and the other for

drogue parachute.

FIGURE 3-11: MAWD FLIGHT COMPUTER

Altimeter Recording and Telemetry System (ARTS2 Flight Computer) (Ozark

Aerospace)

This flight computer calculates the rockets altitude by sampling the surrounding air

pressure relative to the ground level pressure and measuring the rockets acceleration.

The rate at which the altitude above the launch platform is calculated is adjustable and

will be set at 100 samples per second with an overall recording time of 5.4minutes.

Altitude readings are sent to the ground station via the ARTS2 telemetry transmitter.

Also the altitude and other flight data are stored in nonvolatile memory to be

downloaded to a computer through a serial data I/O connector. The ARTS2 has two

channels for parachute deployment; one for the main parachute and the other for

drogue parachute.

1. Terminal Connector

2. GPS Connector

3. Programming header

4. Battery Configuration

5. Main Battery Connection

6. Power Switch Connector

7. 9V Pyro Battery Connection

8. Option Switches

9. Output Channel Terminals. Channel 1 Apogee, Channel 2 Main.

Page 25: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

25

FIGURE 3-12: ARTS2 FLIGHT COMPUTER

ARTS2 Telemetry Transmitter (Ozark Aerospace)

100mW 900MHz spread spectrum transmitter

Integrated wire antenna on the board is connect to a larger antenna on the rocket

Works with the ARTS-TT2-W and ARTS-TT2-RPSMA

ARTS flight computer gets connected directly to the transmitter board

Transmits real time flight data to the ARTS telemetry receiver

FIGURE 3-13: ARTS2 TELEMETRY TRANSMITTER

ARTS2 Telemetry Receiver (Ozark Aerospace)

Receives telemetry from the ARTS2 transmitter and sends it to the computer

Connect to the ground station computer via a serial cable

Page 26: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

26

FIGURE 3-14: ARTS2 TELEMETRY RECEIVER

TABLE 3-2: HARDWARE SPECIFICATIONS

Hardware Operating

Voltage

Minimum

Current Dimensions Weight

Altitude

Accuracy

Operating

Temperature

Maximum

Altitude

MiniAlt/WD 6-10 volts 10

milliamps

0.90”W,

3.00”L,

0.75”T

20

grams +/- .5%

0C to 70C

25,000

feet

ARTS2 9-25 volts

1.40"W,

3.75"L,

0.75"T

~20

grams

100,000

feet

ARTS2

Transmitter

6.8 -25

volts

~2.50"W,

~7.50"L,

~1.50"T

~200

grams

100,000

feet

Switches

The single power switch is a push-on/push-off switch that delivers power to all of the

avionics components when on. The three arming switches are RBF pull-pin switches.

Software

Telemetry software:

Displays flight data in real time using text, 2-D, and 3-D graphical user interfaces.

Page 27: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

27

FIGURE 3-15: ARTS GUI

ARTS Software V1.61 (Data Analyzer):

Used in analyzing the data collected by the ARTS2 and also configuring parachute

deployment and sample rate settings.

FIGURE 3-16: ARTS DATA ANALYZER

Parachute Deployment

Both the ARTS2 and the miniAlt/WD are programmed to deploy the drogue parachute at

apogee, while the main parachute and the UAV are set to deploy after apogee is

reached at an altitude of 2500 feet. This creates system redundancy in case one of the

flight computers fails.

Transmission from Rocket to Ground Station

Since the carbon fiber material of the rocket body tube disrupts any RF signals the wire

on the ARTS2 transmitter will be extended out of the avionics bay. There are two

possible options for doing this.

Page 28: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

28

1) The 14 gauge copper wire is connected to the transmitter antenna via a binding

post. It then extends from the avionics bay and warps around the upper section

of the rocket body. Each loop of the helix is spaced 33 centimeters apart to

prevent destructive interference. Kapton tape is placed above and below the wire

to prevent contact with the carbon fiber.

2) The ARTS2 transmitter antenna is extended directly to the fiberglass nose cone

and connects to a 25 inch long (4 millimeter in diameter) RF antenna. It should

be noted that the nose cone is currently carbon fiber, so it would need to be

changed to fiberglass if this modification is made.

Arming and Power Switches

FIGURE 3-17: POWER SWITCH

The avionics bay contains two plunger type switches that connect the power to the

miniAlt/WD flight computer and the ARTS2 altimeter telemetry system and two switches

with Remove Before Flight [RBF] pins to arm the flight computers. The power and

arming switches are used in order to prevent premature firing of ejection charges and

power usage before the rocket is on the launch pad.

Mounting/Placement

Placed in the avionics bay, which is in the lower segment of the rocket as described

below. The flight computers will be mounted in such as way so that their pressure and

acceleration readings are not disturbed. This means that the barometer on both the

ARTS2 and miniAtl/WD would have to have at least a 1 centimeter clearance from any

closest surface parallel to it. Also, the ARTS2 will be mounted with its length parallel to

the rocket‟s length in order for the accelerometer to record proper positive values.

The avionics will be mounted into an avionics integration tube, which is shown below in

Figure 3-18.

Page 29: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

29

FIGURE 3-18: AVIONICS PACKAGE

As can be seen in the figure, the boards and battery are mounted to a plate, which will

be mounted vertically in the rocket frame. A series of L brackets will be used to mount

this vertical avionics plate to the avionics tube, which can be integrated with the rocket

in a preassembled form. Additionally an ELT will be mounted to the side of the avionics

assembly. The hole in the top of the avionics package is for wires to reach into the

upper portion of the rocket (a similar hole exists in the recovery system bulkhead). The

switches on the bottom image are used to arm each of the following just before launch:

ARTS2/ARTS2 Transmitter Power Switch

MAWD Power Switch

ARTS2 Arming Switch

MAWD Arming Switch

The power switch will be push-on/push-off. The arming switches will be armed by

removing Remove Before Flight [RBF] tags. The switches will also have the capability of

being flipped without reinsertion of the RBF tag.

The bottom avionics plate is grooved so that the phenolic tube packaging shell can be

attached. The boards and batteries can be mounted to the avionics plate, which is

mounted to the top plate using 4x 6-32 fasteners. Nutplates are glued to the insides of

each of the mounting brackets, such that bolts can be used without standard nuts. After

insertion into the tube, four additional 6-32 fasteners are bolted from the bottom plate

Page 30: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

30

into the bottom L brackets, the holes of which are threaded. After this is assembled, the

whole avionics package may be inserted into the rocket as described in the payload

integration plan. This design was chosen to make the avionics assembly as modular as

possible, while still maintaining access just before flight and low mass/cost of the

assembly.

3.3.2.1 DRAWINGS

[See CDR-Drawings document]

3.3.2.2 ANALYSIS RESULTS

In order to verify the design of the rocket, a battery of analysis was applied to the rocket airframe, bulkheads, and mechanisms. The order of analysis is as follows:

Define loading conditions

Design part

Use hand calculations to size the part

Validate hand calculations using finite element method

Re-size as necessary Loading Conditions Determining loading conditions for a vehicle that must withstand a variety of largely unknown dynamic and static loading is a difficult task. Furthermore, the rocket airframe can be significantly overdesigned without applying too significant of a penalty to the mass budget. As a result, the loading conditions were often estimated using significant margin to account for uncertainty. Launch Loading is summarized in Table 3-3.

TABLE 3-3: LAUNCH LOADING

Launch Loading

Aero Loading 90 lbf

Peak Thrust 385 lbf

Payload Mass 15 lbm

Max Accel 8 G

Total Axial 595 lbf

MUF 1.5

Design Axial 892.5 lbf

Total Lateral 150 lbf

MUF 1.5

Design Lateral 225 lbf

Aerodynamic loading is determined from the Rocksim model, peak thrust is determined

from the Cesaroni L1115 Thrust Curve, payload mass is determined from the UAV

Page 31: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

31

design and sabot, and maximum acceleration is determined from the Rocksim model.

Although many of these peak loads are applied independently from each other, to

provide for a conservative calculation, the loads are summed to create a total load,

which is then margined by a 1.5 model uncertainty factor, resulting in a design axial load

of 890 lbf. Lateral loading is determined by summing half of the aerodynamic and

payload forces and margining by a 1.5 model uncertainty factor. This is assumed to be

highly margined since as much as half of each of these loads is unlikely to be applied in

the lateral direction. Regardless, the design lateral load is therefore 225 lbf.

Recovery shock calculations are determined by examining the change in momentum of the rocket due to deployment, as shown in Table 3-4.

TABLE 3-4: RECOVERY SHOCK CALCULATIONS

Recovery Shock Calculations

Initial Rate 64 ft/s

Final Rate 18 ft/s

g 32 ft/s^2

t 0.1 s

accel 460 ft/s^2

Gs 14.375

Rocksim Gs 8

MUF 2

Design Gs 28.75

Design Force 431.25 lbf

Recovery calculations show the descent rates of the system prior to deployment (under the drogue) to be 64 ft/s and of the main rocket after deployment (under tha main) to be 18 ft/s. Assuming a deployment time of 0.1s, this results in 14 Gs. Adding a model uncertainty factor of 2 to this results in 29 Gs, which (given the mass of the payload system) results in a design recovery shock force calculation of 430 lbf. Body Tube Analysis As described in the design section, the body tube is made from Soller Composites Biaxial Weave carbon fiber. The modulus and strength are taken from Soller Composites and the resulting strain allowable is derived, as shown in Table 3-5-5.

TABLE 3-5: CARBON FIBER PROPERTIES

Material Properties

E 4675000 psi

v 0.3

E (claimed) 34 Msi

E_lam (claimed)

4.675 Msi

strength 110 ksi

Page 32: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

32

strain 0.02352941 strain

FOS 3

strain w/MOS 7843.13725 µstrain

Using these properties, hand calculations could be performed for axial compression, global buckling, and bending. These intermediate calculations as well as the resulting margins of safety can be seen in Table 3-6 through Table 3-8. It should be noted that, for the sake of being conservative, lateral loads are taken to be applied at the top of the rocket and restrained at the base.

TABLE 3-6: AXIAL STRESS CALCULATIONS

Axial Stress Calculations

ID 6 in

OD 6.092 in

Area 0.87372718 In^2

Axial Stress

1021.4859 psi

strain 0.0002185 strain

218.499658 µstrain

MOS 34.8954211

TABLE 3-7: BUCKLING CALCULATIONS

Buckling

r/t 81.5217391

Z 62136.005

Kc 4000

Fcr 3182.89745 psi

L/r 28.2666667

Axial Load 2780.98402 lbf

MoS 2

Axial Load Allowable

1390.49201 lbf

MOS 0.55797424

TABLE 3-8: BENDING CALCULATIONS

Bending

I 7.620816554 in^4

z 3.75 in

M 23850 in-lbf

stress 11735.94711 psi

strain 0.002510363 strain

2510.363018 µstrain

MOS 2.124304015

Page 33: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

33

In order to verify these calculations, a finite element model was developed in Femap. The applied boundary conditions of the lateral case are shown in Figure 3-19. The boundary conditions in the axial load case are shown in Figure 3-20.

FIGURE 3-19: AXIAL CASE BCS

FIGURE 3-20: LATERAL CASE BCS

This model was then solved using NEi Nastran, resulting in the ply 1 effective strain and displacement outputs for the axial case, as shown in Figure 3-21. The results for the lateral case are shown in Figure 3-22.

Page 34: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

34

FIGURE 3-21: AXIAL CASE RESULTS

Page 35: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

35

FIGURE 3-22: LATERAL CASE RESULTS

Payload Bulkhead Analysis As described in the design part of the document, 4x #6 bolts are used in order to fasten the tube segments together. From this, the effective strain may be determined and compared to allowables. This calculation takes into account the allowable shear area, using a 4 ply thick doubler and assuming that only two of the bolts are being used, as shown in Table 3-9.

TABLE 3-9: PAYLOAD BULKHEAD BOLT SHEAR CALCULATIONS

P/L Bulkhead Bolt Hole Shear

n 4

n "used" 2

hole dia 0.0997 in

t 0.092 in

shear area 0.0091724 in^2

stress 23508.0241 psi

strain 0.00502845 strain

5028.45435 µstrain

MoS 0.55975111 µstrain

The 3/8” threaded rod is used to connect the parachute shock loads to the motor retention system, as shown in Table 3-10.

TABLE 3-10: THREADED ROD SIZING

Threaded Rod Sizing

rod dia 0.2983 in

Page 36: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

36

A_tot 0.069887 in^2

stress 6170.67566 psi

allowable stress

33000 psi

MoS 4.34787466

Motor Retention Analysis Since the threaded rod transfers shock load to the motor retention system, the motor retention system must be able to react the load of the deployment. It must also, however, be able to react the original axial load. The initial sizing calculations are as shown in Table 3-11.

TABLE 3-11: MOTOR RETENTION SIZING

Motor Retention Sizing

# Used 3

thk 0.5 in

ID 3 in

OD 6 in

avg D 4.5 in

"b" 14.1371669 in

I 0.14726216 in^4

M 669.375 in-lbf

z 0.25 in

stress 1136.36629 psi

failure stress

1500 psi

MoS 0.31999691

This was validated using Ansys Workbench. The loading conditions are shown in Figure 3-23.

Page 37: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

37

FIGURE 3-23: MOTOR RETENTION BCS

The resulting displacement is shown in Figure 3-24 and the stress is shown in Figure 3-25.

FIGURE 3-24: MOTOR RETENTION DISPLACEMENT

Page 38: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

38

FIGURE 3-25: MOTOR RETENTION STRESS

Payload Support Equipment Sabot Stringer Sizing As described in the design portion of the document, the stringers are 4x #10 rods that connect the top and bottom parts of the sabot together. The size of these aluminum-threaded rods can be verified as shown in Table 3-12.

TABLE 3-12: STRINGER SIZING

Stringer Sizing

stringer dia 0.1318 in

# 4

A_tot 0.05457336 in^2

stress 7902.20724 psi

rho 0.041 lb/in^3

length 50 in

sabot dia 6.5 in

mass 0.11187539 lbm

allowable stress

33000 psi

MoS 3.17604841

3.3.2.3 TEST RESULTS

[See Section 3.1.3]

3.3.2.4 MOTOR SELECTION

[See Section 3.1.3]

Page 39: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

39

3.3.3 DEMONSTRATE DESIGN MEETS SYSTEM LEVEL REQUIREMENTS

[See section 3.1.3]

3.3.4 WORKMANSHIP AND RELATION TO SUCCESS

Through past experiences the MIT Rocket Team has identified that the workmanship of

individual components plays an integral role in the final outcome of any project. With

this in mind, the team has set in place schedule of testing and teaching of the various

skills necessary for the fabrication and assembly of all components. Fabrication

methods used by the team are learned from experienced sources, and all methods are

tested at various scales. Team members are taught basic fabrication techniques under

the instruction of senior members, and all components are inspected and tested as

necessary before they are cleared for flight.

The rocket tubes needed for this year‟s USLI competition are the largest composite

tubes that the MIT Rocket Team has constructed to date. As such, the team has spent a

large amount of time evaluating our fabrication techniques and their ability to scale up.

In this pursuit, the team has constructed a series of tube sections using various

materials and methods to test the feasibility of our upcoming fabrication schedule. In the

course of this investigation the team has learned a few important lessons.

First and foremost, the team has learned that techniques normally employed for the

fabrication of smaller diameter body tubes do not easily work for the large diameter

needed for this project. The normal technique employed by the team required plain-

weave fabric to be wrapped around a mandrel during the wet lay-up procedure until the

appropriate number of plies had been achieved. The layup would then be wrapped in a

release film and a layer of breather material. Finally a vacuum bag would be

constructed around the whole layup and when a good vacuum was pulled, the whole

bag would be placed into our custom built curing oven. However when this process was

applied to the large diameter tube sections, we found that because the fabric was

wrapped around the tooling, there was no way to prevent wrinkles from forming within

the layup when a vacuum was pulled. Furthermore because the wrinkles were

throughout the structure of the tubes section, the structural integrity of the part was

weakened. With this lesson we realized we had to move onto a different fabrication

technique.

The team has since developed a relatively simple way of constructing large diameter

tube sections without wrinkles. The new fabrication method uses many of the same

techniques of the old method, but now a tubular braided fabric is being used in placed of

the plain-weave fabric. This change allows for the fabric to adjust diameter to exactly

match what is required. Furthermore, a new bagging method has been developed, and

tested with sample sections, which results with no seam in the finished tube.

Page 40: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

40

For the fabrication of other vehicle components, such as the rocket fins and faring, a

similarly high standard of workmanship is held. To this end, the plywood cores of our

fins are first designed in SolidWorks and then the model is used to generate a cut file for

a Computer-Numeric-Controlled laser cutter available on campus through the Edgerton

Center. This method allows for extremely accurate cores, which are then faced with

carbon fiber as described in section [3.1.7]. For the fabrication of the faring, a computer

model is first generated in SolidWorks, and a full sized template is created of the

complex surface. Next, a custom router jig is used to turn down a foam core to the

appropriate shape according to the template exported from SolidWorks. In this way we

are left with a tool, which will allow for the precise fabrication of multiple faring.

3.3.5 PLANNED COMPONENT, FUNCTIONAL, AND STATIC TESTING

The team‟s first priority will be to perform qualification testing on the structural

components of the rocket. The tests to be performed are as follows and will be

completed after the structural test article is completed post-CDR:

The body tube will be tested using a crush test in the axial direction and bending

test in the lateral direction. It will be tested with a variable mass, such as sand, to

determine the stiffness and failure force.

A crush test will also be performed between two tubes to verify the strength of

the tube coupler.

The bulkheads and their attachment to the body tube will be tested with a pull

test, in which the tube will be fixed and variable mass will be used to determine

pullout force.

The fins will also be tested using a series of pull/push tests (also using a variable

mass and gravity) in order to test the fin strength in each of the 3 orthogonal

directions.

In addition to structural testing, several deployment and recovery tests will need to be

performed. These tests will be performed after the UAV prototype is completed post-

CDR.

Deployment altitude will be verified using barometric testing. The team has

constructed a small vacuum chamber, which is capable of roughly simulating

ambient pressure. As a result, the avionics package will be placed into the

vacuum chamber to ensure that it sends charge ignition commands at the right

times.

In order to verify the failure force of the shear pins, a representative tube will be

used with a representative nose cone, with the open side of the tube covered.

The shear pins are mounted into the relevant brackets in flight orientation. The

black powder charge will be ignited at the closed end to validate the mass of

black powder to be used.

Page 41: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

41

UAV deployment will also require testing, which can be performed in a couple of

phases: (1) the force of the drogue parachute on the sabot can be simulated to

ensure that the sabot separates from the tube and the UAV deploys and (2)

integrated deployment tests from a balloon platform. This test will be described

further in Section 4.3.4.

A series of avionics tests will also be performed. A summary of the tests is provided

below. Greater detail can be found in Section 4.3.4. These tests will be performed prior

to the FRR.

The emergency locator beacons (transmitters and receiver) operation will be

checked, by searching for the beacons in a representative location.

Each computer will also be checked to see if they downlink properly to the

ground station. This will be performed on the ground in a field and then on a

balloon platform using a representative ground station and rocket.

Finally, these tests will culminate in a representative scaled test launch, which will verify

functionality of all systems, including the UAV.

3.3.6 STATUS AND PLAN FOR REMAINING MANUFACTURE AND ASSEMBLY

To produce components of a high caliber the MIT Rocket Team has decided to use a

four-stage fabrication and assembly process. After the finalization of the designs, the

team moved straight into a fabrication-testing period where possible manufacturing

methods were evaluated for their feasibility. In this period the team decided on the

appropriate technique and materials needed for the fabrication of each component of

the flight vehicle. In this stage, fabrication methods were tested on representative

components sized to the approximate dimensions of the specified design. The testing

phase of production has been completed as of mid-January and the team has now

moved into the prototyping phase for the flight vehicle.

In the prototype phase, full-scale components will be constructed using the methods

determined during the testing phase of development. The resulting components will

then be assembled into a full-scale prototype with extra components being produced for

destructive testing methods. When the components are all fully tested, the any

components needing design changes will be refabricated to the new specifications and

a proto-flight model will be constructed.

The purpose of the proto-flight model is to allow for full-scale flight-testing procedures

with, and without the completed payload. It is expected that the proto-flight model will be

completed in early February to allow for multiple launch attempts before the Flight

Readiness Review. Upon successful flight testing of the proto-flight vehicle, any

necessary design changes and repairs will be made to the airframe for the flight model

to be launched in Huntsville AL. Furthermore spare components will be manufactured to

the specifications of the flight model to mitigate the loss of components in transit to AL.

Page 42: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

42

As stated above, the team is currently in the prototype phase of fabrication on track for

completion in early February. The team is has purchased all materials necessary to

construct a complete vehicle as well as a set of spare components. Construction is

currently underway and the components will be tested as listed in section 3.1.6.

3.3.7 INTEGRITY OF DESIGN

[See section 3.3.1]

3.3.7.1 SHAPE AND FIN STYLE

[See section 3.3.1]

3.3.7.2 PROPER USE OF MATERIALS FOR: FINS, BULKHEADS,

STRUCTURE

[See section 3.3.1]

3.3.7.3 PROCEDURES: ASSEMBLY, ATTACHMENT,

ALIGNMENT

[See section 3.3.1]

3.3.7.4 MOTOR MOUNTING AND RETENTION

The motor mount will consist of a commercial 75mm motor tube and laser-cut, plywood

centering rings. There will be four centering rings in total, one located at each end of the

motor tube and two in the middle. The farthest forward will be made from 1/2” plywood.

The farthest aft centering ring will be made from two rings of 3/16” plywood sandwiched

together; the OD of the forward ring will be the ID of the body tube, and the OD of the

aft ring will be the OD of the body tube. This will transfer some of the thrust load through

compression of the aft centering ring, rather than through shear in the epoxy joints

holding the motor mount in the body tube. The middle centering rings will be made from

½” plywood, with four slots to accept the fin tabs. The fin tabs will also be slotted at the

centering ring locations to allow the fins to contact the motor tube for additional support.

One will be located near the forward edge of the fin tabs and the other near the aft edge

of the fin tabs, close to the aft-most centering ring. Plywood is chosen because it is

relatively cheap, strong, light, and able to withstand the high temperatures of the motor

casing without deforming.

Motor retention will be accomplished as follows. Two 8-32 T-nuts will be mounted to the

aft-most centering ring, 180° apart at a radius of roughly 2.375”. 1.5” 8-32 screws will go

through two small clearance holes in the motor retention plate and screw into the T-nuts

to hold the plate in place. The motor retention plate will be a piece of 1/32” steel sheet

that has a hole cut in it; this hole will be made large enough for the motor‟s nozzle to fit

through, but small enough to keep the motor casing from falling out of the motor tube.

Page 43: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

43

There is a thrust ring on our 75mm hardware that prevents the motor casing from

moving forward during burn.

3.3.7.5 STATUS OF VERIFICATION

[See section 3.1.6]

3.4 RECOVERY SYSTEM

3.4.1 PARACHUTE CHOICE AND TESTING

When the drogue parachute is deployed at apogee, it will need to support a total system

mass of 23 kg. A 4ft diameter parachute will be used to achieve a descent rate of 75

ft/s.

Once an altitude of 2500 ft AGL is reached, the tether securing the sabot inside the

rocket will release, allowing the drogue parachute to pull the sabot and the main

parachute out of the rocket. At this point, the rocket body will separate from the

sabot/nose/drogue section and free fall as the main parachute deploys. This will allow

for a considerable gap between the rocket body and the sabot, decreasing the risk of

the deployed UAV colliding with the rocket or becoming entangled in the main

parachute.

With the UAV deployed and the sabot separated from the rocket body, the remaining

structure has a mass of 15 kg. With a 14ft diameter parachute, a final descent rate of 19

ft/s can be achieved. Under the 4ft parachute, the nose cone and sabot will have a final

descent rate of 26 ft/s.

TABLE 3-13: PARACHUTE DESCENT RATES

Final Descent Rate

System Under Drogue 75 ft/s

Nose/Sabot Final Descent

Rate 26 ft/s

Rocket Body Under Main 19 ft/s

The drogue parachute and nose cone are directly connected to the sabot. This

assembly is initially connected to the recovery system bulkhead via the explosive tether.

The main parachute is also secured directly to the recovery system bulkhead (not by the

tether). Its deployment is constrained by the sabot.

The calculations for the amount of black powder required to successfully separate the

nose cone from the body tube can be found below.

Page 44: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

44

The charge release mechanism will contain 0.2 grams of black powder. This number is

recommended by the manufacturer.1

The drogue deployment charge must provide ample force to break the shear pins,

accelerate the nose cone away from the rocket body, and accelerate the drogue

parachute out of the nose cone. Four #2-56 nylon screws (MMC 94735A177) will be

used as shear pins to retain the nose cone. Nylon 6/6 has a shear strength of 10ksi.2

With this, the maximum shear force can then be calculated by the following equation:

,

where A is the cross-sectional area of the bolt, and τ is the shear strength. For a #2-56

screw, the minimum pitch diameter is 0.0717 in.3 This leads to a shear force of 40 lbf.

With four pins, the charge will have to provide a minimum force of 120 lbf. Adding 25%

margin, the charge will need to provide a total force of 150 lbf. This leads to a required

black powder mass of 2.1 g.4

3.4.1.1 TEST RESULTS FROM EJECTION CHARGES AND

ELECTRONICS

3.5 SAFETY AND FAILURE ANALYSIS

TABLE 3-14: POTENTIAL ROCKET FAILURE MODES

Risk Likelihood Effect on Project Risk Reduction Plan

Catastrophe at

Take-Off Low Total mission failure

To mitigate this risk, we

have detailed setup,

integration, and launch

procedures. We will

conduct safety checks

at every stage to

ensure adherence to all

safety guidelines.

Structural

failure Low Total mission failure

Large safety factors

accounted for during

the design process

reduce the impact that

launch loads will have

on weaker structural

areas

1 Tender Descender User‟s Guide, http://fruitychutes.com/Recovery_Tether_manual.pdf

2http://www.aptllc.net/datasheets/Nylon66.pdf

3http://www.engineersedge.com/screw_threads_chart.htm

4Black Powder Pressure-Force Calculator: http://www.info-central.org/files/303-

Pressure_Force_Calculator_Ver2.xls

Page 45: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

45

Birdstrike Low Flight path altered

Follow all NAR launch

rules, holding launch if

any wildlife overhead.

Lack of failure

of shear pins Low

No parachute

deployment;

catastrophic failure

Extensive deployment

testing will be

conducted to validate

the amount of black

powder being used for

deployment is sufficient

to break pins.

Sabot not

deploying Medium

Payload not

deployed; main

parachute not

deployed

Extensive testing. Wing

release locking

mechanism will keep

wings locked until sabot

exits body tube. This

will prevent premature

opening of the sabot,

decreasing the

possibility of the sabot

binding inside the

rocket body.

Drogue

parachute not

deploying

Low

No force available to

pull sabot and main

parachute from

rocket body;

catastrophic failure

Extensive deployment

testing will be

conducted to find

optimal packing method

for drogue parachute.

Entanglement

of main

parachute

Medium

Partial mission

failure. Payload

deployment still

viable. Recovery of

main rocket body

unlikely

Parachute will be

properly packed.

Failure of

recovery

system

attachment

point

Medium

Partial mission

failure. Payload

deployment still

viable. Recovery of

main rocket body

unlikely

Ensure extensive

testing of recovery

system attachment

points to ensure their

ability to meet strength

requirements

Sabot fails to

separate after

ejection from

rocket

Low

UAV unable to

deploy; mission

failure

Extensive testing to

ensure wing rotator

locking mechanism

disengages after sabot

exits rocket body, and

Page 46: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

46

that spring force of

deploying wings is

sufficient to separate

sabot halves.

Motor fails to

ignite Low

Unable to launch;

mission failure Replace igniter

3.6 MISSION PERFORMANCE PREDICTIONS

3.6.1 MISSION PERFORMANCE CRITERIA

In order for this mission to be considered a success, the following events must occur:

Achieve an altitude as close to 5280 feet (1 mile) as possible. (It is preferable to

undershoot the target, as the flight score penalty for overshooting is twice as

great.)

Eject nose cone and deploy drogue parachute at apogee

Deploy UAV and main parachute at an altitude of 2500 ft

The UAV must unfold its wings and start the primary science mission objective.

Land safely (intact and reusable with no necessary repairs) on the ground.

3.6.2 FLIGHT PROFILE SIMULATION

For the Preliminary Design Review flight profile simulations, RockSim was used. A

model of the rocket was built in RockSim, and the mass was verified against the

Solidworks model. Parachute descent rates were verified against the MATLAB

parachute sizing model. The RockSim model agreed with the Solidworks model mass to

within 0.1 pounds and with the MATLAB model descent rates to within 3 feet per

second. Figure 3-19 shows the RockSim model.

FIGURE 3-26: PREDICTED CM AND CP LOCATIONS

A battery of simulations was run, taking into account the approximate location and

altitude of the launch site and average temperature, pressure, and humidity conditions.

It was known that the Cesaroni L1115 would be more powerful than necessary and

propel the rocket higher than the target altitude. With no added ballast or winds, the

Page 47: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

47

rocket flew over 800 feet above the target altitude. This was expected and desired,

especially considering the mass margin of the payload and other components, the

masses of which have only been measured up to this point. Initially, the RockSim model

had a mass of 19.75 kg and an initial stability margin of 2.26, which is comfortably

stable but makes the rocket susceptible to angling toward gusting winds.

Groups of ten simulations were run to find an optimal mass of the ballast that needed to

be added. Each simulation had variable light winds (3-7 mph), and the ballast mass and

launch rail angle were varied until the desired apogee and landing range distance were

achieved. The optimal value for the ballast weight added to the bottom motor bulkhead

mount is 3.65kg, giving the rocket a total wet mass of 23.4 kg, and the optimal launch

angle is 2 degrees. This gives an average altitude over 10 simulations of 5275 feet

(maximum 5296 feet, minimum 5243 feet) and a distance at landing of no more than

500 feet from the launch location, with an average distance of 100 feet.

At t = 0, the Cesaroni L1115 is ignited. Burnout occurs at 4.49s, and apogee occurs at

approximately 19.4 seconds. At this time, the first charge is ignited to eject the

nosecone and deploy the drogue chute, which pulls the sabot out of the rocket. At an

altitude of 2500 feet, the second charge is ignited. This charge releases the UAV from

the sabot, separates the nosecone, drogue chute, and sabot from the rest of the rocket

body tube, and deploys the main parachute.

Figure 3-20 shows the acceleration and velocity of the rocket during the first 30 seconds

of flight (the remaining flight time was omitted for clarity). The maximum speed occurs

near burnout, and does not exceed Mach 0.5. The maximum predicted acceleration

occurs at the parachute deployment, as expected. While the magnitude of the maximum

acceleration is high compared to what was expected, this is still within the range that the

carbon fiber structure of the rocket can stand. An initial concern was that the parachute

cords could rip the body tube apart during high-speed deployment. Future modeling will

try to reconcile the nearly instantaneous parachute deployment featured in RockSim

and the expected unraveling time of the chute to prevent such high accelerations in

simulations.

Page 48: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

48

FIGURE 3-27: PREDICTED ACCELERATION AND VELOCITY PROFILES

Figure 3-27 shows the simulated altitude profile of the rocket. Burnout and apogee are

shown with red and blue dotted lines, respectively, and the main parachute deployment

can be seen as the kink in the altitude line near 50 s.

Page 49: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

49

FIGURE 3-28: SIMULATED ALTITUDE PROFILE

Future flight profile modeling will more accurately define the launch conditions, including

launch pad altitude, predicted weather conditions (relative humidity, average wind

speed, etc.), and competition settings. Immediately before the flight, these conditions

will be taken into account and the mass of the ballast will be adjusted according to on-

site simulations to achieve the predicted altitude given the very best initial conditions

simulations the team can generate.

The scale motor used is the Cesaroni K1085, which was chosen to subject the airframe to full-scale launch conditions and deliver the UAV to a deployable altitude. A simulation of these results is as shown in 3-29.

Page 50: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

50

FIGURE 3-29: SCALED LAUNCH SIMULATED RESULTS

3.6.3 SCALE MODEL TEST

A 1/2 scale test rocket was constructed and launched to test the aerodynamic

properties of our design. See Figure 3-30 for a picture of the scale rocket. The scale

rocket was not scaled in weight because doing so would have required a much larger

and more expensive -class motor. The goal of the scale test launch was to test rocket

stability, and it was determined that this goal could be achieved using a smaller motor.

FIGURE 3-30: SCALE MODEL ROCKET

An Aerotech G80 was originally picked for the test motor. However, the scale rocket‟s

final mass was larger than anticipated, necessitating the use of a larger motor. An

Aerotech H128 was used as the test motor due to its higher average and initial thrust. A

summary of the specifications of the ½ scale rocket can be found in Table 3-15.

TABLE 3-15: SCALE MODEL DIMENSIONS

Specification Value

Page 51: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

51

Diameter 3 in

Length 62 in

Mass (without motor) 4.1 lbs

CG (measured, with motor) 41 in

CP (Rocksim prediction) 45.8 in

Stability Margin 1.6

By adding mass, the CG of the scale test rocket was placed at the scaled location of the

predicted CG of the full scale rocket. This resulted in a very similar stability margin to

that predicted by Rocksim for the full scale rocket.

The scale rocket was outfitted with a PerfectFlite MAWD altimeter for altitude

measurement. The rocket flew straight and stable. The MAWD recorded a final altitude

of 778 ft on the H128, only 50 ft higher than Rocksim predicted, thus validating our

Rocksim model.

3.6.4 STABILITY

The initial static margin of the rocket with all the ballast placed at the bottom of the

bottom motor bulkhead is 1.17. This is an appropriate static margin that makes the

rocket less susceptible to wind gusts during flight that would cause an overstable rocket

to tilt into the wind, but not so close to unstable that unexpected changes in the masses

of some of the components would jeopardize the overall stability. During flight, the static

margin will increase as propellant is burned and the center of mass moves toward the

nose of the rocket. The static margin at burnout is 1.64.

If 0.8 kg of ballast mass is moved from the bottom bulkhead to the sabot, then the initial static margin is 1.56. At burnout, the static margin is 2.08. This does not significantly change the maximum altitude of the rocket.

3.7 PAYLOAD INTEGRATION PLAN

3.7.1 INSTALLATION AND REMOVAL, DIMENSIONS, PRECISION FIT

1) Integrate Avionics Bay a) Integrate avionics boards and ELT onto avionics plate b) Integrate 3 New Batteries c) Test electronics (turn on) d) Attach avionics plate onto top cap with L-brackets and 6-32 bolts, which are

inserted, from the outside, through nutplates on the inside e) Attach avionics plate onto bottom cap with L-brackets and 6-32 bolts, which are

inserted from the outside through nutplates on the insides f) Slide assembly into tube

Page 52: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

52

g) Slide recovery system bulkhead into rocket and secure with screws h) Check all connections i) Check pressure holes

2) Make Black Powder Ejection Charge a) Safety Officer will oversee this step b) Connect to avionics

3) Integrate antenna a) Antenna is pre-attached to main body b) Connect the antenna (14 gauge insulated copper wire) to the avionics using a

binding post connection c) Slide sabot (with UAV) in, while routing the wires from the avionics assembly

through the raceway

Figure 3-22: Avionics assembly on plate inside tube, attached with L-brackets

Page 53: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

53

FIGURE 3-31: TUBE-TUBE INTERFACE

4) Recovery a) If not pre folded, fold drogue parachute b) Integrate drogue parachute and parachute protector

i) Attach to upper sabot hard point with quick link c) If not already properly packed in parachute bag, fold main parachute d) Integrate payload bulkhead

i) Attach main parachute bag to lower sabot hard point ii) Attach main parachute to shock cord with quick link iii) With the upper body segment still detached from the lower body segment,

use quick links to attach one end of the main shock cord to the payload eyebolt via the charge release locking mechanism, and the other end to the sabot eyebolt. Tie the cord off using a bowline knot.

5) Nose Cone a) Attach secondary shock cord between nose cone and sabot with quick links b) Install ELT c) Nose Cone, Drogue, and Sabot should not be attached to main shock cord

6) Integrate rocket body with sabot/UAV assembly a) Connect leads to avionics b) Attach two rocket body segments together (Fig.3)

i) Thread four 6-32 ½‟‟ screws through doublers ii) Reach through the 5‟‟ by 5‟‟ access door and untie the end of the shock cord

connected to the payload eyebolt iii) Tighten the cord and re-knot (using a bowline knot). iv) Cut off extra length of cord. v) Close access door by bolting plastic piano hinge shut using 3 6-32‟‟ bolts

Page 54: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

54

FIGURE 3-32: MAIN PARACHUTE/SHOCK CORD ATTACHED TO EYE BOLT AND RECOVERY

SYSTEM BULKHEAD

7) Integrate Nose Cone a) Slide into upper body tube (Fig.4) and mount using 4 nylon bolts fastened to the

inside using Helicoils, which will act as shear pins

Page 55: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

55

FIGURE 3-33: NOSE CONE/UPPER BODY TUBE INTERFACE

FIGURE 3-34: INTEGRATED AVIONICS ASSEMBLY, MAIN PARACHUTE, SABOT AND UAV

ASSEMBLY

3.7.2 TASKING & INTEGRATION SCHEDULE

TABLE 3-16: TASKING AND INTEGRATION SCHEDULE

Overall Task Number of People* Time

Integrate avionics

assembly

3 15 minutes

Assemble UAV 2 5 minutes

Integrate main parachute 2 15 minutes

Integrate UAV assembly

with recovery system

3 5 minutes

Integrate drogue

parachute

2 5 minutes

Integrate nose cone 2 2 minutes

Integrate motor 2 4 minutes

Total time: Approximately 60 minutes

*This includes one person with the checklist who will be supervising

3.7.3 COMPATIBILITY OF ELEMENTS

[See section or 3.7.1]

Page 56: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

56

3.7.4 SIMPLICITY OF INTEGRATION PROCEDURE

[See section 3.7.1]

3.8 LAUNCH OPERATION PROCEDURES

Caution Statement

Recall the Hazards Recognition Briefing. Always wear proper clothing and safety gear.

Always review procedures and relevant MSDS before commencing potentially

hazardous work. Always ask a knowledgeable member of the team if unsure about

equipment, tools, procedures, material handling, and/or other concerns. Be cognizant of

your and others’ actions. Keep work station as clutter-free as possible.

Equipment Packing Checklist:

1. Support Equipment and Tools

a. Safety Gear

i. Goggles

ii. Rubber Gloves

iii. Leather/Work Gloves

iv. Face Masks

v. All Safety Documents and References

b. Furniture

i. Tent (1x)

ii. Tables (2x)

iii. Chairs (6x)

iv. Rocket assembly benches

c. Generator

i. Gas

ii. Power Strip(s) (3x)

iii. Extension Cord(s) (3x)

d. Tools

i. Corded Drill

ii. Cordless Drill

1. Cordless Drill Batteries

2. Charger

iii. Drill Bit Index(s)

iv. Wrench Set

v. Pliers

vi. Screwdriver Set

vii. Hex Keys Set

Page 57: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

57

viii. Files

ix. Sandpaper

x. Knives

xi. Flashlight

xii. Soldering Iron

1. Solder

2. Solder Wick

3. Sponge

xiii. Wire Cutter/Stripper(s)

xiv. Extra Wire (Black and Red)

xv. Pocket Scale

e. Adhesive

i. 5-minute Epoxy (2 part)

ii. CA and Accelerant

iii. Aeropoxy (2 part)

iv. Epoxy Mixing Cups

v. Popsicle Sticks

vi. Foam (2-part)

vii. Foam (solid)

f. Other supplies

i. Tape

1. Duct Tape

2. Scotch Tape

3. Vacuum Tape

4. Electrical Tape

5. Masking Tape

6. Gaffer‟s Tape

ii. Trash Bags

iii. UAV Camera Port Cleaner

iv. Isopropyl Alcohol (general clean up)

v. Water Bottle

vi. Camera Lens Cleaning Supplies

vii. Paper Towels

viii. Wipes

ix. Spare Hardware

x. Lithium/Silicon Grease (for building reload; other)

xi. Zip-ties

xii. Talcum Powder (for parachutes)

2. Ground Station

a. Antennas

Page 58: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

58

i. Rocket (1)

ii. UAV (3)

iii. Antenna Mounts

b. Emergency Locator Transponder (ELT) (UAV and Rocket) (3x)

c. Emergency Locator Receiver

d. UAV Main “Pilot” Computer

e. UAV Secondary Computer

f. Rocket Ground Station Computer

g. UAV Manual R/C Controller

h. Binoculars

i. Monitors

j. Power Adapters for all Computers

k. Mice (3x)

l. Cables

i. Antennas

ii. Monitors

iii. Other

m. Miniature Weather Station (wind speed/direction, temperature)

3. Launching Equipment

a. Launch Pad

b. Launch Rail

c. Stakes for Pad

d. Angle Measuring Tool

e. Electronic Launch System (ELS)

i. Battery

ii. Battery Charger

iii. Controller

iv. Leads

4. Rocket

a. Body

i. Lower Tube Section

ii. Upper Tube Section

iii. Nose Cone

iv. Ballast

v. Shear Pins (10x)

b. Recovery

i. Parachutes

1. Drogue (2x)

2. Main (2x)

3. Nomex Parachute Protectors (3x)

Page 59: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

59

ii. Shock Cord

iii. Ejection Charges

1. Black Powder

2. Charge Holders (4x)

3. Igniters (4x)

iv. Charge Released Locking Mechanism (2x)

v. Quick links (10x)

c. Motor

i. Casing

ii. Reload (2x)

iii. Retention

1. Retention Plate

2. Retention Hardware

d. Avionics

i. Avionics Bay

ii. Altimeters

1. ARTS2 (1x)

2. ARTS2 Transmitter Board (1x)

3. MAWD (1x)

iii. Antenna (attached to outside of rocket body)

iv. 9V Batteries (10x)

v. ELTs (one in Bay, one in nose cone) (3x)

vi. Hardware

1. 4-40x1” bolts (10x)

2. 4-40 locknuts (6x)

5. UAV

a. UAV

b. Motor (2x)

c. UAV Propeller (3x)

d. UAV Lithium Polymer Batteries (2x) and Spare Batteries (3x)

e. Lithium Polymer Battery Charger/Balancer

f. Spare Servos (3x)

g. Spare Control Linkages

h. Sabot

i. Avionics

i. Flight Computer

ii. Back up Sensor Logging Board

iii. Sensors

iv. Flight Digital Still Camera

v. Video Board and Video Camera

Page 60: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

60

vi. Manual Control Receiver (Back Up: 72MHz)

vii. Antennas (72MHz, 900MHz, 2.4GHz)

viii. ELT

6. Miscellaneous

a. Digital Camera

b. Video Camera

c. Extra Batteries

d. Two-Way Radios

e. Two-Way Radio Chargers

f. Manuals for all Equipment and Gear

Pre-Flight/Final Assembly Checklist:

1. Ground Station

a. Furniture Set Up

b. Generator

i. Full Tank

ii. Extra Gas

iii. Connect Extension Cord(s)/Power Strip(s)

c. Computers

i. Set Up

ii. Plug in Power Adapters

iii. Mice

iv. Set Up Monitors

v. Power Up

d. Antennas

i. Mount and Set Up

1. 2.4GHz

2. 900MHz

ii. Connect to Computers

e. Set Up ELT Receivers

i. Test on each of 3 channels

2. UAV

a. Mechanical

i. Inspect Fuselage (follow detailed checklist)

1. Internal Structure

2. External Structure

3. All Electronics/Avionics Mounts

4. Motor Mounted Securely

5. Kevlar Skid Plate

Page 61: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

61

ii. Inspect Wing and Wing Folding Mechanism

iii. Test Wing Folding Mechanism

1. Fold and let Unfold at least twice

2. Adjust as necessary

iv. Inspect all Hinges

v. Test All Folding Hinges

1. Fold and let Unfold

2. Adjust as necessary

vi. Unfold Everything

vii. Inspect All Control Surfaces

1. All should be free and clear to rotate

2. Inspect and Move All Hinges

3. Inspect Control Linkages and Servos

viii. Inspect Camera Dome

1. Clean Dome if necessary

2. Check Connection to Fuselage

3. Check Camera Mount

ix. Inspect UV Sensor Window

1. Clean if necessary

b. Power Systems

i. Inspect Motor

ii. Check if Propeller Secure

iii. Give Motor a Test Spin (by hand)

iv. Inspect Motor Controller

v. Make sure all electronics are Switched Off

vi. Connect and Secure Charged Lithium Polymer Batteries

c. Avionics

i. Install Flight Computer

ii. Install Back up Sensor Logging Board

iii. Install Video Board and Video Camera

iv. Install Digital Camera

v. Install Manual Control 72MHz Receiver (Back Up)

vi. Inspect All Sensors

vii. Install ELT

viii. Connect Everything

ix. Set No-Fly Zones

x. Set Loiter-mode Landing Location

d. Communication/Controls

i. All servos connected to proper channels

ii. All Avionics Connected

Page 62: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

62

iii. Power On

iv. Test All Control Surfaces (using standard/manual R/C 72MHz

transmitter)

1. Trim

2. Actuate one direction

3. Actuate other direction

v. Test Motor (using standard/manual R/C 72MHz transmitter)

1. Clear objects/people from the plane of the propeller

2. Throttle Up

3. Throttle Down

vi. Power Motor/Motor Controller Off

vii. Test Flight Computer

1. Communicating with Ground Station

viii. Test Data Feeds (turn UAV avionics on)

1. Temperature

2. Humidity

3. Solar Irradiation

4. UV Irradiation

5. Pressure

ix. Test IMU/GPS

1. Transmitting Telemetry

x. Test Autopilot (Make sure control surfaces respond correctly)

1. Pitch UAV Up

2. Pitch UAV Down

3. Yaw UAV Right

4. Yaw UAV Left

5. Roll UAV Left

6. Roll UAV Right

xi. Test Data Logging

1. Digital Camera Still Shot Recorder

2. Back Up Sensor Data Logging

xii. Test Video Feed

1. Receiving Video

xiii. Test ELT

1. Receiving ELT signal

xiv. Power Up Motor/Motor Controller

xv. Flight Test with Manual R/C Control (no autopilot)

1. Receiving All Data

2. Proper Control Responses

xvi. Ground Test of Point-and-Click Control (with autopilot)

Page 63: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

63

1. Receiving All Data

2. Proper Control Responses

xvii. Aerial Test of Point-and-Click Control

1. Trim control surfaces before flight

2. Back Up with Manual R/C Control

e. Switch out Lithium Polymer Batteries

f. Final Overall Inspection

g. Install UAV into Sabot. See Payload Integration Plan.

3. Rocket

a. Lay-out rocket sections in order

b. Check Body Antenna

c. Install Ballast into appropriate sections of sabot and body tube

d. Refer to Payload Integration Plan

i. Follow, then continue with this checklist

e. Install all shear pins

f. Prepare Motor Reload

i. Safety Officer will oversee this step

g. Slide motor casing into rocket

h. Screw on motor retention

i. Make sure the tube-tube and tube-nose cone interfaces are secure

j. Inspect rail guides

k. Do a pre-launch briefing

Launch Checklist:

1. Get approval from event administration to set up pad, ELS, and rocket

2. Set up pad

3. Tip pad over and install rail

4. Check all tube interfaces

5. Slide rocket onto rail down to stop

6. Tip up launch pad

7. Stake pad to ground

8. Arm Electronics

a. Have manuals on-hand

b. Listen for proper beeps

9. Put igniter into motor and secure it

10. Connect launch clips

11. Connect ELS to battery

12. Clear launch area/back up appropriate distance

13. Make sure Ground Station and Pilots are ready

Page 64: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

64

14. Get approval from event administration for launch

The following depend on procedures outlined by event administration:

15. Cameraman ready

16. Check to see if range and skies are clear

17. Insert key into ELS check continuity

18. Countdown from 5

19. Launch

20. Remove key from ELS

21. Disconnect ELS from battery

22. Recover Rocket and UAV

3.8.1 RECOVERY PREPARATION

Using a short length of nylon webbing, attach the inside of the deployment bag to the

loop at the top of the main parachute.

Secure the top of the deployment bag to a table leg or other hard point. Stretch out the

parachute and untangle the lines. Place a weight on the outstretched, untangled lines,

to hold them in place. Next, flake out the canopy.

Page 65: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

65

Next, fold the canopy width-wise so it can fit inside the deployment bag.

Fold the leader connecting the deployment bag and the parachute in a “figure 8” and

secure with a rubber band. Place inside deployment bag. Begin placing the canopy

inside the bag, folding it over itself in an S pattern.

Page 66: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

66

Page 67: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

67

After the parachute is in the bag, begin folding the shroud lines, again, in an S-pattern.

Tuck the folded lines into the bottom of the deployment bag. Secure the Velcro flap of

the bag.

3.8.2 MOTOR PREPARATION

One of the team‟s L2 members will supervise motor assembly. All fire hazards, e.g.

people smoking, lighters, potential ignition sources, will be removed from the immediate

surroundings during motor preparation.

See Appendix 6 for official and detailed Pro75 motor preparation instructions.

The assembled motor will be slid into the motor tube and motor retention will be

screwed on.

3.8.3 IGNITER INSTALLATION

Once the rocket is on the pad, tipped vertical, and all electronics are armed, the motor

igniter will be installed. Care will be taken to fully insert the igniter into the motor. The

igniter will be held in with tape and a 1/8” dowel, which will be easily pushed out when

the motor lights. Launch lead clips will be securely attached to the igniter leads at the

appropriate time.

Page 68: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

68

3.8.4 SETUP ON LAUNCHER

Refer to Section 3.8 for Launch Checklist. After preparation is completed, the rocket will

be carefully carried out to the launch pad. The launch pad will be oriented such that the

rocket sits on the downwind side of the rail to avoid torque on the rail-buttons. The

launch rail will be tipped over to allow the rocket to be slid on horizontally. Care will be

taken when sliding the rail buttons into the rail slot. Then the rocket and rail will be

carefully tipped up to vertical.

3.8.5 TROUBLESHOOTING

Electronics will be disarmed any time the rocket is approached while on the pad. Table

3-17 summarizes possible problems and solutions with the rocket while it is on the pad.

TABLE 3-17: POSSIBLE LAUNCH FAILURE MODES

Problem Possible Causes Possible Solutions

Launch Button suppressed,

but rocket does not launch.

1. Lead acid launch

battery is dead.

2. Igniter lights, but motor

does not.

3. Igniter does not light,

but lead acid launch

battery is charged.

1. Change out battery.

2. Change out igniter.

3. Check all wire

connections.

Rocket electronics do not

arm when switched on.

1. The electronics‟

batteries were not

properly installed or

connected.

2. The electronics‟

batteries are dead.

1. Take rocket off of pad,

2. Take rocket off of pad and

replace electronics‟

batteries.

Avionics fail to report full

continuity

1. Charges are likely not

properly connected

1. Restart electronics to see

if it fixes the issue. If not,

remove rocket from pad and

troubleshoot situation at

prep table

Rail-button pulls out upon

sliding rocket onto pad.

1. Not enough care was

taken when installing the

rocket on the pad.

1. Scrub launch attempt,

bring rocket back to work

station, and repair.

3.8.6 POST FLIGHT INSPECTION

Given the nature of the USLI Launch field, it is unlikely launch organizers will allow more

than 2 people to recover the rocket and UAV. Given the large size of the vehicle, it will

Page 69: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

69

be important to plan ahead to be able to carry it back. A small duffle bag will be carried

by one team member to pack the parachute and other items into after recovery.

Before reaching the rocket and UAV, pictures will be taken for future reference before

disturbing any part of it

Upon approaching the rocket, the two ejection charges will be carefully inspected to

ensure they are no longer live. If one is still live, its wire leads will be cut with a pliers

and it will be placed in a safe location (not to be carried directly by a person). The main

parachute will be disconnected from the shock cord and it will be rolled up and placed in

the bag. The rocket and nosecone section will be repacked for transport. The rocket will

be carried back in once piece by both people. The UAV will be retrieved either

concurrently by the same team if it is determined that one group of people can carry it

back with the rocket, or separately by a different team. Similar photo documentation

techniques will be used.

In the event of a contingency during recovery, plans will be made to adjust to these

situations. Pyrotechnics safety will be a top priority during any situation.

Upon return to the prep area, data will be collected from data logging devices and the

rocket will be prepared for the trip back.

3.9 VEHICLE SAFETY

3.9.1 IDENTIFICATION OF SAFETY OFFICERS

Andrew Wimmer will be the primary rocket safety officer for the team. Ben Corbin is the

team‟s MIT EHS representative and is the assistant safety officer and is in

charge of safety issues not directly related to the rocket. Both team members have

considerable experience in their respective areas.

3.9.2 ANALYSIS OF FAILURE MODES AND MITIGATIONS

The following table provides an updated analysis of the failure modes of the proposed

vehicle design, integration and launch operations.

TABLE 3-18: POTENTIAL FAILURE MODES

Failure Mode Effects Precautions to prevent

result

Precautions to

prevent event

Motor Failure Property Damage,

Injury

Stand up, follow path

of rocket visually,

move if needed.

Follow proper launch

Store and assemble

motor in accordance

with manufacturer‟s

Page 70: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

70

safety distances instructions

Recovery

System

Entanglement

Property Damage,

Injury

Follow rocket‟s

descent path visually,

move if needed

Design and rigorously

test recovery system

in accordance with

accepted HPR

standards

Recovery

System

Structural

Failure

(bulkheads,

shockcords, etc)

Property Damage,

Injury

Follow rocket‟s

descent path visually,

move if needed

Perform pull tests on

unrated components

to ensure their

strength. Components

to be tested to 50g

shock loads

Recovery

System failure to

deploy

Property Damage,

Injury

Follow rocket‟s

descent path visually,

move if needed

Ensure rigorous

testing of black

powder charges,

Tether release

mechanisms and

deployment altimeters

and power supplies.

Don‟t forget to arm

altimeters

Recovery Device

deployment on

ground

Property Damage,

Injury (especially

eye)

Avoid placing body in

path of parts if

electronics are armed.

Wear safety glasses if

necessary.

Shunt charges until

they are attached to

recovery electronics.

Do not move the

rocket with armed

electronics.

Unstable Vehicle Property Damage,

Injury

Stand up, follow

rocket‟s path visually,

move if needed.

Confirm vehicle

stability before launch.

Ensure actual CG

position is acceptable

relative to calculated

CP

Brush Fire Fire damage, injury

Have fire protection

equipment and

personnel trained in its

use onsite

Follow NFPA table for

dry brush around pad

area.

Mid-flight vehicle

destruction

Loss of vehicle,

Injury, Property

Follow rocket‟s path

visually and move if

Design, construct and

test vehicle to assure

Page 71: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

71

3.9.3 POTENTIAL HAZARDS

A listing of personnel hazards and evidence of understanding of safety hazards

is provided in the sections below.

(excessive

forces on

vehicle)

damage needed if vehicle does

come apart

successful flight. Use

standard construction

procedures for LII-LIII

rockets, including

sufficient bulkheads,

fins, motor retention

and couplers.

Failure of UAV

to deploy

Loss of science

value, potential

failure of main

recovery device

Visually track vehicle

& UAV, and move if

needed

Rigorously test UAV

deployment method

as an integrated

component in the

rocket recovery

system. Ensure all

other aspects of the

rocket flight succeed

Failure to

successfully

integrate vehicle

in allotted 4 hour

time period

Loss of launch

opportunity N/A

Practice integration

techniques under time

constrains to ensure

they are achievable in

allotted time.

Failure of vehicle

to reach desired

altitude

Loss of competition

points and potential

loss of science value

N/A

Use multiple

simulation programs

and data from actual

flight tests to fine tune

rocket mass and

motor selection

UAV Scientific

data is

unrecoverable

Loss of science value N/A

Perform range

communication tests

with all flight hardware

in flight configuration.

Allow electronics to

be quickly

reconfigurable in case

of frequency conflicts.

Page 72: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

72

Safety Checklist

In order to assure a safe and successful flight, a checklist must be followed during prep

activities and launch. In order to reduce personnel hazards during the prep of the

vehicle before taking it to the pad, the following precautions must also be taken into

consideration.

Always wear safety glasses when dealing with rocket parts containing small

hardware or pyrotechnic charges.

Never look down a tube with live pyrotechnic charges in it.

Always point rocket and pyrotechnic charges away from body and other people

Avoid carrying devices that have live electrical contacts (radios, cell phones, etc.)

while prepping live pyrotechnic charges.

Never arm electronics when rocket isn‟t on pad unless the area has been cleared

and everyone knows that pyrotechnic continuity checks are being done.

Always follow the NAR/TRA safety codes.

Always follow all applicable local, state and national laws and regulations

Do not allow smoking or open flames within 25 feet of the motor or pyrotechnics.

Respect the launch organizer‟s decisions regarding range safety and weather

conditions

Pay attention to other launches, especially when conditions require a “head‟s up”

Make sure the checklist is followed and all steps are completed properly in a

thorough, workmanlike manner to assure mission success.

To further ensure mission success, considerations must be taken while at the

launch prepping and flying the vehicle to keep all the people around and the vehicle

itself safe.

Important safety related considerations are found in the following list:

Always follow the NAR/TRA safety code.

Adhere to local, state and federal regulations.

Never arm electronics unless rocket is vertical and the criterion for testing

continuity listed above is met.

Never proceed with launch if there are any outstanding technical issues that may

reduce the chances of a safe flight without first consulting both safety officers and

NASA officials if needed.

No smoking or open flames within 25 feet of the vehicle.

Do not put self or others in path of body tube in case of early ejection on

the ground; always be aware of the possibility of ejection charges firing at any time.

Verify that ignition leads are not live before connecting igniter to ground control.

(Touch leads together in the shade and listen and watch for sparks or place against

tongue)

Page 73: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

73

Verify rocket will exit launching device vertically with almost no friction from the

launch guides

Handle rocket carefully to avoid injury to self, others or the vehicle

Be observant of other rocket prep operations in the launch pad area

Verify that ground around launch pad is cleared of flammable materials.

TABLE 3-19: TOOL USE INJURY POTENTIALS AND MITIGATIONS

Tool: Injury Potential: Risk mitigation procedure:

Electric Handheld

Sander Burns, cuts, skin abrasion Avoid loose clothing

Rotary Cutter/Dremel

Cuts, skin abrasion, eye

damage from flying debris,

respiratory damage from dust

Always wear a mask, gloves,

and safety goggles when

operating

Soldering Iron Burns Exhibit care not to come in

contact with hot element

Handsaw Cuts, splinters, skin abrasion Wear proper safety gear (gloves

and goggles)

Table Saw Cuts, Limb/appendage

removal

Avoid loose clothing, follow

safety procedures found in

instruction manual.

Wood Lathe Cuts, broken appendages Avoid loose clothing, use proper

tools and safety equipment

Table Router Cuts, Limb/appendage

removal Use proper protective gear.

Drill Press Cuts, abrasion, loss of limbs/

appendages

Use proper protective gear, hold

down work with clamps

Miter Saw Cuts, Limb/appendage

removal

Avoid loose clothing, follow

safety procedures found in

instruction manual.

Band Saw Cuts, loss of

limbs/appendages Use proper protective gear.

Belt Sander Burns, skin abrasion No loose clothes, wear proper

protective gear (gloves)

Page 74: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

74

CNC Water Cutter Cuts, loss of

limbs/appendages

Only trained personnel use this

tool. Oversight by shop

manager

CNC Laser Cutter

Burns, eye damage,

respiratory issues, poisonous

off-gassing

A training course is required by

MIT to use the laser cutters on

campus. Many safety measures

exist, including ventilation and

failsafe switches.

Mill Loss of limbs, scarring, eye

damage from flying chips

A training course is required by

all shop managers to use mills.

Safety goggles are always worn.

Metal Lathe Loss of limbs, cuts, eye

damage from flying chips

A training course is required by

all shop managers to use lathes.

Safety goggles are always worn.

Safety Codes

The Tripoli Rocketry Association and the National Association of Rocketry have adopted

NFPA 1127 as their safety code for all rocket operations. A general knowledge of these

codes is needed and will be required by all team members. These codes are found in

the CDR-Safety document.

Hazards Recognition

The Hazards Recognition Briefing PowerPoint Presentation will be given prior to

commencing rocket construction. It will cover accident avoidance and hazard

recognition techniques, as well as general safety.

1) General

a) Always ask a knowledgeable member of the team if unsure about:

i) Equipment

ii) Tools

iii) Procedures

iv) Materials Handling

v) Other concerns

b) Be cognizant of your own actions and those of others

i) Point out risks and mitigate them

ii) Review procedures and relevant MSDS before commencing potentially

hazardous actions

c) Safety Equipment

i) Only close-toed shoes may be worn in lab

Page 75: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

75

ii) Always wear goggles where applicable

iii) Always use breathing equipment, i.e. face masks, respirators, etc, where

applicable

iv) Always wear gloves where applicable, e.g. when handling epoxy and other

chemicals

2) Chemicals

a) The following are risks of chemical handling:

i) Irritation of skin, eyes, and respiratory system from contact and/or inhalation

of hazardous fumes.

ii) Secondary exposure from chemical spills

iii) Destruction of lab space

b) Ways to mitigate these risks:

i) Whenever using chemicals, refer to MSDS sheets for proper handling

ii) Always wear appropriate safety gear

iii) Keep work stations clean

iv) Keep ventilation pathways clear

v) Always wear appropriate clothing

3) Equipment and Tools

a) The following are risks of equipment and tool handling:

i) Cuts

ii) Burning

iii) General injury

b) Ways to mitigate these risks:

i) Always wear appropriate clothing, e.g. closed-toed shoes.

ii) Always wear appropriate safety equipment

iii) Always ask if unsure

iv) Err on the side of caution

4) Composites Safety

a) Carbon fiber, fiberglass, epoxy, and other composite materials require

special care when handling.

b) The following are risks composites handling:

i) Respiratory irritation

ii) Skin irritation

iii) Eye irritation

iv) Splinters

v) Secondary exposure

c) Ways to mitigate these risks:

i) Always wear face masks/respirators when sanding, cutting, grinding, etc., lay-

ups.

ii) Always wear gloves when handling pre-cured composites

iii) Always wear puncture-resistant gloves when handling potentially sharp

composites

Page 76: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

76

iv) A dust-room has been constructed, as per MIT EHS guidelines,

specifically for the handling of composite materials.

d) No team member will handle carbon fiber until properly trained

3.9.4 ENVIRONMENTAL CONCERNS

All waste materials will be disposed of using proper trash receptacles

Non-polluting recovery system heat protection will be used

Solid rocket motor manufacturers‟ instructions will be followed when disposing of any

rocket motor parts

Consideration of environmental ramifications will be made regarding applicable

activities

Proper blast shields on the launch pad will be used to prevent direct infringement of

rocket motor exhaust on the ground

Waste receptacles (trash bags) will be available for use around the prep area to

encourage proper disposal of waste from rocket prep activities

The following list of materials have been identified as potentially hazardous:

o Aeropoxy 2032 Epoxy Resin

o Aeropoxy 3660 Hardener

o Ammonium Perchlorate Composite Propellant

o Black Powder

See CDR-MSDS document for complete MSDS specifications on these materials.

4 PAYLOAD CRITERIA

4.1 TESTING AND DESIGN OF PAYLOAD EXPERIMENT

4.1.1 SYSTEM LEVEL REVIEW

Note: All UAV Dimensions are in English (IPS) and all the aerodynamics calculations

are in Metric.

Page 77: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

77

System Mass (lbs) Cost (USD)

UAV

Airframe 3.06 81.87

Motor 0.73 59.58

Avionics 3.21 ?

TABLE 4-1: UAV CHARACTERISTICS

Page 78: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

78

TABLE 4-2: STABILITY ANALYSIS

Page 79: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

79

ϒ

TABLE 4-3: FLIGHT CASE ANALYSIS

ρ

μ

Page 80: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

80

Fuselage

The UAV fuselage is made of separable top and bottom halves. The fuselage is

rotationally symmetric except for two flat sections which are used to place a skid plate

made of Kevlar-epoxy and a camera window. The UAV does not have landing gear so

the Kevlar skid plate will prevent the fuselage from being damaged during landing. An

internal frame consisting of bulkheads and a plate on the bottom of the fuselage provide

structural support and allow attachment of the tail, wings, and avionics. The bulkheads

are epoxied to the top half of the fuselage and screws are used to secure the bottom

half of the fuselage to the bulkheads. This allows for easy removal of the bottom half of

the fuselage in order to gain access to the avionics.

The motor and a folding propeller are located at the rear of the aircraft which allow an

unobstructed view for the camera at the front of the aircraft and allows the propeller to

automatically fold back when it stops spinning. A folding propeller is used to ensure that

the UAV fits inside the rocket. The propeller will also fold up while gliding to reduce drag

and upon landing to avoid incurring damage.

The center of gravity will be located 25% of the fuselage length from the nose (11.25 in),

which will be accomplished by putting the avionics equipment in front of the wings. The

center of gravity and consequently the wings were placed this close to the nose to allow

the wings to fold up without hitting the vertical stabilizer. A stability margin (S.M.) of 0.1,

a horizontal tail volume coefficient (Vh) of 0.5, and a horizontal stabilizer aspect ratio

(ARh) of 4.5 were used to estimate the location of the neutral point and the aircraft wing.

These values were chosen to increase the stability of the airplane.

xnp

c1

41

2

AR

12

ARh

14

AR 2

Vh

Page 81: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

81

The estimate of the neutral point of the aircraft is 2.7 in from the wing leading edge. This

estimate puts the center of gravity of the UAV 2.2 in from the wing leading edge. With

this information, we then calculated the distance from the nose to the wing leading edge

to be 9.1 in (wing chord is 5 in).

Wings

The wings have a chord of 5 in which was chosen because it is the largest chord that

will still allow the UAV to fit inside the rocket. Using this chord we then plotted

coefficients of lift and drag for various angles of attack using Xfoil (Xfoil is CFD

command line program developed at MIT for designing and analyzing airfoils).

Atmospheric data was found using a java applet by DesktopAeronautics

(http://www.desktop.aero/stdatm.php). Standard cruising conditions were considered to

be

Velocity = 25m/s ( )

Altitude = 2500 ft

Reynolds number = 204,000

Using this Reynolds number, nine airfoils were analyzed. The 6 airfoils with the highest

CL are shown in Figure 4-5.

Page 82: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

82

FIGURE 4-1: AIRFOIL COMPARISON

The leftmost graph shows the coefficient of lift plotted against the coefficient of drag.

The center graph shows CL vs. α (the steeper graph) as well as the pitching moment

(Cm) vs. α (the flatter graph). After some consideration, the NACA 4412 was chosen

because it has a very high ratio of CL/cd and it has one of the highest CL around an

angle of attack of 3°, which will be the UAV wing‟s angle of attack while cruising. The 3°

angle of attack was chosen because it provides significantly more lift but doesn‟t

produce too much drag.

Page 83: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

83

At a 3° angle of attack, the NACA 4412 airfoil has a coefficient of lift of 0.778. The stall

angle of attack at 66.0 ft/sec was determined to be roughly 14° (shown in Figure 4-2:

NACA 4412 Polar). The glide ratio and glide angle at 3° are 0.08 and 4.6° respectively.

FIGURE 4-2: NACA 4412 POLAR

After having chosen an airfoil, calculations for total weight were made with the equation:

[Density (ρ) = 2.21E-3 slugs/ft3]

A wingspan of 54 in was then chosen because it allows the aircraft to lift 7 lbs, roughly

the estimated weight of the airplane, while flying at its cruising speed.

Each wing will be horizontal for 3.5 in on either side of the aircraft and will then have a

5.8° dihedral (Υ) for the rest of the wing in order to increase spiral stability. A dihedral of

5.8° was chosen using:

Page 84: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

84

[B = 4; lv= 29.3 in]

In this equation, Υ actually refers to the equivalent dihedral angle but in our

approximations we ignored the contributions of the flat center section of the wing to the

dihedral. The equivalent dihedral will be calculated more accurately in the future when a

more thorough stability analysis is performed.

FIGURE 4-3: TAIL

The UAV tail will consist of a vertical stabilizer and a horizontal stabilizer mounted part

way up the vertical stabilizer. The horizontal stabilizer is mounted away from the

fuselage in order to maximize its area while minimizing the total width of the airplane.

Both the horizontal and vertical tails will be made using the NACA 0008 airfoil. This

airfoil was chosen because it is symmetric and has a slightly smaller thickness/chord

ratio than the wing.

Control surfaces for the aircraft will consist of elevators and a rudder located on the tail.

They will be controlled with pushrods originating from servos located in the fuselage.

Page 85: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

85

For size estimates, a horizontal tail volume coefficient of .5 and a vertical tail volume

coefficient of .05 were chosen in order to increase stability which is important for the

autopilot to function. The following equations were used for estimates of tail sizes.

Typical aspect ratios of 4.5 and 1.4 were chosen for the horizontal and vertical tails

respectively. Furthermore, taper ratios of .4 were used on both the horizontal and

vertical tail.

Aerodynamic Analysis

AVL and XFOIL were used to calculate lift and drag for the aircraft. AVL uses the

horshoe vertex lattice method to calculate inviscid lift and drag and aircraft trim. The

UAV wing and tail were modeled in AVL for standard cruising conditions (angle of attack

of UAV was set to 0°). AVL makes its calculations by breaking up each surface into

many small sections. XFOIL was used to calculate viscous lift and drag for each of the

sections using the inviscid lift coefficient calculated by AVL. Total lift and drag was

calculated for each section and the results from each section were summed to give total

lift and drag for the wing and tail.

AVL and XFOIL are not able to model the fuselage so hand calculations were employed

using the following equations:

(

)

All the results can be seen in the Flight Case analysis table. The UAV has an estimated

lift to drag ratio of 19 which means the UAV should glide well.

Folding Mechanisms

Page 86: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

86

FIGURE 4-4: WING ROTATOR MECHANISM

In order to fit inside the rocket, the wings, horizontal stabilizer, and horizontal stabilizer

all fold.

The wings are attached to a spring loaded rotating mechanism. The mechanism allows

one wing to lift above the other. Both wings will then fold backwards. When unfolding, a

torsion spring swings both wings out until they achieve a 180° angle with each other. A

compression spring is used to pull the elevated wing down into position. The wings are

locked in place with magnets.

Page 87: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

87

FIGURE 4-5: UAV IN STOWED CONFIGURATION

The tail folds by means of spring hinges. Spring hinges were chosen because of their

ease of integration into the existing plan and their relative low cost. Furthermore, the

spring hinges will automatically deploy when the UAV is released from the sabot. A pair

of rare earth magnets will be used to hold the tail in its unfolded position after tail

deployment.

FIGURE 4-6: STOWED TAIL

While inside the rocket, rods will be inserted into the wings and fuselage to hold the

wings in their folded position. This part will be attached to the rocket and will be pulled

out when the UAV falls out of the rocket.

4.1.1.1 DRAWINGS AND SPECIFICATIONS

[See Appendix 4: UAV Drawings]

4.1.1.2 ANALYSIS RESULTS

Page 88: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

88

In order to verify the design of the UAV, analysis was performed on the wings and wing

rotator mechanism. The order of analysis is as follows:

Define loading conditions

Design part

Use hand calculations to size the part

Validate hand calculations using finite element method

Re-size as necessary

Loading Conditions

The wings of the UAV must be capable of withstanding two loads: the aerodynamic

forces during deployment and the weight of the fuselage during steady level flight. The

same analysis was performed on the wing rotator mechanism, as questions to its load-

bearing capability were brought up during PDR.

Deployment loading conditions for a single wing are summarized in Table X

TABLE 4-4: DEPLOYMENT LOADING

Deployment

Loading

Aero Loading 1.57 lbf

Fuselage Weight 8 lbf

MUF 1.5

Design Axial 14.4 lbf

Aerodynamic loading was calculated based on sabot speed at time of deployment, as

predicted by the Matlab recovery simulation. After separation from the main rocket

body, the sabot is decelerated to 26 ft/s, at which point the UAV is deployed. In reality, it

is hoped that the UAV will be in a nose dive during deployment. However, for analysis

purposes, a worst-case scenario of a flat fall was used. Additionally, the entire fuselage

weight was applied to each wing, rather than distributed between the two. The loads are

summed to create a total load, which is then margined by a 1.5 model uncertainty

factor, to account for inaccuracies in the recovery model and unpredictable

aerodynamic turbulence.

Wing Analysis

As described in the design section, the wings are a composite laminate of fiberglass

weave over a rigid foam core. The moduli and strength for the fiberglass and foam are

shown in Table X and Table Y. Note that the properties cited were for a unidirectional

fiberglass composite. Because we use a woven fiberglass sheet, the modulus was

divided by two, as approximately half of the fibers are aligned in a given direction.

TABLE 4-5: FOAM MATERIAL PROPERTIES

Page 89: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

89

Material Properties - Foam5 6

E11 1.6 ksi

E22 2.8 ksi

E33 6.8 ksi

v 0.3

strength 25 psi

TABLE 4-6: FIBERGLASS MATERIAL PROPERTIES

Material Properties - Fiberglass7

E 3.25 Msi

v 0.3

strength 257 ksi

Material properties for the fiberglass/foam laminate were then calculated using the

Layup creator in Femap. Based on the unique shape of the layup and the limited

information available regarding the structural properties of foam, several assumptions

had to be made. First, the average thickness of the airfoil was used as the thickness of

the foam layer. For a NACA 4412 airfoil with a 5in chord, the maximum thickness is

0.60in. Half of this value, or 0.30in, was used as the foam ply thickness. Second,

because the shear modulus of the foam was unknown, the foam was approximated as

an isotropic material with the modulus of elasticity equal to E11. This was considered a

fair assumption because of the difference in magnitude between E11 and E22 of the

foam was small in relation to the magnitude of the fiberglass modulus.

TABLE 4-7: FIBERGLASS LAYUP PROPERTIES

Bending Properties – Fiberglass Layup

Ex 306 ksi

Ey 306 ksi

Gxy 118 ksi

vxy 0.3

vyx 0.3

Using these properties, hand calculations could be performed to calculate the maximum

deflection of the beam. These intermediate calculations can be seen in Table Z.

5 Moduli: http://web.mit.edu/16.unified/www/SPRING/systems/Lab_Notes/appendix.pdf

6 Strength: http://insulation.owenscorning.com/WorkArea/linkit.aspx?LinkIdentifier=id&ItemID=788

7 E-glass Epoxy Composite; http://www.carbonfibertubeshop.com/tube%20properties.html

Page 90: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

90

TABLE 4-8: WING DEFLECTION CALCULATIONS

Wing Deflection

Calculations

Chord 5 in

Mean Thickness 0.3 in

Moment of Inertia 0.01125 In^4

Deflection 10.29 in

In order to verify these calculations, a finite element model was developed in Femap.

The applied boundary conditions are shown in Figure 4-7.

FIGURE 4-7: WING BOUNDARY CONDITIONS

The model was then solved using NEi Nastran, resulting in the ply 1 effective strain and

displacement outputs as shown in Figure 4-8 and Figure 4-9.

Page 91: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

91

FIGURE 4-8: EFFECTIVE STRAIN

Page 92: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

92

FIGURE 4-9: WING DEFLECTION

Analysis verified the deflection value produced by hand calculations. To reduce the

amount of deflection, the wing layup was redesigned with 1in thick carbon fiber strips

centered along the quarter-chord location on the top and bottom surfaces of the wing.

Properties for this layup, as computed by Femap, are listed in Table 4-9.

TABLE 4-9: CARBON FIBER LAYUP PROPERTIES

Bending Properties – Carbon Fiber

Layup

Ex 3.15 Msi

Ey 3.15 Msi

Gxy 1.21 Msi

vxy 0.3

vyx 0.3

Hand calculations were again performed, this time on the I-beam made by the carbon

fiber strips. These intermediate calculations can be seen in Table 4-10.

TABLE 4-10: CARBON FIBER DEFLECTION CALCULATIONS

Page 93: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

93

CF Deflection Calculations

Width, b 1 in

Thickness 0.025 in

Separation

Thickness

0.3 in

Moment of Inertia 0.00132 In^4

Deflection 3.15 in

In order to verify these calculations, the Femap model was refined to incorporate the

carbon fiber strip. The new boundary conditions are shown in Figure 4-10.

FIGURE 4-10: NEW WING BOUNDARY CONDITIONS

The model was then solved using NEi Nastran, resulting in the ply 1 effective strain and

displacement outputs as shown in Figure 4-11 and Figure 4-12.

Page 94: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

94

FIGURE 4-11: NEW EFFECTIVE STRAIN

FIGURE 4-12: NEW WING DEFORMATION

Page 95: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

95

Wing Rotator Mechanism Analysis

The two major structural components of the wing rotator mechanism are the plates that

connect to the wing halves, and the central shaft that connects the entire mechanism to

the UAV fuselage. These components must be able to withstand the aforementioned

loading condition, as well as the moment generated by the force acting along the span

of the wing. A model of the rotator mechanism was made in ANSYS Workbench. Figure

4-13 shows the boundary conditions placed on the rotator mechanism.

FIGURE 4-13: WING ROTATOR BOUNDARY CONDITIONS

The model was then solved using the ANSYS engine. Stress and deformation

distributions can be seen in Figure 4-14 and Figure 4-15.

Page 96: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

96

FIGURE 4-14: STRESS DISTRIBUTION

FIGURE 4-15: DEFORMATION

Page 97: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

97

4.1.1.3 TEST RESULTS

To verify the wing analysis, mockup wings were tested with variable mass to determine

if the unidirectional carbon fiber strips were necessary to ensure the wings will be

capable of handling expected forces upon deployment in launch. Wings with fiberglass

only and wings with the carbon fiber strips were both tested with the same restrictions

with variable mass at a single point. In all the tests, the main mode of failure was point-

stress failure at the restraint, which is expected. The fiberglass wings failed with an

average applied torque of 6.3 foot-pounds. The fiberglass wings with unidirectional

carbon fiber imbedded in the layup failed with an average applied torque of 8.25 foot-

pounds. The wing design with the imbedded carbon fiber will be used to ensure that the

wings will be capable of handling the impulse upon deployment, and are more than

suitable to generate the necessary lift of the UAV.

Analysis done on the wing rotator shows that the components are more than capable of

handling any anticipated impulse load. To verify initial analysis, several wing rotators

will be tested post-CDR.

Other components and sub-systems will be tested post-CDR as seen fit. Only the

wings and wing rotator mechanism have been analyzed and will be thoroughly tested as

the failure of either of these two subsystems will result in the UAV becoming

fundamentally unflyable.

4.1.1.4 INTEGRITY OF DESIGN

A high level of integrity is expected of the UAV design as otherwise the science payload

will be left incapable of completing the mission. The integrity of the UAV design can be

noted throughout the manufacturing, testing and analysis sections. The beginning of

the design process included ample use of SolidWorks and team meetings with senior

team members to ensure that all systems and subsystems will be of high enough caliber

and structural reliability to meet the requirements set by the mission.

4.1.2 DEMONSTRATE DESIGN MEETS SYSTEM LEVEL REQUIREMENTS

Simplify UAV flight process

Due to the stability of the UAV, a control system is being employed to automatically

stabilize the UAV without input from the user. Not only does this act to remove the user

from the complexity of flying a UAV, but it also adds resistance to lag in the telemetry

system as the stabilization takes place on the UAV regardless of user inputs.

The ground station provides a simple „point and click‟ user interface for choosing the

location the UAV should fly to and land at. The same interface also allows the user to

easily select a cruising speed and altitude. To increase the ergonomic aspect of the

ground station, it is run on a tablet PC, although it is capable of running on any windows

computer with modification to be ported to Apple or Linux possible.

Page 98: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

98

Stream telemetry and video to ground station

Telemetry is provided by a pair of XBee 900MHz modules. The telemetry system

provides location, speed, altitude and heading data to the ground station to aid the user

in flying as well as temperature, pressure, humidity, UV index and solar irradiance data

as per SMD requirements).

The video transmission occurs via a separate 2.4GHz link to a secondary computer at

the ground station to provide the user with a first person view from the UAV.

Take "simple" commands from ground station

To simplify the flight process, the UAV is flown using a ground station which converts

the user input to commands which the UAV decodes to control its higher level actions

such as cruising altitude and speed or target location

Employ video tracking systems

Changes in the higher level requirements have reducing this to video tracking only.

Video tracking is performed using a first person video feed operating at 2.4GHz. This

video feed is forward looking and inclined to the horizontal to give the user not only a

view of upcoming terrain, but also a view of the ground aiding in the goal of

reconnaissance.

UAV must be capable to operate for at least 30 min

Based on the power and propulsion system, the UAV should be able to perform a

fly/glide flight profile for over this 30 minute target. However during the USLI competition

the UAV is only expected to fly for 5-10minutes for the purposes of flight demonstration.

4.1.3 WORKMANSHIP AND RELATION TO SUCCESS

Avionics

The avionics fall into two separate components; the flight computer and the backup

board. Since the flight computer is tasked with controlling the UAV, its correct

construction is critical. The majority of the construction is soldering however, which is

neither difficult to perform nor to inspect, so all the solders are inspected after

construction as a part of the verification process. The software on the flight computer is

also critical; to ensure high quality of the software, a branch from the ArduPilot Mega

software repository is being used, with additions such as adjustments to the data

protocol and for sensor data logging.

Although the backup data board is not critical, the majority of construction is also

soldering, verification of correct construction is also not a complex task. Also since there

is significant commonality between the additional flight computer software and the

backup board software should have the consequence of reliable backup board software.

Page 99: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

99

UAV Hardware

As long as a stable UAV platform is produced, then the only aspect of the UAV that is

critical to the correct operation of the UAV is the correct design and construction of the

wing rotator mechanism. A failure of the wing rotator mechanism could result in the UAV

being fundamentally unflyable, and the control system on the flight computer will be

unable to fly the UAV successfully.

UAV Composite Fabrication

The UAV composite components require the testing of new fabrication techniques for

the wings and fuselage. The wings incorporated a technique new to the rocket team

that produces a completely smooth and wrinkle-free wing layup, incorporating plain-

weave carbon fiber strips. An experienced team member in this new fabrication

technique watched over other team members as several practice layups were made,

until satisfactory results were obtained. Additionally, the positive fuselage mold was

made of wood on a wood lathe, by hand, practicing acquiring an appropriate taper. It is

appropriate that several more practice layups are performed to ensure that the

fiberglass layup can be easily removed from the wood mold, without ruining the

fiberglass as experienced from the initial layup. The team members will continue to

improve their skills and layup techniques, continually improving the quality of all the

fabricated composites so the final UAV will be of superb quality. Extra wings,

stabilizers, and entire UAVs will also be made and be available as backups in Huntsville

so that the payload will be readily repairable and flyable in the event of any

transportation or mission breakages.

4.1.4 PLANNED COMPONENT, FUNCTIONAL, AND STATIC TESTING

The team‟s first priority will be to perform qualification testing on the structural

components of the payload. The tests to be performed are as follows and will be

completed after the structural test article is completed post-CDR:

Wings will be tested further with variable mass, using small weights. As verified

by initial testing, wings will not reach full load capacity, failing prematurely at the

point of contact between the wing and edge of table holding wing.

Horizontal stabilizer will be tested in same manner as wings.

Test the wing rotator several times in three manners:

o That wing rotator will deploy wings from a folded manner.

o A symmetric variable mass on attached wings, and wings are expected to

fail before the aluminum wing rotator. Will apply variable mass until wings

break off rotator.

o Drop test of UAV from tethered weather balloon.

Fuselage will be tested in a manner of ways:

o Crush test from nose to tail

Page 100: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

100

o Impact test from the top of the body and the bottom of the body. This will

ensure that the fuselage will be able to withstand the impact force

expected upon landing. Will also verify the connecting points between the

two halves of the fuselage will withstand forces upon deployment and

landing.

o Abrasive test on the Kevlar landing strip, testing the resilience of the

Kevlar for the skidding expected upon landing.

After component structural testing is complete, deployment and recovery tests will be

performed. This will occur with the final prototype assembly.

Deployment test from the sabot to ensure that wings will separate sabot upon

deployment from rocket tube. Ensures that the spring components of the wing

rotator mechanism are capable of separating sabot.

Several flight test to ensure that control gains are suitable for the final UAV

design and prototype.

Drop test from tethered weather balloon, testing the avionics system and

prototype UAV work under mission conditions.

See section 4.3.4 for greater detail in testing UAV and avionics. These tests will

occur before the FRR.

4.1.5 STATUS AND PLAN FOR REMAINING MANUFACTURE AND ASSEMBLY

Payload

Fuselage:

A prototype wood mold of the fuselage body has been created and several layups have

been performed to test the method that will give the best fiber glassing results. Using a

standard fiberglass layup process in the rocket teams own oven, using 3 plies of

fiberglass, only half of the fuselage is made at a time. The two halves are combined

after reaching a full cure using a thin strip of fiberglass and epoxy. The fabrication

process and the team members experience level produce a fuselage of high enough

quality to proceed with assembly and integration of other sub-components. The UAV

prototype will be used for all testing, and once the systems are all approved and

working properly, the team will go into the final fabrication process that will include

making another wood mold of the fuselage to required dimensions. The final prototype

will have the entire fuselage made of fiberglass, and a small window will be cut and

clear polycarbonate installed into the nose of the fuselage with large enough

dimensions to allow for the camera to have a clear view of the ground.

Wings:

The airfoils will be cut out of Owen Corning Foamular 250 using a foam cutter, the

custom foam cutter provided by the MIT Department of Aeronautics and Astronautics for

student use. Using the NACA 4412 for the wings, the settings of the foam cutter

Page 101: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

101

machine were adjusted until the desired shape and finish of the foam is attained. Using

techniques developed my previous years of MIT student trial and error, the wings are

going to be lain up using a single ply of fiberglass and 1” unidirectional carbon fiber

strips across the top and bottom of the wing on the quarter cord to increase the strength

and load capabilities of the wings. This is opposed to simply doing a single ply of

fiberglass and no carbon fiber, which produces wings that will have a much higher

likelihood of failing upon initial deployment. Upon some analysis, the carbon fiber strips

decreases the bending of the wing by 6.5” across one wing with a load of 14 lbs of

force, resulting in only about 2.6” of tip deflection versus the 9.125” tip deflection.

Several layups have been performed and the final wings are of suitable quality. Some of

the internal components, including the hinge components, will be cut with a waterjet for

the aluminum pieces, and a laser cutter for the wood components and will be integrated

when assembling the first prototype for flight. Members of the rocket team have

acquired suitable experience using the machines and have been trained in the safe

operation of this equipment, obtaining fantastic results.

Empennage:

The NACA 0008 airfoils for the horizontal and vertical stabilizers will be cut in same

fashion as the wings, and will undergo the same layup process excluding the

unidirectional carbon fiber strips. After the fiberglassing process is completed, the

stabilizers will be cut and magnets will be installed inside compartments that will be cut

into the foam. This will lock the stabilizers in place upon deployment.

Wing Rotator:

The wing rotator will be constructed of 6061-T6 Aluminum, standard aluminum, as

opposed to the polycarbonate construction in response to anticipated loads upon

deployment. All pieces are machined separately in MIT metal machine shops using

CNC Lathes, CNC Mills, and a water jet. Three complete wing rotator mechanisms will

be made, along with several back up components, the spares will be on hand at

Huntsville in case of any transportation or other accidents leaded to integrated

component failure.

Internal components:

All other internal components will be made using standard machines, along with a

waterjet and laser cutter for appropriate components.

Avionics

TABLE 4-11: AVIONICS TESTING

Sub-System Completed Remaining

Ground station Software Software written Testing

Page 102: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

102

Flight Computer

Core flight computer built

Updated code for UAV specific needs

Tested to ensure correct servo actuation

Integrated with test aircraft

Tested in manual mode via an RC handset

Integrate with sensor assembly

Test in flight

Test telemetry link

Test sensor data logging

Back Up Logging Board

Sensor software written

Logging software written

Construction started

Complete construction

testing

Visual System Integrate with UAV

Test

User Interface Description

FIGURE 4-16: GROUND STATION USER INTERFACE

1

2

3 4 5

6

7

Page 103: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

103

1. Top down view – This provides the user with information of the local area. The

zoom of the view varies with altitude of the UAV to maintain a view 800m above

that of the UAV. The map tracks such that the UAV remains central to the map

which also rotates so the UAV is always travelling upwards on the UAV i.e. the

UAV sprite remains static.

2. UAV Icon – This denotes the location of the UAV on the map and remains static

since the map translates, rotates and resizes around this icon

3. Target Icon – This marks the location of the „target waypoint‟ and is modified by

clicking within the top down view. Moving the target does nothing until one of the

waypoints commands (4) and selected.

4. Waypoint Commands – Once a suitable target location has been selected these

are used to determine how to use that location information; whether to fly to that

location and loiter there or whether to land there.

5. Cruise Control Settings – Here the target cruise altitude and speed can be

selected. Once selected the control system on the UAV will attempt to maintain

these values during flight.

6. Cruise State – Displays the current cruising speed and altitude of the UAV

7. Sensor Data – Displays the current sensor data as recorded by the flight

computer in accordance with SMD requirements.

4.1.6 DESCRIBE INTEGRATION PLAN

Integrating the UAV into the sabot:

The following steps should be completed after the parts of the Pre-Flight Checklist

before this step have been completed. In other words, the UAV should be completely

ready to be deployed before integrating it into the sabot.

Separate the sabot halves and lay them next to each other.

Set the UAV on a sturdy working surface

While bracing the body, carefully fold the UAV‟s wings back, making sure to

depress the rotating mechanism such that one wing folds under the other.

Lock the wings in place with the four pronged locking plate (this stays with the

sabot when the UAV is deployed)

Fold the three spring-hinged tail surfaces.

Place the UAV in one sabot half.

Insert the activation pin that pulls out at time of deployment.

Do one final look-over to make sure everything seems ok.

While holding the tail surfaces so they do not spring out, place the UAV in one of

the sabot halves.

Carefully close the sabot with the other half.

Page 104: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

104

Have someone hold it closed until it‟s ready to be integrated into the rocket.

4.1.7 INSTRUMENTATION PRECISION AND REPEATABILITY

There are two areas which effect precision of the data collected beyond the precision of

the sensors themselves since data is recorded in two ways; transmission to the ground

station and storage on non-volatile memory.

Data transmitted to the ground station has a lower precision than the data collected by

the sensors due to the need to encode the floating point data into integer values for

sake of compatibility. This results in the maximum precision shown in table XXX.

TABLE 4-12: PRECISION OF TRANSMITTED DATA

Data Decimal places

Humidity [%] 1

Solar [Wm-2] 2

UV Index 1

Pressure [Pa] 0

Temperature [oC] 1

The precision of data logged by the backup board is the same as the precision of the

sensors themselves as no conversion from floating point need be done. The precision

for the sensors is shown in table XX and the back board components are highlighted for

clarity.

TABLE 4-13: SENSOR PRECISION

Data Sensor Location Precision

Pressure

SCP1000 Back-Up Board 6Pa

(8.7E-3psi)

BMP085 Flight Computer 100Pa

(1.45E-2psi)

Solar Clairex CLD140

Back-Up Board /

Flight Computer

Humidity Honeywell HIH-4000

Back-Up Board /

Flight Computer 3.5%

UV Index Back-Up Board /

Flight Computer 0.1

Temperature

SCP1000 Back-Up Board 0.03125oC

(0.05625oF)

BMP085 Flight Computer 0.1oC

(0.18oF)

Dallas Back-Up Board / 0.5 oC

Page 105: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

105

Semiconductor DS18S20

Flight Computer (0.9°F)

It is worth noting that the flight computer also logs data from the sensors connected to it

at their precision as this data is not transmitted and so does not need to be converted to

integer values for compatibility.

Given the changing nature of the atmosphere repeatability of data collection is

synonymous with reusability of the data collection hardware and by extension the UAV

and rocket. To this extent all aspects of the rocket, UAV and avionics have been

designed with reusability in mind.

4.2 PAYLOAD CONCEPT FEATURES AND DEFINITION

4.2.1 CREATIVITY & ORIGINALITY OF PAYLOAD

The idea of a deploying an Unmanned Aerial Vehicle (UAV) with a rocket is not an

entirely original idea; however, the end goal of producing a simplified flight control

interface is a new idea. Current UAV technology requires a classically trained pilot to

remotely fly the craft, or at the very least requires operators to undergo a large amount

of training in the operation of remote controlled equipment. The control interface that the

MIT Rocket Team is developing aims to reduce the amount of training required to

successfully complete a UAV mission, opening this class of technology to a greater

range of potential users. As such, a simple “point-and-click” flight system is being

developed to easily translate user operations into functional flight controls, allowing for

successful operation with little or no operator training. Furthermore, by choosing a

rocket deployment, and keeping to a $5000 budget, it further allows for this technology

to be applied to situations where time and budget are controlling factors. This quick

deployment and relative low cost of operation would ideally suit the needs of search and

rescue operations, reconnaissance missions, and even rapid scientific data gathering

missions.

By completing NASA‟s Science Mission Directorate, the MIT Rocket Team is further

proving the range of applications the UAV is capable of completing. The requirements of

the SMD do not explicitly require the complexities of a UAV. However, by using the UAV

form factor, the MIT Rocket Team will be able to complete all required tasks of the SMD

mission in a more precise manner over several missions, and will also have the

capability to loiter in any airspace, being limited only by the charge on the batteries.

payload. For example, during flight, a UAV will generally maintain the same orientation

with respect to the horizon, allowing for all images taken during and after the flight to

keep the sky and ground in the same location with a very low chance of error.

Furthermore, the use of a controllable payload allows for the investigation of specific

areas, allowing for the gathering of data of greater importance while limiting the need for

Page 106: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

106

secondary missions. Finally, the use of a UAV allows for a greater amount of data to be

collected due to the extended flight time of a UAV platform compared to other payload

options.

4.3 SCIENCE VALUE

4.3.1 PAYLOAD SCIENCE OBJECTIVES

There are two different aspects to the payload, each with their own objectives; the SMD

payload requirement and decreased complexity in UAV flight.

The payload objectives relating to the SMD payload are to log atmospheric pressure,

temperature and humidity along with solar intensity and UVI data at 5-second intervals

as well as taking at least two still images during flight and three after landing.

The payload objective relating to decreasing the complexity in flying a UAV is to

complete the flight and mission (visually locating the rocket and landing) solely using the

software provided at the ground station without reverting to back up manual control.

4.3.2 PAYLOAD SUCCESS CRITERIA

The data logging and sensors shall be deemed successful if the payload obtains and

logs atmospheric pressure, temperature and humidity along with solar intensity and UVI

data at 5-second intervals as well as taking at least two stills during flight and three after

landing. It shall be deemed a success regardless if the data is collected by the main or

the back-up sensor package.

Fulfilling the SMD payload requirement successfully shall also demonstrate the flexibility

in the UAV design.

If the UAV operator successfully visually locates the rocket and lands in a state fit for

reusability, without resorting to use of the back-up manual flight control then this will

demonstrate successful reduction in complexity of UAV control.

4.3.3 EXPERIMENTAL LOGIC, APPROACH, VERIFICATION

By using a science payload in a descending UAV, atmospheric measurements

presented in section 4.2 will be collected. The science payload will be contained inside

built-in compartments in the fuselage, preventing thrashing of instruments from launch

initiation to landing of UAV.

To obtain such data, all the sensors will be turned on just prior to launch and

measurements will be recorded at 5-second intervals during launch and decent within

target area. Using a UAV to carry a science payload of multiple sensors and accurately

obtain such data will provide a more efficient means for obtaining such data.

Page 107: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

107

Additionally, the telemetry devices inside the UAV will allow for safe operation of the

vehicle via a pilot at the ground station. A single mission by a UAV with such science

payload gathers data at varying altitudes effectively and efficiently, relative to other

means of acquiring such data.

The goal of the UAV is also to have a simplified flight control interface. This will be

achieved by having stability control on the UAV such that it is able to maintain straight

and level flight, perform controlled turn and land safely with no user input. Combining

this with an appropriately designed user interface, this should be sufficiently automated

that it can be controlled by a person with absolutely no flying experience.

4.3.4 DESCRIBE TEST AND MEASUREMENT, VARIABLES AND CONTROLS

Testing and verification of the avionics occurs in three distinct phases: ground testing,

on a test aircraft and lastly on the final UAV, thus enabling ground testing shall consist

of validating the correct operation of all hardware and sensors in a non-critical

environment. The testing on the test aircraft serves to verify that the subsystems within

the avionics system work as expected in flight case and to validate changes made to

the flight computer hardware and software for the purposes of the competition. The

flight testing on the UAV is to demonstrate the avionics system is able to function

correctly in its intended flight configuration and importantly, that is it capable of recovery

after deployment from the rocket.

Phase One – Ground Testing

First the flight computer, GPS/IMU, and telemetry boards shall be connected to ensure

these systems are functioning. Next this system shall be connected to servos and a

program will be used to actuate the servos in a known fashion to confirm that the servos

can be controlled. Furthermore, an R/C receiver will be attached to the avionics system

to ensure that the equipment accepts commands from an R/C handset. The telemetry

system shall also be tested by communicating the position the GPS reports to a mock-

up ground station. That position will be checked for accuracy, the time taken for the

GPS to get position lock at start up will be noted, and whether or not the GPS is able to

maintain lock when moved at a reasonable speed will be checked.

The back-up board will also be constructed and be tested by exposing it to a variety of

conditions such as varying the altitude under different weather conditions and

comparing to the expected values. This acts to validate that both the sensors and the

data recording systems within the back-up board are working correctly.

The real-time video system will also be tested by varying the distance between the

transmitter and receiver to find the limit of the range the system is able to adequately

transmit the video data.

Phase Two – Test Aircraft

Page 108: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

108

The initial flight-testing will occur on a aircraft team owned and previously built UAV.

This acts to limit the dependency of avionics testing and refining on the construction of

the UAV, thus expediting the development of the avionics. This also minimizes the risk

to the final UAVs; there will be at least one back up UAV and replacement components

for internal mechanisms in the event that the primary UAV fails or breaks.

The initial flights will be manual, i.e. the R/C aircraft shall be controlled solely by an

operator using a standard R/C controller. These initial flights will be to verify the correct

setup of the flight computer and servos. After that, flight testing shall be undertaken to

tune the control gains of the flight computer for stable flight. It is worth noting that these

gains will not necessarily be those required for the final UAV, but the autonomous flying

ability gained from this is essential for further flight testing. Next flight tests shall be

performed where coordinates of waypoints to be flown to will be uploaded to the

avionics system in-flight to ensure that this functionality works as expected. At this point,

the flight computer hardware will be wired to the primary sensors. Also, the flight

software shall be modified to log the sensor data on the internal volatile memory and

transmit the logged data post landing. This additional functionality shall then be tested in

multiple flights to ensure correct operation. Over the course of the latter flight testing the

back-up sensor board, real-time video transmission and still capturing systems shall be

integrated into the R/C aircraft, tested and refined as necessary.

Phase Three –UAV Testing

After the avionics performance has demonstrated adequate performance on the „Test

Aircraft‟, the avionics system shall then be integrated with the UAV. The first flight

testing shall be to determine the control gains required for stable flight of the UAV. For

the purposes of these tests, the equipment not essential for flying (i.e. everything but

flight computer, telemetry link and GPS/IMU) shall be replaced by appropriate ballasting

to minimize the risk of damage to components.

Once adequate control gains have been determined, a series of flight tests shall be

undertaken to ensure that the sensor systems and data logging systems, as well as the

imaging systems, still function as desired. These flights will also determine if the

propulsion system‟s duration and thrust are sufficient to maintain steady-level flight for

at least 30 minutes. Further testing representative of flight scenarios shall also be

undertaken, including point-to-point flying based on user inputs at a ground station.

Drop tests from a tethered weather balloon shall also be used to simulate UAV

deployment to ensure the UAV/Avionics is capable of recovering from the post-

deployment dive. The UAV will be unpowered (propulsion system off) due to safety

reasons for these tests; the lithium polymer propulsion battery will be replaced by ballast

to mitigate the risk of the lithium polymer battery exploding due to damage if the UAV

were to crash. Gliding should be sufficient to test all avionics. A test section of the

rocket body tube will be hung from a balloon platform attached to the weather balloon.

The UAV will be packed into the sabot, and the sabot will be placed in the body tube

Page 109: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

109

and connected to a radio controlled tender descender. The balloon will be tethered and

raised to an altitude sufficient enough such that the UAV and sabot will be falling at

speeds identical to those of launch conditions when approaching an altitude of 200 ft,

releasing from the rocket tube at 200 ft; this altitude should be sufficient for full UAV

deployment, while restricting the safety radius needed to be cleared of personnel on the

ground to a reasonable value. The sabot will be dropped under drogue parachute, and

the UAV will deploy. These tests shall be performed with ballast instead of non-essential

electronic components. This ballast will be placed in such proportions and

arrangements to maintain the center of mass of the UAV, providing sufficiently accurate

mission conditions for the UAV.

4.3.5 RELEVANCE OF EXPECTED DATA

The data collected is vital for the analysis of the systems and subsystems in

determining any necessary changes to the design of the UAV, or to any instruments and

power devices. Accuracy of the data is also significant in that, if the lift produced or

propeller propulsion is not enough, the UAV will need to adjust its attitude, which can

potentially lead to unbalanced forces, instability of the vehicle, or even stalling of wings

or horizontal stabilizer.

Effectively, all data on the stability lift and drag forces for the wings, horizontal

stabilizers, and the assembled body must be accurate to determine the necessary

attitude of the vehicle to achieve specific tasks, such as steady-level flight, landing, and

elevating altitude.

The various measurements of the atmosphere will be gathered, organized and analyzed

to study changes in the atmosphere with changes in altitude, changes in amount of

atmosphere between the payload and ground, and changes in level of atmosphere

between the payload and space. This will provide real data, to contrast to theoretical

data predicting such qualities of the atmosphere based on location, altitude, and density

of the air.

4.3.6 ACCURACY AND ERROR ANALYSIS

Accurate data provides information about atmospheric conditions to people, giving

realistic data for the analysis and design of different potential aerial mechanisms. Such

data will also allow for scientific groups to consider the protection necessary for

instruments of varying sensitivity to cosmic electromagnetic radiation, that are planned

on being deployed at varying altitudes. Devices and forces can be greatly affected by

variables such as pressure, temperature, relative humidity, solar irradiance, and UV

radiation; appropriate knowledge of such variables can allow for proper preparation for

objects entering such conditions.

4.3.7 EXPERIMENT PROCESS PROCEDURES

Page 110: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

110

Individually test all sensors for temperature, pressure, relative humidity, solar irradiance, and UV radiation (primary and back-up sensors).

Pressure can be tested in a wind tunnel with a known dynamic pressure o Temperature probes can be tested at room temperature, and outside ambient

temperature, which will range from 30°F to 60°F, at time of anticipated testing o Relative humidity can be tested in dry rooms and in ambient air, with known

humidity levels known from known weather conditions.

Determine mass of all instruments, avionics, and power devices

Estimate mass of UAV body materials

Identify a suitable propulsion system and battery for device powering

Using computational software, Excel and MATLAB, verify calculations for expected parameters and requirements of the UAV.

Using CAD software, model UAV with appropriate dimensions and parts.

Using hand calculations and analysis software (i.e. AVL, ANYSYS, Nastran) to determine failure loads of wings and internal mechanisms of UAV

Use flight simulation software to determine flight patterns of UAV

Develop mission success criteria o All data accurately acquired and stored properly o Still photographs acquired at SMD prescribed intervals o Communication between payload and ground station seamless o Semi-autonomous navigation capable of navigating to command coordinates o Safe landing of rocket and tethered pieces with use of parachutes o Safe landing of UAV, employing protective underside Kevlar coat

Ensure rocket, UAV and other equipment are reusable after each mission

4.4 PAYLOAD SAFETY

4.4.1 IDENTIFICATION OF SAFETY OFFICER

Andrew Wimmer will be the primary rocket safety officer for the team. Ben Corbin is the

team‟s MIT EHS representative and is the assistant safety officer and is in

charge of safety issues not directly related to the rocket. Both team members have

considerable experience in their respective areas.

4.4.2 FAILURE MODES

UAV

TABLE 4-14: POTENTIAL UAV FAILURE MODES

Risk Consequence Mitigation

UAV is damaged

before launch

weekend

The UAV needs to be

repaired or replaced

quickly to allow for

Avionics testing in a commercial R/C

aircraft and ground testing of the UAV

will be performed before the UAV is

Page 111: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

111

testing to continue. flown. Extensive flight testing with the

final UAV design will be performed, and

an experienced backup pilot will be

standing by during any flight test with

the R/C controller to mitigate chances

of a crash landing.

UAV is damaged on

launch weekend

before launch

The degree of damage

needs to be assessed.

Quick repair or

complete replacement

with a backup UAV

needs to be done.

Extreme care will be taken when

packing and handling the UAV. A

backup UAV will be taken to the launch

site to prevent total mission failure in

the event of the primary UAV being

damaged.

The UAV is

damaged during

deployment

The UAV may not be

controllable in autopilot

or manual mode, and

part or all of the

mission may fail.

High strength materials, including

fiberglass, carbon fiber, polycarbonate,

aluminum, and steel, are used in the

construction of the UAV to prevent total

failure and part separation.

The UAV‟s autopilot

fails

The backup pilot

engages manual

control and the UAV is

flown like a normal R/C

aircraft. All data can

still be collected and

transmitted.

A backup pilot with manual R/C

controller and a spotter with binoculars

will be on hand at all times, ready to

take over control of the UAV in case of

any autopilot failure.

The UAV becomes

entangled in shock

cords or shroud lines

upon exiting the

sabot.

The UAV will not be

able to fly. The pilot will

immediately go to

manual mode to

prevent the UAV from

trying to correct its

flight and potentially

damage the rocket.

The UAV will still be

able to collect and

stream data. Rocket

parachutes may not

deploy correctly.

The location of the parachutes and the

length of the shock cords are such that

the UAV should avoid entanglement.

Testing will drive adjustments to the

rocket‟s recovery system to mitigate

UAV entanglement.

Control surface(s)

break off during

initial dive pull-out

Depending on the

control surface, the

UAV may no longer be

maneuverable and will

likely crash land. Data

Balloon drop tests will verify that the

UAV can pull out of a dive and fly

without sustaining damage.

Page 112: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

112

can still be collected.

Wing breaks off

immediately after

deployment

The UAV will no longer

be maneuverable and

will crash. Depending

on the damage

sustained, data may or

may not be able to be

collected.

The UAV‟s wing rotator and wings have

been over-engineered to sustain much

higher loading than could be

experienced throughout the entire

flight. Balloon drop tests will verify that

the UAV can pull out of a dive without

sustaining damage.

High-wind conditions

on launch day

The UAV could be

damaged by wind

gusts. The UAV

experiences turbulent

flying conditions,

making control difficult.

Video may be shaky.

The UAV structure is designed to

handle high-loading situations, such as

those experienced by strong winds.

The UAV autonomous controls will be

able to stabilize the flight of the UAV in

high winds. The UAV design will not

need to take into account flying in very

high winds (15mph+), because it is

likely that the entire launch will be

postponed if high-wind conditions are

present due to the danger of launching

high power rockets in high-winds.

The propulsion

system fails

The UAV will not be

able to sustain or gain

altitude, decreasing

mission time. The UAV

will still be controllable.

Flight testing and pre-flight checks will

ensure that all UAV systems are

working properly before final

integration. The avionics are designed

to not need a propulsion system to

function properly, and will still be

capable of landing the plane safely.

The UAV‟s

propulsion battery

dies before the end

of the mission

The UAV loses the

ability to sustain or

gain altitude,

decreasing mission

time. The UAV will still

be controllable.

The propulsion and avionics batteries

will be separate, so if the propulsion

battery dies, the UAV will act as a

glider. Both batteries, as well as

backups, will be fully charged on

launch day. Flight testing will determine

necessary battery capacities.

The UAV‟s avionics

battery dies before

the end of the

mission

The UAV loses all

control abilities and will

crash land.

Flight testing will determine minimum

avionics battery capacity. For safety

purposes, this capacity will then be

doubled for the final UAV. Ways of

utilizing the propulsion battery as a

backup avionics battery are currently

being investigated.

The UAV is out of

sight at time of

No knowledge of

whether or not the

Not having sight of the UAV should not

be a problem, as the autopilot in the

Page 113: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

113

deployment UAV has successfully

pulled out of its initial

dive. Backup pilot

cannot engage manual

control without sight of

UAV.

UAV will undergo extensive testing

before launch day, and the tablet pilot

interface should work as planned. A

spotter with binoculars, whose main

responsibility is to track the UAV by

sight, will be with the backup pilot at all

times. The live video feed and GPS

coordinates transmitted from the UAV

should also give information pertaining

to the status of the UAV.

The UAV makes it

out of the sabot, but

does not right itself

(The autopilot and

GPS require the

UAV to be upright.)

The backup pilot will

engage manual control

and hopefully be able

to steady the UAV. If

control is not gained,

the UAV will crash

land, but still be able to

collect and transmit

data.

Upon release from the sabot, the UAV

will immediately and automatically set

its control surfaces to a position that

should pull it out of the initial dive in an

upright position. Wing dihedral should

make being upright a much more

favorable position. If all this fails, the

backup pilot has a long time (2500 ft) to

steady the UAV with manual control.

The UAV‟s propeller

contacts part of the

rocket while under

throttle

Damage to the rocket

and UAV may occur.

The UAV may be put

into a spin due to such

contact.

The autopilot will be programmed not

to engage the motor until a set time

has passed from deployment. If this

fails, the backup pilot can engage

manual control and set the motor

throttle to zero.

An internal

component in the

UAV moves during

flight, shifting the

UAV‟s CG

The UAV becomes

difficult to maneuver.

Autonomous flight

capability may be lost

and manual control

may have to be

engaged.

All components will be securely

mounted. Balloon drop tests will verify

all component mounts are secure

enough.

The UAV deploys

correctly, but flies

over the crowd or

out of range of the

ground station.

Manual control is

engaged and the UAV

is piloted out of the no

fly zone.

A no fly zone will be coded into the

tablet pilot system disallowing the

addition of waypoints above the crowd

or outside the range of the ground

station. The rocket will be launched far

away from the crowd, as per NAR

regulations, so the chance of UAV

deployment over crowd is minimal. The

range of the ground station will be large

enough to cover the UAV at any

possible deployment location.

Page 114: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

114

UAV contact with

ground station is lost

Contact will try to be

regained and/or

manual control will be

engaged.

The UAV will be programmed with a

“loiter-mode” that will be activated if

ground station signal is lost. The UAV

automatically lands at a set location

after a set amount of time out of

contact with the ground station. In

“loiter-mode”, the UAV will still avoid

the no fly zones.

The UAV requires

an emergency or

forced landing due

to one of the above

or other risks

Manual control is

engaged and the

backup pilot brings the

UAV down as quickly

and safely as possible.

If that is not an option,

an emergency “kill

switch” is engaged that

puts the plane in a

steep downward spiral.

Low cruising/reconnaissance altitude

allows for minimal landing time in case

of an emergency. The mass of the UAV

has been minimized to decrease

damage in case of an emergency. The

addition of an emergency “kill switch” in

the programming (controlled by the

backup pilot) is a last resort to quickly

land the UAV.

Note, in all circumstances where control of the UAV is lost, with the exception of loss of

avionics power, the UAV will be able to collect and transmit data while it is falling.

Avionics and Ground Station

TABLE 4-15: POTENTIAL AVIONICS AND GROUND STATION FAILURE MODES

Failure Mode Description Consequence Mitigation

GPS Failure

GPS hardware

failure

Satellite lock failure

No navigation data

to run UI

Testing to ensure

antenna function

and adequate GPS

lock prior to launch

day

Flight is continued

under mode using

visual data

Telemetry Failure

Telemetry module

hardware failure

Antenna failure

Loss of

communication

between UAV and

Ground Station

Testing to ensure

antenna and

telemetry module

functions

adequately prior to

launch day

Flight is continued

under manual

Page 115: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

115

mode using visual

data and sensor

data logged by

backup board

Video Camera

Failure

Camera hardware

failure

Antenna failure

Loss of first person

view video stream

Testing to ensure

antenna and video

hardware functions

correctly

Flight is continued

using pilot and

spotter team

Still Camera

Failure

Servo actuation

failure

Loss of capability

to take still photos

Stills taken from

the video stream

during flight and

landing

If combined with a

video camera

failure then results

in a loss of image

gathering capability

Flight Computer

Sensors Failure

Sensor hardware

failure

No sensor data

collected by the

flight computer

No sensor data

transmitted to

ground station

Backup board logs

sensor data using

an independent set

of sensors to an

SD card

Backup Board

Failure

Ardiuno board

failure

Sensor hardware

failure

SD card failure

SD card writer

failure

No sensor data

collected by the

backup board

Flight computer

logs sensor data

and transmits it to

ground station

If combined with

flight computer

sensor failure then

results in a lack of

sensor data

Flight Computer

Failure

Flight computer

hardware failure

Flight computer

software freezes

Flight computer

software crashes

Loss of

communication

between UAV and

Ground station

No sensor data

collected by the

flight computer

Motor throttled to

Manual control and

a pilot spotter

teams glide the

UAV down safely

Page 116: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

116

idle

Gyroscopic

Sensor Failure

Sensor hardware

failure

Loss of orientation

data

Can be flown under

manual control if

control loops

become unstable

Accelerometer

Failure

Sensor hardware

failure Little consequence

Can be flown under

manual control if

necessary

Loss of Motor

Power

Motor dedicated

battery pack runs

out

Motor hardware

failure

Motor throttled to

idle

UAV can be glide

to landing via the

ground station

Loss of Avionics

Power

Avionics dedicated

battery pack runs

out

Loss of

communication

between UAV and

Ground Station

No sensor data

collected by the

flight computer

Motor throttled to

idle

UAV performs

uncontrolled glide

to ground

Primary Ground

Station Computer

Failure

Computer system

crash

Application crash

Laptop battery runs

out

Loss of telemetry

link

Multiple backup

computers capable

of running the

ground station

software

Employ manual

control until

software restart

Secondary

Ground Station

Computer Failure

Computer system

crash

Application crash

Laptop battery runs

out

Loss of first person

video feed

Multiple backup

computers capable

of displaying video

feed

Use a spotter in

place of video feed

until software

restart

4.4.3 POTENTIAL HAZARDS

Page 117: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

117

For manufacturing hazards, see “Hazards Recognition” and “Tool Use” in Section XX

(Personnel Hazards in rocket section).

In order to assure safe and successful operations concerning the payload, a checklist

must be followed. In order to reduce personnel hazards the following precautions must

be taken:

Avoid standing in the plane of the propeller when UAV propulsion system is on.

Do not try to catch the UAV during landing.

Make sure all relevant testing (reference checklist) has been completed prior to

attempting a flight test.

Make sure the checklist is followed and all steps are completed properly in a

thorough, workmanlike manner to assure mission success.

Lithium Polymer Battery Hazards and Procedures:

Always charge lithium polymer batteries with a balancer. Out of balance packs

can explode.

Never over-discharge a lithium polymer battery (below 2.7V per series cell).

Always use an electronic speed controller (ESC) with a low voltage cut off

feature.

Never attempt to charge a lithium polymer battery if it looks bloated, damaged,

over discharged (below 2.7V per series cell). Damaged packs can explode.

Never leave a lithium polymer battery unattended while charging.

Always charge lithium polymer batteries on a non-flammable surface and away

from flammables.

Take extreme caution around the UAV in the case of a crash. The battery packs

may explode if damaged.

Never discharge a lithium polymer battery at more than the published discharge rate.

The pack may explode if discharged too quickly.

4.4.4 ENVIRONMENTAL CONCERNS

All waste materials will be disposed of using proper trash receptacles

Consideration of environmental ramifications will be made regarding applicable

activities

The following materials have been identified as potentially hazardous:

o Aeropoxy 2032 Epoxy Resin

o Aeropoxy 3660 Hardener

o Lithium Polymer Batteries

See CDR-MSDS document for complete MSDS specifications on these and other

materials.

Page 118: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

118

5 ACTIVITY PLAN

5.1 BUDGET PLAN

Since the completion of CDR the MIT Rocket Team is still awaiting final funding awards

from the Massachusetts Institute of Technology department of Aeronautics and

Astronautics, as well as the Massachusetts Institute of Technology Edgerton Center.

Talks with these two sources are ongoing, and final decisions from these two groups

are expected by the first week of February. The MIT Rocket Team is also investigating

possible funding from two new sources. The first source being looked into is the MIT

Gordon Engineering Leadership program; this program is new on campus and is

offering funding to student engineering groups in return for allowing students within their

program to take part in the project throughout the semester. The MIT Rocket team is

currently waiting to submit a proposal as the program is currently assessing their

application process. The team is also interested in approaching Aurora Flight Sciences.

From research and contacts with a senior level design class the team has learned that

Aurora is interested in funding student-engineering projects that involve UAV

development as it is a field they are heavily invested in. The team has initiated contact

with a member of the Aurora Flight Sciences company and we are awaiting a response.

The MIT Rocket Team has also reevaluated the cost of our project taking into account

the changing design features of both the flight vehicle and UAV payload. At the

Preliminary Design Review many of the components of both the vehicle and payload

were priced using estimates with large margins. Since the maturation of the design the

Master Equipment List has been revised and we now have a more accurate measure of

system value as it sits on the launch pad. A table of contributions and a summary of

system costs are shown below in tables XX and XX

TABLE 5-1: BUDGET

Funding Sources

Source Contribution

MIT Aero-Astro ($7,000)

MIT Edgerton Center ($5,000)

NASA SMD Grant $5,000

MIT RT Savings $5,000

Total ($22,000)

Note: values in parenthesis are anticipated funding sources

TABLE 5-2: TOTAL BUDGET

System Summary

Page 119: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

119

System

Mass (kg) Cost (USD)

Rocket

Propulsion 5.46 552.00

Airframe-Body 3.62 455.09

Airframe-Fairing 1.01 27.00

Avionics/Comm 0.99 947.38

Payload Support Equipment 1.82 152.24

Recovery 2.19 434.60

SUBTOTAL 15.09 2568.31

UAV

Propulsion 1.15 190.00

Airframe 0.00 80.00

ACS 0.16 70.00

Avionics 0.21 647.73

Payload 0.15 622.30

Recovery 0.00 10.00

SUBTOTAL 1.67 1620.03

Support

Ground Station N/A 5,459.90

Testing N/A 2,000.00

Spares N/A 4,000.00

Team Support N/A 4,260.00

TOTALS 16.76 19,908.24

5.2 TIMELINE

The Gantt chart that has been in use since the initial proposal is still being used by the

MIT Rocket Team as the main method of keeping the team on target for completion.

Some small changes have occurred due to the fluid nature of student schedules during

the month of January. However, the team is still on track for completion of all

milestones. The updated Gantt Chart can be found in Appendix 2.

5.3 EDUCATIONAL ENGAGEMENT

We would like to build upon out fall outreach event with three events in the spring, which

will be shaped by the feedback we received.

The team has committed to holding three community outreach events over the next few

months in order to continue to engage the surrounding community in hands-on learning.

These programs will accommodate a range of ages, and will assume no prior

knowledge of rocketry. Our aim is to get the public, particularly middle to high school

students, excited about science, engineering, and the space industry.

MIT Splash and Spark Weekends

Page 120: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

120

MIT‟s Educational Studies Program is a student group that offers services to student

and community members alike. As part of its community outreach it offers student-

taught classes all weekend long during the months of November (called Splash) and

March (called Spark) on campus to a target group of 7th-12th graders.

At Splash, we taught two classes for a total of 25 high school students called “Rockets

and Composites”. We began with a brief lecture on composites, and then guided the

groups through the constructions of their own balsa wood and carbon fiber fins, which

they were able to take home with them. We then moved on to an introduction to rockets,

and further discussion on composites design, fabrication, and testing, and engine

testing.

We handed out a feedback form at the end of the session, which posed a series of

short-answer questions (what did you like most, what improvements could be made,

etc) as well as some multiple choice questions, to gage how the class impacted their

understanding of rocketry as well as their excitement about the subject.

The students reported that they enjoyed the hands-on part the most (making the fins),

and talking to us personally about their interests and any questions they happened to

have. Almost all of them suggested that the class be made longer. While this is not

possible due to the nature of the event, it did make us think about how we could use our

time better, and for the second group we cut down on our first lecture, which left more

time for questions at the end and made us feel less rushed. Most students reported

knowing “a bit” about rockets before the class, and that the class enhanced their

understanding “a lot”. Most said that the class “definitely” made them want to learn

about rockets in the future. Finally, almost all reported that the math and the equations

were the most confusing part, so we cut down on this for our next group.

For Spark, the corresponding spring event, we plan to use a presentation similar to that

given as Splash. Our survey results from Splash will help us to be more effective.

Boston Museum of Science

The MIT Rocket Team is a subset of the MIT chapter of a national organization called

the Students for the Exploration and Development of Space (SEDS), which aims to get

undergraduates involved in space-related projects. These projects often have a

community service side, and in the past the group has organized highly successful

community workshops and presentations at the Boston Museum of Science, where

undergraduate and graduate students conduct hands-on activities for the purpose of

increasing public interest in math, science and higher education.

We are working with the museum‟s Current Science & Technology group to run an

event on February 5th, which will consist of two presentations with hands-on activities

and demonstrations. The two presentations will last 15-20 minutes; the first will be about

rocket technology and its development over time, and another will be about the space

industry. We will run two hands-on workshops before, during, and after the

Page 121: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

121

presentations: one where participants will build their own Alka Seltzer bottle rockets,

and another where participants will design build their own parachutes. We will present

them with a set of materials, such as paper and plastic and cloth, and have them attach

a weight and observe the results.

We are currently working on securing space to set off the rockets and drop the

parachutes. This event will accommodate the wide range of age and experience that the

museum attracts.

We will be able to promote this event through various student websites and public radio,

as well as the museum‟s public relations personnel. We also plan to distribute posters

and flyers around the museum.

The learning objectives for this activity will be the following:

Arrive at a basic understanding of the history of rocketry and the space

industry. We believe that understanding rocketry requires learning about its

development, which includes the figures and organizations that have been key to

the field. Topics will include Wernher von Braun, NASA, the Space Race, and

current commercial organizations such as SpaceX.

How does a rocket work? We want to explain how rockets work, and get our

audience interested in math and science through the amazing technology that is

rocketry. This portion of the presentation will introduce the importance of math

and science in developing rockets by explaining the basics principles that allow

us to send rockets into space. We believe in learning by doing, and therefore will

supplement this with a bottle rocket workshop.

The social impact that low-Earth orbit rocketry has brought to our everyday

lives. We want our audience to leave with an understanding of not only how

rockets work, or how the space industry developed over time, but why all of this

is important and relevant to modern society, and to each of their daily lives. We

will explore rocketry‟s contributions to, for example, telecommunication and

accurate weather forecasting.

To evaluate the success of our engagement, we plan to conclude each talk with a

question session, and consider the accuracy and enthusiasm of their engagement. We

also plan to have questionnaires at each of the workshop tables, asking participants for

their feedback on the activity and the event as a whole.

MIT Museum

The MIT Museum is holding an event called the Cambridge Science Festival (CSF) from

April 30 to May 8. The mixture of talks and hands-on activities and workshops appealed

to our team, and we felt that our presentation would be a good fit for the venue. We

have worked with the museum‟s Educational Coordinator to secure a date and finalize

an event description, reproduced below. The event will be held on May 1, and will last

Page 122: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

122

from 10am to 1pm. The audience will be of all ages. We plan to run the event identically

to our program at the Boston Museum of Science, but will update our talks and

workshops based on the feedback we receive at the Museum of Science.

You Can Be a Rocket Scientist

How do rockets work? How do they affect our daily lives? Explore the history of

rocketry from before NASA to present-day and try your hand at aerospace

engineering with demonstrations, presentations, and hands-on activities by the

MIT Rocket Team.

6 CONCLUSION

From its inception, the MIT Rocket Team has known that project Valhalla would be a

difficult and aggressive challenge. However by taking a structured and thorough

approach to the development of the project, the team is confident that the project will

succeed. Upon its completion, the team will have developed a sophisticated

reconnaissance system capable of being employed in a variety of situations and

mission types. In addition to being rapidly deployable, the system benefits from the

simplified flight control interface already in the final stages of development. Thanks to

the simple “point-and-click” nature of the ground based flight control system, the skill

needed to successfully deploy the system is decreased, leading to a greater success

rate. Furthermore, to demonstrate the adaptability of the UNICRON flight system, we

have chosen to undertake the 2011 USLI Science Mission Directorate, which will

demonstrate the craft‟s performance in a science-gathering mission.

In the time since the completion of the Preliminary Design Review, the MIT Rocket

Team has taken great strides in the design and early testing of project Valhalla.

Furthermore, as the designs of the key components matured, design specifications

were adapted to simplify the manufacture process, while simultaneously increasing the

overall safety of our system. As such the designs of the launch vehicle, TYR, and the

payload, UNICRON, have both undergone a considerable number of revisions. And with

the analysis shown above the MIT Rocket Team is confident that we will be delivering a

system that exceeds the minimum safety requirements of NASA‟s University Student

Launch Initiative, while excelling at the mission for which project Valhalla was designed.

In the coming month, the MIT Rocket Team will continue fabrication and testing for

project Valhalla starting with the proto-flight models of both TYR and UNICRON. By

mid-February both proto-flight structures will be completed and ready to undergo further

testing to confirm the safety and viability of the final designs. Furthermore the

UNICRON avionics subsystem will begin flight-testing in the last week of January using

a standard model aircraft, and transitioning to the prototype versions of UNICRON as

soon as possible. The planned deployment method, MAGIC, will be undergoing testing

in mid-February using a balloon platform drop test. Finally all aspects of project Valhalla

will be tested with a scale launch and UAV deployment by the end of February.

Page 123: MIT Rocket Team USLI 2011 Critical Design Reviewweb.mit.edu/rocketteam/www/2010_www/documents/CDR-final.pdfdestruction, power, and might, and it first appeared in the 1986 Transformers

123

The MIT Rocket Team is looking forward to the coming month and the challenges it

presents. But more importantly the team is looking forward to April‟s launch weekend

where we look forward to a successful launch and mission completion. Until then, the

team will keep working hard to meet its deadlines, and further refine our system.